Slides by: Ms. Shree Jaswal

Page 2: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Introduction

developing the project schedule

Scheduling Charts

logic diagrams and network (AOA,AON)

critical path

calendar scheduling and time based network

management schedule reserve

PDM network,

PERT

CPM

Resource loading, resource leveling

allocating scarce resources to projects and several projects

Goldratt’s critical chain.

Chapter 4 Slides by: Ms. Shree Jaswal 2

Page 3: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Textbook:

* Chp 7: The Project's Schedule and budget

Reference Books:

#1 Chp 7: Network Scheduling and PDM

#1 Chp 8:PERT, CPM, Resource Allocation and GERT

#1 Chp 9: Cost estimating and budgeting

#1 Chp 10:Managing risks in projects

#2 Chp 8:Project Activity Scheduling

Note:* Textbook: "Information Technology Project Management" Jack T.

Marchewka

#1 Reference book: "Project Management for business and Technology"

John M. Nicholas

#2 Reference book: "Project Management" Jack R. Meredith

Chapter 4 Slides by: Ms. Shree Jaswal 3

Page 4: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Chapter 4 Slides by: Ms. Shree Jaswal 4

Page 5: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Activity definition

Activity sequencing

Activity duration estimation

Schedule development

Schedule control

Chapter 4 Slides by: Ms. Shree Jaswal 5

Page 6: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Project Management Tools

Gantt Charts

Project Network Diagrams

Activity on the Node (AON), Activity on arrow (AOA)

Critical Path Analysis

Pert

Precedence Diagramming Method (PDM)

Chapter 4 Slides by: Ms. Shree Jaswal 6

Page 7: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Simplest and most commonly used scheduling

technique

The chart consists of horizontal scale divided into

time units-days, weeks or months and vertical

scale showing project work elements.

Chapter 4 Slides by: Ms. Shree Jaswal 7

Page 8: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Advantages:

Gives a clear pictorial model of the project.

Simplicity for the planner and the user.

Easy to construct & understand.

Is a means for assessing the status of individual work elements and the project as a whole.

It can be used as Expense Charts

1.for labor planning

2.resource allocation

3.budgeting

Chapter 4 Slides by: Ms. Shree Jaswal 8

Page 9: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Chapter 4 Slides by: Ms. Shree Jaswal 9

Page 10: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Chapter 4 Slides by: Ms. Shree Jaswal 10

Page 11: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Chapter 4 Slides by: Ms. Shree Jaswal 11

Page 12: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Chapter 4 Slides by: Ms. Shree Jaswal 12

Page 13: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Drawbacks:

It does not explicitly show interrelationships

among work elements.

Gantt charts are often maintained manually. This

is easy task in small projects, but is burdensome

and a disadvantage in large projects; it causes

apathy and results in charts becoming outdated.

Chapter 4 Slides by: Ms. Shree Jaswal 13

Page 14: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Activity Start time Duration

A 0 5

B 6 3

C 7 4

D 8 5

14Chapter 4 Slides by: Ms. Shree Jaswal

Page 15: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

0 6 12 18 24 30

Gantt charts

Time

Activitie

s

15Chapter 4 Slides by: Ms. Shree Jaswal

Page 16: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Suppose C & D must start only after activity B is

completed.

16Chapter 4 Slides by: Ms. Shree Jaswal

Page 17: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

0 6 12 18 24 30

Gantt charts

Time

Activitie

s

17Chapter 4 Slides by: Ms. Shree Jaswal

Page 18: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Gantt charts don’t explicitly show task

relationships

don’t show impact of delays or shifting

resources well

network models clearly show

interdependencies

18Chapter 4 Slides by: Ms. Shree Jaswal

Page 19: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

network of relationships

elements & relationships (sequence)

this is ACTIVITY-ON-NODE

can have ACTIVITY-ON-ARC

research

what’s

been done

research

what needs

doing pick

final

topicinternet

research

write print

19Chapter 4 Slides by: Ms. Shree Jaswal

Page 20: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Activity on node diagrams

A,6 B,9

20Chapter 4 Slides by: Ms. Shree Jaswal

Page 21: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Activity on arc or arrow

21 3

21Chapter 4 Slides by: Ms. Shree Jaswal

Page 22: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Activity Duration Immediate Predecessor

A 6 _

B 9 A

C 8 A

D 4 B,C

E 6 B,C

Duration is given in weeks

22Chapter 4 Slides by: Ms. Shree Jaswal

Page 23: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

AON diagram corresponding to data in prev table

Critical path A-B-E:21 weeks

Start A,6

B,9 D,4

C,8 E,6

Finish

23Chapter 4 Slides by: Ms. Shree Jaswal

Page 24: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Activity on arc or arrow

Same example on AON network

1 2

A,12

24Chapter 4 Slides by: Ms. Shree Jaswal

Page 25: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Activity Immediate Predecessors Duration

A _ 6

B A 9

C A 8

D B,C 4

E B 6

F D,E 6

Duration is in days

25Chapter 4 Slides by: Ms. Shree Jaswal

Page 26: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

1 2

26Chapter 4 Slides by: Ms. Shree Jaswal

Page 27: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Activity Immediate Predecessors Duration

A _ 6

B A 9

C A 8

D B,C 4

E B 6

F D,E 6

Duration is in days

27Chapter 4 Slides by: Ms. Shree Jaswal

Page 28: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

1 2

4

3

28Chapter 4 Slides by: Ms. Shree Jaswal

Page 29: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Activity Immediate Predecessors Duration

A _ 6

B A 9

C A 8

D B,C 4

E B 6

F D,E 6

Duration is in days

29Chapter 4 Slides by: Ms. Shree Jaswal

Page 30: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

1 2

4

3

55 6

30Chapter 4 Slides by: Ms. Shree Jaswal

Page 31: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Activity Immediate Predecessors Duration

A _ 6

B A 9

C A 8

D B,C 4

E B 6

F D,E 6

Duration is in days

31Chapter 4 Slides by: Ms. Shree Jaswal

Page 32: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

1 2

4

3

5 6

7

32Chapter 4 Slides by: Ms. Shree Jaswal

Page 33: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Activity Immediate Predecessors Duration

A _ 6

B A 9

C A 8

D B,C 4

E B 6

F D,E 6

Duration is in days

33Chapter 4 Slides by: Ms. Shree Jaswal

Page 34: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

3-5, 4-5, 7-8,6-8 are dummy activities

1 2

4

3

5 6

7

8 9

34Chapter 4 Slides by: Ms. Shree Jaswal

Page 35: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Dummy activities are used in AOA diagrams in case a node has more than one immediate predecessor.

In previous example:Activity Immediate Predecessors Duration

D B,C 4

F D,E 6

To represent activities D & F we use dummy activities

Chapter 4 Slides by: Ms. Shree Jaswal 35

Page 36: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

ACTIVITY PREDECESSOR IMMEDIATE PRED: REDUNDANT PRED:

A --

B A A

C A A

D A,B,C B,C A

E A,B,C,D D A,B,C

F A,B,C B,C A

REDUNDANT ACTIVITY

36Chapter 4 Slides by: Ms. Shree Jaswal

Page 37: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

It is only essential to know the immediate

predecessor of a node while constructing a

network.

All the predecessors except the immediate

predecessors of a node are redundant

predecessors( activities).

37Chapter 4 Slides by: Ms. Shree Jaswal

Page 38: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

AON n/ws

There are no dummy activities

They are simpler

They are easier to construct.

38Chapter 4 Slides by: Ms. Shree Jaswal

Page 39: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

AOA n/w’s

AOA method used just as often, probably because it was developed first and is better suited for PERT procedures

The PERT model places emphasis on events and in the AOA method events are specifically designated by nodes.

AOA diagrams use line segments to represent flow of work and time, it is easy to construct schedules that are similar in appearance to Gantt charts but incorporate advantage of networks

39Chapter 4 Slides by: Ms. Shree Jaswal

Page 40: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Most software packages create AOA n/w’s

that look similar to Gantt charts.

In particular it is best to select one form of

technique., AON or AOA, and stick to it.

40Chapter 4 Slides by: Ms. Shree Jaswal

Page 41: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

The longest path from the origin node to the terminal

node

Gives the expected project duration (Te)

One project can have more than one CP

Shortening activities on CP (critical activities) will

help reduce the project duration

Shortening activities NOT on CP has no effect on

project duration

Delay in any activities on CP will result in delay of

project completion

Chapter 4 Slides by: Ms. Shree Jaswal 41

Page 42: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Start A,6

B,9 D,4

C,8 E,6

Finish

Critical path A-B-E:21 weeks

Activity,

duratio

n

predece

ssor

A,6 -

B,9 A

C,8 A

D,4 B,C

E,6 B,C

42Chapter 4 Slides by: Ms. Shree Jaswal

Page 43: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Specifies when at the earliest the activities can be

performed.

ES & EF are computed by taking a FORWARD pass

through the network

When an activity has several predecessors, its ES is

the MAXIMUM of all EF of predecessors

Chapter 4 Slides by: Ms. Shree Jaswal 43

Page 44: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Latest allowable times that the activity can be started

and finished without delaying the completion of the

project.

LS & LF are computed by taking a REVERSE pass

through the network. LS for the last activity (Ts) is

taken same as the EF for that activity (Te); larger value

can be selected if project does not have to be

completed by EF.

When an activity with multiple paths leading back,

backward path with MINIMUM of all LS is selected.

Chapter 4 Slides by: Ms. Shree Jaswal 44

Page 45: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Eg:

activity duration__predecessor

A requirements analysis 3 weeks -

B programming 7 weeks A

C get hardware 1 week A

D train users 3 weeks B, C

45Chapter 4 Slides by: Ms. Shree Jaswal

Page 46: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Critical path is: A-B-D 13 weeks

1 2

3

4

5 6

46Chapter 4 Slides by: Ms. Shree Jaswal

Page 47: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Total slack= LS-ES or LF-EF

Total slack of all activities along critical path

is zero.

Hence delaying any of these activities will

delay the project.

47Chapter 4 Slides by: Ms. Shree Jaswal

Page 48: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Free Slack= ES( earliest successor)- EF

In the eg, activity C has a free slack of 6

weeks( 10-4=6)

Free slack indicated the amount by which

activity can be delayed without affecting the

start of its successor activity.

48Chapter 4 Slides by: Ms. Shree Jaswal

Page 49: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

can have more than one critical path

activity duration predecessor

A requirements analysis 3 weeks -

B programming 7 weeks A

C get hardware 7 weeks A

D train users 3 weeks B, C

critical paths A-B-D

A-C-D

both with duration of 13 weeks

49Chapter 4 Slides by: Ms. Shree Jaswal

Page 50: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

After a project network has been created

and finalized the resulting schedule times

should be converted into a calendar schedule

plan

Calendar schedule plan expresses the

schedule in terms of calendar dates

Chapter 4 Slides by: Ms. Shree Jaswal 50

Page 51: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

To complete the calendar schedule, the

network is converted into a time-based

network

Time based n/w’s have advantages of both

Gantt charts and networks because they

show the calendar schedules as well as

relationships among activities.

Chapter 4 Slides by: Ms. Shree Jaswal 51

Page 52: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Chapter 4 Slides by: Ms. Shree Jaswal 52

Page 53: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Chapter 4 Slides by: Ms. Shree Jaswal 53

Page 54: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Chapter 4 Slides by: Ms. Shree Jaswal 54

Page 55: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

The Te first computed from the n/w is usually not the duration specified as the contractual completion time.

A Management schedule reserve is established by setting the required target time Ts at some amount greater than the time of the final schedule event Te.

Chapter 4 Slides by: Ms. Shree Jaswal 55

Page 56: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

The schedule reserve and a management

budget reserve comprise a “safety buffer” that

the project manager can use to overcome

problems or delays that threaten project

performance

Chapter 4 Slides by: Ms. Shree Jaswal 56

Page 57: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Need for PDM: “Predecessor - Sucessor” type of networks

assume a “strict” sequential relationship between activities

They do not provide for tasks that can be started when their predecessors are only “partially” complete

PDM allows multiple relationships between activities Finish-to-Start (FS)

Start-to-Start (SS)

Start-to-Finish (SF)

Finish-to-Finish (FF)

Chapter 4 Slides by: Ms. Shree Jaswal 57

Page 58: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Finish-to-Start (FS)

The start of the Activity B can occur n days, at the earliest after the finish of Activity A

Start-to-Start (SS)

The start of Activity B can occur n days, at the earliest after the start of Activity A

Chapter 4 Slides by: Ms. Shree Jaswal 58

Page 59: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Start-to-Finish (SF)

The finish of Activity B must occur n days,

at the latest after the start of Activity A

Finish-to-Finish (FF)

The finish of Activity B will occur in n

days, at the latest after Activity A finishes

Chapter 4 Slides by: Ms. Shree Jaswal 59

Page 60: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

PDM: RelationshipsA 15

PlasterWall

B 10Tear-down scaffolding

FS=5

A

FS=5

B

A 15Furniture move in

B 10Peoplemove in

SS=5

A

SS=5

B

A 15Test

new system

B 10Phase outold system

SF=20

A

SF=20

B

A 15Lay

asphalt

B 10Paint

parking linesFF=5

A

FF=5

B

60Chapter 4 Slides by: Ms.

Shree Jaswal

Page 61: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

The two most commonly used methods for project planning and scheduling are:

Program Evaluation and Review Technique (PERT)

Critical Path method (CPM)

Chapter 4 Slides by: Ms. Shree Jaswal 61

Page 62: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Program Evaluation & Review Technique (PERT)

The Framework for PERT and CPM

There are six steps which are common to both

1. Define the Project and all of it’s significant activities or tasks.

2. Develop the relationships among the activities. Decide which activities must precede and which must follow others.

Chapter 4 Slides by: Ms. Shree Jaswal 62

Page 63: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

3. Draw the "Network" connecting all the activities. Each Activity should have unique event numbers. Dummy arrows are used where required to avoid giving the same numbering to two activities

4.Assign time and/or cost estimates to each activity

5. Compute the longest time path through the network. This is called the critical path.

6.Use the Network to help plan, schedule, monitor and control the project.

Chapter 4 Slides by: Ms. Shree Jaswal 63

Page 64: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

PERT was developed for application in projects where there is uncertainty associated with the duration and nature of activities.

Chapter 4 Slides by: Ms. Shree Jaswal 64

Page 65: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

reflects PROBABILISTIC nature of durations

assumes BETA distribution

same as CPM except THREE duration estimates

optimistic

most likely

pessimistic

Chapter 4 Slides by: Ms. Shree Jaswal 65

Page 66: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Three time estimates :

The Optimistic (a) The minimum time in which the activity can be

completed

The Most Likely (m) Completion time having the highest probability

(normal time to complete the job)

The Pessimistic (b)

The longest time an activity could take to complete

Chapter 4 Slides by: Ms. Shree Jaswal 66

Page 67: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Chapter 4 Slides by: Ms. Shree Jaswal 67

Page 68: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

a = optimistic duration estimatem = most likely duration estimateb = pessimistic duration estimate

Mean or expected time for completion of an activity , te is given byte = (a + 4m + b)/6

Variance, V is given byV = sqr((b-a)/6)

Chapter 4 Slides by: Ms. Shree Jaswal 68

Page 69: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

The expected time Te , represents the point on distribution where there is a 50-50 chance that the activity will be completed earlier or later than it.

a=3,b=5,c=13

Te= (3+4(5)+13)/6= 6 days

Variance is the measure of variability in the activity completion time:

V=sqr((13-3)/6)=sqr(1.67)= 2.78

Chapter 4 Slides by: Ms. Shree Jaswal 69

Page 70: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

The larger V, the less reliable Te, and the higher the likelihood that the activity will be completed much earlier or much later than Te.

More dispersed the distribution and greater the chance that the actual time will be significantly different from the expected time Te

Chapter 4 Slides by: Ms. Shree Jaswal 70

Page 71: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Probability of finishing by a target completion

date

The expected duration of a project - Te, is the

sum of expected activity times along the

critical path.

Te = ∑ te

The variation in the project duration

distribution is computed as the sum of the

variances of the activity durations along the

critical path

Vp = ∑ V

Chapter 4 Slides by: Ms. Shree Jaswal 71

Page 72: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Chapter 4 Slides by: Ms. Shree Jaswal 72

Page 73: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Now, although the project is estimated to be completed

within 29 weeks (Te=29) our Project Director would

like to know what is the probability that the project

might be completed within 27 weeks (i.e.Ts=27 or Due

Date or D=27).

For this calculation, we use the formula for calculating

Z, the number of standard deviations that D is away

from Te.

Z =(Ts-Te)/ √ Vp

Chapter 4 Slides by: Ms. Shree Jaswal 73

Page 74: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Thus, Z=(27-29)/ √ 6 = -0.82

After referring to table for Z values for normal

distribution,

X1=-0.8,X2=-1.0,Y1=0.212,Y2=0.159

Now, using the formula,

Y=Y1+[(Y1-Y2)/X1-X2)]*(X-X1), we get

Y=0.2067=0.21(approx)

Therefore, probability is 21% to finish project

in 27 days

Chapter 4 Slides by: Ms. Shree Jaswal 74

Page 75: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Chapter 4 Slides by: Ms. Shree Jaswal 75

Page 76: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

For above example to find out what is the date

when 95% of project will have been

completed…..

Again using the table and interpolating,

probability of 0.95 has Z value=1.645

Thus,1.645=(Ts-29)/ √ 6

So, Ts=33.03 days (highly likely)

Chapter 4 Slides by: Ms. Shree Jaswal 76

Page 77: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Putting too much emphasis on the critical

path can lead managers to ignore other paths

that are near-critical or have large variances,

and which themselves could easily become

critical

Chapter 4 Slides by: Ms. Shree Jaswal 77

Page 78: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Monte Carlo simulation is a procedure that takes into account the effects of near critical paths becoming critical.

Chapter 4 Slides by: Ms. Shree Jaswal 78

Page 79: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Need to have considerable amount of

historical data to make time estimates

PERT gives overly optimistic results.

Beta distribution gives large errors in

estimating Te.

Most of the errors in Te come from faulty

time estimates not Beta distribution.

Chapter 4 Slides by: Ms. Shree Jaswal 79

Page 80: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Although PERT and CPM employ networks and use the concept of critical path, the methods have two points of divergence.

CPM is a deterministic approach.CPM includes a mathematical procedure

for estimating the trade-off between project duration and cost.

CPM features analysis of reallocation of resources from one job to another to achieve the greatest reduction in project duration for the least cost.

Chapter 4 Slides by: Ms. Shree Jaswal 80

Page 81: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Chapter 4 Slides by: Ms. Shree Jaswal 81

BASIS FOR

COMPARISONPERT CPM

Meaning PERT is a project

management

technique, used to

manage uncertain

activities of a

project.

CPM is a statistical

technique of project

management that

manages well defined

activities of a

project.

What is it? A technique of

planning and control

of time.

A method to control

cost and time.

Orientation Event-oriented Activity-oriented

Evolution Evolved as Research

& Development

project

Evolved as

Construction project

Page 82: Slides by: Ms. Shree Jaswalssjaswal.com/wp-content/uploads/2018/08/SPM_Chp4_part1.pdfMost software packages create AOA n/w’s that look similar to Gantt charts. In particular it is

Chapter 4 Slides by: Ms. Shree Jaswal 82

BASIS FOR

COMPARISONPERT CPM

Model Probabilistic Model Deterministic Model

Focuses on Time Time-cost trade-off

Estimates Three time estimates One time estimate

Appropriate for High precision time

estimate

Reasonable time

estimate

Critical and Non-

critical activities

No differentiation Differentiated

Suitable for Research and

Development Project

Non-research

projects like civil

construction, ship

building etc.

Crashing concept Not Applicable Applicable