5
T he roller-compacted con- crete (RCC) technique in- troduced to dam construc- tion in the 1980s has achieved significant time and cost sav- ings compared to conventional meth- ods of concrete placement and con- solidation. International interest in RCC dam design and construction continues to increase, and new tech- niques for design and construction are being developed, particularly to accom- modate higher dams. RCC dams are reaching 200 meters in height: the 192- meter, 396-MW Miel 1 Dam in Co- lombia was completed in 2002; the 192-meter, 4,200-MW Longtan Dam in China is under construction; and the 227-meter, 6,400-MW Ta Sang Dam in Myanmar is under design. In dams this high, lift joint strength and imperme- ability are critical. The sloped layer method of placing RCC was recently developed at the 131-meter high, 300-MW Jiangya Dam owned by the Lishui Hydro and Power Corporation in Hunan Province, China. The method since has been used at sev- eral other dams in China as well as at the recently completed 60-meter-high Tannur Dam in Jordan.The method also was used on a trial basis in placing the top 6 to 8 meters of the 43-meter-high Lajeado Dam, which is part of the 902.5-MW Luis Eduardo Magalhaes Hydro Project in Brazil.The method achieves increased RCC placement rates and largely overcomes concerns about lift joint bonding. Paying attention to lift joints A significant difference between conven- tionally placed concrete dams and RCC dams is the number of horizontal con- struction joints, otherwise referred to as lift joints. In order to achieve required densities by roller compaction, RCC lift thickness typically is maintained at about 0.3 meter, while 1.5 meters is typical for internally vibrated conventional con- crete.Thus, an RCC dam may have five times as many lift joints as it would have had if constructed in conventionally placed concrete. There is no doubt that the bonding of lift joints is the key to achieving a monolithic structure. Failure of a con- ventional concrete or RCC gravity dam is far more likely to occur along its contact with the foundation or along a lift joint than through the concrete itself. At lift joints, tensile and shear strengths are always lower, and perme- ability is always higher, than within the concrete.This is due to several factors: the aging of the lift surface concrete; the tendency for segregation of the con- crete overlying the joint; and the poten- tial for lower density toward the bottom of the lift. Experience has shown that seepage through RCC dams generally occurs along lift joints, which is clear evidence of non-monolithic construc- tion and defective lift joint bonding. RCC dams that are more than 100 meters high require significant vertical tensile strength capacity and horizontal shear resistance throughout, including at the lift joints. Dams of this height typi- cally require shear strengths of 1 to 1.5 megapascals and cohesion strengths of 0.5 to 1.0 megapascals.The difficulty in consistently achieving these strengths is emphasized when one considers that RCC dams now being planned to ex- ceed 200 meters in height will require nearly 700 lift joints. Furthermore, for example,placing Ta Sang Dam’s 8 mil- lion cubic meters of RCC will require preparing and bonding 2,700 hectares of lift surface, with nearly 350 kilome- ters of lift joint line exposed at the upstream face! In any RCC dam, occa- sional sub-standard work on lift joints will be inevitable due to high place- CIVIL STRUCTURES Using Sloped Layers to Improve RCC Dam Construction By Brian A. Forbes Using the sloped layer method to construct a roller-compacted concrete (RCC) dam enables each layer of RCC to be placed within the initial set time of the previous layer.This improves horizontal lift joint strength and impermeability,significantly enhancing the safety of the dam. Brian Forbes, C.P. Eng., MIE Australia, is manager of dams engineering for GHD Pty Ltd., Consulting Engineers, Brisbane, Australia. He is interna- tionally recognized for his work in RCC dam design and construction, and has served on the review boards for some of the world’s highest RCC dams. This article has been evaluated and edited in accordance with reviews conducted by two or more professionals who have relevant expertise. These peer reviewers judge manuscripts for technical accuracy, usefulness, and overall importance within the hydroelectric industry. From HRW, July 2003 - © HCI Publications, www.hcipub.com Reproduced with permission.

Sloped Layers to Improve RCC Dam Construction - ForBES

Embed Size (px)

DESCRIPTION

rcc

Citation preview

  • The roller-compacted con-crete (RCC) technique in-troduced to dam construc-tion in the 1980s has

    achieved significant time and cost sav-ings compared to conventional meth-ods of concrete placement and con-solidation. International interest inRCC dam design and constructioncontinues to increase, and new tech-niques for design and construction arebeing developed, particularly to accom-modate higher dams. RCC dams arereaching 200 meters in height: the 192-meter, 396-MW Miel 1 Dam in Co-lombia was completed in 2002; the192-meter, 4,200-MW Longtan Dam inChina is under construction; and the

    227-meter, 6,400-MW Ta Sang Dam inMyanmar is under design. In dams thishigh, lift joint strength and imperme-ability are critical.

    The sloped layer method of placingRCC was recently developed at the131-meter high, 300-MW Jiangya Damowned by the Lishui Hydro and PowerCorporation in Hunan Province,China.The method since has been used at sev-eral other dams in China as well as atthe recently completed 60-meter-highTannur Dam in Jordan.The method alsowas used on a trial basis in placing thetop 6 to 8 meters of the 43-meter-highLajeado Dam, which is part of the902.5-MW Luis Eduardo MagalhaesHydro Project in Brazil.The methodachieves increased RCC placement ratesand largely overcomes concerns aboutlift joint bonding.

    Paying attention to lift joints

    A significant difference between conven-tionally placed concrete dams and RCCdams is the number of horizontal con-struction joints, otherwise referred to aslift joints. In order to achieve requireddensities by roller compaction, RCC liftthickness typically is maintained at about0.3 meter, while 1.5 meters is typical forinternally vibrated conventional con-crete.Thus, an RCC dam may have fivetimes as many lift joints as it would have

    had if constructed in conventionallyplaced concrete.

    There is no doubt that the bondingof lift joints is the key to achieving amonolithic structure. Failure of a con-ventional concrete or RCC gravitydam is far more likely to occur along itscontact with the foundation or along alift joint than through the concreteitself. At lift joints, tensile and shearstrengths are always lower, and perme-ability is always higher, than within theconcrete.This is due to several factors:the aging of the lift surface concrete; thetendency for segregation of the con-crete overlying the joint; and the poten-tial for lower density toward the bottomof the lift. Experience has shown thatseepage through RCC dams generallyoccurs along lift joints, which is clearevidence of non-monolithic construc-tion and defective lift joint bonding.

    RCC dams that are more than 100meters high require significant verticaltensile strength capacity and horizontalshear resistance throughout, including atthe lift joints. Dams of this height typi-cally require shear strengths of 1 to 1.5megapascals and cohesion strengths of0.5 to 1.0 megapascals.The difficulty inconsistently achieving these strengths isemphasized when one considers thatRCC dams now being planned to ex-ceed 200 meters in height will requirenearly 700 lift joints. Furthermore, forexample, placing Ta Sang Dams 8 mil-lion cubic meters of RCC will requirepreparing and bonding 2,700 hectaresof lift surface, with nearly 350 kilome-ters of lift joint line exposed at theupstream face! In any RCC dam, occa-sional sub-standard work on lift jointswill be inevitable due to high place-

    C I V I L S T R U C T U R E S

    Using Sloped Layers to Improve RCC Dam Construction

    By Brian A. Forbes

    Using the sloped layer method to construct a roller-compacted concrete (RCC) damenables each layer of RCC to be placed within the initial set time of the previouslayer.This improves horizontal lift joint strength and impermeability, significantlyenhancing the safety of the dam.

    Brian Forbes, C.P. Eng., MIE Australia,is manager of dams engineering forGHD Pty Ltd., Consulting Engineers,Brisbane, Australia. He is interna-tionally recognized for his work inRCC dam design and construction,and has served on the review boardsfor some of the worlds highest RCCdams.

    This article has been evaluated and edited inaccordance with reviews conducted by two ormore professionals who have relevant expertise.These peer reviewers judge manuscripts for technical accuracy, usefulness, and overallimportance within the hydroelectric industry.

    From HRW, July 2003 - HCI Publications, www.hcipub.comReproduced with permission.

  • ment rates, the need for night work, andthe urgency to prepare lift surfacesahead of the rapidly advancing nextRCC lift.The inspecting engineer willsimply not be able to ensure that everylift joint is properly constructed, with-out inherent weaknesses.Therefore, thegoal must be to minimize the risk of adefective lift joint.

    To achieve homogeneous,monolithicRCC across a lift joint requires the over-lying lift to be placed within the initialset time of the lower lift. Using retardersin the concrete can easily extend settimes to 5 to 8 hours, compared to 1.5 to2.5 hours without retarders.However, inlarge dams, it usually takes 15 to 30 hoursto complete a horizontal lift from oneabutment across to the other. Com-pletely homogenous, monolithic RCCin large dams with horizontally-placedlift joints cannot be achieved by the usualprecautionary measures such as minimiz-ing the tracking of equipment over com-pleted lift surfaces, repeated compressedair clean-off, application of curing water,and use of high contents of fly ash orslow hydrating pozzolans in the RCCmixture. As a result, zones of lowerstrength in the lift joints of such damswill be inevitable.

    Developing the sloped layermethod

    RCC placement at Jiangya Dam began

    in 1996, with the RCC initially placedin horizontal layers. The dam wasdivided into monoliths or blocks about60 meters wide and extending betweenthe formed upstream and downstreamfaces. Each monolith was constructed in3-meter lifts of RCC, with each liftconsisting of ten 0.3-meter-thick hori-zontal layers.The area of placement wassuch that successive layers of RCCcould be placed within 5 to 6 hours,which was within the initial set time ofthe retarded RCC.When the lift in onemonolith was completed, the form atthe transverse joint was moved and thelift in the adjacent monolith was con-structed.The cold joint at the top of the3-meter lift was green cut and thor-oughly cleaned. Then a thin layer ofbedding mortar was applied when thenext lift was placed on it, as in any con-ventional concrete dam.This methodachieved excellent bond and homo-geneity of the RCC across the lift joint;however, construction was slow andcostly owing to the effort required toerect the transverse form, the difficultyof maintaining a ramp access throughthe form for the RCC trucks, and thecost of the set retarder.

    In 1997, when Jiangya Dam hadreached mid-height, the chief engi-neers of Lishui Hydro and Power Cor-poration, Liaoning Construction Bu-reau (contractor), and Changjiang

    Water Resources Committee (con-struction supervisor) conceived thesloped layer method on site, andadopted the method principally toaccelerate the overall RCC placingrate.The method succeeded, not onlyensuring that lifts were placed withinthe initial set time of the RCC, butalso enabling the dam to be competedon schedule. By placing the 0.3-meter-thick layers of RCC on a slope, fromone abutment to the other betweenthe formed upstream and downstreamfaces, the same 3-meter lift could bebuilt up across the entire dam as a con-tinuous process, without the need for atransverse form.When a new 3-meterlift commenced, the slope of the 0.3-meter layers could be changed tomaintain the desired volume of RCCin each layer.

    Applying the method,realizing the advantages

    For example, suppose one were using 3-meter-high forms and producing RCCwith an initial set time of two hours at arate of 500 cubic meters per hour; then,for the sloped layer to be placed withinthe initial set time, the slope S (horizon-tal on vertical) of a 0.3-meter-thickRCC layer would have to be:

    S < 2x500Wx3x0.3

    i.e., approximately 1,000W

    where W is the width between up-stream and downstream faces as shownin Figure 1.

    Hence, a slope of 1 vertical on 10horizontal would be required at lowerelevations where the width of the dammight be 100 meters; at upper elevations,where the width might be 25 meters, aslope as flat as 1 on 40 could be used.Initial trials at Jiangya Dam confirmedthe feasibility of slopes as steep as 1 on 8with the smooth double drum steelvibratory rollers operating in an up-down slope direction. Slopes are con-trolled during placement by paint linesmarked on the upstream and down-stream forms and by survey methods.

    2 HRW / July 2003

    This figure shows how a 3.0-meter lift in an RCC dam can be constructed in 0.3-meter-thick sloped layers, which can be placed within the initial set time of the RCC in the previous layer.

    Figure 1

  • HRW / July 2003 3

    Using this method, the final clean upand surface preparation of the lower lift including application of beddingmortar is restricted to a narrow stripalong the toe of the sloped layer.Thesurface of the completed 3-meter liftcan be green-cut while the RCC is stillyoung.The upstream and downstreamface forms can be erected in anticipa-tion of placement resuming at this posi-tion in about 10 days, assuming aplacement rate equivalent to one 0.3-meter horizontal lift of RCC per day inthe traditional method.

    If sloped layers are placed within theinitial set time of the RCC, no surfacepreparation or bedding mortar isrequired prior to placing the overlyingsloped layer. For 3-meter formed lifts,this potentially reduces the requiredsurface preparation by 90 percent com-

    pared to conventional placement. It alsoreduces the number of lift joints (andpotential failure surfaces through theRCC dam) by 90 percent.

    In the sloped layer method, the thinwedges or feathered edges at the toeand top of each sloped layer requirespecial treatment. At the toe of eachsloping layer at Jiangya Dam, whereaggregate in the RCC could easily becrushed under the steel roller, a 4- to 5-meter-wide, 0.15- to 0.3-meter-thickhorizontal layer was first placed alongthe top of the previous lift as a footafter the contact area with the lower lifthad been thoroughly cleaned and cov-ered with a thin layer of bedding mor-tar.The foot was placed and rolled in anupstream-downstream direction. Thesloping layer then commenced fromabout the center of the foot. (See Figure

    2.) Later, any feathered edges weretrimmed back 0.1 to 0.2 meter to firmRCC and covered with the beddingmortar just prior to placing the foot forthe start of the next sloping layer.Anyfeathered edges at the top of the slopinglayers were cut back to a thickness of 50to 70 millimeters as part of the greencutting and lift joint preparation proc-ess; this was easily achieved using high-pressure air-water jetting to lift off anypoorly bonded material.

    Besides ensuring improved lift jointquality, the sloped layer method allowsthe surface preparation, curing, and lift-ing of formwork to be performedlargely independent of the RCC place-ment. In addition, the amount of timeavailable for lift surface clean up andpreparation is increased tenfold whenusing 3-meter lifts.

    Because the sloped layers of RCCcan be placed before the lower liftreaches final set condition, the form-work and its anchorage into the RCCmust be designed to resist a greaterload.

    For inclined downstream faces, thebest arrangement appears to be to usevertical steps.When formwork is used,the step height is equal to the liftheight. For example, at Tannur Dam, alift height of 1.2 meters using four 0.3-meter sloped layers per lift was adopted.This matched the design height of thesteps on the downstream face, suitingthe formwork system that had beenoriginally supplied for horizontal layerconstruction.

    At Jiangya Dam, reusable, precastconcrete blocks formed the 1-meter-high, stepped downstream face.This sys-tem was retained when the change wasmade to sloping layers. Blocks weresimply added ahead of the advancinglayers as the horizontal RCC steps wereconstructed and a base for the blocksbecame available. Sheets of steel plateagainst the blocks separated the blocksfrom the RCC. The steel plates ex-tended some 1.5 to 2 meters beyondthe leading block to provide interimsupport for the zone of sloping RCCjust ahead of the horizontal surface of

    At Chinas 131-meter-high Jiangya Dam, precast concrete blocks were used to form the steps in the downstream face of the dam, with steel plates separat-ing the blocks from the grout-enriched RCC facing concrete. This system beganwith horizontal RCC placement at the lower part of the dam and continuedwith the sloped layer method adopted during construction.

    Preventing a transverse feathered edge at the toe of a sloped layer in an RCCdam requires a special approach. At Jiangya Dam, in China, a foot was firstplaced from which to begin the slope, as shown.

    Figure 2

  • the step formed behind. Using this step-precast block-steel plate system wouldappear to be ideal where more than onestep is required to match the selected liftheight. Relocation of the blocks andsteel plate is simple and repetitive; it canbe easily achieved with a few laborersand a small mobile crane or front-endloader.

    The sloped layer method has beenshown to work well in conjunctionwith grout-enriched RCC used for

    facing the upstream and downstreamfaces of the dam and connecting theRCC to the rock abutments. In partic-ular, RCC progress is not delayed whileawaiting delivery and placing of con-ventional concrete facing.

    Placing a sloped layer generally in-volves commencing at the downstreamface and moving across to the upstreamface, working over the full height of thelift and compacting in the up-downslope direction.The placement area can

    be roughly divided into three sub-areas;placement begins by dumping RCCfirst in the downstream sub-area, thenprogressing to the upstream face, fol-lowed by the spreading and compactingoperations accordingly.

    When placing RCC in the narrowriver channel area, the sloped layers canbe oriented in an upstream-down-stream direction. Obviously, the layersmust slope upwards from upstream todownstream, since otherwise the shearresistance along a cold layer jointwould be severely reduced by the re-duction in the effective angle of fric-tion.When the distance between theupstream and downstream faces of thedam equals the distance between abut-ments, i.e., forming an essentiallysquare placement area, the orientationof the slope can be redirected and place-ment can proceed from abutment toabutment as shown in Figure 1.

    In the traditional horizontal layermethod, the RCC layers typically areplaced with a 2 to 3 percent crossfalltoward the upstream to drain rainfall, aswell as wash water generated from liftsurface green cutting, clean up, and gen-eral lift surface preparation.This cross-fall can be retained in the sloped layermethod.

    Comparing the pros and cons of the method

    The most important advantage of usingthe sloped layer method in an RCCdam is undoubtedly the improved safetyachieved by producing homogenous,monolithic RCC across the joints be-tween layers.This is accomplished bylimiting the number of cold lift joints toone every 3 meters, thus reducing thenumber of horizontal lift joints by up to90 percent, or by 50 percent comparedto a conventional internally vibratedconcrete dam. Other significant advan-tages of the method are:

    Increasing overall placement rates,potentially by 30 to 50 percent;

    Reducing clean up, lift joint treat-ment, and bedding mix application byup to 90 percent, with associated costsavings;

    4 HRW / July 2003

    At Jiangya Dam, each sloped layer was placed first at the downstream steppedform with the dumping-spreading-compacting procedures progressing acrossthe dam to the upstream face. Here the width of the dam is approximately 50 meters.

    A sloped layer of RCC is being placed at the recently completed, 60-meter-highTannur Dam, owned by the Jordan Valley Authority, in Jordan. At this dam, alift height of 1.2 meters using 0.3-meter-thick sloped layers was adopted. Thelift height matched the design height of the steps on the downstream face,suiting the formwork system that anticipated horizontal layer construction.

  • HRW / July 2003 5

    Taking green cutting and initial liftjoint preparation off the critical path,allowing up to ten days for this work tobe done before placing the next lift ofRCC;

    Preventing wash-down/cleanupwaste from encroaching on currentplacing areas;

    Removing the final lift joint cleanup from the critical path and allowingup to 90 percent more time for jointpreparation prior to placing the nextlayer of RCC;

    Eliminating the need for greencutting and layer surface preparation ofthe grout-enriched RCC or the con-ventional vibrated concrete facing; thematerial is often so fresh that pokervibrators penetrate into the previouslyplaced layer of facing;

    Allowing upstream and down-stream formwork to proceed off thecritical path, potentially days ahead ofbeing required; this permits formworkto be left in place longer for thermalprotection of the concrete during cur-ing in colder climates or, by adopting aleap frog procedure, achieving a 40 to50 percent reduction in the quantity offormwork required;

    Reducing the total surface area ofRCC required to be cured;

    Reducing the area of exposedyoung RCC that could be damagedby rainfall or freezing conditions and,consequently, the volume of RCC

    that may require removal and replace-ment;

    Reducing the potential for cooledRCC to gain heat from hot ambientconditions; and

    Providing (most of the time) anotch in the crest of the dam capableof passing floods in excess of the nor-mal diversion capacity; this provides amore secure plant and equipmentparking zone above flood water leveland potentially reduces the clean-upwork following the flooding, permit-ting an earlier resumption of RCCplacing.

    Aspects of the sloped layer that mayappear disadvantageous are:

    Limiting downstream formworkoptions by requiring either high steps(equal to the selected lift height) or aprecast concrete block/steel plate stepconstruction system with some associ-ated minor complications in progressiveblock placing;

    Increasing the rate of rise againstthe formwork, requiring additionalformwork anchorages;

    Requiring care and attention of thetoe of the sloped layer to prevent thinfeathered edges, where aggregate couldbe easily crushed under the roller poten-tially creating preferred seepage paths;

    Requiring the removal of thefeathered edges of RCC that can occurwhere the sloped layer ends at the topof the lift;

    Somewhat complicating surveycontrol, with slopes both parallel andtransverse to the dam axis (althoughlaser survey systems can accommodatethis complexity); and

    Somewhat complicating the finish-ing of the downstream step horizontallift surface concrete facing (grout-enriched RCC or conventional inter-nally vibrated concrete).

    Conclusion

    Seeking better ways to prove the qualityand safety of RCC dams and to reducetheir cost and effect on the local envi-ronment is essential as RCC dams be-come more costly and time-consumingto build.The recently developed tech-nique of placing multiple layers on aslope to achieve a much thicker liftlargely eliminates the vexing problem oflift joint bond, allowing monolithic,homogeneous RCC to be achieved inlifts up to 3 meters thick. Eight- to 10-meter-long monolithic concrete coresshowing no evidence of lift joints havebeen extracted from recently completedRCC dams in China where layers havebeen placed within the initial set time.This sort of evidence will give engineersthe confidence to design the 200-meter-high RCC dams of the future. Mr. Forbes may be contacted at GHD Pty. Ltd, GPO Box 668, BrisbaneQ4001, Australia; (61) 7-33163601; E-mail: [email protected].