SMOV3B
SMOV3B PROGRESS
As of 20 March
TIPS 21Mar02Carl Biagetti/NISD
TIPS 21Mar02Carl Biagetti
Page 2
SMOV3B
LAUNCH: 01 Mar. 2002, 06:22 a.m., ESTRELEASE: 09 Mar. 2002, 05:03 a.m., EST
SM3b installations with priorities Italics indicates SMOV verification activities.
1. Reaction Wheel (RWA)2. Solar Array III and Diode Boxes3. Power Control Unit (PCU)4. ACS5. NCS/ESM/Radiator/CPL
7. MLI Bays 5&6
Not installed 6. Gyros 7. MLI Bays 7&8
TIPS 21Mar02Carl Biagetti
Page 3
SMOV3B
SMOV3b PLAN
• MEASURE/MONITOR NEW SPACECRAFT BEHAVIOR• POINTING, THERMAL, POWER
• RECOMMISSION EXISTING SIs• STIS, WFPC2
• COMMISSION NEW SIs• ACS
• Science/EROs in early April
• REVIVE NICMOS• VIA NCS COOLDOWN• Science/EROs in mid/late April
TIPS 21Mar02Carl Biagetti
Page 4
SMOV3B
SMOV3b PLAN THROUGH MARCHTask Name
WFPC2 SCIENCE ENABLE
SM3B MISSION
BRIGHT EARTH AVOIDANCE (BEA)
HST RELEASE
HST RELEASE
(PCS1) FHST FOV TEST
STIS NOISE TEST (POST-BASELINE)
(PCS2) GYRO BIAS DETERMINATION
(PCS3) ATTITUDE INITIALIZATION
(PCS4) FHST/FHST ALIGNMENT
9002 ACS02 - ACS LOAD & DUMP ON-BOARD MEMORY
8949 (WFPC2/1) WFPC2 PROTECT DECON
8957 STIS01 STIS CCD FUNCTIONAL
8994 (FGS01) GUIDE STAR ACQ (FGS 1&3)
8999 (FGS06) PRE-NCS JITTER TEST
9003 ACS03 - ACS SCIENCE DATA BUFFER CHECK
9006 ACS06 - ACS CCD TEMP SET POINT DETERM
8958 STIS02A PRE-NCS IMAGE QUALITY
8959 STIS03 STIS MAMA DARK vs. TEMP
8963 STIS 7 CCD BIAS IMAGES
8964 STIS08 CCD DARKS
8968 (PCS08) VEH DISTURB TEST (ACS FW & NCS ACT)
9005 ACS05 - ACS CCD FUNCTIONAL
8961 STIS05 FIRST END-BEA TEST
8960 STIS04A PRE-NCS JITTER TEST
FGS/FHST HV OFF
NCS FILL PROCEDURE
8967V1 NCS01 START NCS CPL
STIS MAMA HV RESTRICTION
8967 NCS01 NCS ACTIVATION & NICMOS COOLDOWN
8968 VDT visits 31-33
8947 ACS05 ACS DAILY TEST
8961 STIS05 SECOND END-BEA TEST
8945 NCIMOS10 - NICMOS TEMP STABILITY
8958 STIS02B POST-NCS IMAGE QUAL CHK
BEA COMPLETE
8968 VEHICLE DIST'B'CE TEST (+V3)
8968 VEHICLE DIST'B'CE TEST (-V1)
9013 ACS13 - ACS COARSE ALIGNMENT
STIS CCD SCIENCE ENABLE
8950 (WFPC2/2) WFPC2 UVMON, COOL-DOWN, CONTAM MON, FOCUS CHK
8952 (WFPC2/5) WFPC2 FLAT FIELD CALIBRATION
8951 (WFPC2/4) WFPC2 LYMAN ALPHA CHECK
NICMOS "HOT" ATTITUDE
8960 STIS04B POST-NCS JITTER TEST
8944 NICMOS01 FW TESTS 1-7
3/27
3/9
3/9
3/22
3/22
3/22
3/22
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
Mar 3, '02 Mar 10, '02 Mar 17, '02 Mar 24, '02 M
TIPS 21Mar02Carl Biagetti
Page 5
SMOV3B
SMOV - so far BEA completes today
ACS – on schedule and nominal
STIS – on schedule & nominal 2nd end bea test removed
WFPC2 – on schedule & nominal (in PROTECT DECON) 23MAR - Cooldown and UV monitor to begin
NICMOS – Nominal Cooling down NCS fails first two start-up attempts => 2 day delay Cooldown rate is uncertain as of (20mar)
FGS – Nominal BEA science
TIPS 21Mar02Carl Biagetti
Page 6
SMOV3B
MAJOR SMOV MILESTONES (UPDATED AS OF 20 MARCH)
Release 09 March
NICMOS Cooldown 18-27 (tbd) March (NOMINAL 10-DAY COOLDOWN)
STIS Basic GO Science 22 March (No MAMA during initial NICMOS cooldown)
WFPC2 Cooldown 22 March
WFPC2 GO Science 26 March
ACS ALIGN 22 March – 7 April (may be accelerated 2-3 days)
ACS EROs 08-11 April “ “ “
ACS Basic GO Science (CCD) 11 April “ “ “
NICMOS Filter Wheel Test 28 March – 04 April (may be delayed ~ 1 week)
NICMOS Alignment (PAM adjust) 05 April – 12 April “ “ “
NICMOS EROs 20-24 April “ “ “
NICMOS Basic GO Science 20 April (without fine aperture locations)
SMOV Complete 27 July (ACS/NIC coronographs enabled)