Upload
others
View
48
Download
0
Embed Size (px)
Citation preview
Social Safeguard Monitoring Report Project No. 36173-013 January to June 2017
Sri Lanka: Greater Colombo Wastewater
Management
Prepared by the Colombo Municipal Council, Ministry of Provincial Councils and Local Government for the Asian Development Bank. This Social Safeguard Monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section on ADB’s website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area
0
Greater Colombo Wastewater Management Project
Loan Number 2557 (OCR) / 2558 (SF) - SRI
Social Safeguard Bi-Annual Report January to June 2017
Implementing agency
Colombo Municipal Council (CMC)
Executing Agency
Ministry of Provincial Councils and Local Government
November 2017
1
Table of Contents
1. INTRODUCTION ..................................................................................................................................... 3
1.1. Project Background ....................................................................................................................... 3
1.2. Social Safeguards Parameters ....................................................................................................... 3
2. DETAILED SOCIAL SAFEGUARD ACTIVITIES UNDER EACH MAJOR WORKS CONTRACT ........................ 6
2.1. Rehabilitation of Pumping Stations and Pumping Mains ............................................................. 6
2.2. Rehabilitation of Selected 10 km Sewer lines and Condition Assessment of 125 km Sewer lines
within the Colombo Municipal area ......................................................................................................... 7
2.3. Rehabilitation of Sea Out Falls .................................................................................................... 10
2.4. Upgrading Wanathamulla gravity sewer network for Colombo municipal council .................... 10
2.5. Supply and Delivery of Equipment for Operation & Maintenance of sewer System ................. 11
3. PHOTOS ............................................................................................................................................... 12
2
ACRONYMS
ADB Asian Development Bank
Aps Affected Persons
CMC Colombo Municipal Council
CGR Ceylon Government Railways
DSC Design and Construction Supervision Consultants
DSD Divisional Secretariat Division
EA Executing Agency
GCWMP Greater Colombo Wastewater Management Project
GND Grama Niladhari Division
HH Households
IR Involuntary Resettlement
MPCLG Ministry of Provincial Government and Local Government
NIRP National Involuntary Resettlement Policy
PD Project Director
PMU Project Management Unit
RAP Resettlement Action Plan
RS Resettlement Specialist
SC Safeguards Committee
SIA Social Impact Assessment
SSO Social Safeguard Officer
SPS Safeguards Policy Statement
UDA Urban Development Authority
URP Urban Regeneration Project
WP Western Province
EMP Environment Monitoring Plan
3
1. INTRODUCTION
1.1. Project Background
The Greater Colombo Wastewater Management Project (GCWMP) is financed by the Asian
Development Bank (ADB) and the Government of Sri Lanka to a total of USD116.5 million. Out of which
ADB is financing USD100 million. The project became effective in April 2009 and is planned to be
completed by 31 March 2019. The Ministry of Provincial Councils and Local Government (MPCLG) is the
executing agency of the Project. Colombo Municipal Council (CMC) and the National Water Supply and
Drainage Board (NWSDB) are the project implementing agencies. This report elaborates details of
activities under the CMC component.
The expected project impact is an improved urban environment and better public health in the Greater
Colombo area. The project outcome is an improved wastewater management services to the residents
within the project area. The project has three components;
1. Upgrade sewerage infrastructure, including rehabilitating the main sewerage system in Greater
Colombo;
2. Strengthening institutional and operational capacity; and
3. Project management and implementation support.
All major works contracts are carried out under Component-1 which directly involves with environment
and socials safeguards matters.
1.2. Social Safeguards Parameters
Project classification - As per ADB’s Involuntary Resettlement Policy (1995) this project is classified as
Category-B for Involuntary Resettlement. The Construction works under the project are limited to
upgrading existing sewerage infrastructure within existing facility boundaries. Screening during project
preparation showed no impacts on indigenous peoples and based on ADB’s Policy on Indigenous People
(1998) it is classified as Category-C.
Financing - All social safeguard and resettlement related activities are financed by Government of Sri
Lanka as a part of the co-financing to the project.
Resettlement Plans - A Resettlement Planning Document was prepared in May 2009 and was
subsequently approved by the ADB. Resettlement Plans for all major civil works contracts were also
prepared during the project implementation stage and approved by ADB. National Involuntary
Resettlement Policy (NIRP) has been considered in preparation of these documents to avoid
unnecessary disturbance to the people and the project implementation. Details on significant changes to
the project’s originally planned safeguard activities, are submitted in Supplementary Resettlement Plans,
for MPCLG and ADB approval. Socio economic surveys were carried out in preparing the Resettlement
Plans and the following activities were identified in order to mitigate any social safeguard issues
Impact Suggested mitigation measure
• Transportation and
access difficulties
• Difficulties faced by
vehicle users
• Environmental
related impact such
• Road sections should be developed stage by stage (staggered
rehabilitation) without excavating the entire area at once
• Construction work should be completed in a speedy manner
• Exploring all possibilities to use alternative access roads
• Conducting construction activities during night hours (only in suitable
sub-project’s sections).
4
as dust, noise,
vibration, odor, etc.
• Explore possibilities to apply trenchless technology in laying pipes
(especially, in narrow roads).
• Effective management of the project site (clearing the road, providing
steel plates as temporary entrances to houses during construction
period)
• Providing safe vehicle parks during construction phase
• Implementation of the environment management plan to minimize
environment related impact.
Table-1
Planning and implementation – Socio economic surveys were done before preparation of each
resettlement plan. Public awareness programs were carried out under the respective civil work
contracts, and people are informed of the construction activities and the complaint handling procedure
of the project, beforehand. Display boards with contact details are kept at sites for any affected people
to make a complaint. Complaint registers are also maintained in all sites. Complaints are handled
through the Grievance Redress Mechanism as prescribed in the Resettlement Planning Document.
Monitoring and Reporting - CMC’s Project Management Unit (PMU) regularly visits the sites and notes
down all social safeguards activities against the details provided in the Resettlement Plans. PMU reports
to ADB on bi-annual reports on its observations and updates. PMU’s Sociologist and Grievance Redressal
Officer, is the focal point for all monitoring and reporting activities. Project Director (PD) supervises
PMU’s Sociologist.
Stakeholders involvement – Under the MPCLG’s overall responsibility, PMU is in charge of
implementing and overseeing all the social safeguard activities of the project. The Design, Supervision,
and Monitoring (DSC) consultant carry out their respective duties under the PMU’ requirement.
Domestic Resettlement Specialist (DRS) of the DSC is responsible for these activities. PMU’s activities are
also strengthened by staff from CMC. Project’s national steering committee, headed by the ministry
secretary, regularly reviews significant social safeguard issues. Issues which involve external
stakeholders are invited to this committee meeting and solutions are proposed.
Following table illustrates more details on these responsibilities:
Activity Action Approval
Institutional Strengthening:
Consultancy support to PMU Sociologist PMU PMU-PD
Training and support to PMU and District Offices DSC PMU-PD
Preparation of Resettlement Plans:
Design of DMS questionnaire DSC-RS PMU-Sociologist
Implementation of DMS, screening of vulnerable DSC-RS PMU- Sociologist
Calculation of average values for entitlements DSC-RS PMU- Sociologist
Preparation of RP DSC-RS PMU- Sociologist
Public consultation on RP and entitlements DSC-RS PMU- Sociologist
Incorporation of comments, preparation of final RP DSC-RS ADB
Public disclosure of RPs PMU- Sociologist EA, ADB
Implementation of Resettlement Plans:
Appointment of external monitor PMU PMU-PD
Internal and external monitoring PMU- Sociologist PMU-PD, ADB
Allocation of RP budgets PMU Accountant PMU-PD
Preparation of lists of entitled persons and entitlements DSC-RS PMU- Sociologist
5
Evacuation and resettlement of APs UDA, PMU and DSC PMU-PD
Monitoring of Resettlement related activities PMU, DSC PMU-PD
Reporting of monitoring results to ADB and CMC PMU, DSC PMU-PD
Communication of outcome of GRC cases GRC -
Surveys to determine level of AP satisfaction PMU - Sociologist PMU-PD
Table-2
Projects’ Grievance Redress Mechanism (GRM) - Reporting the grievances to the site staff of the
Contractor and the Engineer by the affected persons (APs) and the complaints received by other parties
such as CMC, PD or other relevant officers shall also be channeled through this process. The Contractor
(Contractor’s Public Relations Officer) should then acknowledge in writing the receipt of the complaint
to the APs and report the incident to Engineer’s site staff and the PMU immediately. Contractor shall
attaint to the complaint with the agreeable solution with the consultation of the Engineer’s site staff
within about three days and inform of the solution to the APs/Engineer’s site staff/PMU in writing with
agreeable time frame to solve the issue. If the agreed period is more than month contractor should
update complainant periodically. If the fresh complaint reaches to the level 1 above contractor such as
PMU, CMC, MPCLG or ADB it should be sent to the contractor and acknowledge the complainant. The
PMU SS officer shall follow up on each of these complaints periodically. If the Contractor fails to solve
the complaint within agreed time frame or lagging to adhere to the proposed millstones, the complaint
shall now be informed the PMU- PD level for further action. PD shall provide agreeable solution to the
compliant within the one week. During this period the PMU SS officer shall be responsible to update the
complainant on the same procedure as mentioned above. If PMU PD fails to solve the complaint within
the agreed time frame or lagging schedule, the complainant can take up this to the Safeguard
Committee (SC) the same procedure shall precede to an agreeable solution within two weeks, all these
statuses shall be informed to the APs at the appropriate times. If the SC fails to provide an agreeable
solution, complainant may seek to legal action.
Figure-1: GRM
6
Land Acquisition and Involuntary Resettlement - There are no any land accusations under any of
components under this project due to all the sewer line construction work along the public road and
pumping station construction at existing lands belongs to the CMC. but some resettlement has been
occurred to get land clear for the access to the construction site and the affected parties paid
compensation for their losses what was propose in the resettlement plan before commencing of the
construction works.
2. DETAILED SOCIAL SAFEGUARD ACTIVITIES UNDER EACH MAJOR WORKS
CONTRACT
Under Project Component-1, five major contracts were awarded. Four contracts are of civil works and
the rest is supply of vehicles and equipment. Following paragraphs explain progress of each contract and
the social safeguard matters handled, respectively.
2.1. Rehabilitation of Pumping Stations and Pumping Mains
Contract details - Under this contract 10 number of CMC owned Sewerage pumping stations
(Wanathmulla, Thibirigasyay, Maligawata, Bambalapitiya, Vistvyke, Polwatta, Boralla, Fort, CS3 and Slave
Island) will be rehabilitate. Construction works of 5 number of pumping stations are in progress.
Details Date of
award
Date of
complete
Status Physical
progress
Financial
progress
Contractor: M/s
Larson and
Turbo Pvt. Ltd.
Contract
amount: $57.84
million
30 July
2015
28
August
2018
Designs are in progress in five
numbers of pumping stations
for complete new
construction. Shoring for
excavation is in progress in
three pumping stations.
19%
17%
Table-3
Detailed social safeguard activities - There are no any land accusations under this component. It is
planned to establish social safeguard committee in parallel with the construction work at all pumping
station sites.
Following table illustrates complaints received during the reporting period and their status.
Construction
site
Category Number of
complaints
Status
Wanathamulla House damage 02 Solved & Closed
Regarding drugs addicted people 01 Solved & Closed
Thibirigasyaya House damage 01 Solved & Closed
Table-4
The second round of awareness program has been done for public who are living around the
Wanathamulla, and Vsytvyke pumping station sites to disclose on construction related disturbances and
complaint handling procedure of the project. The site visits are proposed regularly at Wanathamulla,
7
Bambalapitiya, Vistvyke, Thibirigasyaya, and Slave Island pumping stations to follow up for the next half
year.
2.2. Rehabilitation of Selected 10 km Sewer lines and Condition Assessment of 125 km Sewer lines
within the Colombo Municipal area
Contract details - Under this contract there are 5 sub component named A1 sewer, M26, T1, U1, U3 and
CFM9. Rehabilitation works of U1and U3 series has been finished and handed over to the CMC.
Rehabilitation works of the M26 and T1 series now are in progress. CCTV based conditional assessment
of 125 km pipes are also in progress.
Details Date of
award
Date of
complete
Status Physical
progress
Financial
progress
Contractor: Teacly(s)
Pvt. Ltd.
Contract amount:
$35.51 million
3 May
2014
19
December
2017
Cleaning and CCTV work
and Sewer construction
through no- dig
technique and open cut
are in- progress
87% 65%
Table-5
Detailed social safeguard activities – As per the original Resettlement Plan, only one HH along M26 pipe
line at Mallikarama Rd, Demattagoda, was identified for temporary resettlement. However, during the
project implementation, permanent resettlement was proposed. CMC prepared a Supplementary
Resettlement Plan (SRP-1) to cover this change and ADB conditionally approved this in April 2017.
In addition to the above resettlement case along the M26 pipeline, a further 67 HHs were originally
identified along the Railway Quarters Rd Demattagoda, by the project to be permanently resettled
bythe UDA. However, the government had already planned to resettle them in better places under a
separate program, outside the GCWMP scope. This 67 HHs included families living in 57 Quarters
buildings belonging to the Ceylon Railways Dept. and the rest being encroachers. By end of 2016,
Government changed its original plan and accommodated only the 57 HHs to be resettled under the
other government program. Thus, the balance 10 families were determined as project affected parties.
A small shop is also identified which will need to be closed down during the construction and financially
affected. CMC proposed resettlement entitlements for these 10 HHs and the small shop, in a second
Supplementary Resettlement plan (SRP-2) and submitted it to ADB in March 2017. Based on ADB’s
comments a revised version was submitted in May 2017. CMC expected approvals from the ADB and
government for all resettlement activities to be received by second half of 2017.
Following resettlement entitlements have been proposed:
Type of loss Entitled
Persons
Entitlements Intent / Requirement Responsib
ility
A. RESIDENTIAL LAND AND STRUCTURES
A1. Loss of
Residential
structure
Non-titled
users
(encroachers),
Land-for-land option.
Housing unit to be provided
on a freehold basis for each
HH
Replacement of land and
structure
CMC,
MPCLG,
PMU
A2. temporary
removal of
business place
Non-titled
users
(encroachers),
Shop will be allowed to
recommence his business
after the completion of
construction work
Recommence of business at
the same location
8
B. LIVELIHOOD RESTORATION & REHABILITATION ASSISTANCE
B.1 Materials Transport Allowance
HHs
requiring
relocation for
housing
Relocating
HHs
Cash assistance (shifting
allowance) of LKR5,000 per
HH for transportation to new
location
Allowance to cover
transport of household
items
CMC,
MPCLG,
PMU
B.2 Livelihood Restoration (Grant)
Improving
livelihoods
All HHs Livelihood restoration grant
– as cash assistance of
LKR10,000.00 per month for
06 months
Cash sum to offset income
losses not directly paid for,
to provide support while
business re-establishing or
as start-up investment for
new business if AP has to
change livelihood
PMU
B.3. Special Assistance
Effects on
vulnerable
HHs
Vulnerable
HHs including
the poor,
elderly,
female-
headed, and
disabled
A special grant of LKR10,000
per HH to improve living
standards
Assistance, over and above
payment for lost assets, to
reduce impacts of
resettlement which can
disproportionately affect
the already vulnerable and
to ensure that the project
does not simply re-establish
poverty, or levels of
vulnerability/
marginalization
CMC,
MPCLG,
PMU
Income loss
compensation
Small shop/
Business
owner
Livelihood restoration grant
– as cash assistance of
LKR25,000 per month for 06
months
Table-6
Following social safeguard related activities were carried out in terms of information disclosure:
Event Name of the sub project Reason
Second round of
Socio economic
survey
M 26 sewer section of GS
sub project
To collect data to prepare of supplementary
resentment plans for Railway quarters road
and Mallikarama road
Meeting with CGR
and UDA
M26 site On resettlement issue
Distributed leaflet M 26 sewer section of GS
sub project
To educate people on construction work and
benefits of the project
Awareness program T1 sewer section of GS sub
project
To disclose construction information to
Public
Site visit with ADB T1 sewer section of GS sub
project
To inspection of public complaint at St
Michael Rd
Table-7
9
Complaints received under this contract and their status as follows:
Construction
site
Category Number
of
complaint
Status
Solved Ongoing
T1 site Dust 1 1
House/Structure damage 8 4 4
traffic Congestion 1 1
Utility interruption, 29 29
Public health 6 6
Other 7 6 1
M26 site
Vibration 1 1 -
House/Structure damage 1 1
Utility interruption 6 6
Public health 1 1
Other 2 1 1
CCTV Public health 1 1 -
traffic Congestion 2 2
Spot repair Utility interruption 1 1
U3 Utility interruption 1 1
Table-8
Events planned for the next half of the year:
Construction site Event
T1 i Site visits
ii. attending complaints SC committee meetings
iii. preparation of SC report
iv. paying compensation for affected people
27th Lane Site visits, SC committee meetings, attending complaints
M26 i. preparing supplementary resentment plan
ii. SC committee meeting
iii. communicating with CGR and UDA URP on relocating of CGR workers
iv. preparation of SC report
v. paying compensation for affected parties before relocating
vi. house selection
vii. keys hand over to the Aps
viii. awareness session for Aps and host communities on relocation
ix. relocation of the Aps and monitoring
x. site visits
Table-9
10
2.3. Rehabilitation of Sea Out Falls
Contract details - Under this contract Wellawatta and Mutwal long Sea out falls and junction chamber of
the Mutwal Sea Outfall have been rehabilitated.
Details Date of
award
Date of
complete
Status Physical
progress
Financial
progress
Contractor- M/s
Leader civil-
Guangzhou
Salvage
Contract amount:
$15.67 million
5 March
2013
19 May
2015
Completed and under
defects
liability
98%
89%
Table-10
Detailed social safeguard activities - Due to cracks in incoming line to the chamber of Mutwal Sea out
fall it was planned to rehabilitate this sewer section with the combination of Wanathamulla balance
work using saving funds of the project.
2.4. Upgrading Wanathamulla gravity sewer network for Colombo municipal council
Contract details – Under this contract there are two sub components named Sewali Mawatha sewer
and Saranapala him Mawatha sewer to laying new pipe to. Length of the rehabilitation of this sewer line
is 1073 M; and now 662M has been finished.
Procurement
method
Date of
award
Date of
complete
Status Physical
progress
Financial
progress
Contractor: M/s
Vonlan
Construction (Pvt)
Ltd
Contract amount:
$2.45 million
20
December
2013
29
February
2016
Contractor was advised to
continue the work. Third-party
damages for uninsurable
properties of the balance
working area were decided to
be paid by the Project.
65%
50%
Table-11
Sewer construction work along Sewali Mawatha and Saranapalahimi Mawatha is not yet completed;
contractor not capable to complete contract within agreed time therefore employer decided to deduct
delay damage from January 2017 and contract was suspend from March 2017.
Detailed social safeguard activities - Due to suspension of contractor the contractor leave from house
repairing works which was damage by construction works. Therefore, project has prepared estimate to
repair of damage houses but affected people didn’t agree on it therefore, project request to Aps to
prepare estimate by they own due to estimated amount about three time higher than project prepared
estimate project didn’t agreed that estimate. Afterward, project has hired NBRO to prepare estimate
with the approval of Ministry.
Due to unstable house construction and the soil condition, houses along the sewali lane and the
Saranapalahimi Mawatha were damaged during construction work. And as per the condition of contract,
contractor was advised to repair the damage houses. However, due to un-authorized house
11
construction the insurance company declined to pay compensation for the damages. Therefore, the
contractor himself engaged the house repairs. These repairs mainly involve cracks appearing on the
building walls. Around 70 housed had repair works and the contractor attended to 29 of them. As per
the advice of Secretary-MPCLG project has to prepare survey plan on condition of household at
remaining pipe laying road sections. This is proposed for the second half of 2017.
Follow up of events in the next half of the year:
Site Event
Seevali Mawatha I Preparation estimate for damage houses by NBRO
ii. discussion with Aps on NBRO estimate get their agreement
iii. Preparation compensation plan
iv. approval from Ministry ADB
v. pay compensation
Saranapala himi Mawatha I Preparation estimate for damage houses by NBRO
ii. discussion with Aps on NBRO estimate get their agreement
iii. Preparation compensation plan
iv. approval from Ministry ADB
v. pay compensation
Table-12
2.5. Supply and Delivery of Equipment for Operation & Maintenance of sewer System
Contract details – Two contracts were awarded to M/s. Access International Ltd. for a total of $4.44
million to Supply and Deliver the prescribed equipment for Operation & Maintenance of sewer Systems.
All equipment has been delivered and the contracts have been successfully completed.
Detailed social safeguard activities – These contracts involve no social safeguard issues.
12
3. PHOTOS
Public awareness programm at Vystvyke PS site
Aware public on construction works of PS
contract
Safety wall for Dispensary to prevent from dust,
Thibirigasyaya PS site Public awareness programm at Wanathamulla PS
Site