Project Update South Montgomery Community School Corporation October 9, 2017 Board Work Session

South Montgomery Community School Corporation · 2010. 9. 17. · SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Junior/Senior High School Campus - Alternates ALTERNATES BUDGET #1

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: South Montgomery Community School Corporation · 2010. 9. 17. · SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Junior/Senior High School Campus - Alternates ALTERNATES BUDGET #1

Project UpdateSouth Montgomery Community School Corporation

October 9, 2017

Board Work Session

Page 2: South Montgomery Community School Corporation · 2010. 9. 17. · SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Junior/Senior High School Campus - Alternates ALTERNATES BUDGET #1

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Outline:

� Southmont Jr/Sr High School

� Scope Alignment – Site

� Scope Alignment – Jr/Sr HS

� Budget

� Project Schedule

Project Update

Page 3: South Montgomery Community School Corporation · 2010. 9. 17. · SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Junior/Senior High School Campus - Alternates ALTERNATES BUDGET #1

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Junior/Senior High School Campus - Overall Site Plan

North

`

South

`

New Construction

Scope Alignment

Redesign

Alternate

Scope Alignment

Page 4: South Montgomery Community School Corporation · 2010. 9. 17. · SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Junior/Senior High School Campus - Alternates ALTERNATES BUDGET #1

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Junior/Senior High School Campus - North Portion

+83

+34

+88

+14

Page 5: South Montgomery Community School Corporation · 2010. 9. 17. · SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Junior/Senior High School Campus - Alternates ALTERNATES BUDGET #1

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Junior/Senior High School Campus - South Portion

+0

+69

+63

+0

Net increase 263 car spaces (Base Bid)

Page 6: South Montgomery Community School Corporation · 2010. 9. 17. · SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Junior/Senior High School Campus - Alternates ALTERNATES BUDGET #1

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Junior/Senior High School

MS Wrestling Room – Plan

WRESTLING ROOM

STORAGE

TEAM ROOM

STOR WH

NEW LOCKER ROOM ADDITION

Page 7: South Montgomery Community School Corporation · 2010. 9. 17. · SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Junior/Senior High School Campus - Alternates ALTERNATES BUDGET #1

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Final Design Estimates

Project Name Construction Cost

Jr/Sr High School A & R $ 12,950,000

New Administration Building $ 1,258,000

6th Grade Academic House $ 340,500

Note: Costs do not include project soft costs including financing, professional fees, financing, legal, and loose furniture.

Page 8: South Montgomery Community School Corporation · 2010. 9. 17. · SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Junior/Senior High School Campus - Alternates ALTERNATES BUDGET #1

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Junior/Senior High School Campus - Alternates

ALTERNATES BUDGET

#1 Soccer Parking (88 car spaces) $145,915

#2 Concrete Sidewalk at Football Stadium to Soccer Fields $ 47,188

#3 New JV Dugouts (Total of 4) for Baseball and Softball Fields $265,557

#4 Brick on Dugouts for Baseball and Softball Fields $ 74,540

#5 Brick & Insulation on Baseball and Softball Outbuilding $ 74,717

#6 Black PVC Fencing for Baseball and Softball Fields $ 75,000

#7 Air Conditioning of the Main Gymnasium $816,028

#8 LED lights at the Softball and Baseball Fields $110,527

Page 9: South Montgomery Community School Corporation · 2010. 9. 17. · SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Junior/Senior High School Campus - Alternates ALTERNATES BUDGET #1

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Project Schedule

Oct. 9

Page 10: South Montgomery Community School Corporation · 2010. 9. 17. · SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Junior/Senior High School Campus - Alternates ALTERNATES BUDGET #1

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Project Schedule Milestones

Event Date

FH Complete Design Oct 13

Release Bid Documents Oct 17

1st Legal Advertisement Oct 24

Pre-Bid Conference Oct 26

2nd Legal Advertisement Oct 31

Receive Sealed Bids Nov 14

Review GMP #1 w/ Leadership Team Nov 30

Board Award GMP #1 to Skillman Dec 5

Page 11: South Montgomery Community School Corporation · 2010. 9. 17. · SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION Junior/Senior High School Campus - Alternates ALTERNATES BUDGET #1

SOUTH MONTGOMERY COMMUNITY SCHOOL CORPORATION

Project Update