Upload
theresa-mcdowell
View
216
Download
0
Tags:
Embed Size (px)
Citation preview
South Tampa Area Reclaimed (STAR) Project
Phase II
City of Tampa, Florida
Presented to:
Presented by:
May 2005
The City of Tampa’s reclaimed water reuse program accomplishes
several City goals Conserves City’s potable water resources Avoids the purchase of potable water from
Tampa Bay Water Supports SWFWMD beneficial reuse goals
STAR Phase II:
113 miles of 2- to 8-inch
pipe
14 miles of 12- to 24-inch
pipe
Ground storage tank and pump station at Howard F.
Curren facility
Key project components must be addressed for STAR Phase II
Appropriate sizing of pipes, high service pumps, and ground storage tanks to achieve a high quality of service and avoid low pressure problems
Work with the City to achieve customer connections
Achieve hassle-free construction in established South Tampa neighborhoods
Control costs
To successfully implement the STAR II project, the selected team must
provide: A project team and manager with experience with similar
projects Appropriate sizing of facilities to assure reclaimed water
availability to customers and ease of operation A project approach that focuses on achieving hassle- free
construction and cost control Comprehensive communications program that includes
effective public outreach for sign-up and construction, and also achieves communication with all involved City Departments
A team with trust and proven dedication to the City of Tampa
To successfully implement the STAR II project, the selected team must
provide: A project team and manager with experience with
similar projects Appropriate sizing of facilities to assure reclaimed water
availability to customers and ease of operation A project approach that focuses on achieving hassle- free
construction and cost control Comprehensive communications program that includes
effective public outreach for sign-up and construction, and also achieves communication with all involved City Departments
A team with trust and proven dedication to the City of Tampa
Project ManagerRobert Ainslie
Senior ConsultantDavid Tippin, P.E.
Mike Culpepper, CGC
Steve Daignault, P.E.Chairman
Consultants CompetitiveNegotiation Committee
Pipeline DesignJoel Hall, P.E.
ConstructionCoordinationRobert Ainslie
Project ControlsBrenda Ellison
Public OutreachBrian ManwaringKaren Woodworth
Roberts Communicationsand Marketing, Inc.
Pump StationDesign
Hank Postrozny, P.E.
Principal in ChargeTom Waldeck, P.E.
Principal In ChargeTom Waldeck, P.E. 30 Years
Experience JEA Ave Maria GDU
Pipeline DesignJoel Hall, P.E.
20 Years Experience
JEA West Melbourne City of Melbourne
Pump Station DesignHank Postrozny, P.E.
26 Years Experience
City of Tampa Rockdale County Mandarin
Senior ConsultantDavid Tippin, P.E.
41 Years Experience
Former Director, Tampa Water Department
Senior ConsultantMike Culpepper, CGC 31 Years
Experience Pinellas County Fort Lauderdale
Project Manager &Construction Coordination
Robert Ainslie 31 Years Experience David L. Tippin WTF Forsyth County WTP Forsyth County
Transmission Mains Alexander City
Transmission Main
Public OutreachBrian Manwaring 10 Years
Experience Pinellas
County
Public OutreachKaren Woodworth 15 Years
Experience City of Tampa
STAR Phase I
We will meet Tampa’s WMBE* objectives through essential
service firms Metzger & Willard* – Pipeline design services Nodarse & Associates, Inc.* –
Geotechnical services Echezabal & Associates, Inc.* – Surveying Roberts Communications & Marketing, Inc.* –
Public involvement and customer sign-up Kisinger Campo & Associates – Pipeline and
civil design and permitting
14 offices in Florida with 800 employees
– 90 in west central Florida offices
14,500 employees in 120 offices worldwide
Backing our project team are all the resources needed to get the
job done
To successfully implement the STAR II project, the selected team must
provide: A project team and manager with experience with similar
projects Appropriate sizing of facilities to assure reclaimed
water availability to customers and ease of operation A project approach that focuses on achieving hassle-
free construction and cost control Comprehensive communications program that includes
effective public outreach for sign-up and construction, and also achieves communication with all involved City Departments
A team with trust and proven dedication to the City of Tampa
Steps to Size and Design Reclaimed Water Irrigation
System Step 1 – Review current
assumptions and City policies
Step 2 – Review STAR Phase 1 data to determine diurnal use patterns – hour/day and irrigation frequency – days/week
0
10
20
30
40
50
60
70
80
90
12:00:00AM
4:00:00AM
8:00:00AM
12:00:00PM
4:00:00PM
8:00:00PM
Time of Day
mg
d
Step 3 – Determine level of service required Step 4 – Establish STAR Phase II design demand criteria Step 5 – Run modeling scenarios for different peaking
factors Step 6 – Evaluate the need for booster facilities
Steps to Size and Design Reclaimed Water Irrigation
System Step 7 – Size piping to meet required flows and
pressures at different levels of service Step 8 – Develop cost analyses for different flow
scenarios Step 9 – Select pipe sizing alternative Step 10 – Check the diurnal and seasonal availability
of reclaimed water from the Howard F. Curren AWTP and compare with projected demands seasonal, daily, and hourly demands
Step 11 – Size storage facilties and pump station
Keys to success are communication, understanding
and endorsement
Endorsementof Stakeholders
ProcessProcess
SWFWMDSWFWMD
Water DepartmentWater Department
User GroupUser GroupGISGIS
AerialsAerials
Sewer DepartmentSewer Department
Routine DesignRoutine Design
Meet with all agencies at project outset to accelerate
permitting process FDEP
– Reclaimed water service area
City of Tampa– Right of Way
FDOT– Right of Way
Railroad– Right of Way
Examine coordination with other projects
Detailed permit/approvals tracking provides for at-a-glance assessment
of status
We recently sized, designed, and permitted reclaimed water irrigation
facilities for Ave Maria,a 5,000 acre residential development
Ave Maria Water and Wastewater Systems– Planning and design of
residential irrigation system with reclaimed water
– Planning, design and permitting of water and wastewater facilities
To successfully implement the STAR II project, the selected team must
provide: A project team and manager with experience with similar
projects Appropriate sizing of facilities to assure reclaimed water
availability to customers and ease of operation A project approach that focuses on achieving hassle-
free construction and cost control Comprehensive communications program that includes
effective public outreach for sign-up and construction, and also achieve communication with all involved City Departments
A team with trust and proven dedication to the City of Tampa
Project Designed andProject Designed andConstructed in 23 months!Constructed in 23 months!
Task Order Contracting
Divide pipeline projects into approximately 40 task orders
CH2M HILL team to provide 6 design teams City to pre-qualify to retain 6 acceptable
contractors– Unit price bids based on 1/6 of the total quantities
As designs are completed, work is assigned to contractors by task order
Smaller construction packages encourage participation by local contractors
Task Order Contracting optimizes design and construction
Allows for simultaneous design and construction, saving time and cost of individual project bidding
Task orders are sized to reduce impact on neighborhoods
Gets users on line quickly and encourages more customers to connect
Contractor Performance
Criteria
Additional construction is assigned to best-performing
contractors
Meets / beats project scheduleResponsiveness to community issuesResponsiveness to restoration issuesCost saving suggestions
Consistent communication and monitoring of design teams will
expedite delivery Assign design packages - as many as team
can handle Hold weekly progress meetings Maintain ongoing milestone review Ensure that QA/QC standards are followed
Considering construction during design controls project cost
Constructibility reviews Task Order Contracting
– Allows contractors to plan ahead, resulting in lower prices• Maximize resources• Increased productivity
Fast-track design and construction– Saves time overall, and time is money– Controls cost through efficient construction – Improves designer/contractor performance through
workload leveling
REPORTS TO:City Staff
Project TeamElected Officials
CommunityRegulators
Construct Teams
Web-BasedAccess (if desired)
Successful project controls result in effective communication
Schedule
Cost Data
Projects DataDocumentsExpedition
- Primavera (P3 )
Simplified project reporting facilitates tracking and decision-
making
Proposed Site for New Aeration Basin, Southwest Corner of Existing Plant
Critical Issues: Public comment period related to the environmental
assessment will close July 9th Need environmental clearance by the TWDB to begin WWTP
construction
Cost Variance Analysis: Insufficient data currently available from LCRA PeopleSoft
Financial Data System.
Financial Summary : (Data Period) 6-01-00 to 06-30-00 EAC (Estimate At Completion) : $8,181,659
Program: Water Treatment System Design
Project No.: 2001- 01
Project Manager: John Stomp
Major Contracts/Purchase Orders:Vendor PO's CO's Total
1 Brow n & Caldw ell $109,500 $11,500 $121,000
2 PSC $314,834 $0 $314,834
3 MCI $22,863 $0 $22,863
4 CDM $1,245,417 $0 $1,245,417
5 Boyle $2,321,544 $0 $2,321,544
Totals $4,014,158 $11,500 $4,025,658
Project 'S' Curve (Budget vs Actual)
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$8,000,000
$9,000,000
Jan-9
9
Mar
-99
May
-99
Jul-9
9
Sep-9
9
Nov-99
Jan-0
0
Mar
-00
May
-00
Jul-0
0
Sep-0
0
Nov-00
Jan-0
1
Project Duration
BCWS ACWP EAC
EAC$8,181,659
CURRENT FINANCIAL DATA THIS PERIODFISCAL YEAR
1999INCEPTION TO
DATEBCWS (Budgeted Cost of Work Scheduled) $134,000 $2,788,000 $2,788,000ACWP (Actual Cost of Work Performed) $62,209 $2,662,997 $2,662,997Cost Variance Amount (CV = BCWS - ACWP) $71,791 $125,003 $125,003Cost Variance Percent (% = CV / BCWS) 54% 4% 4%
Project IDProject ID Contracts & POsContracts & POs
CashflowCashflow
Financial SummaryFinancial Summary
Cost Variance AnalysisCost Variance Analysis
Critical IssuesCritical Issues
Record PhotoRecord Photo
Successful experience shows capabilities
Pinellas County Galvanized Pipe Replacement Program– Managed design/installation of
118 miles of water distribution pipe in densely urbanized area
– Completed in 18 months, under budget, and under the radar
– Intensive public outreach defused concerns; No issues required elected official involvement
To successfully implement the STAR II project, the selected team must
provide: A project team and manager with experience with similar
projects Appropriate sizing of facilities to assure reclaimed water
availability to customers and ease of operation A project approach that focuses on achieving hassle- free
construction and cost control Comprehensive communications program that
includes effective public outreach for sign-up and construction, and also achieves communication with all involved City Departments
A team with trust and proven dedication to the City of Tampa
Communications plan has four main goals
Achieve customer connections Effectively inform residents of construction
times and locations Effectively respond to complaints Coordinate with all stakeholders and the City
of Tampa
Customer connections are critical to meeting City reclaimed water goals
Potential revisions to reclaimed water rates and policies to encourage sign-up and connection
Broad range of marketing tools encourages hook-up– Website– Neighborhood meetings– Newsletter/FAQs– Focus groups from affected areas
Follow-up with customers who did not sign up or connect
Incentives for connection
Focused communication during construction minimizes customer
complaints
Pinellas County - Suggested Language for Notification Letter of Gal Pipe Replacement Project
(Draft)
Dear Homeowner:
Re: Replacement of water lines in your neighborhood
Pinellas County Commission has approved a water line replacement project for all galvanized pipe
over the next 2 years. (Insert language describing general reasons behind replacement project.)
We will be in your neighborhood within the next several months.
The construction will all be within the dedicated right-of-way and all efforts will be made to limit
the impact to any landscaping or improvements within that right-of-way. However, please be
assured that Pinellas County Utilities will in fact be responsible for restoration of any areas that may
be affected.
Your drinking water supply should not be impacted.
We have set up several ways to keep you informed.
1.Our website is ___________________
2.Please find attached answers to frequently asked questions
3.The hotline phone number is _____________
4.Green Vest Program is (description) and the number to call
during construction is ____________
5.Public Information Meeting for your neighborhood is (location
date and time).
If you have any questions, please call our hotline #, _________. We are looking forward to serving
you.
Sincerely,
Pinellas County Utilities
Pinellas County - Suggested Language for Notification Letter of Gal Pipe Replacement Project
(Draft)
Dear Homeowner:
Re: Replacement of water lines in your neighborhood
Pinellas County Commission has approved a water line replacement project for all galvanized pipe
over the next 2 years. (Insert language describing general reasons behind replacement project.)
We will be in your neighborhood within the next several months.
The construction will all be within the dedicated right-of-way and all efforts will be made to limit
the impact to any landscaping or improvements within that right-of-way. However, please be
assured that Pinellas County Utilities will in fact be responsible for restoration of any areas that may
be affected.
Your drinking water supply should not be impacted.
We have set up several ways to keep you informed.
1.Our website is ___________________
2.Please find attached answers to frequently asked questions
3.The hotline phone number is _____________
4.Green Vest Program is (description) and the number to call
during construction is ____________
5.Public Information Meeting for your neighborhood is (location
date and time).
If you have any questions, please call our hotline #, _________. We are looking forward to serving
you.
Sincerely,
Pinellas County Utilities
Justdropping anote to sayas part of
Fort Lauderdale’sWater System
Upgrade[insert street name]will be closed from
[insert time]to
[insert time]
Neighborhood meetings Direct mail letter Door hangers 24-hour complaint
hotline Interactive website Project info sheets On-site construction
liaisons
Interactive website provides current information to residents
Allows quick search for: – Customer
addresses– Project
boundaries – Pipe to be
installed “Mouse over”
provides project number and construction schedule
Double-click accesses Project Information Sheet
Constant communication with all stakeholders is vital to
success
Must happen at Must happen at all all phases of the projectphases of the project
Contracts AdministrationDepartment
Contracts AdministrationDepartment
STAR HotlineSTAR HotlineCH2M HILL
Team
Community AffairsCommunity Affairs
Engineering DepartmentEngineering Department
Sewer DepartmentSewer Department
Neighborhood andCommunity Relations
Neighborhood andCommunity Relations
FDOTFDOT
Tampa Water DepartmentTampa Water Department
Other InfrastructureProviders
People’s Gas TECOCSX Railroad Verizon
Other InfrastructureProviders
People’s Gas TECOCSX Railroad Verizon
Public Worksand Utility Services
Public Worksand Utility Services
Business andHousing Development
Business andHousing Development
To successfully implement the STAR II project, the selected team must
provide: A project team and manager with experience with
similar projects Appropriate sizing of facilities to assure reclaimed
water availability to customers and ease of operation A project approach that focuses on achieving hassle-
free construction and cost control Comprehensive communications program that includes
effective public outreach for sign-up and construction, and also achieves communication with all involved City Departments
A team with trust and proven dedication to the City of Tampa
CH2M HILL has worked successfully with the City since
the 1980s David L. Tippin WTF
Expansion David L. Tippin WTF Re-rate Tampa Potable Water
Aquifer Storage Recovery (ASR) Program
Security Vulnerability Assessment
Emergency Response Plan
CH2M HILL Team provides the City of Tampa:
A project team and manager with experience with similar projects
Appropriate sizing of facilities to assure reclaimed water availability to customers and ease of operation
A project approach that focuses on achieving hassle- free construction and cost control
Comprehensive communications program that includes effective public outreach for sign-up and construction, and also achieves communication with all involved City Departments
A team with trust and proven dedication to the City of Tampa