1
Southcentral Power Project
International Transmission Substation
Project Update, June 2012
Chugach Electric
Board of Directors
July 25, 2012
2
Project safety
• Safety First
– Two (2) Lost Time Accident to date
– Ten (10) Recordable Events to date
– Fatality of SNC Lavalin Pipefitter
• Remains under investigation by AKOSHA
• Report expected by August 2012
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2
2012 2013
DESIGN
Site/building work
Equipment Installations
Interconnection
Startup
2007 2008 2009 2010 2011
CTGs
STG
OTSGs
Site Prep
CONSTRUCTION
2013
Development & Preliminary Engineering
Construction Permits
Owner Procurement
OE EPC Contract
2007 2008 2009 2010 2011 2012
Guaranteed Substantial Completion
3
Project Schedule
overview
4
epc activities
• Engineering 100% complete
• Construction 86% complete – Hydrostatic testing of boilers along with
pressure testing of the fuel gas system
– CTG filter house cleaning prior to first
fire
– Completing last large cable installations
• Commissioning 31% complete – Vendors on site in support of
commissioning activities for CTGs,
STG, gas compressors and water
systems
– 31 systems accepted from
construction
Power plant
Site condition
July 11, 2012
6
International transmission
SUBSTATION
SCHEDULE overview
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Bid
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Permits
Steel
2010 2011 2012
FAA - Tower Permit
MOA - Fence & Tower Permits
Engineering
2009
2012 2011 2009 2010
Steel
Electrical
Construction
Material Procurement
Breakers
Control Enclosure
Autotransformer
Site Work
Substantial Completion July 2012
7
International transmission
Substation
SITE CONDITION
July 13, 2012
8
GETAWAY STRUCTURE
installation
Installation of structure and wire for ML&P connection
9
INTERNATIONAL TRANSMISSION
SUBSTATION
status
• All getaways have been installed and the
substation is energized
• Items left to complete include the contractor’s
punch list and final connections to the 138/115
kV power transformer
10
Projects summary
Scope Not Changed
(includes road improvements)
Schedule Ahead of Schedule
12/2012 vs. 6/2013
Cost SPP: ML&P $103.5M Chugach $257M Total $360.5M
ITSS: ML&P $5.3M Chugach $16.5M Total $21.8M
Safety 2 LTA
10 Recordables