Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Space Shuttle Lessons Learned Knowledge Sharing Forum
NASA KSC Lesson Learn Entry: 3236
Solid Rocket Booster (SRB) Flame Trench Refractory Failure Modes
Gabor Tanacs
Armand Gosselin
USA L&RS Engineering
January 27, 2011
Page 2 Date
File Name
Problem Definition
• During the launch of STS-124, over 3,500 of the 22,000 interlocking
refractory bricks that line the east wall of the SRB Flame Trench were
liberated from Pad 39A
• The STS-124 launch anomaly generated an agency-wide initiative in
order to determine root cause, assess vehicle safety, ground support
equipment (GSE) safety and reliability, and to determine corrective
action
• The investigation encompassed:
– Radar imaging
– Infrared video review
– Debris transport evaluation
– Computational fluid dynamics (CFD)
– Non-destructive evaluation (NDE)
– Analysis in order to validate the corrective action
Page 3 Date
File Name
Space Shuttle Launch and Systems
Solid Rocket Boosters
(SRB)
Cross Beam
Support
Mobile Launch
Platform (MLP) Crawler
Transporter
(CT)
Orbiter
Space Shuttle Main Engine Exhaust Solid Rocket Booster Exhaust
External Tank (ET)
Solid Rocket Booster (SRB)
Page 4 Date
File Name
Complex 39, Launch Pad Flame Trench Configuration
Main Flame
Deflector
6” Refractory
Wall Surface
North
Vehicle Centerlines
Catacombs
North SRB
Flame Trench
SSME
Flame
Trench
Rotating
Service
Structure
(RSS)
Fixed Service
Structure (FSS)
SRB Flam
Trench
West Side
Pad Surface
Main
Flame Deflector
North
Side
Flame Deflector
e
East Side
Pad Surface
Page 5 Date
File Name
Launch Complex 39 Pad A SRB Flame Trench – Looking South
Solid Rocket Booster
Flame Trench
Solid Rocket Booster
(SRB) (2 Total)
Flame Trench Walls
Mobile Launch
Platform (MLP)
External Tank
(ET)
SRB Flame Deflector
Fixed Service
Structure (FSS)
Page 6 Date
File Name
Complex 39, Pad A Flame Trench Construction ~ 1964
Refractory Brick Installation
Catacomb Cell Construction
Page 7 Date
File Name
Flame Trench Wall Refractory Brick Configuration
Concrete Retaining Wall
Dove Tail Anchor
Refractory Wal
(Non-Slotte
Refractor
(Slotted – D
l Brick
d)
y Wall Brick
ove Tail Slot)
Epoxy/Mortar Bond
Dove Tail Anchor Wall Slot Rail
Typical Worn Refractory Brick
Page 8 Date
File Name
Flame Trench East Wall Damaged Area
• East Brick Wall Damage
– Estimated Total Bricks On East Wall ~ 22,000
– Estimated Lost Bricks ~ 3,540 (16% Loss of East Wall)
>
14.3’ 15.3’ 6.9’
13.8’
73.3’
9.2’ ~ CenterLine
11’
Damaged Area SRB Flame Deflectors
Damage Area
Page 9 Date
File Name
Brick Impact Mapping • Perimeter Fence Damage
– Fence at ~1800 ft from damage initiation
• Bricks Beyond Perimeter Fence
Page 10 Date
File Name
Description of Driving Event
• Radar tracking showed some of the bricks were ejected at about 680 mph but, because of their location and direction of travel, did not damage flight hardware
• An inspection found that:
– The dovetail anchor plates and metal wall slot rails used to secure the refactory bricks to the concrete back wall were heavily corroded
– Mortar between brick joints had eroded
– The epoxy applied to help secure the bricks to the wall was degraded
• When the pad catacomb walls were constructed in the ‘60s imperfections in the straightness of the concrete surface were fixed using a mortar skim mix to which the epoxy was applied
– This mortar skim mix contributed to the de-bonding
Page 11 Date
File Name
Description of Driving Event (continued)
Refractory Wall Brick
-With Dovetail Metal Anchor
Refractory Wall Brick
-With No Metal
Anchor
Dovetail
Metal Anchor
(3/16” Plate)
Metal Wall Slot
(#.10 Ga.)
Epoxy/Mortar bonded to
Concrete Wall (Typical)
• Brick-to-Wall Bond Failure
– Dovetail Anchor Plate Corrosion
– Epoxy Degradation
Page 12 Date
File Name
Description of Driving Event (continued)
• For years, the health of the brick portion of the flame trench was determined by measuring surface erosion
– Surface erosion, to the point where an inch or greater of brick remained from the tongue-and-groove to the face of the brick, was considered structurally sound
– Without other information from which to work, the condition of the metal wall ties and the epoxy could not be determined.
Page 13 Date
File Name
Description of Driving Event (continued)
• The flame trench refractory brick system was designed for the Saturn Apollo program, which had a liquid fuel propulsion system, and was grandfathered into use in the Shuttle program, which has a solid fuel propulsion system
– This was done without a detailed definition of the loads and environments, an inspection plan, or a good set of calculations or assumptions derived from the Saturn design parameters
– The liquid fuel propulsion system generated more heat because the flight vehicle was held down until enough thrust was achieved for launch
– With the solid fuel propulsion system, the launch vehicle ascends from the pad fairly quickly; and with the water from the sound suppression system, there is less direct heat impingement
Page 14 Date
File Name
Description of Driving Event (continued)
• With the solid fuel propulsion system the overall environment is worse
– Materials are heated, then cooled with the sound suppression water
– The solid propellant residue (aluminum oxide) is abrasive
– Another of its byproducts (hydrogen chloride) subjects the materials in the launch environment to a hydrochloric acid bath
– The released water acts like a blanket to trap the acoustic energy of the SRB ignition below it, thus subjecting the materials and equipment below it to a more intense acoustic environment
Page 15 Date
File Name
Lessons Learned
• The fact that a legacy system has never failed catastrophically does not guarantee that it will not fail in the future
• Detailed loads and environments need to be defined for design of new launch vehicle GSE and facilities
• More comprehensive inspection methods should have been used in order to detect material erosion when it was first becoming noticeable in the flame trench
Page 16 Date
File Name
Recommendation
• Define the detailed loads and environments for future programs, and certify the flame trench systems for the launch pads that will be used with any new family of launch vehicles
• Perform a risk analysis for flame trench failure modes
• Develop inspection criteria, inspection methods, and maintenance and repair procedures for the flame trenches for both launch pads
• For a legacy system such as the flame trench
– Obtain as much historical information and data as possible
– Develop a test plan to validate the legacy system against new loads and environments
– Test the performance of new types of refractory materials to see if these advancements can benefit the program
Page 17 Date
File Name
Evidence of Recurrence Control Effectiveness
• A project has been established to gather data during the remaining launches by evaluating two alternative refractory materials on a test stand attached to the SRB main flame deflector
• The Flame Trench and Main Flame Deflector have been instrumented to better understand any deltas between the predicted and actual launch environment parameters
Pressure Measurement
Detail A (Typical)
Tungsten Piston
Calorimeter COTS Sensors
Witness Rod Accelerometer
(Backside)
Flame Trench Wall & MLP
Instrumentation Locations
Main Flame
Deflector
Test Stands (2 places) w/samples
Page 18 Date
File Name
Reference Documents
• Flame Trench Refractory Failure Modes
– Lessons Learned Entry: 3236
• Lesson Date: 2010-06-1
• Submitting Organization: KSC
• Submitted by: Annette Pitt
• POC Name: Michael Olka
• POC Email: [email protected]
• POC Phone: 321-861-9581
• STS-124 Pad 39A Launch Damage High-Visibility Type A Mishap Out Brief
– IRIS Case Number: 2008-176-00002
• Date of Mishap: May 31, 2008
• Presenters: Miguel A. Rodriguez, MIT Chair
Gerald D. Schumann, Ex-Officio
• Date of Briefing: July 15, 2008