SPE-116528-MS

Embed Size (px)

Citation preview

  • 7/21/2019 SPE-116528-MS

    1/14

    SPE 116528

    Horizontal Well Best Practices to Reverse Production Decline in MatureFields in South China SeaYou Hongqing, Wei Ping, Tian Xiang, Xu Xiang Dong, Lian JiHong, Thanh Tran, Yoseph J. Partono : CACT,Jeffrey Kok, Liu Yang, Sarfraz Balka: Schlumberger

    Copyright 2008, Society of Petroleum Engineers

    This paper was prepared for presentation at the 2008 SPE Asia Pacific Oil & Gas Conference and Exhibition held in Perth, Australia, 2022 October 2008.

    This paper was selected for presentation by an SPE program committee following review of information contained in an abstract submitted by the author(s). Contents of the paper have not beenreviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material does not necessarily reflect any position of the Society of Petroleum Engineers, itsofficers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written consent of the Society of Petroleum Engineers is prohibited. Permission toreproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of SPE copyright.

    AbstractThe Huizhou 6S and 3S oil fields in the Pearl River Basin,

    Offshore South China Sea are mature fields which have

    produced 40% to 60% of their original oil in place since1991. Currently the field production is rapidly declining

    and water production is increasing. However, through

    reservoir surveillance data, geologic and reservoirmodeling, significant recoverable oil was identified in

    shaly sandstone reservoirs and attic structural locations of

    clean sandstone reservoirs. As a result, a comprehensiveportfolio of prospects has been built for a robust

    development program. Horizontal wells were utilized toimprove oil recovery in shaly sands and to reduce water

    coning in thin remaining oil columns. Horizontal drillingbest practices were applied during well planning and

    drilling executions, such as optimum well designs,specific LWD/MWD tool selections, low fluid loss

    drilling fluids, real-time geosteering data monitoring and

    the cleaning of the pay zone during completions were

    applied to maximize reserve recovery and successfullyreverse the fields production decline.

    IntroductionThe Huizhou Oil Fields are located in the Pearl River

    Mouth Basin, South China Sea approximately 190 kmsoutheast of Hong Kong (Figures 1). Agip, Chevron and

    Texaco signed the contract in 1983 and they discovered

    nine prolific oil fields by the year of 1989. Firstproduction in this area was from the Huizhou 1S field in

    1990 followed by Huizou 6S field in 1991 and Huizhou

    3S field in 1995. There are currently 7 platforms and anFPSO which are producing oil and gas from 10 fields.

    New efforts were put in the exploration activity with the

    drilling of exploration and appraisal wells in the period of2002-5resulting in another significant discovery and the

    commercialization of two previously discovered fields.

    Geological OverviewHuizhou 6S and 3S oil fields are located in Pearl River

    Mouth basin, South China Sea, which is a continental

    margin sedimentary basin formed during the rifting of theSouth China Sea in the Late Mesozoic to early Tertiary.

    The main pay zones where CACT deploys horizontal and

    multilateral well technology were deposited as delta frontbar and coalesced, stacked fluvial-deltaic channel sands in

    early Miocene time. Oil accumulations with low gas

    saturation and no gas cap are mostly found in 4-way-dipclosures, which are associated with basement highs. In

    some cases the traps are also associated with sand layerpinch-outs.

    The reasons for drilling horizontal wells arepredominantly based on the following two considerations:

    Firstly, after over 15 years of high rate oil production,these fields have gradually entered into a mature and

    high-water-cut phase. Oil to water contacts (OWCs) have

    significantly encroached upward leaving thin remaining

    oil columns and causing high water production from all ofthe existing wells. Due to reservoir heterogeneity, some

    of the reservoirs exhibit uneven strength of aquifersupport causing OWCs to tilt after years of production.

    To reduce and reverse the rapidly declining oil production

    rate is a challenge CACT needs to confront. Tosignificantly improve production efficiency of theremaining potential attic oil locations, horizontal well is

    the first priority among various alternatives.In addition, the poor petrophysical properties of shaly

    layers did not effectively produce oil from vertical wells.

    The recent horizontal and multilateral wells in these shaly

    zones have greatly improved production performance andfield recovery. The petrophysics and depositional

    environment of the reservoirs are briefly described asfollows.

  • 7/21/2019 SPE-116528-MS

    2/14

  • 7/21/2019 SPE-116528-MS

    3/14

    SPE 116528 3

    in vertical depth which could be detrimental to

    the success of a horizontal well drilling and

    completion. This risk may be mitigated bydrilling a pilot hole prior to drilling the

    horizontal well. In May 2008, CACTreprocessed the 3-D seismic data using a pre-

    stacked depth migration (PSDM) technique to

    reduce the structural risk.- The risk of not finding sufficient oil

    accumulation because the current OWC have

    moved higher than expected leaving too thin oilcolumn to produce. If there is no recent

    information on the current fluid contact within

    the radii of 1000m, it is important to acquire data

    to locate the current OWC. Cased hole loggingin nearby wells is a low cost option to survey the

    current fluid contact. If reliable cased-hole datacannot be acquired, a pilot hole is to be drilled

    prior to drilling a horizontal well.

    To anticipate the possibility that the pilot hole does notproof sufficient reserves in the target reservoir due to the

    above risks a backup target (Figure 5) is prepared as acontingency against drilling an uneconomic horizontal

    well.

    Pre-drilling PreparationOnce a horizontal target is selected a detailed well course

    is planned to ensure successful placement of thehorizontal section in the reservoir, casing run, casing

    cementation and installation of completion.

    1. Optimum Well Plan

    The design of the well plan requires close collaboration

    between geologist and drilling engineer in order to ensurethat the well trajectory is drillable and to reduce risks tothe lowest level and to achieve the best performing well.

    The direction of the existing well to be sidetracked does

    not usually following the simplest route to reach the targetlocation because of proximity with other existing wells.

    This condition causes difficulty in achieving low well

    tortuosity and dogleg severity, where iterative targetadjustments are required to optimize the well plan and

    ensure the modeled torque and drag are within allowable

    limits.A tangent section of 5m true vertical depth (TVD) above

    the target is generally planned to accommodate

    uncertainties in the geologic structure interpretation anddirectional survey. (Fig 6)

    Landing point of the horizontal section is typically

    planned 1m or less below the top of the reservoir to allowmaximum displacement from the current OWC. The

    angle along the horizontal section should not exceed 90

    degrees to avoid a goose-neck trajectory that could

    cause water blockage during production. Depending onthe quality of the reservoir and the simulation results a

    horizontal section of 300 to 1000m are planned.To accommodate difficult well drilling operations the

    following upgrades were done on the platform and

    drilling equipment:

    1- 225 tons pipe deck and 3500 m new derrick

    2- Hoisting rating: 350 klbs3- Hydraulic TDS: 37,000 ft-lb

    4- Mud pumps: 2 x P-750 + 1 x 3NB-800

    5- Mud tank: 900 bbls including one removabletank

    6- Shale Shakers: 3 X Derrick Hydrill2000 with

    0.47 cubic feet per min for each7- Centrifuge: 1 X Swaco518FVS

    Well Profil e

    All the well profiles were designed in 3-D, (Fig 7). In

    order to conventionally hit the planned target TVD,

    medium to high doglegs from 3.5 to 4.5 are required.

    But it was possible to limit doglegs to the minimum bydropping the inclination with a turn first and then building

    in the other direction. While designing the well profile, atangent section for ESP and holding of inclination from

    85-87 for a soft landing were also key requirements.

    The average open hole length for the sidetrack wellvaries

    between 2000 to 2500m. The 3-D profile designs producehigh tortuosity and high Directional Difficulty Index (Fig

    8 and Fig 9), where the average tortuosity can varybetween 220-250. Using a water base mud system

    further increased the torque and drag issues. To over-

    come this, basic drilling surface parameters such as RPM,

    WOB, mud pump flow rates are controlled. In addition,well bore improvement techniques such as adding

    lubricants to lower friction factors and the usage of rotarysteerable system (RSS) were employed. The application

    of RSS tool delivered excellent drilling results in all the

    wells, with the exception of one case where the tortuosity

    increases above 250 deg that created some issues whenrunning a 7 liner.

    Depending on the reservoir properties, multilateral wellswere also planned. The side track point selection was akey element of success that required detail planning and

    execution by the drilling and reservoir teams. In total,

    three multilateral wells were successfully drilled andcompleted with the combined teamwork and proper BHA

    selection.

    2. Technology Selection

    Whipstock and mi lli ng Window: In many occasions there

    is little cement behind the casing where a sidetrackwindow is milled. This leaves a sharp, off-sized window

    that causes problems when a drilling BHA or casing

    packer is passed through. As a remedy, a cement squeezearound the window is performed, giving very positive

    results. Experiences from other parts of the world showed

    that after the milling operation, the drilling BHAs had thetendency to track the casing. To address this problem, the

    whipstock on CACT wells are set either left or right of the

    high side.

    Bi t Selection: Historically in CACT, drilling with water

    base mud (WBM) in abrasive formation with the presenceof hard and interbedded stringers greatly reduces a PDC

    bits performance with bit balling and premature broken

  • 7/21/2019 SPE-116528-MS

    4/14

  • 7/21/2019 SPE-116528-MS

    5/14

    SPE 116528 5

    hole and modeling the liner run with various simulations

    to determine the number and position of liner centralizers

    required.With this practice, all the wells except one underwent

    very good results with the liner run arriving to bottom. Inthat single case (well HZ6S-10Sb), the liner got

    prematurely stuck leaving almost 400m of open hole

    exposed. Further investigations identified the root causeof such sticking to the liner hanger assembly. As aremedial, a rotating liner hanger was implemented for

    future liner designs to help break down the excessivefriction by liner rotation and push the liner to bottom.

    ConclusionsHorizontal and multilateral wells have proven effective to

    produce remaining oil in thin columns and shaly

    formations in mature HZ3S and HZ6S oil fields.

    Current surveillance data and pilot holes are essentials toprovide controls for drilling horizontal wells.

    Vigilant team work between subsurface, well placement

    and drilling teams during all phases of operations,including reservoir modeling, well planning and well

    drilling was necessary to provide strategic planning with

    contingencies for the best and timely real time decisions.The sidetrack campaign on the HZ3S and HZ6S fieldsin

    2007 successfully reversed the production decline wherethe cumulative oil in 2007 from four sidetrack wells

    totaled around 1.5MMSTB. This accounted for 30% of

    the total field production where the oil rates from these

    four wells held 30% of the total field production.

    AcknowledgmentsThe authors would like to thank CACT, CNOOC, ENIand Chevron for the permission to publish this

    information.

    AbbreviationLWD: Logging while drilling

    MWD: Measurement while drillingFPSO: Floating Production Storage & Offloading

    OWC: Oil Water Contact

    BOPD: Barrels of Oil per Day

    PVT: Pressure-Volume-TemperaturePSDM: Pre-Stacked Depth Migration

    TVD: True Vertical DepthTDS: Top Drive System

    ESP: Electric Submersible Pump

    RPM: Revolutions per MinuteWOB: Weight on BitRSS: Rotary Steerable System

    PDM: Positive displacement mud motor

    BHA: Bottom Hole AssemblyPOB: Personnel On Board (Rig or Platform)

    WBM: Water Based Mud

    PDC: Polycrystalline Diamond CompactROP: Rate of Penetration

    DIF: Drill in Fluid

    API: American Petroleum InstituteTD: True Depth

    RT: Real Time

    RTGS: Real Time Geosteering Software

    DLS: Dogleg Severity

    CD&I: Continuous direction & inclinationMMSTB: Million Standard Barrels "oil"

  • 7/21/2019 SPE-116528-MS

    6/14

    6 SPE 116528

    Figure 1: CACT oilfields location map

  • 7/21/2019 SPE-116528-MS

    7/14

    SPE 116528 7

    Figure 2: Generalized stratigraphy of Pearl River Mouth Basin.

  • 7/21/2019 SPE-116528-MS

    8/14

  • 7/21/2019 SPE-116528-MS

    9/14

    SPE 116528 9

    Figure 5 Cross section showing a planned horizontal well with a pilot hole and a backup horizontal target

  • 7/21/2019 SPE-116528-MS

    10/14

    10 SPE 116528

    Fig 6: Depth Uncertainties in Landing a Horizontal Well

    Fig 7 Well Profile

  • 7/21/2019 SPE-116528-MS

    11/14

    SPE 116528 11

    Fig 8 Torque and drag modeling, Tripping load analysis will be required

    Fig 9 Torque and drag modeling, Tripping load analysis will be required

  • 7/21/2019 SPE-116528-MS

    12/14

  • 7/21/2019 SPE-116528-MS

    13/14

    SPE 116528 13

    ADN475 RT Image on InterAct

    Layer 1entr

    Cutting up strat

    Fig11 Density Image Example

  • 7/21/2019 SPE-116528-MS

    14/14

    14 SPE 116528

    Fig 12 Landing Model and Correlation Example

    Fig 13 Horizontal Section