    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    1/168

    VESDA FIRE ALARM SYSTEMUPGRADE PROJECT(JCN 805563)

    NEW YORK AIR ROUTE TRAFFIC

    CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    SPECIFICATIONS

    NOVEMBER 2010

    Prepared by: Federal Aviation AdministrationATO Tech Ops Engineering Services

    New York Enroute Engineering Center, AJW-E12A

    Project Engineer - Walter C. Lau

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    2/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    2/168

    TABLE OF CONTENTS

    SECTION INDEX

    SECTION TITLE

    DIVISION 0 - CONTRACT REQUIREMENTS

    DIVISION 1 - GENERAL REQUIREMENTS

    1-1 SUMMARY OF WORK

    1-2 SITE ACCESS, CONSTRUCTION LIMITS, USE OF FACILITIES AND WORK

    HOURS

    1-3 CONTRACTOR QUALITY CONTROL, SAFETY, COORDINATION,

    PERMITS, TESTING

    1-4 CUTTING AND PATCHING1-5 SCHEDULE CONSTRAINTS

    1-6 CONTRACTOR PREPARED CONSTRUCTION SCHEDULE

    1-7 FIRE LIFE SAFETY REQUIREMENTS

    1-8 TEMPORARY FACILITIES

    1-9 MATERIALS AND EQUIPMENT

    1-10 PROTECTION OF WORK

    1-11 CLEANING

    1-12 FINAL INSPECTION AND ACCEPTANCE OF WORK

    1-13 AS-BUILT FIELD DATA

    1-14 ADDITIONAL GENERAL REQUIREMENTS

    01300 SUBMITTAL PROCEDURES01782 OPERATIONS AND MAINTENANCE MANUAL DATA

    01820 DEMONSTRATION AND TRAINING

    DIVISION 2 - SITE WORK

    (NOT USED)

    DIVISION 3 CONCRETE

    (NOT USED)

    DIVISION 4 MASONRY

    (NOT USED)

    DIVISION 5 METALS

    (NOT USED)

    SECTION TITLE

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    3/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    3/168

    DIVISION 6 - WOOD AND PLASTICS

    (NOT USED)

    DIVISION 7 - THERMAL AND MOISTURE PROTECTION07270 FIRESTOPPING

    DIVISION 8 - DOORS AND WINDOWS

    (NOT USED)

    DIVISION 9 FINISHES

    (NOT USED)

    DIVISION 10 SPECIALTIES

    (NOT USED)

    DIVISION 11 EQUIPMENT

    (NOT USED)

    DIVISION 12 FURNISHINGS

    (NOT USED)

    DIVISION 13 SPECIAL CONSTRUCTION

    13850 LASER AIR SAMPLING SMOKE DETECTION SYSTEM

    DIVISION 15 MECHANICAL

    (NOT USED)

    DIVISION 16 - ELECTRICAL

    16050 BASIC ELECTRICAL MATERIALS AND METHODS

    16100 RACEWAYS, BOXES AND CABINETS

    16120 WIRES AND CABLES

    SECTION TITLE

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    4/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    4/168

    16190 SUPPORTING DEVICES

    16195 ELECTRICAL IDENTIFICATION

    16452 GROUNDING* * * * *

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    5/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    5/168

    1-1 SUMMARY OF WORK

    1-1.1 General.-

    1-1.1.1 Scope of work.- These specifications, together with the referenced specifications,standards, and drawings specified in the Contract Documents, cover the requirements for all

    work associated with the construction of the Vesda Fire Alarm System Upgrade Project at the

    New York Air Route Traffic Control Center (ZNY ARTCC) located in Ronkonkoma, New York.

    Following is a general description of the work:

    ZNY VESDA FIRE ALARM SYSTEM UPGRADE PROJECT

    JCN 805563

    SCOPE OF WORK

    THERE ARE FOUR BASIC BUILDING AREAS OF WORK:

    1) DYSIM & CONTROL WING BASEMENT2) OPERATIONS WING BASEMENT3) CONTROL WING FIRST FLOOR4) CONTROL WING ATTIC

    1) DYSIM & CONTROL WING BASEMENT:

    A) DYSIM AREA BASEMENT:

    CONTRACTOR TO REMOVE 1-DETECTOR, 1-CONTROLLER, 1-POWERSUPPLY, 1-BATTERY CABINET.

    FURNISH AND INSTALL:1) ONE VESDA LASER SCANNER SMOKE DETECTOR, MODEL VLS-314

    WITH INTEGRAL DISPLAY, PROGRAMMER, AND SUFFICIENT ON BOARD

    RELAYS.

    2) ONE VESDA POWER SUPPLY, VESDA MODEL VPS-100US-120, WITH 2

    VESDA MODEL VBT-012 BATTERIES.

    3) ESTABLISH ONE ADDITIONAL FIRE ALARM AIR SAMPLING PIPING

    ZONE.

    4) ALL NECESSARY ACCESSORIES AND HARDWARE.

    5) ALL NECESSARY MODIFICATIONS TO EXISTING PIPING, FIRE ALARM

    TERMINAL CABINET, FIRE ALARM CONTROL PANEL, FIRE ALARM AND

    POWER WIRING, FACP PROGRAMMING, ETC,.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    6/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    6/168

    B) CONTROL WING BASEMENT:

    CONTRACTOR TO REMOVE 2-DETECTORS. CONTRACTOR MAY REUSE TWOEXISTING BACKBOXES, IF NEEDED.

    FURNISH AND INSTALL:1) TWO VESDA LASER SCANNER SMOKE DETECTORS, VESDA MODEL

    VLS-304, EACH WITH INTEGRAL DISPLAY.

    2) TWO REMOTE TERMINATION AND RELAY PROCESSOR CARDS,

    VESDA PART # VRT-501.

    3) ESTABLISH THREE ADDITIONAL FIRE ALARM AIR SAMPLING PIPING

    ZONES IN EACH NEW DETECTOR.

    4) ALL NECESSARY ACCESSORIES AND HARDWARE.

    5) ALL NECESSARY MODIFICATIONS TO EXISTING PIPING, FIRE ALARM

    TERMINAL CABINET, FIRE ALARM CONTROL PANEL, FIRE ALARM AND

    POWER WIRING, FACP PROGRAMMING, ETC,.

    6) TIE-IN OF THE TWO NEW VESDA LASER SCANNER SMOKE

    DETECTORS, VESDA MODEL VLS-304 TO THE NEW VESDA LASER

    SCANNER SMOKE DETECTOR, MODEL VLS-314 LOCATED IN THE

    OPERATIONS WING BASEMENT.

    7) TIE IN OF DETECTOR ELECTRICAL POWER TO NEW POWER SUPPLY

    AND BACKUP BATTERIES LOCATED IN OPERATIONS WING BASEMENT.

    2) OPERATIONS WING BASEMENT:

    CONTRACTOR TO REMOVE 2-DETECTORS, 1-CONTROLLER, 1-POWERSUPPLY, 1-BATTERY CABINET. CONTRACTOR MAY REUSE EXISTINGBACKBOXES IF NEEDED.

    FURNISH AND INSTALL:1) ONE VESDA LASER SCANNER SMOKE DETECTOR, MODEL VLS-314,

    WITH INTEGRAL DISPLAY AND PROGRAMMER.

    2) ONE VESDA LASER SCANNER SMOKE DETECTOR, MODEL VLS-304,

    WITH INTEGRAL DISPLAY.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    7/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    7/168

    3) ) TWO REMOTE TERMINATION AND RELAY PROCESSOR CARDS,

    VESDA PART # VRT-501.

    4) ONE VESDA POWER SUPPLY, VESDA MODEL VPS-300US-120, WITH SIX

    VESDA BACKUP BATTERIES, VESDA PART # VBT-012.

    5) ONE VESDA POWER SUPPLY, VESDA MODEL VPS-100-120, WITH TWO

    VESDA BACKUP BATTERIES, VESDA PART # VBT-012.

    6) ESTABLISH THREE ADDITIONAL FIRE ALARM AIR SAMPLING PIPING

    ZONES AT EACH DETECTOR.

    7) ALL NECESSARY ACCESSORIES AND HARDWARE.

    8) ALL NECESSARY MODIFICATIONS TO EXISTING PIPING, FIRE ALARM

    TERMINAL CABINET, FIRE ALARM CONTROL PANEL, FIRE ALARM ANDPOWER WIRING, FACP PROGRAMMING, ETC..

    3) CONTROL WING FIRST FLOOR:

    MODIFY EXISTING UNDERFLOOR AIR SAMPLING PIPING AS SHOWN ONDRAWINGS, ESTABLISHING TWO ADDITIONAL FIRE ALARM AIR SAMPLING

    PIPING ZONES.

    4) CONTROL WING ATTIC FLOOR:

    CONTRACTOR TO REMOVE 4-DETECTORS, 1-CONTROLLER, 1-POWERSUPPLY, 1-BATTERY CABINET. CONTRACTOR MAY REUSE EXISTING

    BACKBOXES IF NEEDED.

    FURNISH AND INSTALL:1) ONE VESDA LASER SCANNER SMOKE DETECTOR, MODEL VLS-314,

    WITH INTEGRAL DISPLAY AND PROGRAMMER.

    2) THREE VESDA LASER SCANNER SMOKE DETECTORS, MODEL VLS-304,

    WITH INTEGRAL DISPLAY.

    3) ONE VESDA POWER SUPPLY, VESDA MODEL VPS-300US-120, WITH SIX

    VESDA BACKUP BATTERIES, VESDA PART # VBT-012.

    4) ONE VESDA POWER SUPPLY, VESDA MODEL VPS-100US-120, WITH

    TWO VESDA BACKUP BATTERIES, VESDA PART # VBT-012.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    8/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    8/168

    5) ESTABLISH 1 ADDITIONAL FIRE ALARM AIR SAMPLING PIPING

    ZONES AT 1 0F 4 DETECTORS.

    6) ESTABLISH 2 ADDITIONAL FIRE ALARM AIR SAMPLING PIPING

    ZONES AT 1 0F 4 DETECTORS.

    7) ESTABLISH TWO ADDITIONAL FIRE ALARM AIR SAMPLING PIPING

    ZONES AT 2 0F 4 DETECTORS.

    8) ALL NECESSARY ACCESSORIES AND HARDWARE.

    9) ALL NECESSARY MODIFICATIONS TO EXISTING PIPING, FIRE ALARM

    TERMINAL CABINET, FIRE ALARM CONTROL PANEL, FIRE ALARM AND

    POWER WIRING, FACP PROGRAMMING, ETC..

    NOTE:

    1. IF CONTRACTOR ENCOUNTERS ANY HAZARDUOUS, OR CONTROLLEDWASTE, HE SHALL DISPOSE OF THE MATERIAL IN ACCORDANCE WITH ALL

    FAA STANDARDS AND ORDERS, ALL NATIONAL STANDARDS AND ALL

    STATE AND LOCAL REQUIREMENTS.

    2. ALL AIR SAMPLING PIPING SHOWN ON DRAWINGS IS EXISTING.LOCATIONS ARE DIAGRAMMATIC ONLY. CONTRACTOR TO FIELD VERIFY

    LOCATION OF ALL AIR SAMPLING PIPING AND RECORD CONFIGURATION

    AND LOCATION ON PROJECT DRAWINGS.

    3. CONTRACTOR TO VERIFY AND CONFIRM IN WRITING TO THE COTR THATTHE EXISTING AIR SAMPLING PIPING IS FREE OF ANY OBSTRUCTIONS AND

    IS CONTINUOUS THROUGHOUT. IF ANY OBSTRUCTIONS ARE

    ENCOUNTERED CONTRACTOR IS TO REMOVE THOSE OBSTRUCTIONS.

    4. CONTRACTOR TO VERIFY THAT THE REPLACEMENT VESDA DETECTORMODEL VLS314 IS FULLY COMPATIBLE WITH EXISTING FIRE ALARM

    SYSTEM AND EXISTING AIR SAMPLING PIPING AND THAT THERE IS NO

    EXISITNG CONDITION THAT WOULD PREVENT THE NEW EQUIPMENT AND

    INSTALLATION FROM MEETING, OR EXCEEDING, MANUFACTURERS

    RECOMMENDED CRITERIA AND THE PROJECTS OBJECTIVES.

    CONTRACTOR TO SUBMIT VERIFICATION IN WRITING TO COTR FOR

    APPROVAL.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    9/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    9/168

    5. WHEN COMPLETED THERE WILL BE A TOTAL OF 29 FIRE ALARM AIRSAMPLING PIPING ZONES ANUNCIATING AT THE FACILITYS FIRE ALARM

    CONTROL PANEL. EACH FIRE ALARM AIR SAMPLING PIPING ZONE WILL

    HAVE FOUR SMOKE THRESHOLD ALARM LEVELS.

    6. CONTRACTOR SHALL PROVIDE IN DEPTH, MANUFACTURER APPROVEDTRAINING, ON SITE, FOR UP TO FOUR FAA EMPLOYEES ON EACH OF THREE

    SHIFTS. TRAINING SHALL INCLUDE REPROGRAMMING OF VESDA

    CONTOLLERS, PREVENTIVE MAINTENANCE, TROUBLESHOOTING, AND

    CLEANING OF AIR SAMPLING PIPING, IN ADDITION TO THE FACTORY

    AUTHORIZED END USER TRAINING.

    7. AT 4, 8, AND 12 MONTHS AFTER ACCEPTANCE OF SYSTEM, CONTRACTORSHALL RETURN TO FACILITY AND RE-VERIFY ALL SYSTEM CHECKS

    DELINEATED IN THE SPECIFICATION. CONTRACTOR WILL DOCUMENT IN

    WRITING THE RESULTS OF THE SYSTEM CHECKS RE-VERIFICATION, AND

    SUBMIT TO THE FACILITY. IF ANY PARAMETERS ARE OUT OF RANGE, OR IF

    THE FACILITY DEEMS IT NECESSARY, CONTRACTOR WILL REPROGRAM

    SYSTEM AS NEEDED, OR REQUIRED.

    8. CONTRACTOR SHALL REPLACE ALL POWER WIRING FROM NEAREST HOMERUN JUNCTION BOX TO NEW EQUIPMENT AND DEVICES. CONTRACTOR

    SHALL ALSO REPLACE ALL FIRE ALARM WIRING FROM EXISTING FIRE

    ALARM LOOP TO NEW EQUIPMENT AND DEVICES. CONTRACTOR SHALL

    ALSO REPLACE ALL WIRING BETWEEN ALL COMPONENTS OF THE VESDA

    FIRE ALARM SYSTEM.

    Contract duration for completion of all work shall be 180 calendar days, excluding FAA

    holiday moratorium periods specified in Division 1-5.

    1-1.1.2 Intent of specifications.-

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    10/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    10/168

    (a) This specification identifies all labor and equipment to perform the work required to

    construct the facility. All work performed and all materials and equipment used shall be

    approved by the Contracting Officer (CO). This shall include but not be limited to

    construction testing, inspection, scheduling, reporting, and submittals.

    (b) Titles.- Titles to division and sections of the specifications and notes and titles on drawings

    referring to subcontractors, division of work by trade, or type of work, are introduced

    merely for convenience in reading the specifications and drawings and do not imply any

    separate contractual arrangements of work assignments. Such separations into titled

    divisions and sections shall not operate to make the Government an arbiter to establish

    subcontract limits between the contractor and subcontractors, or between the

    subcontractors themselves.

    1-1.1.3 Contract documents.-

    (a) The construction of this facility shall be in accordance with the lines and grades shown onthe drawings. The contractor shall not use dimensions scaled from drawings. All

    dimensions shown on the drawings shall be verified by the contractor by actual

    measurements in the field. Any discrepancies between the drawings and specifications

    and the existing conditions shall be referred to the CO for adjustment before any work

    affected is performed.

    1-1.1.4 Precedence of contract documents.-

    (a) In the event of a difference between the following contract provisions, the order of

    precedence to determine which provision shall govern is:

    1. Contract Clauses and Provisions

    2. Project Specifications

    3. Project Drawings as listed in Part III - Section J

    (b) Any discrepancies between the contract provisions, the specifications and the contract

    drawings shall be referred to the CO for a written determination in accordance with

    Contract Clause entitled SPECIFICATION AND DRAWINGS FOR CONSTRUCTION.

    Refer to Part II, Section I.

    1-1.1.5 Contracting Officer.- The term "Contracting Officer" (CO) as used herein denotes the

    person designated to act on behalf of the Government in the performance of this contract. Where

    reference is made to "Federal Aviation Administration" (FAA), "Resident Engineer" (RE),

    "Contracting Officer's Representative" (COR), or the like, this shall mean the Contracting

    Officer or his/her authorized representative.

    1-1.1.6 Contractor Superintendence.- In accordance with Contract Clause entitled

    SUPERINTENDENCE BY THE CONTRACTOR, the Contractor shall at all times during

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    11/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    11/168

    performance of this contract and until the work is completed and accepted, directly superintend

    the work or assign and have on site a competent superintendent with the authority to act for the

    Contractor.

    END OF SECTION

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    12/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    12/168

    1-2 SITE ACCESS, CONSTRUCTION LIMITS, USE OF FACILITIES AND WORK HOURS

    1-2.1 General.-

    1-2.1.1 Existing facility operations.- The ARTCC is a 24 hour, 7 day per week operatingfacility. The Contractor shall perform all work in a manner which does not conflict with or

    adversely affect the air traffic operational environment or functions of the ARTCC. In the event

    of any actual or potential conflict, air traffic control activities shall have priority over all

    Contractor activities. The Contractor shall plan for and provide services in such a manner and at

    such times that will not disrupt facility operations, and shall conform to those procedures

    considered essential by the FAA for ensuring air traffic safety.

    1-2.1.2 Construction limits and access.-

    (a) The contractor shall confine operations, activities, storage of materials and employee

    parking within the designated area, as indicated on the drawings. Additional space thecontractor deems necessary shall be obtained off site, at no additional cost to the

    Government.

    (b) Access for the contractor, sub-contractors, employees, deliveries, etc., will be in

    approximate locations as indicated on the construction staging plan. And as directed by the

    COR.

    (c) Access to the construction site shall be kept unobstructed. If temporary access obstruction

    is unavoidable, the contractor shall advise the Resident Engineer (RE) immediately.

    (d) Temporary roadways and/or other access may be authorized only by the facility, via the

    RE.

    (e) Vehicles transporting materials shall not be loaded beyond the capacity prescribed by

    Federal, State or Local law.

    (f) Obstruction of existing roadways, driveways, etc., to the ARTCC is strictly prohibited.

    Access to the loading dock and ramp shall be maintained.

    (g) Damage caused by the contractor's activities to existing paving, lawns, curbs, sidewalks,interior/exterior of the building shall be repaired. All costs of repairs shall be paid by the

    contractor. After notice to proceed and prior to the commencement of construction, the

    contractor and RE shall conduct joint inspections of the existing areas affected by the

    construction. Existing damage/defects shall be noted and will be used as the basis for

    determination of damages caused by the contractor's operations.

    1-2.1.3 Contractor's use of premises.-

    (a) Contractor shall assume full responsibility for the protection and safekeeping of products

    stored on the site.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    13/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    13/168

    (b) The contractor and his subcontractors shall maintain the job site in a neat and orderly

    condition - This includes the daily removal of rubbish, waste and tools, equipment and

    materials not required for the work in progress.

    (c) Concessionaires shall not be allowed on the grounds of the facility.

    (d) Use of the cafeteria is permitted providing the privilege is coordinated with the COR in

    order not to conflict with FAA personnel lunch shifts.

    1-2.1.4 Government use and access to premises.-

    (a) The Government reserves the right to enter the premises during the term of the contract for

    periodic work inspections and for maintenance of existing equipment. The Contractor shall

    allow the CO and RE complete access to all portions of the work.

    (b) See Part II, Section I, Contract Clause entitled OTHER CONTRACTS, for work by othercontractors.

    1-2.1.5 Work hours.- Work shall be performed as follows:

    DYSIM AREA BASEMENT 4:00 P.M. TO 12:00 A.M.

    OPERATIONS AND CONTROL WING BASEMENT 10:00 P.M. TO 5:30 A.M.

    CONTROL ROOM 12:00 A.M. TO 5:30 A.M.

    CONTROL ROOM ATTIC 7:00 A.M. TO 4:00 P.M.

    ADMINISTRATION SPACES 4:00 P.M. TO 12:00 A.M.

    EQUIPMENT ROOMS 10:00 P.M. TO 5:30 A.M.

    CRITICAL TIE-INS - 12:00 A.M. TO 5:30 A.M.

    ALL FIRE ALARM TIE-INS 12:00 A.M. TO 5:30 A.M.

    except for the following:

    a) Shutdowns and cutovers of environmental, utility and electrical systems impacting the

    facility operations shall be accomplished between the hours of 12 a.m. and 5:30 a.m. All

    preparatory work shall be completed prior to shutdown/cutover to minimize downtime.

    Shutdown and cutovers shall be scheduled and coordinated with the RE a minimum of 10

    working days in advance of the shutdown/cutover.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    14/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    14/168

    (b) No work shall be scheduled or take place during the week of and the weekend preceeding

    and following the Thanksgiving, Christmas and New Years Holidays. Only emergency

    work to restore critical services to the facility will be considered and a moratorium waiver

    must be submitted and approved. The moratorium period will not be counted against the

    contract construction duration for the project.

    1-2.1.6 Notification of planned overtime work.- In the event the contractor intends to work

    overtime, nights, weekends or holidays, he shall notify the RE, who will coordinate with the CO

    for approval, at least 24 hours in advance of his commencement of the overtime work and 48

    hours prior to night, weekend or holiday work.

    1-2.1.7 Security requirements.-

    A. Refer to Contract Clauses, attachments and guidelines provided by the Contracting Officerat the Preconstruction Meeting.

    END OF SECTION

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    15/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    15/168

    1-3 CONTRACTOR QUALITY CONTROL, SAFETY, COORDINATION, PERMITS,

    TESTING

    1-3.1 General.- The Contractor is responsible for quality control and shall establish and maintain

    an effective quality control system in compliance with the Contract Clause entitled "Inspectionof Construction." The quality control system shall consist of plans, procedures, and organization

    necessary to produce an end product which complies with the contract requirements. The system

    shall cover all construction operations, both on-site and off-site, and shall be keyed to the

    proposed construction sequence.

    1-3.2 Quality Control Plan.-

    1-3.2.1 General.- The Contractor shall furnish for review by the Government, not later than

    30 days after receipt of notice to proceed, the Contractor Quality Control (CQC) Plan proposed

    to implement the requirements of the Contract Clause entitled "Inspection of Construction." The

    plan shall identify personnel, procedures, control, instructions, test, records, and forms to beused. The Contractor shall provide an interim plan for the first 30 days of operation WITHIN 14

    DAYS AFTER AWARD OF CONTRACT. Construction will be permitted to begin only after

    acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature

    of work to be started. Work outside of the features of work included in an accepted interim plan

    will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing

    the additional features of work to be started.

    1-3.2.2 Content of the CQC Plan.- The CQC plan shall include, as a minimum, the following to

    cover all construction operations, both on-site and off-site, including work by subcontractors,

    fabricators, suppliers and purchasing agents:

    (a) A description of the quality control organization, including a chart showing lines of

    authority and acknowledgment that the CQC staff shall implement the three phase control

    system for all aspects of the work specified. The staff shall include a CQC system manager

    who shall report to the project manager or someone higher in the Contractor's organization.

    Project manager in this context shall mean the individual with responsibility for the overall

    management of the project including quality and production.

    (b) The name, qualifications (in resume format), duties, responsibilities, and authorities of each

    person assigned a QC function.

    (c) A copy of the letter to the CQC System Manager signed by an authorized official of the

    firm which describes the responsibilities and delegates sufficient authorities to adequately

    perform the functions of the CQC System Manager including authority to stop work which

    is not in compliance with the contract. The CQC System Manager shall issue letters of

    direction to all other various quality control representatives outlining duties, authorities and

    responsibilities. Copies of these letters will also be furnished to the Government.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    16/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    16/168

    (d) Procedures for scheduling, reviewing, certifying, and managing submittals, including those

    of subcontractors, off-site fabricators, suppliers and purchasing agents. These procedures

    shall be in accordance with Section 1-7 SUBMITTALS.

    (e) Control, verification and acceptance testing procedures for each specific test to include thetest name, specification paragraph requiring test, feature of work to be tested, test

    frequency, and person or laboratory responsible for each test.

    (f) Procedures for tracking preparatory, initial, and follow-up control phases and control,

    verification, and acceptance tests including documentation.

    (g) Procedures for tracking construction deficiencies from identification through acceptable

    corrective action. These procedures will establish verification that identified deficiencies

    have been corrected.

    (h) Reporting procedures, including proposed reporting formats.

    (i) A list of the definable features of work. A definable feature of work is a task which is

    separate and distinct from other tasks and has separate control requirements. It could be

    identified by different trades or disciplines, or it could be work by the same trade in a

    different environment. Although each section of the specifications may generally be

    considered as a definable feature of work, there are frequently more than one definable

    feature under a particular section. This list will be reviewed for concurrence during the

    coordination meeting.

    1-3.2.3 Acceptance of Plan.- Acceptance of the Contractor's CQC plan is required prior to the

    start of construction. Acceptance is conditional and will be predicated on satisfactory

    performance during the construction. The Government reserves the right to require the

    Contractor to make changes in his CQC plan and operations including removal of personnel, as

    necessary, to obtain the quality specified.

    1-3.2.4 Notification of Changes.- After acceptance of the QC plan, the Contractor shall notify

    the Contracting Officer in writing a minimum of seven calendar days prior to any proposed

    change. Proposed changes are subject to acceptance by the Contracting Officer.

    1-3.3 Coordination Meeting.- After the Preconstruction Conference, before start of construction,

    and prior to acceptance by the Government of the Quality Control Plan, the Contractor shall

    meet with the Contracting Officer or Authorized Representative and discuss the Contractor's

    quality control system. During the meeting, a mutual understanding of the system details shall

    be developed, including the forms for recording the CQC operations, control activities, testing,

    administration of the system for both on-site and off-site work, and the interrelationship of

    Contractor's Management and control with the Government's Quality Assurance. Minutes of the

    meeting will be prepared by the Contractor and signed by both the Contractor and the

    Contracting Officer. The minutes shall become a part of the contract file. There may be

    occasions when subsequent conferences will be called by either party to reconfirm mutual

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    17/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    17/168

    understandings and/or address deficiencies in the CQC system or procedures which may require

    corrective action by the Contractor.

    1-3.4 Quality Control Organization.-

    1-3.4.1 General.- The quality control system manager and surveillance personnel shall be fully

    qualified by experience and background to perform their assigned responsibilities.

    1-3.4.2 System Manager.- The Contractor shall identify an individual, within his organization at

    the site of the work as Contractor Quality Control System Manager, who shall be responsible for

    overall management and have the authority to act in all Contractor's Quality Control (CQC)

    matters for the Contractor; for this project it is allowed to have the project superintendent

    act as the CQC System Manager. The designated System Manager shall have a minimum of 5

    years experience in supervision or inspection of building construction projects of complexity,

    magnitude, and type of work similar to the project orprior approval of the Contracting Officer.

    The System Manager's performance shall be acceptable to the Contracting Officer, andacceptability will be based principally on timeliness, accuracy, and completeness of the CQC's

    assessment of the condition of the elements of contract work. Contract work will not be

    permitted to be performed without an acceptable incumbent CQC System Manager onsite unless

    specifically authorized by the Contracting Officer.

    1-3.5 Quality Control Meetings.- The Contractor's Project Manager shall meet with the

    Contracting Officer or the Contracting Officer's Authorized Representative at regular intervals,

    weekly or monthly as considered necessary by the Contracting Officer, to assess the

    effectiveness of the Quality Control system. Special meetings may be called at any time when

    desired by the Contracting Officer. Reports will be reviewed to determine their effectiveness in

    the overall Quality Control system. Particular emphasis will be placed on discussion of methods

    to eliminate the recurrence of problem areas.

    1-3.6 Submittals.- Procedures for processing shop drawings, samples, certificates, and other

    submittals shall be developed and submitted for approval as part of the Contractor's Quality

    Control Plan. The procedures shall include the establishment of responsibilities to assure at each

    level adequate review and approval; timely delivery, including verification procedures; and

    proper storage.

    1-3.6.1 Certification.- The Contractor is responsible for, and the Quality Control manager shall

    certify that, the submittals comply with contract requirements. Submittals shall be as specified

    in Section 1-7 SUBMITTALS.

    1-3.6.2 Government Approved Submittals.- Submittals requiring Government approval will be

    identified as having received Contractor approval by being so stamped and dated. Delays in the

    approval process shall not be the basis for consideration of a time extension when such delay is

    the result of the Contractor's failure to make proper submittal or make corrections in accordance

    with the specifications or the Contracting Officer's comments or is the result of a resubmittal

    which is required because of an unsatisfactory original submittal. Approval action will not

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    18/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    18/168

    relieve the Contractor of his responsibility for compliance with the contract but will indicate

    only that the general method of construction and detailing is satisfactory.

    1-3.6.3 Deviations.- All proposed deviations from contract requirements shall be submitted in

    writing for approval.

    1-3.7 Control.- Contractor Quality Control is the means by which the Contractor ensures that the

    construction, to include that of subcontractors and suppliers, complies with the requirements of

    the contract. The controls shall be adequate to cover all construction operations, including both

    on-site and off-site fabrication, and will be keyed to the proposed construction sequence. The

    controls shall include at least three phases of control to be conducted by the CQC system

    manager for all definable features of work, as follows:

    1-3.7.1 Preparatory Phase.- This phase shall be performed prior to beginning work on each

    definable feature of work and shall include:

    (a) A review of each paragraph of applicable specifications.

    (b) A review of the contract plans.

    (c) A check to assure that all materials and/or equipment have been tested, submitted, and

    approved.

    (d) A check to assure that provisions have been made to provide required control inspection

    and testing.

    (e) Examination of the work area to assure that all required preliminary work has been

    completed and is in compliance with the contract.

    (f) A physical examination of required materials, equipment, and sample work to assure that

    they are on hand, conform to approved shop drawing or submitted data, and are properly

    stored.

    (g) Complete the FAA Pre-Construction and Maintenance Project Safety and Health

    Checklist (N3900.57) to assure safety and risk analysis requirements are met. Work

    with the Resident Engineer to identify potential life safety and work related risks to

    the air traffic control system for inclusion in the Project Risk Mangement Plan. The

    Risk Management Plan is maintained by the FAA and shall be reviewed before

    starting any phase of work as applicable.

    (h) Discussion of procedures for constructing the work including repetitive deficiencies.

    Document construction tolerances and workmanship standards for that phase of work.

    (i) A check to ensure that the portion of the plan for the work to be performed has been

    accepted by the Contracting Officer.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    19/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    19/168

    (j) The Government shall be notified at least 48 hours in advance of beginning any of the

    required action of the preparatory phase. This phase shall include a meeting conducted by

    the CQC system manager and attended by the superintendent, other CQC personnel (as

    applicable), and the foreman responsible for the definable feature. The results of the

    preparatory phase actions shall be documented by separate minutes prepared by the CQCsystem manager and attached to the daily QC report. The Contractor shall instruct

    applicable workers as to the acceptable level of workmanship required in order to meet

    contract specifications.

    1-3.7.2 Initial Phase.- This phase shall be accomplished at the beginning of a definable feature

    of work. The following shall be accomplished:

    (a) A check of preliminary work to ensure that it is in compliance with contract requirements.

    Review minutes of the preparatory meeting.

    (b) Verification of full contract compliance. Verify required control inspection and testing.

    (c) Establish level of workmanship and verify that it meets minimum acceptable workmanship

    standards. Compare with sample panels is appropriate.

    (d) Resolve all differences.

    (e) Check safety to include compliance with and upgrading of the safety plan and activity

    hazard analysis. Review the activity analysis with each worker.

    (f) The Government shall be notified at least 48 hours in advance of beginning the initial

    phase. Separate minutes of this phase shall be prepared by the CQC system manager and

    attached to the daily QC report. Exact location of initial phase shall be indicated for future

    reference and comparison with follow-up phases.

    (g) The initial phase should be repeated for each new crew to work on-site, or any time

    acceptable specified quality standards are not being met.

    1-3.7.3 Follow-up Phase.- Daily checks shall be performed to assure continuing compliance

    with contract requirements, including control testing, until completion of the particular feature of

    work. The checks shall be made a matter of record in the CQC documentation. Final follow-up

    checks shall be conducted and all deficiencies corrected prior to the start of additional features of

    work which may be affected by the deficient work. The Contractor shall not build upon or

    conceal non-conforming work.

    1-3.7.4 Additional Preparatory and Initial Phases.- Additional preparatory and initial phases

    may be conducted on the same definable features of work as determined by the Government if

    the quality of on-going work is unacceptable; or if there are changes in the applicable QC staff or

    in the on-site production supervision or work crew; or if work on a definable feature is resumed

    after a substantial period of inactivity, or if other problems develop.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    20/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    20/168

    1-3.8 Contractor Request For Information (RFI).- In accordance with Contract Clause

    "SPECIFICATIONS AND DRAWINGS", in case of discrepancy either in the figures, in the

    drawings, or in the specifications, the matter shall be promptly submitted to the RE, who shall

    promptly respond in writing. Submit a written request to RE and allow at least 3 working days

    for Government response. Include the date of the request, the date response is needed, adescription of the problem, identification of work on hold, impact of delay in Government

    response, scope changes deemed necessary and recommended solutions, and any other

    information pertinent. The Government reserves the right to charge the contractor for

    administrative costs associated with responding to an RFI, which does not involve discrepancies

    in the specifications and drawings.

    1-3.9 Tests.-

    1-3.9.1 Testing Procedure.- The Contractor shall perform tests specified or required to verify

    that control measures are adequate to provide a product which conforms to contract

    requirements. Testing includes operation and/or acceptance tests when specified. TheContractor shall procure the services of an approved testing laboratory or establish an approved

    testing laboratory at the project site. A list of tests to be performed shall be furnished as a part of

    the CQC plan. The list shall give the test name, frequency, specification paragraph containing

    the test requirements, the personnel and laboratory responsible for each type of test, and an

    estimate of the number of tests required. The Contractor shall perform the following activities

    and record and provide the following data:

    (a) Verify that testing procedures comply with contract requirements.

    (b) Verify that facilities and testing equipment are available and comply with testing standards.

    (c) Check test instrument calibration data against certified standards.

    (d) Verify that recording forms and test identification control number system, including all of

    the test documentation requirements, have been prepared.

    (e) Results of all tests taken, both passing and failing tests, will be recorded on the Quality

    Control report for the date taken. Specification paragraph reference, location where tests

    were taken, and the sequential control number identifying the test will be given. Actual

    test reports may be submitted later, if approved by the Contracting Officer, with a reference

    to the test number and date taken. An information copy of tests performed by an off-site or

    commercial test facility will be provided directly to the Contracting Officer. Failure to

    submit timely test reports, as stated, may result in nonpayment for related work performed

    and disapproval of the test facility for this contract.

    1-3.10 Completion Inspection.- At the completion of all work or any increment thereof

    established by a completion time stated in the Special Clause entitled "Commencement,

    Prosecution, and Completion of Work," or stated elsewhere in the specifications, the CQC

    system manager shall conduct an inspection of the work and develop a "punch list" of items

    which do not conform to the approved plans and specifications. Such a list of deficiencies shall

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    21/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    21/168

    be included in the CQC documentation, as required by paragraph DOCUMENTATION below,

    and shall include the estimated date by which the deficiencies will be corrected. The CQC

    system manager or staff shall make a second inspection to ascertain that all deficiencies have

    been corrected and so notify the Government. These inspections and any deficiency corrections

    required by this paragraph will be accomplished within the time stated for completion of theentire work or any particular increment thereof if the project is divided into increments by

    separate completion dates.

    1-3.11 Documentation.- The Contractor shall maintain current records of quality control

    operations, activities, and tests performed, including the work of subcontractors and suppliers.

    These records shall be on an acceptable form and shall include factual evidence that required

    quality control activities and/or tests have been performed, including but not limited to the

    following:

    (a) Contractor/subcontractor and their area of responsibility.

    (b) Operating plant/equipment with hours worked, idle, or down for repair.

    (c) Work performed today, giving location, description, and by whom. When Network

    Analysis (NAS) is used, identify each phase of work performed each day by NAS activity

    number.

    (d) Test and/or control activities performed with results and references to specifications/plan

    requirements. The control phase should be identified (Preparatory, Initial, Follow-up).

    List deficiencies noted along with corrective action.

    (e) Material received with statement as to its acceptability and storage.

    (f) Identify submittals reviewed, with contract reference, by whom, and action taken.

    (g) Off-site surveillance activities, including actions taken.

    (h) Job safety evaluations stating what was checked, results, and instructions or corrective

    actions.

    (i) List instructions given/received and conflicts in plans and/or specifications.

    (j) Contractor's verification statement.

    (k) These records shall indicate a description of trades working on the project; the number of

    personnel working; weather conditions encountered; and any delays encountered. These

    records shall cover both conforming and deficient features and shall include a statement

    that equipment and materials incorporated in the work and workmanship comply with the

    contract. The original and one copy of these records in report form shall be furnished to

    the Government daily within 24 hours after the date(s) covered by the report, except that

    reports need not be submitted for days on which no work is performed. As a minimum,

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    22/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    22/168

    one report shall be prepared and submitted for every seven days of no work and on the last

    day of a no work period. All calendar days shall be accounted for throughout the life of the

    contract. The first report following a day of no work shall be for that day only. Reports

    shall be signed and dated by the CQC system manager. The report from the CQC system

    manager shall include copies of test reports and copies of reports prepared by allsubordinate quality control personnel.

    1-3.12 Sample Forms.- Sample Contractor Quality Control Report forms are enclosed at the end

    of this section.

    1-3.13 Notification of Noncompliance.- The Contracting Officer will notify the Contractor of

    any detected noncompliance with the foregoing requirements. The Contractor shall, after receipt

    of such notice, immediately take corrective action. Such notice, when delivered to the

    Contractor at the site of the work, shall be deemed sufficient for the purpose of notification. If

    the Contractor fails or refuses to comply promptly, the Contracting Officer may issue an order

    stopping all or part of the work until satisfactory corrective action has been taken. No part of thetime lost due to such stop orders shall be made the subject of claim for extension of time or for

    excess costs or damages by the Contractor.

    1-3.14 Coordination, Local Permits and Testing.-

    1-3.14.1 Project Coordination.-

    (a) It shall be the duty of the Contractor to prepare a detailed schedule of work and work

    layout to resolve conflicts and to assure coordination of the work by different trades.

    (b) It shall be the duty of the Contractor to resolve all coordination conflicts that arise among

    his subcontractors. If, in the opinion of the RE, a potential or actual conflict exists, the RE

    will notify the CO, who shall instruct the contractor to take immediate steps to coordinate

    the work and resolve any conflicts.

    1-3.14.2 Local Permits.& National Electrical Code-

    (a) The Contractor shall make application, pay fees, etc., to obtain local building permits and

    inspection as required.

    (b) This project is designed in accordance with the International Building Code, the Uniform

    Plumbing Code, and the National Electric Code. The Contractor shall perform all work in

    compliance with the latest edition of these codes.

    (c) The requirements of the specification and drawings applicable to this contract areintended to be in conformity with the National Electrical Code, National Safety Code,State and Local electrical codes and all pertinent FAA orders. The contractor shall reviewthese documents prior to starting work. If they are found to be in conflict, the moststringent requirement shall be provided by the contractor. In determining whether anadjustment in contract price or time may be involved, it shall be understood that the

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    23/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    23/168

    Contractors bid price has been based on performing the work in conformity with themost stringent requirement.

    1-3.14.3 Testing.- The Contractor shall arrange and pay for the services of Independent TestingLaboratories/Engineers to perform specified services and testing as required. (sample of typical

    Contractor's daily report)

    1-3.15 Safety Requirements.-1-3.15.1Contractor Safety Plan.- The Contractor shall develop and submit a required Safety Planand other safety documents showing how the work shall be accomplished in accordance with

    OSHA 29 CFR 1910 and OSHA 29 CFR 1926. The Safety Plan, and other safety documents,

    shall be submitted to the Site Representative for review and approval. The Safety Plan shall be

    submitted with in 10 days of the Notice-to-proceed. No construction will be authorized until the

    Safety Plan has been approved.

    END OF SECTION

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    24/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    24/168

    DAILY CONSTRUCTION QUALITY CONTROL REPORT

    Contract Number: ______________________ Date: __________ Rpt No.____________

    Contract Title: ______________________________ Location: ____________________

    Weather: Clear __ P.Cloudy __ Cloudy __ Rainfall __ (__% of workday)

    Temperature during workday: High ____ degrees F. Low ___ degrees F.

    1. WORK PERFORMED BY CONTRACTOR/SUBCONTRACTOR(S):

    Contractor Name No. of Workers Crafts/Hours Work performed

    ______________________________________________________________________________

    ______________________________________________________________________________

    ______________________________________________________________________________

    ______________________________________________________________________________

    ______________________________________________________________________________

    2. EQUIPMENT DATA:

    Type, Size, Etc. Owned/Rented Hours Used Hours Standby

    ______________________________________________________________________________

    ______________________________________________________________________________

    ______________________________________________________________________________

    3. QUALITY CONTROL INSPECTIONS AND RESULTS: (Include a description of

    preparatory, initial, and/or follow up inspections or meetings; check of subcontractors work and

    materials delivered to the site compared to submittals and/or specifications; comments on the

    proper storage of materials; include comments on corrective actions to be taken):

    ______________________________________________________________________________

    ______________________________________________________________________________

    ______________________________________________________________________________

    ______________________________________________________________________________

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    25/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    25/168

    4. QUALITY CONTROL TESTING AND RESULTS (comment on tests and attach test

    reports):

    ______________________________________________________________________________

    ______________________________________________________________________________

    ______________________________________________________________________________

    5. DAILY SAFETY INSPECTIONS (Include comments on new hazards to be added to the

    Hazard Analysis and corrective action of any safety issues):

    ______________________________________________________________________________

    ______________________________________________________________________________

    ______________________________________________________________________________

    6. REMARKS (Include conversations with or instructions from the Government representatives;

    delays of any kind that are impacting the job; conflicts in the contract documents; comments on

    change orders; environmental considerations; etc.):

    ______________________________________________________________________________

    ______________________________________________________________________________

    ______________________________________________________________________________

    ______________________________________________________________________________

    ______________________________________________________________________________

    ______________________________________________________________________________

    ______________________________________________________________________________

    CONTRACTOR'S VERIFICATION: The above report is complete and correct. All material,

    equipment used, and work performed during this reporting period are in compliance with the

    contract documents except as noted above.

    ___________________________________

    CONTRACTOR QC REPRESENTATIVE

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    26/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    26/168

    TEST REPORT

    STRUCTURE OR BUILDING CONTRACT NO.

    DESCRIPTION OF ITEM, SYSTEM, OR PART OF SYSTEM TESTED:

    __________________

    ______________________________________________________________________________

    ______________________________________________________________________________

    DESCRIPTION OF TEST:

    _________________________________________________________

    ______________________________________________________________________________

    ______________________________________________________________________________

    ______________________________________________________________________________

    NAME AND TITLE OF PERSON IN CHARGE OF PERFORMING TESTS FOR

    CONTRACTOR:

    NAME TITLE

    SIGNATURE

    I HEREBY CERTIFY THAT THE ABOVE DESCRIBED ITEM, SYSTEM, OR PART OF

    SYSTEM HAS BEEN TESTED AS INDICATED ABOVE AND FOUND TO BE ENTIRELY

    SATISFACTORY AS REQUIRED IN THE CONTRACT SPECIFICATIONS.

    SIGNATURE OF CONTRACTOR QUALITY CONTROL INSPECTOR _

    DATE

    REMARKS:

    _____________________________________________________________________

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    27/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    27/168

    DAILY CONSTRUCTION QUALITY CONTROL REPORT

    Date: Report No. _Contract No.: ____________________________

    Description and Location of Work:

    ___________________________________________________

    WEATHER: (Clear) (P. Cloudy); Temperature: _____________ Min. ___________ Max;

    (Snow) (Rainfall) _____________ Inches

    Contractor/Subcontractor Activity:

    Contractor/ TimeWork in Progress Subcontractor Craft Worked

    a.____________________________________________________________________________

    b.____________________________________________________________________________

    c.____________________________________________________________________________

    d.____________________________________________________________________________

    e.____________________________________________________________________________

    f.____________________________________________________________________________

    Equipment Data: (Indicate items of construction equipment, other than hand tools, at the job site

    and whether or not used.)

    Contractor/ Time

    Equipment Subcontractor Craft Used _

    a.___________________________________________________________________________

    b.____________________________________________________________________________

    c.____________________________________________________________________________

    d.____________________________________________________________________________

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    28/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    28/168

    Three Phase Inspection Program:

    1. Preparatory Inspection: Include status of transmittals, Quality Control meetings, tests

    required, materials delivered, materials compliance with sub- mittals and standards, material

    storage, conflict in drawings or specifications, environmental conflicts, instructions from

    Government.

    Job Safety: (Analyze hazards. Plan safety program. Schedule safety meetings.)

    2. Initial Inspection: Include new feature of work started, number of per- sonnel in trades and

    hours worked, result of inspection, compliance of work with plans and specifications, results of

    tests, instructions from Government.

    Job Safety: (Insure compliance with Safety Program and Analysis. Observe safety

    meetings and reporting.)

    3. Followup Inspections: Include work inspected, result of inspection, compliance with plans

    and specifications, results of tests, delays to work, defects, and rejection of work, proposed

    remedial action, corrective action taken, instructions from Government.

    Job Safety: (Note any deficiencies and corrections.)

    CONTRACTOR'S VERIFICATION: The above report is complete and correct and all material

    and equipment used and work performed during this reporting period are in compliance with the

    contract plans and specifications except as noted above.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    29/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    29/168

    ______________________________________________CONTRACTOR QUALITY CONTROL INSPECTOR

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    30/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    30/168

    1-4 CUTTING AND PATCHING

    1-4.1 General.-

    1-4.1.1 Requirements included.- Contractor shall be responsible for all cutting, fitting andpatching, required to complete the work or to:

    (a) Make the parts fit together properly.

    (b) Remove and replace defective work.

    (c) Remove and replace work not conforming to requirements

    (d) Remove samples of installed work as specified for testing.

    (e) Provide penetrations of surfaces for installation of piping, air ductwork, and electrical

    conduit.

    1-4.1.2 Submittals.-

    (a) Submit a written Request for Information (RFI) to the RE a minimum of 5 days in advance

    of executing any cutting or alteration which may affect:

    1. Work of the Government or any separate contractor.

    2. Structural integrity of any element of the Project.

    3. Integrity of weather-exposed or moisture- resistant elements or systems.

    4. Efficiency, operational life, maintenance or safety of operational elements.

    5. Visual qualities of sight-exposed elements.

    (b) Request shall include:

    1. Identification of the Project.

    2. Description of affected work.

    3. The necessity for cutting, alteration, or excavation.

    4. Effect on work of Government or other work, or on structural or weatherproof integrity

    of the affected element.

    5. Description of proposed work:

    a) Scope of cutting, patching, alteration, or excavation.

    b) Trades who will execute the work.

    c) Products proposed to be used.

    d) Extent of refinishing to be done.

    6. Alternatives to cutting and patching.

    7. Cost proposal, when applicable

    8. Written concurrence of any separate contractor whose work will be affected.

    (c) Should conditions of work or the schedule indicate a change of products from original

    installation, contractor shall submit request for substitution as specified in Section 1-9,

    "Materials and Equipment."

    (d) Submit written notice to the RE designating the date and time the work will be uncovered.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    31/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    31/168

    1-4.2 Products.-

    1-4.2.1 Materials.- Comply with specifications and standards for each specific product

    involved.

    1-4.3 Execution.-

    1-4.3.1 Inspection.-

    (a) Inspect existing conditions of project, including elements subject to damage or to

    movement during cutting and patching.

    (b) After uncovering work, inspect conditions affecting installation of products, or

    performance of work.

    (c) Report unsatisfactory or questionable conditions to the RE in writing; do not proceed with

    work until the RE has provided further instructions.

    1-4.3.2 Preparation.-

    (a) Provide adequate temporary support as necessary to assure structural value or integrity of

    affected portion of work.

    (b) Provide devices and methods to protect other portions of project from damage.

    (c) Provide protection from elements for that portion of the project which may be exposed by

    cutting and patching work.

    1-4.3.3 Performance.-

    (a) Execute cutting and demolition by methods which will prevent damage to other work, and

    will provide proper surfaces to receive installation of repairs.

    (b) Execute fitting and adjustment of products to provide a finished installation to comply

    with specified products, functions, tolerance and finishes.

    (c) Restore work which has been cut or removed; install new products to provide complete

    work in accordance with requirements of Contract Documents.

    (d) Fit work airtight to pipes, sleeves, ducts, conduit and other penetrations through surfaces.

    (e) Refinish entire surfaces as necessary to provide an even finish to match adjacent finishes:

    1. For continuous surfaces, refinish entire unit to the nearest natural break line.

    2. For an assembly, refinish entire unit.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    32/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    32/168

    END OF SECTION

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    33/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    33/168

    1-5 SCHEDULE CONSTRAINTS

    1-5.1. Critical Time Constraints.- Contract duration for completion of all work shall be 180

    calendar days from notice to proceed, excluding the FAA holiday moratorium days.

    FAA Holiday Moratorium: No work shall be scheduled or take place during the week of

    and the weekend preceeding and following the Thanksgiving, Christmas and New Years

    Holidays as well as other days as indicated in Part I Section H Special Contract

    Requirements. Only emergency work to restore critical services to the facility will be

    considered and a moratorium waiver must be submitted and approved. The moratorium

    period will not be counted against the contract construction duration for the project.

    1-5.3 Critical Activities.- The constraints identified in this specification section shall be

    included as activities on the Contractor prepared construction schedule.

    END OF SECTION

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    34/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    34/168

    1-6 CONTRACTOR PREPARED CONSTRUCTION SCHEDULE

    1-6.1 Construction Schedule.- The progress chart to be prepared by the Contractor pursuant to

    the Contract Clause entitled "SCHEDULE FOR CONSTRUCTION CONTRACTS" shall consist

    of a Gantt or bar chart as described below. The scheduling of construction is the responsibilityof the Contractor and contractor management personnel shall actively participate in development

    of the schedule so that intended sequences and procedures are clearly understood

    1-6.2 Activity number and duration.- Provide a chart with a minimum of 50 activities indicating

    all major activities and associated durations, including major submittals, material delivery

    durations and installation, unless otherwise approved by the Contracting Officer (CO). The

    number of activities shall be subject to CO approval. In calculating activity duration, normal

    inclement weather, holidays and other non-working days shall be considered. Activities which

    are planned to be performed by use of overtime or multi-shifts to be worked including Saturdays,

    Sundays, and holidays, shall be identified and must be coordinated in accordance with the

    requirements in specification section 1-2, Site Access, Construction Limits, Use of Facilities andWork Hours.

    1-6.3 Two-week "Look Ahead" schedule.- A weekly construction coordination meeting shall be

    held between the Contractor and the Resident Engineer. Schedules shall be submitted weekly,

    just prior to the weekly construction site meetings. Only activities scheduled to be occurring

    during the forecasted two week time periods are to be shown. The two week time periods are

    determined by starting day being the day of the weekly construction site meeting. Early and

    Late Start and Finish dates, and subcontractors involved are data to be included in the schedule.

    END OF SECTION

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    35/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    35/168

    1-7 FIRE LIFE SAFETY REQUIREMENTS

    PROCEDURE FOR FIRE/LIFE SAFETY OUTAGES & INTERIM SAFETY

    MEASURES FOR FULL OR PARTIAL FIRE/LIFE SAFETY SYSTEM ANDFEATURE OUTAGES

    Implementation of interim measures is required for a nonfunctional or partially

    operating fire/life safety (F/LS) systems in FAA owned, operated or occupied

    facilities.

    The following Procedure for Fire/Life Safety Outages, includes steps mandated by

    the Federal Aviation Administration and nationally recognized F/LS codes and

    standards. This procedure and the appropriate interim measures should be

    implemented as soon as fire/life safety systems are out of service. Where thefire/life safety system outage is planned due to construction and maintenance,

    execution of the procedures identified should be planned and initiated prior to the

    outage.

    INCLUDED F/LS FEATURES AND SYSTEMS

    F/LS features and systems are those facility components provided to protect the

    building occupants, facility, NAS operational continuity, and ultimately the mission

    of the FAA from the hazards of fire and explosion. A partial listing of F/LS systemsand features, addressed by this procedure are provided below:

    Fire Alarm & Detection

    Fire Sprinklers

    Fire Standpipes & Valves

    Fire Suppression Releasing

    Fire Pumps & Controllers

    Fire Extinguishers

    Elevator Recall

    Air Handling Unit Shutdown

    Emergency Security InterfacesSmoke Management

    Fire & Smoke Barriers

    Fire & Smoke Opening Protection

    Fire & Smoke Dampers

    Fire & Smoke Doors

    Firestopping & Joint Protection

    Protected & Unobstructed Egress

    Emergency Lighting

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    36/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    36/168

    Egress Marking

    Emergency Power Supplies

    STAKEHOLDERS IN F/LS OUTAGES

    All impacted stakeholders should be notified of outages and be included in the

    implementation of planned F/LS system and feature outages. Potential stakeholders

    may include facility management and occupants, safety management team, fire

    department, resident engineer, contractors, and the central fire alarm monitoring

    station.

    Initial communications for unplanned outages should be accomplished as soon as

    possible and include documentation by memorandum, email, letter or signage

    postings within the facility, in accordance with FAA policy.

    INTERIM MEASURES (PARTIAL LIST)

    1. Inform all facility occupants of the outage or partially functional F/LS feature anddiscuss its effect on daily and emergency operations. The facility Emergency Action

    Plan should be reviewed to identify necessary modifications. The information

    should highlight the purpose and importance of the F/LS feature, the impact on

    everyday operations, and the increased responsibility of all personnel.

    2. Evaluate the level of risk posed by the non-functioning or partially functioningfeature and the hazards present in the facility. Identify any areas that may have a

    specific risk and may require a fire watch in order to provide appropriate protection

    to the occupants. Appoint a fire warden to oversee implementation and evaluate

    the effectiveness of the interim procedures. The local safety manager should be

    consulted for long term, broad reaching or high impact outages. Additionally, FAA

    safety professionals should be consulted when the proper interim measures are

    unclear.

    3. Conduct daily inspections to ensure the means of egress is not obstructed orcompromised. Confirm the egress is free of combustibles or storage of any kind.

    4. Ensure all doors opening into the stairs are checked to ensure door hardware isfunctioning properly. This includes a visual inspection of all doors to ensure the

    construction has not been compromised and checking all door hardware including

    latching hardware and self-closing devices to verify proper operation. Magnetic

    door holders should be disconnected and not be returned to use until the fire alarm

    system is functioning normally.

    5. Ensure that fire and smoke doors in the facility are not propped open for any reason.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    37/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    37/168

    6. Institute the necessary risk reduction actions, which may include the following:a. Enhancing occupant evacuation procedures by requiring

    immediate evacuation upon alarmb. Updating building occupants on the proper use of fire extinguishersc. Providing additional fire extinguishersd. Strictly enforcing all working contractors site safety planse. Implementing a requirement for daily construction activity

    briefings by the resident engineer

    f. Strictly enforcing "hot work", (e.g., welding, cutting,etc.) safety approvals or banning all hot work during

    F/LS outages

    g. Maintaining the storage of construction combustibles orflammable and combustible liquids outside of the facility

    h. Strictly enforcing the daily clean up of constructionmaterials and excess dust

    7. Conduct biweekly testing and inspections of:a. Exit signageb. Exits for improper storage or obstructionsc. Exit stairs including treads, landings, and handrailsd. Exit illuminatione. Emergency lightingf. Housekeeping and fire prevention measures are in effect

    8. Post signage throughout the facility to indicate interim measures are in effect.9. Confirm, through testing and inspection, the proper operation of all F/LS features,

    systems and components remaining operational during the outage.

    10. In cases where the fire detection & alarm system is compromised, implementprocedures for notifying facility occupants in the event of an emergency (e.g., radio,

    public address, etc.) and ensure personnel are aware of the procedures in effect and

    clear of their responsibilities.

    11. In cases where the F/LS systems interface with building controls is compromised,provide a temporary manual switch in the control areas (cab or control room), which

    activate the stair pressurization system, elevator recall or other special facility

    features. If the facility (specifically an ATCT) has a vented vestibule system, ensure

    louvers are in the open position while the fire alarm system is not functioning.

    12. Ensure trouble signals at the main fire alarm control panel and the control areaannunciator panels remain functional. Trouble signals at either panel should not be

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    38/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    38/168

    by-passed. All trouble signals should be cleared only upon the systems return to

    normal operations.

    13. Inform all personnel upon restoring the F/LS feature to full operation and reinstatethe normal occupant emergency procedures.

    For additional information, contact the local safety officer, Regional Occupational Safety

    and Health Manager, or the facility manager.

    END OF SECTION

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    39/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    39/168

    1-8 TEMPORARY FACILITIES

    1-8.1 General.-

    1-8.1.1 Requirement Included.-

    (a) Furnish, install and maintain temporary facilities required for construction; remove on

    completion of the work.

    (b) Facilities include, sanitary, water, electricity, lighting, heating, ventilation, telephone,

    construction aids, barriers, project sign, parking and site access.

    1-8.1.2 Related Requirements.-

    (a) Section 1-2: Site Access, Construction limits, Use of Facilities and Work

    Hours.

    (b) Section 1-10: Protection of Work

    1-8.2 Products.-

    1-8.2.1 Temporary Sanitary Facilities.-

    (a) The contractor shall provide and maintain adequate temporary toilet accommodations for

    those persons employed on the project site outside the construction area. The

    accommodations shall be sanitary, chemical-type toilet facilities.

    (b) Permanent sanitary facilities within the construction area may be used by construction

    personnel.

    1-8.2.2 Temporary Water.-

    (a) The contractor shall provide temporary service and hose bibbs for drinking and

    construction use.

    (b) The existing building water system may be used for construction purposes at no cost to the

    contractor. Obtain location connections from the Resident Engineer. Extend system as

    necessary to comply with temporary water requirements.

    1-8.2.3 Temporary Electrical Power.-

    (a) Reasonable amounts of electrical power will be furnished at no cost. Contractor will have

    to supply breakers perform all work required to access power. Connections to the existing

    facility electrical system at any other point is prohibited.

    (b) The contractor shall provide a fused disconnect switch at the point of connection.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    40/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    40/168

    (c) The contractor shall provide all supply lines for lights and power, extension outlets, and

    extension cords, trailers, receptacles, bulbs, fuses and other equipment required for safety

    and for proper execution of the work, and for inspection purposes. ALL ELECTRICAL

    WORK THAT CONNECTS TO THE FACILITY ELECTRICAL SYSTEM SHALL BECOORDINATED THROUGH THE RESIDENT ENGINEER. The only personnel

    authorized to access energized electrical panels are the FAA Environmental Support Unit

    personnel. Failure to adhere to these requirements may result in removal from the jobsite.

    1-8.2.4 Temporary Lighting.- Provide temporary artificial lighting in enclosed areas and for all

    areas when natural light does not meet minimum requirements for:

    (a) Construction Areas: Uniform illumination of 20 foot-candles.

    (b) Security.

    (c) Temporary offices, storage, shop and other construction buildings.

    1-8.2.5 Not Used

    1-8.2.6 Temporary Ventilation.- Furnish, install and maintain temporary ventilating as required

    to prevent hazardous accumulations of dusts, fumes, mists, vapors, or gases in areas occupied

    during construction.

    (a) Provide local exhaust ventilation to prevent harmful dispersal of hazardous substances into

    atmosphere of occupied areas.

    (b) Provide local exhaust ventilation with capacity to produce negative pressure and enclose

    the immediate work area with dust partitions to protect adjacent equipment.

    (c) Dispose of exhaust materials in a manner which will not result in harmful exposure to

    persons.

    1-8.2.7 Temporary Telephone.-

    (a) The Contractor shall furnish, install and maintain temporary telephone service for

    construction needs throughout construction period.

    (b) The Contractor shall arrange with local telephone service company, provide direct line

    service for use of personnel and employees:

    1. One direct line instrument in contractor's field office.

    2. Other instruments at contractor's option, or as required by regulations.

    (c) The Contractor shall pay cost for installation, maintenance and removal of temporary

    services, and restoration of existing or permanent facilities used.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    41/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    41/168

    (d) The Contractor shall pay service company charges for local telephone service, and for toll

    charges. Cell phones may be used with in the construction area.

    1-8.2.8 Construction Aids.-

    (a) Furnish, install and maintain required construction aids. Remove on completion of work.

    (b) Provide construction aids and equipment required by personnel and to facilitate execution

    of the work; trench boxes, scaffolds, staging, ladders, stairs, ramps, runways, platforms,

    railings, hoists, cranes, chutes and other such facilities and equipment.

    1-8.2.9 Barriers.-

    (a) Furnish, install and maintain suitable barriers as required to prevent public entry, and to

    protect the work, existing facilities, trees and plants from construction operations; removewhen no longer needed, or at completion of work.

    (b) Materials of contractor's option, as appropriate to serve required purpose.

    (c) Where any removal, drilling or cutting of walls or other surfaces in areas of existing

    facilities operations occurs, the contractor shall install temporary partitions prior to

    demolition to prevent entrance of dust or other matter into the working areas. Where

    normal activities are to be carried on inside the building adjacent to the partition, the

    partition shall be thermally insulated and acoustically treated to prevent entry of

    temperature extremes and construction noise.

    1-8.2.10 Not Used

    1-8.2.11 Not Used

    1-8.2.12 Temporary Parking and Access.-

    (a) Provide and maintain, all weather, vehicular access to site and within site to provide

    uninterrupted access:

    1. To temporary construction facilities, storage and work areas.

    2. For use by persons and equipment involved in construction project.

    3. For use by emergency vehicles.

    (b) Provide and maintain, all weather temporary parking facilities for use by construction

    personnel.

    (c) Locate roads, drives, walks and parking facilities to provide uninterrupted access to

    construction offices, mobilization, work, storage areas, and other areas required for

    execution of the contract.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    42/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    42/168

    1. Contractor and the contractor's personnel shall utilize the parking areas

    designated on the drawing.

    (d) Provide access for emergency vehicles.

    1. Maintain driveways a minimum of 15 feet wide between and around combustible

    materials in storage and mobilization areas.

    (e) Maintain traffic areas free as possible of excavated materials, construction equipment,

    products, snow, ice and debris.

    (f) Keep fire hydrants and water control valves free from obstruction and accessible for use.

    (g) Maintain roads, walks and parking areas in sound, clean condition.

    1. Repair or replace any portions damaged during progress of construction work.

    (h) Completely remove temporary materials and construction when construction needs can be

    met by use of permanent installation.

    1. Remove and dispose of compacted materials to depths required by various

    conditions to be met in completed work.

    (i) Restore areas to original or to specified conditions at completion of work.

    1-8.3 Execution.-

    1-8.3.1 Utility Costs.-

    (a) Consumption costs of the temporary power service and temporary water service furnished

    to the contractor will be paid by the Government. Extension from the point of connection,

    including equipment, operation and attendance shall be paid for by the contractor.

    1-8.3.2 Maintenance.-

    (a) All costs in connection with the maintenance of all temporary facilities shall be paid by the

    contractor.

    1-8.3.3 Compliance.- All work covered in this section shall comply with provisions of other

    applicable divisions and all applicable local requirements

    1-8.3.4 Operation of Permanent Equipment.- Use of permanent equipment by the contractor is

    strictly prohibited without written approval of the FAA prior to use.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    43/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    43/168

    1-8.3.5 Removal of Temporary Facilities.- The contractor shall promptly remove all temporary

    facilities from premises at end of work. If the contractor fails to do so within a reasonable time

    after notification, the FAA will have the items removed at the contractor's expense.

    END OF SECTION

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    44/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    44/168

    1-9 MATERIALS AND EQUIPMENT

    1-9.1 General.-

    1-9.1.1 Requirements Included.-

    (a) Material and equipment incorporated into the work:

    1. Conform to applicable specifications and standards.

    2. Comply with size, make, type and quality specified, or as specifically approved in

    writing by the CO.

    3. Manufactured and Fabricated Products:

    a) Design, fabricate and assemble in accordance with the best engineering and shop

    practices.

    b) Manufacture like parts of duplicate units to standard sizes and gages, to be

    interchangeable.c) Two or more items of the same kind shall be identical, by the same manufacturer.

    d) Products shall be suitable for service conditions.

    e) Equipment capacities, sizes and dimensions shown or specified hall be adhered to

    unless variations are specifically approved in writing.

    4. Do not use material or equipment for any purpose other than for which it is

    designed or is specified.

    (b) Furnish and install products specified, under options and conditions for substitution stated

    in this section.

    1-9.1.2 Related Requirements.-

    (a) Part I, Section E, F, G.

    (b) Section 1-7: Submittals

    1-9.1.3 Manufacturer's Instructions.-

    (a) When Contract Documents requires that installation of work shall comply with

    manufacturer's printed instructions, obtain and distribute copies of such instructions to

    parties involved in the installation, including two copies to the RE.

    1. Maintain one set of complete instructions at the job site during installation and until

    completion.

    (b) Handle, install, connect, clean, condition and adjust products in strict accordance with such

    instructions and in conformity with specified requirements.

    1. Should job conditions or specified requirements conflict with manufacturer's

    instructions, consult with the RE for further instructions.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    45/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    45/168

    2. Do not proceed with work without clear instructions.

    (c) Perform work in accordance with manufacturer's instructions. Do not omit any preparatory

    step or installation procedure unless specifically modified or exempted by Contract

    Documents.

    1-9.1.4 Transportation and Handling.-

    (a) Arrange deliveries of products in accordance with construction schedules, coordinate to

    avoid conflict with work and conditions at the site. All deliveries shall be coordinated in

    advance with the Resident Engineer and the Security personnel at the main entrance.

    The contractor shall have a point of contact identified and available to receive the

    shipment. Failure to adhere to these requirements may result in the shipment being

    turned away at the Main Entrance by the Security personnel. Any additional costs or

    time as a result of failure to adhere to these requirements shall be the responsibility of

    the Contractor.

    1. Deliver products in undamaged condition, in manufacturers original containers or

    packing, with identifying labels intact and legible.

    2. Immediately on delivery, inspect shipments to assure compliance with requirements

    of Contract Documents and approved submittals, and that products are properly

    protected and undamaged.

    (b) Provide equipment and personnel to handle products by methods to prevent soiling or

    damage to products or packing.

    1-9.1.5 Storage.-

    (a) Store products in accord with manufacturer's instructions, with seals and labels intact and

    legible.

    1. Store products subject to damage by the elements in weathertight enclosures.

    2. Maintain temperature and humidity within the ranges required by manufacturer's

    instructions.

    (b) Exterior Storage.

    1. Store fabricated products above the ground, on blocking or skids, prevent soiling or

    staining. Cover products which are subject to deterioration with impervious sheet

    coverings, provide adequate ventilation to avoid condensation.

    2. Store loose granular materials in a well-drained area on solid surfaces to prevent

    mixing with foreign matter.

    (c) Arrange storage in a manner to provide easy access for inspection. Make periodic

    inspections of stored products to assure that products are maintained under specified

    conditions, and free from damage or deterioration.

  • 8/12/2019 Specifications Zny Vesda 11-24-10

    46/168

    VESDA FIRE ALARM SYSTEM UPGRADE PROJECT NOVEMBER, 2010

    NEW YORK AIR ROUTE TRAFFIC CONTROL CENTER (ZNY)

    RONKONKOMA, NEW YORK

    46/168

    1-9.1.6 Substitutions.-

    (a) Submit separate request for each substitution, support each request with:

    1. Complete data substantiating compliance of proposed substitution with requirements

    stated in Contract Documents:

    a) Product identification, including manufacturer's name and address.

    b) Manufacturer's literature; identify:

    1) Product description.

    2) Reference standards.

    3) Performance and test data.

    c) Samples, as applicable.d) Name and address of similar projects on which product has been used, and date of

    each installation.

    2. Itemized comparison of the proposed substitution with product specified. List

    significant variations.

    3. Data relating to changes in construction schedule.

    4. Any effect of substitution on separate contracts.

    5. List of changes required in other work or products.

    6. Accurate cost data comparing proposed substitution with product specified include:

    a) Amount of any net change to Contract Sum.

    7. Designation of required license fees or royalties.

    8. Designation of availability of maintenance services, sources of replacement materials.

    (b) Substitutions will not be considered for accept