Spillway Salaan

Embed Size (px)

Citation preview

  • 8/11/2019 Spillway Salaan

    1/21

    1. Concreting of Plain Flooring 2 men pour 1.2

    2. Concreting of Reinf. Flooring 2 men pour 0.84

    3. Concreting of Column & Beam 2 men pour 0.50

    4. Finishing of Flooring (rough) 2 men finishes

    5. Finishing of CHB Joints 2 men finishes

    6. Plastering of CHB 2 men plaster

    7. Laying of CHB 2 men lay 100

    8. Breaking old RC Flooring 2 men break 0.3

    9. Laying of glazed tile 4"x4" 2 men lay 10010. Laying of glazed tile 6"x6" 2 men lay 72

    11. Installation of Water Closet 2 men install 1

    12. Installation of Lavatory 2 men install 1

    13. Installation of G.I. Sheets 32"x8" on Steel Frames 2 men install 11

    14. Installation of G.I. Sheets 32"x8" on Wooden Frames 2 men install 20

    15. Installation of G.I. Sheets 32"x12" on Steel Frames 2 men install 10

    16. Installation of G.I. Sheets 32"x12" on Wooden Frames 2 men install 15

    17. Fabricating and Installation of Gutter Downspout, Ridge roll 2 men fab. Install18. Installation of G.I. Pipe 1/2 x 20" 2 men install 20

    19. Installation of Doors and Window Jamp 1 men install 3

    20. Installation of Door (Complete of Hinges and Knob) 1 men install 2

    21. Fabrication of Doors (Excluding Planning of Frames) 1 men make 3

    22. Planning Rough Lumber (Including Allignment) 1 man Plane 48

    23. Planning Rough Lumber (No Allignment) 1 man Plane 120

    24. Installation of Plywood Board 2 men install 1525. Installation of Wooden Post 2 men install 96

    26. Installation of Wood Jalousies Windows 1 men install 18.75

    I. Earth Works:

    a. Excavation 1.82 man hours/cu.m.

    b. Backfill 1.34 man hours/cu.m.

    II. Form Works:

    a. Footing, grade, 2.5 man hours/sq.m.

    column

    Labor EstimateActivities

    CONSTRUCTION WORK CAPACITIES IN M

  • 8/11/2019 Spillway Salaan

    2/21

    g. Form oil application 6 man hrs./sq.m.

    III. Reinforcement:

    a. Reinforcement of 9 man hours/100 kilosfooting up to roofing

    b. Grade Slab EWP 13 man hours/100sq.m.

    c. Floor membrane 15 man hours/100sq.m.

    d. Roof beams & bond 2.88 man hours/cu.m.

    beams

    e. Stairs 2.6 man hours/cu.m.

    f. Roof Slab 2.91 man hours/cu.m.

    g. Curing (water) 2 man hours/day for 7 days

    h. Equipment:

    1 Vibrator 16 min./cu.m.

    2 Crane 4 cu.m./man hour

    FORMWORKSMANHOURS PER SQUARE METER

    ITEMS

    Carpenter Laborer

    1. Continous Wall Type (CHB) 0.70 0.40 1.10

    2. Foundation on Pile Caps 1.50 0.65 2.15

    3. Grade Beam or FTB 0.75 0.40 1.15

    4. Walls Ground to 8 ft. high 1.10 0.72 1.82

    5. Walls 8 ft. to 16 ft. high 1.21 0.78 1.996. Walls 16 ft. to 20 ft. high 1.35 0.90 2.25

    7. Columns 1.22 0.80 2.02

    8. Beams & Girders 1.90 1.22 3.12

    9. Elevated Slabs (word shores) 1.15 1.16 2.31

    10. Elevated Slabs (adjusted shores) 0.70 0.90 1.60

    SCAFFOLDINGLENGTHErect Dismantle Total Erect

    1 to 2 Section Long 1.20 0.35 1.55 1.40

    3 to 5 Section Long 0.75 0.5 1.25 0.85

    MANHOURS

    Total

    1 or 2 Section High More than

    Dism

    1.

    0.

  • 8/11/2019 Spillway Salaan

    3/21

    5. Structural Backfill (Machine) 2.00 MH/cu.m.

    6. Hauling Spoils 1.00 MH/cu.m.

    7. Trenching by Hand 6.00 MH/cu.m.

    8. Trenching by Machine 0.20 MH/cu.m.9. Piping Installation

    CONCRETE FOUNDATION AND ELEVATED CONCRETE UNIT MANHOURS

    1. GRADE MEMBER

    Formwork 2.54 MH/sq.m.

    Concreting 8.54 MH/sq.m.

    Rebar Works 0.07 MH/sq.m.

    Finishing 0.40 MH/sq.m.

    2. SUSPENDED MEMBER

    Formwork 3.28 MH/sq.m.

    Concreting 16.70 MH/sq.m.

    Rebar Works 0.08 MH/sq.m.

    Finishing 0.80 MH/sq.m.

    Excavation 1.35 cu.m./man day

    Backfill 3.87 cu.m./man day

    Disposal of spoils 4.70 cu.m./man day

    Formworks 2.70 cu.m./man daySteelworks 10.00 kg./man day

    Concreting 0.91 cu.m./man day

    Finishing 11.80 cu.m./man day

    CHB Zocalo wall 2.40 sq.m./man day

    Ground floor slab (concreting) 1.00 cu.m./man day

    6 mm 0.222 0.2827 1.332 1.665 1.998

    10 mm 0.616 0.7854 3.696 4.62 5.544

    12 mm 0.887 1.131 5.322 6.6525 7.983

    16 mm 1 577 2 011 9 462 11 8275 14 193

    MISCELLANEOUS LABOR OUTPUT

    PHILIPPINE STANDARD WEIGHT OF REINFORCING BARSNominal

    diameter

    Unit Wt.

    kg./meter

    Nominal

    sectional

    6.00m

    kilograms

    7.50m

    kilograms

    9.00m

    kilograms

    10.50m kilograms 12.00m kilo

    2.331 2.6

    6.468 7.3

    9.3135 10.

    16 5585 18

  • 8/11/2019 Spillway Salaan

    4/21

    Number of Pounds (12d + 60d, framing) = d/6 x BF/100

    Number of Pounds (2d to 12d, sheating) = d/4 x BF/100

    whered = size of desired nail in pennies

    BF = total board feet to be nailed

  • 8/11/2019 Spillway Salaan

    5/21

    cu.m. concrete/day

    cu.m. conc./daycu.m. conc./day

    72 sq.m./day

    420 pcs./day

    8 sq.m./day

    pcs./day

    cu.m./day

    pcs./daypcs./day

    set water closet/2 days

    set Lav./1 1/2 day

    sheets/day

    sheets/day

    sheets/day

    sheets/day

    5 sheets: 32"x8" G.I. sheets/daylights/day

    pcs. 2"x5"x16" or 40 bd.ft./day

    pcs. Door/day

    pcs./day

    bd.ft./day

    bd.ft./day

    sheets 4'x8'/daybd.ft./day

    sq.ft/day

    AN HOURS

  • 8/11/2019 Spillway Salaan

    6/21

    Total

    2.40

    1.45

    Sec. High

    antle

    0

    0

  • 8/11/2019 Spillway Salaan

    7/21

    grams

    64

    92

    44

    24

  • 8/11/2019 Spillway Salaan

    8/21

  • 8/11/2019 Spillway Salaan

    9/21

    PROJECT : PROPOSED CHANGE ORDER OF CREEK CROSSINGLocation : Spillway, Brgy. Salaan, Zamboanga City

    Project Cost :

    Project Duration : THIRTY(30) Calendar Days

    Manpower Requirements : 15 Manpower (1-Engineering Assistant, 1-Mason/Steelman, 1-Pipefitter, 1-Welder, 1-Carpenter & 10-Laborers)

    NON-ENGINEERING BASIC ITEMS

    A. SUPERVISION 4.01%

    ENGINEERING BASIC ITEMS

    I. MOBILIZATION 1.28%

    II. HAULING OF MATERIALS 13.11% # # # # #

    III. FINAL STAKING/LINE AND GRADE 0.25%

    IV. EXCAVATION AND BACKFILLING WORKS 1.21%V. CONSTRUCTION OF CATENARY AND INSTALLATION OF G.I. PIPE 78.87% # # # # # # # # # # # # # # # # # # # # #

    VI. DEMOBILIZATION 1.28%TOTAL PROJECT COST 100%

    CASH OUTLAY REQUIREMENT

    TARGETED COMPLETION THIS PERIOD

    COMMULATIVE COMPLETION TO DATE

    RecommendingPrepared by: Reviewed & Checked by: Approved by: Project Implementation:

    FELIXBERTO R. CAARE, JR. RMP MARIE CLAIRE C. BONGO MARLI P. ACOSTA-DE FIESTA ARNULFO A. ALFONSOResearcher/Analyst A (J.O.) Principal Engineer C Officer-In-Charge Department ManagerPlanning & Development Section Planning & Development Section Planning & Design Division Maintenance Department

    56,518.00PhP

    Php431,266.00

    100.00%

    17,292.00PhP

    Amounts % Perfected

    C A L E N D A R D A Y S

    Work Item

    1,072.50PhP

    340,153.00PhP

    100.00%

    431,266.00Php

    5,500.00PhP

    Republic of the Philippines

    ZAMBOANGA CITY WATER DISTRICTPilar St., Zamboanga City

    5,230.50PhP

    5,500.00PhP

    GANTT CHART

    431,266.00Php

    30

  • 8/11/2019 Spillway Salaan

    10/21

    # # # # # # #

    Approved for Project Implementation:

    LEONARDO REY D. VASQUEZGeneral Manager

  • 8/11/2019 Spillway Salaan

    11/21

    Project: PROPOSED CHANGE ORDER OF CREEK CROSSING

    Location: Spillway, Brgy. Salaan, Zamboanga City

    Project Description:

    Construction/ installation of catenary, pipe creek crossing

    Scope of Works:

    Non - Engineering Basic Cost

    A. Supervision

    Engineering Basic Cost

    I. MobilizationII. Hauling of Materials

    III. Final Staking/Lay-outing/Line and Grade

    IV. Excavation and Backfilling Works

    V. Construction of Catenary/ G.I. Pipe Installation Works

    VI. Demobilization

    Cost of Project: Php431,266.00

    ITEMNO.

    UNIT QTY. UNIT COST AMOUNT

    A.

    1 - Engineering Assistant days 30 524.00 15,720.00

    15,720.00

    DIRECT COST 15,720.00

    I. lot 1 5,000.00 5,000.00

    5,000.00

    DIRECT COST 5,000.00

    II.

    A. Equipment Rental:

    1 - Cargo Truck (w/ fuel & driver) days 5 9,008.00 45,040.00

    45,040.00

    B. Labor:

    4 - Laborers days 5 317.00 6,340.00

    6,340.00

    DIRECT COST 51,380.00

    III.

    Republic of the Philippines

    ZAMBOANGA CITY WATER DISTRICT

    Pilar Street, Zamboanga City

    D E S C R I P T I O N

    NON - ENGINEERING BASIC COST

    SUPERVISION

    ENGINEERING BASIC COSTMOBILIZATION

    Note : Hauling of materials from Pasonanca Motorpool to Project Site

    HAULING OF MATERIALS

    FINAL STAKING/LINE AND GRADE

  • 8/11/2019 Spillway Salaan

    12/21

    * 16mm. x 7.50m. Def. Reinforcing Steel Bars pcs. 6 525.00 3,150.00

    * 10mm. x 6.00m. Def. Reinforcing Steel Bars pcs. 15 168.00 2,520.00

    #16 G.I. Tie-wire kgs. 6 75.00 450.00

    39 pcs. - 2" x 3" x 10' Coco Lumber bd.ft. 195 20.00 3,900.00

    12 pcs. - 2" x 4" x 10' Coco Lumber bd.ft. 80 20.00 1,600.00* 12mm. thk x 1.20m. x 2.40m. Ordinary Plywood shts. 2 750.00 1,500.00

    2" C.W. Nail kg. 1 63.00 63.00

    4" C.W. Nail kgs. 6 58.00 348.00

    * 25mm. x 6.00m. M.S. Plain Round Bar pcs. 3 1,364.00 4,092.00

    * 12mm. x 6.00m. M.S. Plain Round Bar pc. 1 255.00 255.00

    16mm. x 6 x 19 Galvanized Strand Wire Rope, IWRC EIPS ln.mtrs. 47 612.00 28,764.00

    25mm. Hook & Eye Galvanized Iron Turnbuckle (Heavy Duty) pcs. 2 473.00 946.00

    16mm. G.I. Extra Heavy Wire Rope Thimbles pcs. 2 240.00 480.00

    * 6mm. thk. x 50mm. x 6.00m. M.S. Flat Bar pcs. 9 824.00 7,416.00

    12mm. x 38mm. Stainless Steel Bolt w/ Nut & Washer pcs. 116 36.00 4,176.00

  • 8/11/2019 Spillway Salaan

    13/21

    19mm. Thk. X 300mm. X 350mm. M.S. Plate w/ 4-22mm. Bolt Holes pcs. 2 2,400.00 4,800.00

    19mm. x 150mm. Bent Concrete Anchor Bolt w/ Nut & Washer (Heavy Duty) pcs. 8 127.00 1,016.00

    16mm. G.I. Wire Rope Clip, Heavy Duty pcs. 6 28.00 168.00

    100mm. x 6.00m. G.I. Pipe, ASTM A53-90A Heavy Gauge pcs. 5 9,877.00 49,385.00

    16mm. Thk. X 229mm. O.D. x 116mm. I.D. Steel Ring Flange w/ 8-19mm. pcs. 18 516.00 9,288.00Bolt Holes in accordance w/ AWWA C207 Class D Std.

    6mm. Thk Rubber Gasket kgs. 18 60.00 1,080.00

    16mm. x 63.50mm. Hex. Head Stainless Bolt w/ Nut & Washer pcs. 72 82.00 5,904.00

    * 6mm. thk. x 50mm. x 50mm. M.S. Angle Bar pc. 1 1,500.00 1,500.00

    16mm. x 150mm. Bent Concrete Anchor Bolt w/ Nut & Washer (Heavy Duty) pcs. 6 107.00 642.00

    Hacksaw Blade pcs. 5 62.00 310.00

    6011 Welding Rod kgs. 3 144.00 432.00

    Metal Primer gal. 1 427.00 427.00

    Quick Dry Enamel (Paint Blue) gal. 1 606.00 606.00

    2" Paint Brush pcs. 3 27.00 81.00155,910.00

    B. Labor:

    10 - Laborers days 28 317.00 88,760.00

    1 - Steelman days 28 366.00 10,248.00

    1 - Welder days 28 366.00 10,248.00

    1 - Carpenter days 28 366.00 10,248.00

    1 - Pipefitter days 28 341.00 9,548.00

    129,052.00

    C. Equipment Rental:

    1 - Unit Generator Set/ Welding Machine w/ Complete accessories (w/ fuel) days 6 3,128.00 18,768.002 - Units Chain Block days 2 500.00 2,000.00

    1 - Unit Angle Grinder days 5 300 1,500.00

    2 - Units Wire Rope Grip/ Pull Lifting Machines (Winch) days 2 500 2,000.00

    24,268.00

    DIRECT COST 309,230.00

    VI. DEMOBILIZATION lot 1 5,000.00 5,000.00

    5,000.00

    DIRECT COST 5,000.00

    Sizing Requirements

    Note: *All sizes referred herein should mean commercially available measurements with tolerance of + 1mm.

    Summary of Manpower:

    5 - Skilled

    10 - Unskilled

  • 8/11/2019 Spillway Salaan

    14/21

    PROPOSED CHANGE ORDER OF SALAAN CREEK CROSSING SPILLWAY, BRGY. SALAAN, ZAMBOANGA CITY

    Stations : Sta. 0+000.00 - Sta. 0+042.00

    Length : 42.00 LN. MTRS.

    ITEM ESTIMATED DIRECT TOTAL

    NO. COST INDIRECT COST

    (9) (10) (11)

    (5)X(8) 12%((5)+(9)) (9)+(10)

    NON - ENGINEERING BASIC COSTA. 30 days 15,720.00Php 10% 10% 1,572.00Php 1,572.00Php

    ENGINEERING BASIC COST

    I. Mobilization 1 lot 5,000.00Php 10% 10% 500.00Php 500.00Php

    II. Hauling of Materials 5 days 51,380.00Php 10% 10% 5,138.00Php 5,138.00Php

    III. 1 day 975.00Php 10% 10% 97.50Php 97.50Php

    IV. Excavation & Backfilling Works 9.11 cu.m. 4,755.00Php 10% 10% 475.50Php 475.50Php

    V. 42 ln.mtrs. 309,230.00Php 10% 10% 30,923.00Php 30,923.00Php

    VI. 1 lot 5,000.00Php 10% 10% 500.00Php 500.00Php

    TOTALDATE PREPARED:

    October 23, 2013

    Prepared by: Designed by: Checked & Reviewed by: Submitted By:

    FELIXBERTO R. CAARE, JR., RMP EDITO M. BAUTISTA, JR. MARIE CLAIRE C. BONGO MARLI ACOSTA - DE FIESTA

    Researcher/ Analyst A Senior Engineer A - C.E. Principal Engineer C Officer - In - Charge

    Planning & Design Division Planning & Design Division Planning & Design Division Planning & Design Division

    Approved by: Recommending Project Implementation: Approved for Project Implementation:

    EFREN C. SALVACION ALNULFO A. ALFONSO LEONARDO REY D. VASQUEZ

    Officer - In - Charge Department Manager C General Manager A

    Planning & Design Division Maintenance Department

    Demobilization

    Final Staking/ Line & Grade

    NO VAT

    PROJECT WILL

    BE UNDER

    TAKEN BY

    ADMIN.

    Construction of Catenary & Installation of

    G.I. Pipe

    (1) (2) (3) (4) (5) (6)

    VAT

    Supervision

    (7)

    IN PERCENT

    OCM PROFIT % VALUE

    (8)

    APPROVED BUDGET FOR THE CONTRACT

    Project Name and Location

    Contract

    DESCRIPTION QUANTITY UNIT

    MARK-UPSTOTAL MARK-UP

  • 8/11/2019 Spillway Salaan

    15/21

    30 Calendar Days

    UNIT

    COST

    (13)

    (12)/(3)

    576.40Php

    5,500.00Php

    11,303.60Php

    1,072.50Php

    574.15Php

    8,098.88Php

    5,500.00Php

    431,266.00Php

    5,500.00Php

    56,518.00Php

    5,230.50Php

    340,153.00Php

    (12)

    (5)+(11)

    17,292.00Php

    1,072.50Php

    5,500.00Php

    TOTAL COST

    ATTACHMENT "A"

    D.O. No. 29 S.2011

    uration:

  • 8/11/2019 Spillway Salaan

    16/21

    Project: PROPOSED BOARD ROOM CONFERRENCE TABLELocation: 2nd. Floor Board Room, Main Office, Pilar Street, Zamboanga City

    Project Description:

    d. Painting Works

    Scope of Works:

    Non - Engineering Basic Cost

    SupervisionEngineering Basic Cost

    I. Mobilization

    II. Carpentry Works

    III. Office Equipment

    IV. Painting Works

    V. Demobilization

    Cost of Project: Php248,012.70

    ITEM

    NO.UNIT QTY. UNIT COST AMOUNT

    1 - Engineering Assistant days 21 524.00 11,004.00

    11,004.00

    Direct Cost 11,004.00

    I. lot 1 5,000.00 5,000.00

    5,000.00

    Direct Cost 5,000.00

    II.

    a. Materials:

    19mm. thk. x 1.20m. x 2.40m. Marine Plywood shts. 10 1,898.75 18,987.50

    * 6mm. Thk. X 1.20m. X 2.40m. Marine Plywood shts. 2 575.75 1,151.50

    8 pcs. - 1" x 1" x 8' Lauan Wood, S4s (wood nosing) bd.ft. 5 37.00 185.00

    2" Finishing Nail kgs. 3 85.00 255.00

    1 1/2" Finishing Nail kg. 1 85.00 85.00

    CARPENTRY WORKS

    1. Fabrication of Five (5) Units Office Tables

    Republic of the Philippines

    ZAMBOANGA CITY WATER DISTRICT

    Pilar Street, Zamboanga City

    D E S C R I P T I O N

    MOBILIZATION

    ENGINEERING BASIC COST

    NON - ENGINEERING BASIC COST

    SUPERVISION

    a. Fabrication of Twelve (12) Units Conferrence Table

    b. Fabrication of Five (5) Units Office Tables

    c. Supply & Delivery of Five (5) Units Office Chair

    1. Fabrication of Five (5) Units Office Tables

    2. Fabrication of Twelve (12) Units Conferrence Table

    Supply & Delivery of Five (5) Units Office Chair

  • 8/11/2019 Spillway Salaan

    17/21

    Direct Cost 41,274.00

    a. Materials

    19mm. thk. x 1.20m. x 2.40m. Marine Plywood shts. 20 1,898.75 37,975.00

    * 6mm. Thk. X 1.20m. X 2.40m. Marine Plywood shts. 5 575.75 2,878.7512 pcs. - 1" x 6" x 6' Lauan Wood, S4s bd.ft. 36 37.00 1,332.00

    6 pcs. - 1" x 1 1/2" x 8' Lauan Wood, S4s bd.ft. 6 37.00 222.00

    2" Finishing Nail kgs. 5 85.00 425.00

    1 1/2" Finishing Nail kgs. 2 85.00 170.00

    400mm. Length Drawer Rolling Slide sets 24 64.75 1,554.00

    White Wood Glue gals. 2 490.00 980.00

    Drawer Handle sets 12 37.00 444.00

    2. Fabrication of Twelve (12) Units Conferrence Table

  • 8/11/2019 Spillway Salaan

    18/21

    Drawer Lock sets 12 116.00 1,392.00

    47,372.75

    b. Labor:

    4 - Carpenters days 10 366.00 14,640.00

    2 - Laborers days 10 317.00 6,340.00

    20,980.00

    Direct Cost 68,352.75

    III.

    Office Chair/ Low back and seat molded foam cushion, lockable tilting units 5 4,600.00 23,000.00

    mechanism, polyurethane or polypropylene armrest, five legged and black

    leatherette back and nylon twin caster pneumatic height adjustment

    Direct Cost 23,000.00

    IV. PAINTING WORKS

    a. Materials

    #120 Sand Paper Water Proof pcs. 15 11.00 165.00

    2" Paint Brush pcs. 5 36.75 183.75

    1" Paint Brush pcs. 5 13.75 68.75

    Lacquer Thinner gal. 1 462.25 462.25

    Paint Thinner gals. 2 390.00 780.00

    Acrylic Solvent Based Primer gals. 5 820.000 4,100.00

    Acrylic Solvent Based Putty Filler gals. 4 506.000 2,024.00

    Acrylic Solvent Based Top Coat White gals. 10 1,040.55 10,405.50

    Acrylic Solvent Based Reducer gals. 5 384.75 1,923.75

    Tinting for acrylic base solvent finish paint:

    Raw Sienna (1/4L) cans 2 96.75 193.50

    Black (1/4L) cans 2 96.75 193.50

    Thalo Blue (1/4L) cans 2 96.75 193.50

    Toluodine Red (1/4L) cans 2 96.75 193.50

    Burt Umber (1/4L) cans 2 96.75 193.50

    Baby Roller w/ Tray pcs. 2 130.00 260.00

    21,340.50

    b. Labor:

    2 - Painters days 7 366.00 5,124.002 - Laborers days 7 317.00 4,438.00

    9,562.00

    Direct Cost 30,902.50

    V. DEMOBILIZATION lot 1 5,000.00 5,000.00

    5,000.00

    Direct Cost 5,000.00

    Sizing Requirements

    Note: *All sizes referred herein should mean commercially available measurements with tolerance of + 1mm.

    Summary of Manpower:

    7 - Skilled Workers

    2 - Unskilled Workers

    OFFICE EQUIPMENT

    Supply & Delivery of Five (5) Units Office Chair

  • 8/11/2019 Spillway Salaan

    19/21

    PROPOSED BOARD ROOM CONFERRENCE TABLE 2ND FLOOR, BOARD ROOM, MAIN OFFICE, PILAR ST., ZAMBOANGA CITY

    Stations :

    Length :

    ITEM ESTIMATED DIRECT TOTAL

    NO. COST INDIRECT COST

    (9) (10) (11)

    (5)X(8) 12%((5)+(9)) (9)+(10)

    NON - ENGINEERING BASIC COST21 days 11,004.00Php 10% 10% 20% 2,200.80Php 1,584.58Php 3,785.38Php

    ENGINEERING BASIC COST

    I. Mobilization 1 lot 5,000.00Php 10% 10% 20% 1,000.00Php 720.00Php 1,720.00Php

    II. Carpentry Works

    1. Fabrication of Office Tables 5 units 41,274.00Php 10% 10% 20% 8,254.80Php 5,943.46Php 14,198.26Php

    2. Fabrication of Conferrence Table 12 units 68,352.75Php 10% 10% 20% 13,670.55Php 9,842.80Php 23,513.35Php

    III. 5 units 23,000.00Php 10% 10% 20% 4,600.00Php 3,312.00Php 7,912.00Php

    IV. Painting Works 7 days 30,902.50Php 10% 10% 20% 6,180.50Php 4,449.96Php 10,630.46Php

    V. 1 lot 5,000.00Php 10% 10% 20% 1,000.00Php 720.00Php 1,720.00Php

    TOTAL

    DATE PREPARED:

    December 1, 2013

    Prepared by: Designed by: Checked & Reviewed by: Submitted By:

    FELIXBERTO R. CAARE, JR., RMP EDITO M. BAUTISTA, JR. ERLYN J-F. GODINEZ MARLI ACOSTA - DE FIESTA

    Researcher/ Analyst A Senior Engineer A - C.E. Principal Engineer C Officer - In - Charge

    Planning & Design Division Planning & Design Division Planning & Design Division Planning & Design Division

    Approved by: Recommending Project Implementation: Approved for Project Implementation:

    EFREN C. SALVACION ALNULFO A. ALFONSO LEONARDO REY D. VASQUEZ

    Officer - In - Charge Department Manager C General Manager A

    Planning & Design Division Maintenance Department

    APPROVED BUDGET FOR THE CONTRACT

    Project Name and Location

    Contract

    DESCRIPTION QUANTITY UNIT

    MARK-UPSTOTAL MARK-UP

    VATIN PERCENT

    OCM PROFIT % VALUE

    (1) (2) (3) (4) (5) (6) (7) (8)

    Demobilization

    Supervision

    Office Equipment

  • 8/11/2019 Spillway Salaan

    20/21

    21 CALENDAR DAYS

    UNIT

    COST

    (13)

    (12)/(3)

    704.26Php

    6,720.00Php

    11,094.45Php

    7,655.51Php

    6,182.40Php

    5,933.28Php

    6,720.00Php

    ATTACHMENT "A"

    D.O. No. 29 S.2011

    uration:

    TOTAL COST

    41,532.96Php

    55,472.26Php

    91,866.10Php

    (12)

    (5)+(11)

    6,720.00Php

    248,012.70Php

    14,789.38Php

    6,720.00Php

    30,912.00Php

  • 8/11/2019 Spillway Salaan

    21/21

    PROJECT : PROPOSED BOARD ROOM CONFERRENCE TABLELocation : 2nd. Floor Board Room, Main Office, Pilar Street, Zamboanga City

    Project Cost :

    Project Duration : TWENTY ONE(21) Calendar Days

    Manpower Requirements : 9 Manpower (1-Engineering Assistant, 4 -Carpenters, 2 -Painters, 2 -Laborers)

    NON-ENGINEERING BASIC ITEMS

    SUPERVISION 5.96%ENGINEERING BASIC ITEMS

    I. MOBILIZATION 2.71%

    II. CARPENTRY WORKS1. Fabrication of Five (5) Units Office Tables 22.37% # # # # # #

    2. Fabrication of Twelve (12) Units Conferrence Table 37.04% # # # # # # # # # #

    III. OFFICE EQUIPMENT 12.46%

    IV. PAINTING WORKS 16.75% # # # # # # #V. DEMOBILIZATION 2.71% #

    TOTAL PROJECT COST 100%

    CASH OUTLAY REQUIREMENTTARGETED COMPLETION THIS PERIOD

    COMMULATIVE COMPLETION TO DATE

    Prepared by: Reviewed & Checked by: Submitted by: Approved by:

    FELIXBERTO R. CAARE, JR. RMP ERLYN J-F. GODINEZ MARLI P. ACOSTA-DE FIESTA EFREN C. SALVACION

    Researcher/Analyst A (J.O.) Principal Engineer C Officer-In-Charge Officer - In - Charge

    Planning & Design Division Planning & Design Division Planning & Design Division Planning & Design Division

    RecommendingProject Implementation: Approved for Project Implementation:

    ARNULFO A. ALFONSO LEONARDO REY D. VASQUEZ

    Department Manager General Manager

    Maintenance Department

    14,789.38PhP

    Amounts

    30,912.00PhP

    41,532.96PhP

    6,720.00PhP

    % Perfected

    Republic of the Philippines

    ZAMBOANGA CITY WATER DISTRICTPilar St., Zamboanga City

    6,720.00PhP

    GANTT CHART

    248,012.70Php

    Work Item

    248,012.70Php

    55,472.26PhP91,866.10PhP

    C A L E N D A R D A Y S

    21

    Php248,012.70100.00%

    100.00%