I-205 IMPROVEMENTS Stafford Rd to OR 213
Urban Mobility OfficeOctober 14, 2020
I-205 IMPROVEMENTS
Project Issues & Benefits
Issues
• This two-lane section of I-205 creates a bottleneck, causing congestion and crashes, creating delays.
• Closely spaced on-ramps contribute to safety and travel-time predictability issues.
• The Abernethy Bridge and eight bridge sites are seismically vulnerable in the event of a major earthquake.
Benefits
• The addition of a third lane in each direction helps prevent bottlenecks.
• Extending the I-205 northboundon-ramp across the Abernethy Bridge increases safety and travel-time predictability.
• Seismically upgrading the Abernethy Bridge and replacing eight bridge sites in the project area ensures bridges can better withstand a major earthquake.
I-205 IMPROVEMENTS
Major Project Features
I-205 IMPROVEMENTS
Project Phasing
I-205 IMPROVEMENTS
Phase 2 – Stafford Road to 10th Street Phase 1 – 10th Street to OR213
Phase 3 – Real Time Sign Construction
• I-205 Stafford Rd to OR213 Real Time Signs Construction
• $5.5M construction authorized September 2019
• Sign & structure installation complete– Advisory speed signs (VAS)– Travel time/traveler information
signs (VMS)
• Remaining work includes:– Sign commissioning– Grading around sign installs– Landscape - seeding
• Work expected to be complete Fall 2020
I-205 IMPROVEMENTS
DBE Performance and Schedule
Phase 1*
(OR213 to 10th St)
• 60% = Aug ‘20
• AP = Mar ‘21
• Final = Aug ’21
• PCO = Dec ’21
• Bid = Apr ’22
Phase 2
(10th St to Stafford)
• 60% = Nov ‘20
• AP = Oct ‘21
• Final = Apr ’22
• PCO = Aug ‘22
• Bid = Dec ‘22
Phase 3
• Bid = Sept 19, 2019
• Completion = Fall ‘2020
Project Schedule (As of October 2020)
DBE Performance
I-205 IMPROVEMENTS
• Project Participation Goal – 8.5%
• HDR Lead – 26 subs – 15 DBE firms
• DBE Participation to date = 10.8%
• Total DBE payments = $4.5 Million +
• DBE Goals for construction are TBD
*Note: Dependent on available construction funding –ODOT is currently working on funding options for Phase 1
THANK YOU
For more information, please contact:Allen Hendy, PE – ODOT Resident EngineerI-205 Improvements Project ManagerPhone: 971-235-3861Email: [email protected]
I-205 IMPROVEMENTS