STAKEHOLDER WORKSHOP #1
JUNE 28, 2016
Project Timeline
What We’ve HeardThe following are important:
Safe streets with slow speeds
Limited impacts to businesses and homes
Green space such as gardens, parks, and landscaping
Safe streets with separate spaces for different users
Project Objectives Connect Sun Valley to Downtown and surrounding
neighborhoods
Provide safe and convenient routes/facilities for all modes
Extend a gridded street network to support community vitality
Enhance 13th Avenue and Holden Place as green connections to parks and trails
Create a street network that supports economic development
Today’s Workshop
Overview of Alternatives Development and Evaluation Process
Review of Tier 1 Design Elements
Tier 1 Screening Results
Presentation of Packaged Alternatives
Questions and Discussion on Packaged Alternatives
Evaluation Process
Tier 1 EvaluationConsiders:
• Pedestrian connectivity, comfort and safety
• Bicycle comfort and safety• Access to trails and green space• Connectivity• Complete Street vision• Safety for all modes
• Parking• Property impacts• Economic redevelopment• Community character• Green infrastructure• Consistency with other plans
Tier 1 Design Elements• Alignment
• Cross-section
• Holden and Decatur intersection
• Bicycle network
Tier 1 Design ElementsAlignments• No action
• Transition west of S. Platte River with 13th Avenue tie-in
• Transition west of S. Platte River with 13th Avenue dead end
• Transition west of Decatur Street
• One-way couplet
• Grid network completion
Alignments in red were eliminated
Transition west of S. Platte River with 13th Avenue tie-in
Transition west of S. Platte River with 13th Avenue dead-end
Transition west of Decatur Street
One-way couplet
Grid Network Completion
Tier 1 Design ElementsCross-Sections• No action
• Basic street with tree lawn
• Basic street with bike lane
• Street with parking on one side
• Sun Valley Master Plan cross-section
Tier 1 Design ElementsHolden and Decatur Intersection• No action
• Realign west of Decatur
• Realign east of Decatur
• Roundabout
Tier 1 Design ElementsBike Network• No action
• Bike route on Holden Place
• Bike route on 13th Avenue
Tier 1 Screening SummaryAlignments• No action – RETAIN
• Transition west of S. Platte River with 13th Avenue tie-in – RETAIN
• Transition west of S. Platte River with 13th Avenue dead end – ELIMINATE
• Transition west of Decatur Street – ELIMINATE
• One-way couplet – ELIMINATE
• Grid network completion – RETAIN
All other elements (cross-sections, Holden and Decatur intersection treatments, and bike network) – RETAIN
Alternatives DevelopmentFour alternatives were assembled:
No action
Grid completion
Green infrastructure emphasis
Multimodal emphasis
No Action Alternative
Grid Network Completion
• Adds Riverfront Drive to complete grid network
• Roundabout at W. Holden Place and Decatur Street
• No change in roadway width of W. Holden Place and W. 13th Avenue, improvements to infrastructure, reconstruction of roadway and sidewalks
• Bike route on W. 13th Avenue
Grid Network Completion13th Avenue Holden Place
Grid Network Completion
Holden Place
Green Infrastructure Alternative
• Roadway transition west of the South Platte River
• Realign Decatur Street at W. Holden Place intersection to the west
• Tree lawn and bioswales on W. Holden Place
• Bike lanes with intermittent bioswales on W. 13th Avenue
• Bike route on W. 13th Avenue
Green Infrastructure Alternative13th Avenue Holden Place
Green Infrastructure Alternative
Holden Place
Multimodal Emphasis Alternative
• Roadway transition west of the South Platte River
• Realign Decatur Street at W. Holden Place intersection to the east
• W. Holden Place – Modified Sun Valley master plan cross section with protected bike lanes
• W. 13th Avenue – tree lawn cross section
• Bike route on W. Holden Place; enhanced sidewalk crossings and bus stops
Multimodal Emphasis Alternative13th Avenue Holden Place
Multimodal Emphasis Alternative
Holden Place
Next Steps
Fill out a comment sheet
Participate in the online survey
Spread the word about the survey!
Save the date: Next Stakeholder Workshop is scheduled for Tuesday,
September 13th, from 5 p.m. to 6:30 p.m.
Discussion
Time for brief comments from all participants and further discussion about the alternatives…