EDC TN published 18.07.2017 32-4 Rev 6 Document Template Standard Title: Integrated Risk Management Standard Document Identifier: 32-391 Alternative Reference Number: N/A Area of Applicability: Eskom Holdings SOC Limited Functional Area: Enterprise Risk & Resilience Revision: 4 Total Pages: 32 Next Review Date: March 2020 Disclosure Classification: Public

Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

EDC TN published 18.07.2017 32-4 Rev 6 Document Template

Standard

Title: Integrated Risk Management Standard

Document Identifier: 32-391

Alternative Reference Number:

N/A

Area of Applicability: Eskom Holdings SOC Limited

Functional Area: Enterprise Risk & Resilience

Revision: 4

Total Pages: 32

Next Review Date: March 2020

Disclosure Classification:

Public

Page 2: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Standard Unique Identifier: 32-391

Revision: 4

Page: 2 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

Content

Page

1. Introduction .................................................................................................................................................. 4

2. Supporting Clauses ..................................................................................................................................... 5

2.1 Scope ................................................................................................................................................. 5

2.1.1 Purpose .................................................................................................................................. 5

2.1.2 Applicability ............................................................................................................................ 5

2.2 Normative/Informative References ..................................................................................................... 5

2.2.1 Normative ............................................................................................................................... 5

2.2.2 Informative ............................................................................................................................. 6

2.3 Definitions ........................................................................................................................................... 7

2.4 Abbreviations ...................................................................................................................................... 9

2.5 Roles and Responsibilities ............................................................................................................... 10

2.6 Process for Monitoring ..................................................................................................................... 10

2.7 Related/Supporting Documents ....................................................................................................... 10

3. Standard .................................................................................................................................................... 11

3.1 Integrated Risk Management Preamble........................................................................................... 11

3.2 Institutionalising (Incorporating) Integrated Risk Management in the organisation ......................... 12

3.2.1 Foundational Principles ........................................................................................................ 12

3.2.2 Building blocks ..................................................................................................................... 13

3.3 Integrated Risk Management Process ............................................................................................. 15

3.3.1 Communicate and Consult ................................................................................................... 16

3.3.2 Establish the context ............................................................................................................ 16

3.3.3 Identify the risk ..................................................................................................................... 17

3.3.4 Analyse the risk .................................................................................................................... 17

3.3.5 Evaluate the risk .................................................................................................................. 22

3.3.6 Treat the risk ........................................................................................................................ 23

3.3.7 Monitor and Review ............................................................................................................. 24

3.4 Integrated Risk Management Standard Requirements .................................................................... 25

3.4.1 Requirement 1: Risks of Divisional Business and Operational Plans.................................. 25

3.4.2 Requirement 2: Divisional risk reviews ................................................................................ 25

3.4.3 Requirement 3: Risks of significant decisions and/or changes ........................................... 25

3.4.4 Requirement 4: Assurance of Critical Controls .................................................................... 25

3.4.5 Requirement 5: Learning from Successes and Failures ...................................................... 25

3.4.6 Requirement 6: Risk Management Planning ....................................................................... 26

3.4.7 Requirement 7: Recording Risk Management ..................................................................... 26

3.4.8 Requirement 8: Monitoring and Reporting Risk Management ............................................. 26

3.4.9 Requirement 9: Integrated Risk Management and Projects ................................................ 26

3.4.10 Requirement 10: Business Continuity Management ........................................................... 26

3.4.11 Requirement 11: Disaster Management .............................................................................. 27

4. Acceptance ................................................................................................................................................ 28

Page 3: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Standard Unique Identifier: 32-391

Revision: 4

Page: 3 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

5. Revisions ................................................................................................................................................... 29

6. Development Team ................................................................................................................................... 29

7. Acknowledgements ................................................................................................................................... 29

Appendix 1 - Quantitative Risk Analysis (QRA) ............................................................................................... 30

Appendix 2 – Disaster Risk Assessment .......................................................................................................... 32

Page 4: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 4 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

1. Introduction

The effective management of risk and resilience is essential for Eskom as a company, particularly given the role it plays in the South African economy. It is therefore an important element of the Eskom Corporate Plan.

This standard includes 12 approved building blocks for Risk & Resilience (see figure 1 below), focussing specifically on the 8 common Risk & Resilience management components to ensure that risk management will be consistently applied. The four remaining building blocks deal specifically with Resilience and are covered within their documentation.

Figure 1: 12 Building Blocks for Risk & Resilience

These building blocks support the following:

• Effective shaping, safeguarding and specialised servicing of risk and resilience across the organisation through a centre-lead governance and operating model.

• An integrated approach to managing risk and resilience.

• Compliance to applicable legislation

Eskom is committed to the effective management of risk which is central to Eskom’s governance and management processes, and essential for achieving the organisation’s mandate and objectives. Eskom’s mandate is to provide electricity in an efficient and sustainable manner, including its generation, transmission, and distribution and sales. Eskom is a critical and strategic contributor to the South African government’s goal of ensuring security of electricity supply in the country as well as economic growth and prosperity.

Governance &

Reporting

Standardised Risk &

Resilience Methodologies

National / International Networking,

Collaboration, Benchmarking

Approved Enterprise

Risk Appetite & Tolerance

Business Continuity

Management

Disaster Management

Policies & Standards

Enterprise Risk &

Resilience Management

Plans

Defined Performance Measures &

Maturity Evaluation

Effective Risk Control,

Feedback & Continuous

Improvement

Incident Command

Simulation Exercises

8 common building blocks for Risk & Resilience 4 building blocks for Resilience

Page 5: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 5 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

It is therefore imperative that there will be one standard for the management of all types of risks that will be consistently applied across all of Eskom including its subsidiaries and projects. The objective of managing risk is to ensure that Eskom is able to formulate and execute its strategy effectively, to operate its business efficiently. It is therefore important that risks that impact Eskom’s objectives are identified, effectively managed and continuously monitored.

2. Supporting Clauses

2.1 Scope

This standard supports Eskom’s Enterprise Risk and Resilience Policy and describes a structured approach to risk management, using consistent approaches to the assessment and treatment of all types of risk, at all levels and for all activities in the company and describes a common methodology.

2.1.1 Purpose

This standard, when complied with at all levels and for all activities in the company, will ensure a standard approach to Integrated Risk Management throughout and at all levels of the organisation.

2.1.2 Applicability

This standard shall apply throughout Eskom Holdings SOC Ltd, its divisions, subsidiaries, integrated operations, and entities wherein Eskom has a controlling interest.

2.2 Normative/Informative References

Parties using this document shall apply the most recent edition of the documents listed in the following paragraphs.

2.2.1 Normative

[1] 32-86 – Enterprise Risk & Resilience Policy.

[2] ISO 31000: 2009 - Risk Management - Principles and guidelines on implementation

[3] ISO 31004: 2013 - Risk Management – Guidance for the implementation of ISO 31000

[4] ISO/IEC Guide 73 - Vocabulary for Risk Management

[5] ISO 31010: 2009 - Risk management – Risk assessment techniques

[6] King III - King Code of Governance for South Africa 2009

[7] Eskom Risk Appetite and Tolerance Statement and Profile

[8] Disaster Management Act (Act No. 57 of 2002) as amended

Page 6: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 6 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

2.2.2 Informative

[9] ISO 9001: 2015 - Quality Management Systems

[10] 240-79747329 – Business Continuity Standard

[11] 240-86786675 – Disaster Management Standard

[12] 240-105203484 – Incident Command System Standard

[13] 32-973 – Simulation Exercise Standard

Page 7: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 7 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

2.3 Definitions

Definition Explanation

Assurance Assurance is a process that provides confidence that objectives will be achieved with a tolerable level of residual risk.

Business Risk

Cause Something that gives rise to or creates a risk or an event.

Communication and consultation

Continual or iterative process that an organization conducts to provide, share and or obtain information and to engage in dialogue with stakeholders regarding the management of risk

Consequence Outcome of an event affecting objectives

Control Measure that is modifying risk

Control owner The person nominated as accountable for the assurance of the control to ensure that both the design and the operation of the control are effective. Control owners names are recorded in risk registers.

Control self-assessment

The planned, periodic review by managers of work processes, procedures and systems to ensure that the risk controls are still effective and appropriate. The review should focus on opportunities for improvement with existing work processes; procedures and systems and with the risk controls.

Control tasks Process of developing, selecting and implementing measures to enhance controls.

Cost benefit analysis An objective assessment comparing all the costs of treating a risk against all the benefits from the residual risk.

Disaster A progressive or sudden, widespread or localised, natural or human-caused occurrence which -

(a) causes or threatens to cause -

(i) death, injury or disease;

(ii) damage to property, infrastructure or the environment; or

(iii) significant disruption of the life of a community; and

(b) is of a magnitude that exceeds the ability of those affected by the disaster to cope with its effects using only their own resources

Emerging risk Emerging risks are those risks an organization has not yet recognized or those which are known to exist, but are not well understood.

Exposure Extent to which an organization is subjected to an event

External context External environment in which the organization seeks to achieve its objectives

Key element structure

Page 8: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 8 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

Internal context Internal environment in which the organization seeks to achieve its objectives

Level of risk Magnitude of a risk expressed in terms of the combination of consequences and their likelihood

Likelihood Chance of something happening.

Monitoring Continual checking, supervising, critically observing or determining the status in order to identify change from the performance level required or expected.

Potential exposure The total plausible maximum impact on Eskom arising from a risk without regard to controls.

Review Activity undertaken to determine the suitability, adequacy and effectiveness of the subject matter to achieve established objectives

Risk The effect of uncertainty on objectives.

Risk analysis Process to comprehend the nature of risk and to determine the level of risk

Risk appetite Amount and type of risk that the organization is prepared to take in order to achieve its objectives.

Risk assessment Overall process of risk identification , risk analysis and risk evaluation

Risk control effectiveness (RCE)

A relative assessment of actual level of control that is currently present and effective compared with that which is reasonably achievable for a particular risk.

Risk criteria Terms of reference against which the significance of a risk is evaluated

Risk evaluation Process of comparing the results of the risk analysis against risk criteria to determine whether the level of risk is acceptable or tolerable.

Risk identification Process of finding, recognizing and describing risks

Risk management Coordinated activities to direct and control an organization with regard to risk

Risk management framework

Set of components that provide the foundations and organizational arrangements for designing, implementing, monitoring, reviewing and continually improving risk management processes throughout the organization

Risk management information system

The database operated by Eskom that holds all risk management information including all risk registers, risk treatment plans and risk management plans.

Page 9: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 9 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

Risk management policy

Overall intentions and direction of an organization related to risk management

Risk management process

Systematic application of management policies, procedures and practices to the tasks of communicating, consultation, establishing the context, identifying, analysing, evaluating, treating, monitoring and reviewing risk

Risk matrix Tool for ranking and displaying risks by defining ranges for consequence and likelihood

Risk owner Person with the accountability and authority for managing the risk and any associated risk treatments.

Risk register Record of information about identified risks

Risk reporting Form of communication intended to address particular internal or external stakeholders to provide information regarding the current state of risk and its management

Risk tolerance

Risk tolerance is the organization’s readiness to bear the risk after risk treatment, in order to achieve its objectives.

Risk treatment Process of developing, selecting and implementing measures to modify risk

Risk treatment plan Documents the risk treatment actions to be taken. Includes details of separate tasks, task owners and completing dates.

Situation awareness

Situation awareness (SA) involves being aware of what is happening in the vicinity, in order to understand how information, events, and one's own actions will impact goals and objectives, both immediately and in the near future. It is critical to decision-makers in complex, dynamic areas.

Task owner The person nominated as accountable for the completion of a risk treatment action.

2.4 Abbreviations

Abbreviation Explanation

DE Divisional Executive

ER&R Enterprise Risk and Resilience

EXCO Executive Committee

GE Group Executive

GM General Manager

IRM Integrated Risk Management

Page 10: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 10 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

Abbreviation Explanation

Manco Management Committee

RM Risk Management

2.5 Roles and Responsibilities

This standard is issued under the authority of the Group Executive – Transmission and Sustainability & Risk. The roles and responsibilities are fully defined in the Enterprise Risk and Resilience Policy (32-86) for the oversight and management of risk and include the following role players:

• Eskom Board of Directors

• Group Chief Executive

• Group Executive assigned accountability for risk (Chief Risk Officer)

• Group/Divisional Executives

• Risk process experts (champions)

2.6 Process for Monitoring

The implementation of this standard will be monitored as part of a divisional self-assessment process and peer reviews as well as other assurance providers.

2.7 Related/Supporting Documents

Not applicable

Page 11: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 11 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

3. Standard

3.1 Integrated Risk Management Preamble

•••• Eskom promotes an organisational culture which values effective management of risk and resilience through capabilities and measures embedded within its operations, decision-making processes, and the development and implementation of strategy.

•••• Eskom's governance of risk and resilience is aligned with the principles as set out by the King Code on Corporate Governance, including the allocation of dedicated time at the Board Audit & Risk Committee to assist it in carrying out its responsibilities in relation to executing its oversight of risk and resilience management in the company.

•••• Eskom is committed to embedding risk management at all levels of the organization in order to identify the risks and manage them in a consistent and proactive way, prior to events occurring that might prevent us from achieving our objectives.

•••• Eskom will adopt a structured approach to risk management, using consistent approaches to the assessment, treatment, monitoring and reporting of all types of risk, at all levels and for all activities across the business.

•••• There will be one standard for the management of all types of risks that will be consistently applied across Eskom including its subsidiaries and projects.

•••• The Board Audit and Risk Committee will set Eskom’s risk appetite and risk tolerance levels.

•••• Risk Management is primarily the responsibility of line management, regarded as the first line of defence.

•••• The Eskom Executive Committee (Exco), through its Risk & Sustainability Sub-committee will monitor and review the organisation’s risk management plan, risk management system and risk performance and report this to the Board on a quarterly basis.

•••• The Audit and Risk Committee is responsible for providing oversight over the functioning of Combined Assurance activities as the third line of defence. Assurance is provided through Independent reviews on adequacy of risk, control and governance mechanisms, including compliance of Eskom-wide risk management practices and processes.

•••• One Integrated Risk Management System (CURA) is use for all business risk information.

•••• Integrated Risk Management is included in performance contracts of all Group and Divisional Executives.

•••• Eskom drives continued enhancement of its risk and resilience management practices, through an annually updated Eskom Holdings Risk & Resilience Management Plan which is prepared by management and approved by the Eskom Board.

Page 12: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 12 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

3.2 Institutionalising (Incorporating) Integrated R isk Management in the organisation

3.2.1 Foundational Principles

•••• Inculcating a risk culture at all levels of the or ganisation

A risk intelligent organisation will require a significant shift in culture. A clear set of risk traits have been identified that will clearly communicate the expectation of leadership and staff in relation to risk. These traits are:

- Think holistically about risk and uncertainty

- Take the right risks for reward (managing threats and capitalising on opportunities)

- Speak a common risk language

- Effectively use forward-thinking risk concepts and tools to make better decisions

- Create lasting value and ensure sustainability

- Continuously learn

•••• Effective change management and communication

Communication and change management are intended to address particular internal or external stakeholders to provide information regarding the current state of risk and its management and to solicit understanding and support for the step changes that are required to get Eskom to a risk intelligent state.

The implementation of changes must be supported by setting up communication processes and channels, organisational support structures and the means for ongoing monitoring and performance review.

•••• Implementing risk into foundations of business str ategy and planning

Organizations must develop, implement and continuously improve a framework whose purpose is to integrate the process for managing risk into the organization's overall governance, strategy and planning, management, reporting processes, policies, values and culture.

Eskom’s risk management process should be aligned with the organization's culture, processes, structures and strategy. Integration with Eskom’s strategy must be established as:

o risk management assists the organisation to achieve its objectives;

o objectives and criteria of a particular project, process or activity should be considered in the light of objectives of the organization as a whole; and

Page 13: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 13 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

o some organisations fail to recognize opportunities to achieve their strategic, project or business objectives, and this affects ongoing organizational commitment, credibility, trust and value.

•••• Integrated risk management systems

In accordance with best practice and in order to safeguard risk at a corporate level, a single risk management system based on ISO 31000 has been implemented. All other working systems utilised should be inputs to the Eskom single risk management system (E.g.: project specific tools for analysis)

•••• Integration with audit, compliance, governance, an d combined assurance initiatives

Cooperation with internal audit, compliance, governance and other related management governance processes is essential to enable a comprehensive compliance and assurance framework delivering combined assurance.

Eskom internal audit has the role of providing assurance that the risk standards are being complied with and will also monitor and annually evaluate the effectiveness of Risk Management.

3.2.2 Building blocks

•••• Governance and Reporting

Assurance of good corporate governance will be achieved through the regular measurement, reporting and communication of risk and resilience management performance. The Risk and Sustainability Manco will monitor and review the organisation’s risk management system and performance and report this to Exco on a regular basis.

A quarterly report will be submitted by Enterprise Risk and Resilience to the Board Audit and Risk Committee, a subcommittee of the Eskom Board.

Resolutions requested from governing bodies across the business shall be accompanied by a formal risk assessment in accordance with the Eskom risk methodology. The associated resource requirements shall form part of the approval requested.

•••• Policies and standards

The Enterprise Risk and Resilience policy defines Eskom’s integrated risk management principles formulated to promote the creation of a consistent and value adding process that assists the organisation to achieve its objectives.

Page 14: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 14 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

The Integrated risk management standard supports Eskom’s Enterprise Risk Management Policy and describes how Eskom will adopt a structured approach to risk management, using consistent approaches to the assessment and treatment of all types of risk initiatives, at all levels and for all activities in the company.

•••• Standardised Risk & Resilience methodology

Eskom will adopt a structured and consistent approach to risk & resilience management at all levels and for all activities in the organisation.

•••• Enterprise Risk & Resilience Management plans

Eskom, its Divisions and Functions will prepare and maintain suitable risk management plans.

Risk management plans will be reviewed annually as part of the business planning process and will be revised to reflect the actions required to be taken to further comply with these Standards.

In preparing and maintaining risk management plans, stakeholder analysis will be conducted in order to develop a communication plan for stakeholders. This will specify the risk management reporting that should take place in each case.

•••• National and International Networking, Collaborati on and Benchmarking

In order to achieve the end-state of a risk intelligent organisation, Enterprise Risk, at least annually, performs maturity assessments to evaluate progress. In addition, benchmarking of best practice to evaluate the organisation’s position with regard to its ability to reach and sustain world class status is also performed from time to time.

•••• Defined performance measures and maturity evaluati on

Holdings and Divisional level performance will be measured against approved risk management plans and key performance indicators that will be created as part of the annual performance management process and using the Risk Management Maturity Evaluation Process.

The focus is to provide assurance as to whether the Integrated Risk Management Framework and Standard as a whole is effective and is being implemented correctly.

•••• Approved Enterprise Risk Appetite & Tolerance

Risk appetite is the amount and type of risk an organization is prepared to pursue or take, and risk tolerance is the organisation’s readiness to bear the risk after risk treatment, in order to achieve its objectives.

Page 15: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 15 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

Risk appetite statements exist for Key Functional Areas including its respective tolerance levels. Key Performance Indicators with relevant Key Risk Indicators are defined to measure performance against the key functional areas and also act as early warning measures for Key Functional Areas.

Enterprise Risk is responsible to update appetite and tolerance levels annually for approval by Eskom Board and also give assurance to the Board that risks are managed within current approved appetite and tolerance levels.

•••• Feedback and Continuous Improvement

Effective and timely feedback is a critical component to ensure organisational effectiveness. An environment must be created where feedback is viewed as an opportunity for improvement, not just an opportunity to point out where someone has done something wrong.

3.3 Integrated Risk Management Process

The risk management process that will be followed in all cases is that detailed in ISO 31000 as shown in Figure 2 below. All steps in the process will be applied. Risk is defined as the “effect of uncertainty on objectives”.

Figure 2: Integrated Risk Management Process

Monitor and Review

Establishingthe Context

RiskIdentification

RiskAnalysis

RiskEvaluation

RiskTreatment

Communication and Consult

What do we need to take into account and what are

our objectives?

What might happen?

How, when, and why?

What this will mean

for our objectives?

Which risks need

treating and

priority for attention?

How should we best deal

with them?

Page 16: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 16 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

3.3.1 Communicate and Consult

The Integrated Risk Management (IRM) process will start and continually involve consultation and communication with relevant stakeholders. All risk assessments will be preceded with stakeholder analysis that defines relevant stakeholders, their objectives and communication needs. From this a communication plan will be developed. This communication plan can be a part of the treatment plan.

3.3.2 Establish the context

Before any risk management activity takes place and especially before risk assessment occurs, the external, internal and risk management contexts will be established. The external context includes, but is not limited to:

• the social and cultural, political, legal, regulatory, financial, technological, economic, natural and competitive environment, whether international, national, regional or local;

• key assumptions, drivers and trends that have an impact on the objectives of the organization;

• relationships with stakeholders, and • Shareholder requirements

The internal context includes, but is not limited to: • governance, organizational structure, roles and accountabilities; • policies, objectives, and the strategies that are in place to achieve them; • capabilities, understood in terms of resources and knowledge (e.g. capital, time, people,

processes, systems and technologies); • the relationships with and perceptions and values of internal stakeholders; • the organization's culture; • information systems, information flows and decision making processes (both formal and

informal); • standards, guidelines and models adopted by the organization; and • form and extent of contractual relationships.

The risk management context will include the definition of suitable risk criteria and a key element structure for the subsequent risk assessment. Part of defining risk criteria will be determining the level at which risk becomes acceptable or tolerable. This means that stating a targeted level of risk which is in line with the risk appetite and tolerance of the organisation is part of establishing risk criteria. The objectives and criteria of a particular project, process or activity should be considered in the light of objectives of the organization as a whole. This means that risk criteria can be defined for specific projects, processes and activities whilst also making use of the Eskom consequence and likelihood criteria.

Page 17: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 17 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

The most appropriate tools and methods for risk identification and analysis will be determined during this step in the ERM Process.

3.3.3 Identify the risk

This will always involve stakeholders i.e. the participants of a risk identification exercise should not be limited only to the members of the project, process or activity concerned.

Risk identification will always occur using a recognised system and by following the key element structure determined when the risk management context was established.

Risks will be described in terms of an event, changes in situation or circumstances and how these lead to main consequences (both positive and negative). Risks will not be described in terms of consequences only.

Causes and consequences shall be identified for each identified risk with existing controls aligned to each of the identified causes.

Risk owners and controls owners will be named individuals from line management and their names will be recorded in the Risk Management Information System.

As part of the continuous scanning of the environment the identification of emerging risks is becoming more and more important as this will sensitise decision makers on choosing the correct line of action.

3.3.4 Analyse the risk

This will generally occur using a qualitative system as specified in this standard using the Eskom Consequence and Likelihood criteria. However a quantitative system could be used where it is appropriate e.g. project management environment.

Risk analysis will be the means whereby we develop an understanding of a risk and its causes and consequences so that we can decide on the adequate enhancement of existing controls as well as appropriate risk treatment. Both existing controls and new treatment tasks will generally be aimed at the addressing the causes of a risk proactively. The risk will be rated, taking into account the adequacy of existing controls and their effectiveness.

Controls are measures that modify risk in order to enable the achievement of objectives.

Controls can modify risk by changing any source of uncertainty (e.g. by making it more or less likely that something will occur) or by changing the range of possible consequences and where they may occur.

Risk Control Effectiveness (RCE) will be estimated during risk analysis taking into account both the adequacy and effectiveness of controls. RCE will be a measure of the completeness, relevance

Page 18: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 18 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

and efficacy of the existing controls when compared with that which is reasonably achievable. RCE will be rated using the guide in Table 1. RCE will be estimated for each control taking into account both the adequacy and effectiveness of each control in light of the objectives of that particular control.

Table 1: Risk Control Effectiveness Guide

RCE Guide

Fully effective

Nothing more to be done except review and monitor the existing controls. Controls are well designed for the risk, are largely preventative and address the root causes and Management believes that they are effective and reliable at all times. Reactive controls only support preventative controls.

Mostly effective Most controls are designed correctly and are in place and effective. Some more work to be done to improve operating effectiveness or Management has doubts about operational effectiveness and reliability of the controls.

Mostly Ineffective

While the design of controls may be largely correct in that they treat most of the root causes of the risk, they are not currently operationally very effective. There may be an over-reliance on reactive controls, or Some of the controls do not seem correctly designed in that they do not treat root causes.

None Virtually no credible control. Management has no confidence that any degree of control is being achieved due to poor control design and/or very limited operational effectiveness.

Elaborating on existing controls, current practices included the creation of treatment tasks in an endeavour to enhance controls for controls that were not fully effective and others included control tasks to enhance the ineffective controls. After much debate regarding control tasks vs treatment tasks, the following practice will be adopted.

• All information relating to a mostly effective, mostly ineffective, and totally ineffective existing control will be captured for that control with the sole purpose to enhance the control. These include control tasks, control owners, start dates, due dates, task completion percentage, etc. that will be recorded in the Risk Management Information System.

• If any new task(s) is/are identified, not covered by the existing controls will be deemed treatment tasks and should be dealt with as such during risk assessments. This will be discussed in more detail when dealing with the treatment of risks.

Risk analysis can be undertaken with varying degrees of detail, depending on the risk, the purpose of the analysis, and the information, data and resources available. Analysis can be qualitative or quantitative, or a combination of these, depending on the circumstances.

Page 19: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Framework and Standard Unique Identifier: 32-391

Revision: 4

Page: 19 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

The risk rating will always be based on risk, taking into account existing controls and their adequacy and effectiveness. Eskom, within its risk management methodology will not use measures of “inherent risk”.

A consequence rating will be chosen from the Table 2 on the basis of the most likely impact on Eskom and its stakeholders choosing the most severe of the consequence types given.

A likelihood rating will be chosen from Table 3 on the basis of the corresponding likelihood that Eskom and its stakeholders could be affected at the chosen level of consequence.

Combining the outcomes from consequence and likelihood rating will allow risks to be plotted on the risk matrix shown on Figure 3.

Page 20: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Standard Unique Identifier: 32-391

Revision: 4

Page: 20 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

Table 2: Consequence Criteria

Financial Sustainability Operations Sustainable Asset Creation Environmental & Climate Change Sustainability Legal & Compliance Reputation Health and Safety Information Management

6

Net position between Revenue

and operational expenditure

(EBITDA = Revenue - Opex - PE)

> R3Bn

Impact:

Catastrophic impact (financial and

business operations) that

threatens the existence of Eskom

GWh lost:

>5000GWh (Unable to meet demand by

equivalent of a PS unit for a period of 3

months)

National load shedding

> six months.

National blackout:

Enormous impact on country from

image, economic, point of view.

Project Cost:

> 20%

Schedule deviate:

> 35% delay

Quality:

Catastrophic - Major non-

conformance that would result in

a chain reaction that has huge

negative impact on the plant.

Project outcomes effectively

unusable.

Community:

* Irreversible long term environmental harm

* Community outrage due to environmental harm in the area-

potential large-scale class action (legal). e.g. greenhouse gas

emissions, continued use of coal)

Regulation and Legal:

* Public inquiry by Government agency

* Environmental licence revoked

* Potential for significant legal sanctions against Eskom

* Stringent carbon budgets and taxes imposed

Physical changes to the Climate:

* Major generation and transmission infrastructure damage due to

severe climate events

* Inadequate water supply for power generation

Legal and Compliance:

* Major litigation or prosecution with

damages including costs in excess of

R100m

* Custodial sentence for Chief

Executive.

* Custodial sentence for multiple

company Executives.

* Closure of operations by authorities

across multiple sites / regions.

* Inability to meet suspensive

conditions in multiple loan agreement

Reputation:

* Sustained adverse international /

national press reporting over several

weeks

* Prolonged loss of shareholder/ client

confidence and community support

* Critical event that the organisation

would be forced to undergo significant

change

Fatalities:

Multiple Fatalities

Cyber-resiliency - Malicious damage to computer networks or systems resulting in

widespread prolonged national supply interruptions and the ongoing inability to safely

operate or restore supply to the country

Data confidentiality - Disclosure of sensitive and/or confidential data and information

could lead to ongoing community unrest, sabotage of operations, damage to Eskom's

credit rating and reputation(nationally and abroad) plus result in litigation

Critical System/Data Availability - Major loss of or unavailability of mission critical

systems and/or data throughout Eskom could severely impact Eskom's revenue,

profitability, license to operate, credit rating and reputation

Information/data governed as a corporate asset - Failure to fulfil Eskom's fiduciary

duties pertaining to the treatment of data/information as a corporate asset, could result

in investigations, liability and harm to Eskom's reputation

5

Net position between Revenue

and operational expenditure

Between R1Bn and R3Bn

Impact:

Severe financial loss and / or

impairment impacting financial

health and business operations

GWh lost:

500 – 5000GWh (Unable to meet

demand by equivalent of PS Unit for a

period of 1 month)

Regional blackout:

Lasting <60hrs

National load shedding:

Stage 2. Loss of critical supply to critical

customer for an extended period (deep

level mines, smelters etc.)

Project cost deviate:

> 15% and ≤ 20%

Schedule deviate:

> 25% and ≤ 35% delay

Quality:

Severe – Major non-conformance

that would results in a few chain

reactions, negatively impacting

project outcome.

Community:

* Prolonged environmental impact

* High-profile community concerns raised – requiring significant

rectification measures

Regulation and Legal:

* Government agency inquiry

* Environmental licences revoked and directives issued

* Significant financial penalties due to non -compliance with carbon

emission limits

Physical Changes to the Climate:

* Significant impact on infrastructure - long lead times for repairs

* Eskom's water allowance reduced due to inadequate supply of

water

Legal and Compliance:

* Major litigation or prosecution with

damages including costs between

R50m and R100m.

* Custodial sentence for a company

Executive.

* Closure of operations by authorities

at single sites / region.

* Inability to meet sus pensive

conditions in any loan agreement

Reputation:

* Significant event that would require

ongoing management and brings the

organisation into the national /

international spotlight

* Sustained adverse national press

reporting over several days

* Sustained impact on the reputation

of Eskom / Rotek / Roshcon

* Loss of Government trust

* Executive management restructure

Fatality:

Single fatality

Cyber-resiliency - Malicious damage to computer networks or systems resulting in

prolonged regional supply interruptions and the inability to safely operate or restore

supply to the region

Data confidentiality - The disclosure of confidential / sensitive data to unauthorised

employees could result in labour unrest in specific regions

Critical System/Data Availability - Major loss of or unavailability of mission critical

systems and/or data throughout an Eskom region could severely impact on a region's

revenue and profitability

Information/data governed as a corporate asset - Governance structures to be aligned

across divisions in all regions ensuring protection and enhancement of data

Data integrity - Incorrect decisions based on corrupt regional data, resulting in regional

inefficiencies

4

Net position between Revenue

and operational expenditure

Between R100m and R1Bn

Impact:

Significant financial loss and / or

impairment impacting financial

health and business operations

GWh lost:

100 – 500GWh (Unable to meet demand

by equivalent of PS Unit for a period of 1

month)

Regional blackout:

Lasting <6hrs.

National load shedding:

Stage 1. Loss of supply to major Centre

or customer for >12 hrs.

Project cost deviate:

> 10% and ≤ 15%

Schedule deviate:

> 15% and ≤ 25% delay

Quality:

Substantial - Major non-

conformance resulting in

scrapping of product. Product

that is not fit for the purpose.

Community:

* Measurable environmental harm – medium term recovery

* High potential for complaints from stakeholders and community

Regulation and Legal:

* Environmental directives issued by authorities

* Carbon budgets imposed with grace period for compliance (5

years)

Physical changes to the Climate:

Significant climate events - plant unavailability or impact on coal

supply (e.g. flooding) or unavailability of water

Legal and Compliance:

* Litigation or prosecution with

damages including costs between

R10m and R50m.

* Major breach of regulation with

punitive fine.

* Significant litigation involving many

weeks of senior management time.

* Legal / Regulatory directives issued

by authorities with < 6 month

compliance notice period

Reputation:

* Major event that causes adverse

national media reporting – over several

days

* Minister raises concerns

Section 24 injury

Multiple Sect. 24 injured,

irreversible disability or

impairment cases due to

single incident

Cyber-resiliency

Malicious attempts to damage or disrupt computer networks or systems, could disrupt

core operations in other divisions

Data confidentiality

Confidential / sensitive data in a division could be leaked to unauthorised employees

Information/data governed as a corporate asset

Divisional structures to be aligned across divisions ensuring protection and enhancement

of data

Data integrity

Incorrect decisions based on corrupt data from divisional sources, resulting in

inefficiencies

Data availability

Interdependency of data across divisions compromised

3

Net position between Revenue

and operational expenditure

Between R50m and R100m

Impact:

Moderate financial loss and / or

impairment impacting financial

health and business operations

GWh lost:

10 – 100GWh (based on 1 month of up

to 100 MW partial load loss)

Local loss of supply:

Effecting >10,000 customers (<50MW)

for >12hrs.

Project cost deviate:

> 5% and ≤ 10%

Schedule deviate:

> 10% and ≤ 15% delay

Quality:

Significant - Standard

requirements not met and rework

needed. Significant elements of

scope or functionality are

affected.

Community:

Medium term recovery, immaterial effect on environment /

community

Regulation and Legal:

* Required to inform Government agency, (e.g.: noise, dust)

* Carbon emission limits imposed but not linked to penalties

Physical changes to the Climate:

Minor climate events that result in partial unavailability of plant

(few hours as opposed to months - e.g. flash floods)

Legal and Compliance:

* Litigation or prosecution with

damages including costs less than

R10m.

* Breach of regulation with

investigation or report to authority

with prosecution and/or moderate fine

possible.

* Legal / Regulatory directives issued

by authorities with > 6 month

compliance notice period

Reputation:

* Serious event that can be readily

managed but management effort is still

required to minimise impact locally

* Adverse local media reporting

* Disciplinary action likely

Lost time injury:

Multiple Lost time injured

and/or extensive injuries or

irreversible disability or

impairment to one person

(Sect. 24)

Cyber-resiliency - Malicious attempts to damage or disrupt computer networks or

systems, could disrupt core operations performed by BUs/departments within a division

Data confidentiality - Confidential / sensitive data in a division could be leaked to

unauthorised employees within a division

Information/data governed as a corporate asset - BU structures to be aligned across

different BUs ensuring protection and enhancement of data

Data integrity - Incorrect decisions based on corrupt data from BU sources, resulting in

inefficiencies

Data availability - Interdependency of data across BUs compromised

2

Net position between Revenue

and operational expenditure

Between R10m and R50m

Impact:

Minor financial loss and / or

impairment impacting financial

health and business operations

GWh lost:

1 – 10GWh (based on 1 month of 10

MW partial load loss)

Local loss of supply:

Loss of supply to large customer or

affecting >10,000 customers for <4hrs.

Loss of large load Centre for <2 hours

(typically between 0.1 and1 system

minutes)

Project cost deviate:

> 2% and ≤ 5%

Schedule deviate:

> 5% and ≤ 10% delay

Quality:

Moderate - Requirements not met

but requires concession. Failure to

include certain elements promised

to stakeholders.

Community:

Short term transient environmental or community impact- some

clean-up costs

Regulation and Legal:

Carbon emission limits imposed but not linked to penalties

Physical changes to the Climate:

Climate events have minor impact on infrastructure performance

Legal and Compliance:

Minor legal issues, non-compliances

and breaches of regulation.

Reputation:

* Event that site management can

readily manage internally

* No press reporting or external

interest

* Disciplinary action may be taken

Medical Treatment:

Medical treatment cases or

single lost time injury

Cyber-resiliency - Malicious attempts to damage or disrupt computer networks or

systems could disrupt core operations performed by departments/BU

Data confidentiality - Confidential / sensitive data in a BU could be leaked to

unauthorised employees within a BU

Information/data governed as a corporate asset - BU structures to be aligned across

different departments ensuring protection and enhancement of data

Data integrity - Incorrect decisions based on corrupt data from departmental sources,

resulting in inefficiencies

Data availability - Interdependency of data across departments compromised

1

Net position between Revenue

and operational expenditure

Between R1m and R10m

Impact:

Insignificant – no apparent

disruption

GWh lost:

<1 GWh (based on 1 month of 1 MW

partial load loss)

Local loss of supply:

Loss of supply to some customers

(normal interruption) effects 3,000

customers for <4hrs. <0.1 System

minute incident

Project cost deviate:

≤ 2%

Schedule deviate:

≤ 5% delay

Quality:

Minor - Slight deviation from

specified requirements. Has no

overall impact on usability /

standards.

Community:

Negligible impact on the environment, little to no ecological effect

and no measurable impact on human health

Physical changes to the Climate:

Minor climate events that do not impact on infrastructure

performance

Legal and Compliance:

Very minor breaches.

Reputation:

* Entirely an internal issue

* Attention is confined to site

First Aid:

First aid treatment or

minor injuries requiring no

treatment

Cyber-resiliency - Malicious attempts to damage or disrupt computer networks or

systems that could disrupt core operations performed by specific departments

Data confidentiality - Confidential / sensitive data in a department could be leaked to

unauthorised employees within a department

Information/data governed as a corporate asset - Departmental structures to be aligned

across systems and data bases ensuring protection and enhancement of data

Data integrity - Incorrect decisions based on corrupt data from departmental sources,

resulting in departmental inefficiencies

Data availability - Interdependency of data across department specific systems

compromised

Page 21: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Standard Unique Identifier: 32-391

Revision: 4

Page: 21 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

Table 3: Likelihood Criteria

Category Criteria

E

• Could occur within “days to weeks”, or

• Impact is imminent, or

• ≥ 90% probability

D

• Could occur within “weeks to months”, or

• Balance of probability will occur, or

• ≥ 70% and < 90% probability

C

• Could occur within “months to years”, or

• May occur shortly but a distinct probability it won’t, or

• ≥ 20% and < 70% probability

B

• Could occur in “years to decades”, or

• May occur but not anticipated, or

• ≥ 5% and < 20% probability

A • More than a “100 year event”

• Exceptionally unlikely, even in the long term future

• < 5% probability

Figure 3: Risk Matrix

Page 22: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Standard Unique Identifier: 32-391

Revision: 4

Page: 22 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

Potential Exposure (PE) will be estimated for each risk. This will represent the total plausible maximum impact on Eskom arising from a risk without regard to controls. It will be expressed in terms of a consequence rating as given on the Consequence Criteria Table 2. The purposes of this measure are:

• Assisting / alerting Eskom’s Enterprise Resilience Department to ensure effective disaster response strategies.

• Assisting Audit & Forensic Department to align their audit plans to ensure that significant risks are always included. Risks with high consequences as a result of not taking any existing controls into account will focus their attention on the existing controls to determine their effectiveness and adequacy.

3.3.5 Evaluate the risk

The purpose of risk evaluation is to assist in making decisions, based on the outcomes of risk analysis, about which risks need treatment and the priority for treatment implementation.

This will be conducted by way of:

• Comparison of the risk rating with any risk criteria i.e. target level of risk developed as part of establishing the context and Eskom’s risk appetite and tolerance;

• Cost benefit analysis to determine if risk treatment is justifiable. Cost benefit analysis will be both qualitative and quantitative depending on the circumstances. Decisions should take account of the need to consider carefully rare but severe risks that may warrant risk treatment actions that are not justifiable on strictly economic grounds. The rigour of the cost benefit analysis will match the level of risk.

The result of risk evaluation is a decision on the most appropriate way to treat the risk. The options are as follows:

• Change the likelihood (including risk avoidance, taking more risk or reducing it) to reach the target level of risk in the time limit prescribed by the “Priority for attention” table shown on Table 6.

• Change the consequence including risk sharing to reach the target level of risk in the time limit prescribed by the “Priority for attention” table shown on Table 6.

• Tolerate the risk until a certain condition is reached or indefinitely.

In some cases the time limit suggested by the “Priority for attention” table (shown on Table 6) will be inappropriate, in such cases an explicit decision must be made to continue to tolerate the risk until the treatment plan is authorised. The “Priority for attention” table stipulates the level at which such a decision may be taken.

Page 23: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Standard Unique Identifier: 32-391

Revision: 4

Page: 23 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

Table 6: Priority for Attention

Priority Timing of approval of a treatment

plan Authority for continued toleration

of identified risk level

I Short term. Normally within 1

month. Group and Divisional Executives,

Chief Executive and Board

II Medium term. Normally within 3

months.

Group and Divisional Executives, Senior General Managers and

General Managers

III Normally within 1 year Senior General Managers, General

Managers and Managers

IV Ongoing control as part of a

management system. All staff

3.3.6 Treat the risk

As stated earlier in the section dealing with control and control tasks the following practice will apply for the treatment of risks. Existing controls and their respective control tasks are handled under the section 3.3.4 - analysis of the risk. All NEW task(s) identified, not covered by the existing controls to further manage a risk will be deemed treatment tasks and should be dealt with as such during risk assessments. The information will include treatment tasks, treatment task owners, start dates, due dates, task completion percentage, etc. that will be recorded in the Risk Management Information System.

Risk treatment plans are defined as a combination of existing controls and its respective tasks as well all new treatment tasks. Both mentioned actions have the sole purpose to modify the risk to levels that are acceptable and falls within Eskom’s defined appetite and tolerance levels. This is depicted in the figure 4 below.

Figure 4: Treatment Plan

All existing controls including control tasks to enhance existing

controls

All new treatment tasks

=Treatment Plan

Page 24: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Standard Unique Identifier: 32-391

Revision: 4

Page: 24 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

3.3.7 Monitor and Review

Risks will continually be subjected to formal review by risk owners. This review will involve the monitoring of actions, control effectiveness and changes to the external or internal context, including changes to Eskom’s or stakeholder’s objectives and perceptions. Where appropriate, leading key risk indicators should be established to provide situational awareness for early warning when a threshold is reached or to raise a flag of change in the external risk context. This situational awareness should adequately support emergency response and recovery to high risk conditions, including identified priorities that require business continuity and disaster management.

Controls and treatment tasks will be reviewed periodically by respective risk owners to determine if they are adequate, effective and indeed progressing. The primary means of control assurance will be through the use of control self-assessment by control owners as the “first line of defence”. As part of the second line of defence, actions will also include self-assessments performed by divisional risk managers and peer reviews conducted by Enterprise Risk Department. The third line of defence provides independent assurance by internal and external audit functions.

Some controls require real-time situational awareness and the control owner in conjunction with the risk owner shall determine the appropriate monitoring systems.

To ensure that risks are continuously monitored and controls and treatment assessed continuously regarding their effectiveness, a decision was made to have risks active at all times, irrespective of all controls and treatments being completed and do away with risk statuses that prevented continuous monitoring. The risk statuses available are:

• Draft - A risk is classified as “draft’ when the risk assessment process has not yet been completed (a risk does not comply fully with the set quality criteria to be followed). A risk with this status must be changed to active within 3 month, or deleted after 3 months.

• Active - A risk is classified as “active” when all the steps involved in the risk assessment process have been completed and the quality criteria met. The risk assessment process includes risk identification, risk analysis and risk evaluation.

• Retired - A risk is classified as “retired” when its context has changed in a manner that renders the risk obsolete. This can arise in different circumstances such as the objective that gave rise to the risk changed or was removed.

. Quarterly reports are produced by divisions to sensitise the organisation of potential changes in the environment, emerging risks, feedback on their specific risks and progress made in managing them as well as progression with respect to their risk management plans.

Risk management is included in the performance contracts of all Group Executives and is assessed quarterly as per the Eskom performance management cycle.

Page 25: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Standard Unique Identifier: 32-391

Revision: 4

Page: 25 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

3.4 Integrated Risk Management Standard Requirement s

The standard imposes mandatory requirements on all divisions, functions and projects.

3.4.1 Requirement 1: Risks of Divisional Business a nd Operational Plans

A risk assessment will be conducted as part of the development of all business and operational plans in Eskom. These risk assessments will be used to identify significant risks that could affect the achievement of the plan’s objectives i.e. the risk of implementation of the business/operational plan.

Risk treatment plans will be developed and implemented to ensure that plan objectives and budgets are met. There may be circumstances where the level of risk and/or the cost of treatment is unacceptable and leads to a change in business plan objectives.

3.4.2 Requirement 2: Divisional risk reviews

Divisions will conduct formal reviews of all risks on a quarterly basis. These reviews will involve identifying any new or emerging risks that might affect the achievement of business and operational plan objectives.

3.4.3 Requirement 3: Risks of significant decisions and/or changes

Before any significant change, event or decision occurs within Eskom or when a significant external change or event is detected, a risk assessment will be conducted to determine the appropriate risk treatment. All submissions to governance bodies that require decisions to be made will be accompanied by a risk assessment. The risk treatment plan shall be approved as part of the decision and minuted as part of the resolution. This includes business-, operational- and project plans.

3.4.4 Requirement 4: Assurance of Critical Controls

All controls will be allocated to named control owners for checking and assurance. Critical controls are those whose effectiveness will contribute materially to the achievement of the Eskom business plan objectives and budgets or are required for contractual or regulatory compliance or to modify risks with a high Potential Exposure. Control tasks shall be identified and monitored for controls that are not fully effective.

3.4.5 Requirement 5: Learning from Successes and Fa ilures

After any event or change that has a material impact on Eskom or its customers or stakeholders’ objectives and budgets or to ensure legal or contractual compliance, a suitable root cause analysis, which identifies not only direct causes, but also latent and root causes, will be conducted to learn lessons from both successes and failures.

Page 26: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Standard Unique Identifier: 32-391

Revision: 4

Page: 26 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

3.4.6 Requirement 6: Risk Management Planning

Eskom will prepare and maintain an appropriate Risk Management Plan. The Divisions will adopt this plan, expand upon it as appropriate to form a Divisional Risk Plan, and implement it throughout the business. Each project will also prepare a risk management plan and this will be updated for each phase.

Risk Management Plans will be reviewed annually as part of the business planning process and will be revised to reflect the actions required to be taken to further comply with this standard and any subsequent direction provided by the Enterprise Risk & Resilience Department.

3.4.7 Requirement 7: Recording Risk Management

The outputs from each stage of the risk management process will be recorded appropriately on the Risk Management Information System. The output from setting the context will also be recorded on the Risk Information Management System. The Risk Management Information System is the only risk repository to be used for all risk management reporting purposes.

3.4.8 Requirement 8: Monitoring and Reporting Risk Management

The Eskom Board Audit and Risk Committee (ARC) will review each quarter:

• Emerging risks • Enterprise risks; • Business risks as required; • Risks with Potential Exposure level “6” This will be done utilising quarterly Divisional risk reports, the Risk Management Information System as well as information obtained via the environmental scanning process.

3.4.9 Requirement 9: Integrated Risk Management and Projects

Integrated Risk Management shall be implemented on all projects, irrespective of value. On projects where quantitative risk analysis (QRA) is implemented, this shall be done as required by the Eskom Standard (240-108940660, Implementation of Quantitative Uncertainty and Risk Analysis on Eskom Projects) which is supported by the Guideline 265-12 (Eskom Quantitative Risk Analysis Guideline). A high level synopsis of the QRA technique is provided in Appendix 1. 3.4.10 Requirement 10: Business Continuity Manageme nt The Eskom Business Continuity Management standard (240-79747329) defines the types of risks for which a business continuity plan is required. Whilst developing a business continuity plan may be prudent for high-consequence risks, it is a requirement that such a plan is in place for high-consequence risks where a time-critical response is required (as defined in the standard).

Page 27: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Standard Unique Identifier: 32-391

Revision: 4

Page: 27 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

The Eskom Business Continuity Standard requires a risk assessment to be undertaken as part of the Business Impact Analysis - this to determine the potential consequence of a disruption to a process or operation that is critical to the business or its reputation. This stage of the business continuity process does not consider the likelihood of an incident, but the impact should controls fail. It focusses on disruptions to:

• Eskom buildings (office facilities, stores etc)

• Production assets (generators, substations, lines etc)

• Systems (operations and information technologies)

• People (leadership, staff and contractors), and

• Third-party elements of the supply chain e.g. primary energy suppliers, customers etc.)

The Business Impact Analysis does not consider the specific cause of such a disruption - this in order to ensure that a robust business continuity plan is in place, rather one that only addresses specific scenarios. The Eskom Business Continuity Standard also requires a full risk assessment to be undertaken to determine the possible causes of a disruption and the ability to respond to and recover from this. The focus here is on the controls that must be in place (and monitored), as well as the treatment actions required to address the prevention of an incident as well as the readiness and ability to respond effectively and recover from it.

3.4.11 Requirement 11: Disaster Management

Eskom, as an organ of state is required to comply with the requirements of the Disaster Management Act (Act No.57 of 2002), to provide an integrated Eskom Disaster Management Plan based on functional role and responsibilities for major electricity related incidents. The Eskom Disaster Management Standard (240-86786675) prescribes the requirements of the Act, supported by the National Disaster Management Framework. Two key performance areas are directly related to the IRM Standard; namely Disaster Risk Assessment and Disaster Risk Reduction. In the guideline developed for the Eskom Disaster Management working groups (240-121405847), reference is made to the risk process discussed in the IRM Standard (32-391) to be adopted and for the risks to be uploaded on CURA. The business objectives related to disaster management that inform the Disaster Risk Assessment and Disaster Risk Reduction are based on the following categories: • Prevention of incident or disaster • Response & recovery to an incident or disaster • Business continuity requirements during an incident or disaster • Effective coordination between Eskom and external response partners and stakeholders.

Page 28: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Standard Unique Identifier: 32-391

Revision: 4

Page: 28 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

The business risk may be augmented by quantified risk assessments related to the specific hazard and geographic impacts (e.g. for weather-related incidents, climate change impacts). Appendix 2 provides an overview of techniques for quantitative elements of the Disaster Risk Assessment that informs the controls and treatment (Disaster Risk Reduction).

4. Acceptance

This document has been seen and accepted by:

Division Divisional Risk Responsibility

Generation Gloria Mogashoa

Transmission Leburu Mahumapelo

Distribution Eileen Bhoodram

Customer Services Mohato Mokhobo

Group Technology Esther Wallace

Group Capital Rolland Ngugama

Group Information Technology Zanele Sihlali

Primary Energy Division Martinus Biemond

Enterprise Risk Lwazi Mbele

Rotek Thandeka Sibisi

Sustainability Richard Nkuna

Human Resources Charles Gradwell

Corporate Affairs Gugu Khumalo

Security Rion Dreyer

Commercial Mthokozisi Zondo

Finance Reneta Hiss

Office of the Chief Executive Malebitsi Mgodi

Page 29: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Standard Unique Identifier: 32-391

Revision: 4

Page: 29 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

5. Revisions

Date Rev. Compiler Remarks

Dec 2008 1 GN Law New document

Feb 2009 2 CH Palm • Superseded previous Rev.0

• Consequence Table was replaced and formatting corrected

March 2014 3 L Mbele • Superseded previous version (Rev 1)

• Framework was removed.

• Document architecture was removed.

• Consequence Table was adjusted.

• Control Effectiveness Table was added.

• Risk Rigour Guide was removed.

• Risk Category Table was removed.

• Potential Exposure Table was removed.

• Treatment options consolidated.

March 2017 4 G Rohde • Superseded previous version (Rev 2)

• Eskom Holdings SOC Limited Enterprise Risk & Resilience Framework now incorporated in this document

• Updated consequence table included

• Section on Institutionalising (Incorporating) IRM in the organisation was added which included risk intelligent organisational traits

• IRM Standard Requirements was updated

• Part of the requirements now include a section on IRM and Projects

6. Development Team

The following people were involved in the development of this document:

• Gunter Rohde

7. Acknowledgements

• Keith Rodseth

• Malcolm van Harte

• Sajedah Mahomed

Page 30: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Standard Unique Identifier: 32-391

Revision: 4

Page: 30 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

Appendix 1 - Quantitative Risk Analysis (QRA)

"Risk is present in all projects, whatever their nature. Some projects are more 'risky' than others..."

(PRAM Guide, Association of Project Managers 1997, ISBN 0 9531590 0 0)

Seeing that projects are risky it is often necessary for the project managers to quantify the project

risks and this helps determine whether the project is a viable proposition in terms of time and cost.

The duration and cost of the tasks in a project are subject to variation and it is the combination of

these variations that add to the risks in a project.

In terms of cost and schedule, the expected outcome that is communicated to stakeholders is often

based on the summation of the single point estimates for each activity in a work breakdown

structure. Single-point estimates are referred to as “deterministic” values and assume that there is

no possibility for variance and that the projected cost/date will be achieved with 100% certainty.

They are also generally optimistic, leading to final project duration and spends that are significantly

above expectations.

Quantitative risk analysis (QRA) quantifies these risks by allowing the Project Manager to assign

durations and costs as a distribution rather than a single value. Using this data, specialised

software can simulate the project many times. Each simulation (or iteration) represents one way in

which the project could run. The combination of several iterations allows statistically significant

results to be generated. From these results questions such as "What chance do I have of finishing

the project on time and in budget?" can be answered.

QRA, in Eskom, is based on the Monte Carlo statistical sampling technique. It uses a proprietary

software tool to analyse the effect of uncertainty, identified risks and related treatment plans on

both project schedules and project cost plans. Such models are called probabilistic risk models

and enable a deeper understanding than can be achieved by qualitative techniques alone.

The results are used to better inform project decision-makers and stakeholders about the effect of

uncertainty and risks on project durations and costs. Better quantification of the benefits that can

be realised from different treatment options is also provided.

The following are some of the benefits of performing ORA:

• manage stakeholder expectations by enabling realistic project durations / finish dates and

budgets to be set, informed by the confidence levels for schedule task durations / finish dates

and costs,

• determine a budget for proactively managing risks,

• inform decisions about where to get the best return on money spent on risk management,

Page 31: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Standard Unique Identifier: 32-391

Revision: 4

Page: 31 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

• develop a defensible contingency for the project execution phase,

• review the trend of contingency utilization during the project execution phase (also known as

'contingency burn-down rate'),

• provide confidence levels for the forecast duration / finish dates and cost estimates at

completion where these may be derived using earned value management indices,

• support requests for changes to release approval budgets

• model revenue streams to give a complete investment / benefit scenario for each business

case,

• use schedule logic in the analysis to prioritise treatment actions as a more effective method

than using a qualitative assessment only of schedule delay.

Page 32: Standard Integrated Risk Management 4 32 - zitholele … · Integrated Risk Management Framework and Standard Unique Identifier: 32-391 Revision: 4 Page: 7 of 32 CONTROLLED DISCLOSURE

Integrated Risk Management Standard Unique Identifier: 32-391

Revision: 4

Page: 32 of 32

CONTROLLED DISCLOSURE

When downloaded from the document management system, this document is uncontrolled and the responsibility rests with the user to ensure it is in line with the authorised version on the system.

No part of this document may be reproduced without the expressed consent of the copyright holder, Eskom Holdings SOC Limited, Reg No 2002/015527/06.

Hard copy printed on: 18 July 2017

Appendix 2 – Disaster Risk Assessment

The basis for Disaster Management lies in understanding the hazards, exposure and vulnerabilities

of people and Eskom assets to those hazards. Disaster Risk Assessment is defined in the Disaster

Management Act (Act No 57 of 2002), as amended, as a methodology to determine the nature and

extent of risk by analysing potential hazards and evaluating existing conditions of vulnerability that

together could potentially harm exposed people, property, services, livelihoods and the

environment on which they depend.

The Disaster Risk Assessment should identify causes, controls and assess the adequacy and

effectiveness of existing controls for effective disaster risk management and risk reduction

planning.

The definition of disaster risk is depicted in the equation below for a defined boundary:

���������� = �� ��� �������������

��������

Hazard can be measured in terms of an index comprising of probability, magnitude, frequency or

predictability of a natural, technological or environmental hazard.

Vulnerability can be measured in terms of an index comprising of susceptibility to the hazard

relative to physical, social, economic and environmental factors or processes.

Capacity can be measured in terms of an index comprising of institutional/management,

programme, physical/resources, people & competencies or support network capacities available to

reduce the risk, or to support with disaster preparedness, response and recovery.

The results of the hazard analysis, vulnerability assessment and coping capacity assessment are

mapped geo-spatially (on a geographical information system) to indicate the areas exposed and

vulnerable to the hazard to inform risk reduction strategies.

With regards to natural hazards, the ability to prevent or reduce the hazard from occurring is

minimal; hence efforts should be focused on reducing the vulnerabilities and improving coping

capacities. This is regarded as the resilience index in terms of disaster management for which

strategies are developed for risk reduction.

Disaster Risk Reduction programmes and plans (Risk Treatment plans in Eskom IRM standard)

must be budgeted for and included in the Eskom Corporate Plan and Divisional Plans.