Standardizing Transportation Project Submittals to DNR
TeamJim Doperalski WDNRMike Halsted WDNRJanet Smith WisDOTTroy Stapelmann WisDOT
Standard Submittal Cover Letter
Goal of Submittal Cover Letter
• Improve interagency communication
• Standardize submittal content
• Establish project review expectations
• Ensure project timelines are met
Used for ALL DOT projects under Cooperative Agreement, including local roads, that need DNR review
When should this be used?
Completed by : Anyone in need of DNR reviewIncluding:
1. REC/SWEC2. PDS 3. Planning4. Consultants5. Municipalities 6. (other)
Who should use this and who should submit it?
Submitted to DNR Liaison by:
1. REC (or assigns)2. Consultant Representing DOT3. Local Program4. Municipality (or assigns)
DNR acknowledges submittal via e-mail or phone
DNR / DOT PROJECT REVIEW State of Wisconsin Department of Natural Resources (DNR) and Department of Transportation (WisDOT) DNR0002 7/2012
DNR Internet: http://dnr.wi.gov/ WisDOT Internet: http://www.dot.wisconsin.gov/
Dnr Liaison Dnr Region Dnr Address Dnr City, State Zip
Wisconsin Department of Transportation Division of Transportation Systems Development Region Address Region City, State, Zip
Inform WisDOT Regional Environmental Coordinator, if more than 45 days is needed.
Design Project ID
Project Highway
Review Request Date (m/d/yy)
Construction Project ID
Estimated Project Cost (range) to Construction Year
Project Name
Project Limits
County
Project On Tribal Land
Yes No Contact Name (first, mi, last)
Contact (Area Code) Phone Number
Section of Roadway Being Evaluated
Type of Review Requested
Initial Review Final Concurrence Scope Change
Other:
Document Type Environmental Assessment (EA) Environmental Report (ER) Programmatic Env Report (pER)
WisDOT Project Classification Bridge Rehabilitation Bridge Replacement Expansion Pavement Replacement Preventive Maintenance SHRM (state hwy rehab/maint) Recondition Reconstruction Resurface Safety
Other:
Work Involved Beam Guard Replacement Borrow and/or Waste Site Required Channel Change/Stream Relocation Clearing and Grubbing Culvert Replacement or Extensions Dredging Grading Fill Outside Toe of Slope Intersection Improvement Right of Way Acquisition Shoulder Work Storm Sewer
Other:
Storm Water Management (check all that apply) Trans 401 post construction requirements NPDES MS4/Urbanized Area TMDL Implementation Area
DNR / DOT PROJECT REVIEW State of Wisconsin Department of Natural Resources (DNR) and Department of Transportation (WisDOT) DNR0002 7/2012
DNR Internet: http://dnr.wi.gov/ WisDOT Internet: http://www.dot.wisconsin.gov/
Dnr Liaison Dnr Region Dnr Address Dnr City, State Zip http://dnr.wi.gov/org/es/science/TransportationLiaisonStaff.pdf http://dnr.wi.gov/contact/ssbyregion.html
Wisconsin Department of Transportation Division of Transportation Systems Development Region Address Region City, State, Zip HTTP://WWW.DOT.STATE.WI.US/ABOUT/LOCATE/DTD.HTM
Inform WisDOT Regional Environmental Coordinator, if more than 45 days is needed.
Design Project ID
XXXX-XX-XX Project Highway
STH XX Review Request Date (m/d/yy)
MONTH DAY, YEAR Construction Project ID
XXXX-XX-XX
Estimated Project Cost (range)
XXX,XXX to X,XXX,XXX Construction Year
YEAR
Project Name
AS DESCRIBED IN FIIPS/CDR
Project Limits
FROM CTH X TO XXXX ROAD
County
COUNTY
Project On Tribal Land
Yes No Contact Name (first, mi, last)
JANE DOE
Contact (Area Code) Phone Number
XXX-XXX-XXXX
Section of Roadway Being Evaluated
Type of Review Requested
Initial Review (PREVIOUSLY CALLED INITIAL CONCURRENCE/COMMENTS) Final Concurrence Scope Change(ATTACH PREVIOUS DNR LETTER)
Other:
Document Type Environmental Assessment (EA) Environmental Report (ER) Programmatic Environmental Report (pER)
WisDOT Project Classification Bridge Rehabilitation Bridge Replacement Expansion Pavement Replacement Preventive Maintenance SHRM (state hwy rehab/maint) Recondition Reconstruction Resurface Safety
Other:
Work Involved Beam Guard Replacement Borrow and/or Waste Site Required Channel Change/Stream Relocation Clearing and Grubbing Culvert Replacement or Extensions Dredging Grading Fill Outside Toe of Slope Intersection Improvement Right of Way Acquisition Shoulder Work Storm Sewer
Other:
Storm Water Management (check all that apply) Trans 401 post construction requirements NPDES MS4/Urbanized Area TMDL Implementation Area
For more information and directions, please see the back of this form.
WisDOT Project Classification Bridge Rehabilitation: FDM 3-5-2 Bridge Replacement: FDM 3-5-2 Expansion: FDM 3-5-2 Pavement Replacement: FDM 3-5-2 Preventive Maintenance (PM): FDM 3-1-5 SHRM (State Hwy Rehab/Maint): Maint Manual 13.08 Recondition: FDM 3-5-2 Reconstruction: FDM 3-5-2 Resurface: FDM 3-5-2 Safety (HSIP): PMM 4-1-10
See WisDOT region storm water/erosion control engineer.
Page 2 Project Description and Reason for Project: (Include copy of Concept Definition Report and preliminary plans indicating location and nature of work. List contingency construction year if applicable.)
This Wisconsin Department of Transportation, NW Region project involves routine maintenance for structure B-61-0054 (on State Highway 93 over the Trempealeau River), to be completed by a let construction contract (tied with state project 7130-01-70). [See attached project location map -Exhibit A.] The existing structure was constructed in 1977, on former County Highway A. It is not classified as structurally deficient or functionally obsolete. Routine maintenance of the structure is needed to correct problems that if left untreated will reduce the overall lifespan of the structure. The existing deck is smooth (little surface friction), with spalls and cracks. The concrete girder ends are cracked with rust staining. Both joints are leaking. Bearings are rust coated. The drainage inlets are low and present a traffic hazard.
The proposed project will address the maintenance concerns and provide a better driving surface, increasing safety for the traveling public. State Highway 93 is a long truck route, making it a critical link for the local and statewide economy. The project length is restricted to the structure and approaches (approximately 350 feet). The proposed work includes a concrete deck overlay, joint replacements, bearing replacements and girder repair (limited to girders at the abutments). [See record drawing -Exhibit B.] The approaches will be evaluated for concrete approach slabs. There will be no change to the waterway. Work under the structure is limited to at the abutments. There is no work proposed at any of the piers. The existing State Highway 93 cross-section will be maintained [see attached typical sections-Exhibit C]. Construction will either be staged under traffic or with traffic detoured onto County Road A and State Highway 95.
No impacts to wetlands are expected. There is no proposed fill, other than very minor blending of the shoulder material to match the minimally increased profile (approximately 1-inch) after the concrete deck overlay. Some minor roadway excavation at the abutments may be necessary to perform repairs. Best management practices will be required for protecting Trempealeau River for before, during & after construction. If wetlands are impacted it will be limited to temporary loss.