16
STANDING COMMITTEE ON APPROPRIATIONS STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs on the Briefing by Department of Water Affairs on the management of the Internal Construction management of the Internal Construction Unit Unit . .

STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

Embed Size (px)

Citation preview

Page 1: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

STANDING COMMITTEE ON APPROPRIATIONS STANDING COMMITTEE ON APPROPRIATIONS

Presentation by

Zandile MatheDeputy Director General: NWRI

11 February 2014

1

Briefing by Department of Water Affairs on the Briefing by Department of Water Affairs on the

management of the Internal Construction Unitmanagement of the Internal Construction Unit. .

Page 2: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

CONTENTS

1. Purpose2. Background3. Progress

2

Page 3: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

3

Briefing by Department of Water Affairs on the management

of the Internal Construction Unit.

PURPOSE

Page 4: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

4

Page 5: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

5

Page 6: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

6

Page 7: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

Overview: branch structure

7

Page 8: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

Construction Management Unit

8

Construction Management:

The purpose of the Construction management is to construct new water resources infrastructure and rehabilitate existing infrastructure to meet social water needs and to facilitate economic growth and development.

DIRECTORATE PURPOSE

Construction Support Is responsible for the construction of new water resources infrastructure . They also supply administrative, Human Resources, Financial; Human Relations support and Safety and Security for the 5 Construction Units

Construction Equipment They manufacture and refurbish mechanical equipment. It also ensures the procurement, operation, maintenance, rebuilding and disposal of construction equipment

Page 9: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

9

Page 10: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

GovernanceChallenges

• Construction unit would execute and project managed the same project. This affected the segregation of duties between construction management unit and Infrastructure development unit.

• Construction units were guaranteed internal construction jobs without competing with the external service providers. This affected the total project costs as costs were not benchmarked with the market.

• The construction unit is now employed as a contractor by the Infrastructure development unit and the independent project managers are appointed from infrastructure development unit.

• Construction unit gets requested to submit the proposal to execute the project before the job can be awarded to them. The approval to award is based on price, quality and ability to deliver.

10

Page 11: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

GovernanceChallenges

• The progress on the projects were not easily available to Top Management. This is due to the fact that there were no proper reporting structure.

• There was no proper project methodology in place. This impacted on projects monitoring as Gantt charts and project plans were not easily available.

• The appointed project managers are expected to report the progress on projects on monthly basis or as when required.

• The project methodology is now enforced. The project plans and Gantt charts are prepared and projects progress are monitored on the regular basis.

11

Page 12: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

Financial ManagementChallenges

• The budget for new infrastructure, Dam Safety Rehabilitation Programme (DSRP) and Water Services resided within the control of the construction units. This model resulted in the allocation of budget being done without consulting financial expects.

• The total projects costing were done without looking at the activities on bill of quantities as the bill of quantities were not easily available. This resulted in under/over costing of the projects.

• The allocation of budget is managed from the office of the Chief Financial Officer (CFO) and the budget reside with the infrastructure unit instead of construction unit. Construction unit is paid based on the work done.

• The projects are now being costed at an activity level based on the bill of quantities.

12

Page 13: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

Financial Management…ContChallenges

• The costing unit did not exit within Water Trading Entity.

• The actual project cost were overstated due to the fact that construction unit was making profit on the internal projects.

• The was no separation between operational expenditure and capital expenditure.

• The Water Trading Entity is in the process of appointing quantity surveyors to assist in project costing.

• The internal profit made by construction is identified and adjustment are made to ensure that there is compliance with accounting standard.

• The internal order system was implemented as a temporary measure to separate operational expenditure and capital expenditure

13

Page 14: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

SystemChallenges

• There was no system in place to cater for the project costing on the ERP system. The monthly projects cost are available after 4-6 weeks due to delays in projects cost allocation.

• There was no system of managing the flee that construction unit has.

• There was no proper project management system in place.

• WTE is in the process upgrading the current ERP system to include the following modules that will cater for construction environment; Project system (PS) Fleet management (FM) Portfolio and Project Management (PPM) Plant Maintenance (PM)

• The implementation of the above modules will ensure that project cost are real time.

14

Page 15: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

Audit Opinion Challenges

• In 2011/12 the construction unit obtained a disclaimer opinion. The issues raised were as follows: No policy in place to manage abnormal

costs. Lack of proper costing system in place. Lack of segregation of duties. Construction making internal profit. Discrepancies on accounting and costing

depreciation. Inability to separate operating and capital

expenditure.

• In 2012/13 the construction unit was unqualified with matters of emphasis. The following were put in place: Abnormal cost policy. Internal profit were eliminated. The accounting depreciation policy was

aligned to the construction costing policies.

Internal order project was implemented to account for capital expenditure.

15

Page 16: STANDING COMMITTEE ON APPROPRIATIONS Presentation by Zandile Mathe Deputy Director General: NWRI 11 February 2014 1 Briefing by Department of Water Affairs

THANK YOU