Operational SOP Doc. No. OPS.03.0710 Start Up the Evap System Version Number Aug 23 2017 v1 Page 1 of 14 SAMPLE PROCEDURE ONLY DO NOT USE FOR EQUIPMENT OPERATION www.aps-online.net Applied Performance Strategies, Inc. (610) 987-4050 Purpose: To start the Evaporator System for normal operation. Required PPE: Safety Glasses Hearing Protection Steel Toed Shoes Nitrile Gloves Potential Hazards: In the automatic mode the equipment may start without warning. Keep hands clear unless the unit is locked out in a safe condition. Fall hazard exists on ladder and the raised platform. Use three-point contact when climbing up to or down from the platform. The vessels, heat exchangers and piping for have hot surfaces which could cause burns. Avoid contact with these hot surfaces. Reference Documents: None Required Equipment & Materials: Startup process log sheet S-2536 pH tester

Start Up the Evap System Number Page 1 14 - aps … SOP Doc. No. OPS .03 710 Start Up the Evap System Version Number Aug 23 2017 v1 ... 24. Visually inspect heat exchanger for leaks

Embed Size (px)

Citation preview

Operational SOP Doc. No. OPS.03.0710

Start Up the Evap System Version Number

Aug 23 2017 v1

Page 1 of 14

SAMPLE PROCEDURE ONLY – DO NOT USE FOR EQUIPMENT OPERATION

www.aps-online.net Applied Performance Strategies, Inc. (610) 987-4050

Purpose: To start the Evaporator System for normal operation.

Required PPE:

Safety Glasses

Hearing Protection

Steel Toed Shoes

Nitrile Gloves

Potential Hazards:

In the automatic mode the equipment may start without warning. Keep hands clear unless the unit is locked out in a safe condition.

Fall hazard exists on ladder and the raised platform. Use three-point contact when climbing up to or down from the platform.

The vessels, heat exchangers and piping for have hot surfaces which could cause burns. Avoid contact with these hot surfaces.

Reference Documents: None

Required Equipment & Materials:

• Startup process log sheet S-2536

• pH tester

Operational SOP Doc. No. OPS.03.0710

Start Up the Evap System Version Number

Aug 23 2017 v1

Page 1 of 14

SAMPLE PROCEDURE ONLY – DO NOT USE FOR EQUIPMENT OPERATION

www.aps-online.net Applied Performance Strategies, Inc. (610) 987-4050

Steps Key Points

Line up Cooling Tower Water Note: if the cooling tower is already in operation, proceed to the next section.

1. Turn CONTROL POWER Switch ON at the Main control panel.

2. Verify that Green CONTROL POWER light is lit.

3. Wait for HMIs to boot up.

4. Turn on Disconnect Switch for COOLING TOWER PUMP.

Operational SOP Doc. No. OPS.03.0710

Start Up the Evap System Version Number

Aug 23 2017 v1

Page 2 of 14

SAMPLE PROCEDURE ONLY – DO NOT USE FOR EQUIPMENT OPERATION

www.aps-online.net Applied Performance Strategies, Inc. (610) 987-4050

Steps Key Points

5. Turn on Disconnect Switch for COOLING TOWER FAN.

6. Press the START button on the CT Fan Controller to start the controller.

7. At the Concentrator HMI (Page 2) turn on the cooling tower water:

a. Turn on CONDENSER WATER PUMP.

b. Turn on COOLING TOWER PUMP.

c. Turn on COOLING TOWER (fan).

a.

b.

c.

Operational SOP Doc. No. OPS.03.0710

Start Up the Evap System Version Number

Aug 23 2017 v1

Page 3 of 14

SAMPLE PROCEDURE ONLY – DO NOT USE FOR EQUIPMENT OPERATION

www.aps-online.net Applied Performance Strategies, Inc. (610) 987-4050

Steps Key Points

Start the Seal Water System Note: if the seal water system is already in operation, proceed to the next section.

8. At the Stripper HMI (Page 2) turn on the WATER SEAL PUMP.

9. Verify water seal return flow to tank.

10. Inspect stripper system pumps for seal water leaks.

Flow should be visible here

Operational SOP Doc. No. OPS.03.0710

Start Up the Evap System Version Number

Aug 23 2017 v1

Page 4 of 14

SAMPLE PROCEDURE ONLY – DO NOT USE FOR EQUIPMENT OPERATION

www.aps-online.net Applied Performance Strategies, Inc. (610) 987-4050

Steps Key Points

Start Up the Evap System

11. Remove and inspect filter screen.

12. Clean screen if any debris or foreign material is found.

13. Open Recovery Water Valve.

Operational SOP Doc. No. OPS.03.0710

Start Up the Evap System Version Number

Aug 23 2017 v1

Page 5 of 14

SAMPLE PROCEDURE ONLY – DO NOT USE FOR EQUIPMENT OPERATION

www.aps-online.net Applied Performance Strategies, Inc. (610) 987-4050

Steps Key Points

14. At the Stripper HMI (Page 1) Start the FEED PUMP.

15. Wait 10 seconds before proceeding.

16. Start the 1ST EFFECT EXTRACT PUMP.

17. Start the 2nd EFFECT EXTRACT PUMP.

Operational SOP Doc. No. OPS.03.0710

Start Up the Evap System Version Number

Aug 23 2017 v1

Page 6 of 14

SAMPLE PROCEDURE ONLY – DO NOT USE FOR EQUIPMENT OPERATION

www.aps-online.net Applied Performance Strategies, Inc. (610) 987-4050

Steps Key Points

18. Verify that the vacuum break valve is closed.

19. At the Stripper HMI (Page 2) Start the VACUUM PUMP.

20. Start the ESSENCE VACUUM PUMP.

Operational SOP Doc. No. OPS.03.0710

Start Up the Evap System Version Number

Aug 23 2017 v1

Page 7 of 14

SAMPLE PROCEDURE ONLY – DO NOT USE FOR EQUIPMENT OPERATION

www.aps-online.net Applied Performance Strategies, Inc. (610) 987-4050

Steps Key Points

21. Verify that system is building vacuum. Gauge should read at least 10 inHg. Before continuing to the next step.

22. Start the HOT WATER PUMP at the Evap System HMI.

23. Verify that injection water supply valve is open.

24. Visually inspect heat exchanger for leaks.

Operational SOP Doc. No. OPS.03.0710

Start Up the Evap System Version Number

Aug 23 2017 v1

Page 8 of 14

SAMPLE PROCEDURE ONLY – DO NOT USE FOR EQUIPMENT OPERATION

www.aps-online.net Applied Performance Strategies, Inc. (610) 987-4050

Steps Key Points

25. Set injection spray water valve to 45-degree position as shown.

26. Open spray heater water supply valve.

27. Prime the fluid column to ensure there is a level visible in the sight glass.

Sight Glass

Operational SOP Doc. No. OPS.03.0710

Start Up the Evap System Version Number

Aug 23 2017 v1

Page 9 of 14

SAMPLE PROCEDURE ONLY – DO NOT USE FOR EQUIPMENT OPERATION

www.aps-online.net Applied Performance Strategies, Inc. (610) 987-4050

Steps Key Points

28. At the Stripper HMI (Page 1) Start the condensate and extract pumps:

a. 1ST EFFECT COND PUMP

b. 2ND EFFECT COND PUMP

c. SPRAY HEATER EXTRACT PUMP

d. CONDENSOR EXTRACT PUMP

e. ESSENCE COND PUMP

29. Open steam supply valve to hot set.

a. b. c. d. e.

Operational SOP Doc. No. OPS.03.0710

Start Up the Evap System Version Number

Aug 23 2017 v1

Page 10 of 14

SAMPLE PROCEDURE ONLY – DO NOT USE FOR EQUIPMENT OPERATION

www.aps-online.net Applied Performance Strategies, Inc. (610) 987-4050

Steps Key Points

30. Open condensate valve to drain water from the system

31. Close valve when only steam is present.

32. Open steam supply valve (Chain Operated).

Operational SOP Doc. No. OPS.03.0710

Start Up the Evap System Version Number

Aug 23 2017 v1

Page 11 of 14

SAMPLE PROCEDURE ONLY – DO NOT USE FOR EQUIPMENT OPERATION

www.aps-online.net Applied Performance Strategies, Inc. (610) 987-4050

Steps Key Points

33. Open condensate valve to drain water from the system

34. Close valve when only steam is present.

35. Adjust STRIPPER STEAM SUPPLY PRESSURE setpoint to 20 PSI:

Touch to bring up

keypad for entry.

Operational SOP Doc. No. OPS.03.0710

Start Up the Evap System Version Number

Aug 23 2017 v1

Page 12 of 14

SAMPLE PROCEDURE ONLY – DO NOT USE FOR EQUIPMENT OPERATION

www.aps-online.net Applied Performance Strategies, Inc. (610) 987-4050

Steps Key Points

36. Turn STEAM VALVE on.

37. Open the manual inlet valve to balance tank.

38. Adjust flow rate and 1st stage vacuum to as needed to achieve desired brix.

Operational SOP Doc. No. OPS.03.0710

Start Up the Evap System Version Number

Aug 23 2017 v1

Page 13 of 14

SAMPLE PROCEDURE ONLY – DO NOT USE FOR EQUIPMENT OPERATION

www.aps-online.net Applied Performance Strategies, Inc. (610) 987-4050

History of Revisions

Revision Number

Revision Date

Revised By Reason for Revision