31
Clients People Performance Design, Construction and Startup of the First Enhanced Nutrient Removal Plant in Maryland Funded by the Chesapeake Bay Restoration Fund Rip Copithorn, Jeff Sturdevant, Vince Maillard GHD

Startup and Initial Operation of a

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Startup and Initial Operation of a

Clients People Performance

Design, Construction and Startup of the

First Enhanced Nutrient Removal Plant in Maryland Funded by the

Chesapeake Bay Restoration Fund

Rip Copithorn, Jeff Sturdevant, Vince Maillard

GHD

Page 2: Startup and Initial Operation of a

Introduction

• Chesapeake Bay 2000 Agreement• Maryland, Virginia, Pennsylvania, DC• Reduce N and P by 20 million and 1 million lbs, resp.• Follows the 1983 agreement that resulted in the BNR

program• Enhanced Nutrient Removal (ENR) Program

• ENR Program requires WWTFs to achieve annual average effluent TN of 3 mg/L and TP of 0.3 mg/L

• New limits achieve only 1/3 of the reduction in Agreement

Page 3: Startup and Initial Operation of a

USGS MD-DE-DC Water Science Center

Background • All WWTFs in the

Chesapeake Bay watershed will be subject to strict effluent nutrient loading limits:• Maryland, Pennsylvania,

and Virginia already have nutrient limits

• Delaware, New York, and West Virginia are developing similar requirements

• Maryland has regulations for all 66 major WWTFs

Page 4: Startup and Initial Operation of a

Funding

• All WWTFs 0.5 mgd or greater (total of 66 plants)• Required to upgrade to BNR levels first• ENR eligible items are 100% fundable• Statewide “flush tax” ($50/yr per household)• Easton, MD was first plant to enter the ENR

program in MD in 2003

Page 5: Startup and Initial Operation of a

Easton, MD

Page 6: Startup and Initial Operation of a

Nitrogen Removal

20 mg/L 10 mg/L 5 mg/L 0 mg/L

Nitrification BNR ENR UNR

Easton Goal (3 mg/L)

Permit = 4.0 mg/L

Approximate Limit of Technology

Previous MD Goal/ Standard

Original Permit had NH3 Removal Only

Page 7: Startup and Initial Operation of a

Phosphorus Removal

10 mg/L 1 mg/L 0.1 mg/L 0.01 mg/L

New Permit(0.3 mg/L)

Approximate Limit of Technology

Original Permit (1.2 mg/L)

Previous MD Standard

Page 8: Startup and Initial Operation of a

Overview of Existing Facility

Overland Flow Terraces

Facultative Lagoons

Cl2 & SO2 Buildings

Laboratory

Chlorine Contact

Tank

Outfall

Maintenance Building

Page 9: Startup and Initial Operation of a

Existing Process Flow Diagram

Primary Lagoon

SecondaryLagoon

OverlandFlow

Terraces (5)

PostAeration

Cl2SO2

Raw Influent Outfall

Recycle Pumps

Page 10: Startup and Initial Operation of a

Existing Facility

• Capacity = 2.35 mgd• Limits

BOD5 (6/1 - 10/31) 20 mg/l(11/1 – 5/31) 30 mg/l

Ammonia (6/1 – 10/31) 5 mg/l

Page 11: Startup and Initial Operation of a

New Facility

• Average = 4.0 mgd• Design (Max Month) = 5.5 mgd• Peak Day = 7.8 mgd (higher flows equalized)• Limits

BOD5 (4/1 - 9/30) 11 mg/l(10/1 – 3/31) 30 mg/l

TSS 30 mg/LAmmonia (4/1 - 9/30) 2.1 mg/l

(10/1 – 3/31) 3.7 mg/lTP 1.2 mg/L

Page 12: Startup and Initial Operation of a

Future Limits and Current Goals

On an average annual basis• TN – 4.0 mg/L (goal 3.0 mg/L)• TP – 0.3 mg/L

Page 13: Startup and Initial Operation of a

Biological Process Selection

Workshop 1•Biolac•Orbal•Bardenpho•Schreiber•Batch SBR•ICEAS SBR•5-Stage BNR

•Site Visits•Capital and O&M Cost Estimates

Workshop 2Qualitative and quantitative analysis of remaining alternatives

•Biolac •Orbal•Bardenpho

Selection of EIMCO 5-Stage Bardenpho System

Page 14: Startup and Initial Operation of a

Overview of New Facility

Preliminary Treatment

5-Stage Bardenpho Reactors

Secondary Clarifiers

Operations Building

Pump & Blower Building

Waste Sludge Holding Tanks

Effluent FiltersSolids

Processing Building

Dried Biosolids

Storage SiloUV Disinfection

Page 15: Startup and Initial Operation of a

Easton WWTF Bioreactors

Process includes two (2) parallel oxidation ditches followed by post- anoxic and re-aeration tanks, clarifiers, and deep bed continuously- backwashing up-flow filters

Page 16: Startup and Initial Operation of a

Easton WWTF Bioreactors

Oxidation ditches configured as 5-stage Bardenpho process with a “racetrack” style central aerobic cell aerated w/ vertical shaft surface aerators

Page 17: Startup and Initial Operation of a

Easton WWTF Bioreactors

Process cut-away showing the Bioreactors at the Easton WWTF

OVIVO Eimco Water Technologies (EWT) Carrousel® System Surface Aerator

Anaerobic andPre-Anoxic ZonesAerated “Racetrack”

Zone

Page 18: Startup and Initial Operation of a

Easton WWTF Bioreactors

SCADA control screen for the Bioreactors at the Easton WWTF

Page 19: Startup and Initial Operation of a

Easton WWTF Bioreactor Volume

1The second post anoxic zone was placed into service from October 2008 to April 2009 and October 2009 to March 2010.

Because influent flow and load are only about 60% of the full design values, the plant operators have only operated one of the two bioreactors since the plant went on line.

Treatment Stage

Units in Service (m3) (MG)

Percent of

Reactor Volume

Anaerobic 1 681 0.18 8%Pre Anoxic 1 681 0.18 8%Oxidation Ditch 1 5,867 1.55 70%Post Anoxic 21 908 0.24 11%Reaeration 1 189 0.05 2%Total Volume 8,328 2.2 100%

Volume in Service

Page 20: Startup and Initial Operation of a

Selection of Bio-Solids Treatment Process

• Existing process required no sludge treatment or disposal

• New process will produce approximately 5,000 lbs dry solids per day under average conditions

• Outline of major decisions• Class A or B Bio-Solids • Treatment method to meet Class A or B• Dewatering Method• Storage and/or disposal of final product

Page 21: Startup and Initial Operation of a

New Solids Process Flow Diagram

AeratedHolding Tanks Dryer Storage

SiloCentrifuge

Distribution or DisposalLandfill Daily CoverLandscapingNurseriesFarmsGeneral Public

DisposalLandfill

Page 22: Startup and Initial Operation of a

Construction

• $26,000,000 construction cost (50% BNR, 25% ENR)• Notice to proceed – 12/04• Liquid Processes Operational

• Oxidation Ditch – 10/06 (one train, limited controls)• Filter – 12/06 (no chemical addition until mid 1/07)

• Solids Processes Operational – 1/07• Substantial Completion – 3/07• Startup of Oxidation Ditch w/o seeding• Only one train available for > 50% flow• Limited controls due to sequencing of work

Page 23: Startup and Initial Operation of a

MLSS and Effluent NH3 vs. Time

0

500

1000

1500

2000

2500

3000

3500

4000

0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40Time (Days)

[MLS

S] (m

g/l)

0

5

10

15

20

MLSS NH3 (mg/l)

Efflu

ent[

NH 3

](m

g/l)

Page 24: Startup and Initial Operation of a

Effluent Nitrogen

0

1

2

3

4

5

6

7

8

9

10

11

12/15/06 3/25/07 7/3/07 10/11/07 1/19/08 4/28/08

Nitr

ogen

(mg/

L)

Ammonia Nitrate TN TN Goal Average TN

TN Goal

Average TN 3.18 mg/L w/o Supplemental Carbon Addition

Average TN 2.26 mg/L w/o Supplemental Carbon Addition

Average TN 5.52 mg/L

Plant UpsetStart Up

Page 25: Startup and Initial Operation of a

Easton WWTF Nitrogen Removal Performance

0.0

5.0

10.0

15.0

20.0

25.0

30.0

35.0

40.0

45.0

Jan-

08

Feb-

08

Mar

-08

Apr

-08

May

-08

Jun-

08

Jul-0

8

Aug

-08

Sep

-08

Oct

-08

Nov

-08

Dec

-08

Jan-

09

Feb-

09

Mar

-09

Apr

-09

May

-09

Jun-

09

Jul-0

9

Aug

-09

Sep

-09

Oct

-09

Nov

-09

Dec

-09

Jan-

10

Feb-

10

Mar

-10

Apr

-10

May

-10

Jun-

10

Influ

ent T

KN

, mg/

L

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.0

Efflu

ent N

itrog

en, m

g/L

Influent TKN Effluent TN Effluent NH3 Effluent NO3

4.0 mg/L EffluentTN Goal

Page 26: Startup and Initial Operation of a

Nitrate Concentrations through Process

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

Jan-

08

Feb-

08

Mar

-08

Apr

-08

May

-08

Jun-

08

Jul-0

8

Aug

-08

Sep

-08

Oct

-08

Nov

-08

Dec

-08

Jan-

09

Feb-

09

Mar

-09

Apr

-09

May

-09

Jun-

09

Jul-0

9

Aug

-09

Sep

-09

Oct

-09

Nov

-09

Dec

-09

Jan-

10

Feb-

10

Mar

-10

Apr

-10

May

-10

Jun-

10

NO

3 C

once

ntra

tion,

N m

g/L

NO3 @ Pre Anox Exit NO3 @ Ox Ditch Exit NO3 @ Post Anox Exit

2ndPost-Anoxic Tank Put in Service

Page 27: Startup and Initial Operation of a

Effluent Phosphorus

0.0

0.3

0.6

0.9

1.2

1.5

1.8

12/15/06 3/25/07 7/3/07 10/11/07 1/19/08 4/28/08

Phos

phor

us (m

g/L)

Ortho P TP TP Goal Average TP

TP Goal

Average TP 0.22 mg/L

Average TP 0.66 mg/L

Start UpPlant Upset

Average TP 0.23 mg/L

Page 28: Startup and Initial Operation of a

Easton WWTF Phosphorus Removal Performance

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

Jan-

08

Feb-

08

Mar

-08

Apr

-08

May

-08

Jun-

08

Jul-0

8

Aug

-08

Sep

-08

Oct

-08

Nov

-08

Dec

-08

Jan-

09

Feb-

09

Mar

-09

Apr

-09

May

-09

Jun-

09

Jul-0

9

Aug

-09

Sep

-09

Oct

-09

Nov

-09

Dec

-09

Jan-

10

Feb-

10

Mar

-10

Apr

-10

May

-10

Jun-

10

Influ

ent P

hosp

hpor

us, m

g/L

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0

Efflu

ent P

hosp

horu

s, m

g/L

Influent TP Effluent TP Effluent OP Effluent TP GOal

0.3 mg/L Effluent TPGoal

Page 29: Startup and Initial Operation of a

OP Concentrations Through Process

0.0

5.0

10.0

15.0

20.0

25.0Jan‐08

Feb‐08

Mar‐08

Apr‐08

May‐08

Jun‐08

Jul‐0

8

Aug

‐08

Sep‐08

Oct‐08

Nov

‐08

Dec‐08

Jan‐09

Feb‐09

Mar‐09

Apr‐09

May‐09

Jun‐09

Jul‐0

9

Aug

‐09

Sep‐09

Oct‐09

Nov

‐09

Dec‐09

Jan‐10

Feb‐10

Mar‐10

Apr‐10

May‐10

Jun‐10

Ana

erob

ic &

Rec

ycle

OP

Con

cent

ratio

n, O

P m

g/L

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0

Ox

Ditc

h &

Pos

t Ano

xic

OP

Con

cent

ratio

n, O

P m

g/L

Anearobic Eff OP in Recycle Stream OP @ Ox Ditch Exit OP @ Post Anox Exit

Page 30: Startup and Initial Operation of a

Ongoing Improvements

Page 31: Startup and Initial Operation of a

Questions ?

[email protected]