STATUS OF ACTION TAKEN ON RECOMMENDATIONS OF THE ENQUIRY COMMITTEE ON GRID DISTURBANCE IN NORTHERN REGION
ON 30th JULY 2012 AND IN NORTHERN, EASTERN & NORTH-EASTERN REGION ON 31st JULY 2012. (As on 22-03-2013)
S.No. RECOMMENDATIONS Action Taken
9.1.1
There is a need to review protection schemes. This
Committee concurs with recommendation of previous
enquiry committees that a thorough third party protection
audit need to be carried out in time bound manner. This
exercise should be repeated periodically and monitored by
RPCs.
Action: RPCs, CTU, STUs
Time Frame: 1 year
NR : PGCIL has completed protection audit of all 132 important substations/
switchyards in the Northern Region in various phases on 15th
November 2012. Gist is
given at Appendix-I.
WR: The audit of 137 out of 212 important substations in the Western Region has
been completed and audit in remaining sub-stations is likely to complete by April
2013. In Gujarat, the audit was completed by a third party earlier in 2010 itself and
all deficiencies rectified. In Maharashtra, audit of 90 s/s out of 119 S/s has been done
rest to complete by March-13. In MP audit of 11 out of 37 S/S have been carried out
rest to complete by April 2013. In Chhattisgarh audit of 9 out of 16 have been
completed rest to complete by March-13, Goa & UTs, the process of audit is being
finalized. 18 sub-station out of 31 sub-station belonging to PGCIL and NTPC has
been comleted and rest is likely to complete by Aril-13.
SR : Protection Audit have been completed for all 194 critical substations in the
region on 22nd
December 2012. Audit report circulated to all States and action plan to
was discussed in SRPC meeting held on 2nd
Feb-2013. As per the action plan the
corrective measures have been initiated and to be complete within time frame ranging
from 3 months to two years and total expenditure of around 158 Crores.
ER : Protection audit for 42 S/s of 400kV, 1 HVDC and 11 S/s of 220 kV completed
and report subted to RPC. DVC, West Bengal and Odhisha prepared action paln and
intitiated actions. Jharkhand and Bihar to prepare the action plan and has to started
work.
NER : In NER there are about 135 Nos. of substation and generating stations of
132kV and above voltage class. The protection audit was planned in consultation
with NERLDC, STU, CTU and Generating companies of NER. In February 2013, the
protection audit of all stations was completed as per schedule. The report on audit of
Protection system along with recommendations and implementation plan is likely to
2
S.No. RECOMMENDATIONS Action Taken
be submitted by March 2013.
9.1.2
Till protection audit is taken up, there is need to take
immediate review of zone-3 philosophy in particular.
Techniques are available to modify characteristics of the
relay so that it can distinguish between load encroachment
and faults. These techniques and other alternatives should
be explored immediately.
Action: RPCs, CTU, STUs
Time Frame: Immediate
Earlier, Zone-3 settings were not considered as part of the line loadability criterion.
However, after the grid disturbances, the Zone-3 settings have been collected and
analyzed to arrive at the safe line loading limits. In a meeting taken by Member (PS),
CEA with CTU and POSOCO on 26th
September 2012 regarding transmission line
loadability, loading limits of transmission lines on all India basis were finalized and
circulated vide letter dated 3rd
October 2012. The report contains Zone-3 settings as
well, wherever available. All concerned have been advised to check the settings
where indicated / intimate the settings where not available. It was also decided at the
meeting that Zone-3 settings need to be reviewed by POWERGRID in coordination
with STUs, Generators and POSOCO so as to avoid load encroachment.
POWERGRID has reviewed and verified all the implemented Zone-3 settings.
9.1.3
The application of synchro-phasor measurements from
PMUs should be explored for protection systems. There is
also an urgent need to deploy Special Protection System
(SPS) in critical transmission elements. Also, there is need
to make already approved SPS operational.
Action: RPCs, CTU
Time Frame: 1 year
As per information from CTU, NR 9 PMUs; SR 3 (+9 under implementation) PMUs;
ER 12 PMUs (under implementation) and WR 10 PMUs (+7 under implementation)
are functional.
Further, Unified Real Time Dynamic State Measurement (URTDSM) Scheme with
large scale deployment of PMUs is under CERC approval.
12 SPS of SR are already functional. 6 more SPS, are under various stage of
implementation. In NR & ER 3 SPS each and in WR 2 SPS are implemented.
9.1.4
A complete independent audit of time synchronization of
DRs, ELs and PMUs should be carried out.
Action: Generators, CTU, STUs.
Time Frame: 1 month
This also forms a part of the protection audit undertaken / to be undertaken by CTU /
STUs as per item 9.1.1 above.
3
S.No. RECOMMENDATIONS Action Taken
9.2.1
Frequency band needs to be further tightened and brought
close to 50 Hz. POSOCO may file an urgency application
in Supreme Court for early resolution of the issue in view
of the recent grid disturbances.
Action: POSOCO
Time Frame: 1 month
CERC has directed the Commission Staff vide its order dated 29.11.12 to consider
the POSOCO petition for further tightening of frequency band to 49.9 - 50.1. Hz. and
prepare a proposal for further action on the same.
Under active consideration of the Commission and involves examination by a
committee comprising CEA, CTU and CERC. Commission to take a view based on
recommendations of committee.
Committee expected to take about 4 weeks time and about another 8 weeks required
to amend the Regulations. (in about 3 months time) by June 2013
9.2.2
A review of UI mechanism should be carried out in view of
its impact on recent grid disturbances. Frequency control
through UI may be phased out in a time bound manner and
Generation reserves/Ancillary services may be used for
frequency control. Appropriate regulatory mechanism
needs to be put in place for this purpose. POSOCO should
take up the matter with CERC.
Action: POSOCO
Time Frame: 3 months
Regarding the Generation Reserves / Ancillary services, the petition for introducing
these services in the country was filed by NLDC with CERC on 29.11.2010. Against
this, CERC in its order issued on dated 20.07.2012 has directed its staff for
formulation of draft Regulations for Ancillary Services and CERC staff is working
on this proposal alongwith the proposal for amendment to the IEGC.
9.3
All STUs should immediately enable under frequency and
df/dt based load shedding schemes. Central Commission
should explore ways and means for implementation of
various regulations issued under the Electricity Act, 2003.
Any violation of these regulations can prove to be costly as
has been the case this time. RPCs need to take up the matter
for compliance. In case non-compliance persists, POSOCO
should approach Central Commission.
Action: STUs, RPCs, POSOCO
Time Frame: Immediate
NR: status of functioning of Under-Frequency Relays (UFRs) and df/dt relays in NR
as per the information received from various constituents are as under:
1. In Delhi all 24 UFR and 13 df/dt realys are functional.
2. In UP out of total 148 nos of UFR only 58 are functioning. (18 nos. of UFR have
been procured and are being installed. 76 nos. of UFR are being procured and
expected with expected delivery upto May 2013)
3. In Punjab out of 31 nos of UFRs 05 are non-functional and out of 28 nos of df/dt
03 nos are non-functional (3 nos of UFR and 01 no. df/dt of have been made
operational. Information in regard to balance 02 nos of UFR and 02 nos of df/dt
is awaited)
4. In Haryana out of 28 nos of UFR and 6 df/dt relays, 9 UFR were found defective
5 UFRs made operational and for 4 nos. of UFR order has been placed for
4
S.No. RECOMMENDATIONS Action Taken
replacement.
5. In Rajasthan all 4 defective UFR out of 88 UFR, would be operational by 31-03-
2013.
6. In Himachal Pradesh all 3 UFR are operational one df/dt relay out of 3 is
defective which is being rectified.
7. J&K and Uttarakhand – status not submitted, matter has been taken up with
respective electricity departments.
8. Chandigarh has not submitted the self certification for its total 2 UFRs., matter
taken up with Chandigarh.
WR: Formed a committee to look into the matter of UFR and df/dt relay settings.
The committee has revised (increased) the load-relief to be provided by UFRs
keeping in view the voltage and frequency dependence of load.
SR: Data regarding status of functioning of UFRs and df/dt relays has already been
collected and sent to SRPC by PGCIL. It has been found that relays are available and
enabled at all substations except some lines (Tamilnadu - 8 locations, Karnataka -11
locations, Andhra Pradesh – 7 locations and one location each in Kerala and
Puducherry). Corrective action on deficiencies is in progress.
ER: UFR settings have been revised and made equivalent to those in NR and WR i.e.
48.8, 48.6 & 48.2 Hz and also finalized the quantum of load relief from each State of
ER. States have confirmed that all UFRs as per the scheme of load-relief decided by
ERPC are functional. A sub-group has been formed to carry out inspection of
healthiness of UFRs. The inspection is being carried out regularly. The subgroup has
been entrusted to carryout at least two inspections every month and submit the report
in monthly OCC meetings.
NER: The states in NER are understood to have submitted self-certification
regarding functioning of under-frequency relays. No df/dt relay is installed in NER.
POSOCO: Non-compliance of CERC regulations are being brought to the notice of
the commission. High level logic for an automated contingency load shedding
5
S.No. RECOMMENDATIONS Action Taken
protocol was circulated by POSOCO on 11th September 2012. Detailed logic for
implementation being worked out in consultation with the states. A Petition on UFRs
& df/dt relays was filed by NRLDC with CERC on 19th Sept, 2012.
As per record of proceedings of hearing held on 14.02.2013,
(a) All entities shall ensure healthiness of the defense mechanisms i.e. UFR, df/dt
relays etc at all the time;
(b) RPC secretariats shall monitor and ensure corrective actions within time frame;
(c) All entities, who have not submitted the information, shall immediately file
information, on affidavit with an advance copy to NRPC and NRLDC on or
before15.3.2013;
(d) NRPC shall take up the issue in the next NRPC meeting and submit the time
schedule for procurement/rectification of all the relays in the NR and submit
compliance report by 15.3.3013 as per Regulation 1.5 of the Grid
Code.
(e) NRLDC shall submit the operational report of the load relief obtained from the
under frequency relays to NRPC Secretariat and to the Commission by 22.3.32013;
and
(f) NRLDC and NRPC may file, any discrepancy detected on the submissions filed
by the respondents, on affidavit, with copy to the respondents, by 1.4.2013.
The Commission directed the officer in charge of State STUs and SLDCs, who have
not filed any response, appear before the Commission in next date of hearing to
explain the reasons for non-compliance of the Commission's directions.
The petition is listed for hearing on 9.4.2013.
6
S.No. RECOMMENDATIONS Action Taken
9.4 All out efforts should be made to implement provisions of
IEGC with regard to governor action. Central Commission
needs to look into ways and means to hasten
implementation of provisions of IEGC including that on
governor action. POSOCO need to take up the matter with
Central Commission.
Action: POSOCO
Time Frame: 3 months
CERC in its order dated 31.12.2012 reiterated the need for compliance by generators
and directed as to why they may not be held responsible for non-implementation of
RGMO / FGMO mode of operation.
CERC directed the task force constituted under Member (Thermal), CEA to complete
the testing / tuning of identified units and finalize the protocols / modalities of testing
in a time bound manner.
9.5.1 POSOCO should take up with Central Commission the
issue of inconsistency between Congestion regulation and
the detailed procedure framed there under so that
congestion due to forced outages and Unscheduled
Interchange (UI) can be handled effectively.
Action: POSOCO
Time Frame: 1 month
CERC vide order issued on 18.12.2012 has directed staff of the CERC to consider the
proposal by NLDC and initiate amendment process in the CERC Regulations 2009.
CERC staff is working on the proposal.
Proposal under active consideration of the Commission and orders expected shortly.
9.5.2
NLDC and each RLDC should have one real-time security
desk in all the shifts to be manned by engineer capable of
carrying out TTC calculations. To facilitate this, manpower
at NLDC and RLDCs need to be enhanced with regulatory
support to take care of financial aspects. Till this
arrangement can be firmed up, various scenarios of outages
could be built, which then can be used by despatcher in real
time. Faster algorithm for calculation of TTC may be
adopted by the load despatchers to update it in real time
under outage conditions.
Action: POSOCO
Time Frame: 6 months
Updated version of PSS/E is installed at all SLDCs, RLDCs, NLDC, RPCs, CEA and
CERC enabling simulation of the system and carrying out stability studies.
Presently all planned outages are approved and TTC is reviewed and updated, if
required, for these conditions.
9.6 Outage planning of inter-State and inter-regional
transmission elements should be carried out in a
coordinated manner at RPC fora (say Operation Co-
This provision has been implemented. NLDC has been asked to depute its
representatives to attend monthly OCC meetings in all the five RPCs to ensure proper
implementation of this provision.
7
S.No. RECOMMENDATIONS Action Taken
ordination sub-committee of RPCs) in accordance with
regulation 5 of Central Electricity Authority (Grid
Standards) Regulation, 2010 and Section 5.7.1 of Indian
Electricity Grid Code. In case need for emergency
maintenance arises in between two meeting of Operation
Co-ordination sub-committee, NLDC and RLDCs should
allow such maintenance after carefully looking at prevailing
system conditions under intimation to RPC Secretariat.
Action: RPCs
Time Frame: Immediate
9.7 In order to avoid frequent outages/opening of lines under
over voltages and also providing voltage support under
steady state and dynamic conditions, installation of
adequate static and dynamic reactive power compensators
should be planned.
Action: CEA, CTU, STUs
Time Frame: 6 months
Installation of Fixed Reactors as already approved in various RPCs are under various
stages of implementation. Further study on dynamic support is in progress by CTU
and POSOCO in consultation with CEA.
9.8 The powers of Load Despatch Centres and Regulatory
Commissions related to non-compliance of
statutory/regulatory provisions including that for non-
compliance of directions and non-payment of UI charges,
need review. Appropriate amendments need to be carried
out in the Electricity Act, 2003 after such review.
Action: Ministry of Power, GoI.
Time Frame: 6 months
Report of the Committee constituted under the chairmanship of Chairperson CEA to
be submitted to MoP on amendments in the Electricity Act 2003 relating to grid
matters shortly.
9.9.1 The regulatory provisions regarding absorption of reactive
power by generating units needs to be implemented
Action: POSOCO
Time Frame: Immediate
As per system requirement the generators are being advised to absorb reactive power
to control voltage. All RLDCs have issued communication to the Generators in this
regard. The matter is also being discussed regularly in the Operation Co-ordination
Sub-committee meetings of RPCs.
8
S.No. RECOMMENDATIONS Action Taken
9.9.2 An audit of devices such as HVDC, TCSC, SVC and PSS
should be done immediately to ensure that their stability
features are enabled. Further, exercise of PSS tuning should
be planned and implemented. Settings of these dynamic
stabilizing devices should be reviewed at appropriate
intervals.
Action: CTU, STUs, Generators
Time Frame: 6 months
As per information from CTU, audit of Rihand-Dadri HVDC and Pasauli HVDC has
been done and the stability features thereof are enabled. SVC is installed at Kanpur
substation only and it is ON. TCSCs - installed at Gorakhpur, Purnea and Raipur only
and the audit has been done. It was reported by PGCIL that TCSCs are functional.
RPCs will deliberate this as well as implementation of other recommendations by the
utilities in their forthcoming RPC / TCC meetings.
9.9.3 Functioning of existing PMUs and availability of their
output to RLDCs and accuracy of time synchronization
should be monitored on daily basis and, if required,
corrective actions should be taken on priority basis.
Action: CTU, POSOCO
Time Frame: Immediate
POWERGRID has time synchronized all the existing PMUs that have been installed
under pilot project in identified substations in the country and made them fully
functional. The real time output displays of the PMUs are now being accordingly
made available to the respective system operators in the concerned RLDC. The PMU
data from various locations is also available at the NLDC Control Room.
9.10.1
The synchrophasor based WAMS employing PMUs offer a
wide applications for real time monitoring and control of
the system, specially under the dynamic conditions.
Adequate number of PMUs should be installed to improve
the visibility and real time monitoring of the system.
Further the applications related to the synchrophasor based
wide area monitoring, protection and control should be
embedded in the system.
Action: CTU
Time Frame: 1 year
Unified Real Time Dynamic State Measurement (URTDSM) system with large scale
deployment of PMUs is being discussed with various RPCs prior to taking up with
CERC for approval. Meanwhile, preparation of DPR and tender document by CTU is
in progress. NIT floated in December 2012.
9.10.2
Possibility of voltage collapse prediction, sensing global
power system conditions derived from local measurements
may be explored.
Action: RPCs
It is learnt that voltage collapse prediction relays are available in the market. RPCs
are in the process of examining use of such relays through discussions in the
respective Protection Coordination Sub-committee meetings.
9
S.No. RECOMMENDATIONS Action Taken
Time Frame: 1 year
9.11 Need of Dynamic Security Assessment and review of State Estimation In order to assess the system security in
real time and assess the vulnerability condition of the
system, dynamic security assessment need to be
periodically carried out at the control centers. A proper
review and upgradation of the state estimation procedure is
required to improve the visibility and situational awareness
of the system.
Action: POSOCO
Time Frame: 6 months
As per information from POSOCO, present system does not have dynamic security
assessment capability. New systems are being developed / planned for the future.
9.12 Efforts should be made to design islanding scheme based
on frequency sensing relays so that in case of imminent grid
failure, electrical islands can be formed. These electrical
islands can not only help in maintaining supply to essential
services but would also help in faster restoration of grid.
Action: CEA, RPCs, POWERGRID, STUs, SLDCs and
Generators
Time Frame: 6 months
NR : NAPS and RAPS islanding schemes are already functional. Islanding scheme
for Delhi has been finalised by DTL in October 2012 and the same is under
implementation. Punjab developed islanding schemes for GGSSTP Ropar with
Gobindgarh area load , GHTP & GNDTP with Bathinda area load and the same is to
be taken for implementation . UP submitted islanding schemes around Unchahar
thermal power stations Haryana submitted its islanding schemes around Faridabad
Panipat power stations .Islanding schemes for UP and Haryana has been deliberated
22-01-2013 in NRPC and they were advised to revise the scheme as per the decisions
in the meeting. UP submitted the revised and final islanding scheme. Rajasthan
initiated preparation of islanding schemes.
WR : Mumbai, Ahmedabad, GTPS Uran islanding schemes are already functional.
Islanding schemes for Vadodara, Bhopal and Nagpur are under study. All CPPs are
planned for islanding at a slightly higher frequency than 48.8 Hz so that these
stations are available for extending startup power.
ER : CESC and many CPPs like Bokaro Steel, NALCO, etc. already have islanding
schemes. Three islanding schemes viz. Bakreshwar with WB load, Chandrapura of
DVC and Bandel TPS, are finalized and the process for implementation of these
schemes have been initiated.
10
S.No. RECOMMENDATIONS Action Taken
SR : Islanding schemes for Hyderabad and Chennai are already functional. 14
islanding schemes in the states of AP, Karnataka, Tamilnadu, Kerala around power
stations located in these states have been taken up for study by the respective STUs.
NER : An islanding scheme around Namrup TPS in Assam is already functional.
Eight new islanding schemes have been taken up for study / examination.
9.13.1
As National Grid is on the horizon, homogenization of
system operation philosophy is need of the hour. The
present organizational set up of Load Despatch Centres
need to be reviewed. System operation needs to be
entrusted to Independent System Operator (ISO). In
addition, SLDCs should be reinforced and ring fenced for
ensuring functional autonomy.
Action: Govt. of India, State Govts.
Time Frame: 1 year
Although POSOCO in 100% subsidiary company of PGCIL, it has functional and
financial autonomy in grid operations. Further, strengthening of SLDCs is required to
be done by the states.
9.13.2
Training and certification of system operators need to be
given focused attention. Sufficient financial incentives need
to be given to certified system operators so that system
operation gets recognized as specialized activity.
Action: Govt. of India, State Govts.
Time Frame: 3 months
Discussed on 21st August 2012 in the proposed National Power Committee meeting
with participation of Chairmen of RPCs/TCCs and the Member Secretaries for
implementation in the respective regions.
Maharashtra has already started such scheme. Other State Govts. have to start the
incentive scheme in this regard.
9.14
Intra-State transmission system needs to be planned and
strengthened in a better way to avoid problems of frequent
congestion.
Action: STUs
Time Frame: 2 years
SLDCs should provide inputs to the respective STUs for better planning /
strengthening of intra-state transmission system. This needs to be implemented and
monitored through RPCs.
In NR, STUs have already been requested through OCC meeting to plan and
strengthen their Intra-state transmission network. This would be continuously
monitored at NRPC forum.
11
S.No. RECOMMENDATIONS Action Taken
9.15.1
Appropriate amendments should be carried out in Grid
Connectivity Standards to restrain connectivity of a
generating station or a transmission element without
required communication and telemetry facilities.
Action: CEA.
Time Frame: 6 months
Connectivity standards are already having the requisite provisions in regard to the
communication and telemetry facilities and as such amendment is not needed.
9.15.2
The Communication network should be strengthened by
putting fibre optic communication system. Further, the
Communication network should be maintained properly to
ensure reliability of data at Load Despatch Cenres.
Action: CTU and STUs
Time Frame: One years
PGCIL have informed that requirement of Fibre Optic link for effective
communication is being worked out by them with STUs through different RPCs and
its implementation is being done in a progressive manner. The work of laying Fibre
Optic cables in all the regions is being awarded progressively from December 2012
and is likely to be completed by the year 2014. Some of the states like J&K, Punjab
have also sought assistance from PGCIL in installing fibre optic communication
network.
9.15.3
RTUs and communication equipment should have
uninterrupted power supply with proper battery backup so
that in case of total power failure, supervisory control and
data acquisition channels do not fail.
Action: CTU and STUs
Time Frame: 3 months
PGCIL have intimated that at all locations batteries have been replaced except 6
locations in NR and rest of the other region it has been replaced.
9.15.4
In case of existing generating stations or transmission
elements without telemetry facility, the same should be put
in place at the earliest. If prolonged operation without
telemetry continues, POSOCO should approach Central
Commission.
Action: RPCs, POSOCO
Time Frame: 6 months
The status of availability of Telemetry from various stations is being monitored
closely by the RLDCs/NLDC. In case of non-availability of data from any location,
the matter is being taken up with the concerned agency.
NRPC and ERPC have also taken up the matter with the ISTS users at OCC / RPC
forum and are monitoring the same.
12
S.No. RECOMMENDATIONS Action Taken
9.16
Large variations are observed in time taken for initiation of
unit start up (Boiler light up) by the stations after
availability of start-up power and also for start ups/light up
of subsequent units. While subsequent start-ups were very
fast (10-20 minutes) in some of the units, in other cases
they took considerably longer time – several hours. Reasons
for the delays in attempting first start-up and subsequent
start-ups may be examined by the utilities in consultation
with CEA. A standard procedure for preparatory activities
and sequence of start up may be put in place by the stations
to restore units as early as possible particularly in
contingencies.
Action: CEA, Generating Utilities and RLDCs
Time Frame: one year
Meeting was taken by Member (GO&D), CEA on 28th
Aug., 2012 with POSOCO,
NTPC & NRPC to examine delay in extension of start-up power to thermal power
stations, wherein suggestions have been made to accelerate the process. Minutes have
been sent to RPCs & CERC for discussion / implementation / suitable action on the
suggestions and feedback to CEA. Gist of the suggestions enclosed at Appendix-II.
Action plan prepared by CEA in this regard has already been circulated to all
Generators in NR and generators have been requested to work on the action plan and
implement the same.
Member (Thermal), CEA is also studying the matter and likely to come up with the
recommendations thereon soon.
9.17 At inter-State level, the entire landscape has changed over
past few years. With de-licensing of generation and
provision of open access in Electricity Act, 2003 and
development of organized electricity markets, lot of
generation is coming in the form of merchant generation.
Four out of the five regions have been integrated and
formation of National Grid is on the horizon. Under such
scenario, there is need to review the Transmission Planning
criteria.
Action: CEA
Time Frame: 3 months
The review of transmission planning criteria has been completed by CEA. The
revised transmission planning criteria has been circulated to all concerned.
9.18 There is need to reinforce system study groups in power
sector organisations to analyse the system behaviour under
different network status/ tripping of lines/outage of
generators. Where these do not exist, these should be
created.
Action: CEA, CTU and STU
Time Span: one year
CTU is procuring system study software for distributing to various utilities. First
phase of training programme on system studies has been held in September 2012,
where software was distributed to STUs of Northern Region. Similar activity has
been completed in SR in October 2012 and will be repeated in other regions also by
the CTU.
13
S.No. RECOMMENDATIONS Action Taken
9.19
It was felt that a separate task force may be formed,
involving experts from academics, power utilities and
system operators, to carry out a detailed analysis of the
present grid conditions and anticipated scenarios which
might lead to any such disturbances in future. The
committee may identify medium and long term corrective
measures as well as technological solutions to improve the
health of the grid.
Action: MOP, CEA
Time Frame: 1 month
The Task Force has been constituted by MoP on 13-12-2012. The Task Force held
meeting five meetings since then. The fifth meeting was held on 8th
March 2013. The
Task Force has initiated the study on present grid conditions and anticipated
scenarios. Relay coordination and general philosophy on islanding scheme is also
under study.
9.20 For smooth operation of grid systems, it is absolutely
important that all the power generating and distributing
stations are connected on a very reliable telecom network.
(i) A proper network may be built up preferably using
MPLS (Multi Protocol Label Switching) which is simple,
cost effective and reliable. In remote place where
connectivity is a problem, the stations can use dedicated
fibre cable from the nearest node.
(ii) Since POWERGRID has its own fibre optic cables,
practically covering all major nodes and power stations, a
proper communication/IT network may be built using
dedicated fibres to avoid any cyber attack on the power
system.
Action: CTU, STUs
Time frame: 1 Yr
CTU have informed that they already have a dedicated independent communication
network in place. Further, they are in the process of developing a Grid Security
Expert System (GSES) at an estimated cost of about Rs.1300 Crore which involves
laying of optical fiber network costing about Rs.1100 Crore for reliable
communication and control of under-frequency & df/dt relay based load shedding,
etc. System will include substations of 132 kV level and above.
14
Appendix-I Abstract of protection audit in NR
Basic Protection Audit for all 132 nos. of important sub-stations/switchyard was carried out by POWERGRID in association with CPRI in six phases. The audit had indicated following deficiencies of critical nature:
(i) Replacement of distance relays of static type with Numerical type
(ii) Non-availability/ non-functioning of bus bar protection
(iii) Non-availability/non-functioning of Single Phase Auto Recloser Scheme
(iv) Non-availability/ non-functioning of Disturbance Recorder (DR) and Event Loggers (EL)
(v) Non-availability/ non-functioning of Local Breaker Back up protection
(vi) Earth fault in DC system
(vii) Time synchronization of Disturbance Recorder (DR) and Event Logger (EL)
(viii) Problems relating to DG set
(ix) Problems relating to PLCC/protection coupler
The issue of rectifying the above deficiencies was discussed in the 19th Protection Sub-Committee meeting held on 21.11.2012 and thereafter in the 24th TCC/27th NRPC meetings held on 29th /30th November 2012. During the discussions, it emerged that while some of the deficiencies can be rectified in a short period of about 03 months, the deficiencies which require procurement of new equipment may take about a year. The utilities were advised to submit action plan/action taken to rectify deficiencies observed. So far, only Rajasthan, NHPC, HVPNL, THDC and Karcham Wangtoo Hydro Power Station have submitted the action taken on the deficiencies observed.
15
Appendix-II
Suggestions made at the meeting taken by CEA to examine delay in extension of start-up power
CEA had taken a meeting on 28.08.2012 wherein representative from POSOCO, NTPC and NRPC Secretariat were present. In this meeting, it was decided that following actions would help in accelerating the process restoration of the grid and should be discussed in RPC forum for the purpose of monitoring & implementation and feedback forwarded to CEA :
1. All generating stations with self-start facility should be advised clearly to start their unit(s) on house load without waiting for any code / instruction from any agency / authority. However, such generating stations should charge a transmission line, only after receiving a go-ahead signal from the concerned Area LDC / SLDC / RLDC / neighboring substation / generating station for extending the supply further.
2. Various groups need to be formed & trained in each power station / substation to carry out specific tasks so that they may carry out those tasks efficiently during an emergency like a grid-failure.
3. Communication systems needed to be improved between RLDC and SLDCs, SLDCs and Area LDCs, and Area LDCs and substations in the area. This would improve coordination among them and help in connecting proper load during restoration process of the grid.
4. Fixation of charges by CERC for the start-up power extended by a power station to any other power station / utility would eliminate the commercial constraint in quick extension of start-up power. No power station should refuse extension of start-up power during emergencies for any reason except due to a valid technical constraint. The matter may be referred to CERC.
5. POSOCO should evolve a procedure to send communication regarding any grid disturbance to all the power utilities of the country immediately. This might involve the use of SMS on mobiles of heads of different agencies along with posting of preliminary report about the incident on the website of POSOCO for those who want to know the details. This report should be updated periodically, say on hourly basis, after the disturbance. This would help healthy parts of the grid take preventive action and avoid spread of disturbance to those areas. This is also likely to facilitate quick restoration of the grid by getting quick start-up supply from healthy areas.
6. Mock exercise should be carried out regularly by the power stations / substations, particularly those which generally play a prominent role in restoration of the grid. To ensure that the mock exercise was actually carried out by the power station in a realistic manner, the power station concerned should be required to submit a certificate to this effect from an independent 3rd party.
7. POSOCO would send the list of all those central / state transmission lines, which are used for extending the start-up power from a power station / substation to another, to CEA to monitor their healthiness. This list with CEA would be kept updated by POSOCO after each review of the restoration procedure.