23
(SIX MONTHLY PROGRESS REPORT) (Oct 2013 to March 2014) Status of Environmental Management Plan Teesta VI (500 MW) HEP M/s TEESTA HYDRO POWER. LTD. (Formerly Known as Lanco Energy Pvt. Ltd.) Teesta Hydro Power Limited (Formerly Known as Lanco Energy Pvt. Ltd.) Plot No.-404-405, Udyog Vihar, Phase No-III Gurgaon, Haryana-122016

Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Embed Size (px)

Citation preview

Page 1: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

(SIX MONTHLY PROGRESS REPORT)

(Oct 2013 to March 2014)

Status of Environmental Management Plan

Teesta VI (500 MW) HEP

M/s TEESTA HYDRO POWER. LTD.

(Formerly Known as Lanco Energy Pvt. Ltd.)

Teesta Hydro Power Limited (Formerly Known as Lanco Energy Pvt. Ltd.) Plot No.-404-405, Udyog Vihar, Phase No-III Gurgaon, Haryana-122016

Page 2: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power. Ltd, 500 MW Teesta VI HEP

INDEX

S.No. INDEX Page No.

1 “Six Monthly Progress Report” for the period ending March -2014

2-4

2 Status of implementation of EMP Annexure I(5-17)

a) Solid waste collection and disposal 5

b) Muck Management and River Protection 5-6

c) Air Pollution Management 6-7

d) Water Quality Management 7

e) Control of Pollution from Labour Camps 7-8

f) Environment Management during Road Construction

8

g) Public Health Delivery System 8-11

h) Safety Measures 11-13

i) Community Kitchens 13

j) Forest Protection Plan 13-14

k) Catchment Area Treatment Plan 14-16

l) Employment Opportunities 16

m) Economic Opportunities 16

n) Social Welfare Activities 17-18

O) present status of construction activities 19

3 MoEF Compliance towards MoEF Environmental Clearance

Annexure II(20-23)

Page 3: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power. Ltd, 500 MW Teesta VI HEP

1.500 MW Teesta VI HEP of M/s LANCO Teesta Hydro Power Private Limited “Six Monthly Progress Report” for the period ending April .2014.

1. Name of the Project Teesta VI Hydro Electric Project

2. Type of the Project River Valley hydro Electric Project (Run off the River)

3. Clearance Letter(s) OM No. & Date a) Environment Clearance

b) Forest Clearance

a. No. J-12011/55/2006-IA.I dated 21st September 2006.

b. 1004/1004(394-1)/ FEWMD on 29th May 2008

4. Locations 1. District 2. State 3. Latitude 4. Longitude

South Sikkim Sikkim 27° 10’42”N 88° 30’40”E

5. Address for correspondence: a) Address of concerned Project Head ( with Pin code and telephone/fax nos)

Mr C.V.P. Rao LTHPL,TEESTA VI HEP Majitar,East Sikkim-737136 Sikkim Contact No- 08016097236 Fax No. 03592-246053

6. Address of concerned Project

Head at Corporate Office

Chief ( with Pin code and

telephone/fax nos)

Mr. S.R Ganguly

SPV Head

Lanco Teesta Hydro Power Ltd.

Plot No: 397, Udyog Vihar, Phase III

Gurgaon, Haryana- 122016.

Office No- 0124-4741000

Fax No- 0124-4741400

7 Break-up of the project area (land details)

Page 4: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power. Ltd, 500 MW Teesta VI HEP

a) Submergence area Forest Non Forest

b) Others Forest Non Forest

36 Ha

0.00 Ha

53.426 Ha

32.134Ha

8. Breakup o f the project affected population with enumeration of those losing houses/ dwelling units only, agricultural land only. a) SC /ST /Adivasis b) Others

Nil Nil

9. Forest land requirements Status of approval for diversion of forestland for non-forestry use

89.4266 Ha- As per Forest Clearance letter- 1004/ 1004 (394-1) /FEWMD ON 29th May 2008.

10. Status of construction Date of commencement (actual and/or planned)

Nov 2008

11. Reasons for the delay, if the project is yet to be started

Not applicable

12. Details of Site Visit

a) By Regional Office

b) By Monitoring

Committee

13. Construction activities and status of Implementation of EMP

The details of the present status of the construction activities and the status of implementation of EMP are attached as Annexure-I

14 Brief note on the status of compliance of the conditions stipulated by MoEF

Status of compliance of the conditions stipulated by MOEF is enclosed as Annexure- II

Page 5: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power. Ltd, 500 MW Teesta VI HEP

Annexure-I

Status of implementation of EMP as per the progress of the construction

a) Solid waste collection and disposal

Vats fixed at various project sites for collection and disposal of solid waste at appropriate site.

Dustbin at the Project area

b) Muck Management and River Protection

• Environmentally friendly measures undertaken for dumping of Muck at designated dump yards. • Dump yards are provided with adequate retaining structures such as crate walls, RRM walls, etc. as per requirement. • The nallah and river sections are provided with adequate protection measures such as crate wall and concrete plugs. • The portals of tunnels are provided with silt & sludge settling tanks. In the event of any damages due to landslides etc, the same will be rectified.

Page 6: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Pvt. Ltd, 500 MW Teesta VI HEP

Muck Management

River Protection & Road protection work

c) Air/Noise Pollution Management

• M/s SGS Kolkata has been appointed for monitoring of ambient Air quality& Noise levels and is carrying tests on periodical basis.

• Application for Renewal of Consent to Establish for 500 MW Teesta VI HEP under Air Act, 1981, under Water Act & DG Sets is under process.

• Water Sprinklers/Miller are used on regular basis in project roads to control the Fugitive dust (SPM).

Air Pollution control measures at Site

Page 7: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Pvt. Ltd, 500 MW Teesta VI HEP

Noise Monitoring at Site

d) Water Quality Management

• Four number of water sampling locations have been identified in project area to monitor water quality of Teesta River and the adjoining streams. The main parameters are being analyzed by M/s SGS Kolkata.

• Renewal of Consent to Establish 500 MW Teesta VI HEP under Water Act, 1974, is under process.

• Settling tanks have been constructed at each portal site to arrest the sediments and sludge coming along with the tunnel water before discharging.

Settling Tank & Sampling for Water Monitoring

e) Control of Pollution from Labour Camps

• Maximum labourers in the project site are residing in the labour camp at Power House & Barrage site equipped with good sanitation facilities.

• Labourers are using Kerosene Oil/LPG for their cooking purpose. • Community Toilets are available with proper Septic Tanks & Soak pits for labors and staff in

the labourer camp

Page 8: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Pvt. Ltd, 500 MW Teesta VI HEP

Labour Camp and Community Toilets

f) Environmental Management during Road Construction

• Roads are constructed using cut and fill method. The muck retaining structures like RCC wall and Crate walls are constructed towards valley side and the RRM walls, Plumb walls or dry walls are constructed towards the hillside of the roads for protection purpose.

Plantation are carried out on both sides of constructed Road depending upon the availability of space.

RCC Road Side Protection & Road Side Plantation

g) Public Health Delivery System

• Dispensaries have been established at both Barrage and Power House Sites.

• Complete health screening and periodic health checkups of labourers are

carried out on regular basis. Free of cost medical facility is provided to

Project employees as well as villager

• Health camps were organized for local people at Barrage (Lot1 area)

Page 9: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Pvt. Ltd, 500 MW Teesta VI HEP

• Blood donation camp was organized on 1st October 2014 in which

31 employees donated blood. • In addition, medical team of Lanco is engaged in providing medical

facilities to project-area villages as well as people from other nearby areas.

• LANCO Mobile H e a l t h service provides medical facilities to 10 villages a d j o i n i n g project area on free of cost basis.

Blood donation Camp at Sirwani Dispensary

Health Camp at Barrage site HIV/AIDS awareness Programme at Barrage site

Page 10: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Ltd, 500 MW Teesta VI HEP

Women & Child Health Camp Health Check Up at Project Site & in Nearby Villages

Patients who benefitted by LANCO Mobile Medical facilities in the Period of October 2013 to April 2014

.

Number of Patients benefited 4431

During reporting period, 4431 persons benefited through 150 Mobile Health camps. About 9011 persons benefited during the financial year 2013-14 through 302 camps.

h) Safety Measures.

• P o s t e r s and slogans a r e used extensively to spread awareness among the laborers

about importance of safety

• Safety instructions are given to laborers and staff regularly for each and every

activity which includes tunneling.

Page 11: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Ltd, 500 MW Teesta VI HEP

• Safety department with Safety Officers and supervisors have been appointed at site for

effective monitoring and implementation of Safety related issues.

• All labourer and staffs are being p r o v i d e d with PPEs such as full body ha r nes s , high

visibility j a c k e t s , Helmets, Safety shoes, Gloves, Gumboots, etc. as per

work requirement.

• T o o l b o x talk conducted at project site on regular basis.

Safety Instruction at project site

Page 12: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Ltd, 500 MW Teesta VI HEP

Environmental & Safety training conducted at project site

i) Community Kitchens

• LTHPL & its C o n t rac t o r s have established s e v e n no. of C o m m u n i t y K i t c h e n s covering staff of whole project construction area.

• Hostels are equipped with recreation facilities like Televisions etc.

Community Kitchen for staff

(j) Forest Protection Plan

Forest Dept. monitors the trespasses by installing a check post at Pamphok Village.

To maintain the Forest cover and the environment of the region, a Forest Protection Plan i s be i ng implemented by F o r e s t Department at a cost o f Rs 78 L a k h s . Entire amount has been deposited in CAMPA Fund as a part of forest clearance in May 2008.

Demarcation and fencing of diverted forestland has been done to avoid damage to nearby area not diverted for the purpose.

Page 13: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Ltd, 500 MW Teesta VI HEP

Forest Check Post Construction

(k)Catchment Area Treatment Plan & Compensatory Afforestation Scheme

• Rs. 9.82 Crores has been d e p o s i t e d in CAMPA funds for the implementation of CAT works by State Forest Department.

• Rs 1.41 Crores has been deposited in CAMPA funds for implementation of revised CAT works by State forest department

• Rs. 1.14 Crores deposited towards the implementation of Compensatory Afforestation.

• Rs 5.68 Crores deposited in CAMPA Funds towards Net Present Value of the Forest cover in the project area.

Expenditure incurred CAT Plan of Financial Year (2010-11& 2011-12)

S.no Financial year Work executed Expenditure(East) in Rs

Total Amount

1 2010-11 Forest Land:

• Jhora training in Sausage wall(Crate wall)

• Dry Stone wall

• Catch water drain

• Bally Benching

• Barbed wire fencing

• ANR

• Vegetative fencing

41.94 Lakhs

86.97 Lakhs

2 Agri- Land:

• Jhora training in Sausage wall(Crate wall)

• Dry Stone wall

29.56 Lakhs

Page 14: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Ltd, 500 MW Teesta VI HEP

• Catch water drain

• Bally Benching

3

Medicinal Plantation

15.47 Lakhs

4 2011-12 • ANR

• Small Bamboo(Pareng)

• Medicinal Plant Plantation

• Artificial Regeneration

• Bally Benching( In Forest Land)

• Fodder (Broom) Plantation.

• Maintenance of ANR

• Maintenance of Medicinal Plantation.

• Vegetative Fencing

50.56 lakhs

50.56 lakhs

S.no Financial year

Work executed Expenditure(South) in Rs

Total Amount

1 2010-11 Plantations/Nursery creation 3,25,0000.00

3,054,73,29.00

2 2010-11 Engineering measures 1,44,27,974.00

3 2011-12 Engineering measures

(CWD)

3,86,941.00

4 2011-12 Plantations/overhead. 1,046,5190.00

5 2011-12 Seedlings cost for plantation. 20,17,224.00

Page 15: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Ltd, 500 MW Teesta VI HEP

Work executed against CAT Plan

(l)Employment Opportunities

Based on the skills and qualification, the employment preference has been given to local people and is employed in project activities.

(m) Economic Opportunities

Award of the petty contract- Local people have been given contract for activities like construction of drainage along the roads, protection works along new cuttings, plantation work, bush cleaning in the construction sites, etc. to benefit and facilitate economic opportunity.

Vehicle hiring- Vehicles o f l o c a l s are hired t o provide them economic benefits.

Contract for supply of ration and other material for community kitchen have been given to local vendors.

Buildings of locals are being ren ted for office setup & staff accommodation

Page 16: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Ltd, 500 MW Teesta VI HEP

(n) Social Welfare Activities

M/s LTHPL has undertaken f o l l o w i n g a c t i v i t i e s on regular basis for larea development-

CSR Activities

Place of Work

School Kit and note book distribution program

No CSR Activities Beneficiaries Location

1 Distribution of school kits 247 students Namthang senior

secondary school

2 Organising medical health camps at

project affected villages

4431 Project Vicinity(South

and East districts)

3 Providing free medical check-up and

medicines for labourers and their

families

Karek, South Sikkim

4 Blood donation camp at Sirwani

Dispensary.

31 employees

5 Note book distribution for school

students.

About 13600 note

books distributed

Project Vicinity

Page 17: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Ltd, 500 MW Teesta VI HEP

Community infrastructure development

Constructed Community Hall in village Turung

Constructed Irrigation channel & water supply tank for villagers

Page 18: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Ltd, 500 MW Teesta VI HEP

O) Present status of Construction Activities

The component wise progress is summarized as below:

Structures Status as on May 2014

Barrage 98%

Desilting Structure (including Desilting Inlet and Chambers) 26%

HRT (Heading Excavation) 36%

Surge Shaft 70%

Pressure Shaft 70%

Power House(Civil works) 78%

E&M Works 50%

HM Works 53%

Page 19: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Ltd, 500 MW Teesta VI HEP

Annexure II Conditions and Compliances towards MOEF Environmental Clearance

Sl. No. Conditions Status i) Biodiversity Conservation Plan as

proposed in the EMP should b e implemented in toto in the identified location.

Being Complied. Rs.1,69,12,000 has been deposited with the nodal agency i.e, Forest department, Govt. of Sikkim and Rs. 1,83,53,000 for Soil Conservation and Forest

ii) For propagation of migratory fishes a fish f a r m / hatchery s h a l l be developed a s proposed v i d e letter dated 18th August 2006.

Being Complied. • Project consultancy has been

given to NRCCWF, Bhimtal. • The scientists from

NRCCWF, Bhimtal have v i s i te d the site & identified the site for development of Fisheries farm.

• Project report has been approved by Fisheries department.

• Further Rs. 50 lakhs has been deposited with state Forest department

iii) Catchment area treatment s h a l l be according the stipulated clearance.

Rs.9.82 c rore has b e e n deposited with Forest department to carry out the works and further Rs 1.41 Crore has been deposited for r e v i s e d CAT p l a n with Forest department.

Page 20: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Ltd, 500 MW Teesta VI HEP

Sl. No. Conditions Status iv) Landslide prone area tunneling

should be done with great care. For land slide prone area tunneling is being carried out with proper controlled blasting and providing adequate support system

v) Monitoring committee shall be constituted which must include representative from affected person from SC/ST category and a women beneficiary.

Complied

vi) All t h e assurance/commitment must be honored in letter and spirit.

Being complied

vii) Clearance shall be obtained for acquiring forest land and submitted.

Forest Clearance obtained

viii) “During lean season, 10% of available water (82.5 cumec), should be released downstream of dam for sustenance of aquatic life”.

We have provided two No(s) of MS pipes of 800 dia with knife edge valves in the river intake pier to release 10% of available water (82.5 cumecs) regularly downstream of dam for sustenance of aquatic life.

viii) Any o t h e r clearance from any o t h e r organization if required should b e obtained.

All required clearances are being obtained as per requirement

PART-B i) Adequate free fuel arrangement should

be made for the labour force engaged in the construction work at project cost so that indiscriminate felling of trees is prevented.

Free f u e l ( LPG & Kerosene) i s p r o v i d e d to the manpower engaged.

ii) Fuel depot may be opened a t the site to provide the fuel (kerosene/wood/LPG).Medical facilities as wel l a s recreat ional facilities should also be provided to the labourers.

Being procured as and when required from the local market.

iii) All t h e labourers to be engaged for construction works should also be thoroughly examined by health personnel and adequately treated before issuing them work permit.

The medical Health Checku ps & Health monitoring a r e carried o u t at all the Project Sites. Dispensaries have been set up at both Barrage and power house.

Page 21: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Ltd, 500 MW Teesta VI HEP

iv) Restoration of construction area including dumping area with levelling, filling up of burrow pits, landscaping etc. area should be properly treated with suitable plantation.

The restoration of dumping areas shall be taken up as the dumping get completed in those areas, leveling & feeling works of the project area is being done & duly protected by way of Crate walls, the tree plantation in the project area & along the project road are being done

Sl. Conditions Status v) Financial measure shall be made in

the total budget for safeguard measures

Separate budget for execution of safeguard measures is provided

vi) A multidisciplinary committee should be constituted with representatives from various disciplines of forestry, ecology, wildlife, soil conservation, NGO etc. to oversee the effective implementation of the suggested safeguard measures.

Complied.

vii) Six monthly monitoring reports should be s u bm i t t ed to the Ministry and its regional Office, Shilong for review.

Being Complied

viii Officials from Regional O f f i c e MoEF, Shilong who would b e monitoring the implementation of environmental safeguards should be given full cooperation, facilities and documents/ data by the project proponents during their inspection.

Being Complied

ix The responsibility of implementation of environmental safeguards rests fully with the M/s Lanco Energy Private Limited & Government of Sikkim

Noted

x Project require fresh appraisal in case of change in the scope of the project

Noted

xi Ministry reserve right to add additional safe guards and to ensure effective implementation of suggested safeguard in time bound and satisfactory manner

Noted

xii Valid for 5 year from date of issue of this letter

Noted

Page 22: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Ltd, 500 MW Teesta VI HEP

xiii A copy of letter needs to mark to concerned panchayat, Local NGO and those from whom any suggestion/representation has been received.

Complied

xiv SPCB shall display a copy clearance letter to regional office, District Industries Center and Collector’s office/Tahsildar office for 30 days

Complied

xv Within seven days Project Proponent shall advertise in two local Newspaper circulated in vernacular language of the locality concerned

Complied

Page 23: Status of Environmental Management Plan Teesta VI (500 … Yaerly Environment Clearance... · SixMonthlyReporton EMP FromOct 2013 –March 2014 Teesta HydroPower. Ltd, 500 MWTeestaVI

Six Monthly Report on EMP From Oct 2013 –March 2014

Teesta Hydro Power Ltd, 500 MW Teesta VI HEP