STATUS OF THE ALICE MAINTENANCE AND OPERATION BUDGETS – CATEGORIES A &B 30 th meeting of the ALICE RRB C. Decosse CERN-RRB-2011-035

Status of the ALICE Maintenance and Operation budgets – Categories A &B

  • Upload
    lyndon

  • View
    43

  • Download
    0

Embed Size (px)

DESCRIPTION

CERN-RRB-2011-035. Status of the ALICE Maintenance and Operation budgets – Categories A &B. 30 th meeting of the ALICE RRB C. Decosse. Report on 2010 M&O-A income, outstanding contributions and expenditures 2011 Incomes and outstanding contributions 2011 current expenditures - PowerPoint PPT Presentation

Citation preview

Page 1: Status of the ALICE Maintenance and Operation budgets – Categories A &B

STATUS OF THE ALICE MAINTENANCE AND OPERATION BUDGETS – CATEGORIES A &B30th meeting of the ALICE RRB

C. Decosse

CERN-RRB-2011-035

Page 2: Status of the ALICE Maintenance and Operation budgets – Categories A &B

30th meeting of the ALICE RRB 2

Report on 2010 M&O-A income, outstanding contributions and expenditures

2011 Incomes and outstanding contributions 2011 current expenditures M&O-A 2012 preliminary budget and

estimates for the period 2013-2015 M&O-A preliminary sharing M&O-B 2012 preliminary budgets and

estimates for the period 2013-2015

Page 3: Status of the ALICE Maintenance and Operation budgets – Categories A &B

30th meeting of the ALICE RRB 3

M&O-A INCOMES AND OUTSTANDING CONTRIBUTIONS 2002-2010

Closing date 31/12/2010

Unit: KCHF

Outstanding paid early 2011:Greece 43 kCHFCroatia 22 kCHFRussia 25 kCHF

Still due for 2002-2010Poland 36 kCHFBrazil 24 kCHFChina Beijing 13 kCHFJINR 34 kCHFUkraine 41 kCHF

Over paidArmenia + 5 kCHFUSA DOE + 77 kCHF

Page 4: Status of the ALICE Maintenance and Operation budgets – Categories A &B

30th meeting of the ALICE RRB 4

2010 M&O-A EXPENDITUREIN KCHF

Page 5: Status of the ALICE Maintenance and Operation budgets – Categories A &B

30th meeting of the ALICE RRB 5

M&O-A SUMMARY 2002-2010CASH BALANCE: INCOME AND PAYMENTS IN KCHF

Page 6: Status of the ALICE Maintenance and Operation budgets – Categories A &B

30th meeting of the ALICE RRB 6

M&O-A INCOME AND OUTSTANDING 2002-2011 (AS 8 APRIL 2011 IN KCHF)

Page 7: Status of the ALICE Maintenance and Operation budgets – Categories A &B

30th meeting of the ALICE RRB 7

2011 M&O-A EXPENDITURES IN KCHF AS BEGINNING OF APRIL 2011 – POWER NOT INCLUDED

Page 8: Status of the ALICE Maintenance and Operation budgets – Categories A &B

30th meeting of the ALICE RRB 8

PRELIMINARY 2012 M&O-A BUDGET AND COST ESTIMATES FOR 2013-2015 IN KCHF

Budget prepared with the following operating model a 2-months Technical Stop (Jan-Feb 2012) followed by a 10-months Running (Mar-Nov 2012) and a 17-months Shutdown (Dec 2012-Apr 2014).

Request will be reviewed by the SG over Summer.

Page 9: Status of the ALICE Maintenance and Operation budgets – Categories A &B

30th meeting of the ALICE RRB 9

2012 M&O-A SHARING

Preliminary numbers based on 1/9/2010 heads count

No rebate on energy in 2012 since the 2010 budget was totally spent

Page 10: Status of the ALICE Maintenance and Operation budgets – Categories A &B

30th meeting of the ALICE RRB 10

2012 PRELIMINARY M&O-B IN KCHF

Page 11: Status of the ALICE Maintenance and Operation budgets – Categories A &B

30th meeting of the ALICE RRB 11

2012 PRELIMINARY M&O-B BY FUNDING AGENCIES

IN KCHF

Page 12: Status of the ALICE Maintenance and Operation budgets – Categories A &B

30th meeting of the ALICE RRB 12

M&O-B ESTIMATES FOR 2013-2015 IN KCHF

Page 13: Status of the ALICE Maintenance and Operation budgets – Categories A &B

30th meeting of the ALICE RRB 13

MOUS

South Africa recently signed addenda to the MoUs Two addenda under preparation with Indian

institutes (Bose Inst. Kolkata and Gauhati University) which joined the Collaboration in 2011.

Pending signatures: Brazil and China