Upload
harry-perry
View
213
Download
0
Tags:
Embed Size (px)
Citation preview
Status report on studying and Status report on studying and preventing ageing in the LHCb preventing ageing in the LHCb
OTOT
S.Bachmann (on behalf of the LHCb OT group)
Physikalisches Institut Heidelberg
Many thanks to A.Pellegrino and U.Uwer for providing material!
LHCC Referee Meeting, Sep 24, 2007
Outer Tracker Aging Investigations on Outer Tracker Aging Investigations on Ageing:Ageing:
StatusoUnderstanding ageing:
Epoxy (Araldite AY103) has been identified as cause for ageing.
oPreventing ageing:
Main line:
Long term flushing + heating of modules.
More studies on:
Adding new component to gas, i.e. oxygen (beneficial) and CF4 (non-beneficial).
HV training (inspection of wire after training, long term).
Detailed study of chemical properties of AY103/HY991.
Glue Tests in Mini OT Modules:Glue Tests in Mini OT Modules:Constructed mini OT modules to test effect of different glues
o 32 channels, 1m longo materials and procedure in so far as possible from mass production
Could consider constructing a real OT module with different glue (e.g. Tra-Bond 2115 epoxy, from TRA-CON) to test our ability to produce modules not affected by the ageing problem
o availability of components (F or S module?)
Araldite at straw entrance:Araldite at straw entrance:No araldite used:No araldite used:
Test module (straws):480 hrs, 20mCu
Finding the culprit for ageing using Finding the culprit for ageing using an openable test chamber:an openable test chamber:
Glue Tests in Openable ChamberGlue Tests in Openable Chamber
Normal F-module:20 hrs, 20mCu
Openable chamber:17 hrs, 2 mCu
Gas flow
Glue Tests in Openable Chamber Glue Tests in Openable Chamber (cont’d)(cont’d)
Openable chamber:17 hrs, 2 mCu
Gas flow
o Irradiation damage related to gas flow
• Pollution transported
o no ageing if glue is removed
out-gassing of AY103/HY991
Effect of long term flushing:Effect of long term flushing:
Taken from PhD thesis T. Haas
Exponential to black dots
c = 18.3 m3
c = 22.6 m3
c = 15.7 m3
cVole
Note: All detectors have been installed and continuously flushed since
November ’06 (C-side) and June ’07 (A-side)
• A warm-up of the modules (10 days at 40oC while being flushed) leads in many cases to additional improvement.
12% 10% 14% 10%
43h 112h
Before heating
After heating
20h 90h
source
Effect of heating:Effect of heating:
• Summary of the heating of nine modules (taken from PhD thesis T.Haas)
Preparation of possibility to warm-up the modules
Bar to protect the modules
Electrical Heating blankets:
-4 blankets per side
-8 blanktes per C frame
Avoid heating of the vertical C arm
5950
475
985
475
5000
Heating area
First Prototype
2 point regulation
Temperature
sensors
Uniformity test in vertical position:
2 blankets on mini C frame w/ 4 modules
Measured between module & blanket
Measured between modules
Temperature results in vertical position
Module length
Heat sink at bottom
Larger heating zones also work
Tnominal ~40 oC Tnominal ~40 oC
2oC
2oC
Installation at the pit
Lessons learned from prototypes:Lessons learned from prototypes:
5160
520 5202060 2060
•electrical and mechanical design ok
•homogeneous warm-up of a complete frame possible
•account for possible heat sinks located at the upper and lower C frame arm Modification of the heating zones:
•Still to be checked that no heat is spread to the vertical arm of the C-frame (1st warm-up test is situ planned after LHCb Magnet test)
Monitoring ageing in situ:Monitoring ageing in situ:Module Scanning Tool for ageing-test in situ is ready for installation (using 90Sr radioactive source(s))
Monitor evolution of module performance under continuous flushing
Give Feed-Back about heating Monitor long-term effects during regular beam operations (tool “parked” out of acceptance, usable during access)
C-Frame Warm-Up StatusC-Frame Warm-Up StatusStatus
oA full set of blankets (improved design) has been ordered
• 1st blanket ready, being checked at Heidelberg, test at LHCb after Magnet Test
oExpect delivery of remaining blankets by end of October
oControl system (including safety interlocks) being worked on Monitoring
oPrepare ageing-test system to be operated in situ to (sample) check results of warm-up
• Scanning tool being built
o During 1st warm-up, careful monitoring of the mechanical clearances that could be affected (e.g. module supports)
• special attention to the temperature monitoring in the vicinity of the RICH2
C-Frame Warm-Up OutlookC-Frame Warm-Up OutlookRealistic (pessimistic?) scenario:o fully operation from the beginning of Novembero serial operations (one C-Frame at the time)
Side C
Side A
Backup slides
Update on Ageing Studies:Update on Ageing Studies:Although attention focused on preparations for warming-up and monitoring tools in situ, a number of ageing studies was carried on during the summer:
o Further warm-up tests on the bench with F and S modules• (see summary talk(s) from September 2007 LHCb Week)
o Resume studies with added O2 to gas mixture
• (see summary talk(s) from September 2007 LHCb Week)
o Further investigations of treatment with high-currents (direct and reverse polarity)
• wire inspection after treatmento Studies with openable test vessel to establish origin of the problem
o Detailed studies of the AY103/HY991 properties (degree of polymerization, out-gassing, etc.) in cooperation with the CERN chemistry department (P. Chiggiato, R. Setnescu, I. Sorin, B. Teissandier, D. Letant-Delrieux, …)
• studies in progress, joint report in preparation
Cure – Negative HV Training:Cure – Negative HV Training:
Trained straws
Before Training
~60 hours at -1480 V repairs the damage previously inflicted by
irradiation
Cure – Positive HV Training:Cure – Positive HV Training:Gas flow
340 hrs
After HV After HV
340+350 hrs
2nd HV training
1st HV training
3rd HV training• ~20 hours at +1900 V repairs the damage previously inflicted by irradiation
• HV training repeatable
Wire Inspection after HV Training:Wire Inspection after HV Training:
11 Sep 2007
Recommendation of the Ageing Workshop panel:
1: not irradiated, trained
25/17
1: not irradiated, trained1: not irradiated, trained
4: irradiated, trained
12: new wire off the shelf
inspect wire after HV training to check that high currents have no “burning” effects on the anode surface qualityTook various samples of wire from openable chamber from the trained and non-trained region and from the irradiated and non-irradiate region, and compare with wire from new spool
No effect on wire surface from optical inspection (20 50
magnification)
Glue Tests in Mini OT Modules:Glue Tests in Mini OT Modules:Constructed mini OT modules to test effect of different glues
o 32 channels, 1m longo materials and procedure in so far as possiblefrom mass production
Could consider constructing a real OT module with different glue (e.g. Tra-Bond 2115 epoxy, from TRA-CON) to test our ability to produce modules not affected by the ageing problem
o availability of components (F or S module?)