Steering Committee February 11, 2019

Page 2: Steering Committee February 11, - TriMet

Partners

Page 3: Steering Committee February 11, - TriMet

Project Benefits30-minute congestion-proof trip from

Bridgeport to PortlandServes a two-way commute

3

Page 4: Steering Committee February 11, - TriMet

Project Benefits

4

43,000 rides on the line on an average weekday in 2035

1 in 5 commuters on MAX going southbound from downtown during 2035 PM rush hour

Page 5: Steering Committee February 11, - TriMet

SW Equitable Development Strategy (SWEDS)• Ensure opportunities for all current

and future SW Corridor residents• Housing• Workforce development• Business stabilization

• Collaboration with public, private, and non-profit partners

• Pilot programs• Identify pre-light rail investments

Page 6: Steering Committee February 11, - TriMet

6

Page 7: Steering Committee February 11, - TriMet

7

Page 8: Steering Committee February 11, - TriMet

Steering Committee

PMG (executive)

PTL (manager)

Technical staff

CAC and other

community engagement

Decision-making

Page 9: Steering Committee February 11, - TriMet

Near-term design topics

9

Feb Mar Apr May JuneCrossroads routeBonita to Bridgeport routeMarquam Hill Connector type

Park & RidesStation areas

Page 10: Steering Committee February 11, - TriMet

Project Development

10

• Respond to issues in DEIS; define mitigation in FEIS

• Refine project scope, cost• Secure 30% of local funding• Advance design to 30%

Develop designs

Technical review and

cost estimates

Community feedback

2019-2020

Page 11: Steering Committee February 11, - TriMet

Engineering

11

• Advance design to 100%• Secure permits• Begin property acquisition,

early construction

Develop designs

Technical review and

cost estimates

Community feedback

2021-2022

Page 12: Steering Committee February 11, - TriMet

Construction, startup

12

• Full Funding Grant Agreement (FFGA) from Federal Transit Administration (FTA)

• Construction and mitigation• Testing and training

Develop designs

Technical review and

cost estimates

Community feedback

2023-2027

Page 13: Steering Committee February 11, - TriMet

Finance

13

Regional funds for project development• Partner contributions• Regional transportation funding

measure: November 2020

• Federal Transit Administration (FTA) New Starts grant program

Page 14: Steering Committee February 11, - TriMet

Design Team: SWTPSW Transit Partners: AECOM, David Evans & Associates, Parametrix

Akana* Barsum Consulting*Brightside Engagement*CH2MDKS AssociatesDonaldson Enterprises*Elcon Associates*Epic Land Solution, Inc*Faithful+GouldGlobal Signals Group

14

Global Transportation Engineering*IML Services*LTK Engineering ServicesLife Simplified*Maintenance Design Group/HDR*Ott-Sakai & Associates*Shannon and WilsonTriunity Engineering & Management*

* DBE, MBE, and/or WBE

Page 15: Steering Committee February 11, - TriMet

Design Team: UDIGUrban Design Integration Group: ZGF, VIA, Mayer-Reed

2. Ink studio*ALTA Planning & DesignArchitectural ApplicationsCarleton HartCascadia Partners**Consult: Ron Stewart**DAO Architecture*Donaldson Enterprises*ECONorthwestFehr & Peers

15

GreenworksHolst Architects*Larco/Knudsen**Merryman Barnes Arch*Marianne Zarkin LA*NNA LA*Pacific HabitatWinterbrook Planning*** DBE, MBE, and/or WBE** ESB

Page 16: Steering Committee February 11, - TriMet

Crossroads

Page 17: Steering Committee February 11, - TriMet

LPA• Steering Committee

directed more study of Refinement 2 and Alternative B2 prior to the FEIS

• CAC also recommended a third idea

17

Page 18: Steering Committee February 11, - TriMet

Community Engagement• Letter to 60

property owners

• Three meetings attended by 190 people

• 125 comments by email

18

Page 19: Steering Committee February 11, - TriMet

October optionsAlternative B2  from Steering Committee 

Smith Modified  developed by staff

Collins  developed by staff

Refinement 2  from Steering Committee

Smith  from neighbor suggestion

Page 20: Steering Committee February 11, - TriMet

December options

Alternative B2 

Collins 

B2 – station near pedestrian bridgeB2 – station near Barbur*

Collins – station on CollinsCollins – station on Collins w/buses*Collins – station on Barbur*

* New variations

Page 21: Steering Committee February 11, - TriMet

B2 / Collins Comparison

Page 22: Steering Committee February 11, - TriMet

Collins

Page 23: Steering Committee February 11, - TriMet

B2

Page 24: Steering Committee February 11, - TriMet

Route preference• Support for B2• Concerns about Collins: impacts to Woods

Creek, park, businesses and homesCrossroads area• Concern about traffic congestion• Desire for safe, comfortable walking and

biking; easy access between MAX, bus, Park & Ride

What we heard

Page 25: Steering Committee February 11, - TriMet

New information• No significant cost difference between

Collins and B2• Support column for lower-cost I-5

bridge would trigger additional impacts• Complexity of utility conflicts via Collins

Page 26: Steering Committee February 11, - TriMet

Bonita to Bridgeport

Page 27: Steering Committee February 11, - TriMet

Locally Preferred Alternative (LPA) route between Bonita and Bridgeport

• Draft Environmental Impact Statement (DEIS) identified significant traffic issues at Upper Boones Ferry Rd at-grade crossing

• DEIS received hundreds of comments advocating against Village Inn displacement at Bridgeport station

Page 28: Steering Committee February 11, - TriMet

Community Engagement• Letter to 70

property owners

• Meeting attended by 60 people

28

Page 29: Steering Committee February 11, - TriMet

Locally Preferred Alternative (LPA) selected by Steering Committee

74th Ave.

Bonita Rd.

BRIDGEPORT VILLAGE 

Bonita Station 

Upper Boones Ferry 

Station

Bridgeport Station 

Interstate 5

Durham

72nd Ave.72nd Ave.

NORTH

Elevated StructureImpact/Concern

Page 30: Steering Committee February 11, - TriMet

2019 Design Exploration: LPA Elevated Route

74th Ave.

Bonita Rd.

BRIDGEPORT VILLAGE 

Bonita Station 

Upper Boones Ferry Station?

Bridgeport Station 

Interstate 5

Durham

72nd Ave.72nd Ave.

CONCERNS• Long structure and 

property impacts, including Fought Steel

• Elevated alignment carries high cost 

• Calls into question Upper Boones Ferry Station, which has very low projected ridership

NORTH

Elevated Structure

Page 31: Steering Committee February 11, - TriMet

2019 Design Exploration: 74th Ave Route

74th Ave.

Bonita Rd.

BRIDGEPORT VILLAGE 

Bonita Station 

Bridgeport Station 

Interstate 5

Durham

72nd Ave.72nd Ave.

CONCERNS• Property and 

employment impacts• Calls into question 

Upper Boones Ferry Station, which has very low projected ridership

74th

NORTH

Elevated Structure

More alternatives being explored

Page 32: Steering Committee February 11, - TriMet

Via LPA Route: Bridgeport Station east of 72nd Ave2018 DEIS layout

72nd Ave.

Retail

Village Inn 

AB

MAX StationBus Hub 

Park & Ride (P&R)Mobility Plaza

CD

A

B

E

BRIDGEPORT VILLAGE 

Signalized IntersectionImpact or Concern

• Station adjacent to bus hub

• Park & Ride south of Bridgeport Rd, with pedestrian bridge 

• Impact to Village Inn 

CD

NORTH

Pedestrian BridgeTransit Oriented Development (TOD)

EF

Retail

Page 33: Steering Committee February 11, - TriMet

• Station adjacent to bus hub

• Park & Ride south of Bridgeport Rd, with pedestrian bridge 

• Impact to retail site• Potential bus/auto 

traffic conflict• Potential 

redevelopment

72nd Ave.

Retail

AB

MAX StationBus Hub 

Park & Ride (P&R)Mobility Plaza

CD

AB

E

BRIDGEPORT VILLAGE 

Signalized Intersection

CD

NORTH

Pedestrian BridgeTransit Oriented Development (TOD)

EF

Via LPA Route: Bridgeport Station east of 72nd Ave2019 concept B

F

Village Inn 

Page 34: Steering Committee February 11, - TriMet

72nd Ave.

AB

MAX StationBus Hub 

Park & Ride (P&R)Mobility Plaza

CD

AB

BRIDGEPORT VILLAGE 

Signalized Intersection

F

D

NORTH

Pedestrian BridgeTransit Oriented Development (TOD)

EF

F

Via LPA Route: Bridgeport Station east of 72nd Ave2019 concept C

Village Inn 

FC

F

• Station adjacent to bus hub and Park & Ride

• More impacts retail site

• Potential bus/auto traffic conflict

• Potential redevelopment

Page 35: Steering Committee February 11, - TriMet

• Station adjacent to bus hub

• Park & Ride across 72nd Ave, east of Village Inn

• Impact to flex‐office site

• At‐grade crossing of Durham Rd

• Potential bus/auto traffic conflict

• Potential redevelopment

72nd Ave.

Retail

AB

MAX StationBus Hub 

Park & Ride (P&R)Mobility Plaza

CD

AB

BRIDGEPORT VILLAGE 

Signalized Intersection

C

D

NORTH

Pedestrian BridgeTransit Oriented Development (TOD)

EF

Village Inn 

F

Via 74th Ave route: Bridgeport Station west of 72nd Ave2019 concept D

F

Connection to Neighborhood south of Upper Boones Ferry Rd.

Page 36: Steering Committee February 11, - TriMet

What we heard• Concerns from potentially

impacted property owners• Concerns about pedestrian

access, safety• Preference to avoid at-grade

crossings; concerns about traffic • Preference for consolidated

station, bus hub, Park & Ride

Page 37: Steering Committee February 11, - TriMet

Steering CommitteeMarch 119 a.m.Tigard City Hall

CACMarch 76 p.m.Girl Scouts

Bonita to BridgeportFeb 216 p.m.Tigard Library

MarquamHill ConnectorFeb 134 p.m.OHSU

trimet.org/swcorridor