Upload
osdocs2012
View
230
Download
0
Embed Size (px)
Citation preview
8/3/2019 Stevick, Glen Expert Report Only
1/121
Expert Report of Glen Stevick Ph.D P.E
IN THE UNITED STATES DISTRICT COURT
FOR THE EASTERNDISTRICT
OFLOUISIANA
IN RE OIL SPILL by the OIL RIG
DEEPWATER HORIZON in the
GULF OF MEXICO MDL No 2179
on APRIL20 2010
SectionJ
Applies to
The Honorable Judge Barbier
ALL CASES and Mag Judge Shushan210-cv-02771
____________________________________________________________________________
AMENDED EXPERT REPORT OF GLEN STEVICK Ph.D P.E
II
8/3/2019 Stevick, Glen Expert Report Only
2/121
Expert Report of Glen Stevick Ph.D P.E
TABLE OF CONTENTS
FINDINGS
II THE BLOWOUT PREVENTER PURPOSE
STRUCTURE AND DESIGN
The BOP Purpose
BOP Structure
BOP Control 10
Communicating with the BOP 10
Activating the BSR 11
BOP Design 13
Ill THE BOP DESIGN WAS DEFECTIVE BECAUSE
IT RELIED ON SINGLE BSR 15
The BSR was Single Point of Failure for the
DWHBOP 15
The Potential for Off-Center Drill Pipe was
Well Known to BP and Transocean 16
IV TRANSOCEAN USED FLAWED CONDITION-
BASED MAINTENANCE 17
Transocean Failed to Recertify the BOP Every
3-5 Years as Specified by API and Cameron 17
Transoceans Condition-Based Maintenance
is Flawed Because Only Equipment With
Measured Problems or Failures Gets Fixed or
Replaced 19
Problems that cannot be measured are
not considered 19
Need for improved equipment is not
considered 20
21
8/3/2019 Stevick, Glen Expert Report Only
3/121
Expert Report of Glen Stevick Ph.D P.E
Implementing BAST is discouraged 21
BP FAILED TO IMPLEMENT BAST IN THE BOP 21
BP Failed to Implement BAST for the BSR 21
BP and Transocean Failed to Upgrade the
BOP to Include Second BSR 24
BP and Transocean Failed to Upgrade to
Camerons Mark Ill BOP Control Pod 24
BP Failed to Implement BAST by Relying
Solely on MUX Cablesfor EDS 25
BP and Transocean Failed to Implement
BAST by Using EDS-1 Instead of EDS-2 25
VI THE UNDERCHARGED BLUE CONTROL POD
BATTERIES AND INCORRECTLY WIRED
YELLOW CONTROL POD SOLENOID 103Y MAY
HAVE BEEN CONTRIBUTING CAUSES OF THE
BOPS INABILITY TO STOP THE BLOWOUT 26
Undercharged Blue Control Pod Batteries 27
Incorrectly Wired Yellow Control Pod Solenoid
103Y 27
The AMF/Deadman Likely Failed to Actuate
the BSR because of Low Blue Pod Battery
and the Incorrectly Wired Yellow Pod Solenoid 28
The BSR Likely Would Have Completely
Sheared the Drill Pipe and Sealed the Well if
the BSR had been Activated when the Drill
Pipe was Centered 28
8/3/2019 Stevick, Glen Expert Report Only
4/121
Expert Report of Glen Stevick Ph.D P.E
LIST OF FIGURES
Figure The DWH BOP showing the position of annulars and valves
Figure The Cameron BSR used in the DWH BOP
Figure Model of the DWH BOP BSR from the Det Norske Veritas
DNV report
Figure Model of the DWH and BOP from the DNV report
41
8/3/2019 Stevick, Glen Expert Report Only
5/121
Expert Report of Glen Stevick Ph.D P.E
INTRODUCTION
Berkeley Engineering And Research Inc was retained by Halliburton
Energy Services Inc to assess the design of the blowout preventerBOP used at the Deepwater Horizon DWH and the BOPscontribution to the well blowout explosion fire and spill on April 20 2010
At the time of the incident the DWH was in the process of temporarily
abandoning BPs Macondo deepwater well after reaching depth of
approximately 18360 ft 12360 ft below the seafloor in the Gulf of
Mexico G0M
My opinions are based upon the materials and information have
reviewed my analysis of that information my education training
experience and knowledge in the areas of mechanical engineering failure
analysis and design and material behavior and my knowledge of oilfield
and offshore equipment e.g offshore platforms BOPs casings and drill
strings
My opinions are also based upon the engineering standard of care
standards recommended practices and regulations relevant to
offshore oil and gas exploration and drilling and production activities
have not been asked to make any assumptions nor have presumed
anyfacts
beyondthose which are cited as material relied
uponin this
Reportand its attachments
FINDINGS
Based upon my education training experience in hydraulics electronic
controls and offshore mechanical engineering design review of Phase
and Phase II forensic testing and examination of the DWH BOP my review
of supporting documents testimony and other evidence including the
materials identified in Appendix and the calculations shown in this report
and itsappendixes
have found thefollowing
to be true
British Petroleum BP and Vastar Resources Inc Vastarwhich BP acquired specified the design and configuration of the
DWH BOP which was constructed by Cameron International
Corp Cameron
The BOP relied upon single blind shear ram BSR to be ableto shear drill pipe and seal the well in the case of an emergency
51
8/3/2019 Stevick, Glen Expert Report Only
6/121
Expert Report of Glen Stevick Ph.D P.E
This made the BSR single point of failure for the entire BOP of
which BP was aware
Transocean implemented flawed condition-based maintenance
system that did not identify the need for technology upgrades to
account for past design deficiencies and the issues associated
with drilling in deeper and deeper water This condition-based
maintenance program did not allow Transocean to ensure proper
maintenance and certification of the existing BOP and its
components
BP and Transocean failed to implement the best available and
safest technologyBAST
in theBOP
SpecificallyBP
andTransocean failed to use
BSR Double Shear rams that would have sheared and
sealed off-center drill pipe
two BSRs--one to shear the pipe and the other to seal the well
an Emergency Disconnect Sequence EDS that activated theCasing Shear Rams CSR5 to center the pipe before
activating the BSR to shear and seal the pipe
an Acoustic Control System ACS as redundant means ofcommunication between the DWH rig and the BOP and
Camerons Mark Ill control pod system that used rechargeable
BOP control pod batteries and enabled battery lev els to be
monitored remotely
The undercharged batteries in the blue BOP control pod and
incorrectly wired solenoid 103Y were the result of Transoceans
flawed condition-based maintenance program and the failure of
BP and Transocean to implement BAST The undercharged
batteries and incorrectly wired solenoid may have beencontributing causes of the blowout if they prevented the Automatic
Mode Function AMF/Deadman from activating the BSR at
time when the drill pipe was centered and could have been
sheared and closed by the BSR
61
8/3/2019 Stevick, Glen Expert Report Only
7/121
Expert Report of Glen Stevick Ph.D P.E
II THE BLOWOUT PREVENTER PURPOSE STRUCTURE AND
DESIGN
The BOP Purpose
The primary purpose of the BOP is to prevent uncontrolled oil and gas from
reaching the DWH i.e to prevent blowout As in any mobile offshore
drilling unit MODU the DWH BOP is critical subsea component usedto seal control and monitor the well during drilling operations As stated in
BPs internal documents
Blowout equipment is the final l ine of defense
agains t catastrophic event which may include
fatalities uncontrollable release of oil and gas and
evacuation of entire communities.1
Indeed BPs CEO considered BOP to be fail-safe piece of equipment
that was the last line of defense against blowout.2 Similarly
Transocean recognized the BOP as critical piece of equipment.3
BP-Wells Engineer OJT Module BP-HZN-2179MDL01342044-01342052 Exhibit
2096
Deposition of Tony Hayward June and 2011 23510-19
Deposition of William Stringfellow April 11-12 2011 2036-9
71
8/3/2019 Stevick, Glen Expert Report Only
8/121
Expert Report of Glen Stevick Ph.D P.E
BOP Structure
As shown to the right in figure
the BOP on the DWH consists of
two main parts an upper
portion called the Lower Marine
Riser Package LMRP andLower BOP Stack sitting below
the LMRP The LMPR contains
two annulars while the lower
BOP package includes single
BSR single CSR two variable
shear rams VBR5 and TestRam an inverted VBR to resist
downward pressure
till
________H_LowerBOP Stack
Fig The DWH BOP showing the position of annulars and valves.4
The BSR used in the BOP is of particular importance because the BSR is
the device ultimately responsible for shearing the drill pipe and sealing thewell in the case of an emergency The single BSR in the DWH BOP was
Cameron shearing blind ram as shown below
Perkin CS Expert Report August 26 2011 Cited image source EngineeringPartners International LLC
Upper Annular
Lower Annular
81
8/3/2019 Stevick, Glen Expert Report Only
9/121
SF-E4A11Q FLIND FA
Fig The Cameron BSR used in the DWH BOP
The shearing blind ram includes lower ram with straight blade and an
upper ram with shaped blade The shearing blind ram is designed to
shear drill pipe located within the cutting blades and seal the wellbore The
BOP has bore of 18-3/4 inches and the cutting blades are only 17-7/8
inches for the lower straight blade and 15-1/4 inches for the upper V-shaped
blade This leaves gaps within the wellbore that are outside of the cutting area
of the shearing blind ram blades as shown below in figure
Fig Model of the DWH BOP BSR from the Det Norske Veritas
DNV report.6
Cameron EB 852D Exhibit 7001 The shaded areas represent elastomeric sealing
elements
Expert Report of Glen Stevick Ph.D P.E
91
8/3/2019 Stevick, Glen Expert Report Only
10/121
Expert Report of Glen Stevick Ph.D P.E
BOP Control
Communicating with the BOP
The DWH BOP was controlled by Cameron Mark II electro-hydraulic
multiplex UX control system.7
As shown in the modified
version of figure to the
right the LMRP portion of
the BOP contains two
redundant control pods
referred to as the blue and
yellow pods The control
pods provided control
functionality and
communication between
the BOP and the DWH rig
via wired MUX cables that
ran from the control pods
through the water up to
the DWH where the crewcould control the BOP
using control panels
Because control
commands from the DWH
could only be transmitted
via the MUX cables the
ability of the DWH crew to
directly control the BOP
was completely contingent
upon properly functioning
MUX cables
Lwr AnrijIa
Det Norske Veritas Final Report for United States Department of the Interior Bureau
of Ocean Energy Management Regulation and Enforcement Forensic Examination of
Deepwater Horizon Blowout Preventer Contract Award No M10PX00335 Volume
Final Report Report No EP030842 20 March 2011 DNV Report Vol Figure 132
Deposition of Jack Erwin June 6-7 2011 36715-17
Yellow Coritol Pod
iue Control
4-Ipp .nriuia
Lor BOF
101
8/3/2019 Stevick, Glen Expert Report Only
11/121
Expert Report of Glen Stevick Ph.D P.E
Fig The DWH BOP including identification of the blue and yellow control
pods.8
Figure below shows model of the DWH rig and BOP including
identification of various BOP components the MUX cables the
accumulators that provide hydraulic pressure to activate the BOP rams
images of BOP control panels and an image of BOP control pod
Fig Model of the DWH and BOP from the DNV report.9
Activating the BSR
There were several different methods of controlling the BOP and activating
the BSR including
Perkin CS Expert Report August 26 2011 Cited image source EngineeringPartners International LLC Image modified to identify the blue and yellow control
pods
DNV Report Vol Appendix Figure
LMAP
M.tI
4- i1 li.W
III
8/3/2019 Stevick, Glen Expert Report Only
12/121
Expert Report of Glen Stevick Ph.D P.E
Activation of the BOP high pressure BSR function from
either of two control panels located on theDWH
Thismethod requires MUX line communication to an operational
control pod
Activation of the Emergency Disconnect Sequence
EDS which is also activated from either of the two controlpanels on the DWH and requires MUX line communication to
an operational control pod The primary function of the EDS
is to allow the rig to disconnect from the BOP if the dynamic
positioning system that holds the rig in position fails
Activation of the AMF/Deadman circuits located in the
Subsea Electronic Modules SEM5 within either of the blueor yellow control pods mounted on the LMRP The AMF is
designed to activate automatically i.e without requiring
initiation by user when the BOP loses hydraulic pressureelectrical power or electronic communication with the DWH
Remotely Operated Vehicle ROy initiation of the AMFby cutting the MUX and hydraulic lines on the BOP
ROV initiation of the Autoshear function by severing the
autoshear activation rod that connects the LMRP to the BOP
stack intended to activate if the LMRP and BOP are
separated
ROV hot stab connection to the BOP hydraulics The
ROV can use onboard hydraulic pumping to power the BOP
hydraulics
The AMF is based on Cameron circuit board that implements the AMFfunctionality The AMF requires at least one functional control pod i.eeither the blue or yellow control pod to initiate and complete its sequence
including to activate the BSR Each of the two control pods contains two
SEMs i.e SEM and SEM and each SEM contains an AMF card To
power the AMF cards each SEM contains dedicated volt battery i.eone per SEM two for each of the blue and yellow control pods and four
total for the BOP Each control pod also contains single 27 volt DCbattery pack to power the two SEMs in that pod Each control pod also
12
8/3/2019 Stevick, Glen Expert Report Only
13/121
Expert Report of Glen Stevick Ph.D P.E
contains high-pressure shear circuit that activates the BSR The high-
pressure shear circuit is energized by solenoid 103 in that pod i.e 103B
forthe blue pod and 103Y
forthe yellow pod which activates
for
30seconds when the AMF is triggered Each solenoid 103 contains two coils
with one coil connected to each of SEM and SEM in that solenoids
pod Each of the 103 solenoids is powered by the 27 volt battery packfrom its respective pod.11
BOP Design
According to information reviewed by BPs Vice President of Engineeringand Quality for the Drilling Systems Division12 BP was involved in the
configuration ofDWH BOP from the beginning13 and BP played an
active role in specifying DWH BOP stack.14
The DWH was built in 2000 at the Hyundai Heavy Industries Shipyard in
South Korea for cost of approximately $350 million It was originally built
for and commissioned by Falcon Drilling Co Falcon which later
became part of Transocean The DWH was originally contracted to Vastar
which was later acquired by BP The DWH BOP was first contemplated in
1998 Drilling Contract between Vastar and Falcon Drilling Contract.5
Under the Drilling Contract Falcon was to furnish and pay for the B0P16
and to ensure that the BOP was adequately maintained and in such
condition as to permit continuous and efficient operation.7
10
Deposition of Edward Gaude September 19 2011 12414-25
Deposition of William LeNormand June 20-21 2011 15822 1593
12
Deposition of David McWhorter July 7-8 2011 1316-18
13
Deposition of David McWhorter July 7-8 2011 5919-11
14
Depositionof David McWhorter
July7-8 2011 33023-3313
15BP-HZN-21 79MDL00056656-936
16BP-HZN-2 79MDL00056656-936 at BP-HZN-21 79MDL00056768 Blowout
preventers are to be furnished and paid for by the CONTRACTOR i.e Falcon under
Exhibit B-3 paragraph .20 of the Drilling Contract
17BP-HZN-21 79MDL00056656-936 at BP-HZN-21 79MDL00056674 Under section
14.1.1 of the Drilling Contract CONTRACTOR i.e Falcon agrees to maintain all
equipment and materials furnished by CONTRACTOR which i ncludes t he BOP as
noted in Exhibit B-3 paragraph .20 of the Drilling Contract
131
8/3/2019 Stevick, Glen Expert Report Only
14/121
Expert Report of Glen Stevick Ph.D P.E
Although the BOP was manufactured and sold by Cameron and purchased
by Falcon Vastar was heavily involvedin
theBOP
design configurationchoice of components and controls.18 Vastar chose the configuration
of the BOP Stack and the type of rams for each cavity19 the routing of
the MUX lines20 that there would be no acoustic communications21
factory adjustments by Cameron prior to acceptance22 and the EDS
program mode EDS-1 23
Furthermore for BOP designs BP decides what the BOP stack
configuration will be and instructs its drilling contractors including
Transocean regarding what types of rams should be used and where the
rams will be located in the BOP.24 Here BP specified the configuration of
the BOP in its original contract with Transocean and re-specified the
configuration in September 2009 in contract amendment.25 As Operator
of the Macondo well site BP is also ultimately responsible for the BOP
under the Code of Federal Regulations CFR5 and the AmericanPetroleum Institute API Recommended Practices RP26
18
Exhibit
5094BP-HZNBLYOO294O35
19Exhibit 4112 deposition of Michael Byrd July 13-14 2011 48812-49418
20 BP-HZNBLY00294826
21
BP-HZNBLYOO29435O
22BP-HZNBLY00294352
23BP-HZNCECO30029 As discussed further below EDS-1 closes only the BSR
whereas the other available EDS mode EDS-2 first closes the CSR and then the BSR
Had this mode been selected it likely would have centered the drill pipe before attempt
attempting to shear the pipe which likely would have sealed the well
24Deposition of Tony Hayward June and 2011 5731-14
25 Amendment 38 to Contract No 980249 September 28 2009 BP-HZN-CECO4 1476Exhibit 1488
26Code of Federal Regulations Title 30 Part 250 Oil and Gas and Sulphur Operations in
the Outer Continental Shelf Subpart 30 CFR 250 Section 250.400 et seqAmerican Petroleum Institution Recommended Practice 53 Recommended Practices
for Blowout Prevention Equipment Systems for Drilling Wells API RP 53
141
8/3/2019 Stevick, Glen Expert Report Only
15/121
Expert Report of Glen Stevick Ph.D P.E
Ill THE BOP DESIGN WAS DEFECTIVE BECAUSE IT RELIED ON
SINGLE BSR
After the Macondo blowout BP acknowledged that it had relied on the BOP
as the ultimate form of containment in the event of blowout.27 BP also
recognized that in the case of blowout the BSR was the most critical well
control device within the BOP.28 Despite the importance of the BSR and its
crucial role in the operation of the BOP and overall well safety BP failed to
design and implement within the BOP BSR that could reliably shear the
drill pipe and seal the well under foreseeable operating conditions
The BSR was Single Point of Failure for the DWH BOP
Although there are several ways to activate the BSR all of the DWH
emergency systems relied upon the BOPs single BSR to be able to shear
the drill pipe and seal the well in the case of an emergency making the
BSR single point of failure for the entire BOP safety system Failure of
the BSR to shear the drill pipe and seal the well for whatever reason
would result in total failure of the entire BOP to perform its intended
function of preventing blowout Indeed 2001 Risk Assessment of the
DWH BOP identified the risks inherent to the BOP stack configuration with
single BSR
The major contributor to the failure likelihood
associated with the BOP control system results from
the selected stack configuration With only one
shear ram capable of sealing the well in it is
extremely difficult to remove all of the single failure
points from the system.29
27Deposition of Tony Hayward June and 820112351-92777-103017-10
28Deposition of Tony Hayward June and 820112897-14
29Risk Assessment of the Deepwater Horizon Blowout Preventer BOP Control
System Final Report April 2000 CAM-CIV-0019032 CAM-CIV-0019076 at CAM-CIV
0019070 Exhibit 4120 at 37
151
8/3/2019 Stevick, Glen Expert Report Only
16/121
Expert Report of Glen Stevick Ph.D P.E
The Risk Assessment further noted that the BSR including the final shuttle
valve that supplies hydraulic pressure to the BSR accounts for 56% of the
failurelikelihood of the system to successfully perform
its EDSoperation.3
The Potential for Off-Center Drill Pipe was Well Known to
BP and Transocean
BOP with single BSR is particularly deficient For example in
situations when the EDS system requires activation BPs VP of
Technology for Global Wells Organization noted that EDS pipe is alwaysoff center.31 As discussed above EDS is primarily designed for use in
scenarioswhere some aspect
of therigs dynamic positioning system has
failed and the rig has drifted from its intended location
those scenarios for which EDS has been
designed the pipe is likely to be off center because
of the huge tension that is on the pipe.32
Potential causes of off-center drill pipe include pipe distortion or bowing
from internal pressure loss of rig control and drift debris pushing the pipe
off-center ram pushing the drill pipe off-center multiple pipes in the riser
and elastic buckling.33 Of the potential causes elastic buckling is the most
likely to have forced the drill pipe off-center.34 Additionally helical buckling
is particular type of elastic buckling that has been well known for many
years in the drilling context.35 It does not appear that Transocean or BP
ever conducted any testing or analysis of the BSRs ability to shear off-
center drill pipe
30
Risk Assessment of the Deepwater Horizon Blowout Preventer BOP ControlSystem Final Report April 2000 CAM-CIV-0019032 CAM-CIV-0019076 at CAM-CIV
0019072 Exhibit 4120at
3931
Deposition of Fereidoun Abbassian May 3-4 2011 502-3
32Deposition of Fereidoun Abbassian May 3-4 2011 5010-13
DNV Report Addendum p.6-8 section 2.2.1
DNV Report Addendum 6-11 section 2.2
Lubinski Althouse W.S and Logan J.L Helical Buckling of Tubing Sealed in
Packers JPT 655-70 June 1962
161
8/3/2019 Stevick, Glen Expert Report Only
17/121
Expert Report of Glen Stevick Ph.D P.E
IV TRANSOCEAN USED FLAWED CONDITION-BASED
MAINTENANCE
As noted above under the Drilling Contract between BP through its
predecessor Vastar and Transocean through its predecessor Falcon
Transocean had primary responsibility for maintenance of the BOP.36
Transocean Failed to Recertify the BOP Every 3-5 Years as
Specified by API and Cameron
Transocean failed to follow the testing and maintenance guidelines
specified in 30 CFR 250 and API RP 5337 In particular Transocean
ignored the requirement that
After every 3-5 years of sen/ice the BOP stack
choke manifold and diverter components should be
disassembled and inspected in accordance with the
manufacturers guidellnes.38
36
BP-HZN-21 79MDL00056656-936 at BP-HZN-21 79MDL00056674 Under section
14.1.1 of the Drilling Contract CONTRACTOR i.e Falcon agrees to maintain all
equipment and materials furnished by CONTRACTOR which i ncludes t he BOP as
noted in Exhibit B-3 paragraph .20 of the Drilling Contract
See 30 CFR 250 et seq API RP 53
38API RP 53 section 17.10.3 see also 30 CFR 250.446 requiring that BOP
maintenance and inspections must meet or exceed the provisions described in API
RP 53
171
8/3/2019 Stevick, Glen Expert Report Only
18/121
Expert Report of Glen Stevick Ph.D P.E
The recurring disassembly and inspection of the entire BOP as outlined in
API RP 53 occurs at the surface and is important to maintaining safe and
effective BOP The advantages of regularly scheduled recertification areas follows
Consistent with the API the BOP manufacturer Cameron also
recommends that the BOP stack be recertified every 3-5 years.39 In
contrast an independent inspection of DWH two weeks before the blowout
found that for the BOP upon review of certification documentation it was
noted that the date of last manufacturers certification was 13 December
2000 and this is beyond the yearly inspection overhaul and re
certification requirement.4 Although Transocean recognized that both the
API and Cameron recommended disassembly inspection and
recertification of the entire BOP every 3-5 years Transocean knowinglychose not to follow this recommendation.41
Deposition of Mark Hay June 29-30 2011 1197-12011
40 MODU Condition Assessment DEEPWATER HORIZON ModuSpec USA Inc 4/1-
14/2010 TRN-USCG_
MMS-00038652
41
Deposition of William Stringfellow April 11-12 2011 21625-21713
Advantages of API/Cameron BOP
Recertification
Provides periodic opportunities to examine
individual BOP components for corrosion wear
and other flaws and to replace components when
necessary
Provides periodic opportunities to evaluate the
BOP design and replace deficient or outdated
components with BAST components and
technology
Ensures
components
every 3-5 years
that the entire BOP and its
are inspected at least as often as
181
8/3/2019 Stevick, Glen Expert Report Only
19/121
Expert Report of Glen Stevick Ph.D P.E
Transoceans Condition-Based Maintenance is Flawed
Because Only Equipment With Measured Problems or
Failures Gets Fixedor Replaced
When the piece of equipment falls we replace it or make
repairs to it.42
Instead of complying with the API and Camerons maintenance guidelines
for the BOP Transocean followed its own condition-based maintenance
program.43 Under this condition-based maintenance program BOP
components are not automatically removed from operation and inspected
every 3-5 years.44 Rather Transocean personnel would take
measurements and test BOP equipment45 and when piece of equipment
s tarted to create problems or fail Transocean fixed it.46 This type of
condition-based maintenance is subject to numerous flaws
Problems with Transoceans Condition-Based
Maintenance
Equipment deterior at ion that cannot be
measured is not considered
Need for improved equipment based on design
flaws new industry experience or operation in
more difficult environment is not considered
Replacement of otherwise functioning
equipment with BAST is discouraged
Problems that cannot be measured are not considered
Transoceans condition-based maintenance program failed to detect
several problems with the DWH including the low charge on the blue
42Deposition of Mark Hay June 29-30 2011 12018-19
Deposition of Mark Hay June 29-30 2011 1146-11522
Deposition of Mark Hay June 29-30 2011 1216-9
Deposition of Pharr Smith June 27-28 2011 157-1
46
Deposition of Pharr Smith June 27-28 2011 157-13 deposition of Mark Hay June
29-30 2011 12018-1 12117-19
191
8/3/2019 Stevick, Glen Expert Report Only
20/121
Expert Report of Glen Stevick Ph.D P.E
pod batteries and the incorrect wiring on yellow pod solenoid 103Y in
the DWH BOP These types of equipment problems are undetectable by
condition-based maintenance because theBOP
d id no t have sensors thatindicated pod battery levels and physical inspection and testing was
needed to evaluate the wiring on yellow pod solenoid 103Y But it cannot
be debated that properly functioning pod batteries and solenoids are highly
important to the safe and effective operation of the BOP and should
therefore be regularly tested and evaluated under any maintenance
program Transoceans condition-based maintenance is flawed because it
fails to consider equipment that cannot be measured whereas such
equipment is evaluated under the recertification process found in API and
Camerons guidelines
As discussed further below the undercharged blue pod batteries and
incorrectly wired yellow pod solenoid 103Y may have prevented the
AMF/Deadman from activating the BSR at the time of the incident and
ultimately lead to the blowout But regardless of whether these battery and
solenoid problems were direct cause of the blowout these problems do
highlight flaws in Transoceans condition-based maintenance program
The working condition of critical components was not evaluated by
Transocean because it could not be measured
Need for improved equipment is not considered
Another flaw wi th Transoceans condition-based maintenance program is
that it does not detect the need to improve existing equipment that is
otherwise functioning properly Equipment measurements during
condition-based maintenance are not going to identify design flaws
improvements in industry knowledge and practices or increased system
requirements due to operation in more difficult environment Under
condition-based maintenance if equipment measurements are in line with
expectations that equipment will not be considered further for potentially
necessary upgrades For example had Transocean disassembled and
inspected the DWH BOP for recertification and performed perfunctory
engineering review or industry comparison at any time since 2006Transocean would have found that the DWH di d n ot have Camerons most
up to date BOP control system Mark Ill which as described below
provides numerous safety benefits over the Mark II system used for the
DWH BOP recurring BOP recertification process that involves BOP
disassembly and inspection as part of an engineering review is superior to
20
8/3/2019 Stevick, Glen Expert Report Only
21/121
Expert Report of Glen Stevick Ph.D P.E
Transoceans condition-based process because recurring recertification
provides an opportunity to identify changing requirements for equipment
thatis
otherwisein
perfect working order
Implementing BAST is discouraged
Transoceans condition-based maintenance program discourages the
implementation of BAST because it focuses on replacing equipment only in
the event of measurable problems or failures as opposed to periodically
evaluating whether improved equipment exists that should replace
otherwise functional existing equipment Transoceans condition-based
maintenance program further discourages the implementation of BAST by
failing to provide the opportunity to implement BAST equipment and
technology which typically must occur at the surface In contrast
maintenance programs based on engineering review i.e recertification at
the surface encourage the implementation of BAST by providing the
opportunity to evaluate BAST for all equipment and the opportunity to
implement BAST when available The many failures to implement BAST in
the DWH BOP discussed below are unsurprising in light of the flaws of
Transoceans condition-based maintenance program
BP FAILED TO IMPLEMENT BAST IN THE BOP
The CFR requires that BP as Operator of the Macondo well site must use
the best available and safest technology BAST whenever practical on all
exploration development and production operations.47 But BP failed to
implement BAST in numerous areas of the BOP including the single BSR
that was ultimately unable to perform its intended function of severing the
drill pipe and sealing the well
BP Failed to ImplementBAST for the BSR
Implementing BAST in the single BSR was particularly critical due to the
BSR being single point of failure and the device that was ultimately relied
upon to seal the well in the case of an emergency BP knew the BSR was
the most important piece of equipment for preventing blowout48 and yet
BP still failed to implement BAST in the BSR and preferably add second
30 C.F.R 250.107c
48
Deposition of Tony Hayward June and 820112897-14
211
8/3/2019 Stevick, Glen Expert Report Only
22/121
Expert Report of Glen Stevick Ph.D P.E
BSR.49 Indeed the BSRs on the DWH BOP had not been upgraded since
the rig was first ordered in ggg50
BSRs with double shaped cutting blades and wider blades were
available when the BOP was designed For example Camerons Double
Shear DVS Rams featured shaped cutting blades on both the
upper and lower blocks.51 The double design provided the benefits of
helping to center the drill pipe during activation and also improving shearing
efficiency by reducing the necessary shearing force.52 Accordingly using
DVS ram block instead of the shearing blind ram block for the BSR in the
DWH BOP would have allowed the BSR to shear greater range of pipe
with the maximum 4000 psi available to the emergency system.53
The improved shearing efficiency of double rams was further
demonstrated by testing by West Engineering Services in 2004 for MMS
that showed double blades lower the required shear force and
therefore required hydraulic pressure by factor of approximately 20%
when compared to BSRs with single blade and straight blade.54 For
the DWH BOP Camerons DVS was also superior to the shearing blind
ram because the DVS blade length was maximized to increase shearing
capabilities.55 BP must have known about these advantages of the DVS
over the shearing blind ram which Cameron touted inits
product literature
as shown below.56
BP-HZN-BLY00294352-59
50Deposition of Jack Erwin June 6-7 2011 6524 661
51
Cameron EB 852D Exhibit 7001
52 Cameron EB 852D Exhibit 7001 deposition of Jack Erwin June 6-7 2011
4616-19
Deposition of David McWhorter July 7-8 2011 1108-12
West Engineering Services Shear Ram Capabilities Study for U.S Minerals
Management Service Requisition No 3-4025-1001 page 3-5 September 2004
Cameron EB 852D Exhibit 7001
56Cameron EB 852D 13 Exhibit 7001
22
8/3/2019 Stevick, Glen Expert Report Only
23/121
Expert Report of Glen Stevick Ph.D P.E
5Rs -vs- DYS
5hearin BLindRams
Dcuble ShearRams
Longer packer fatigue Life Require Less shear force
CapabLe of shearing Larger
diameters
No toss of fatigue life
Fig Comparison of Shearing Blind Ram versus DVS rams from
Cameron Product Literature.57
DVS rams and blades for an 18-3/4 inch wellbore 15000 psi TL BOP
which could have been used in the DWH BOP were available from
Cameron at least as early as 2002.58 Cameron sales representative also
acknowledged that by 2009 or 2010 DVS was much more used ram
than the SBR and the DVS ram was considered to be the best in practice
at that time.59
BP also did not implement Camerons tandem boosters which feature
two-part piston that increases shearing force without additional wear on the
packers.6 The tandem boosters were available at least as early as 199861
and use of tandem boosters would have increased the shear force of the
BSR on the DWH BOP If BP had used DVS rams with blades that
covered the entire well bore the BSR most likely would have successfully
sheared the off center drill pipe and sealed the well preventing the
blowout
Cameron EB 852D 13 Exhibit 7001
58Cameron 2002 Replacement Parts Catalog pg 108 BP-HZN
BLY0036641
Deposition of Jack Erwin June 6-7 2011 6220-25
60Cameron EB 852D 10 Exhibit 7001
61Cameron EB 852D 10 Exhibit 7001
23
8/3/2019 Stevick, Glen Expert Report Only
24/121
Expert Report of Glen Stevick Ph.D P.E
BP and Transocean Failed to Upgrade the BOP to Include
Second BSR
second BSR installed below the CSR would provide redundancy and
significantly improve the reliability of both shearing pipe in the BOP and
sealing the well If drill string is suspended and sheared first with the
CSR i.e Super Shears during an emergency the drill pipe should fall
clearing the BSR located below the casing ram This allows the lower BSR
to close and seal without pipe interference in its bore Moreover
Cameron sales representative testified that by 2009 or 2010 most of the
rigs had double BSRs.62
BP and Transocean Failed to Upgrade to Camerons MarkIll BOP Control Pod
The DWH BOP used Cameron Mark II BOP control pods63 with double coil
solenoids and batteries that were not rechargeable and the charge of which
could not be monitored from the rig.64 As discussed above properly
functioning control pod solenoids and batteries are needed to operate the
AMF system and are critical components for safe and effective BOP BP
and Transocean failed to upgrade to Mark Ill control pods that have been
available since 2006.65
62
Deposition of Jack Erwin June 6-7 2011 622-14
63
Deposition of Jack Erwin June 6-7 2011 36715-17
64
Deposition of David McWhorter July 7-8 2011 2901-4
65Deposition of David McWhorter July 7-8 2011 28917-20
24
8/3/2019 Stevick, Glen Expert Report Only
25/121
Expert Report of Glen Stevick Ph.D P.E
Mark Ill control pods have rechargeable batteries66 and the charge on the
batteries can be monitored from the rig.67 Mark Ill control pods also have
improved singlecoil
solenoids with higher pulling force68 which eliminatesthe potential incorrect wiring problem of the dual coil solenoids used in
Mark II control pods and found in yellow pod solenoid 103Y of the DWH
BOP Moreover Cameron corporate representative has testified that
Cameron made its customers aware of the new Mark Ill system and its
improvements over the Mark II system and that Transocean was aware of
the Mark Ill system in 2006.69
BP Failed to Implement BAST by Relying Solely on MUX
Cables for EDS
All methods of activating the DWH EDS relied on communications
transmitted by MUX cables from the rig down to the BOP DWH rig crew
members testified that they attempted to activate the EDS system after the
explosion but were unsuccessful The EDS may have failed to activate due
to physical damage to the MUX cables caused by the explosion An ACS
could have been used as redundant means of communication between
the DWH rig and the BOP Cameron had ACS available when the DWH
was being configured.7 redundant ACS system could provide BOP
communications and control in the case of an emergency even if MUX
cables were damaged
BP and Transocean Failed to Implement BAST by Using
EDS-1 Instead of EDS-2
Cameron could program various EDS sequences into the DWH BOP
depending on what was requested by BP and Transocean.71 The DWH
BOP implemented an EDS program called EDS-1 that specifies
predetermined sequence of emergency disconnect events such that if the
66
Deposition of Jack Erwin June 6-7 2011 36718-22
67
Deposition of David McWhorter July 7-8 2011 28921-25
68
Deposition of Jack Erwin June 6-7 2011 37014 3716
69
Deposition of David McWhorter July 7-8 2011 3587 3606
70
Deposition of David McWhorter July 7-8 2011 1286-16
71
Deposition of David McWhorter July 7-8 2011 2248-12
25
8/3/2019 Stevick, Glen Expert Report Only
26/121
Expert Report of Glen Stevick Ph.D P.E
EDSI- button is pushed the predetermined sequence of events will
occur.72 EDS-1 for the DWH was programmed to close the BSR and then
disconnect theLMRP.73
AnotherEDS
sequence was available onDWH
called EDS-2 whereby the CSR closed before the BSR closed.74 Because
EDS-2 first applies the CSR which has capabilities the BSR does not
activation of EDS-2 is more likely to successfully shear the pipe and seal
the well.75 Although the CSR is not designed to seal the wellbore
activation of the CSR first would have centered the drill pipe for the BSR
making it much more likely that the BSR would completely shear the drill
pipe and seal the well BP and Transocean failed to implement BAST by
having Cameron program the EDS-1 sequence as the primary disconnect
sequence for the DWH BOP instead of EDS-2 which was more likely to
successfully seal the well if activated
VI THE UNDERCHARGED BLUE CONTROL POD BATTERIES AND
INCORRECTLY WIRED YELLOW CONTROL POD SOLENOID
103Y MAY HAVE BEEN CONTRIBUTING CAUSES OF THE BOPS
INABILITY TO STOP THE BLOWOUT
As discussed above when the AMF/Deadman is activated it causes the
BSR to fire But the AMF/Deadman can only be activated if at least one of
the control pods is functioning properly which requires charged batteries
and working solenoids Based on my review of the post-incident testing of
the BOP and related deposition testimony76 it appears that neither was
true
72
Deposition of Jack Erwin June 6-7 2011 2714 -2810
Deposition of Jack Erwin June 6-7 2011 301-9
Deposition of David McWhorter July 7-8 2011 22513-24
Deposition of David McWhorter July 7-8 2011 22610-25
76Deposition of Robert Turlak July 28-29 2011 22817 2295 deposition of Edward
Gaude September 19 2011 13011-22 testifying that if two coils in single solenoid
are wired in opposite directions the electromagnetic fields would oppose each other
and cancel out and the solenoid valve would not operate 2103-8 testifying that if
solenoid is not wired correctly it will not function correctly
26
8/3/2019 Stevick, Glen Expert Report Only
27/121
Expert Report of Glen Stevick Ph.D P.E
Undercharged Blue Control Pod Batteries
During post incident forensic testing by DNV of the blue control pod
batteries the 27 volt battery registered low charge as shown below.77
Blue P01 VoLts Yellow Pod Volts
Batten- Test Test Test Test
SEMA9V 8.9 8.9 3.7 8.7
SEMB9V 8.7 8.7 8.4 8.4
Solenoid TransclucerC7V 1.1 1.0 2S.2 28.2
Fig BOP Control Pod Battery Measurements from the DNV
report.78
Due these to low charge in the 27 volt battery it is very unlikely that the
blue control pod would have had sufficient power to activate the
AMF/Deadman at the time of the incident
Incorrectly Wired Yellow Control Pod Solenoid 103Y
Post incident forensic testing by DNV also showed that one of the two coils
from yellow control pod solenoid 03Y had been incorrectly wired and 03Y
failed to activate either yellow control pod SEM during bench testing.79 As
result of 103Y being incorrectly wired the two coils had opposite
polarities and the electromagnetic fields generated by the two coils would
largely cancel each other out and could prevent 03Y actuating the BSR in
response to the AMF/Deadman circuit in the yellow pod
DNV Report Vol page 42
78DNV Report Vol Table page 42
DNV Report Vol page 44 The results of solenoid 103Y testing are inconclusive
because 03Y worked properly when connected to and operated by SEM and SEM
as would have occurred in the field Laboratory Notes from DNV testing of 103Y
016862 Exhibit 3130
27
8/3/2019 Stevick, Glen Expert Report Only
28/121
Expert Report of Glen Stevick Ph.D P.E
The AMF/Deadman Likely Failed to Actuate the BSR
because of Low Blue Pod Battery and the Incorrectly Wired
Yellow Pod Solenoid
Even though the BOP had redundant mechanisms for actuating the BSR in
response to the AMF/Deadman conditions it appears likely that both
mechanisms failed The low battery charge measurements for the blue pod
27 volt battery pack suggest that it did not have enough charge to power
the two blue pod SEMs at the time of the incident which would prevent the
blue pod from activating the BSR The incorrect wiring on solenoid 103Y
suggests that because each coil received the same voltage80 and the two
coils were activated simultaneously as is the normal operation during AMF
activation81 the magnetic fields from the two coils would cancel each other
out and would prevent the yellow pod from activating the BSR.82 It is
therefore likely that the AMF/Deadman failed to activate the BSR as
result of the low charge on the 27 volt blue pod battery and the incorrectly
wired yellow pod solenoid O3Y
The BSR Likely Would Have Completely Sheared the Drill
Pipe and Sealed the Well if the BSR had been Activated
when the Drill Pipe was Centered
The undercharged blue pod batteries and incorrectly wired solenoid 03Y
may have prevented the AMF/Deadman from properly functioning at the
time of the incident and activating the BSR.84 If the drill pipe was centered
at the time of the incident and did not become off-center until later then
activating the BSR probably would have completely sheared the drill pipe
and sealed the well preventing the blowout
80
Deposition of Edward Gaude September 19 2011 1387-12
81
Deposition of Edward Gaude September 19 2011 131 9-16
82Deposition of Edward Gaude September 19 2011 131 23 1323
83As discussed above there is evidence that suggests the AMF/Deadman function did
not activate the BSR but overall the evidence is inconclusive on this point There is
also evidence that suggests the AMF/Deadman may have act ivat ed t he BSR
84It is possible for example that the BSR was activated at later time by the ROy
28
8/3/2019 Stevick, Glen Expert Report Only
29/121
Expert Report of Glen Stevick Ph.D P.E
As discussed above undercharged blue pod batteries would have been
avoided if BP and Transocean had implemented Camerons Mark Ill BOP
control system that uses rechargeable control pod batteries and allowsremote monitoring of battery charge from the rig maintenance program
based on recurring disassembly inspection and recertification as opposed
to Transoceans condition-based maintenance probably would have also
detected the undercharged blue pod batteries and would have provided an
opportunity to replace them will fully charge and functional batteries
Similarly implementation of Camerons Mark Ill BOP control system with
single coil solenoids would have prevented the problem of incorrectly wired
solenoids as found in 03Y recurring recertification based maintenance
program probably would have detected that 103Y was incorrectly wired
and would provided an opportunity to replace 103Y with properly
functioning solenoid
reserve the right to modify this report and to supplement my opinions if
additional data becomes available and in response to reports served by
other parties
Dated January 17 2012
Dr Glen St vick P.E
29
8/3/2019 Stevick, Glen Expert Report Only
30/121
APPENDIX
8/3/2019 Stevick, Glen Expert Report Only
31/121
MDL
NO
2179
In
re
OilSpillby
the
OilRig
DeepwaterHorizoninthe
GulfofMexico
onApril20
2010
DR
GLEN
STEVICK
SOURCE
RELIANCE
APPENDIX
BP-HZN-21
79MDL00056656-56936
BP-HZN-BLYOO1
24026
BP-HZN-BLYOO1
24588-124698
ProDerties
ofPart
01366513
of65
Pages
8/3/2019 Stevick, Glen Expert Report Only
32/121
BP-HZN-BLYOO1
78528-1
78530
Properties
ofPart01366516
Collar
Float
BP-HZN-BLY00294035-294036
5/31/2010
Wong
to
Abbassian
re
MBI
HearingTranscripts
BP-HZN-BLY00294350-294351
6/8/2010
Diasemailto
Abbassian
re
Assignment/Paul
DiasBOPsystems
BP-HZN-BLY00294352-294359
5/27/2010
Questionsfrom
Fereidoun
Abbasian
May
27th
BP-HZN-BLY00346210-346212
7/1/2010
DeepwaterH
orizon
Incident
Investigation
--
CF1-NTF1O
FloatCollarFailure
BP-HZN-BLYOO35O1
58-3
50159
5/13/2010
DeepwaterH
orizon
Incident
Investigation
--
Preliminary
F
actual
Critical
FactorOutcome
Form
BP-HZN-BLY00366307-366448
00/00/2002
Cameron
2002
Replacement
Parts
Catalog
BP-HZN-CECO1
1425
7M45AP
Float
CollarDrawing
BP-HZN-CEC030029-30030
10/11/2004
Letter
Agreem
ent
forConversion
ofVBR
to
TestRam
b
etween
Transocean
and
BP
BP-HZN-CEC030137
Spreadsheet
re
Casing
Thread
Damage
BP-HZN-MBI00061
305-6
1
403
4/14/2009
IntermoorMODU
Mooring
AnalysisReportforBP
BP-HZN-MB100128436-128438
4/16/2010
Paikattu
ema
iltoMorelre
Actual
vs
model
9-7
/8
in
liner
run
BP-HZN-MBIOO1
28489-128490
4/17/2010
Gagliano
em
ailto
Moreletalre
Revised
OptiCem
Reportwith
additional
Centralizers
BP-HZN-MB10012961
6-129619
4/28/2010
Bob
KaluzaInterview
Notes
BP-HZN-MBIOO1
34806-1
34834
DeepwaterH
orizon
--
HAZOP
ofWellControl
Systems
BP-HZN-MBIOO1
37364-1
37377
4/20/2010
Halliburton
9
.875
Foamed
Production
Casing
PostJ
ob
Report
BP-HZN-MB100294826-294833
1/1
4/2010
BP
Application
for
Revised
New
Well
CAM_
CIV_
001
9664-1
9819
00/00/2006
Cameron
2006
Drilling
Replacement
Parts
Catalog
CAM_
CIV_
0370157-370165
6/28/2006
Engineering
Bulletin
Errata
Sheet
re
ShearingCapabilities
ofCameron
Shear
Rams
CAM_
DIV_
03701
00-3
701
16
7/9/2010
Cameron
En
gineering
Bulletin
re
Shearing
Capabilities
of
Cameron
Shear
Rams
DECO77-006509-6528
1/21/2008
Cameron
En
gineering
Bulletin
re
Shearing
Capabilities
of
Cameron
Shear
Rams
1M5054-0
16139-1
6143
1/27/2004
Engineering
Bulletin
Errata
Sheet
re
ShearingCapabilities
ofCameron
Shear
Rams
TRN-INV-00580489-580497
3/23/2007
Engineering
Bulletin
Errata
Sheet
re
ShearingCapabilities
ofCameron
Shear
Rams
TRN-INV-03489834-3489863
NASA/DNV
Summary
ofTestPreparation
Sheet
BOP-Ol
TestSolenoid
at
Deep
Sea
Temperture
and
Pressure
TRN-MDL-00286767
3/31/2009
Transocean
WellControl
Hand
book
TRN-MDL00607699-607707
8/6/2007
Cameron
En
gineering
Bulletin
Revision
Ex
257
02/00/2011
ChiefCouns
elsReportto
National
Commissionon
the
BP
Deepwater
Horizon
OilSpill
01/00/2011
FinalReport
tothe
Presidentre
Deepwater
The
GulfOil
Disaster
and
the
Futureof
Offshore
Drilling
11/16/2010
National
Academy
ofSciences
Interim
Reporton
Causes
ofBlowout
Republicofthe
Marshall
Islands
Office
ofthe
MaritimeAdministratorDeepwater
Horizon
MarineCasua
ltylnvestigaton
Report
of65
Pages
8/3/2019 Stevick, Glen Expert Report Only
33/121
9/14/2011
The
Bureau
ofOcean
Energy
Management
Regulationand
Enforcement--
Report
Regarding
th
e
Causes
ofthe
April20
2010
Macondo
WellblowoutJITReport
4/22/2011
United
States
Coast
Guard
ReportofInvestigation
intothe
Circumstances
Surrounding
the
Explosion
Fire
Sinking
and
Loss
ofEleven
Crew
Mem
bers
Aboard
the
MobilOffshore
DrillUnitDeepwater
Horizon
in
the
GulfofMexico
April2
0-222010
3/20/2011
DNV
Report
EP030842
forBOEMRE
Volumes
and
II
6/22/2011
Transocean
Investigation
ReportVolumes
and
II
9/8/2010
BP
Deepwate
r
HorizonAccidentInvestigation
ReportBly
Report
6/8/2011
Transoceans
Response
to
USCG
DraftReport
6/6/20
Erwin
Jack
CarterDeposition
Transcript
6/7/20
Erwin
Jack
CarterDeposition
Transcript
6/29/2011
Hay
MarkDavid
Deposition
Transcript
7/6/2011
Kenney
Gary
Deposition
Transcript
6/20/2011
LeNormand
William
Deposition
Transcript
6/21/2011
LeNormand
William
Deposition
Transcript
7/7/2011
McWtiorter
David
Deposition
Transcript
7/8/2011
McWtiorter
David
Deposition
Transcript
3/14/2011
PleasantCh
ristopher
Deposition
Transcript
3/15/2011
PleasantCh
ristopher
Deposition
Transcript
7/5/2011
Thompson
NeilDeposition
Transcript
7/20/2011
McWtiorter
James
Owen
Deposition
Transcript
7/21/2011
McWtiorter
James
Owen
Deposition
Transcript
7/18/2011
WhitbyMelvy
Deposition
Transcript
7/19/2011
WhitbyMelvy
Deposition
Transcript
6/30/2011
Hay
MarkDavid
Deposition
Transcript
Ex
7043
Ex
7044
Ex
7045
Ex
7046
Ex
7000
Ex
7001
Ex
7002
Ex
7003
Ex
7004
Ex
7005
Ex
7006
of65
Pages
8/3/2019 Stevick, Glen Expert Report Only
34/121
Ex
7007
Ex
7008
Ex
7009
Ex
7010
Ex
7011
Ex
7012
Ex
7013
Ex
7014
Ex
7015
Ex
7016
Ex
7017
Ex
7018
Ex
7019
Ex
7020
Ex
7021
Ex
7022
Ex
7023
Ex
7024
Ex
7025
Ex
7026
Ex
7027
Ex
7028
Ex
7029
Ex
7030
Ex
7031
Ex
7032
Ex
7033
Ex
7034
Ex
7035
Ex
7036
Ex
7037
Ex
7038
Ex
7039
Ex
7040
Ex
7041
Ex
7042
Ex
3626
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
35/121
Ex
3627
Ex
3628
Ex
3601
Ex
3602
Ex
3603
Ex
3604
Ex
3605
Ex
3606
Ex
3607
Ex
3608
Ex
3609
Ex
3610
Ex
3611
Ex
3612
Ex
3613
Ex
3614
Ex
3615
Ex
3616
Ex
3617
Ex
3618
Ex
3619
Ex
3620
Ex
3621
Ex
3622
Ex
3623
Ex
3624
Ex
3625
Ex
592
Ex
593
Ex
594
Ex
580
Ex
581
Ex
582
Ex
583
Ex
584
Ex
585
Ex
586
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
36/121
Ex
587
Ex
588
Ex
589
Ex
590
Ex
591
HBRA
Flow
and
Force
Calculation-Odmund
HBRA
Thermal
Expansion
Calculation
BOP
Data
F
iles
04182011
through
06232011
DNV
daily
notebook
entries
testing
spreadsheets
laserscanning
data
BOP
Image
files
04182011
throough
06212011
DNV
daily
pictures
taken
ofinvestigation
BOP
Video
file
listing
04182011
through
06222011
DNV
inventoryof
videofiles
taken
of
investigation
8/27/2010
DNV
Report
No
201
0-1
220
G0M
vs
Norway
from
OLF/NOFO
Summary
ofdifferences
between
offshore
drilling
regulations
in
Norway
and
U.S
GulfofMexico
9/1/2004
API
Recomme
nded
Practice
63
Third
Edition
March
199
7
Reaffirmed
September
2004
Recommended
Practices
for
Blowout
Prevention
Equipment
SystemsforDrilling
Wells
3/1/2011
DHSG
Final
Report
9/1/2010
BP
Reportre
Deepwater
Horizon
Containment
and
Respo
nse
and
Lessons
Learned
Ex
3342
Ex
3343
Ex
3344
Ex
3286
Ex
3287
Ex
3288
Ex
3289
Ex
3290
Ex
3291
Ex
3292
Ex
3293
Ex
3294
Ex
3295
Ex
3296
Ex
3297
Ex
3298
Ex
3299
of65
Pages
8/3/2019 Stevick, Glen Expert Report Only
37/121
Ex
3300
Ex
3301
Ex
3302
Ex
3303
Ex
3304
Ex
3305
Ex
3306
Ex
3307
Ex
3308
Ex
3309
Ex
3310
Ex
3311
Ex
3312
Ex
3313
Ex
3314
Ex
3315
Ex
3316
Ex
3317
Ex
3318
Ex
3319
Ex
3320
Ex
3321
Ex
3322
Ex
3323
Ex
3324
Ex
3325
Ex
3326
Ex
3327
Ex
3328
Ex
3329
Ex
3330
Ex
3331
Ex
3332
Ex
3333
Ex
3334
Ex
3335
Ex
3336
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
38/121
Ex
3337
Ex
3338
Ex
3339
Ex
3340
Ex
3341
Ex
3147
Ex
3148
Ex
3129
Ex
3130
Ex
131
Ex
132
Ex
133
Ex
134
Ex
135
Ex
136
Ex
137
Ex
138
Ex
139
Ex
3140
Ex
3141
Ex
3142
Ex
3143
Ex
3144
Ex
3145
Ex
3146
Ex
3184
Ex
3185
Ex
186
Ex
187
Ex
166
Ex
167
Ex
168
Ex
169
Ex
170
Ex
171
Ex
172
Ex
3173
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
39/121
Ex
3174
Ex
3175
Ex
3176
Ex
3177
Ex
3178
Ex
3179
Ex
3180
Ex
3181
Ex
3182
Ex
3183
Ex
3797
Ex
3798
Ex
3799
Ex
3779
Ex
3780
Ex
3781
Ex
3782
Ex
3783
Ex
3784
Ex
3785
Ex
3786
Ex
3787
Ex
3788
Ex
3789
Ex
3790
Ex
3791
Ex
3792
Ex
3793
Ex
3794
Ex
3795
Ex
3796
Ex
3986
Ex
3987
Ex
3979
Ex
3980
Ex
3981
Ex
3982
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
40/121
8/3/2019 Stevick, Glen Expert Report Only
41/121
Ex1179
Ex1180
Ex
181
Ex
182
Ex
183
Ex
184
Ex
185
Ex
186
Ex
187
Ex
188
Ex
189
Ex
190
Ex
192
Ex
193
Ex
194
Ex1300
Ex3121
Ex3122
Ex3123
Ex3124
Ex3125
Ex3126
Ex3127
Ex3128
8/26/2011
Bea-G
ale
Ex
pertReportPis
8/26/20
George
Birch
ExpertReportPis
8/26/2011
Andrew
Hurs
t
ExpertReportP15
8/26/2011
Gregg
Perkin
ExpertReportP15
8/26/2011
David
Pritchard
ExpertReportP15
8/26/2011
GeoffWebste
r
ExpertReportPis
BP
Macondo
Bypass
Plot
Range
4-1
9-1
250
to
4-2
0
2200
SecSurface
Data
Review.x
ls
12/00/2002
West
Engine
ering
Services
Inc
Mini
Shear
Study
for
U.S
Minerals
Management
Service
Requisition
No
2-1
011-1
003
8/31/2011
Benge
Glen
ExpertReportUSA
8/31/2011
Davis
DrRory
ExpertReportUSA
8/31/2011
HeenanRic
hard
ExpertReportUSA
11
of65
Pages
8/3/2019 Stevick, Glen Expert Report Only
42/121
8/31/2011
Hu
ffman
Dr
Alan
Expert
ReportUSA
6/29/2011
Cow
ie
Jame
s
Deposition
Transcript
6/30/2011
Cow
ie
Jame
s
Deposition
Transcript
7/21/2011
Kasal
KalD
eposition
Transcript
4/6/2011
Sims
David
Deposition
Transcript
4/7/2011
Sims
David
Deposition
Transcript
Ex
1488
Ex
2223
Casing
Run
Torque
Data
9/19/2011
Gaude
EdD
eposition
Transcript
Ex
738
Ex
1260
3/30/20
Vargo
Richa
rd
Deposition
Transcript
3/31/2011
Vargo
Richa
rd
Deposition
Transcript
4/21/2011
Wa
lz
Gregory
Deposition
Transcript
4/22/20
Wa
lz
Gregory
Deposition
Transcript
5/11/2011
Gagliano
Jesse
Deposition
Transcript
9/27/2011
Childs
Greg
Expert
Report
Transocean
Ex
5768
Ex
5769
Ex
5770
Ex
5771
Ex
4000
Ex
4001
Ex
4002
Ex
4003
Ex
4004
Ex
4005
Ex
4006
Ex
4007
Ex
4008
Ex
4009
Ex
4010
Ex
4011
Ex
4012
Ex
4013
Ex
4014
12
of65
Pages
8/3/2019 Stevick, Glen Expert Report Only
43/121
Ex
4015
Ex
4016
Ex
4017
Ex
4018
Ex
4019
Ex
4020
Ex
4021
Ex
4022
Ex
4023
Ex
4024
Ex
4025
Ex
4026
Ex
4027
Ex
4028
Ex
4029
Ex
4030
Ex
4031
Ex
4032
Ex
4033
Ex
4034
Ex
4035
Ex
4036
Ex
4037
Ex
4038
Ex
4039
Ex
4040
Ex
4041
Ex
4042
Ex
4043
Ex
4044
Ex
4045
Ex
4046
Ex
4047
Ex
4048
Ex
4049
Ex
4050
Ex
4051
13
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
44/121
Ex
4052
Ex
4053
Ex
4054
Ex
4055
Ex
4056
Ex
4057
Ex
4058
Ex
4059
Ex
4060
Ex
4061
Ex
4062
Ex
4063
Ex
4064
Ex
4065
Ex
4066
Ex
4067
Ex
4068
Ex
4069
Ex
4070
Ex
4071
Ex
4072
Ex
4073
Ex
4074
Ex
4075
Ex
4076
Ex
4077
Ex
4078
Ex
4079
Ex
4080
Ex
4081
Ex
4082
Ex
4083
Ex
4084
Ex
4085
Ex
4086
Ex
4087
Ex
4088
14
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
45/121
Ex
4089
Ex
4090
Ex
4091
Ex
4092
Ex
4093
Ex
4094
Ex
4095
Ex
4096
Ex
4097
Ex
4098
Ex
4099
Ex
400
Ex
4101
Ex
4102
Ex
4103
Ex
4104
Ex
4105
Ex
4106
Ex
4107
Ex
4108
Ex
4109
Ex
4110
Ex
4111
Ex
4112
Ex
4113
Ex
4114
Ex
4115
Ex
4116
Ex
4117
Ex
4118
Ex
4119
Ex
4120
Ex
4121
Ex
4122
Ex
4123
Ex
4124
Ex
4125
15
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
46/121
Ex
4126
Ex
4127
Ex
128
Ex
129
Ex
130
Ex
131
Ex
132
Ex
133
Ex
134
Ex
135
Ex
136
Ex
137
Ex
138
Ex
139
Ex
140
Ex
141
Ex
142
Ex
143
Ex
144
Ex
145
Ex
146
Ex
147
Ex
148
Ex
149
Ex
150
Ex
151
Ex
152
Ex
153
Ex
154
Ex
155
Ex
156
Ex
157
Ex
158
Ex
159
Ex
160
Ex
161
Ex
4162
16
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
47/121
Ex
4163
Ex
4164
Ex
165
Ex
166
Ex
167
Ex
168
Ex
169
Ex
170
Ex
171
Ex
172
Ex
173
Ex
174
Ex
175
Ex
176
Ex
177
Ex
178
Ex
179
Ex
180
Ex
181
Ex
182
Ex
183
Ex
184
Ex
185
Ex
186
Ex
187
Ex
188
Ex
189
Ex
190
Ex
191
Ex
192
Ex
193
Ex
194
Ex
195
Ex
196
Ex
197
Ex
198
Ex
4199
17
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
48/121
Ex
4200
Ex
4201
Ex
4202
Ex
4203
Ex
4204
Ex
4205
Ex
4206
Ex
4207
Ex
4208
Ex
4209
Ex
4210
Ex
4211
Ex
4212
Ex
4213
Ex
4214
Ex
4215
Ex
4216
Ex
4217
Ex
4218
Ex
4219
Ex
4220
Ex
4221
Ex
4222
Ex
4223
Ex
4224
Ex
4225
Ex
4226
Ex
4227
Ex
4228
Ex
4229
Ex
4230
Ex
4231
Ex
4232
Ex
4233
Ex
4234
Ex
4235
Ex
4236
18
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
49/121
Ex
4237
Ex
4238
Ex
4239
Ex
4240
Ex
4241
Ex
4242
Ex
4243
Ex
4244
Ex
4245
Ex
4246
Ex
4247
Ex
4248
Ex
4249
Ex
4250
Ex
4251
Ex
4252
Ex
4253
Ex
4254
Ex
4255
Ex
4256
Ex
4257
Ex
4258
Ex
4259
Ex
4260
Ex
4261
Ex
4262
Ex
4263
Ex
4264
Ex
4265
Ex
4266
Ex
4267
Ex
4268
Ex
4269
Ex
4270
Ex
4271
Ex
4272
Ex
4273
19
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
50/121
Ex
4274
Ex
4275
Ex
4276
Ex
4277
Ex
4278
Ex
4279
Ex
4280
Ex
4281
Ex
4282
Ex
4283
Ex
4310
Ex
4311
Ex
4312
Ex
4313
Ex
4314
Ex
4315
Ex
4316
Ex
4317
Ex
4318
Ex
4319
Ex
4320
Ex
4321
Ex
4322
Ex
4323
Ex
4324
Ex
4325
Ex
4326
Ex
4327
Ex
4328
Ex
4329
Ex
4330
Ex
4331
Ex
4332
Ex
4333
Ex
4334
Ex
4335
Ex
4336
20
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
51/121
Ex
4337
Ex
4338
Ex
4339
Ex
4340
Ex
4341
Ex
4342
Ex
4343
Ex
4344
Ex
4345
Ex
4346
Ex
4347
Ex
4348
Ex
4349
Ex
4350
Ex
4351
Ex
4352
Ex
4353
Ex
4354
Ex
4355
Ex
4356
Ex
4357
Ex
4358
Ex
4359
Ex
4360
Ex
4361
Ex
4362
Ex
4363
Ex
4364
Ex
4365
Ex
4366
Ex
4367
Ex
4368
Ex
4369
Ex
4370
Ex
4371
Ex
4372
Ex
4373
21
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
52/121
Ex
4374
Ex
4380
Ex
4381
Ex
4382
Ex
4383
Ex
4384
Ex
4385
Ex
4386
Ex
4387
Ex
4388
Ex
4389
Ex
4390
Ex
4391
Ex
4392
Ex
4393
Ex
4394
Ex
4395
Ex
4400
Ex
4401
Ex
4402
Ex
4403
Ex
4404
Ex
4405
Ex
4406
Ex
4407
Ex
4408
Ex
4409
Ex
4410
Ex
4411
Ex
4412
Ex
4413
Ex
4414
Ex
4415
Ex
4416
Ex
4417
Ex
4418
Ex
4419
22
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
53/121
Ex
4420
Ex
4421
Ex
4422
Ex
4423
Ex
4424
Ex
4425
Ex
4426
Ex
4427
Ex
4428
Ex
4429
Ex
4430
Ex
4431
Ex
4432
Ex
4433
Ex
4434
Ex
4435
Ex
4436
Ex
4437
Ex
4438
Ex
4439
Ex
4440
Ex
4441
Ex
4442
Ex
4443
Ex
4444
Ex
4445
Ex
4446
Ex
4447
Ex
4448
Ex
4449
Ex
4450
Ex
4451
Ex
4452
Ex
4453
Ex
4454
Ex
4455
Ex
4456
23
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
54/121
Ex
4457
Ex
4458
Ex
4459
Ex
4460
Ex
4461
Ex
4462
Ex
4463
Ex
4464
Ex
4465
Ex
4466
Ex
4467
Ex
4468
Ex
4469
Ex
4470
Ex
4471
Ex
4472
Ex
4476
Ex
4477
Ex
4478
Ex
4479
Ex
4480
Ex
4481
Ex
4482
Ex
4483
Ex
4484
Ex
4485
Ex
4486
Ex
4487
Ex
4488
Ex
4489
Ex
4490
Ex
4491
Ex
4492
Ex
4493
Ex
4494
Ex
4500
Ex
4501
24
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
55/121
Ex
4502
Ex
4503
Ex
4504
Ex
4505
Ex
4506
Ex
4507
Ex
4508
Ex
4509
Ex
4510
Ex
4511
Ex
4512
Ex
4513
Ex
4514
Ex
4515
Ex
4516
Ex
4517
Ex
4518
Ex
4519
Ex
4520
Ex
4521
Ex
4522
Ex
4523
Ex
4524
Ex
4525
Ex
4526
Ex
4527
Ex
4528
Ex
4529
Ex
4530
Ex
4531
Ex
4532
Ex
4533
Ex
4534
Ex
4535
Ex
4536
Ex
4537
Ex
4538
25
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
56/121
Ex
4539
Ex
4540
Ex
4541
Ex
4542
Ex
4543
Ex
4544
Ex
4545
Ex
4546
Ex
4547
Ex
4548
Ex
4549
Ex
4550
Ex
4551
Ex
4552
Ex
4553
Ex
4554
Ex
4555
Ex
4556
Ex
4557
Ex
4558
Ex
4559
Ex
4560
Ex
4561
Ex
4562
Ex
4563
Ex
4564
Ex
4565
Ex
4566
Ex
4567
Ex
4568
Ex
4569
Ex
4570
Ex
4571
Ex
4572
Ex
4573
Ex
4574
Ex
4575
26
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
57/121
Ex
4576
Ex
4577
Ex
4578
Ex
4579
Ex
4580
Ex
4581
Ex
4582
Ex
4583
Ex
4584
Ex
4585
Ex
4586
Ex
4587
Ex
4588
Ex
4589
Ex
4590
Ex
4591
Ex
4592
Ex
4593
Ex
4594
Ex
4595
Ex
4596
Ex
4597
Ex
4598
Ex
4599
Ex
4600
Ex
4601
Ex
4602
Ex
4603
Ex
4604
Ex
4605
Ex
4606
Ex
4607
Ex
4608
Ex
4609
Ex
4610
Ex
4611
Ex
4612
27
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
58/121
Ex
4613
Ex
4614
Ex
4615
Ex
4616
Ex
4617
Ex
4618
Ex
4619
Ex
4620
Ex
4621
Ex
4622
Ex
4623
Ex
4624
Ex
4625
Ex
4626
Ex
4627
Ex
4628
Ex
4629
Ex
4630
Ex
4631
Ex
4632
Ex
4633
Ex
4634
Ex
4635
Ex
4636
Ex
4637
Ex
4638
Ex
4639
Ex
4640
Ex
4641
Ex
4642
Ex
4643
Ex
4644
Ex
4645
Ex
4646
Ex
4647
Ex
4648
Ex
4649
28
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
59/121
Ex
4650
Ex
4651
Ex
4652
Ex
4653
Ex
4654
Ex
4655
Ex
4656
Ex
4657
Ex
4658
Ex
4659
Ex
4660
Ex
4661
Ex
4662
Ex
4663
Ex
4664
Ex
4665
Ex
4666
Ex
4667
Ex
4668
Ex
4669
Ex
4670
Ex
4671
Ex
4672
Ex
4673
Ex
4674
Ex
4675
Ex
4676
Ex
4677
Ex
4678
Ex
4679
Ex
4680
Ex
4681
Ex
4682
Ex
4683
Ex
4684
Ex
4685
Ex
4686
29
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
60/121
Ex
4687
Ex
4688
Ex
4689
Ex
4690
Ex
4691
Ex
4692
Ex
4693
Ex
4694
Ex
4695
Ex
4696
Ex
4697
Ex
4698
Ex
4699
Ex
4700
Ex
4701
Ex
4702
Ex
4703
Ex
4704
Ex
4705
Ex
4706
Ex
4707
Ex
4708
Ex
4709
Ex
4710
Ex
4711
Ex
4712
Ex
4713
Ex
4714
Ex
4715
Ex
4716
Ex
4717
Ex
4718
Ex
4719
Ex
4720
Ex
4721
Ex
4722
Ex
4723
30
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
61/121
Ex
4724
Ex
4725
Ex
4726
Ex
4727
Ex
4728
Ex
4729
Ex
4730
Ex
4731
Ex
4732
Ex
4733
Ex
4734
Ex
4735
Ex
4736
Ex
4737
Ex
4738
Ex
4739
Ex
4740
Ex
4741
Ex
4742
Ex
4743
Ex
4744
Ex
4745
Ex
4746
Ex
4747
Ex
4748
Ex
4749
Ex
4750
Ex
4751
Ex
4752
Ex
4753
Ex
4754
Ex
4755
Ex
4756
Ex
4757
Ex
4758
Ex
4759
Ex
4760
31
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
62/121
Ex
4761
Ex
4762
Ex
4763
Ex
4764
Ex
4765
Ex
4766
Ex
4767
Ex
4768
Ex
4769
Ex
4770
Ex
4771
Ex
4772
Ex
4773
Ex
4774
Ex
4775
Ex
4776
Ex
4777
Ex
4778
Ex
4779
Ex
4780
Ex
4781
Ex
4782
Ex
4783
Ex
4784
Ex
4785
Ex
4786
Ex
4787
Ex
4788
Ex
4789
Ex
4790
Ex
4791
Ex
4792
Ex
4793
Ex
4794
Ex
4795
Ex
4796
Ex
4797
32
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
63/121
Ex
4798
Ex
4799
Ex
4800
Ex
4801
Ex
4802
Ex
4803
Ex
4804
Ex
4805
Ex
4806
Ex
4807
Ex
4808
Ex
4809
Ex
4810
Ex
4811
Ex
4812
Ex
4813
Ex
4814
Ex
4815
Ex
4816
Ex
4817
Ex
4818
Ex
4819
Ex
4820
Ex
4821
Ex
4822
Ex
4823
Ex
4824
Ex
4825
Ex
4826
Ex
4827
Ex
4828
Ex
4829
Ex
4830
Ex
4831
Ex
4832
Ex
4833
Ex
4834
33
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
64/121
Ex
4835
Ex
4836
Ex
4837
Ex
4838
Ex
4839
Ex
4840
Ex
4841
Ex
4842
Ex
4843
Ex
4844
Ex
4845
Ex
4846
Ex
4847
Ex
4848
Ex
4849
Ex
4850
Ex
4851
Ex
4852
Ex
4853
Ex
4854
Ex
4855
Ex
4856
Ex
4857
Ex
4858
Ex
4859
Ex
4860
Ex
4861
Ex
4862
Ex
4863
Ex
4864
Ex
4865
Ex
4866
Ex
4867
Ex
4868
Ex
4869
Ex
4870
Ex
4871
34
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
65/121
Ex
4872
Ex
4873
Ex
4874
Ex
4875
Ex
4876
Ex
4877
Ex
4878
Ex
4879
Ex
4880
Ex
4881
Ex
4882
Ex
4883
Ex
4884
Ex
4885
Ex
4886
Ex
4887
Ex
4888
Ex
4889
Ex
4890
Ex
4891
Ex
4892
Ex
4893
Ex
4894
Ex
4895
Ex
4896
Ex
4897
Ex
4898
Ex
4899
Ex
4900
Ex
4901
Ex
4902
Ex
4903
Ex
4904
Ex
4905
Ex
4906
Ex
4907
Ex
4908
35
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
66/121
Ex
4909
Ex
4910
Ex
4911
Ex
4912
Ex
4913
Ex
4914
Ex
4915
Ex
4916
Ex
4917
Ex
4918
Ex
4919
Ex
4920
Ex
4921
Ex
4922
Ex
4923
Ex
4924
Ex
4925
Ex
4926
Ex
4927
Ex
4928
Ex
4929
Ex
4930
Ex
4931
Ex
4932
Ex
4933
Ex
4934
Ex
4935
Ex
4936
Ex
4937
Ex
4938
Ex
4939
Ex
4940
Ex
4941
Ex
4942
Ex
4943
Ex
4944
Ex
4945
36
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
67/121
Ex
4946
Ex
4947
Ex
4948
Ex
4949
Ex
4950
Ex
4951
Ex
4952
Ex
4953
Ex
4954
Ex
4955
Ex
4956
Ex
4957
Ex
4958
Ex
4959
Ex
4960
Ex
4961
Ex
4962
Ex
4963
Ex
4964
Ex
4965
Ex
4966
Ex
4967
Ex
4968
Ex
4969
Ex
4970
Ex
4971
Ex
4972
Ex
4973
Ex
4974
Ex
4975
Ex
4976
Ex
4977
Ex
4978
Ex
4979
Ex
4980
Ex
4981
Ex
4982
37
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
68/121
Ex
4983
Ex
4984
Ex
4985
Ex
4986
Ex
4987
Ex
4988
Ex
4989
Ex
4990
Ex
4991
Ex
4992
Ex
4993
Ex
4994
Ex
4995
Ex
4996
Ex
4997
Ex
4998
Ex
4999
Ex
5000
Ex
5001
Ex
5002
Ex
5003
Ex
5004
Ex
5005
Ex
5006
Ex
5007
Ex
5008
Ex
5009
Ex
5010
Ex
5011
Ex
5012
Ex
5013
Ex
5014
Ex
5015
Ex
5016
Ex
5017
Ex
5018
Ex
5019
38
of
65
Pages
8/3/2019 Stevick, Glen Expert Report Only
69/121
Ex
5020
Ex
5021
Ex
5022
Ex
5023
Ex
5024
Ex
5025
Ex
5026
Ex
5027
Ex
5028
Ex
5029
Ex
5030
Ex
5031
Ex
5032
Ex
5033
Ex
5034
Ex
5035
Ex
5036
Ex
5037
Ex
5038
Ex
5039
Ex
5040
Ex
5041
Ex
5042
Ex
5043
Ex
5044
Ex
5045
Ex
5046
Ex
5047
Ex
5048
Ex
5049
Ex
5050
Ex
5051
Ex
5052
5053
5054
5055
5056
39