Stevick, Glen Expert Report Only

Embed Size (px)

Citation preview

  • 8/3/2019 Stevick, Glen Expert Report Only

    1/121

    Expert Report of Glen Stevick Ph.D P.E

    IN THE UNITED STATES DISTRICT COURT

    FOR THE EASTERNDISTRICT

    OFLOUISIANA

    IN RE OIL SPILL by the OIL RIG

    DEEPWATER HORIZON in the

    GULF OF MEXICO MDL No 2179

    on APRIL20 2010

    SectionJ

    Applies to

    The Honorable Judge Barbier

    ALL CASES and Mag Judge Shushan210-cv-02771

    ____________________________________________________________________________

    AMENDED EXPERT REPORT OF GLEN STEVICK Ph.D P.E

    II

  • 8/3/2019 Stevick, Glen Expert Report Only

    2/121

    Expert Report of Glen Stevick Ph.D P.E

    TABLE OF CONTENTS

    FINDINGS

    II THE BLOWOUT PREVENTER PURPOSE

    STRUCTURE AND DESIGN

    The BOP Purpose

    BOP Structure

    BOP Control 10

    Communicating with the BOP 10

    Activating the BSR 11

    BOP Design 13

    Ill THE BOP DESIGN WAS DEFECTIVE BECAUSE

    IT RELIED ON SINGLE BSR 15

    The BSR was Single Point of Failure for the

    DWHBOP 15

    The Potential for Off-Center Drill Pipe was

    Well Known to BP and Transocean 16

    IV TRANSOCEAN USED FLAWED CONDITION-

    BASED MAINTENANCE 17

    Transocean Failed to Recertify the BOP Every

    3-5 Years as Specified by API and Cameron 17

    Transoceans Condition-Based Maintenance

    is Flawed Because Only Equipment With

    Measured Problems or Failures Gets Fixed or

    Replaced 19

    Problems that cannot be measured are

    not considered 19

    Need for improved equipment is not

    considered 20

    21

  • 8/3/2019 Stevick, Glen Expert Report Only

    3/121

    Expert Report of Glen Stevick Ph.D P.E

    Implementing BAST is discouraged 21

    BP FAILED TO IMPLEMENT BAST IN THE BOP 21

    BP Failed to Implement BAST for the BSR 21

    BP and Transocean Failed to Upgrade the

    BOP to Include Second BSR 24

    BP and Transocean Failed to Upgrade to

    Camerons Mark Ill BOP Control Pod 24

    BP Failed to Implement BAST by Relying

    Solely on MUX Cablesfor EDS 25

    BP and Transocean Failed to Implement

    BAST by Using EDS-1 Instead of EDS-2 25

    VI THE UNDERCHARGED BLUE CONTROL POD

    BATTERIES AND INCORRECTLY WIRED

    YELLOW CONTROL POD SOLENOID 103Y MAY

    HAVE BEEN CONTRIBUTING CAUSES OF THE

    BOPS INABILITY TO STOP THE BLOWOUT 26

    Undercharged Blue Control Pod Batteries 27

    Incorrectly Wired Yellow Control Pod Solenoid

    103Y 27

    The AMF/Deadman Likely Failed to Actuate

    the BSR because of Low Blue Pod Battery

    and the Incorrectly Wired Yellow Pod Solenoid 28

    The BSR Likely Would Have Completely

    Sheared the Drill Pipe and Sealed the Well if

    the BSR had been Activated when the Drill

    Pipe was Centered 28

  • 8/3/2019 Stevick, Glen Expert Report Only

    4/121

    Expert Report of Glen Stevick Ph.D P.E

    LIST OF FIGURES

    Figure The DWH BOP showing the position of annulars and valves

    Figure The Cameron BSR used in the DWH BOP

    Figure Model of the DWH BOP BSR from the Det Norske Veritas

    DNV report

    Figure Model of the DWH and BOP from the DNV report

    41

  • 8/3/2019 Stevick, Glen Expert Report Only

    5/121

    Expert Report of Glen Stevick Ph.D P.E

    INTRODUCTION

    Berkeley Engineering And Research Inc was retained by Halliburton

    Energy Services Inc to assess the design of the blowout preventerBOP used at the Deepwater Horizon DWH and the BOPscontribution to the well blowout explosion fire and spill on April 20 2010

    At the time of the incident the DWH was in the process of temporarily

    abandoning BPs Macondo deepwater well after reaching depth of

    approximately 18360 ft 12360 ft below the seafloor in the Gulf of

    Mexico G0M

    My opinions are based upon the materials and information have

    reviewed my analysis of that information my education training

    experience and knowledge in the areas of mechanical engineering failure

    analysis and design and material behavior and my knowledge of oilfield

    and offshore equipment e.g offshore platforms BOPs casings and drill

    strings

    My opinions are also based upon the engineering standard of care

    standards recommended practices and regulations relevant to

    offshore oil and gas exploration and drilling and production activities

    have not been asked to make any assumptions nor have presumed

    anyfacts

    beyondthose which are cited as material relied

    uponin this

    Reportand its attachments

    FINDINGS

    Based upon my education training experience in hydraulics electronic

    controls and offshore mechanical engineering design review of Phase

    and Phase II forensic testing and examination of the DWH BOP my review

    of supporting documents testimony and other evidence including the

    materials identified in Appendix and the calculations shown in this report

    and itsappendixes

    have found thefollowing

    to be true

    British Petroleum BP and Vastar Resources Inc Vastarwhich BP acquired specified the design and configuration of the

    DWH BOP which was constructed by Cameron International

    Corp Cameron

    The BOP relied upon single blind shear ram BSR to be ableto shear drill pipe and seal the well in the case of an emergency

    51

  • 8/3/2019 Stevick, Glen Expert Report Only

    6/121

    Expert Report of Glen Stevick Ph.D P.E

    This made the BSR single point of failure for the entire BOP of

    which BP was aware

    Transocean implemented flawed condition-based maintenance

    system that did not identify the need for technology upgrades to

    account for past design deficiencies and the issues associated

    with drilling in deeper and deeper water This condition-based

    maintenance program did not allow Transocean to ensure proper

    maintenance and certification of the existing BOP and its

    components

    BP and Transocean failed to implement the best available and

    safest technologyBAST

    in theBOP

    SpecificallyBP

    andTransocean failed to use

    BSR Double Shear rams that would have sheared and

    sealed off-center drill pipe

    two BSRs--one to shear the pipe and the other to seal the well

    an Emergency Disconnect Sequence EDS that activated theCasing Shear Rams CSR5 to center the pipe before

    activating the BSR to shear and seal the pipe

    an Acoustic Control System ACS as redundant means ofcommunication between the DWH rig and the BOP and

    Camerons Mark Ill control pod system that used rechargeable

    BOP control pod batteries and enabled battery lev els to be

    monitored remotely

    The undercharged batteries in the blue BOP control pod and

    incorrectly wired solenoid 103Y were the result of Transoceans

    flawed condition-based maintenance program and the failure of

    BP and Transocean to implement BAST The undercharged

    batteries and incorrectly wired solenoid may have beencontributing causes of the blowout if they prevented the Automatic

    Mode Function AMF/Deadman from activating the BSR at

    time when the drill pipe was centered and could have been

    sheared and closed by the BSR

    61

  • 8/3/2019 Stevick, Glen Expert Report Only

    7/121

    Expert Report of Glen Stevick Ph.D P.E

    II THE BLOWOUT PREVENTER PURPOSE STRUCTURE AND

    DESIGN

    The BOP Purpose

    The primary purpose of the BOP is to prevent uncontrolled oil and gas from

    reaching the DWH i.e to prevent blowout As in any mobile offshore

    drilling unit MODU the DWH BOP is critical subsea component usedto seal control and monitor the well during drilling operations As stated in

    BPs internal documents

    Blowout equipment is the final l ine of defense

    agains t catastrophic event which may include

    fatalities uncontrollable release of oil and gas and

    evacuation of entire communities.1

    Indeed BPs CEO considered BOP to be fail-safe piece of equipment

    that was the last line of defense against blowout.2 Similarly

    Transocean recognized the BOP as critical piece of equipment.3

    BP-Wells Engineer OJT Module BP-HZN-2179MDL01342044-01342052 Exhibit

    2096

    Deposition of Tony Hayward June and 2011 23510-19

    Deposition of William Stringfellow April 11-12 2011 2036-9

    71

  • 8/3/2019 Stevick, Glen Expert Report Only

    8/121

    Expert Report of Glen Stevick Ph.D P.E

    BOP Structure

    As shown to the right in figure

    the BOP on the DWH consists of

    two main parts an upper

    portion called the Lower Marine

    Riser Package LMRP andLower BOP Stack sitting below

    the LMRP The LMPR contains

    two annulars while the lower

    BOP package includes single

    BSR single CSR two variable

    shear rams VBR5 and TestRam an inverted VBR to resist

    downward pressure

    till

    ________H_LowerBOP Stack

    Fig The DWH BOP showing the position of annulars and valves.4

    The BSR used in the BOP is of particular importance because the BSR is

    the device ultimately responsible for shearing the drill pipe and sealing thewell in the case of an emergency The single BSR in the DWH BOP was

    Cameron shearing blind ram as shown below

    Perkin CS Expert Report August 26 2011 Cited image source EngineeringPartners International LLC

    Upper Annular

    Lower Annular

    81

  • 8/3/2019 Stevick, Glen Expert Report Only

    9/121

    SF-E4A11Q FLIND FA

    Fig The Cameron BSR used in the DWH BOP

    The shearing blind ram includes lower ram with straight blade and an

    upper ram with shaped blade The shearing blind ram is designed to

    shear drill pipe located within the cutting blades and seal the wellbore The

    BOP has bore of 18-3/4 inches and the cutting blades are only 17-7/8

    inches for the lower straight blade and 15-1/4 inches for the upper V-shaped

    blade This leaves gaps within the wellbore that are outside of the cutting area

    of the shearing blind ram blades as shown below in figure

    Fig Model of the DWH BOP BSR from the Det Norske Veritas

    DNV report.6

    Cameron EB 852D Exhibit 7001 The shaded areas represent elastomeric sealing

    elements

    Expert Report of Glen Stevick Ph.D P.E

    91

  • 8/3/2019 Stevick, Glen Expert Report Only

    10/121

    Expert Report of Glen Stevick Ph.D P.E

    BOP Control

    Communicating with the BOP

    The DWH BOP was controlled by Cameron Mark II electro-hydraulic

    multiplex UX control system.7

    As shown in the modified

    version of figure to the

    right the LMRP portion of

    the BOP contains two

    redundant control pods

    referred to as the blue and

    yellow pods The control

    pods provided control

    functionality and

    communication between

    the BOP and the DWH rig

    via wired MUX cables that

    ran from the control pods

    through the water up to

    the DWH where the crewcould control the BOP

    using control panels

    Because control

    commands from the DWH

    could only be transmitted

    via the MUX cables the

    ability of the DWH crew to

    directly control the BOP

    was completely contingent

    upon properly functioning

    MUX cables

    Lwr AnrijIa

    Det Norske Veritas Final Report for United States Department of the Interior Bureau

    of Ocean Energy Management Regulation and Enforcement Forensic Examination of

    Deepwater Horizon Blowout Preventer Contract Award No M10PX00335 Volume

    Final Report Report No EP030842 20 March 2011 DNV Report Vol Figure 132

    Deposition of Jack Erwin June 6-7 2011 36715-17

    Yellow Coritol Pod

    iue Control

    4-Ipp .nriuia

    Lor BOF

    101

  • 8/3/2019 Stevick, Glen Expert Report Only

    11/121

    Expert Report of Glen Stevick Ph.D P.E

    Fig The DWH BOP including identification of the blue and yellow control

    pods.8

    Figure below shows model of the DWH rig and BOP including

    identification of various BOP components the MUX cables the

    accumulators that provide hydraulic pressure to activate the BOP rams

    images of BOP control panels and an image of BOP control pod

    Fig Model of the DWH and BOP from the DNV report.9

    Activating the BSR

    There were several different methods of controlling the BOP and activating

    the BSR including

    Perkin CS Expert Report August 26 2011 Cited image source EngineeringPartners International LLC Image modified to identify the blue and yellow control

    pods

    DNV Report Vol Appendix Figure

    LMAP

    M.tI

    4- i1 li.W

    III

  • 8/3/2019 Stevick, Glen Expert Report Only

    12/121

    Expert Report of Glen Stevick Ph.D P.E

    Activation of the BOP high pressure BSR function from

    either of two control panels located on theDWH

    Thismethod requires MUX line communication to an operational

    control pod

    Activation of the Emergency Disconnect Sequence

    EDS which is also activated from either of the two controlpanels on the DWH and requires MUX line communication to

    an operational control pod The primary function of the EDS

    is to allow the rig to disconnect from the BOP if the dynamic

    positioning system that holds the rig in position fails

    Activation of the AMF/Deadman circuits located in the

    Subsea Electronic Modules SEM5 within either of the blueor yellow control pods mounted on the LMRP The AMF is

    designed to activate automatically i.e without requiring

    initiation by user when the BOP loses hydraulic pressureelectrical power or electronic communication with the DWH

    Remotely Operated Vehicle ROy initiation of the AMFby cutting the MUX and hydraulic lines on the BOP

    ROV initiation of the Autoshear function by severing the

    autoshear activation rod that connects the LMRP to the BOP

    stack intended to activate if the LMRP and BOP are

    separated

    ROV hot stab connection to the BOP hydraulics The

    ROV can use onboard hydraulic pumping to power the BOP

    hydraulics

    The AMF is based on Cameron circuit board that implements the AMFfunctionality The AMF requires at least one functional control pod i.eeither the blue or yellow control pod to initiate and complete its sequence

    including to activate the BSR Each of the two control pods contains two

    SEMs i.e SEM and SEM and each SEM contains an AMF card To

    power the AMF cards each SEM contains dedicated volt battery i.eone per SEM two for each of the blue and yellow control pods and four

    total for the BOP Each control pod also contains single 27 volt DCbattery pack to power the two SEMs in that pod Each control pod also

    12

  • 8/3/2019 Stevick, Glen Expert Report Only

    13/121

    Expert Report of Glen Stevick Ph.D P.E

    contains high-pressure shear circuit that activates the BSR The high-

    pressure shear circuit is energized by solenoid 103 in that pod i.e 103B

    forthe blue pod and 103Y

    forthe yellow pod which activates

    for

    30seconds when the AMF is triggered Each solenoid 103 contains two coils

    with one coil connected to each of SEM and SEM in that solenoids

    pod Each of the 103 solenoids is powered by the 27 volt battery packfrom its respective pod.11

    BOP Design

    According to information reviewed by BPs Vice President of Engineeringand Quality for the Drilling Systems Division12 BP was involved in the

    configuration ofDWH BOP from the beginning13 and BP played an

    active role in specifying DWH BOP stack.14

    The DWH was built in 2000 at the Hyundai Heavy Industries Shipyard in

    South Korea for cost of approximately $350 million It was originally built

    for and commissioned by Falcon Drilling Co Falcon which later

    became part of Transocean The DWH was originally contracted to Vastar

    which was later acquired by BP The DWH BOP was first contemplated in

    1998 Drilling Contract between Vastar and Falcon Drilling Contract.5

    Under the Drilling Contract Falcon was to furnish and pay for the B0P16

    and to ensure that the BOP was adequately maintained and in such

    condition as to permit continuous and efficient operation.7

    10

    Deposition of Edward Gaude September 19 2011 12414-25

    Deposition of William LeNormand June 20-21 2011 15822 1593

    12

    Deposition of David McWhorter July 7-8 2011 1316-18

    13

    Deposition of David McWhorter July 7-8 2011 5919-11

    14

    Depositionof David McWhorter

    July7-8 2011 33023-3313

    15BP-HZN-21 79MDL00056656-936

    16BP-HZN-2 79MDL00056656-936 at BP-HZN-21 79MDL00056768 Blowout

    preventers are to be furnished and paid for by the CONTRACTOR i.e Falcon under

    Exhibit B-3 paragraph .20 of the Drilling Contract

    17BP-HZN-21 79MDL00056656-936 at BP-HZN-21 79MDL00056674 Under section

    14.1.1 of the Drilling Contract CONTRACTOR i.e Falcon agrees to maintain all

    equipment and materials furnished by CONTRACTOR which i ncludes t he BOP as

    noted in Exhibit B-3 paragraph .20 of the Drilling Contract

    131

  • 8/3/2019 Stevick, Glen Expert Report Only

    14/121

    Expert Report of Glen Stevick Ph.D P.E

    Although the BOP was manufactured and sold by Cameron and purchased

    by Falcon Vastar was heavily involvedin

    theBOP

    design configurationchoice of components and controls.18 Vastar chose the configuration

    of the BOP Stack and the type of rams for each cavity19 the routing of

    the MUX lines20 that there would be no acoustic communications21

    factory adjustments by Cameron prior to acceptance22 and the EDS

    program mode EDS-1 23

    Furthermore for BOP designs BP decides what the BOP stack

    configuration will be and instructs its drilling contractors including

    Transocean regarding what types of rams should be used and where the

    rams will be located in the BOP.24 Here BP specified the configuration of

    the BOP in its original contract with Transocean and re-specified the

    configuration in September 2009 in contract amendment.25 As Operator

    of the Macondo well site BP is also ultimately responsible for the BOP

    under the Code of Federal Regulations CFR5 and the AmericanPetroleum Institute API Recommended Practices RP26

    18

    Exhibit

    5094BP-HZNBLYOO294O35

    19Exhibit 4112 deposition of Michael Byrd July 13-14 2011 48812-49418

    20 BP-HZNBLY00294826

    21

    BP-HZNBLYOO29435O

    22BP-HZNBLY00294352

    23BP-HZNCECO30029 As discussed further below EDS-1 closes only the BSR

    whereas the other available EDS mode EDS-2 first closes the CSR and then the BSR

    Had this mode been selected it likely would have centered the drill pipe before attempt

    attempting to shear the pipe which likely would have sealed the well

    24Deposition of Tony Hayward June and 2011 5731-14

    25 Amendment 38 to Contract No 980249 September 28 2009 BP-HZN-CECO4 1476Exhibit 1488

    26Code of Federal Regulations Title 30 Part 250 Oil and Gas and Sulphur Operations in

    the Outer Continental Shelf Subpart 30 CFR 250 Section 250.400 et seqAmerican Petroleum Institution Recommended Practice 53 Recommended Practices

    for Blowout Prevention Equipment Systems for Drilling Wells API RP 53

    141

  • 8/3/2019 Stevick, Glen Expert Report Only

    15/121

    Expert Report of Glen Stevick Ph.D P.E

    Ill THE BOP DESIGN WAS DEFECTIVE BECAUSE IT RELIED ON

    SINGLE BSR

    After the Macondo blowout BP acknowledged that it had relied on the BOP

    as the ultimate form of containment in the event of blowout.27 BP also

    recognized that in the case of blowout the BSR was the most critical well

    control device within the BOP.28 Despite the importance of the BSR and its

    crucial role in the operation of the BOP and overall well safety BP failed to

    design and implement within the BOP BSR that could reliably shear the

    drill pipe and seal the well under foreseeable operating conditions

    The BSR was Single Point of Failure for the DWH BOP

    Although there are several ways to activate the BSR all of the DWH

    emergency systems relied upon the BOPs single BSR to be able to shear

    the drill pipe and seal the well in the case of an emergency making the

    BSR single point of failure for the entire BOP safety system Failure of

    the BSR to shear the drill pipe and seal the well for whatever reason

    would result in total failure of the entire BOP to perform its intended

    function of preventing blowout Indeed 2001 Risk Assessment of the

    DWH BOP identified the risks inherent to the BOP stack configuration with

    single BSR

    The major contributor to the failure likelihood

    associated with the BOP control system results from

    the selected stack configuration With only one

    shear ram capable of sealing the well in it is

    extremely difficult to remove all of the single failure

    points from the system.29

    27Deposition of Tony Hayward June and 820112351-92777-103017-10

    28Deposition of Tony Hayward June and 820112897-14

    29Risk Assessment of the Deepwater Horizon Blowout Preventer BOP Control

    System Final Report April 2000 CAM-CIV-0019032 CAM-CIV-0019076 at CAM-CIV

    0019070 Exhibit 4120 at 37

    151

  • 8/3/2019 Stevick, Glen Expert Report Only

    16/121

    Expert Report of Glen Stevick Ph.D P.E

    The Risk Assessment further noted that the BSR including the final shuttle

    valve that supplies hydraulic pressure to the BSR accounts for 56% of the

    failurelikelihood of the system to successfully perform

    its EDSoperation.3

    The Potential for Off-Center Drill Pipe was Well Known to

    BP and Transocean

    BOP with single BSR is particularly deficient For example in

    situations when the EDS system requires activation BPs VP of

    Technology for Global Wells Organization noted that EDS pipe is alwaysoff center.31 As discussed above EDS is primarily designed for use in

    scenarioswhere some aspect

    of therigs dynamic positioning system has

    failed and the rig has drifted from its intended location

    those scenarios for which EDS has been

    designed the pipe is likely to be off center because

    of the huge tension that is on the pipe.32

    Potential causes of off-center drill pipe include pipe distortion or bowing

    from internal pressure loss of rig control and drift debris pushing the pipe

    off-center ram pushing the drill pipe off-center multiple pipes in the riser

    and elastic buckling.33 Of the potential causes elastic buckling is the most

    likely to have forced the drill pipe off-center.34 Additionally helical buckling

    is particular type of elastic buckling that has been well known for many

    years in the drilling context.35 It does not appear that Transocean or BP

    ever conducted any testing or analysis of the BSRs ability to shear off-

    center drill pipe

    30

    Risk Assessment of the Deepwater Horizon Blowout Preventer BOP ControlSystem Final Report April 2000 CAM-CIV-0019032 CAM-CIV-0019076 at CAM-CIV

    0019072 Exhibit 4120at

    3931

    Deposition of Fereidoun Abbassian May 3-4 2011 502-3

    32Deposition of Fereidoun Abbassian May 3-4 2011 5010-13

    DNV Report Addendum p.6-8 section 2.2.1

    DNV Report Addendum 6-11 section 2.2

    Lubinski Althouse W.S and Logan J.L Helical Buckling of Tubing Sealed in

    Packers JPT 655-70 June 1962

    161

  • 8/3/2019 Stevick, Glen Expert Report Only

    17/121

    Expert Report of Glen Stevick Ph.D P.E

    IV TRANSOCEAN USED FLAWED CONDITION-BASED

    MAINTENANCE

    As noted above under the Drilling Contract between BP through its

    predecessor Vastar and Transocean through its predecessor Falcon

    Transocean had primary responsibility for maintenance of the BOP.36

    Transocean Failed to Recertify the BOP Every 3-5 Years as

    Specified by API and Cameron

    Transocean failed to follow the testing and maintenance guidelines

    specified in 30 CFR 250 and API RP 5337 In particular Transocean

    ignored the requirement that

    After every 3-5 years of sen/ice the BOP stack

    choke manifold and diverter components should be

    disassembled and inspected in accordance with the

    manufacturers guidellnes.38

    36

    BP-HZN-21 79MDL00056656-936 at BP-HZN-21 79MDL00056674 Under section

    14.1.1 of the Drilling Contract CONTRACTOR i.e Falcon agrees to maintain all

    equipment and materials furnished by CONTRACTOR which i ncludes t he BOP as

    noted in Exhibit B-3 paragraph .20 of the Drilling Contract

    See 30 CFR 250 et seq API RP 53

    38API RP 53 section 17.10.3 see also 30 CFR 250.446 requiring that BOP

    maintenance and inspections must meet or exceed the provisions described in API

    RP 53

    171

  • 8/3/2019 Stevick, Glen Expert Report Only

    18/121

    Expert Report of Glen Stevick Ph.D P.E

    The recurring disassembly and inspection of the entire BOP as outlined in

    API RP 53 occurs at the surface and is important to maintaining safe and

    effective BOP The advantages of regularly scheduled recertification areas follows

    Consistent with the API the BOP manufacturer Cameron also

    recommends that the BOP stack be recertified every 3-5 years.39 In

    contrast an independent inspection of DWH two weeks before the blowout

    found that for the BOP upon review of certification documentation it was

    noted that the date of last manufacturers certification was 13 December

    2000 and this is beyond the yearly inspection overhaul and re

    certification requirement.4 Although Transocean recognized that both the

    API and Cameron recommended disassembly inspection and

    recertification of the entire BOP every 3-5 years Transocean knowinglychose not to follow this recommendation.41

    Deposition of Mark Hay June 29-30 2011 1197-12011

    40 MODU Condition Assessment DEEPWATER HORIZON ModuSpec USA Inc 4/1-

    14/2010 TRN-USCG_

    MMS-00038652

    41

    Deposition of William Stringfellow April 11-12 2011 21625-21713

    Advantages of API/Cameron BOP

    Recertification

    Provides periodic opportunities to examine

    individual BOP components for corrosion wear

    and other flaws and to replace components when

    necessary

    Provides periodic opportunities to evaluate the

    BOP design and replace deficient or outdated

    components with BAST components and

    technology

    Ensures

    components

    every 3-5 years

    that the entire BOP and its

    are inspected at least as often as

    181

  • 8/3/2019 Stevick, Glen Expert Report Only

    19/121

    Expert Report of Glen Stevick Ph.D P.E

    Transoceans Condition-Based Maintenance is Flawed

    Because Only Equipment With Measured Problems or

    Failures Gets Fixedor Replaced

    When the piece of equipment falls we replace it or make

    repairs to it.42

    Instead of complying with the API and Camerons maintenance guidelines

    for the BOP Transocean followed its own condition-based maintenance

    program.43 Under this condition-based maintenance program BOP

    components are not automatically removed from operation and inspected

    every 3-5 years.44 Rather Transocean personnel would take

    measurements and test BOP equipment45 and when piece of equipment

    s tarted to create problems or fail Transocean fixed it.46 This type of

    condition-based maintenance is subject to numerous flaws

    Problems with Transoceans Condition-Based

    Maintenance

    Equipment deterior at ion that cannot be

    measured is not considered

    Need for improved equipment based on design

    flaws new industry experience or operation in

    more difficult environment is not considered

    Replacement of otherwise functioning

    equipment with BAST is discouraged

    Problems that cannot be measured are not considered

    Transoceans condition-based maintenance program failed to detect

    several problems with the DWH including the low charge on the blue

    42Deposition of Mark Hay June 29-30 2011 12018-19

    Deposition of Mark Hay June 29-30 2011 1146-11522

    Deposition of Mark Hay June 29-30 2011 1216-9

    Deposition of Pharr Smith June 27-28 2011 157-1

    46

    Deposition of Pharr Smith June 27-28 2011 157-13 deposition of Mark Hay June

    29-30 2011 12018-1 12117-19

    191

  • 8/3/2019 Stevick, Glen Expert Report Only

    20/121

    Expert Report of Glen Stevick Ph.D P.E

    pod batteries and the incorrect wiring on yellow pod solenoid 103Y in

    the DWH BOP These types of equipment problems are undetectable by

    condition-based maintenance because theBOP

    d id no t have sensors thatindicated pod battery levels and physical inspection and testing was

    needed to evaluate the wiring on yellow pod solenoid 103Y But it cannot

    be debated that properly functioning pod batteries and solenoids are highly

    important to the safe and effective operation of the BOP and should

    therefore be regularly tested and evaluated under any maintenance

    program Transoceans condition-based maintenance is flawed because it

    fails to consider equipment that cannot be measured whereas such

    equipment is evaluated under the recertification process found in API and

    Camerons guidelines

    As discussed further below the undercharged blue pod batteries and

    incorrectly wired yellow pod solenoid 103Y may have prevented the

    AMF/Deadman from activating the BSR at the time of the incident and

    ultimately lead to the blowout But regardless of whether these battery and

    solenoid problems were direct cause of the blowout these problems do

    highlight flaws in Transoceans condition-based maintenance program

    The working condition of critical components was not evaluated by

    Transocean because it could not be measured

    Need for improved equipment is not considered

    Another flaw wi th Transoceans condition-based maintenance program is

    that it does not detect the need to improve existing equipment that is

    otherwise functioning properly Equipment measurements during

    condition-based maintenance are not going to identify design flaws

    improvements in industry knowledge and practices or increased system

    requirements due to operation in more difficult environment Under

    condition-based maintenance if equipment measurements are in line with

    expectations that equipment will not be considered further for potentially

    necessary upgrades For example had Transocean disassembled and

    inspected the DWH BOP for recertification and performed perfunctory

    engineering review or industry comparison at any time since 2006Transocean would have found that the DWH di d n ot have Camerons most

    up to date BOP control system Mark Ill which as described below

    provides numerous safety benefits over the Mark II system used for the

    DWH BOP recurring BOP recertification process that involves BOP

    disassembly and inspection as part of an engineering review is superior to

    20

  • 8/3/2019 Stevick, Glen Expert Report Only

    21/121

    Expert Report of Glen Stevick Ph.D P.E

    Transoceans condition-based process because recurring recertification

    provides an opportunity to identify changing requirements for equipment

    thatis

    otherwisein

    perfect working order

    Implementing BAST is discouraged

    Transoceans condition-based maintenance program discourages the

    implementation of BAST because it focuses on replacing equipment only in

    the event of measurable problems or failures as opposed to periodically

    evaluating whether improved equipment exists that should replace

    otherwise functional existing equipment Transoceans condition-based

    maintenance program further discourages the implementation of BAST by

    failing to provide the opportunity to implement BAST equipment and

    technology which typically must occur at the surface In contrast

    maintenance programs based on engineering review i.e recertification at

    the surface encourage the implementation of BAST by providing the

    opportunity to evaluate BAST for all equipment and the opportunity to

    implement BAST when available The many failures to implement BAST in

    the DWH BOP discussed below are unsurprising in light of the flaws of

    Transoceans condition-based maintenance program

    BP FAILED TO IMPLEMENT BAST IN THE BOP

    The CFR requires that BP as Operator of the Macondo well site must use

    the best available and safest technology BAST whenever practical on all

    exploration development and production operations.47 But BP failed to

    implement BAST in numerous areas of the BOP including the single BSR

    that was ultimately unable to perform its intended function of severing the

    drill pipe and sealing the well

    BP Failed to ImplementBAST for the BSR

    Implementing BAST in the single BSR was particularly critical due to the

    BSR being single point of failure and the device that was ultimately relied

    upon to seal the well in the case of an emergency BP knew the BSR was

    the most important piece of equipment for preventing blowout48 and yet

    BP still failed to implement BAST in the BSR and preferably add second

    30 C.F.R 250.107c

    48

    Deposition of Tony Hayward June and 820112897-14

    211

  • 8/3/2019 Stevick, Glen Expert Report Only

    22/121

    Expert Report of Glen Stevick Ph.D P.E

    BSR.49 Indeed the BSRs on the DWH BOP had not been upgraded since

    the rig was first ordered in ggg50

    BSRs with double shaped cutting blades and wider blades were

    available when the BOP was designed For example Camerons Double

    Shear DVS Rams featured shaped cutting blades on both the

    upper and lower blocks.51 The double design provided the benefits of

    helping to center the drill pipe during activation and also improving shearing

    efficiency by reducing the necessary shearing force.52 Accordingly using

    DVS ram block instead of the shearing blind ram block for the BSR in the

    DWH BOP would have allowed the BSR to shear greater range of pipe

    with the maximum 4000 psi available to the emergency system.53

    The improved shearing efficiency of double rams was further

    demonstrated by testing by West Engineering Services in 2004 for MMS

    that showed double blades lower the required shear force and

    therefore required hydraulic pressure by factor of approximately 20%

    when compared to BSRs with single blade and straight blade.54 For

    the DWH BOP Camerons DVS was also superior to the shearing blind

    ram because the DVS blade length was maximized to increase shearing

    capabilities.55 BP must have known about these advantages of the DVS

    over the shearing blind ram which Cameron touted inits

    product literature

    as shown below.56

    BP-HZN-BLY00294352-59

    50Deposition of Jack Erwin June 6-7 2011 6524 661

    51

    Cameron EB 852D Exhibit 7001

    52 Cameron EB 852D Exhibit 7001 deposition of Jack Erwin June 6-7 2011

    4616-19

    Deposition of David McWhorter July 7-8 2011 1108-12

    West Engineering Services Shear Ram Capabilities Study for U.S Minerals

    Management Service Requisition No 3-4025-1001 page 3-5 September 2004

    Cameron EB 852D Exhibit 7001

    56Cameron EB 852D 13 Exhibit 7001

    22

  • 8/3/2019 Stevick, Glen Expert Report Only

    23/121

    Expert Report of Glen Stevick Ph.D P.E

    5Rs -vs- DYS

    5hearin BLindRams

    Dcuble ShearRams

    Longer packer fatigue Life Require Less shear force

    CapabLe of shearing Larger

    diameters

    No toss of fatigue life

    Fig Comparison of Shearing Blind Ram versus DVS rams from

    Cameron Product Literature.57

    DVS rams and blades for an 18-3/4 inch wellbore 15000 psi TL BOP

    which could have been used in the DWH BOP were available from

    Cameron at least as early as 2002.58 Cameron sales representative also

    acknowledged that by 2009 or 2010 DVS was much more used ram

    than the SBR and the DVS ram was considered to be the best in practice

    at that time.59

    BP also did not implement Camerons tandem boosters which feature

    two-part piston that increases shearing force without additional wear on the

    packers.6 The tandem boosters were available at least as early as 199861

    and use of tandem boosters would have increased the shear force of the

    BSR on the DWH BOP If BP had used DVS rams with blades that

    covered the entire well bore the BSR most likely would have successfully

    sheared the off center drill pipe and sealed the well preventing the

    blowout

    Cameron EB 852D 13 Exhibit 7001

    58Cameron 2002 Replacement Parts Catalog pg 108 BP-HZN

    BLY0036641

    Deposition of Jack Erwin June 6-7 2011 6220-25

    60Cameron EB 852D 10 Exhibit 7001

    61Cameron EB 852D 10 Exhibit 7001

    23

  • 8/3/2019 Stevick, Glen Expert Report Only

    24/121

    Expert Report of Glen Stevick Ph.D P.E

    BP and Transocean Failed to Upgrade the BOP to Include

    Second BSR

    second BSR installed below the CSR would provide redundancy and

    significantly improve the reliability of both shearing pipe in the BOP and

    sealing the well If drill string is suspended and sheared first with the

    CSR i.e Super Shears during an emergency the drill pipe should fall

    clearing the BSR located below the casing ram This allows the lower BSR

    to close and seal without pipe interference in its bore Moreover

    Cameron sales representative testified that by 2009 or 2010 most of the

    rigs had double BSRs.62

    BP and Transocean Failed to Upgrade to Camerons MarkIll BOP Control Pod

    The DWH BOP used Cameron Mark II BOP control pods63 with double coil

    solenoids and batteries that were not rechargeable and the charge of which

    could not be monitored from the rig.64 As discussed above properly

    functioning control pod solenoids and batteries are needed to operate the

    AMF system and are critical components for safe and effective BOP BP

    and Transocean failed to upgrade to Mark Ill control pods that have been

    available since 2006.65

    62

    Deposition of Jack Erwin June 6-7 2011 622-14

    63

    Deposition of Jack Erwin June 6-7 2011 36715-17

    64

    Deposition of David McWhorter July 7-8 2011 2901-4

    65Deposition of David McWhorter July 7-8 2011 28917-20

    24

  • 8/3/2019 Stevick, Glen Expert Report Only

    25/121

    Expert Report of Glen Stevick Ph.D P.E

    Mark Ill control pods have rechargeable batteries66 and the charge on the

    batteries can be monitored from the rig.67 Mark Ill control pods also have

    improved singlecoil

    solenoids with higher pulling force68 which eliminatesthe potential incorrect wiring problem of the dual coil solenoids used in

    Mark II control pods and found in yellow pod solenoid 103Y of the DWH

    BOP Moreover Cameron corporate representative has testified that

    Cameron made its customers aware of the new Mark Ill system and its

    improvements over the Mark II system and that Transocean was aware of

    the Mark Ill system in 2006.69

    BP Failed to Implement BAST by Relying Solely on MUX

    Cables for EDS

    All methods of activating the DWH EDS relied on communications

    transmitted by MUX cables from the rig down to the BOP DWH rig crew

    members testified that they attempted to activate the EDS system after the

    explosion but were unsuccessful The EDS may have failed to activate due

    to physical damage to the MUX cables caused by the explosion An ACS

    could have been used as redundant means of communication between

    the DWH rig and the BOP Cameron had ACS available when the DWH

    was being configured.7 redundant ACS system could provide BOP

    communications and control in the case of an emergency even if MUX

    cables were damaged

    BP and Transocean Failed to Implement BAST by Using

    EDS-1 Instead of EDS-2

    Cameron could program various EDS sequences into the DWH BOP

    depending on what was requested by BP and Transocean.71 The DWH

    BOP implemented an EDS program called EDS-1 that specifies

    predetermined sequence of emergency disconnect events such that if the

    66

    Deposition of Jack Erwin June 6-7 2011 36718-22

    67

    Deposition of David McWhorter July 7-8 2011 28921-25

    68

    Deposition of Jack Erwin June 6-7 2011 37014 3716

    69

    Deposition of David McWhorter July 7-8 2011 3587 3606

    70

    Deposition of David McWhorter July 7-8 2011 1286-16

    71

    Deposition of David McWhorter July 7-8 2011 2248-12

    25

  • 8/3/2019 Stevick, Glen Expert Report Only

    26/121

    Expert Report of Glen Stevick Ph.D P.E

    EDSI- button is pushed the predetermined sequence of events will

    occur.72 EDS-1 for the DWH was programmed to close the BSR and then

    disconnect theLMRP.73

    AnotherEDS

    sequence was available onDWH

    called EDS-2 whereby the CSR closed before the BSR closed.74 Because

    EDS-2 first applies the CSR which has capabilities the BSR does not

    activation of EDS-2 is more likely to successfully shear the pipe and seal

    the well.75 Although the CSR is not designed to seal the wellbore

    activation of the CSR first would have centered the drill pipe for the BSR

    making it much more likely that the BSR would completely shear the drill

    pipe and seal the well BP and Transocean failed to implement BAST by

    having Cameron program the EDS-1 sequence as the primary disconnect

    sequence for the DWH BOP instead of EDS-2 which was more likely to

    successfully seal the well if activated

    VI THE UNDERCHARGED BLUE CONTROL POD BATTERIES AND

    INCORRECTLY WIRED YELLOW CONTROL POD SOLENOID

    103Y MAY HAVE BEEN CONTRIBUTING CAUSES OF THE BOPS

    INABILITY TO STOP THE BLOWOUT

    As discussed above when the AMF/Deadman is activated it causes the

    BSR to fire But the AMF/Deadman can only be activated if at least one of

    the control pods is functioning properly which requires charged batteries

    and working solenoids Based on my review of the post-incident testing of

    the BOP and related deposition testimony76 it appears that neither was

    true

    72

    Deposition of Jack Erwin June 6-7 2011 2714 -2810

    Deposition of Jack Erwin June 6-7 2011 301-9

    Deposition of David McWhorter July 7-8 2011 22513-24

    Deposition of David McWhorter July 7-8 2011 22610-25

    76Deposition of Robert Turlak July 28-29 2011 22817 2295 deposition of Edward

    Gaude September 19 2011 13011-22 testifying that if two coils in single solenoid

    are wired in opposite directions the electromagnetic fields would oppose each other

    and cancel out and the solenoid valve would not operate 2103-8 testifying that if

    solenoid is not wired correctly it will not function correctly

    26

  • 8/3/2019 Stevick, Glen Expert Report Only

    27/121

    Expert Report of Glen Stevick Ph.D P.E

    Undercharged Blue Control Pod Batteries

    During post incident forensic testing by DNV of the blue control pod

    batteries the 27 volt battery registered low charge as shown below.77

    Blue P01 VoLts Yellow Pod Volts

    Batten- Test Test Test Test

    SEMA9V 8.9 8.9 3.7 8.7

    SEMB9V 8.7 8.7 8.4 8.4

    Solenoid TransclucerC7V 1.1 1.0 2S.2 28.2

    Fig BOP Control Pod Battery Measurements from the DNV

    report.78

    Due these to low charge in the 27 volt battery it is very unlikely that the

    blue control pod would have had sufficient power to activate the

    AMF/Deadman at the time of the incident

    Incorrectly Wired Yellow Control Pod Solenoid 103Y

    Post incident forensic testing by DNV also showed that one of the two coils

    from yellow control pod solenoid 03Y had been incorrectly wired and 03Y

    failed to activate either yellow control pod SEM during bench testing.79 As

    result of 103Y being incorrectly wired the two coils had opposite

    polarities and the electromagnetic fields generated by the two coils would

    largely cancel each other out and could prevent 03Y actuating the BSR in

    response to the AMF/Deadman circuit in the yellow pod

    DNV Report Vol page 42

    78DNV Report Vol Table page 42

    DNV Report Vol page 44 The results of solenoid 103Y testing are inconclusive

    because 03Y worked properly when connected to and operated by SEM and SEM

    as would have occurred in the field Laboratory Notes from DNV testing of 103Y

    016862 Exhibit 3130

    27

  • 8/3/2019 Stevick, Glen Expert Report Only

    28/121

    Expert Report of Glen Stevick Ph.D P.E

    The AMF/Deadman Likely Failed to Actuate the BSR

    because of Low Blue Pod Battery and the Incorrectly Wired

    Yellow Pod Solenoid

    Even though the BOP had redundant mechanisms for actuating the BSR in

    response to the AMF/Deadman conditions it appears likely that both

    mechanisms failed The low battery charge measurements for the blue pod

    27 volt battery pack suggest that it did not have enough charge to power

    the two blue pod SEMs at the time of the incident which would prevent the

    blue pod from activating the BSR The incorrect wiring on solenoid 103Y

    suggests that because each coil received the same voltage80 and the two

    coils were activated simultaneously as is the normal operation during AMF

    activation81 the magnetic fields from the two coils would cancel each other

    out and would prevent the yellow pod from activating the BSR.82 It is

    therefore likely that the AMF/Deadman failed to activate the BSR as

    result of the low charge on the 27 volt blue pod battery and the incorrectly

    wired yellow pod solenoid O3Y

    The BSR Likely Would Have Completely Sheared the Drill

    Pipe and Sealed the Well if the BSR had been Activated

    when the Drill Pipe was Centered

    The undercharged blue pod batteries and incorrectly wired solenoid 03Y

    may have prevented the AMF/Deadman from properly functioning at the

    time of the incident and activating the BSR.84 If the drill pipe was centered

    at the time of the incident and did not become off-center until later then

    activating the BSR probably would have completely sheared the drill pipe

    and sealed the well preventing the blowout

    80

    Deposition of Edward Gaude September 19 2011 1387-12

    81

    Deposition of Edward Gaude September 19 2011 131 9-16

    82Deposition of Edward Gaude September 19 2011 131 23 1323

    83As discussed above there is evidence that suggests the AMF/Deadman function did

    not activate the BSR but overall the evidence is inconclusive on this point There is

    also evidence that suggests the AMF/Deadman may have act ivat ed t he BSR

    84It is possible for example that the BSR was activated at later time by the ROy

    28

  • 8/3/2019 Stevick, Glen Expert Report Only

    29/121

    Expert Report of Glen Stevick Ph.D P.E

    As discussed above undercharged blue pod batteries would have been

    avoided if BP and Transocean had implemented Camerons Mark Ill BOP

    control system that uses rechargeable control pod batteries and allowsremote monitoring of battery charge from the rig maintenance program

    based on recurring disassembly inspection and recertification as opposed

    to Transoceans condition-based maintenance probably would have also

    detected the undercharged blue pod batteries and would have provided an

    opportunity to replace them will fully charge and functional batteries

    Similarly implementation of Camerons Mark Ill BOP control system with

    single coil solenoids would have prevented the problem of incorrectly wired

    solenoids as found in 03Y recurring recertification based maintenance

    program probably would have detected that 103Y was incorrectly wired

    and would provided an opportunity to replace 103Y with properly

    functioning solenoid

    reserve the right to modify this report and to supplement my opinions if

    additional data becomes available and in response to reports served by

    other parties

    Dated January 17 2012

    Dr Glen St vick P.E

    29

  • 8/3/2019 Stevick, Glen Expert Report Only

    30/121

    APPENDIX

  • 8/3/2019 Stevick, Glen Expert Report Only

    31/121

    MDL

    NO

    2179

    In

    re

    OilSpillby

    the

    OilRig

    DeepwaterHorizoninthe

    GulfofMexico

    onApril20

    2010

    DR

    GLEN

    STEVICK

    SOURCE

    RELIANCE

    APPENDIX

    BP-HZN-21

    79MDL00056656-56936

    BP-HZN-BLYOO1

    24026

    BP-HZN-BLYOO1

    24588-124698

    ProDerties

    ofPart

    01366513

    of65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    32/121

    BP-HZN-BLYOO1

    78528-1

    78530

    Properties

    ofPart01366516

    Collar

    Float

    BP-HZN-BLY00294035-294036

    5/31/2010

    Wong

    email

    to

    Abbassian

    re

    MBI

    HearingTranscripts

    BP-HZN-BLY00294350-294351

    6/8/2010

    Diasemailto

    Abbassian

    re

    Assignment/Paul

    DiasBOPsystems

    BP-HZN-BLY00294352-294359

    5/27/2010

    Questionsfrom

    Fereidoun

    Abbasian

    May

    27th

    BP-HZN-BLY00346210-346212

    7/1/2010

    DeepwaterH

    orizon

    Incident

    Investigation

    --

    CF1-NTF1O

    FloatCollarFailure

    BP-HZN-BLYOO35O1

    58-3

    50159

    5/13/2010

    DeepwaterH

    orizon

    Incident

    Investigation

    --

    Preliminary

    F

    actual

    Critical

    FactorOutcome

    Form

    BP-HZN-BLY00366307-366448

    00/00/2002

    Cameron

    2002

    Replacement

    Parts

    Catalog

    BP-HZN-CECO1

    1425

    7M45AP

    Float

    CollarDrawing

    BP-HZN-CEC030029-30030

    10/11/2004

    Letter

    Agreem

    ent

    forConversion

    ofVBR

    to

    TestRam

    b

    etween

    Transocean

    and

    BP

    BP-HZN-CEC030137

    Spreadsheet

    re

    Casing

    Thread

    Damage

    BP-HZN-MBI00061

    305-6

    1

    403

    4/14/2009

    IntermoorMODU

    Mooring

    AnalysisReportforBP

    BP-HZN-MB100128436-128438

    4/16/2010

    Paikattu

    ema

    iltoMorelre

    Actual

    vs

    model

    9-7

    /8

    in

    liner

    run

    BP-HZN-MBIOO1

    28489-128490

    4/17/2010

    Gagliano

    em

    ailto

    Moreletalre

    Revised

    OptiCem

    Reportwith

    additional

    Centralizers

    BP-HZN-MB10012961

    6-129619

    4/28/2010

    Bob

    KaluzaInterview

    Notes

    BP-HZN-MBIOO1

    34806-1

    34834

    DeepwaterH

    orizon

    --

    HAZOP

    ofWellControl

    Systems

    BP-HZN-MBIOO1

    37364-1

    37377

    4/20/2010

    Halliburton

    9

    .875

    Foamed

    Production

    Casing

    PostJ

    ob

    Report

    BP-HZN-MB100294826-294833

    1/1

    4/2010

    BP

    Application

    for

    Revised

    New

    Well

    CAM_

    CIV_

    001

    9664-1

    9819

    00/00/2006

    Cameron

    2006

    Drilling

    Replacement

    Parts

    Catalog

    CAM_

    CIV_

    0370157-370165

    6/28/2006

    Engineering

    Bulletin

    Errata

    Sheet

    re

    ShearingCapabilities

    ofCameron

    Shear

    Rams

    CAM_

    DIV_

    03701

    00-3

    701

    16

    7/9/2010

    Cameron

    En

    gineering

    Bulletin

    re

    Shearing

    Capabilities

    of

    Cameron

    Shear

    Rams

    DECO77-006509-6528

    1/21/2008

    Cameron

    En

    gineering

    Bulletin

    re

    Shearing

    Capabilities

    of

    Cameron

    Shear

    Rams

    1M5054-0

    16139-1

    6143

    1/27/2004

    Engineering

    Bulletin

    Errata

    Sheet

    re

    ShearingCapabilities

    ofCameron

    Shear

    Rams

    TRN-INV-00580489-580497

    3/23/2007

    Engineering

    Bulletin

    Errata

    Sheet

    re

    ShearingCapabilities

    ofCameron

    Shear

    Rams

    TRN-INV-03489834-3489863

    NASA/DNV

    Summary

    ofTestPreparation

    Sheet

    BOP-Ol

    TestSolenoid

    at

    Deep

    Sea

    Temperture

    and

    Pressure

    TRN-MDL-00286767

    3/31/2009

    Transocean

    WellControl

    Hand

    book

    TRN-MDL00607699-607707

    8/6/2007

    Cameron

    En

    gineering

    Bulletin

    Revision

    Ex

    257

    02/00/2011

    ChiefCouns

    elsReportto

    National

    Commissionon

    the

    BP

    Deepwater

    Horizon

    OilSpill

    01/00/2011

    FinalReport

    tothe

    Presidentre

    Deepwater

    The

    GulfOil

    Disaster

    and

    the

    Futureof

    Offshore

    Drilling

    11/16/2010

    National

    Academy

    ofSciences

    Interim

    Reporton

    Causes

    ofBlowout

    Republicofthe

    Marshall

    Islands

    Office

    ofthe

    MaritimeAdministratorDeepwater

    Horizon

    MarineCasua

    ltylnvestigaton

    Report

    of65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    33/121

    9/14/2011

    The

    Bureau

    ofOcean

    Energy

    Management

    Regulationand

    Enforcement--

    Report

    Regarding

    th

    e

    Causes

    ofthe

    April20

    2010

    Macondo

    WellblowoutJITReport

    4/22/2011

    United

    States

    Coast

    Guard

    ReportofInvestigation

    intothe

    Circumstances

    Surrounding

    the

    Explosion

    Fire

    Sinking

    and

    Loss

    ofEleven

    Crew

    Mem

    bers

    Aboard

    the

    MobilOffshore

    DrillUnitDeepwater

    Horizon

    in

    the

    GulfofMexico

    April2

    0-222010

    3/20/2011

    DNV

    Report

    EP030842

    forBOEMRE

    Volumes

    and

    II

    6/22/2011

    Transocean

    Investigation

    ReportVolumes

    and

    II

    9/8/2010

    BP

    Deepwate

    r

    HorizonAccidentInvestigation

    ReportBly

    Report

    6/8/2011

    Transoceans

    Response

    to

    USCG

    DraftReport

    6/6/20

    Erwin

    Jack

    CarterDeposition

    Transcript

    6/7/20

    Erwin

    Jack

    CarterDeposition

    Transcript

    6/29/2011

    Hay

    MarkDavid

    Deposition

    Transcript

    7/6/2011

    Kenney

    Gary

    Deposition

    Transcript

    6/20/2011

    LeNormand

    William

    Deposition

    Transcript

    6/21/2011

    LeNormand

    William

    Deposition

    Transcript

    7/7/2011

    McWtiorter

    David

    Deposition

    Transcript

    7/8/2011

    McWtiorter

    David

    Deposition

    Transcript

    3/14/2011

    PleasantCh

    ristopher

    Deposition

    Transcript

    3/15/2011

    PleasantCh

    ristopher

    Deposition

    Transcript

    7/5/2011

    Thompson

    NeilDeposition

    Transcript

    7/20/2011

    McWtiorter

    James

    Owen

    Deposition

    Transcript

    7/21/2011

    McWtiorter

    James

    Owen

    Deposition

    Transcript

    7/18/2011

    WhitbyMelvy

    Deposition

    Transcript

    7/19/2011

    WhitbyMelvy

    Deposition

    Transcript

    6/30/2011

    Hay

    MarkDavid

    Deposition

    Transcript

    Ex

    7043

    Ex

    7044

    Ex

    7045

    Ex

    7046

    Ex

    7000

    Ex

    7001

    Ex

    7002

    Ex

    7003

    Ex

    7004

    Ex

    7005

    Ex

    7006

    of65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    34/121

    Ex

    7007

    Ex

    7008

    Ex

    7009

    Ex

    7010

    Ex

    7011

    Ex

    7012

    Ex

    7013

    Ex

    7014

    Ex

    7015

    Ex

    7016

    Ex

    7017

    Ex

    7018

    Ex

    7019

    Ex

    7020

    Ex

    7021

    Ex

    7022

    Ex

    7023

    Ex

    7024

    Ex

    7025

    Ex

    7026

    Ex

    7027

    Ex

    7028

    Ex

    7029

    Ex

    7030

    Ex

    7031

    Ex

    7032

    Ex

    7033

    Ex

    7034

    Ex

    7035

    Ex

    7036

    Ex

    7037

    Ex

    7038

    Ex

    7039

    Ex

    7040

    Ex

    7041

    Ex

    7042

    Ex

    3626

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    35/121

    Ex

    3627

    Ex

    3628

    Ex

    3601

    Ex

    3602

    Ex

    3603

    Ex

    3604

    Ex

    3605

    Ex

    3606

    Ex

    3607

    Ex

    3608

    Ex

    3609

    Ex

    3610

    Ex

    3611

    Ex

    3612

    Ex

    3613

    Ex

    3614

    Ex

    3615

    Ex

    3616

    Ex

    3617

    Ex

    3618

    Ex

    3619

    Ex

    3620

    Ex

    3621

    Ex

    3622

    Ex

    3623

    Ex

    3624

    Ex

    3625

    Ex

    592

    Ex

    593

    Ex

    594

    Ex

    580

    Ex

    581

    Ex

    582

    Ex

    583

    Ex

    584

    Ex

    585

    Ex

    586

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    36/121

    Ex

    587

    Ex

    588

    Ex

    589

    Ex

    590

    Ex

    591

    HBRA

    Flow

    and

    Force

    Calculation-Odmund

    HBRA

    Thermal

    Expansion

    Calculation

    BOP

    Data

    F

    iles

    04182011

    through

    06232011

    DNV

    daily

    notebook

    entries

    testing

    spreadsheets

    laserscanning

    data

    BOP

    Image

    files

    04182011

    throough

    06212011

    DNV

    daily

    pictures

    taken

    ofinvestigation

    BOP

    Video

    file

    listing

    04182011

    through

    06222011

    DNV

    inventoryof

    videofiles

    taken

    of

    investigation

    8/27/2010

    DNV

    Report

    No

    201

    0-1

    220

    G0M

    vs

    Norway

    from

    OLF/NOFO

    Summary

    ofdifferences

    between

    offshore

    drilling

    regulations

    in

    Norway

    and

    U.S

    GulfofMexico

    9/1/2004

    API

    Recomme

    nded

    Practice

    63

    Third

    Edition

    March

    199

    7

    Reaffirmed

    September

    2004

    Recommended

    Practices

    for

    Blowout

    Prevention

    Equipment

    SystemsforDrilling

    Wells

    3/1/2011

    DHSG

    Final

    Report

    9/1/2010

    BP

    Reportre

    Deepwater

    Horizon

    Containment

    and

    Respo

    nse

    and

    Lessons

    Learned

    Ex

    3342

    Ex

    3343

    Ex

    3344

    Ex

    3286

    Ex

    3287

    Ex

    3288

    Ex

    3289

    Ex

    3290

    Ex

    3291

    Ex

    3292

    Ex

    3293

    Ex

    3294

    Ex

    3295

    Ex

    3296

    Ex

    3297

    Ex

    3298

    Ex

    3299

    of65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    37/121

    Ex

    3300

    Ex

    3301

    Ex

    3302

    Ex

    3303

    Ex

    3304

    Ex

    3305

    Ex

    3306

    Ex

    3307

    Ex

    3308

    Ex

    3309

    Ex

    3310

    Ex

    3311

    Ex

    3312

    Ex

    3313

    Ex

    3314

    Ex

    3315

    Ex

    3316

    Ex

    3317

    Ex

    3318

    Ex

    3319

    Ex

    3320

    Ex

    3321

    Ex

    3322

    Ex

    3323

    Ex

    3324

    Ex

    3325

    Ex

    3326

    Ex

    3327

    Ex

    3328

    Ex

    3329

    Ex

    3330

    Ex

    3331

    Ex

    3332

    Ex

    3333

    Ex

    3334

    Ex

    3335

    Ex

    3336

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    38/121

    Ex

    3337

    Ex

    3338

    Ex

    3339

    Ex

    3340

    Ex

    3341

    Ex

    3147

    Ex

    3148

    Ex

    3129

    Ex

    3130

    Ex

    131

    Ex

    132

    Ex

    133

    Ex

    134

    Ex

    135

    Ex

    136

    Ex

    137

    Ex

    138

    Ex

    139

    Ex

    3140

    Ex

    3141

    Ex

    3142

    Ex

    3143

    Ex

    3144

    Ex

    3145

    Ex

    3146

    Ex

    3184

    Ex

    3185

    Ex

    186

    Ex

    187

    Ex

    166

    Ex

    167

    Ex

    168

    Ex

    169

    Ex

    170

    Ex

    171

    Ex

    172

    Ex

    3173

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    39/121

    Ex

    3174

    Ex

    3175

    Ex

    3176

    Ex

    3177

    Ex

    3178

    Ex

    3179

    Ex

    3180

    Ex

    3181

    Ex

    3182

    Ex

    3183

    Ex

    3797

    Ex

    3798

    Ex

    3799

    Ex

    3779

    Ex

    3780

    Ex

    3781

    Ex

    3782

    Ex

    3783

    Ex

    3784

    Ex

    3785

    Ex

    3786

    Ex

    3787

    Ex

    3788

    Ex

    3789

    Ex

    3790

    Ex

    3791

    Ex

    3792

    Ex

    3793

    Ex

    3794

    Ex

    3795

    Ex

    3796

    Ex

    3986

    Ex

    3987

    Ex

    3979

    Ex

    3980

    Ex

    3981

    Ex

    3982

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    40/121

  • 8/3/2019 Stevick, Glen Expert Report Only

    41/121

    Ex1179

    Ex1180

    Ex

    181

    Ex

    182

    Ex

    183

    Ex

    184

    Ex

    185

    Ex

    186

    Ex

    187

    Ex

    188

    Ex

    189

    Ex

    190

    Ex

    192

    Ex

    193

    Ex

    194

    Ex1300

    Ex3121

    Ex3122

    Ex3123

    Ex3124

    Ex3125

    Ex3126

    Ex3127

    Ex3128

    8/26/2011

    Bea-G

    ale

    Ex

    pertReportPis

    8/26/20

    George

    Birch

    ExpertReportPis

    8/26/2011

    Andrew

    Hurs

    t

    ExpertReportP15

    8/26/2011

    Gregg

    Perkin

    ExpertReportP15

    8/26/2011

    David

    Pritchard

    ExpertReportP15

    8/26/2011

    GeoffWebste

    r

    ExpertReportPis

    BP

    Macondo

    Bypass

    Plot

    Range

    4-1

    9-1

    250

    to

    4-2

    0

    2200

    SecSurface

    Data

    Review.x

    ls

    12/00/2002

    West

    Engine

    ering

    Services

    Inc

    Mini

    Shear

    Study

    for

    U.S

    Minerals

    Management

    Service

    Requisition

    No

    2-1

    011-1

    003

    8/31/2011

    Benge

    Glen

    ExpertReportUSA

    8/31/2011

    Davis

    DrRory

    ExpertReportUSA

    8/31/2011

    HeenanRic

    hard

    ExpertReportUSA

    11

    of65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    42/121

    8/31/2011

    Hu

    ffman

    Dr

    Alan

    Expert

    ReportUSA

    6/29/2011

    Cow

    ie

    Jame

    s

    Deposition

    Transcript

    6/30/2011

    Cow

    ie

    Jame

    s

    Deposition

    Transcript

    7/21/2011

    Kasal

    KalD

    eposition

    Transcript

    4/6/2011

    Sims

    David

    Deposition

    Transcript

    4/7/2011

    Sims

    David

    Deposition

    Transcript

    Ex

    1488

    Ex

    2223

    Casing

    Run

    Torque

    Data

    9/19/2011

    Gaude

    EdD

    eposition

    Transcript

    Ex

    738

    Ex

    1260

    3/30/20

    Vargo

    Richa

    rd

    Deposition

    Transcript

    3/31/2011

    Vargo

    Richa

    rd

    Deposition

    Transcript

    4/21/2011

    Wa

    lz

    Gregory

    Deposition

    Transcript

    4/22/20

    Wa

    lz

    Gregory

    Deposition

    Transcript

    5/11/2011

    Gagliano

    Jesse

    Deposition

    Transcript

    9/27/2011

    Childs

    Greg

    Expert

    Report

    Transocean

    Ex

    5768

    Ex

    5769

    Ex

    5770

    Ex

    5771

    Ex

    4000

    Ex

    4001

    Ex

    4002

    Ex

    4003

    Ex

    4004

    Ex

    4005

    Ex

    4006

    Ex

    4007

    Ex

    4008

    Ex

    4009

    Ex

    4010

    Ex

    4011

    Ex

    4012

    Ex

    4013

    Ex

    4014

    12

    of65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    43/121

    Ex

    4015

    Ex

    4016

    Ex

    4017

    Ex

    4018

    Ex

    4019

    Ex

    4020

    Ex

    4021

    Ex

    4022

    Ex

    4023

    Ex

    4024

    Ex

    4025

    Ex

    4026

    Ex

    4027

    Ex

    4028

    Ex

    4029

    Ex

    4030

    Ex

    4031

    Ex

    4032

    Ex

    4033

    Ex

    4034

    Ex

    4035

    Ex

    4036

    Ex

    4037

    Ex

    4038

    Ex

    4039

    Ex

    4040

    Ex

    4041

    Ex

    4042

    Ex

    4043

    Ex

    4044

    Ex

    4045

    Ex

    4046

    Ex

    4047

    Ex

    4048

    Ex

    4049

    Ex

    4050

    Ex

    4051

    13

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    44/121

    Ex

    4052

    Ex

    4053

    Ex

    4054

    Ex

    4055

    Ex

    4056

    Ex

    4057

    Ex

    4058

    Ex

    4059

    Ex

    4060

    Ex

    4061

    Ex

    4062

    Ex

    4063

    Ex

    4064

    Ex

    4065

    Ex

    4066

    Ex

    4067

    Ex

    4068

    Ex

    4069

    Ex

    4070

    Ex

    4071

    Ex

    4072

    Ex

    4073

    Ex

    4074

    Ex

    4075

    Ex

    4076

    Ex

    4077

    Ex

    4078

    Ex

    4079

    Ex

    4080

    Ex

    4081

    Ex

    4082

    Ex

    4083

    Ex

    4084

    Ex

    4085

    Ex

    4086

    Ex

    4087

    Ex

    4088

    14

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    45/121

    Ex

    4089

    Ex

    4090

    Ex

    4091

    Ex

    4092

    Ex

    4093

    Ex

    4094

    Ex

    4095

    Ex

    4096

    Ex

    4097

    Ex

    4098

    Ex

    4099

    Ex

    400

    Ex

    4101

    Ex

    4102

    Ex

    4103

    Ex

    4104

    Ex

    4105

    Ex

    4106

    Ex

    4107

    Ex

    4108

    Ex

    4109

    Ex

    4110

    Ex

    4111

    Ex

    4112

    Ex

    4113

    Ex

    4114

    Ex

    4115

    Ex

    4116

    Ex

    4117

    Ex

    4118

    Ex

    4119

    Ex

    4120

    Ex

    4121

    Ex

    4122

    Ex

    4123

    Ex

    4124

    Ex

    4125

    15

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    46/121

    Ex

    4126

    Ex

    4127

    Ex

    128

    Ex

    129

    Ex

    130

    Ex

    131

    Ex

    132

    Ex

    133

    Ex

    134

    Ex

    135

    Ex

    136

    Ex

    137

    Ex

    138

    Ex

    139

    Ex

    140

    Ex

    141

    Ex

    142

    Ex

    143

    Ex

    144

    Ex

    145

    Ex

    146

    Ex

    147

    Ex

    148

    Ex

    149

    Ex

    150

    Ex

    151

    Ex

    152

    Ex

    153

    Ex

    154

    Ex

    155

    Ex

    156

    Ex

    157

    Ex

    158

    Ex

    159

    Ex

    160

    Ex

    161

    Ex

    4162

    16

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    47/121

    Ex

    4163

    Ex

    4164

    Ex

    165

    Ex

    166

    Ex

    167

    Ex

    168

    Ex

    169

    Ex

    170

    Ex

    171

    Ex

    172

    Ex

    173

    Ex

    174

    Ex

    175

    Ex

    176

    Ex

    177

    Ex

    178

    Ex

    179

    Ex

    180

    Ex

    181

    Ex

    182

    Ex

    183

    Ex

    184

    Ex

    185

    Ex

    186

    Ex

    187

    Ex

    188

    Ex

    189

    Ex

    190

    Ex

    191

    Ex

    192

    Ex

    193

    Ex

    194

    Ex

    195

    Ex

    196

    Ex

    197

    Ex

    198

    Ex

    4199

    17

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    48/121

    Ex

    4200

    Ex

    4201

    Ex

    4202

    Ex

    4203

    Ex

    4204

    Ex

    4205

    Ex

    4206

    Ex

    4207

    Ex

    4208

    Ex

    4209

    Ex

    4210

    Ex

    4211

    Ex

    4212

    Ex

    4213

    Ex

    4214

    Ex

    4215

    Ex

    4216

    Ex

    4217

    Ex

    4218

    Ex

    4219

    Ex

    4220

    Ex

    4221

    Ex

    4222

    Ex

    4223

    Ex

    4224

    Ex

    4225

    Ex

    4226

    Ex

    4227

    Ex

    4228

    Ex

    4229

    Ex

    4230

    Ex

    4231

    Ex

    4232

    Ex

    4233

    Ex

    4234

    Ex

    4235

    Ex

    4236

    18

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    49/121

    Ex

    4237

    Ex

    4238

    Ex

    4239

    Ex

    4240

    Ex

    4241

    Ex

    4242

    Ex

    4243

    Ex

    4244

    Ex

    4245

    Ex

    4246

    Ex

    4247

    Ex

    4248

    Ex

    4249

    Ex

    4250

    Ex

    4251

    Ex

    4252

    Ex

    4253

    Ex

    4254

    Ex

    4255

    Ex

    4256

    Ex

    4257

    Ex

    4258

    Ex

    4259

    Ex

    4260

    Ex

    4261

    Ex

    4262

    Ex

    4263

    Ex

    4264

    Ex

    4265

    Ex

    4266

    Ex

    4267

    Ex

    4268

    Ex

    4269

    Ex

    4270

    Ex

    4271

    Ex

    4272

    Ex

    4273

    19

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    50/121

    Ex

    4274

    Ex

    4275

    Ex

    4276

    Ex

    4277

    Ex

    4278

    Ex

    4279

    Ex

    4280

    Ex

    4281

    Ex

    4282

    Ex

    4283

    Ex

    4310

    Ex

    4311

    Ex

    4312

    Ex

    4313

    Ex

    4314

    Ex

    4315

    Ex

    4316

    Ex

    4317

    Ex

    4318

    Ex

    4319

    Ex

    4320

    Ex

    4321

    Ex

    4322

    Ex

    4323

    Ex

    4324

    Ex

    4325

    Ex

    4326

    Ex

    4327

    Ex

    4328

    Ex

    4329

    Ex

    4330

    Ex

    4331

    Ex

    4332

    Ex

    4333

    Ex

    4334

    Ex

    4335

    Ex

    4336

    20

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    51/121

    Ex

    4337

    Ex

    4338

    Ex

    4339

    Ex

    4340

    Ex

    4341

    Ex

    4342

    Ex

    4343

    Ex

    4344

    Ex

    4345

    Ex

    4346

    Ex

    4347

    Ex

    4348

    Ex

    4349

    Ex

    4350

    Ex

    4351

    Ex

    4352

    Ex

    4353

    Ex

    4354

    Ex

    4355

    Ex

    4356

    Ex

    4357

    Ex

    4358

    Ex

    4359

    Ex

    4360

    Ex

    4361

    Ex

    4362

    Ex

    4363

    Ex

    4364

    Ex

    4365

    Ex

    4366

    Ex

    4367

    Ex

    4368

    Ex

    4369

    Ex

    4370

    Ex

    4371

    Ex

    4372

    Ex

    4373

    21

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    52/121

    Ex

    4374

    Ex

    4380

    Ex

    4381

    Ex

    4382

    Ex

    4383

    Ex

    4384

    Ex

    4385

    Ex

    4386

    Ex

    4387

    Ex

    4388

    Ex

    4389

    Ex

    4390

    Ex

    4391

    Ex

    4392

    Ex

    4393

    Ex

    4394

    Ex

    4395

    Ex

    4400

    Ex

    4401

    Ex

    4402

    Ex

    4403

    Ex

    4404

    Ex

    4405

    Ex

    4406

    Ex

    4407

    Ex

    4408

    Ex

    4409

    Ex

    4410

    Ex

    4411

    Ex

    4412

    Ex

    4413

    Ex

    4414

    Ex

    4415

    Ex

    4416

    Ex

    4417

    Ex

    4418

    Ex

    4419

    22

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    53/121

    Ex

    4420

    Ex

    4421

    Ex

    4422

    Ex

    4423

    Ex

    4424

    Ex

    4425

    Ex

    4426

    Ex

    4427

    Ex

    4428

    Ex

    4429

    Ex

    4430

    Ex

    4431

    Ex

    4432

    Ex

    4433

    Ex

    4434

    Ex

    4435

    Ex

    4436

    Ex

    4437

    Ex

    4438

    Ex

    4439

    Ex

    4440

    Ex

    4441

    Ex

    4442

    Ex

    4443

    Ex

    4444

    Ex

    4445

    Ex

    4446

    Ex

    4447

    Ex

    4448

    Ex

    4449

    Ex

    4450

    Ex

    4451

    Ex

    4452

    Ex

    4453

    Ex

    4454

    Ex

    4455

    Ex

    4456

    23

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    54/121

    Ex

    4457

    Ex

    4458

    Ex

    4459

    Ex

    4460

    Ex

    4461

    Ex

    4462

    Ex

    4463

    Ex

    4464

    Ex

    4465

    Ex

    4466

    Ex

    4467

    Ex

    4468

    Ex

    4469

    Ex

    4470

    Ex

    4471

    Ex

    4472

    Ex

    4476

    Ex

    4477

    Ex

    4478

    Ex

    4479

    Ex

    4480

    Ex

    4481

    Ex

    4482

    Ex

    4483

    Ex

    4484

    Ex

    4485

    Ex

    4486

    Ex

    4487

    Ex

    4488

    Ex

    4489

    Ex

    4490

    Ex

    4491

    Ex

    4492

    Ex

    4493

    Ex

    4494

    Ex

    4500

    Ex

    4501

    24

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    55/121

    Ex

    4502

    Ex

    4503

    Ex

    4504

    Ex

    4505

    Ex

    4506

    Ex

    4507

    Ex

    4508

    Ex

    4509

    Ex

    4510

    Ex

    4511

    Ex

    4512

    Ex

    4513

    Ex

    4514

    Ex

    4515

    Ex

    4516

    Ex

    4517

    Ex

    4518

    Ex

    4519

    Ex

    4520

    Ex

    4521

    Ex

    4522

    Ex

    4523

    Ex

    4524

    Ex

    4525

    Ex

    4526

    Ex

    4527

    Ex

    4528

    Ex

    4529

    Ex

    4530

    Ex

    4531

    Ex

    4532

    Ex

    4533

    Ex

    4534

    Ex

    4535

    Ex

    4536

    Ex

    4537

    Ex

    4538

    25

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    56/121

    Ex

    4539

    Ex

    4540

    Ex

    4541

    Ex

    4542

    Ex

    4543

    Ex

    4544

    Ex

    4545

    Ex

    4546

    Ex

    4547

    Ex

    4548

    Ex

    4549

    Ex

    4550

    Ex

    4551

    Ex

    4552

    Ex

    4553

    Ex

    4554

    Ex

    4555

    Ex

    4556

    Ex

    4557

    Ex

    4558

    Ex

    4559

    Ex

    4560

    Ex

    4561

    Ex

    4562

    Ex

    4563

    Ex

    4564

    Ex

    4565

    Ex

    4566

    Ex

    4567

    Ex

    4568

    Ex

    4569

    Ex

    4570

    Ex

    4571

    Ex

    4572

    Ex

    4573

    Ex

    4574

    Ex

    4575

    26

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    57/121

    Ex

    4576

    Ex

    4577

    Ex

    4578

    Ex

    4579

    Ex

    4580

    Ex

    4581

    Ex

    4582

    Ex

    4583

    Ex

    4584

    Ex

    4585

    Ex

    4586

    Ex

    4587

    Ex

    4588

    Ex

    4589

    Ex

    4590

    Ex

    4591

    Ex

    4592

    Ex

    4593

    Ex

    4594

    Ex

    4595

    Ex

    4596

    Ex

    4597

    Ex

    4598

    Ex

    4599

    Ex

    4600

    Ex

    4601

    Ex

    4602

    Ex

    4603

    Ex

    4604

    Ex

    4605

    Ex

    4606

    Ex

    4607

    Ex

    4608

    Ex

    4609

    Ex

    4610

    Ex

    4611

    Ex

    4612

    27

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    58/121

    Ex

    4613

    Ex

    4614

    Ex

    4615

    Ex

    4616

    Ex

    4617

    Ex

    4618

    Ex

    4619

    Ex

    4620

    Ex

    4621

    Ex

    4622

    Ex

    4623

    Ex

    4624

    Ex

    4625

    Ex

    4626

    Ex

    4627

    Ex

    4628

    Ex

    4629

    Ex

    4630

    Ex

    4631

    Ex

    4632

    Ex

    4633

    Ex

    4634

    Ex

    4635

    Ex

    4636

    Ex

    4637

    Ex

    4638

    Ex

    4639

    Ex

    4640

    Ex

    4641

    Ex

    4642

    Ex

    4643

    Ex

    4644

    Ex

    4645

    Ex

    4646

    Ex

    4647

    Ex

    4648

    Ex

    4649

    28

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    59/121

    Ex

    4650

    Ex

    4651

    Ex

    4652

    Ex

    4653

    Ex

    4654

    Ex

    4655

    Ex

    4656

    Ex

    4657

    Ex

    4658

    Ex

    4659

    Ex

    4660

    Ex

    4661

    Ex

    4662

    Ex

    4663

    Ex

    4664

    Ex

    4665

    Ex

    4666

    Ex

    4667

    Ex

    4668

    Ex

    4669

    Ex

    4670

    Ex

    4671

    Ex

    4672

    Ex

    4673

    Ex

    4674

    Ex

    4675

    Ex

    4676

    Ex

    4677

    Ex

    4678

    Ex

    4679

    Ex

    4680

    Ex

    4681

    Ex

    4682

    Ex

    4683

    Ex

    4684

    Ex

    4685

    Ex

    4686

    29

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    60/121

    Ex

    4687

    Ex

    4688

    Ex

    4689

    Ex

    4690

    Ex

    4691

    Ex

    4692

    Ex

    4693

    Ex

    4694

    Ex

    4695

    Ex

    4696

    Ex

    4697

    Ex

    4698

    Ex

    4699

    Ex

    4700

    Ex

    4701

    Ex

    4702

    Ex

    4703

    Ex

    4704

    Ex

    4705

    Ex

    4706

    Ex

    4707

    Ex

    4708

    Ex

    4709

    Ex

    4710

    Ex

    4711

    Ex

    4712

    Ex

    4713

    Ex

    4714

    Ex

    4715

    Ex

    4716

    Ex

    4717

    Ex

    4718

    Ex

    4719

    Ex

    4720

    Ex

    4721

    Ex

    4722

    Ex

    4723

    30

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    61/121

    Ex

    4724

    Ex

    4725

    Ex

    4726

    Ex

    4727

    Ex

    4728

    Ex

    4729

    Ex

    4730

    Ex

    4731

    Ex

    4732

    Ex

    4733

    Ex

    4734

    Ex

    4735

    Ex

    4736

    Ex

    4737

    Ex

    4738

    Ex

    4739

    Ex

    4740

    Ex

    4741

    Ex

    4742

    Ex

    4743

    Ex

    4744

    Ex

    4745

    Ex

    4746

    Ex

    4747

    Ex

    4748

    Ex

    4749

    Ex

    4750

    Ex

    4751

    Ex

    4752

    Ex

    4753

    Ex

    4754

    Ex

    4755

    Ex

    4756

    Ex

    4757

    Ex

    4758

    Ex

    4759

    Ex

    4760

    31

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    62/121

    Ex

    4761

    Ex

    4762

    Ex

    4763

    Ex

    4764

    Ex

    4765

    Ex

    4766

    Ex

    4767

    Ex

    4768

    Ex

    4769

    Ex

    4770

    Ex

    4771

    Ex

    4772

    Ex

    4773

    Ex

    4774

    Ex

    4775

    Ex

    4776

    Ex

    4777

    Ex

    4778

    Ex

    4779

    Ex

    4780

    Ex

    4781

    Ex

    4782

    Ex

    4783

    Ex

    4784

    Ex

    4785

    Ex

    4786

    Ex

    4787

    Ex

    4788

    Ex

    4789

    Ex

    4790

    Ex

    4791

    Ex

    4792

    Ex

    4793

    Ex

    4794

    Ex

    4795

    Ex

    4796

    Ex

    4797

    32

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    63/121

    Ex

    4798

    Ex

    4799

    Ex

    4800

    Ex

    4801

    Ex

    4802

    Ex

    4803

    Ex

    4804

    Ex

    4805

    Ex

    4806

    Ex

    4807

    Ex

    4808

    Ex

    4809

    Ex

    4810

    Ex

    4811

    Ex

    4812

    Ex

    4813

    Ex

    4814

    Ex

    4815

    Ex

    4816

    Ex

    4817

    Ex

    4818

    Ex

    4819

    Ex

    4820

    Ex

    4821

    Ex

    4822

    Ex

    4823

    Ex

    4824

    Ex

    4825

    Ex

    4826

    Ex

    4827

    Ex

    4828

    Ex

    4829

    Ex

    4830

    Ex

    4831

    Ex

    4832

    Ex

    4833

    Ex

    4834

    33

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    64/121

    Ex

    4835

    Ex

    4836

    Ex

    4837

    Ex

    4838

    Ex

    4839

    Ex

    4840

    Ex

    4841

    Ex

    4842

    Ex

    4843

    Ex

    4844

    Ex

    4845

    Ex

    4846

    Ex

    4847

    Ex

    4848

    Ex

    4849

    Ex

    4850

    Ex

    4851

    Ex

    4852

    Ex

    4853

    Ex

    4854

    Ex

    4855

    Ex

    4856

    Ex

    4857

    Ex

    4858

    Ex

    4859

    Ex

    4860

    Ex

    4861

    Ex

    4862

    Ex

    4863

    Ex

    4864

    Ex

    4865

    Ex

    4866

    Ex

    4867

    Ex

    4868

    Ex

    4869

    Ex

    4870

    Ex

    4871

    34

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    65/121

    Ex

    4872

    Ex

    4873

    Ex

    4874

    Ex

    4875

    Ex

    4876

    Ex

    4877

    Ex

    4878

    Ex

    4879

    Ex

    4880

    Ex

    4881

    Ex

    4882

    Ex

    4883

    Ex

    4884

    Ex

    4885

    Ex

    4886

    Ex

    4887

    Ex

    4888

    Ex

    4889

    Ex

    4890

    Ex

    4891

    Ex

    4892

    Ex

    4893

    Ex

    4894

    Ex

    4895

    Ex

    4896

    Ex

    4897

    Ex

    4898

    Ex

    4899

    Ex

    4900

    Ex

    4901

    Ex

    4902

    Ex

    4903

    Ex

    4904

    Ex

    4905

    Ex

    4906

    Ex

    4907

    Ex

    4908

    35

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    66/121

    Ex

    4909

    Ex

    4910

    Ex

    4911

    Ex

    4912

    Ex

    4913

    Ex

    4914

    Ex

    4915

    Ex

    4916

    Ex

    4917

    Ex

    4918

    Ex

    4919

    Ex

    4920

    Ex

    4921

    Ex

    4922

    Ex

    4923

    Ex

    4924

    Ex

    4925

    Ex

    4926

    Ex

    4927

    Ex

    4928

    Ex

    4929

    Ex

    4930

    Ex

    4931

    Ex

    4932

    Ex

    4933

    Ex

    4934

    Ex

    4935

    Ex

    4936

    Ex

    4937

    Ex

    4938

    Ex

    4939

    Ex

    4940

    Ex

    4941

    Ex

    4942

    Ex

    4943

    Ex

    4944

    Ex

    4945

    36

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    67/121

    Ex

    4946

    Ex

    4947

    Ex

    4948

    Ex

    4949

    Ex

    4950

    Ex

    4951

    Ex

    4952

    Ex

    4953

    Ex

    4954

    Ex

    4955

    Ex

    4956

    Ex

    4957

    Ex

    4958

    Ex

    4959

    Ex

    4960

    Ex

    4961

    Ex

    4962

    Ex

    4963

    Ex

    4964

    Ex

    4965

    Ex

    4966

    Ex

    4967

    Ex

    4968

    Ex

    4969

    Ex

    4970

    Ex

    4971

    Ex

    4972

    Ex

    4973

    Ex

    4974

    Ex

    4975

    Ex

    4976

    Ex

    4977

    Ex

    4978

    Ex

    4979

    Ex

    4980

    Ex

    4981

    Ex

    4982

    37

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    68/121

    Ex

    4983

    Ex

    4984

    Ex

    4985

    Ex

    4986

    Ex

    4987

    Ex

    4988

    Ex

    4989

    Ex

    4990

    Ex

    4991

    Ex

    4992

    Ex

    4993

    Ex

    4994

    Ex

    4995

    Ex

    4996

    Ex

    4997

    Ex

    4998

    Ex

    4999

    Ex

    5000

    Ex

    5001

    Ex

    5002

    Ex

    5003

    Ex

    5004

    Ex

    5005

    Ex

    5006

    Ex

    5007

    Ex

    5008

    Ex

    5009

    Ex

    5010

    Ex

    5011

    Ex

    5012

    Ex

    5013

    Ex

    5014

    Ex

    5015

    Ex

    5016

    Ex

    5017

    Ex

    5018

    Ex

    5019

    38

    of

    65

    Pages

  • 8/3/2019 Stevick, Glen Expert Report Only

    69/121

    Ex

    5020

    Ex

    5021

    Ex

    5022

    Ex

    5023

    Ex

    5024

    Ex

    5025

    Ex

    5026

    Ex

    5027

    Ex

    5028

    Ex

    5029

    Ex

    5030

    Ex

    5031

    Ex

    5032

    Ex

    5033

    Ex

    5034

    Ex

    5035

    Ex

    5036

    Ex

    5037

    Ex

    5038

    Ex

    5039

    Ex

    5040

    Ex

    5041

    Ex

    5042

    Ex

    5043

    Ex

    5044

    Ex

    5045

    Ex

    5046

    Ex

    5047

    Ex

    5048

    Ex

    5049

    Ex

    5050

    Ex

    5051

    Ex

    5052

    5053

    5054

    5055

    5056

    39