    Potential TIGER StreetcarOperation and Maintenance

    Funding Mechanisms

    Transportation & Environment Committee

    June 10, 2013

  • 7/28/2019 Streetcar Extension O&M Funding Issue

    3/10

    2

    TIGER Streetcar Project Overview

    Phase I - The 1.6 mile base project currently under construction

    runs from Union Station to Methodist Hospital at a cost ofapproximately $48.6 million, including vehicles $26 million in federal funding

    $12.8 million in local funding (Regional Toll Road Revenue)

    $1.5 million (reprogrammed bond program dollars)

    $9 million from DART for vehicles

    Phase II One-half mile northern extension loop is in conceptualdesign, proposed to run from Union Station to the Omni DallasConvention Center Hotel, at a cost of approximately $10 million Local funding (Texas Mobility Funds)

    Phase III Three-quarter mile southern extension loop is in

    conceptual design, proposed to run from Methodist Hospital tothe Zang Blvd. / Davis St. intersection at the Bishop Arts District,at a cost of approximately $21 million Local funding (Texas Mobility Funds)

  • 7/28/2019 Streetcar Extension O&M Funding Issue

    4/10

    3

    Dallas Streetcar Network

  • 7/28/2019 Streetcar Extension O&M Funding Issue

    5/10

    4

    TIGER Streetcar:Operations & Maintenance (O&M) Costs

    O&M cost for Phase 1 ($500,000 per year) funded byDallas Area Rapid Transit (DART) and privatedeveloper (Stratford Land) $200,000 a year from DART

    $300,000 a year for ten years ($3 million total) from Stratford,

    reimbursed through Davis Garden TIF District Base project assumes weekday service only

    Between 5:00 a.m. to 7:00 p.m.

    Assumes 20 minute peak service and 30 minute off peakservice

  • 7/28/2019 Streetcar Extension O&M Funding Issue

    6/10

    5

    TIGER Streetcar:Operations & Maintenance (O&M) Costs

    O&M cost for Streetcar Extension

    Phases 2 & 3 Extensions with weekday service only estimated at $750,000per year

    Between 5:00 a.m. to 7:00 p.m. Assumes 20 minute peak service and 30 minute off peak

    service

    Extensions with weekday and weekend extendedhours estimated at $2.5 million per year

    Service from 5:00 a.m. to midnight Assumes 15 minute headways DART funds $750,000 per year

    Unfunded gap of $1.75 million per year

  • 7/28/2019 Streetcar Extension O&M Funding Issue

    7/10

    6

    Potential O&M Funding Sources

    Tax Increment Financing (TIF) City Center TIF

    Downtown Connection TIF

    Oak Cliff Gateway TIF

    New TIF districts yet to be created

    Public Improvement District (PID) Downtown Improvement District (DID)

    New PIDs in North Oak Cliff or Downtown overlay

    DART 2030 Plan

  • 7/28/2019 Streetcar Extension O&M Funding Issue

    8/10

    7

    Dallas Streetcar Phase 2 Extension

  • 7/28/2019 Streetcar Extension O&M Funding Issue

    9/10

    8

    Dallas Streetcar Phase 3 Extension

  • 7/28/2019 Streetcar Extension O&M Funding Issue

    10/10

    9

    Funding Challenges TIF funding availability uncertain

    Timing an issue because increment collection varies bydistrict and is dependent on property value increases

    Existing TIF commitments in Downtown and Oak CliffGateway TIFs

    New Oak Cliff TIF would require large catalyst project to

    ensure new increment is generated Public Improvement Districts

    Formation and assessment rate requires consent ofland-owning stakeholders

    Existing Downtown Improvement District (DID) has

    some capacity but many priorities (potential to form astreetcar-centric Downtown overlay PID) New Oak Cliff PID would require institutional support

    DART 2030 Plan