Upload
avocadocolor
View
254
Download
1
Embed Size (px)
Citation preview
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
1/111
1
This Thesis is submitted in Partial Fulfillment for the
Requirement of the Degree of Bachelor of Science in
Electrical & Electronic Engineering
Course Code: EEE-499
STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION &
DISTRIBUTION IN BANGLADESH
Prepared By:
1. Jagadish Chandra Sutradhar ID # 112-0070-511
2. Md. Sharif Hossain ID # 112-0164-511
3. Syed Shawkat Aziz ID # 112-0011-511
4. Mohammad Ali Hasan ID # 112-0135-511
5. Md. Jakir Hossain ID # 122-0197-511
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
2/111
2
STUDY OF ELECTRICAL POWER GENERATION, TRANSMISSION &
DISTRIBUTION IN BANGLADESH
A Project / internship / thesis report submitted to the department of EEE, Atish
Dipankar Biggayan O Projokti Bishawbiddaloy for partial fulfillment of the Degree
of B.Sc in Electrical and Electronic Engineering.
Submitted By:
1. Jagadish Chandra Sutradhar ID # 112-0070-511
2. Md. Sharif Hossain ID # 112-0164-511
3. Syed Shawkat Aziz ID # 112-0011-511
4. Mohammad Ali Hasan ID # 112-0135-511
5. Md. Jakir Hossain ID # 122-0197-511
Supervised By:
Marzia Hoque Signature :
Date:
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
3/111
3
Declaration
It is here by declared that no part of this thesis bearers the copyright violation and no plagiarism
opted during the course of material preparation. The entire works has been planned and carried
out under the thesis supervisor of the honorable faculty member Marzia Haque department of
Electrical and Electronic Engineering, Atish Dipankar Biggayan O Projokti Bishawbiddaloy,
Dhaka, Bangladesh.
The content of this thesis is submitted by the groupName : Jagadish Chandra Sutradhar, ID #
112-0070-511, Name : Md. Sharif Hossain ID # 112-0164-511, Name : Syed Shawkat Aziz ID
# 112-0011-511, Name : Mohammad Ali Hasan ID # 112-0135-511, Name : Md. Jakir
Hossain ID # 122-0197-511.
Only for the fulfillment of the course ofSTUDY OF ELECTRICAL POWER
GENERATION, TRANSMISSION DISTRIBUTION IN BANGLADESH .And no part
of this is used anywhere for the achievement of any academic Degree or Certificate.
Jagadish Chandra Sutradhar
ID # 112-0070-511
Department of EEE
Syed Shawkat Aziz
ID # 112-0011-511
Department of EEE
Md. Sharif Hossain
ID # 112-0164-511
Department of EEE
Mohammad Ali Hasan
ID # 112-0135-511
Department of EEE
Md. Jakir Hossain
ID # 122-0197-511
Department of EEE
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
4/111
4
Certificate
This is to certify that the B.Sc. thesis entitled STUDY OF ELECTRICAL POWER
GENERATION, TRANSMISSION DISTRIBUTION IN BANGLADESH
. submitted by
following group:
This is to certify that the B.Sc thesis entitled STUDY OF ELECTRICAL POWER GENERATION,
TRANSMISSION DISTRIBUTION IN BANGLADESH
submitted by following groupName
: Jagadish Chandra Sutradhar, ID # 112-0070-511, Name : Md. Sharif Hossain ID # 112-
0164-511, Name : Syed Shawkat Aziz ID # 112-0011-511, Name : Mohammad Ali Hasan ID# 112-0135-511, Name : Md. Jakir Hossain ID # 122-0197-511.
The thesis represents an independent and original work on the part of the
candidates. The research work has not been previously formed the basis for the
award of any Degree, Diploma, Fellowship or any other discipline.
The whole work of this thesis has been planned and carried out by this group
under the supervision and guidance of the faculty members of Atish Dipankar
Biggayan O Projokti Bishawbiddaloy, Bangladesh.
Marzia Hoque
LecturerDepartment of Electrical and Electronic EngineeringAtish Dipankar Biggayan O Projokti Bishawbiddaloy
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
5/111
5
Transmittal
Date: 26/05/2014Faculty of Engineering
Department of EEEAtish Dipankar Biggayan O Projokti BishawbiddaloyDhaka, Bangladesh.
Subject: letter of transmittal.
Dear Sir,With due respect, we should like to inform you that is a great pleasure for us to submit the final
project on STUDY OF ELECTRICAL POWER GENERATION, TRANSMISSION &
DISTRIBUTION IN BANGLADESHfor Department of Electrical and Electronic Engineering
as requirement bachelor degree/ program. This project provided us with a practical exposure to
the overall working environment and very good experience which is prevailing in to professional
life. We came to know about many things regarding the current world on the concept of
Electronic Development. We have tried to our best to put through effort for the preparation of this
report. Any short coming or fault may arise as our unintentional mistake we will whole heartily
welcome for any clarification and suggestion about any view and conception disseminated
through this project.
We hope and strongly believe that this project will meet the requirement as well as satisfying your
purpose. We will available for any further classification in this regard.
Sincerely Yours,
ID # 112-0070-511
ID # 112-0164-511
ID # 112-0011-511
ID # 112-0135-511
ID # 122-0197-511
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
6/111
6
APPORAVAL SHEET
This project title is STUDY OF ELECTRICAL POWER GENERATION, TRANSMISSION &
DISTRIBUTION IN BANGLADESH has been submitted to the following respected members of
the Board of Examiners of the Department of Electrical and Electronic Engineering in partial
fulfillment of the requirements of the degree of Bachelor of Department of Electrical and
Electronic Engineering by the following students.
1. Jagadish Chandra Sutradhar ID # 112-0070-511
2. Md. Sharif Hossain ID # 112-0164-511
3. Syed Shawkat Aziz ID # 112-0011-511
4. Mohammad Ali Hasan ID # 112-0135-511
5. Md. Jakir Hossain ID # 122-0197-511
As the supervisor I have approved this paper for submission.
.. ..
Marzia Hoque Md.Imam HossainProject Supervisor & Senior Lecturer & CoordinatorLecturer Department of EEEDepartment Of EEE Atish Dipankar Biggayan O AtishDipankar Biggayan O Projokti BishawbiddaloyProjokti Bishawbiddaloy
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
7/111
7
ACKNOWLEDGEMENT
At first we would like to thank our Supervisor Marzia Haque
(Lecturer) for giving us the opportunity to work to under his supervision, the endless hours of
help, Suggestions, Advice and Support to keep us on track during the development of this thesis.
We also want to express gratitude to Mr. Md. Imam Hossainfor his support during our work on
this thesis.
Last, but not the least, we would like to thank our parents and family for making it possible for us
to study and for their constant help and support.
May, 2014
1. Jagadish Chandra Sutradhar ID # 112-0070-511
2. Md. Sharif Hossain ID # 112-0164-511
3. Syed Shawkat Aziz ID # 112-0011-511
4. Mohammad Ali Hasan ID # 112-0135-511
5. Md. Jakir Hossain ID # 122-0197-511
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
8/111
8
ABSTRACT
In this modern world, the dependence on electricity is so much that it has become a part and
parcel of our life. The development of any country of the world is based on electricity and its
proper generation, transmission and distribution. For the proper utilization, it is required to
transmit and distribute the generating electrical power through the proper way.
For proper power generation, we have to consider the selection of power station according to the
site selection of the different power station and their advantage and disadvantage.
In this thesis work, we have discussed about different types of power station, their merits &
demerits, power generation in Bangladesh, power demand, installed capacity deficiency of power,
power plant under construction.
We have also discussed about the transmission and distribution system. Where has been included
mechanical design of transmission system, electrical design of transmission system, different
types of transmission loss, remedy of loss. For distribution system, we have included the bhurulia
distribution sub-station.
We think that, this study will be very helpful for better understanding about generation and
transmission system of Bangladesh.
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
9/111
9
ABBREVIATIONS & NOTATIONS
BPDB : Bangladesh Power Development Board
PGCB : Power Grid Company of Bangladesh Ltd
DESA : Dhaka Electric Supply Authority
DESCO : Dhaka Electric Supply Company
REB : Rural Electrification Board
LDC : Load dispatch Centre
A.C : Alternating Current
D.C : Direct Current
KVA : Kilo Volt Ampere
Km : Kilometer
KV : Kilo Volt
KW : Kilo Watt
KWH : Kilo Watt Hour
HVDC : High Voltage Direct Current
CB : Circuit Breaker
GS : Generation Station
HEPS : Hydro Electric Power Station
DPS : Diesel Power Station
NPS : Nuclear Power Station
IPP : Independent Power Producer
EHV : Extra High Voltage
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
10/111
10
CONTENTS
TABLE OF CONTENTS
Contents Page No.
Cover Page 1Initial Page 2Declaration 3Certificate 4
Transmittal 5Approval Sheet 6Acknowledgement 7Abstract 8Abbreviation & Notations 9Table of Contents 10List of Table 11List of Figure 12
CHAPTER-1: Introduction
1.1 Background 19
1.2 Objective of thesis 19
CHAPTER-2: Study of power generation system
2.1 Generation Station 20
2.2 Types of Generating Station 20
2.3 Steam power plant 20
2.3.1 Choice of site for Steam power plant 20
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
11/111
11
2.3.2 Advantages of Steam power plant 21
2.3.3 Disadvantages of Steam power plant 21
2.3.4 Schematic arrangement of Steam power plant 21
2.3.5 Description of various section of Steam power plant 22
2.3.6 Typical Steam power plant 24
2.3.7 Efficiency of Steam power plant 34
2.4 Hydro-Electric power Station 34
2.4.1 Choice of site for Hydro-Electric power Station 35
2.4.2 Advantages of Hydro-Electric power Station 35
2.4.3 Disadvantages of Hydro-Electric power Station 36
2.4.4 Constituents of Hydro-Electric power Station 36
2.5 Nuclear power station 37
2.5.1 Choice of site for nuclear power station 37
2.5.2 Advantages of Nuclear power station 38
2.5.3 Disadvantages of Nuclear power station 38
2.5.4 Schematic arrangement of nuclear power station 38
2.6 Diesel power station 40
2.6.1 Choice of site for Diesel power station 40
2.6.2 Advantages of Diesel power station 40
2.6.3 Disadvantages of Diesel power station 40
2.6.4 Schematic arrangement of Diesel power station 41
2.7 Gas turbine power station 41
2.7.1 Advantages of Gas turbine power station 41
2.7.2 Disadvantages of Gas turbine power station 41
2.7.3 Schematic arrangement of Gas turbine power station 42
2.7.4 The main components of the plant 42
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
12/111
12
CHAPTER-3: Power generation in Bangladesh
3.1 Generating voltage of different power station 44
3.2 Power demand 44
3.3 Load factor and Load management 44
3.4 Installed capacity 44
3.5 Owner Wise Daily Generation 45
3.5.1 Installed Capacity of BPDB Power Plants as on April 2014. 46
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
13/111
13
CHAPTER-4: Transmission System of Bangladesh
4.1 Transmission System 52
4.2 Primary Transmission 52
4.2.1 Grid System 52
4.2.2 Grid sub- station 52
4.3 Secondary Transmission 53
4.4 Classification of overhead transmission line 53
4.5 Definition of important terms 53
4.6 Advantages of high voltage transmission system 54
4.7 Advantages and disadvantages of high voltage direct current system 55
4.8 Transmission system of different countries 55
4.8.1 Transmission system of India 55
4.8.2 Transmission system of Srilanka 56
4.8.3 Transmission system of Nepal 56
4.8.4 Transmission system of Pakistan 57
CHAPTER-5: Mechanical design of overhead transmission line
5.1 Properties of conductor materials 58
5.2 Conductors materials 58
5.3 Types of conductor 59
5.4 Line support 61
5.5 Types of line support 61
5.6 Insulators 62
5.7 Types of Insulators 62
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
14/111
14
CHAPTER-6: Electrical design of overhead transmission line6.1 Electrical design aspects 656.2 Constant of transmission line 656.3 Characteristics of different transmission line 716.4 Transmission voltage level 76
6.5 Standardization of transmission voltage 776.6 Extra high voltage transmission 776.7 Protection system of transmission line 786.8 Protection components 786.9 LIST OF TRANSMISSION LINES IN BANGLADESH 79
6.9.1 Recent Completed Project for Transmission6.9 132 KV Transmission Lines 806.9.1 Recent Completed Project for Transmission 816.9.2 Hasnabad & Tongi 230 kV and Kalyanpur 132 kV S/s Construction (Hasnabad-
Aminbazar-Tongi & Haripur-Me82
6.9.3 Joydevpur-Kabirpur-Tangail 78 km 132 kV T/L & 3 S/s Extn. Project (Joydebpur-
Kabirpur-Tangail 132 kV
83
6.9.4 Ishurdi-Baghabari 54 km 230 kV T/L Construction (Ishurdi Baghabari-Serajgonj-Bogra 230 kV T/L Project)
83
6.9.5 On Going Project for Transmission400/230/132 Network Developmemt project (Trance-2)
84
6.9.6 Goalpara-Bagerhat 132 kV Double Circuit Transmission Line 846.9.7 Meghnaghat-Aminbazar 400 kV Transmission Line (NG1) 846.9.8 Construction & Extension of Grid Substations including transmission line facilities
(Phase-1)85
6.9.9 Aminbazar-Old Airport 230 kV Transmission Line and Associated Substations 856.9.10 Transmission Efficiency Improvement through Reactive Power Compensation at
Grid Substations and Reinforcement of Goalpara Substation85
6.9.11 Siddhirganj-Maniknagar 230 kV Transmission Line 866.9.12 132 kV Grid Network Development Project in Eastern Region. 866.9.13 National Power Transmission Network Development Project 866.9.14 Barisal-Bhola-Burhanuddin 230 kV Transmission Line Project 876.9.15 Grid Interconnction between Bangladesh(Bheramara) and India(Baharampur) 876.9.16 Two new 132/33 kV substations at Kulaura & Sherpur with interconnecting line 876.9.17 Bibiyana-Kaliakoir 400 KV and Fenchuganj-Bibiyana 230KV Transmission Line
(NG2)88
6.9.18 Haripur 360 MW Combined Cycle Power Plant and Associated Substation (PGCBPart)
88
6.10 Transmission line losses 88
6.10.1 Types of losses 88
6.10.2 Skin effect 89
6.11 Minimization of Transmission line losses 90
CHAPTER-7: Distribution System
7.1 Definition of Substation 91
7.2 Importance of Substation 91
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
15/111
15
7.3 Equipment of electrical Substation 91
7.4 Classification of Substation 91
7.5 Definition of different equipments 92
7.5.1 Transformer 93
7.5.2 Power Transformer 93
7.5.3 Instrument Transformer 93
7.5.4 Isolator 94
7.5.5 Lighting arrester 95
7.5.6 Insulator 95
7.5.7 Bus-Bar 977.5.8 Circuit-Breaker 99
7.5.9 Basic principles of operation of circuit breaker 100
7.6 Different types of Circuit Breaker 100
7.6.1 Plain Breaker Oil circuit Breaker (POCB) 100
7.6.2Vacuum Circuit Breaker (VCB) 101
7.6.3 Sulphur Hexa Fluoride Circuit Breaker (SF6) 102
7.7 List of equipments of bhurulia sub-station 1047.8 Rating of different equipments 104
7.9 Single line diagram of bhurulia sub-station 106
7.9 Calculation of power factor for different feeder 107
CHAPTER-8: Future plan of Bangladesh
8.1 Power generation plan up to 2016 108
8.2 India Bangladesh transmission link 108
8.3 400 KV transmission line 108
CHAPTER-9: Discussion And Conclusion Reference
LIST OF FIGURE
Figure : 2.1 Schematic arrangement of a steam power station. 22
Figure : 2.2 Steam power plant 24
Figure : 2.3 Steam Generator 25
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
16/111
16
Figure : 2.4 Turbo Generator 29
Figure : 2.5 Diagram of a typical water cooled surface condenser. 30
Figure : 2.6 A Ranking cycle with a two stage steam turbine and a single feed
water heater.
31
Figure : 2.7 Boiler feed water desecrator 32
Figure : 2.8 Schematic arrangement of a hydro-electric power station. 35
Figure : 2.9 Schematic Arrangement of a Nuclear power Station. 39
Figure : 2.10 Schematic Arrangement of a Diesel Power Plant 41
Figure : 2.11 Schematic arrangement of a gas turbine power plant. 42
Figure : 5.1 Conductor Section of AAC. 59
Figure : 5.2 (a): 37 Bobbin Stranding Machine (b) : 61 Bobbin Stranding Machine
(c) : Conductor Section of AAAC (d) : Conductor Section of ACSR
60
61
Figure : 5.3 Steel Tower 62
Figure : 5.4 Pin type Insulator 63
Figure : 5.5 Outside and inside constructional diagram of long rod insulators 64
Figure : 6.1 Equilateral Spacing (inductance). 67
Figure : 6.2 (a) Unsymmetrical Spacing (inductance).
(b) Unsymmetrical Lines (inductance).
68
Figure : 6.3 Equilateral Spacing (capacitance). 69
Figure : 6.4 Unsymmetrical Spacing (capacitance). 70
Figure : 6.5 Two port network. 72
Figure : 6.6 Short Transmission line. 72
Figure : 6.7 Medium Transmission Line. 73
Figure : 6.8 NominalT representation. 74
Figure : 6.9 Nominal representation. 74
Figure : 6.10 Long Transmission Line. 74
Figure : 7.1 Transformer. 93
Figure : 7.2 Three Phase Power Transformer 93
Figure : 7.3 Isolator 94
Figure : 7.4 Lightning arrestor 95
Figure : 7.5 Pin type insulator 96
Figure : 7.6 Suspension type insulator 96
Figure : 7.7 Strain insulator 97
Figure : 7.8 Single Bus bar 98
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
17/111
17
Figure : 7.9 Single Bus bar system with Sectionalisation 99
Figure : 7.10 Basic operation of circuit breaker 100
Figure : 7.11 Oil Circuit Breaker 101
Figure : 7.12 Vacuum circuit break 102
Figure : 7.13 Sulphur Hexa Fluoride Circuit Breaker 103
Figure : 7.15 Single Line diagram of Bhurulia Sub-Station 106
Figure : 7.16 Power triangle 107
LIST OF TABLE
Table List Description Page No
3.5 Owner wise monthly Generation 45
3.5.1 Installed Capacity of BPDB Power Plants as on April 2014. 46
3.5.2 Power supply situation on 18thMarch 2014 (Monday) 47
3.5.3 Daily Generation Report 48
4.8.2 Transmission System Of Srilanka 56
6.9 230 KV Transmission Lines 79
6.10 132 KV Transmission Lines 80
6.10.1 Recent Completed Project for Transmission 81
6.10.2 Hasnabad & Tongi 230 kV and Kalyanpur 132 kV S/s
Construction (Hasnabad-Aminbazar-Tongi & Haripur-Me
82
6.10.3 Joydevpur-Kabirpur-Tangail 78 km 132 kV T/L & 3 S/s Extn.
Project (Joydebpur-Kabirpur-Tangail 132 kV
83
6.10.4 Ishurdi-Baghabari 54 km 230 kV T/L Construction (Ishurdi
Baghabari-Serajgonj-Bogra 230 kV T/L Project)
83
6.10.5 On Going Project for Transmission
400/230/132 Network Development project (Trance-2)
84
6.10.6 Goalpara-Bagerhat 132 kV Double Circuit Transmission Line 84
6.10.7 Meghnaghat-Aminbazar 400 kV Transmission Line (NG1) 84
6.10.8 Construction & Extension of Grid Substations including
transmission line facilities (Phase-1)
85
6.10.9 Aminbazar-Old Airport 230 kV Transmission Line and Associated
Substations
85
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
18/111
18
6.10.10 Transmission Efficiency Improvement through Reactive Power Compensation at
Grid Substations and Reinforcement of Goalpara Substation
85
6.10.11 Siddhirganj-Maniknagar 230 kV Transmission Line 86
6.10.12 132 kV Grid Network Development Project in Eastern Region. 86
6.10.13 National Power Transmission Network Development Project 86
6.10.14 Barisal-Bhola-Burhanuddin 230 kV Transmission Line Project 87
6.10.15 Grid Interconnction between Bangladesh(Bheramara) and
India(Baharampur)
87
6.10.16 Two new 132/33 kV substations at Kulaura & Sherpur with
interconnecting line
87
6.10.17 Bibiyana-Kaliakoir 400 KV and Fenchuganj-Bibiyana 230KV
Transmission Line (NG2)
88
6.10.18 Haripur 360 MW Combined Cycle Power Plant and Associated
Substation (PGCB Part)
88
7.7 List of equipment of Bhurulia substation 104
7.8 Rating of different equipment used in bhurulia sub-station
Rating of Oil circuit breaker
104
7.9 Rating of SF6circuit breaker 105
7.10 Rating of Vacuumcircuit breaker 105
7.11 Rating of Transformer (T1) 105
7.12 Rating of Transformer (T2) 105
7.13 Rating of Transformer (T3) 106
7.18 Voltage Regulator(For each phase) 106
REFERENCES 109
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
19/111
19
CHAPTER-1
INTRODUCTION
1.1 BACKGROUND
For growing development of a country, electricity has a vital role in all sectors. For the proper
utilization, is required to transmit and distribute the electrical power through proper way. During
the early years small local generating station supplied power to respective local loads. Each
generating station needed enough installed capacity to meet the local peak loads. Bangladesh is an
underdeveloped country. Its socio- economic structure is gradually increasing. So the demand of
power is extending day by day and thus the importance of Generation, Transmission and
Distribution are becoming more complicated.
An electric power system consist of the three principal components are the generation system,
transmission system and distribution system. The increasing uses of electric power for domestic,
commercial and industrial purposes necessities to provide bulk electric power economically. This
is achieved with the help of suitable power generating units, known as power plant. An electric
power station is an assembly of equipments in which energy is converted from one form to
another into electric energy. Electrical equipments of power station include generators,transformers, switch gears and control gears. The transmission lines are the connecting links
between the generating stations and the distribution system and lead to the power system over
interconnections. It is required to proper distribute the electric power to the consumer by a
network is called the distribution system.
1.2 OBJECTIVES OF THE THESIS
a) To study the different power stations such as hydro electric power station, thermal power
station, Nuclear power station, diesel power station and Gas turbine power station.
b) To study the comparative facilities of different power station.
c) To study the comparative productive ability of different power stations.
d) To study the power generation in Bangladesh.
e) To study the transmission system in Bangladesh.
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
20/111
20
CHAPTER-2
OVERVIEW OF POWER GENERATION SYSTEMS
2.1 GENERATING STATION
Bulk electric power is produced by special plant is known as the generating station or power
plants. A generating station essentially employs a prime mover coupled to an alternator for the
production of electric power. The alternator converts mechanical energy of the prime mover into
electrical energy. The electrical energy produced by the generating station is transmitted and
distributed with the help of conductors of various consumers.
2.2 TYPES OF GENERATING STATION
1) Steam power plant
2) Hydro-electric power plant
3) Nuclear power plant
4) Diesel power plant
2.3 STEAM POWER PLANT
A generating station that converts the heat energy of coal combustion into electrical energy is
known as a steam power station.
2.3.1 CHOICE OF SITE FOR STEAM POWER STATIONS
1. Supply of fuel:The steam power station should be located near the coal mines so that
transportation cost is minimum. However, if such a plant is to be installed taken that
adequate facilities exists for the transportation of coal.
2. Availability of water:As huge amount water is required for the condenser therefore, such
a plant should be located at the bank of a river or near a canal to endure the continuous
supply of water.
3. Transportation facilities:A modern steam power station often requires the transportation
of material and machinery. Therefore, adequate transportation facilities must exist. The
plant should be well connected to others part of the country by the rail road etc.
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
21/111
21
4. Cost and Type of Land:The steam power station should be located at a place where land
is cheap and further extension, if necessary is possible. More ever the bearing capacity of
the ground should be adequate so that heavy equipment could be installed.
5. Nearness to the Load Centre:In order to reduce the transmission cost the plant should be
located near the centre of load. This is particularly important if dc supply is adopted, this
factor becomes relatively less important with consequent reduced transmission cost. It
possible to install the plant away from the load centers provided other conditions are
favorable.
6. Distance from Populated Area:As huge amount of coal is burnt in a steam power
station, therefore smoke and fumes plant should be located at a considerable distance from
the populated areas.
2.3.2 ADVANTAGES OF STEAM POWER PLANT
a) The fuel is quite cheap
b) Less initial cost as compared to other generating stations
c) It can be installed at by place irrespective of the existence of coal. The coal can be
transported to the site of the plant by rail or road.
d) It required less space as compared to the hydro-electric power station.
e) The cost of generation is lesser than that of the diesel power station.
2.3.3 DISADVANTAGES OF STEAM POWER PLANT
a) It pollutes the atmosphere due to the production of large amount of smoke and fumes.
b) It costlier in running cost as compared to hydro-electric plant.
2.3.4 SCHEMATIC ARRANGEMENT OF STEAM POWER PLANT
Although steam power station simply involves the conversion of heat of coal combustion into
electrical energy, etc if embraces many arrangements for proper working and efficiency. The
schematic arrangement of a modern steam power station is shown in bellow. Where the whole
arrangement can be divided into the following stages for the sake of simplicity.
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
22/111
22
Fig: 2.1 Schematic arrangement of a steam power station.
2.3.5 DISCRIPTION OF VARIOUS SECTION OF STEAM POWER PLANT
1. Coal and ash handling arrangement
2. Steam generating plant
3. Steam turbine
4. Alternator
5. Feed water
6. Cooling arrangement
Coal and ash handling plant:
The coal is transported to the power station by road or rail and is stored in the coal storage plant.
Storage of coal is primarily a matter of protection against shortages. From the coal storage plant
coal is delivered to the coal handling plat where it is pulverized combustion without using large
quantity of excess air. The pulverized coal is fed to the boiler by belt conveyors. The coal is burnt
in the boiler and the ash produced after the complete combustion of coal is removed to the ash
handling plant and then delivered to the ash storage plant for disposal. The removal of the ash
from the boiler furnace is necessary for proper burning of coal.
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
23/111
23
It is worthwhile to give a passing reference to the amount of coal burnt and ash produced in a
modern thermal power station. A 100 MW station operating at 50% load factor may burn about
20000 tons of coal per month and ash produced may be to the tune of 10% to 15% of coal fired
i.e., 2000 to 3000 tons. In fact in thermal power station about 50% to 60% of the total operating
cost consists of a boiler for the production of steam and other auxiliary equipment for the
utilization of flue gases.
a) Boiler:The heat of combustion of coal in the boiler is utilized to convert water into steam at
high temperature and pressure. The flue gases the boilers makes their journey through super
heater economizer, air pre heater and are finally exhausted to atmosphere through the
chimney.
b)
Super heater:The steam produced in the boiler is wet and is passed through a super heater
where it is dried and superheated water by the flue gases on their way to chimney.
Superheating provides two principal benefits. Firstly the overall efficiency is increased.
Secondly too much condensation in the last stages of turbine is avoided the supper heated
steam turbine through the main valve.
c) Economizer: An economizer is essentially a feed water heater and derives heat from flue
gases for this purpose. The fed to the economizer before supplying to the boiler. The
economizer extracts a part of heat of flues gassed to increase the feed water temperature.d) Air pre-heater: An Air pre-heater increase the temperature of the air supplied from coal
burning by deriving heat from flue gases. Air is drown from the atmosphere by a forced
draught fan and is passed through air pre heater before supplying to the boiler furnace. The air
drowns from the atmosphere by a forced draught fan and is passed through air pre heater
before supplying to the boiler furnace. The pre heater extracts heat from flue gases and
increases the temperature of air used for coal combustion. The principal benefits of preheating
the air are increased thermal efficiency and increased steam capacity per square meter of
boiler surface.
e) Steam turbine: The dry and superheated steam from the super heater id fed to the steam
turbine through main valve. The heat energy of steam when passing over the blades of turbine
is converted into mechanical energy. After giving heat energy to the turbine the steam is
exhausted to the condenser which condenses the exhausted steam by means of cold water
circulation.
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
24/111
24
f) Alternator: The Steam turbine is coupled to an alternator. the alternator converts mechanical
energy of turbine into electrical energy. The electrical output from the alternator is delivered
to the bus bars through transformer circuit breaker and insulators.
g) Feed water:The condensate from condenser is used as feed water to the boiler some water
may lost in the cycle which is made up from external source. The feed water on its way to the
boiler is heated by water heaters and economizer. This helps in raising the overall efficiency
of the plant.
h) Cooling arrangement: In order to improve the efficiency of the plant. The steam exhausted
from the turbine is condensed by means of a condenser.
2.3.6: TYPICAL STEAM POWER PLANT
Fig: 2.2 Steam power plant
1. Cooling tower 15. Air intake
2. Cooling water pump 16. Economizer
3. Transmission line (3-phase) 17. Air pre heater
4. Unit Transmission line (3-phase) 18. Precipitator Electric generator (3-phase)
19. Feed heater
5. Low pressure turbine 20. Coal conveyor
6. Condensate extractions pump 21. Coal hopper
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
25/111
25
7. Condenser 22. Pulverized fuel mill
8. Intermediate pressure turbine 23. Boiler dr10Steam
9. Steam governor valve 24. Ash hopper
10. High pressure turbine 25. Induced draught fan
11. Deaerator 26. Chimney stack
12. Super heater
13. Re heater
2.3.6.1: Steam generator:
Schematic diagram of typical coal-fired power plant steam generator highlighting the air pre
heater (APH) location (For simplicity, any radiant section tubing is not shown)
Fig: 2.3 Steam generator
In fossil fueled power plants, steam generator refers to a furnace that burns the fossil fuel to boil
water to generate steam. In the nuclear plant field, steam generator refers to a specific type of
large heat exchanger used in a pressurized water reactor (PWR) to thermally connect the primary
and secondary systems, which of course is used to generate steam. In nuclear reactor called a
boiling water reactor (BWR), water is boiled to generate steam directly in the reactor itself and
there are no units called steam generators. In some industrial settings, there can also be steam-
producing heat exchangers called heat recovery steam generators which utilize heat from some
industrial process. The steam generating boiler has to produce steam at the high purity, pressure
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
26/111
26
and temperature required or the steam turbine that drives the electrical generator. A fossil fuel
steam generator includes an economizer, a steam drum, and the furnace with its steam generating
tubes and super heater coils. Necessary safety valves are located at suitable points to avoid
excessive boiler pressure. The air and flue gas path equipment include forced draft fan, air pre
heater boiler furnace, fly ash collectors and the flue gas stack.
Geothermal plants need no boiler since they used naturally occurring steam source. Heat
exchangers may be used where the geothermal steam is very corrosive or contains excessive
suspended solids. Nuclear also boil water to raise steam, either directly generating steam from the
reactor (BWR) or else using an intermediate heat exchanger (PWR).
For units over about 200 MW capacity, redundancy of key components is provided by installing
duplicates of the FD fan, APH, fly ash collectors and ID fan with isolating dampers. On some
units of about 60 MW, tow boilers per uint may instead be provided.
2.3.6.2: Boiler furnace and steam drum:
Once water inside the boiler or steam generator, the process of adding the latent heat of
vaporization or enthalpy is underway. The boiler transfers energy to the water by the chemical
reaction of burning some type of fuel. The water enters the boiler through a section in the
convection pass called the economizer. From the economizer it passes to the steam drum. Once
the water enters the stream drum it goes down the down comers to the lower inlet water wall
headers. From the inlet headers the water rises through the water walls and is eventually turned
into steam and due to the heat being generated by the burners located on the front and rear water
walls. As the water is turned into steam in the water walls, the steam once again enters the steam
drum. The steam/vapor is passed through a series of the steam and water separators and then
dryers inside the steam drum . The steam separators and dryers remove water droplets from the
steam and the cycle through the water walls is repeated. This process is known as natural
circulation.
The boiler furnace auxiliary equipment includes coal feed nozzles and igniter guns, soot blowers,
water lancing and observation ports (in the furnace walls) for observation of the furnace interior.
Furnace explosions due to any accumulation of combustible gases after a trip-out are avoided by
flushing out such gases from the combustion zone before igniting the coal.
The steam drum (as well as the super heater coils and headers) have air vents and drains neededfor initial startup. The steam drum has internal devices that remove moisture from the wet steam
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
27/111
27
entering the drum from the steam generating tubes. The dry steam then flows into the super heater
coils.
2.3.6.3: Super heater:
Fossil fuel power plants can have a super heater and/or re-heater section in the steam generating
furnace. Nuclear-powered steam plants do not have such sections but produce steam at essentially
saturated conditions. In a fossil fuel plant, after the steam is conditioned by the drying equipment
inside the steam drum, it is piped from the upper drum area into tubes inside an area of the
furnace known as the super-heater, which has an elaborate set up of tubing where the steam vapor
picks up more energy from hot flue gases outside the tubing and its temperature is now
superheated above the saturation temperature. The superheated steam is then piped through the
main steam lines to the valves before the high pressure turbine.
2.3.6.4: Re-heater:
Power plant furnaces may have a re-heater section containing tubes heated by hot flow gases
outside the tubes. Exhaust steam from the high pressure turbine is rerouted to go inside the re-
heater tubes to pickup more energy to go drive intermediate or lower pressure turbines. This is
what is called as thermal power.
2.3.6.5: Fuel preparation system:
In coal-fired power stations, the row feed coal from the coal storage area is first crushed into
small pieces and then conveyed to the coal feed hoppers at boilers. The coal is next pulverized
may be ball mills, rotating drum grinders, or other types of grinders. Some power station burn fuel
oil rather than coal. The oil must kept warm (above its pour point) in the fuel oil storage tanks to
prevent the oil from congealing and becoming unpumpable. The oil is usually heated to about
1000
c before being pimped through the furnace fuel oil spray nozzles.
Boilers in some power stations use processed natural gas as their main fuel. Other power stations
may use processed natural gas as auxiliary fuel in the event that their main fuel supply (coal or
oil) is interrupted. In such cases, separate gas burners are provided on the boiler furnaces.
2.3.6.6: Air path:
External fans are provided to give sufficient air for combustion. The forced draft fan takes air
from the atmosphere and first warming it in the air pre-heater for better combustion, injects it via
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
28/111
28
the air nozzles on the furnace wall. The induced draft fan assists the FD fan by drawing out
combustible gases from the furnace, maintaining a slightly negative pressure in the furnace to
avoid backfiring through any opening.
2.3.6.7: Auxiliary Systems:
Fly ash collection: Fly ash is captured and removed from the flue gas by electrostatic
precipitators or fabric bag filters (or sometimes both) located at the outlet of the furnace and
before the induced draft fan. The fly ash is periodically removed from the collection hoppers
below the precipitators or bag filters. Generally, the fly ash is pneumatically transported to storage
silos for subsequent transport by trucks or railroad cars.
2.3.6.8 : Action and disposal:
Bottom ash collie: At the bottom of the furnace, there is a hopper for collection of bottom ash.
This hopper is always filled with water to quench the ash and clinkers falling down from the
furnace. Some arrangement is included to crush the clinkers and for conveying the crushed
clinkers and bottom ash to a storage site.
Boiler make-up water treatment plant and storage: Since there is continuous withdrawal of
steam and continuous return of condensate to the boiler, losses due to blow down and leakages
have to be made up to maintain a desired water level in the boiler steam drum. For this,
continuous make-up water is added to the boiler water system. Impurities in the raw water input to
the plant generally consist of calcium and magnesium salts which impart hardness to the water.
Hardness in the make-up water to the boiler will from deposits on the tube water surface which
will lead to overheating and failure of the tubes. Thus, the salts have to be removed from the
water, and that is done by water demineralising treatment plant (DM). A DM plant generally
consist of caution, anion, and mixed bed exchangers. Any ions in the final water from this processconsist essentially of hydrogen ions and hydroxide ions, which recombine to form pure water.
Very pure DM water becomes highly corrosive once it absorbs oxygen from the atmosphere
because of its very high affinity for oxygen.
The capacity of the DM plant is dictated by the type and quantity of salt s in the raw water input.
However, some storage is essential as the DM plant may be down for maintenance. For this
purpose, a storage tank is installed from which DM water is continuously withdrawn for boiler
make-up.the storage tank for DM water is made from materials not affected by corrosive water,
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
29/111
29
such as PVC. The piping and valves are generally of stainless steel. Sometimes, a steam
blanketing arrangement or stainless steel doughnut float is provided on top of the water in the tank
to avoid contact with air.DM water make-up is generally added at the steam space of the surface
condenser (i.e., the vacuum side). This arrangement not only sprays the water but also DM water
gets deaerated, with the dissolved gases being removed by an air ejector attached to the condenser
2.3.6.9: Steam turbine-driven electric generator:Rotor of the modern steam turbine, used in a
power station.
Turbo generator:
Fig: 2.4 Turbo generator
The steam turbine-driven generators have auxiliary systems enabling them to work satisfactorily
and safely. The steam turbine generator being rotating equipment generally has a heavy, large
diameter shaft. The shaft therefore requires not only supports but also has to be kept in position
while running. To minimize the frictional resistance to the rotation, the shaft has a numbering of
bearings. The bearing shells, in which the shaft rotates, are lined with a low friction material like
Babbitt metal. Oil lubrication is provided to further reduce the friction between shaft and bearing
surface and to limit the heat generated.
2.3.6.10: Bearing gear:
Barring gear (or turning gear) is the mechanism provided to rotate the turbine the turbine
generator shaft at a very low speed after unit stoppages. Once the unit is tripped (i.e., the steam
inlet valve is closed), the turbine coasts down towards standstill. When it stops completely, there
is a tendency for the turbine shaft to deflect or bend if allowed to remain in one position too long.This is because the heat inside the turbine casing tends to concentrate in the top half of the casing,
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
30/111
30
making the top half portion of the shaft hotter than the bottom half. The shaft therefore could
wrap or bend by millionths of inches.
This small shaft deflection, only detectable by eccentricity meters, would be enough to cause
damaging vibrations to the entire steam turbine generator unit when it is restarted. The shaft is
therefore automatically turned al low speed (about one percent rated speed) by the barring gear
until it has cooled sufficiently to permit a complete stop.
Condenser:
Fig: 2.5 Diagram of a typical water cooled surface condenser.
The surface condenser is a shell and tube heat exchanger in which cooling water is circulated
through the tubes. The exhaust steam from the low pressure turbine enters the shell where it is
cooled and converted to condensate (water) by flowing over the tubes as shown in the adjacent
diagram. Such condensers use steam ejectors or rotary motor-driven exhausters for continuous
removal of air and gases from the steam side to maintain vacuum. For best efficiency, the
temperature in the condenser must be kept as low as practical in order to achieve the lowest
possible pressure in the condensing steam. Since the condenser temperature can almost always be
kept significantly below 1000c where the vapor pressure of water is much less than atmospheric
pressure, the condenser generally works under vacuum. Thus leaks of non condensable air into the
closed loop must be prevented. Plants operating in hot climates may have to reduce output if their
source of condenser cooling water becomes warmer; unfortunately this usually coincides with
periods of high electrical demand for air conditioning. The condenser generally uses either
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
31/111
31
circulating cooling water from a cooling tower to reject waste heat to the atmosphere or once-
through water from a river, lake or ocean
Feed water heater:
Fig: 2.6 A Ranking cycle with a two stage steam turbine and a single feed water heater.
In the case of a conventional steam-electric power plant utilizing a drum boiler, the surface
condenser removes the latent heat of vaporization from the steam as it changes states from vapor
to liquid. The heat content (btu) in the steam is referred to as Enthalpy. The condensate pump then
pumps the condensate water through a feed water heater The feed water heating equipment then
raises the temperature of the water by utilizing extraction steam from various stages of the
turbine, Preheating the feed water reduce the irreversibility involved in steam generation and
therefore improves the thermodynamic efficiency of the system,[9] This reduces plant operatingcost and also helps to avoid thermal shock to the boiler metal when the feed water is introduced
back into the steam cycle
2.3.6.11: Super heater:
As the steam is conditioned by the drying equipment inside the drum, it is piped from the upper
drum area into an elaborate set up of tubing different areas of the boiler. The areas known as super
heater and re-heater, the steam vapor picks up energy and its temperature is now superheated
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
32/111
32
above the saturation temperature. The superheated steam is then piped through the main steam
lines to the valves of the high pressure turbine
Deaerator:
Fig: 2.7 Boiler feed water deaerator.
A steam generating boiler requires that the boiler feet water should be devoid of air and other
dissolved gases, particularly corrosive ones, in order to avoid corrosion of the metal. Generally,
power station use a deaerator to provide for the removal of air and other dissolved gases from the
boiler feed water. A deaerator typically includes a vertical, domed deaeration section mounted on
top of a horizontal cylindrical vessel which serves as the deaerated boiler feed water storage tank.
There are many different designs for a deaerator and the designs will vary from one manufacturer
to another. The adjacent diagram depicts a typical conventional traded deaerator. If operated
properly; most deaerator manufacturers will guarantee that oxygen in the deaerated water will not
exceed 7 ppb by weight (0.005 cm3
/L).
2.3.6.12: Auxiliary systems:
Oil system:An auxiliary oil system pump is used to supply oil at the start-up of the steam turbine
generator. It supplies the hydraulic oil system required for steam turbines main inlet steam stop
valve, the governing control valves, the bearing and seal oil systems, the relevant hydraulic relays
and other mechanisms. At a preset speed of the turbine during start-ups, a pump driven by the
turbine main shaft takes over the functions of the auxiliary system.
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
33/111
33
Generatorheat dissipation:The electricity generator requires cooling to dissipate the heat that it
generators. While small units may be cooled by air drawn through filters at the inlet, lager units
generally require special cooling arrangements. Hydrogen gas cooling, in an oil sealed casing, is
used because it has the highest known heat transfer coefficient of any gas and for its low viscosity
which reduces winding losses. This system requires special handling during start up, with air in
the chamber first displaced by carbon dioxide before filing with hydrogen ensures that the highly
flammable hydrogen does not mix with oxygen in the air.
The hydrogen pressure inside the casing is maintained slightly higher than atmospheric pressure
to avoid outside air ingress. The hydrogen must be sealed against outward leakage where the shaft
emerges from the casing. Mechanical seals around the shaft are installed with a very small annular
gap to avoid rubbing between the shaft and the seals. Sal oil is used to prevent the hydrogen gas
leakage to atmosphere.
The generator also uses water cooling. Since the generator coils are at a potential of about 22 KV
and water is conductive, an insulting barrier such as Teflon is used to interconnect the water line
and the generator high voltage windings. Dematerialized water of low conductivity is used.
Generator high voltage system: The generator voltage ranges from 11 KV in smaller unit to 22
KV in larger units. The generator high voltage leads are normally large aluminum channelsbecause of their high current as compared to the cables used in smaller machines. They are
enclosed in well-grounded aluminum bus ducts and are supported on suitable insulators. The
generator high channels are connected to step-up transformers for connecting to a high voltage
electrical substation (of the order of 115 KV to 520 KV) for further transmission by the local
power grid. The necessary protection and metering devices are included for the high voltage
leads. Thus, the steam turbine generator and the transformer from one unit. In smaller units,
generating at 11 KV, a breaker is provided to connect it to a common 11 KV bus system
2.3.6.13: Other Systems:
Monitoring and alarm system: Most of the power plant operational control is automatic.
However, at times, manual intervention may be required. Thus, the plant is provided with
monitors and alarm systems that alert the plant operators when certain operating parameters are
seriously deviating from their normal range.
Battery supplied emergency lighting and communication: A central battery system consistingof lead acid cell units is provided to supply emergency electric power, when needed, to essential
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
34/111
34
items such as the power plants control systems, communication systems, turbine lube oil pumps,
and emergency lighting. This is essential for a safe, damage-free shutdown of the units in an
emergency situation.
Transport of coal fuel to site and to storage: Most thermal stations use coal as the main fuel.
Raw coal is transported from coal mines to a power site by trucks, barges, bulk cargo ships or
railway cars. The coal received at site may be off different sizes. The railway cars are unloaded at
site by rotary dumpers or side till dumpers to tip over onto conveyors conveyor belt below. The
coal is generally conveyed to crush the coal to about inch (6mm) size. The crushed coal is then
sent by belt conveyors to a storage pile. Normally, the crushed coal is compacted by bulldozers, as
compacting of highly volatile coal avoids spontaneous ignition.
2.3.7 EFFICIENCY OF STEAM POWER PLANT
There are two types of efficiency in thermal power plant.
I) Thermal efficiency
II) Overall efficiency.
Thermal efficiency:
The ratio of heat equivalent of mechanical energy transmitted to the turbine shaft to the heat of
combustion of coal is known as Thermal efficiency of steam power station
2.4 HYDRO-ELECTRIC POWER STATION
A generating station which utilizes the potential energy of water at a high level for the generation
of electrical energy is known as hydro-electric power station
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
35/111
35
Fig: 2.8 Schematic arrangement of a hydro-electric power station.
2.4.1 CHOICE OF SITE FOR HYDROELECTRIC POWER STATIONS
The following points should be taken into account whole selecting the site for a hydro electric
power station.
1. Availability of water: Such plants should be built at a place where adequate water is
available at a good head due to the primary requirement of a hydro-electric power station
is the availability of huge quantity of water.
2. Storage of water: There are wide variations in water supply from a river or canal during
the year. This makes it necessary to store water by constructing a dam. Site selection for a
hydro-electric power plant should be provides adequate facilities for erecting a dam and
storage of water.
3.
Cost and type of land: the land for the construction of the plant should be available at a
reasonable price. The bearing capacity of the ground should be adequate to withstand the
weight of heavy equipment to be installed.
4. Transportation facilities:the site selection for a hydro-electric plant should be accessible
by rail, river and road. So that necessary equipment and machinery could be easily
transported.
2.4.2 ADVANTAGES OF HYDRO-ELECTRIC POWER STATION
1. It is neat and clean as no smoke or ash is produced
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
36/111
36
2. It has a longer life.
3. It required very small running charges because water is available free of cost.
4. As compare to steam power station, it does not require a long starting time.
5. Such plants serve many purposes. In additional to the generation of electrical energy,
they also help in irrigation and controlling flood.
6. No fuel is burnt.
2.4.3 DISADVANTAGE OF HYDRO-ELECTRIC POWER STATION
1. Capital cost is high as compare to other stations.
2. Skilled and experienced hands are required to build the plant.
3. Transmission cost is high as the plant is located in hilly areas which are quite away from
the consumers.
4. Uncertainty about the availability of huge amount of water due to dependence on
weather conditions.
2.4.4 CONSTITUENTS OF HYDRO-ELECTRIC PLANT:
a) Dam: A dam is a barrier, which stores water and creates water heads. Dams are building
of concrete or stone -masonry, earth or rock field. The type and arrangement depend
upon the topography of site. The type of dam also depends upon the type of foundation
conditions local materials and transportations available, occurrence of earthquakes and
other hazards.
b) Spillways: In order to discharge the surplus water the storage reservoir in to the river on
the down-steam side of the dam, spillways are used.
c)
Head work:The head works consists of diversion structures at the head of an intake.
The generally include booms and racks for the diverting floating debris, sluices for by
passing debris and sediments and valves for the controlling the follow of water to the
turbine.
d) Surge tank: A surge tank is a small reservoir or tank in which water level rises or falls
to reduce the pressures swings in the conduit. A surge tank is located near the beginning
of the conduit. When the load on the turbine decreases, then increases the water level of
the surge tank and reversal.
e)
Penstocks:Penstocks are conduits, which carry water to the turbines; they are generally
made of reinforced concrete or steel. Various devices such as automatic butterfly valve,
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
37/111
37
air valve and surge tank are provided for the protection of penstocks. Automatic
butterfly valve shuts off water flow through the penstocks promptly if it raptures. Air
valve maintains the air.
1. For high head.
2. Reaction turbine- for low and medium head
f)
Electrical equipments: This includes alternators, transformers, circuit breaker and other
switching and protective devices.
2.5 NEUCLEAR POWER STATION
A generating station in which nuclear energy is converted into electrical energy is known as a
nuclear power station. In nuclear power station, heavy elements such as Uranium (U-235) or
thorium (Th-232) are subjected to nuclear fission in a special apparatus known as a reactor. The
energy thus related is utilized in raising steam at high temperature and pressure. The steam runs
the turbine which converts energy into mechanical energy. The turbine drives the alternator which
converts mechanical energy into electrical energy.
2.5.1 SELECTION OF SITE FOR NUCLEAR POWER STATION
1. Availability of water: as sufficient water is required for cooling purposes, therefore, the
plant side should be located where ample quantity of water is available, e.g., across a river
or by sea side
2. Disposal if water: the waste produce by the fission in a nuclear power station is generally
radioactive which must be disposed of properly to avoid health hazards. The waste should
either be buried in a deep trench or disposal off in sea quite away from the sea short.
Therefore, the site selected for such a plant should have adequate arrangement for the
disposal of radioactive waste
3.
Steam turbine: the steam produce in the heat exchange is led to steam turbine through a
valve. After doing a useful work in the turbine, the steam is exhausted to condenser. The
condenser condenses the steam which is fed to the heat exchanger through feed water
pump.
4. Alternator: The steam turbine drives the alternator which converts mechanical energy
into electrical energy. The output from the alternator is delivered to the bus-bares through
transformer, circuit breaker and isolators.
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
38/111
38
2.5.2 ADVANTAGES OF NUCLEAR POWER STATION
1. The amount of fuel required is quite small. Therefore, there is a considerable saving in
the cost of fuel transportation?
2. A nuclear power plant requires less space as compared to any type of the same size.
3. It has low running charges as a small amount of fuel is used to producing bulk electrical
energy.
4. This type of plant is very economical for producing bulk electrical energy.
5. It can be located near the load centers because it does not require large quantities of
water and need not be near coal mines. Therefore, the cost of primary distribution is
reduced.
6. There are large deposits of nuclear fuels available all over the world .Therefore, such
plant can ensure continued supply of electrical energy for thousands of years.
7. It ensures reliability of operation.
2.5.3 DISADVANTAGES OF NUCLEAR POWER STATION
1. The fuel used is expensive and difficult to recover.
2. The capital cost on a nuclear plant is very high as compared to other types of plants.
3. The erection and commissioning of the plant requires greater technical knowhow.
4. The fission by products is generally radioactive and may cause a dangerous amount of
radioactive pollution.
5. Maintenance charges are high due to lack of standardization.
6. Nuclear plants are not well suited for varying loads as the reactor does not respond to the
load efficiently.
7. The disposal of the by products, which are radioactive, is big problem. They have either
to be disposed off in a deep trench or in a sea away from sea shore.
2.5.4 SCHEMATIC ARRANGEMENT OF NUCLEAR POWER STATION
The schematic arrangement of a nuclear power station is shown in fig. the whole arrangement can
be divided into the following main stages:
1. Nuclear reactor
2. Heat exchange
3. Steam turbine
4. Alternator
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
39/111
39
Fig: 2.9 Schematic Arrangement of a Nuclear power Station.
Nuclear reactor:It is an apparatus in which nuclear fuel (U-235) is subjected to nuclear fission.
It control is the chain reaction that start once the fission is done. If the chain reaction is not
controlled, the result will be an explosion due to the fast increase in the energy released.
Chain reaction: nuclear fission is done by bombarding Uranium nuclei with slow moving
neutrons. This splits the Uranium nuclei with the release of huge amount of energy and emission
of neutrons. This fissions neutron cause further fission. If this process continues, then in a very
short time huge amount of energy will be released which may cause explosion. This is known as
explosive chain reaction. But in a reactor, controlled chain reaction is allowed. This is done by
systematically removing the fission neutrons from the reactor. The greater the number of fission
neutrons removes, the lesser is intensive of energy of released.
1. Heat exchanger: The coolant gives up heat exchanger which is utilized in raising
the steam. After giving up the heat, the coolant is again fed to the reactor.
2. Steam turbine:The steam produced in the heat exchanger led to the steam turbine
through a valve after doing useful work in the turbine, the steam is exhausted to
condenser. The condenser condenses the steam which is feed to the heat exchanger
through feed water pump
3. Alternator: The steam turbine drives the alternator which converts mechanical
energy into electrical. The output from the alternator is delivered to the bus-bars
through transformer, circuit breakers and isolators.
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
40/111
40
2.6 DISEL POWER STATION
A generating station in which diesel engine is used as the prime mover for the generation of
electrical energy is known as diesel power station.
2.6.1 CHOICE OF SITE FOR DIESEL POWER STATION
1. Distance from load center [the plant should be located nearby the load center to be
minimum transmission loss].
2. Availability of water.
3. Foundation condition. [A foundation at a reasonable depth should be capable of
providing a strong support to the engine].
4. Fuel transportation. [Plant should be near to the source of fuel supply so thattransportation charges are low].
5. Access to site. [The site selected should have road and rail transportation facilities].
2.6.2 ADVANTAGES OF DIESEL POWER STATION
a) It requires less space as compare to other stations.
b) The design and layout of this plant are very simple.
c)
For cooling system less quantity of water is required.d) It can be located at any place.
e) There are no standby losses.
f)It can be started quickly.
g) It requires less operating staff.
2.6.3 DISADVANTAGES OF DIESEL POWER STATION
a) This plant can generate small power.
b) The fuel cost is high.
c) This plant does not work for a longer period.
d) The cost of lubricating is high.
e) The maintenance charges are high.
f) It pollutes the atmosphere.
g) It makes a noise.
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
41/111
41
2.6.4 SCHEMATIC ARRANGEMENT OF DIESEL POWER PLANT
Fig: Schematic diagram of a diesel power Station.
Fig: 2.10 Schematic Arrangement of a Diesel Power Plant
2.7 GAS TURBINE POWER STATION
A generating station which employs gas turbine as the prime mover for the generation of electrical
energy is known as a gas turbine power plant.
2.7.1 ADVANTAGES OF GAS TURBINE POWER STATION
a) It is simple in design.
b) It is much smaller in size.
c) Initial and operating costs are lower than other.
d) The maintenance charges are quite small.
e) There is no stand by losses.
2.7.2 DISADVANTAGES OF GAS TURBINE POWER STATION
a.There is a problem for starting the unit.
b. Since a greater part of power developed by the turbine is used in driving the
compressor, the net output is low
c.It pollutes the atmosphere.
d. The overall efficiency of such plants is low.
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
42/111
42
2.7.3 SCHEMATIC ARRANGEMENT OF A GAS TURBINE POWER PLANT
Fig: 2.11 Schematic arrangement of a gas turbine power plant.
2.7.4 THE MAIN COMPONENT OF THE PLANTS
a)
Compressor: The compressor draws the air via the filter, which removes the dust from
air. The rotary blades of the compressor push the air between stationary blades to raise
its pressure. Thus air at high pressure is available at the output of the compressor.
b) Regenerator:A regenerator is a device, which recovers heat from the exits gases of the
turbine. A regenerator consists of nest of tubes contained in a shell. The compressed air
from the compressor passes through the tubes on its way to the combustion chamber. In
this way compressed air is heated by the exhaust gases.
c)
Combustion chamber: The air at high pressure from the compressor is led to thecombustion chamber via the regenerator. In the combustion chamber heat is added to the
air by burning oil/gas. The result is that the chamber attains a very high temperature. The
combustion gases are suitably cooled to 70000c-8000c and then delivered to the gas
turbine.
d) Gas turbine: The product of combustion comprising of a mixture of gases at high
temperature and pressure are passed to the gas turbine. These gases in passing over the
turbine blades expand and thus do the mechanical work. The temperature of the exhaustgases from the turbine is about 4800c
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
43/111
43
e) Alternator: The gas turbine is coupled to the alternator. The alternator converts
mechanical energy of the turbine into electrical energy.
f)Starting Motor: Before starting the turbine, compressor has to be started. For this
purpose, an electrical motor is mounted on the same shaft of the turbine. This is
energized by the batteries. Once the unit starts, a part of mechanical power of the drives
the compressor and there is no need of motor now.
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
44/111
44
CHAPTER-3
POWER GENERATION IN BANGLADESH
3.1 GENERATING VOLTAGE OF DIFFERENT POWER STATION
15.75kv
11kv
10.5kv
6.6kv
3.2 POWER DEMAND
The peak demand for January 2012 is 7,518 MW as per update power system master plan
(PSMP-2010). The maximum demand serves 5036.50 MW.
3.3 LOAD FACTOR AND LOAD MANAGEMENT
Consumer demand in BPDB system, as in any other electric utility varies throughout the day &
night. The maximum occurs during 5 PM to11 PM termed as peak hour. The extent of this
variation is measured in terms of load factor, which is the ratio of average & maximum demand,
for economic reason it is desirable to have a high load factor as this would permit better utilization
of plant capacity. The cost of energy supply during peak hour is high as some relatively costlier
power plants are required to be used during peak hour.
3.4 INSTALLED CAPACITY
Although the total installed capacity was 5493MW including 1330MW in IPP and 351MW in
internal power plant (Excluding REB).the maximum availability were
(1)Some plants were out of operation due to maintenance, rehabilitation &overhauling.
(2) Capacities of some plants were de-rated due to aging and Gas shortage.
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
45/111
45
3.5Owner Wise Daily Generation:
Table : 01
Owner Name Derated Capacity (MW) Day Peak (MW) Eve. Peak (MW)
Generation of 21/04/2014
PDB 3502.00 1648.00 1972.00
SBU,PDB 223.00 194.00 201.00
EGCB 622.00 235.00 417.00
APSCL 682.00 468.00 465.00
IPP 1617.00 1165.00 877.00
SIPP,PDB 110.00 89.00 90.00
RENTAL(3 yrs) 33.00 0.00 0.00
SIPP,REB 215.00 160.00 175.00
Q.Rental 3 Years 100.00 95.00 100.00
QRPP(5yrs) 200.00 181.00 192.00
Other 825.00 650.00 581.00
RPP (3 Yrs.) 1069.00 740.00 780.00
QRPP (3 Yrs.) 416.00 335.00 380.00
RPP (15 Yrs.) 169.00 140.00 146.00
Total 9783.00 6100.00 6376.00
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
46/111
46
3.5.1 Installed Capacity of BPDB Power Plants as on April 2014.
Capacity Type: Power Generation Units (Fuel Type Wise)
Installed Capacity of BPDB Power Plants as on April 2014
Unit Type Capacity(Unit) Total(%)
Coal 250.00 MW 2.44 %
FO 0.00 MW 0 %
Gas 6615.00 MW 64.59 %
HFO 1963.00 MW 19.17 %
HSD 683.00 MW 6.67 %
Hydro 230.00 MW 2.25 %
Imported 500.00 MW 4.88 %
Total 10241.00 MW 100 %
De rated Capacity of BPDB Power Plants as on April 2014
Unit Type Capacity(Unit) Total(%)
Coal 200.00 MW 2.04 %
FO 52.00 MW 0.53 %Gas 6224.00 MW 63.62 %
HFO 1926.00 MW 19.69 %
HSD 661.00 MW 6.76 %
Hydro 220.00 MW 2.25 %
Imported 500.00 MW 5.11 %
Total 9783.00 MW 100 %
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
47/111
47
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
48/111
48
Daily Generation Report
Power Station NameDerated
Capacity(Unit)Day Peak Eve Peak
Daily Generation of 21/04/2014
a) Ghorasal ST 1, 2 78.00 MW 42.00 MW 45.00 MW
Ghorasal ST :Unit-3, 180.00 MW 100.00 MW 100.00 MW
Ghorashal ST 4 180.00 MW 170.00 MW 170.00 MW
Ghorashal 100 100.00 MW 84.00 MW 99.00 MW
Ghorrashal ST 5 190.00 MW 190.00 MW 190.00 MW
Ghorashal ST 6 190.00 MW 0.00 MW 0.00 MW
Ghorashal 45 MW 45.00 MW 43.00 MW 46.00 MW
Ghorashal MAX 78.00 MW 76.00 MW 78.00 MW
Ghorashal Regent 0.00 MW 2.00 MW 0.00 MW
Horipur SBU GT 1,2,3 60.00 MW 0.00 MW 0.00 MW
Horipur NEPC 110.00 MW 93.00 MW 110.00 MW
Horipur P. Ltd CCPP 360.00 MW 246.00 MW 325.00 MW
Meghnaghat P.Ltd CCPP 450.00 MW 440.00 MW 0.00 MW
Meghnaghat Summit 0.00 MW 0.00 MW 0.00 MW
Meghnaghat IEL 100.00 MW 91.00 MW 100.00 MW
Madanganj 102 MW 100.00 MW 95.00 MW 100.00 MW
Karanigonj 100.00 MW 90.00 MW 90.00 MW
Narshingdi 22.00 MW 16.00 MW 18.00 MW
Shiddirganj ST 150.00 MW 0.00 MW 0.00 MW
Siddirgonj GT 1,2 210.00 MW 0.00 MW 0.00 MW
Siddirgonj 100 MW 96.00 MW 56.00 MW 64.00 MW
Dutch Bangla 100 MW 100.00 MW 90.00 MW 92.00 MW
DPA Power 50 MW 50.00 MW 40.00 MW 46.00 MW
Gahamagar 0.00 MW 0.00 MW 0.00 MW
Horipur EGCB 360MW 412.00 MW 235.00 MW 417.00 MW
Summit Power (Dhaka) 146.00 MW 108.00 MW 116.00 MW
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
49/111
49
Gazipur RPCL 52.00 MW 33.00 MW 32.00 MW
Tongi GT 105.00 MW 0.00 MW 0.00 MW
ChittagongRaozanST(Gas):Unit-1
180.00 MW 120.00 MW 120.00 MW
Raozan 25MW 25.00 MW 26.00 MW 26.00 MW
Patenga 50 MW 50.00 MW 3.00 MW 14.00 MW
ChittagongRaozanST(Gas):Unit-2
180.00 MW 0.00 MW 0.00 MW
Kaptai Hydro:Unit-1,2,3,4,5 220.00 MW 41.00 MW 106.00 MW
Shikalbaha ST 40.00 MW 0.00 MW 0.00 MW
b) Shikalbaha Peaking (GT) 150.00 MW 110.00 MW 120.00 MW
Hathazari 98.00 MW 23.00 MW 88.00 MW
Shikalbaha(Energis) 0.00 MW 0.00 MW 0.00 MW
Dohazari Sangu 102.00 MW 34.00 MW 51.00 MW
Julda 100.00 MW 80.00 MW 102.00 MW
Malancha, Ctg. EPZ(United)
0.00 MW 0.00 MW 23.00 MW
Barabkunda (Regent) 22.00 MW 17.00 MW 17.00 MW
a) Ashuganj ST Unit -1,2 110.00 MW 40.00 MW 40.00 MWb) Ashuganj ST 3 140.00 MW 140.00 MW 140.00 MW
Ashugonj ST 4 150.00 MW 140.00 MW 140.00 MW
Ashugonj ST 5 140.00 MW 80.00 MW 80.00 MW
c) Ashuganj CCPP-146MW 91.00 MW 40.00 MW 40.00 MW
d) Ashuganj 50 MW 51.00 MW 28.00 MW 25.00 MW
Ashuganj (Precision) 55.00 MW 51.00 MW 57.00 MW
Ashuganj (Aggreko) 80.00 MW 77.00 MW 82.00 MWAshugonj Up-53 MW 53.00 MW 53.00 MW 53.00 MW
Ashuganj Midland 51.00 MW 0.00 MW 0.00 MW
Brahmanbaria (Agrico)(Gas)
70.00 MW 70.00 MW 72.00 MW
Daudkandi 50 MW 52.00 MW 0.00 MW 49.00 MW
Chandpur CCPP 163.00 MW 155.00 MW 0.00 MW
Feni (Doreen) 22.00 MW 17.00 MW 18.00 MW
Feni, Mahipal (Doreen) 11.00 MW 8.00 MW 5.00 MW
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
50/111
50
Jangalia (Summit) 33.00 MW 32.00 MW 32.00 MW
Summit Power, Comilla 25.00 MW 18.00 MW 21.00 MW
RPCL,CCPP, Mymensingh 197.00 MW 146.00 MW 145.00 MW
Tangail (Doreen) 22.00 MW 15.00 MW 18.00 MW
Fenchuganj CCPP-1 (Gas) 90.00 MW 66.00 MW 68.00 MW
Fenchuganj CCPP-2(New) 104.00 MW 84.00 MW 82.00 MW
Fenchuganj (BEDL) 51.00 MW 42.00 MW 42.00 MW
Fenchuganj Prima 50 MW 50.00 MW 46.00 MW 50.00 MW
Hobiganj (Confidence-EP) 11.00 MW 10.00 MW 10.00 MW
Shajibazar GT Unit-8, 9 66.00 MW 63.00 MW 68.00 MW
Shajibazar 86 MW 86.00 MW 74.00 MW 74.00 MW
Shajibazar - 50 MW 50.00 MW 45.00 MW 47.00 MW
Sylhet 150MW 142.00 MW 0.00 MW 108.00 MW
Sylhet GT (Gas) 20.00 MW 17.00 MW 19.00 MW
Sylhet 50 MW 50.00 MW 41.00 MW 44.00 MW
Sylhet 11 MW 10.00 MW 7.00 MW 9.00 MW
Shahjahanulla 25mw 25.00 MW 14.00 MW 24.00 MW
Bheramara GT (Unit-1,2,3) 46.00 MW 32.00 MW 32.00 MW
Bheramara 105.00 MW 0.00 MW 0.00 MW
a)Khulna ST 110 MW 55.00 MW 0.00 MW 58.00 MW
HVDC C/B. Interconnector 500.00 MW 403.00 MW 304.00 MW
b)Khulna ST 60MW 30.00 MW 0.00 MW 0.00 MW
KPC, Khulna 110.00 MW 53.00 MW 100.00 MW
KPCL Khulna (New) 115.00 MW 99.00 MW 99.00 MW
Khulna 150 MW 150.00 MW 156.00 MW 158.00 MW
Faridpur 54.00 MW 19.00 MW 45.00 MW
Gopalganj 110 MW 109.00 MW 0.00 MW 32.00 MW
Noapara (105MW)Quantam
101.00 MW 0.00 MW 0.00 MW
Noapara (40MW),KZA 40.00 MW 40.00 MW 40.00 MW
Khulna 40 MW 40.00 MW 0.00 MW 0.00 MW
Khulna 55 MW 55.00 MW 42.00 MW 53.00 MW
Barisal Diesel(HSD) 0.00 MW 0.00 MW 0.00 MW
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
51/111
51
Barisal GT 1& 2 32.00 MW 15.00 MW 15.00 MW
Bhola Venture 33.00 MW 0.00 MW 0.00 MW
a)Baghabari GT 1 71.00 MW 67.00 MW 69.00 MW
b)Baghabari GT 2 100.00 MW 95.00 MW 100.00 MW
Baghabari 50 MW 52.00 MW 32.00 MW 32.00 MW
Baghabari Westmont 70.00 MW 0.00 MW 0.00 MW
Bera 70 MW 71.00 MW 67.00 MW 70.00 MW
Amnura 50 MW 50.00 MW 51.00 MW 50.00 MW
Khtakhali NPS 50MW 50.00 MW 50.00 MW 50.00 MW
Katakhali PPP 50 MW 50.00 MW 18.00 MW 46.00 MW
Sirajganj 150 MW 150.00 MW 75.00 MW 72.00 MW
Santahar 50MW 50.00 MW 46.00 MW 46.00 MW
Bogra GBB 22.00 MW 17.00 MW 21.00 MW
Rajlanka 52MW 52.00 MW 52.00 MW 52.00 MW
Barupukuria ST 1 100.00 MW 90.00 MW 90.00 MW
Barupukuria ST 2 100.00 MW 92.00 MW 93.00 MW
Bogra 20 MW 20.00 MW 9.00 MW 9.00 MW
Summit Powser(Ullapara) 11.00 MW 8.00 MW 10.00 MW
Rangpur GT (HSD) 20.00 MW 10.00 MW 17.00 MW
Syedpur GT 20MW(HSD) 20.00 MW 18.00 MW 18.00 MW
Thakurgaon 47 MW((RZ) 47.00 MW 31.00 MW 28.00 MW
Total 9783.00 MW 6100.00 MW 6376.00 MW
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
52/111
52
CHAPTER 4
TRANSMISSION SYSTEM OF BANGLADESH
4.1 TRANSMISSION SYSTEM
The system by which the electrical power transmitted from generating station to distribution
system is known as transmission system. The transmission line divided in two parts:
1. Primary transmission
2. Secondary transmission
4.2 PRIMARY TRANSMISSION
The electric power at 132 KV is transmitted by 3-phase 3-wire over head system to the outskirts
of the city. This form is the primary transmission.
4.2.1 GRID SYSTEM
The entire AC network is interconnected network called national grid. Even neighboring national
grid are interconnected to from sub grid. In power system when all generating station line with the
operation of substation called grid system of electric power.
In the grid system of Bangladesh power development board, mainly two types of transmission
lines are used. These are 230KV and 132KV lines. Also there is another grid line of Bangladesh
i.e. 66KV.
4.2.2 GRID SUB-STATION
As in Bangladesh there are two types of grid transmission line, one 132KV line and other 230KV
line. So we have mainly two categories grid substation. The total number of grid substation
operated as of 2012 is 95, of which13 number are 230KV and 82 numbers are 132KV. Capacity
of 230KV grid substation is 6675MVA and 132KV is 8587MVA and their transmission length are
2647.3 circuit km and 6071.34 circuit km
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
53/111
53
4.3 SECONDARY TRANSMISSION
The primary transmission line terminates at the receiving station which usually lies as the
outskirts of the city. At the receiving station, the voltages are reduced to 33KV by step down
transformers. From this station, electric power is transmitted at 33KV by three phase three wire
overhead system to various sub stations located at the strategic points in the city. This form is the
secondary transmission.
4.4 CLASSIFICATION OF OVERHEAD TRANSMISSION LINE
The overhead transmission lines are classified as
a) Short transmission line
b) Medium transmission line
c) Long transmission line
a) Short transmission line:When the length of an overhead transmission line is up to 50km and
the line voltage is comparatively high (20KV 100KV), it is usually considered as a Long
transmission line.
4.5 DEFINATION OF IMPORTANT TERMS:
1. Earthling or grounding: Connecting to earth or ground.
2. Neutral earthing: Connecting to earth, the neutral point i.e. the star point of generator,
transformer, rotating machine, neutral point of grounding transformer.
3. Reactance earthling: Connecting to the neutral point to earth through a reactance.
4. Resistance earthling: Connecting to the neutral point to earth through a resistance.
5. Non effecting earthling: when an intentional resistance or reactance is connected between
neutral point and earth.
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
54/111
54
6. Solid earth or effective earth line: Connecting to the neutral point to earth without
intentional resistance or reactance co-efficient earthling.
7. Resonant earthing: Earthing through a reactance of such as value that power frequency
current in the neutral to ground connection almost equal opposite to power frequency
capacitance current between unsalted line and earth.
8. Co-efficient of ear thing: it is defined as the ratio of highest r.m.s voltage of healthy line to
earth to the line r.m.s voltage.
9. Petersen coil, suppression coil, ground fault neutralized: All the three terms have the same
meaning the adjustable reactor connected between neutral to earth.
10.Underground system: The system whose neutral point is not earth.
11.Earth fault factor: It is calculated at the selected point of the system for a given system. It
is a ratio of fault factor =V1/V2.
Where,
V1 = highest r.m.s phase to phase power frequency voltage of sound
phase during earth fault on another phase.
V2= r.m.s phase to phase power frequency voltage at the same
location with fault on the faulty removed.
12.Bus coupling transformer: it is a special kind of transformer using in electric power
transmission line. It is a bidirectional device that makes injection or taking electric power
between two buses. It is also a matching or interfacing transformer between two buses.
13. Bus: There are three kinds of buses in power system
a) PQ bus b) PV bus and c) Stack or swing or reference bus.
For studying and analyzing an electric bus, we have to need for important variables.They are:
a) P-active power b) Q-reactive power
c) V-voltage and d) -swing angle
4.6 ADVANTAGE OF HIGH VOLTAGE TRANSMISSION LINE
The transmission of electric power is carried at high voltage due to the following reason:
a) To reduce the volume of conductor material.
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
55/111
55
b) To increase the transmission efficiency and
c) To decrease the percentage line drop
4.7 ADVANTAGES AND DISADVANTAGES OF HIGH VOLTAGE DC
TRANSMISSION
Advantages:
i. It requires only two conductors as compared to three for ac transmission.
ii. There is no inductance, capacitance, phase displacement and surge problem in dc
transmission.
iii. A dc transmission. Line has better voltage regulation as compared to the line for same load
and sending voltage.
iv. There is no skin effect in dc system.
v. A dc line requires less insulation as compared to ac line for the same working voltage.
vi. A dc line has less corona loss and interference with communication circuit.
vii. The high voltage dc transmission is free from the dielectric losses, particularly in the case
of cables and
viii. In dc transmission, there is no stability problem and synchronizing difficulties.
Disadvantages:
i. Electric power cannot be generated at high voltage dc due to commutation problems.
ii. The dc voltage cannot be stepped up for transmission of power at high voltages and
iii. The dc switches and circuit breaker have their own limitations.
4.8 TRANSMISSION SYSTEM OF DIFFERENT COUNTRIES
4.8.1 TRANSMISSION SYSTEM OF INDIA:
Bulk transmission system has increased to more than 165000 Circuit kmtoday. The entire country
has been divided into five regions for transmission systems. Namely:
1. Northern region
2. North Eastern region
3. Eastern region
8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH
56/111
56
4. Southern region
5. Western region
Indias transmission system comprises a 400KV network as the main and bulk transmission
system at each region, 132KV and 110KV network as the main and support transmission systems
in each state, 66KV, 33KV and 22KV network as sub transmission system, frequent power cuts,
unscheduled shut downs and severe restrictions on industrial usage during summer months are
constraint on industrial development and overall economic development of the country. In this
context, POWERGRID is involved in along term plan for the development of an Indian national
transmission network to make efficient usage of generating capacity. As part of this strengthening
of the national grid, POWERGRID had developed series of high voltage direct current (HVDC)
inter regional links between North, East, South and westerns of Indias power system.
4.8.2 TRANSMISSION SYSTEM OF SRILANKA
Transmission voltage levels:
a) 220KV
b) 132KV
Transmission lines
220 KV----------------331km
132KV-----------------1684km
Grid substations NO. MVA
132/33KV 40 2570
220/132/33KV 6 2205
132/11KV 4 306
4.8.3 TRANSMISSION SYSTEM OF NEPAL
Nepal transmission voltage