STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

Embed Size (px)

Citation preview

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    1/111

    1

    This Thesis is submitted in Partial Fulfillment for the

    Requirement of the Degree of Bachelor of Science in

    Electrical & Electronic Engineering

    Course Code: EEE-499

    STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION &

    DISTRIBUTION IN BANGLADESH

    Prepared By:

    1. Jagadish Chandra Sutradhar ID # 112-0070-511

    2. Md. Sharif Hossain ID # 112-0164-511

    3. Syed Shawkat Aziz ID # 112-0011-511

    4. Mohammad Ali Hasan ID # 112-0135-511

    5. Md. Jakir Hossain ID # 122-0197-511

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    2/111

    2

    STUDY OF ELECTRICAL POWER GENERATION, TRANSMISSION &

    DISTRIBUTION IN BANGLADESH

    A Project / internship / thesis report submitted to the department of EEE, Atish

    Dipankar Biggayan O Projokti Bishawbiddaloy for partial fulfillment of the Degree

    of B.Sc in Electrical and Electronic Engineering.

    Submitted By:

    1. Jagadish Chandra Sutradhar ID # 112-0070-511

    2. Md. Sharif Hossain ID # 112-0164-511

    3. Syed Shawkat Aziz ID # 112-0011-511

    4. Mohammad Ali Hasan ID # 112-0135-511

    5. Md. Jakir Hossain ID # 122-0197-511

    Supervised By:

    Marzia Hoque Signature :

    Date:

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    3/111

    3

    Declaration

    It is here by declared that no part of this thesis bearers the copyright violation and no plagiarism

    opted during the course of material preparation. The entire works has been planned and carried

    out under the thesis supervisor of the honorable faculty member Marzia Haque department of

    Electrical and Electronic Engineering, Atish Dipankar Biggayan O Projokti Bishawbiddaloy,

    Dhaka, Bangladesh.

    The content of this thesis is submitted by the groupName : Jagadish Chandra Sutradhar, ID #

    112-0070-511, Name : Md. Sharif Hossain ID # 112-0164-511, Name : Syed Shawkat Aziz ID

    # 112-0011-511, Name : Mohammad Ali Hasan ID # 112-0135-511, Name : Md. Jakir

    Hossain ID # 122-0197-511.

    Only for the fulfillment of the course ofSTUDY OF ELECTRICAL POWER

    GENERATION, TRANSMISSION DISTRIBUTION IN BANGLADESH .And no part

    of this is used anywhere for the achievement of any academic Degree or Certificate.

    Jagadish Chandra Sutradhar

    ID # 112-0070-511

    Department of EEE

    Syed Shawkat Aziz

    ID # 112-0011-511

    Department of EEE

    Md. Sharif Hossain

    ID # 112-0164-511

    Department of EEE

    Mohammad Ali Hasan

    ID # 112-0135-511

    Department of EEE

    Md. Jakir Hossain

    ID # 122-0197-511

    Department of EEE

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    4/111

    4

    Certificate

    This is to certify that the B.Sc. thesis entitled STUDY OF ELECTRICAL POWER

    GENERATION, TRANSMISSION DISTRIBUTION IN BANGLADESH

    . submitted by

    following group:

    This is to certify that the B.Sc thesis entitled STUDY OF ELECTRICAL POWER GENERATION,

    TRANSMISSION DISTRIBUTION IN BANGLADESH

    submitted by following groupName

    : Jagadish Chandra Sutradhar, ID # 112-0070-511, Name : Md. Sharif Hossain ID # 112-

    0164-511, Name : Syed Shawkat Aziz ID # 112-0011-511, Name : Mohammad Ali Hasan ID# 112-0135-511, Name : Md. Jakir Hossain ID # 122-0197-511.

    The thesis represents an independent and original work on the part of the

    candidates. The research work has not been previously formed the basis for the

    award of any Degree, Diploma, Fellowship or any other discipline.

    The whole work of this thesis has been planned and carried out by this group

    under the supervision and guidance of the faculty members of Atish Dipankar

    Biggayan O Projokti Bishawbiddaloy, Bangladesh.

    Marzia Hoque

    LecturerDepartment of Electrical and Electronic EngineeringAtish Dipankar Biggayan O Projokti Bishawbiddaloy

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    5/111

    5

    Transmittal

    Date: 26/05/2014Faculty of Engineering

    Department of EEEAtish Dipankar Biggayan O Projokti BishawbiddaloyDhaka, Bangladesh.

    Subject: letter of transmittal.

    Dear Sir,With due respect, we should like to inform you that is a great pleasure for us to submit the final

    project on STUDY OF ELECTRICAL POWER GENERATION, TRANSMISSION &

    DISTRIBUTION IN BANGLADESHfor Department of Electrical and Electronic Engineering

    as requirement bachelor degree/ program. This project provided us with a practical exposure to

    the overall working environment and very good experience which is prevailing in to professional

    life. We came to know about many things regarding the current world on the concept of

    Electronic Development. We have tried to our best to put through effort for the preparation of this

    report. Any short coming or fault may arise as our unintentional mistake we will whole heartily

    welcome for any clarification and suggestion about any view and conception disseminated

    through this project.

    We hope and strongly believe that this project will meet the requirement as well as satisfying your

    purpose. We will available for any further classification in this regard.

    Sincerely Yours,

    ID # 112-0070-511

    ID # 112-0164-511

    ID # 112-0011-511

    ID # 112-0135-511

    ID # 122-0197-511

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    6/111

    6

    APPORAVAL SHEET

    This project title is STUDY OF ELECTRICAL POWER GENERATION, TRANSMISSION &

    DISTRIBUTION IN BANGLADESH has been submitted to the following respected members of

    the Board of Examiners of the Department of Electrical and Electronic Engineering in partial

    fulfillment of the requirements of the degree of Bachelor of Department of Electrical and

    Electronic Engineering by the following students.

    1. Jagadish Chandra Sutradhar ID # 112-0070-511

    2. Md. Sharif Hossain ID # 112-0164-511

    3. Syed Shawkat Aziz ID # 112-0011-511

    4. Mohammad Ali Hasan ID # 112-0135-511

    5. Md. Jakir Hossain ID # 122-0197-511

    As the supervisor I have approved this paper for submission.

    .. ..

    Marzia Hoque Md.Imam HossainProject Supervisor & Senior Lecturer & CoordinatorLecturer Department of EEEDepartment Of EEE Atish Dipankar Biggayan O AtishDipankar Biggayan O Projokti BishawbiddaloyProjokti Bishawbiddaloy

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    7/111

    7

    ACKNOWLEDGEMENT

    At first we would like to thank our Supervisor Marzia Haque

    (Lecturer) for giving us the opportunity to work to under his supervision, the endless hours of

    help, Suggestions, Advice and Support to keep us on track during the development of this thesis.

    We also want to express gratitude to Mr. Md. Imam Hossainfor his support during our work on

    this thesis.

    Last, but not the least, we would like to thank our parents and family for making it possible for us

    to study and for their constant help and support.

    May, 2014

    1. Jagadish Chandra Sutradhar ID # 112-0070-511

    2. Md. Sharif Hossain ID # 112-0164-511

    3. Syed Shawkat Aziz ID # 112-0011-511

    4. Mohammad Ali Hasan ID # 112-0135-511

    5. Md. Jakir Hossain ID # 122-0197-511

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    8/111

    8

    ABSTRACT

    In this modern world, the dependence on electricity is so much that it has become a part and

    parcel of our life. The development of any country of the world is based on electricity and its

    proper generation, transmission and distribution. For the proper utilization, it is required to

    transmit and distribute the generating electrical power through the proper way.

    For proper power generation, we have to consider the selection of power station according to the

    site selection of the different power station and their advantage and disadvantage.

    In this thesis work, we have discussed about different types of power station, their merits &

    demerits, power generation in Bangladesh, power demand, installed capacity deficiency of power,

    power plant under construction.

    We have also discussed about the transmission and distribution system. Where has been included

    mechanical design of transmission system, electrical design of transmission system, different

    types of transmission loss, remedy of loss. For distribution system, we have included the bhurulia

    distribution sub-station.

    We think that, this study will be very helpful for better understanding about generation and

    transmission system of Bangladesh.

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    9/111

    9

    ABBREVIATIONS & NOTATIONS

    BPDB : Bangladesh Power Development Board

    PGCB : Power Grid Company of Bangladesh Ltd

    DESA : Dhaka Electric Supply Authority

    DESCO : Dhaka Electric Supply Company

    REB : Rural Electrification Board

    LDC : Load dispatch Centre

    A.C : Alternating Current

    D.C : Direct Current

    KVA : Kilo Volt Ampere

    Km : Kilometer

    KV : Kilo Volt

    KW : Kilo Watt

    KWH : Kilo Watt Hour

    HVDC : High Voltage Direct Current

    CB : Circuit Breaker

    GS : Generation Station

    HEPS : Hydro Electric Power Station

    DPS : Diesel Power Station

    NPS : Nuclear Power Station

    IPP : Independent Power Producer

    EHV : Extra High Voltage

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    10/111

    10

    CONTENTS

    TABLE OF CONTENTS

    Contents Page No.

    Cover Page 1Initial Page 2Declaration 3Certificate 4

    Transmittal 5Approval Sheet 6Acknowledgement 7Abstract 8Abbreviation & Notations 9Table of Contents 10List of Table 11List of Figure 12

    CHAPTER-1: Introduction

    1.1 Background 19

    1.2 Objective of thesis 19

    CHAPTER-2: Study of power generation system

    2.1 Generation Station 20

    2.2 Types of Generating Station 20

    2.3 Steam power plant 20

    2.3.1 Choice of site for Steam power plant 20

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    11/111

    11

    2.3.2 Advantages of Steam power plant 21

    2.3.3 Disadvantages of Steam power plant 21

    2.3.4 Schematic arrangement of Steam power plant 21

    2.3.5 Description of various section of Steam power plant 22

    2.3.6 Typical Steam power plant 24

    2.3.7 Efficiency of Steam power plant 34

    2.4 Hydro-Electric power Station 34

    2.4.1 Choice of site for Hydro-Electric power Station 35

    2.4.2 Advantages of Hydro-Electric power Station 35

    2.4.3 Disadvantages of Hydro-Electric power Station 36

    2.4.4 Constituents of Hydro-Electric power Station 36

    2.5 Nuclear power station 37

    2.5.1 Choice of site for nuclear power station 37

    2.5.2 Advantages of Nuclear power station 38

    2.5.3 Disadvantages of Nuclear power station 38

    2.5.4 Schematic arrangement of nuclear power station 38

    2.6 Diesel power station 40

    2.6.1 Choice of site for Diesel power station 40

    2.6.2 Advantages of Diesel power station 40

    2.6.3 Disadvantages of Diesel power station 40

    2.6.4 Schematic arrangement of Diesel power station 41

    2.7 Gas turbine power station 41

    2.7.1 Advantages of Gas turbine power station 41

    2.7.2 Disadvantages of Gas turbine power station 41

    2.7.3 Schematic arrangement of Gas turbine power station 42

    2.7.4 The main components of the plant 42

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    12/111

    12

    CHAPTER-3: Power generation in Bangladesh

    3.1 Generating voltage of different power station 44

    3.2 Power demand 44

    3.3 Load factor and Load management 44

    3.4 Installed capacity 44

    3.5 Owner Wise Daily Generation 45

    3.5.1 Installed Capacity of BPDB Power Plants as on April 2014. 46

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    13/111

    13

    CHAPTER-4: Transmission System of Bangladesh

    4.1 Transmission System 52

    4.2 Primary Transmission 52

    4.2.1 Grid System 52

    4.2.2 Grid sub- station 52

    4.3 Secondary Transmission 53

    4.4 Classification of overhead transmission line 53

    4.5 Definition of important terms 53

    4.6 Advantages of high voltage transmission system 54

    4.7 Advantages and disadvantages of high voltage direct current system 55

    4.8 Transmission system of different countries 55

    4.8.1 Transmission system of India 55

    4.8.2 Transmission system of Srilanka 56

    4.8.3 Transmission system of Nepal 56

    4.8.4 Transmission system of Pakistan 57

    CHAPTER-5: Mechanical design of overhead transmission line

    5.1 Properties of conductor materials 58

    5.2 Conductors materials 58

    5.3 Types of conductor 59

    5.4 Line support 61

    5.5 Types of line support 61

    5.6 Insulators 62

    5.7 Types of Insulators 62

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    14/111

    14

    CHAPTER-6: Electrical design of overhead transmission line6.1 Electrical design aspects 656.2 Constant of transmission line 656.3 Characteristics of different transmission line 716.4 Transmission voltage level 76

    6.5 Standardization of transmission voltage 776.6 Extra high voltage transmission 776.7 Protection system of transmission line 786.8 Protection components 786.9 LIST OF TRANSMISSION LINES IN BANGLADESH 79

    6.9.1 Recent Completed Project for Transmission6.9 132 KV Transmission Lines 806.9.1 Recent Completed Project for Transmission 816.9.2 Hasnabad & Tongi 230 kV and Kalyanpur 132 kV S/s Construction (Hasnabad-

    Aminbazar-Tongi & Haripur-Me82

    6.9.3 Joydevpur-Kabirpur-Tangail 78 km 132 kV T/L & 3 S/s Extn. Project (Joydebpur-

    Kabirpur-Tangail 132 kV

    83

    6.9.4 Ishurdi-Baghabari 54 km 230 kV T/L Construction (Ishurdi Baghabari-Serajgonj-Bogra 230 kV T/L Project)

    83

    6.9.5 On Going Project for Transmission400/230/132 Network Developmemt project (Trance-2)

    84

    6.9.6 Goalpara-Bagerhat 132 kV Double Circuit Transmission Line 846.9.7 Meghnaghat-Aminbazar 400 kV Transmission Line (NG1) 846.9.8 Construction & Extension of Grid Substations including transmission line facilities

    (Phase-1)85

    6.9.9 Aminbazar-Old Airport 230 kV Transmission Line and Associated Substations 856.9.10 Transmission Efficiency Improvement through Reactive Power Compensation at

    Grid Substations and Reinforcement of Goalpara Substation85

    6.9.11 Siddhirganj-Maniknagar 230 kV Transmission Line 866.9.12 132 kV Grid Network Development Project in Eastern Region. 866.9.13 National Power Transmission Network Development Project 866.9.14 Barisal-Bhola-Burhanuddin 230 kV Transmission Line Project 876.9.15 Grid Interconnction between Bangladesh(Bheramara) and India(Baharampur) 876.9.16 Two new 132/33 kV substations at Kulaura & Sherpur with interconnecting line 876.9.17 Bibiyana-Kaliakoir 400 KV and Fenchuganj-Bibiyana 230KV Transmission Line

    (NG2)88

    6.9.18 Haripur 360 MW Combined Cycle Power Plant and Associated Substation (PGCBPart)

    88

    6.10 Transmission line losses 88

    6.10.1 Types of losses 88

    6.10.2 Skin effect 89

    6.11 Minimization of Transmission line losses 90

    CHAPTER-7: Distribution System

    7.1 Definition of Substation 91

    7.2 Importance of Substation 91

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    15/111

    15

    7.3 Equipment of electrical Substation 91

    7.4 Classification of Substation 91

    7.5 Definition of different equipments 92

    7.5.1 Transformer 93

    7.5.2 Power Transformer 93

    7.5.3 Instrument Transformer 93

    7.5.4 Isolator 94

    7.5.5 Lighting arrester 95

    7.5.6 Insulator 95

    7.5.7 Bus-Bar 977.5.8 Circuit-Breaker 99

    7.5.9 Basic principles of operation of circuit breaker 100

    7.6 Different types of Circuit Breaker 100

    7.6.1 Plain Breaker Oil circuit Breaker (POCB) 100

    7.6.2Vacuum Circuit Breaker (VCB) 101

    7.6.3 Sulphur Hexa Fluoride Circuit Breaker (SF6) 102

    7.7 List of equipments of bhurulia sub-station 1047.8 Rating of different equipments 104

    7.9 Single line diagram of bhurulia sub-station 106

    7.9 Calculation of power factor for different feeder 107

    CHAPTER-8: Future plan of Bangladesh

    8.1 Power generation plan up to 2016 108

    8.2 India Bangladesh transmission link 108

    8.3 400 KV transmission line 108

    CHAPTER-9: Discussion And Conclusion Reference

    LIST OF FIGURE

    Figure : 2.1 Schematic arrangement of a steam power station. 22

    Figure : 2.2 Steam power plant 24

    Figure : 2.3 Steam Generator 25

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    16/111

    16

    Figure : 2.4 Turbo Generator 29

    Figure : 2.5 Diagram of a typical water cooled surface condenser. 30

    Figure : 2.6 A Ranking cycle with a two stage steam turbine and a single feed

    water heater.

    31

    Figure : 2.7 Boiler feed water desecrator 32

    Figure : 2.8 Schematic arrangement of a hydro-electric power station. 35

    Figure : 2.9 Schematic Arrangement of a Nuclear power Station. 39

    Figure : 2.10 Schematic Arrangement of a Diesel Power Plant 41

    Figure : 2.11 Schematic arrangement of a gas turbine power plant. 42

    Figure : 5.1 Conductor Section of AAC. 59

    Figure : 5.2 (a): 37 Bobbin Stranding Machine (b) : 61 Bobbin Stranding Machine

    (c) : Conductor Section of AAAC (d) : Conductor Section of ACSR

    60

    61

    Figure : 5.3 Steel Tower 62

    Figure : 5.4 Pin type Insulator 63

    Figure : 5.5 Outside and inside constructional diagram of long rod insulators 64

    Figure : 6.1 Equilateral Spacing (inductance). 67

    Figure : 6.2 (a) Unsymmetrical Spacing (inductance).

    (b) Unsymmetrical Lines (inductance).

    68

    Figure : 6.3 Equilateral Spacing (capacitance). 69

    Figure : 6.4 Unsymmetrical Spacing (capacitance). 70

    Figure : 6.5 Two port network. 72

    Figure : 6.6 Short Transmission line. 72

    Figure : 6.7 Medium Transmission Line. 73

    Figure : 6.8 NominalT representation. 74

    Figure : 6.9 Nominal representation. 74

    Figure : 6.10 Long Transmission Line. 74

    Figure : 7.1 Transformer. 93

    Figure : 7.2 Three Phase Power Transformer 93

    Figure : 7.3 Isolator 94

    Figure : 7.4 Lightning arrestor 95

    Figure : 7.5 Pin type insulator 96

    Figure : 7.6 Suspension type insulator 96

    Figure : 7.7 Strain insulator 97

    Figure : 7.8 Single Bus bar 98

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    17/111

    17

    Figure : 7.9 Single Bus bar system with Sectionalisation 99

    Figure : 7.10 Basic operation of circuit breaker 100

    Figure : 7.11 Oil Circuit Breaker 101

    Figure : 7.12 Vacuum circuit break 102

    Figure : 7.13 Sulphur Hexa Fluoride Circuit Breaker 103

    Figure : 7.15 Single Line diagram of Bhurulia Sub-Station 106

    Figure : 7.16 Power triangle 107

    LIST OF TABLE

    Table List Description Page No

    3.5 Owner wise monthly Generation 45

    3.5.1 Installed Capacity of BPDB Power Plants as on April 2014. 46

    3.5.2 Power supply situation on 18thMarch 2014 (Monday) 47

    3.5.3 Daily Generation Report 48

    4.8.2 Transmission System Of Srilanka 56

    6.9 230 KV Transmission Lines 79

    6.10 132 KV Transmission Lines 80

    6.10.1 Recent Completed Project for Transmission 81

    6.10.2 Hasnabad & Tongi 230 kV and Kalyanpur 132 kV S/s

    Construction (Hasnabad-Aminbazar-Tongi & Haripur-Me

    82

    6.10.3 Joydevpur-Kabirpur-Tangail 78 km 132 kV T/L & 3 S/s Extn.

    Project (Joydebpur-Kabirpur-Tangail 132 kV

    83

    6.10.4 Ishurdi-Baghabari 54 km 230 kV T/L Construction (Ishurdi

    Baghabari-Serajgonj-Bogra 230 kV T/L Project)

    83

    6.10.5 On Going Project for Transmission

    400/230/132 Network Development project (Trance-2)

    84

    6.10.6 Goalpara-Bagerhat 132 kV Double Circuit Transmission Line 84

    6.10.7 Meghnaghat-Aminbazar 400 kV Transmission Line (NG1) 84

    6.10.8 Construction & Extension of Grid Substations including

    transmission line facilities (Phase-1)

    85

    6.10.9 Aminbazar-Old Airport 230 kV Transmission Line and Associated

    Substations

    85

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    18/111

    18

    6.10.10 Transmission Efficiency Improvement through Reactive Power Compensation at

    Grid Substations and Reinforcement of Goalpara Substation

    85

    6.10.11 Siddhirganj-Maniknagar 230 kV Transmission Line 86

    6.10.12 132 kV Grid Network Development Project in Eastern Region. 86

    6.10.13 National Power Transmission Network Development Project 86

    6.10.14 Barisal-Bhola-Burhanuddin 230 kV Transmission Line Project 87

    6.10.15 Grid Interconnction between Bangladesh(Bheramara) and

    India(Baharampur)

    87

    6.10.16 Two new 132/33 kV substations at Kulaura & Sherpur with

    interconnecting line

    87

    6.10.17 Bibiyana-Kaliakoir 400 KV and Fenchuganj-Bibiyana 230KV

    Transmission Line (NG2)

    88

    6.10.18 Haripur 360 MW Combined Cycle Power Plant and Associated

    Substation (PGCB Part)

    88

    7.7 List of equipment of Bhurulia substation 104

    7.8 Rating of different equipment used in bhurulia sub-station

    Rating of Oil circuit breaker

    104

    7.9 Rating of SF6circuit breaker 105

    7.10 Rating of Vacuumcircuit breaker 105

    7.11 Rating of Transformer (T1) 105

    7.12 Rating of Transformer (T2) 105

    7.13 Rating of Transformer (T3) 106

    7.18 Voltage Regulator(For each phase) 106

    REFERENCES 109

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    19/111

    19

    CHAPTER-1

    INTRODUCTION

    1.1 BACKGROUND

    For growing development of a country, electricity has a vital role in all sectors. For the proper

    utilization, is required to transmit and distribute the electrical power through proper way. During

    the early years small local generating station supplied power to respective local loads. Each

    generating station needed enough installed capacity to meet the local peak loads. Bangladesh is an

    underdeveloped country. Its socio- economic structure is gradually increasing. So the demand of

    power is extending day by day and thus the importance of Generation, Transmission and

    Distribution are becoming more complicated.

    An electric power system consist of the three principal components are the generation system,

    transmission system and distribution system. The increasing uses of electric power for domestic,

    commercial and industrial purposes necessities to provide bulk electric power economically. This

    is achieved with the help of suitable power generating units, known as power plant. An electric

    power station is an assembly of equipments in which energy is converted from one form to

    another into electric energy. Electrical equipments of power station include generators,transformers, switch gears and control gears. The transmission lines are the connecting links

    between the generating stations and the distribution system and lead to the power system over

    interconnections. It is required to proper distribute the electric power to the consumer by a

    network is called the distribution system.

    1.2 OBJECTIVES OF THE THESIS

    a) To study the different power stations such as hydro electric power station, thermal power

    station, Nuclear power station, diesel power station and Gas turbine power station.

    b) To study the comparative facilities of different power station.

    c) To study the comparative productive ability of different power stations.

    d) To study the power generation in Bangladesh.

    e) To study the transmission system in Bangladesh.

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    20/111

    20

    CHAPTER-2

    OVERVIEW OF POWER GENERATION SYSTEMS

    2.1 GENERATING STATION

    Bulk electric power is produced by special plant is known as the generating station or power

    plants. A generating station essentially employs a prime mover coupled to an alternator for the

    production of electric power. The alternator converts mechanical energy of the prime mover into

    electrical energy. The electrical energy produced by the generating station is transmitted and

    distributed with the help of conductors of various consumers.

    2.2 TYPES OF GENERATING STATION

    1) Steam power plant

    2) Hydro-electric power plant

    3) Nuclear power plant

    4) Diesel power plant

    2.3 STEAM POWER PLANT

    A generating station that converts the heat energy of coal combustion into electrical energy is

    known as a steam power station.

    2.3.1 CHOICE OF SITE FOR STEAM POWER STATIONS

    1. Supply of fuel:The steam power station should be located near the coal mines so that

    transportation cost is minimum. However, if such a plant is to be installed taken that

    adequate facilities exists for the transportation of coal.

    2. Availability of water:As huge amount water is required for the condenser therefore, such

    a plant should be located at the bank of a river or near a canal to endure the continuous

    supply of water.

    3. Transportation facilities:A modern steam power station often requires the transportation

    of material and machinery. Therefore, adequate transportation facilities must exist. The

    plant should be well connected to others part of the country by the rail road etc.

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    21/111

    21

    4. Cost and Type of Land:The steam power station should be located at a place where land

    is cheap and further extension, if necessary is possible. More ever the bearing capacity of

    the ground should be adequate so that heavy equipment could be installed.

    5. Nearness to the Load Centre:In order to reduce the transmission cost the plant should be

    located near the centre of load. This is particularly important if dc supply is adopted, this

    factor becomes relatively less important with consequent reduced transmission cost. It

    possible to install the plant away from the load centers provided other conditions are

    favorable.

    6. Distance from Populated Area:As huge amount of coal is burnt in a steam power

    station, therefore smoke and fumes plant should be located at a considerable distance from

    the populated areas.

    2.3.2 ADVANTAGES OF STEAM POWER PLANT

    a) The fuel is quite cheap

    b) Less initial cost as compared to other generating stations

    c) It can be installed at by place irrespective of the existence of coal. The coal can be

    transported to the site of the plant by rail or road.

    d) It required less space as compared to the hydro-electric power station.

    e) The cost of generation is lesser than that of the diesel power station.

    2.3.3 DISADVANTAGES OF STEAM POWER PLANT

    a) It pollutes the atmosphere due to the production of large amount of smoke and fumes.

    b) It costlier in running cost as compared to hydro-electric plant.

    2.3.4 SCHEMATIC ARRANGEMENT OF STEAM POWER PLANT

    Although steam power station simply involves the conversion of heat of coal combustion into

    electrical energy, etc if embraces many arrangements for proper working and efficiency. The

    schematic arrangement of a modern steam power station is shown in bellow. Where the whole

    arrangement can be divided into the following stages for the sake of simplicity.

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    22/111

    22

    Fig: 2.1 Schematic arrangement of a steam power station.

    2.3.5 DISCRIPTION OF VARIOUS SECTION OF STEAM POWER PLANT

    1. Coal and ash handling arrangement

    2. Steam generating plant

    3. Steam turbine

    4. Alternator

    5. Feed water

    6. Cooling arrangement

    Coal and ash handling plant:

    The coal is transported to the power station by road or rail and is stored in the coal storage plant.

    Storage of coal is primarily a matter of protection against shortages. From the coal storage plant

    coal is delivered to the coal handling plat where it is pulverized combustion without using large

    quantity of excess air. The pulverized coal is fed to the boiler by belt conveyors. The coal is burnt

    in the boiler and the ash produced after the complete combustion of coal is removed to the ash

    handling plant and then delivered to the ash storage plant for disposal. The removal of the ash

    from the boiler furnace is necessary for proper burning of coal.

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    23/111

    23

    It is worthwhile to give a passing reference to the amount of coal burnt and ash produced in a

    modern thermal power station. A 100 MW station operating at 50% load factor may burn about

    20000 tons of coal per month and ash produced may be to the tune of 10% to 15% of coal fired

    i.e., 2000 to 3000 tons. In fact in thermal power station about 50% to 60% of the total operating

    cost consists of a boiler for the production of steam and other auxiliary equipment for the

    utilization of flue gases.

    a) Boiler:The heat of combustion of coal in the boiler is utilized to convert water into steam at

    high temperature and pressure. The flue gases the boilers makes their journey through super

    heater economizer, air pre heater and are finally exhausted to atmosphere through the

    chimney.

    b)

    Super heater:The steam produced in the boiler is wet and is passed through a super heater

    where it is dried and superheated water by the flue gases on their way to chimney.

    Superheating provides two principal benefits. Firstly the overall efficiency is increased.

    Secondly too much condensation in the last stages of turbine is avoided the supper heated

    steam turbine through the main valve.

    c) Economizer: An economizer is essentially a feed water heater and derives heat from flue

    gases for this purpose. The fed to the economizer before supplying to the boiler. The

    economizer extracts a part of heat of flues gassed to increase the feed water temperature.d) Air pre-heater: An Air pre-heater increase the temperature of the air supplied from coal

    burning by deriving heat from flue gases. Air is drown from the atmosphere by a forced

    draught fan and is passed through air pre heater before supplying to the boiler furnace. The air

    drowns from the atmosphere by a forced draught fan and is passed through air pre heater

    before supplying to the boiler furnace. The pre heater extracts heat from flue gases and

    increases the temperature of air used for coal combustion. The principal benefits of preheating

    the air are increased thermal efficiency and increased steam capacity per square meter of

    boiler surface.

    e) Steam turbine: The dry and superheated steam from the super heater id fed to the steam

    turbine through main valve. The heat energy of steam when passing over the blades of turbine

    is converted into mechanical energy. After giving heat energy to the turbine the steam is

    exhausted to the condenser which condenses the exhausted steam by means of cold water

    circulation.

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    24/111

    24

    f) Alternator: The Steam turbine is coupled to an alternator. the alternator converts mechanical

    energy of turbine into electrical energy. The electrical output from the alternator is delivered

    to the bus bars through transformer circuit breaker and insulators.

    g) Feed water:The condensate from condenser is used as feed water to the boiler some water

    may lost in the cycle which is made up from external source. The feed water on its way to the

    boiler is heated by water heaters and economizer. This helps in raising the overall efficiency

    of the plant.

    h) Cooling arrangement: In order to improve the efficiency of the plant. The steam exhausted

    from the turbine is condensed by means of a condenser.

    2.3.6: TYPICAL STEAM POWER PLANT

    Fig: 2.2 Steam power plant

    1. Cooling tower 15. Air intake

    2. Cooling water pump 16. Economizer

    3. Transmission line (3-phase) 17. Air pre heater

    4. Unit Transmission line (3-phase) 18. Precipitator Electric generator (3-phase)

    19. Feed heater

    5. Low pressure turbine 20. Coal conveyor

    6. Condensate extractions pump 21. Coal hopper

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    25/111

    25

    7. Condenser 22. Pulverized fuel mill

    8. Intermediate pressure turbine 23. Boiler dr10Steam

    9. Steam governor valve 24. Ash hopper

    10. High pressure turbine 25. Induced draught fan

    11. Deaerator 26. Chimney stack

    12. Super heater

    13. Re heater

    2.3.6.1: Steam generator:

    Schematic diagram of typical coal-fired power plant steam generator highlighting the air pre

    heater (APH) location (For simplicity, any radiant section tubing is not shown)

    Fig: 2.3 Steam generator

    In fossil fueled power plants, steam generator refers to a furnace that burns the fossil fuel to boil

    water to generate steam. In the nuclear plant field, steam generator refers to a specific type of

    large heat exchanger used in a pressurized water reactor (PWR) to thermally connect the primary

    and secondary systems, which of course is used to generate steam. In nuclear reactor called a

    boiling water reactor (BWR), water is boiled to generate steam directly in the reactor itself and

    there are no units called steam generators. In some industrial settings, there can also be steam-

    producing heat exchangers called heat recovery steam generators which utilize heat from some

    industrial process. The steam generating boiler has to produce steam at the high purity, pressure

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    26/111

    26

    and temperature required or the steam turbine that drives the electrical generator. A fossil fuel

    steam generator includes an economizer, a steam drum, and the furnace with its steam generating

    tubes and super heater coils. Necessary safety valves are located at suitable points to avoid

    excessive boiler pressure. The air and flue gas path equipment include forced draft fan, air pre

    heater boiler furnace, fly ash collectors and the flue gas stack.

    Geothermal plants need no boiler since they used naturally occurring steam source. Heat

    exchangers may be used where the geothermal steam is very corrosive or contains excessive

    suspended solids. Nuclear also boil water to raise steam, either directly generating steam from the

    reactor (BWR) or else using an intermediate heat exchanger (PWR).

    For units over about 200 MW capacity, redundancy of key components is provided by installing

    duplicates of the FD fan, APH, fly ash collectors and ID fan with isolating dampers. On some

    units of about 60 MW, tow boilers per uint may instead be provided.

    2.3.6.2: Boiler furnace and steam drum:

    Once water inside the boiler or steam generator, the process of adding the latent heat of

    vaporization or enthalpy is underway. The boiler transfers energy to the water by the chemical

    reaction of burning some type of fuel. The water enters the boiler through a section in the

    convection pass called the economizer. From the economizer it passes to the steam drum. Once

    the water enters the stream drum it goes down the down comers to the lower inlet water wall

    headers. From the inlet headers the water rises through the water walls and is eventually turned

    into steam and due to the heat being generated by the burners located on the front and rear water

    walls. As the water is turned into steam in the water walls, the steam once again enters the steam

    drum. The steam/vapor is passed through a series of the steam and water separators and then

    dryers inside the steam drum . The steam separators and dryers remove water droplets from the

    steam and the cycle through the water walls is repeated. This process is known as natural

    circulation.

    The boiler furnace auxiliary equipment includes coal feed nozzles and igniter guns, soot blowers,

    water lancing and observation ports (in the furnace walls) for observation of the furnace interior.

    Furnace explosions due to any accumulation of combustible gases after a trip-out are avoided by

    flushing out such gases from the combustion zone before igniting the coal.

    The steam drum (as well as the super heater coils and headers) have air vents and drains neededfor initial startup. The steam drum has internal devices that remove moisture from the wet steam

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    27/111

    27

    entering the drum from the steam generating tubes. The dry steam then flows into the super heater

    coils.

    2.3.6.3: Super heater:

    Fossil fuel power plants can have a super heater and/or re-heater section in the steam generating

    furnace. Nuclear-powered steam plants do not have such sections but produce steam at essentially

    saturated conditions. In a fossil fuel plant, after the steam is conditioned by the drying equipment

    inside the steam drum, it is piped from the upper drum area into tubes inside an area of the

    furnace known as the super-heater, which has an elaborate set up of tubing where the steam vapor

    picks up more energy from hot flue gases outside the tubing and its temperature is now

    superheated above the saturation temperature. The superheated steam is then piped through the

    main steam lines to the valves before the high pressure turbine.

    2.3.6.4: Re-heater:

    Power plant furnaces may have a re-heater section containing tubes heated by hot flow gases

    outside the tubes. Exhaust steam from the high pressure turbine is rerouted to go inside the re-

    heater tubes to pickup more energy to go drive intermediate or lower pressure turbines. This is

    what is called as thermal power.

    2.3.6.5: Fuel preparation system:

    In coal-fired power stations, the row feed coal from the coal storage area is first crushed into

    small pieces and then conveyed to the coal feed hoppers at boilers. The coal is next pulverized

    may be ball mills, rotating drum grinders, or other types of grinders. Some power station burn fuel

    oil rather than coal. The oil must kept warm (above its pour point) in the fuel oil storage tanks to

    prevent the oil from congealing and becoming unpumpable. The oil is usually heated to about

    1000

    c before being pimped through the furnace fuel oil spray nozzles.

    Boilers in some power stations use processed natural gas as their main fuel. Other power stations

    may use processed natural gas as auxiliary fuel in the event that their main fuel supply (coal or

    oil) is interrupted. In such cases, separate gas burners are provided on the boiler furnaces.

    2.3.6.6: Air path:

    External fans are provided to give sufficient air for combustion. The forced draft fan takes air

    from the atmosphere and first warming it in the air pre-heater for better combustion, injects it via

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    28/111

    28

    the air nozzles on the furnace wall. The induced draft fan assists the FD fan by drawing out

    combustible gases from the furnace, maintaining a slightly negative pressure in the furnace to

    avoid backfiring through any opening.

    2.3.6.7: Auxiliary Systems:

    Fly ash collection: Fly ash is captured and removed from the flue gas by electrostatic

    precipitators or fabric bag filters (or sometimes both) located at the outlet of the furnace and

    before the induced draft fan. The fly ash is periodically removed from the collection hoppers

    below the precipitators or bag filters. Generally, the fly ash is pneumatically transported to storage

    silos for subsequent transport by trucks or railroad cars.

    2.3.6.8 : Action and disposal:

    Bottom ash collie: At the bottom of the furnace, there is a hopper for collection of bottom ash.

    This hopper is always filled with water to quench the ash and clinkers falling down from the

    furnace. Some arrangement is included to crush the clinkers and for conveying the crushed

    clinkers and bottom ash to a storage site.

    Boiler make-up water treatment plant and storage: Since there is continuous withdrawal of

    steam and continuous return of condensate to the boiler, losses due to blow down and leakages

    have to be made up to maintain a desired water level in the boiler steam drum. For this,

    continuous make-up water is added to the boiler water system. Impurities in the raw water input to

    the plant generally consist of calcium and magnesium salts which impart hardness to the water.

    Hardness in the make-up water to the boiler will from deposits on the tube water surface which

    will lead to overheating and failure of the tubes. Thus, the salts have to be removed from the

    water, and that is done by water demineralising treatment plant (DM). A DM plant generally

    consist of caution, anion, and mixed bed exchangers. Any ions in the final water from this processconsist essentially of hydrogen ions and hydroxide ions, which recombine to form pure water.

    Very pure DM water becomes highly corrosive once it absorbs oxygen from the atmosphere

    because of its very high affinity for oxygen.

    The capacity of the DM plant is dictated by the type and quantity of salt s in the raw water input.

    However, some storage is essential as the DM plant may be down for maintenance. For this

    purpose, a storage tank is installed from which DM water is continuously withdrawn for boiler

    make-up.the storage tank for DM water is made from materials not affected by corrosive water,

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    29/111

    29

    such as PVC. The piping and valves are generally of stainless steel. Sometimes, a steam

    blanketing arrangement or stainless steel doughnut float is provided on top of the water in the tank

    to avoid contact with air.DM water make-up is generally added at the steam space of the surface

    condenser (i.e., the vacuum side). This arrangement not only sprays the water but also DM water

    gets deaerated, with the dissolved gases being removed by an air ejector attached to the condenser

    2.3.6.9: Steam turbine-driven electric generator:Rotor of the modern steam turbine, used in a

    power station.

    Turbo generator:

    Fig: 2.4 Turbo generator

    The steam turbine-driven generators have auxiliary systems enabling them to work satisfactorily

    and safely. The steam turbine generator being rotating equipment generally has a heavy, large

    diameter shaft. The shaft therefore requires not only supports but also has to be kept in position

    while running. To minimize the frictional resistance to the rotation, the shaft has a numbering of

    bearings. The bearing shells, in which the shaft rotates, are lined with a low friction material like

    Babbitt metal. Oil lubrication is provided to further reduce the friction between shaft and bearing

    surface and to limit the heat generated.

    2.3.6.10: Bearing gear:

    Barring gear (or turning gear) is the mechanism provided to rotate the turbine the turbine

    generator shaft at a very low speed after unit stoppages. Once the unit is tripped (i.e., the steam

    inlet valve is closed), the turbine coasts down towards standstill. When it stops completely, there

    is a tendency for the turbine shaft to deflect or bend if allowed to remain in one position too long.This is because the heat inside the turbine casing tends to concentrate in the top half of the casing,

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    30/111

    30

    making the top half portion of the shaft hotter than the bottom half. The shaft therefore could

    wrap or bend by millionths of inches.

    This small shaft deflection, only detectable by eccentricity meters, would be enough to cause

    damaging vibrations to the entire steam turbine generator unit when it is restarted. The shaft is

    therefore automatically turned al low speed (about one percent rated speed) by the barring gear

    until it has cooled sufficiently to permit a complete stop.

    Condenser:

    Fig: 2.5 Diagram of a typical water cooled surface condenser.

    The surface condenser is a shell and tube heat exchanger in which cooling water is circulated

    through the tubes. The exhaust steam from the low pressure turbine enters the shell where it is

    cooled and converted to condensate (water) by flowing over the tubes as shown in the adjacent

    diagram. Such condensers use steam ejectors or rotary motor-driven exhausters for continuous

    removal of air and gases from the steam side to maintain vacuum. For best efficiency, the

    temperature in the condenser must be kept as low as practical in order to achieve the lowest

    possible pressure in the condensing steam. Since the condenser temperature can almost always be

    kept significantly below 1000c where the vapor pressure of water is much less than atmospheric

    pressure, the condenser generally works under vacuum. Thus leaks of non condensable air into the

    closed loop must be prevented. Plants operating in hot climates may have to reduce output if their

    source of condenser cooling water becomes warmer; unfortunately this usually coincides with

    periods of high electrical demand for air conditioning. The condenser generally uses either

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    31/111

    31

    circulating cooling water from a cooling tower to reject waste heat to the atmosphere or once-

    through water from a river, lake or ocean

    Feed water heater:

    Fig: 2.6 A Ranking cycle with a two stage steam turbine and a single feed water heater.

    In the case of a conventional steam-electric power plant utilizing a drum boiler, the surface

    condenser removes the latent heat of vaporization from the steam as it changes states from vapor

    to liquid. The heat content (btu) in the steam is referred to as Enthalpy. The condensate pump then

    pumps the condensate water through a feed water heater The feed water heating equipment then

    raises the temperature of the water by utilizing extraction steam from various stages of the

    turbine, Preheating the feed water reduce the irreversibility involved in steam generation and

    therefore improves the thermodynamic efficiency of the system,[9] This reduces plant operatingcost and also helps to avoid thermal shock to the boiler metal when the feed water is introduced

    back into the steam cycle

    2.3.6.11: Super heater:

    As the steam is conditioned by the drying equipment inside the drum, it is piped from the upper

    drum area into an elaborate set up of tubing different areas of the boiler. The areas known as super

    heater and re-heater, the steam vapor picks up energy and its temperature is now superheated

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    32/111

    32

    above the saturation temperature. The superheated steam is then piped through the main steam

    lines to the valves of the high pressure turbine

    Deaerator:

    Fig: 2.7 Boiler feed water deaerator.

    A steam generating boiler requires that the boiler feet water should be devoid of air and other

    dissolved gases, particularly corrosive ones, in order to avoid corrosion of the metal. Generally,

    power station use a deaerator to provide for the removal of air and other dissolved gases from the

    boiler feed water. A deaerator typically includes a vertical, domed deaeration section mounted on

    top of a horizontal cylindrical vessel which serves as the deaerated boiler feed water storage tank.

    There are many different designs for a deaerator and the designs will vary from one manufacturer

    to another. The adjacent diagram depicts a typical conventional traded deaerator. If operated

    properly; most deaerator manufacturers will guarantee that oxygen in the deaerated water will not

    exceed 7 ppb by weight (0.005 cm3

    /L).

    2.3.6.12: Auxiliary systems:

    Oil system:An auxiliary oil system pump is used to supply oil at the start-up of the steam turbine

    generator. It supplies the hydraulic oil system required for steam turbines main inlet steam stop

    valve, the governing control valves, the bearing and seal oil systems, the relevant hydraulic relays

    and other mechanisms. At a preset speed of the turbine during start-ups, a pump driven by the

    turbine main shaft takes over the functions of the auxiliary system.

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    33/111

    33

    Generatorheat dissipation:The electricity generator requires cooling to dissipate the heat that it

    generators. While small units may be cooled by air drawn through filters at the inlet, lager units

    generally require special cooling arrangements. Hydrogen gas cooling, in an oil sealed casing, is

    used because it has the highest known heat transfer coefficient of any gas and for its low viscosity

    which reduces winding losses. This system requires special handling during start up, with air in

    the chamber first displaced by carbon dioxide before filing with hydrogen ensures that the highly

    flammable hydrogen does not mix with oxygen in the air.

    The hydrogen pressure inside the casing is maintained slightly higher than atmospheric pressure

    to avoid outside air ingress. The hydrogen must be sealed against outward leakage where the shaft

    emerges from the casing. Mechanical seals around the shaft are installed with a very small annular

    gap to avoid rubbing between the shaft and the seals. Sal oil is used to prevent the hydrogen gas

    leakage to atmosphere.

    The generator also uses water cooling. Since the generator coils are at a potential of about 22 KV

    and water is conductive, an insulting barrier such as Teflon is used to interconnect the water line

    and the generator high voltage windings. Dematerialized water of low conductivity is used.

    Generator high voltage system: The generator voltage ranges from 11 KV in smaller unit to 22

    KV in larger units. The generator high voltage leads are normally large aluminum channelsbecause of their high current as compared to the cables used in smaller machines. They are

    enclosed in well-grounded aluminum bus ducts and are supported on suitable insulators. The

    generator high channels are connected to step-up transformers for connecting to a high voltage

    electrical substation (of the order of 115 KV to 520 KV) for further transmission by the local

    power grid. The necessary protection and metering devices are included for the high voltage

    leads. Thus, the steam turbine generator and the transformer from one unit. In smaller units,

    generating at 11 KV, a breaker is provided to connect it to a common 11 KV bus system

    2.3.6.13: Other Systems:

    Monitoring and alarm system: Most of the power plant operational control is automatic.

    However, at times, manual intervention may be required. Thus, the plant is provided with

    monitors and alarm systems that alert the plant operators when certain operating parameters are

    seriously deviating from their normal range.

    Battery supplied emergency lighting and communication: A central battery system consistingof lead acid cell units is provided to supply emergency electric power, when needed, to essential

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    34/111

    34

    items such as the power plants control systems, communication systems, turbine lube oil pumps,

    and emergency lighting. This is essential for a safe, damage-free shutdown of the units in an

    emergency situation.

    Transport of coal fuel to site and to storage: Most thermal stations use coal as the main fuel.

    Raw coal is transported from coal mines to a power site by trucks, barges, bulk cargo ships or

    railway cars. The coal received at site may be off different sizes. The railway cars are unloaded at

    site by rotary dumpers or side till dumpers to tip over onto conveyors conveyor belt below. The

    coal is generally conveyed to crush the coal to about inch (6mm) size. The crushed coal is then

    sent by belt conveyors to a storage pile. Normally, the crushed coal is compacted by bulldozers, as

    compacting of highly volatile coal avoids spontaneous ignition.

    2.3.7 EFFICIENCY OF STEAM POWER PLANT

    There are two types of efficiency in thermal power plant.

    I) Thermal efficiency

    II) Overall efficiency.

    Thermal efficiency:

    The ratio of heat equivalent of mechanical energy transmitted to the turbine shaft to the heat of

    combustion of coal is known as Thermal efficiency of steam power station

    2.4 HYDRO-ELECTRIC POWER STATION

    A generating station which utilizes the potential energy of water at a high level for the generation

    of electrical energy is known as hydro-electric power station

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    35/111

    35

    Fig: 2.8 Schematic arrangement of a hydro-electric power station.

    2.4.1 CHOICE OF SITE FOR HYDROELECTRIC POWER STATIONS

    The following points should be taken into account whole selecting the site for a hydro electric

    power station.

    1. Availability of water: Such plants should be built at a place where adequate water is

    available at a good head due to the primary requirement of a hydro-electric power station

    is the availability of huge quantity of water.

    2. Storage of water: There are wide variations in water supply from a river or canal during

    the year. This makes it necessary to store water by constructing a dam. Site selection for a

    hydro-electric power plant should be provides adequate facilities for erecting a dam and

    storage of water.

    3.

    Cost and type of land: the land for the construction of the plant should be available at a

    reasonable price. The bearing capacity of the ground should be adequate to withstand the

    weight of heavy equipment to be installed.

    4. Transportation facilities:the site selection for a hydro-electric plant should be accessible

    by rail, river and road. So that necessary equipment and machinery could be easily

    transported.

    2.4.2 ADVANTAGES OF HYDRO-ELECTRIC POWER STATION

    1. It is neat and clean as no smoke or ash is produced

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    36/111

    36

    2. It has a longer life.

    3. It required very small running charges because water is available free of cost.

    4. As compare to steam power station, it does not require a long starting time.

    5. Such plants serve many purposes. In additional to the generation of electrical energy,

    they also help in irrigation and controlling flood.

    6. No fuel is burnt.

    2.4.3 DISADVANTAGE OF HYDRO-ELECTRIC POWER STATION

    1. Capital cost is high as compare to other stations.

    2. Skilled and experienced hands are required to build the plant.

    3. Transmission cost is high as the plant is located in hilly areas which are quite away from

    the consumers.

    4. Uncertainty about the availability of huge amount of water due to dependence on

    weather conditions.

    2.4.4 CONSTITUENTS OF HYDRO-ELECTRIC PLANT:

    a) Dam: A dam is a barrier, which stores water and creates water heads. Dams are building

    of concrete or stone -masonry, earth or rock field. The type and arrangement depend

    upon the topography of site. The type of dam also depends upon the type of foundation

    conditions local materials and transportations available, occurrence of earthquakes and

    other hazards.

    b) Spillways: In order to discharge the surplus water the storage reservoir in to the river on

    the down-steam side of the dam, spillways are used.

    c)

    Head work:The head works consists of diversion structures at the head of an intake.

    The generally include booms and racks for the diverting floating debris, sluices for by

    passing debris and sediments and valves for the controlling the follow of water to the

    turbine.

    d) Surge tank: A surge tank is a small reservoir or tank in which water level rises or falls

    to reduce the pressures swings in the conduit. A surge tank is located near the beginning

    of the conduit. When the load on the turbine decreases, then increases the water level of

    the surge tank and reversal.

    e)

    Penstocks:Penstocks are conduits, which carry water to the turbines; they are generally

    made of reinforced concrete or steel. Various devices such as automatic butterfly valve,

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    37/111

    37

    air valve and surge tank are provided for the protection of penstocks. Automatic

    butterfly valve shuts off water flow through the penstocks promptly if it raptures. Air

    valve maintains the air.

    1. For high head.

    2. Reaction turbine- for low and medium head

    f)

    Electrical equipments: This includes alternators, transformers, circuit breaker and other

    switching and protective devices.

    2.5 NEUCLEAR POWER STATION

    A generating station in which nuclear energy is converted into electrical energy is known as a

    nuclear power station. In nuclear power station, heavy elements such as Uranium (U-235) or

    thorium (Th-232) are subjected to nuclear fission in a special apparatus known as a reactor. The

    energy thus related is utilized in raising steam at high temperature and pressure. The steam runs

    the turbine which converts energy into mechanical energy. The turbine drives the alternator which

    converts mechanical energy into electrical energy.

    2.5.1 SELECTION OF SITE FOR NUCLEAR POWER STATION

    1. Availability of water: as sufficient water is required for cooling purposes, therefore, the

    plant side should be located where ample quantity of water is available, e.g., across a river

    or by sea side

    2. Disposal if water: the waste produce by the fission in a nuclear power station is generally

    radioactive which must be disposed of properly to avoid health hazards. The waste should

    either be buried in a deep trench or disposal off in sea quite away from the sea short.

    Therefore, the site selected for such a plant should have adequate arrangement for the

    disposal of radioactive waste

    3.

    Steam turbine: the steam produce in the heat exchange is led to steam turbine through a

    valve. After doing a useful work in the turbine, the steam is exhausted to condenser. The

    condenser condenses the steam which is fed to the heat exchanger through feed water

    pump.

    4. Alternator: The steam turbine drives the alternator which converts mechanical energy

    into electrical energy. The output from the alternator is delivered to the bus-bares through

    transformer, circuit breaker and isolators.

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    38/111

    38

    2.5.2 ADVANTAGES OF NUCLEAR POWER STATION

    1. The amount of fuel required is quite small. Therefore, there is a considerable saving in

    the cost of fuel transportation?

    2. A nuclear power plant requires less space as compared to any type of the same size.

    3. It has low running charges as a small amount of fuel is used to producing bulk electrical

    energy.

    4. This type of plant is very economical for producing bulk electrical energy.

    5. It can be located near the load centers because it does not require large quantities of

    water and need not be near coal mines. Therefore, the cost of primary distribution is

    reduced.

    6. There are large deposits of nuclear fuels available all over the world .Therefore, such

    plant can ensure continued supply of electrical energy for thousands of years.

    7. It ensures reliability of operation.

    2.5.3 DISADVANTAGES OF NUCLEAR POWER STATION

    1. The fuel used is expensive and difficult to recover.

    2. The capital cost on a nuclear plant is very high as compared to other types of plants.

    3. The erection and commissioning of the plant requires greater technical knowhow.

    4. The fission by products is generally radioactive and may cause a dangerous amount of

    radioactive pollution.

    5. Maintenance charges are high due to lack of standardization.

    6. Nuclear plants are not well suited for varying loads as the reactor does not respond to the

    load efficiently.

    7. The disposal of the by products, which are radioactive, is big problem. They have either

    to be disposed off in a deep trench or in a sea away from sea shore.

    2.5.4 SCHEMATIC ARRANGEMENT OF NUCLEAR POWER STATION

    The schematic arrangement of a nuclear power station is shown in fig. the whole arrangement can

    be divided into the following main stages:

    1. Nuclear reactor

    2. Heat exchange

    3. Steam turbine

    4. Alternator

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    39/111

    39

    Fig: 2.9 Schematic Arrangement of a Nuclear power Station.

    Nuclear reactor:It is an apparatus in which nuclear fuel (U-235) is subjected to nuclear fission.

    It control is the chain reaction that start once the fission is done. If the chain reaction is not

    controlled, the result will be an explosion due to the fast increase in the energy released.

    Chain reaction: nuclear fission is done by bombarding Uranium nuclei with slow moving

    neutrons. This splits the Uranium nuclei with the release of huge amount of energy and emission

    of neutrons. This fissions neutron cause further fission. If this process continues, then in a very

    short time huge amount of energy will be released which may cause explosion. This is known as

    explosive chain reaction. But in a reactor, controlled chain reaction is allowed. This is done by

    systematically removing the fission neutrons from the reactor. The greater the number of fission

    neutrons removes, the lesser is intensive of energy of released.

    1. Heat exchanger: The coolant gives up heat exchanger which is utilized in raising

    the steam. After giving up the heat, the coolant is again fed to the reactor.

    2. Steam turbine:The steam produced in the heat exchanger led to the steam turbine

    through a valve after doing useful work in the turbine, the steam is exhausted to

    condenser. The condenser condenses the steam which is feed to the heat exchanger

    through feed water pump

    3. Alternator: The steam turbine drives the alternator which converts mechanical

    energy into electrical. The output from the alternator is delivered to the bus-bars

    through transformer, circuit breakers and isolators.

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    40/111

    40

    2.6 DISEL POWER STATION

    A generating station in which diesel engine is used as the prime mover for the generation of

    electrical energy is known as diesel power station.

    2.6.1 CHOICE OF SITE FOR DIESEL POWER STATION

    1. Distance from load center [the plant should be located nearby the load center to be

    minimum transmission loss].

    2. Availability of water.

    3. Foundation condition. [A foundation at a reasonable depth should be capable of

    providing a strong support to the engine].

    4. Fuel transportation. [Plant should be near to the source of fuel supply so thattransportation charges are low].

    5. Access to site. [The site selected should have road and rail transportation facilities].

    2.6.2 ADVANTAGES OF DIESEL POWER STATION

    a) It requires less space as compare to other stations.

    b) The design and layout of this plant are very simple.

    c)

    For cooling system less quantity of water is required.d) It can be located at any place.

    e) There are no standby losses.

    f)It can be started quickly.

    g) It requires less operating staff.

    2.6.3 DISADVANTAGES OF DIESEL POWER STATION

    a) This plant can generate small power.

    b) The fuel cost is high.

    c) This plant does not work for a longer period.

    d) The cost of lubricating is high.

    e) The maintenance charges are high.

    f) It pollutes the atmosphere.

    g) It makes a noise.

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    41/111

    41

    2.6.4 SCHEMATIC ARRANGEMENT OF DIESEL POWER PLANT

    Fig: Schematic diagram of a diesel power Station.

    Fig: 2.10 Schematic Arrangement of a Diesel Power Plant

    2.7 GAS TURBINE POWER STATION

    A generating station which employs gas turbine as the prime mover for the generation of electrical

    energy is known as a gas turbine power plant.

    2.7.1 ADVANTAGES OF GAS TURBINE POWER STATION

    a) It is simple in design.

    b) It is much smaller in size.

    c) Initial and operating costs are lower than other.

    d) The maintenance charges are quite small.

    e) There is no stand by losses.

    2.7.2 DISADVANTAGES OF GAS TURBINE POWER STATION

    a.There is a problem for starting the unit.

    b. Since a greater part of power developed by the turbine is used in driving the

    compressor, the net output is low

    c.It pollutes the atmosphere.

    d. The overall efficiency of such plants is low.

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    42/111

    42

    2.7.3 SCHEMATIC ARRANGEMENT OF A GAS TURBINE POWER PLANT

    Fig: 2.11 Schematic arrangement of a gas turbine power plant.

    2.7.4 THE MAIN COMPONENT OF THE PLANTS

    a)

    Compressor: The compressor draws the air via the filter, which removes the dust from

    air. The rotary blades of the compressor push the air between stationary blades to raise

    its pressure. Thus air at high pressure is available at the output of the compressor.

    b) Regenerator:A regenerator is a device, which recovers heat from the exits gases of the

    turbine. A regenerator consists of nest of tubes contained in a shell. The compressed air

    from the compressor passes through the tubes on its way to the combustion chamber. In

    this way compressed air is heated by the exhaust gases.

    c)

    Combustion chamber: The air at high pressure from the compressor is led to thecombustion chamber via the regenerator. In the combustion chamber heat is added to the

    air by burning oil/gas. The result is that the chamber attains a very high temperature. The

    combustion gases are suitably cooled to 70000c-8000c and then delivered to the gas

    turbine.

    d) Gas turbine: The product of combustion comprising of a mixture of gases at high

    temperature and pressure are passed to the gas turbine. These gases in passing over the

    turbine blades expand and thus do the mechanical work. The temperature of the exhaustgases from the turbine is about 4800c

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    43/111

    43

    e) Alternator: The gas turbine is coupled to the alternator. The alternator converts

    mechanical energy of the turbine into electrical energy.

    f)Starting Motor: Before starting the turbine, compressor has to be started. For this

    purpose, an electrical motor is mounted on the same shaft of the turbine. This is

    energized by the batteries. Once the unit starts, a part of mechanical power of the drives

    the compressor and there is no need of motor now.

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    44/111

    44

    CHAPTER-3

    POWER GENERATION IN BANGLADESH

    3.1 GENERATING VOLTAGE OF DIFFERENT POWER STATION

    15.75kv

    11kv

    10.5kv

    6.6kv

    3.2 POWER DEMAND

    The peak demand for January 2012 is 7,518 MW as per update power system master plan

    (PSMP-2010). The maximum demand serves 5036.50 MW.

    3.3 LOAD FACTOR AND LOAD MANAGEMENT

    Consumer demand in BPDB system, as in any other electric utility varies throughout the day &

    night. The maximum occurs during 5 PM to11 PM termed as peak hour. The extent of this

    variation is measured in terms of load factor, which is the ratio of average & maximum demand,

    for economic reason it is desirable to have a high load factor as this would permit better utilization

    of plant capacity. The cost of energy supply during peak hour is high as some relatively costlier

    power plants are required to be used during peak hour.

    3.4 INSTALLED CAPACITY

    Although the total installed capacity was 5493MW including 1330MW in IPP and 351MW in

    internal power plant (Excluding REB).the maximum availability were

    (1)Some plants were out of operation due to maintenance, rehabilitation &overhauling.

    (2) Capacities of some plants were de-rated due to aging and Gas shortage.

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    45/111

    45

    3.5Owner Wise Daily Generation:

    Table : 01

    Owner Name Derated Capacity (MW) Day Peak (MW) Eve. Peak (MW)

    Generation of 21/04/2014

    PDB 3502.00 1648.00 1972.00

    SBU,PDB 223.00 194.00 201.00

    EGCB 622.00 235.00 417.00

    APSCL 682.00 468.00 465.00

    IPP 1617.00 1165.00 877.00

    SIPP,PDB 110.00 89.00 90.00

    RENTAL(3 yrs) 33.00 0.00 0.00

    SIPP,REB 215.00 160.00 175.00

    Q.Rental 3 Years 100.00 95.00 100.00

    QRPP(5yrs) 200.00 181.00 192.00

    Other 825.00 650.00 581.00

    RPP (3 Yrs.) 1069.00 740.00 780.00

    QRPP (3 Yrs.) 416.00 335.00 380.00

    RPP (15 Yrs.) 169.00 140.00 146.00

    Total 9783.00 6100.00 6376.00

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    46/111

    46

    3.5.1 Installed Capacity of BPDB Power Plants as on April 2014.

    Capacity Type: Power Generation Units (Fuel Type Wise)

    Installed Capacity of BPDB Power Plants as on April 2014

    Unit Type Capacity(Unit) Total(%)

    Coal 250.00 MW 2.44 %

    FO 0.00 MW 0 %

    Gas 6615.00 MW 64.59 %

    HFO 1963.00 MW 19.17 %

    HSD 683.00 MW 6.67 %

    Hydro 230.00 MW 2.25 %

    Imported 500.00 MW 4.88 %

    Total 10241.00 MW 100 %

    De rated Capacity of BPDB Power Plants as on April 2014

    Unit Type Capacity(Unit) Total(%)

    Coal 200.00 MW 2.04 %

    FO 52.00 MW 0.53 %Gas 6224.00 MW 63.62 %

    HFO 1926.00 MW 19.69 %

    HSD 661.00 MW 6.76 %

    Hydro 220.00 MW 2.25 %

    Imported 500.00 MW 5.11 %

    Total 9783.00 MW 100 %

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    47/111

    47

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    48/111

    48

    Daily Generation Report

    Power Station NameDerated

    Capacity(Unit)Day Peak Eve Peak

    Daily Generation of 21/04/2014

    a) Ghorasal ST 1, 2 78.00 MW 42.00 MW 45.00 MW

    Ghorasal ST :Unit-3, 180.00 MW 100.00 MW 100.00 MW

    Ghorashal ST 4 180.00 MW 170.00 MW 170.00 MW

    Ghorashal 100 100.00 MW 84.00 MW 99.00 MW

    Ghorrashal ST 5 190.00 MW 190.00 MW 190.00 MW

    Ghorashal ST 6 190.00 MW 0.00 MW 0.00 MW

    Ghorashal 45 MW 45.00 MW 43.00 MW 46.00 MW

    Ghorashal MAX 78.00 MW 76.00 MW 78.00 MW

    Ghorashal Regent 0.00 MW 2.00 MW 0.00 MW

    Horipur SBU GT 1,2,3 60.00 MW 0.00 MW 0.00 MW

    Horipur NEPC 110.00 MW 93.00 MW 110.00 MW

    Horipur P. Ltd CCPP 360.00 MW 246.00 MW 325.00 MW

    Meghnaghat P.Ltd CCPP 450.00 MW 440.00 MW 0.00 MW

    Meghnaghat Summit 0.00 MW 0.00 MW 0.00 MW

    Meghnaghat IEL 100.00 MW 91.00 MW 100.00 MW

    Madanganj 102 MW 100.00 MW 95.00 MW 100.00 MW

    Karanigonj 100.00 MW 90.00 MW 90.00 MW

    Narshingdi 22.00 MW 16.00 MW 18.00 MW

    Shiddirganj ST 150.00 MW 0.00 MW 0.00 MW

    Siddirgonj GT 1,2 210.00 MW 0.00 MW 0.00 MW

    Siddirgonj 100 MW 96.00 MW 56.00 MW 64.00 MW

    Dutch Bangla 100 MW 100.00 MW 90.00 MW 92.00 MW

    DPA Power 50 MW 50.00 MW 40.00 MW 46.00 MW

    Gahamagar 0.00 MW 0.00 MW 0.00 MW

    Horipur EGCB 360MW 412.00 MW 235.00 MW 417.00 MW

    Summit Power (Dhaka) 146.00 MW 108.00 MW 116.00 MW

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    49/111

    49

    Gazipur RPCL 52.00 MW 33.00 MW 32.00 MW

    Tongi GT 105.00 MW 0.00 MW 0.00 MW

    ChittagongRaozanST(Gas):Unit-1

    180.00 MW 120.00 MW 120.00 MW

    Raozan 25MW 25.00 MW 26.00 MW 26.00 MW

    Patenga 50 MW 50.00 MW 3.00 MW 14.00 MW

    ChittagongRaozanST(Gas):Unit-2

    180.00 MW 0.00 MW 0.00 MW

    Kaptai Hydro:Unit-1,2,3,4,5 220.00 MW 41.00 MW 106.00 MW

    Shikalbaha ST 40.00 MW 0.00 MW 0.00 MW

    b) Shikalbaha Peaking (GT) 150.00 MW 110.00 MW 120.00 MW

    Hathazari 98.00 MW 23.00 MW 88.00 MW

    Shikalbaha(Energis) 0.00 MW 0.00 MW 0.00 MW

    Dohazari Sangu 102.00 MW 34.00 MW 51.00 MW

    Julda 100.00 MW 80.00 MW 102.00 MW

    Malancha, Ctg. EPZ(United)

    0.00 MW 0.00 MW 23.00 MW

    Barabkunda (Regent) 22.00 MW 17.00 MW 17.00 MW

    a) Ashuganj ST Unit -1,2 110.00 MW 40.00 MW 40.00 MWb) Ashuganj ST 3 140.00 MW 140.00 MW 140.00 MW

    Ashugonj ST 4 150.00 MW 140.00 MW 140.00 MW

    Ashugonj ST 5 140.00 MW 80.00 MW 80.00 MW

    c) Ashuganj CCPP-146MW 91.00 MW 40.00 MW 40.00 MW

    d) Ashuganj 50 MW 51.00 MW 28.00 MW 25.00 MW

    Ashuganj (Precision) 55.00 MW 51.00 MW 57.00 MW

    Ashuganj (Aggreko) 80.00 MW 77.00 MW 82.00 MWAshugonj Up-53 MW 53.00 MW 53.00 MW 53.00 MW

    Ashuganj Midland 51.00 MW 0.00 MW 0.00 MW

    Brahmanbaria (Agrico)(Gas)

    70.00 MW 70.00 MW 72.00 MW

    Daudkandi 50 MW 52.00 MW 0.00 MW 49.00 MW

    Chandpur CCPP 163.00 MW 155.00 MW 0.00 MW

    Feni (Doreen) 22.00 MW 17.00 MW 18.00 MW

    Feni, Mahipal (Doreen) 11.00 MW 8.00 MW 5.00 MW

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    50/111

    50

    Jangalia (Summit) 33.00 MW 32.00 MW 32.00 MW

    Summit Power, Comilla 25.00 MW 18.00 MW 21.00 MW

    RPCL,CCPP, Mymensingh 197.00 MW 146.00 MW 145.00 MW

    Tangail (Doreen) 22.00 MW 15.00 MW 18.00 MW

    Fenchuganj CCPP-1 (Gas) 90.00 MW 66.00 MW 68.00 MW

    Fenchuganj CCPP-2(New) 104.00 MW 84.00 MW 82.00 MW

    Fenchuganj (BEDL) 51.00 MW 42.00 MW 42.00 MW

    Fenchuganj Prima 50 MW 50.00 MW 46.00 MW 50.00 MW

    Hobiganj (Confidence-EP) 11.00 MW 10.00 MW 10.00 MW

    Shajibazar GT Unit-8, 9 66.00 MW 63.00 MW 68.00 MW

    Shajibazar 86 MW 86.00 MW 74.00 MW 74.00 MW

    Shajibazar - 50 MW 50.00 MW 45.00 MW 47.00 MW

    Sylhet 150MW 142.00 MW 0.00 MW 108.00 MW

    Sylhet GT (Gas) 20.00 MW 17.00 MW 19.00 MW

    Sylhet 50 MW 50.00 MW 41.00 MW 44.00 MW

    Sylhet 11 MW 10.00 MW 7.00 MW 9.00 MW

    Shahjahanulla 25mw 25.00 MW 14.00 MW 24.00 MW

    Bheramara GT (Unit-1,2,3) 46.00 MW 32.00 MW 32.00 MW

    Bheramara 105.00 MW 0.00 MW 0.00 MW

    a)Khulna ST 110 MW 55.00 MW 0.00 MW 58.00 MW

    HVDC C/B. Interconnector 500.00 MW 403.00 MW 304.00 MW

    b)Khulna ST 60MW 30.00 MW 0.00 MW 0.00 MW

    KPC, Khulna 110.00 MW 53.00 MW 100.00 MW

    KPCL Khulna (New) 115.00 MW 99.00 MW 99.00 MW

    Khulna 150 MW 150.00 MW 156.00 MW 158.00 MW

    Faridpur 54.00 MW 19.00 MW 45.00 MW

    Gopalganj 110 MW 109.00 MW 0.00 MW 32.00 MW

    Noapara (105MW)Quantam

    101.00 MW 0.00 MW 0.00 MW

    Noapara (40MW),KZA 40.00 MW 40.00 MW 40.00 MW

    Khulna 40 MW 40.00 MW 0.00 MW 0.00 MW

    Khulna 55 MW 55.00 MW 42.00 MW 53.00 MW

    Barisal Diesel(HSD) 0.00 MW 0.00 MW 0.00 MW

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    51/111

    51

    Barisal GT 1& 2 32.00 MW 15.00 MW 15.00 MW

    Bhola Venture 33.00 MW 0.00 MW 0.00 MW

    a)Baghabari GT 1 71.00 MW 67.00 MW 69.00 MW

    b)Baghabari GT 2 100.00 MW 95.00 MW 100.00 MW

    Baghabari 50 MW 52.00 MW 32.00 MW 32.00 MW

    Baghabari Westmont 70.00 MW 0.00 MW 0.00 MW

    Bera 70 MW 71.00 MW 67.00 MW 70.00 MW

    Amnura 50 MW 50.00 MW 51.00 MW 50.00 MW

    Khtakhali NPS 50MW 50.00 MW 50.00 MW 50.00 MW

    Katakhali PPP 50 MW 50.00 MW 18.00 MW 46.00 MW

    Sirajganj 150 MW 150.00 MW 75.00 MW 72.00 MW

    Santahar 50MW 50.00 MW 46.00 MW 46.00 MW

    Bogra GBB 22.00 MW 17.00 MW 21.00 MW

    Rajlanka 52MW 52.00 MW 52.00 MW 52.00 MW

    Barupukuria ST 1 100.00 MW 90.00 MW 90.00 MW

    Barupukuria ST 2 100.00 MW 92.00 MW 93.00 MW

    Bogra 20 MW 20.00 MW 9.00 MW 9.00 MW

    Summit Powser(Ullapara) 11.00 MW 8.00 MW 10.00 MW

    Rangpur GT (HSD) 20.00 MW 10.00 MW 17.00 MW

    Syedpur GT 20MW(HSD) 20.00 MW 18.00 MW 18.00 MW

    Thakurgaon 47 MW((RZ) 47.00 MW 31.00 MW 28.00 MW

    Total 9783.00 MW 6100.00 MW 6376.00 MW

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    52/111

    52

    CHAPTER 4

    TRANSMISSION SYSTEM OF BANGLADESH

    4.1 TRANSMISSION SYSTEM

    The system by which the electrical power transmitted from generating station to distribution

    system is known as transmission system. The transmission line divided in two parts:

    1. Primary transmission

    2. Secondary transmission

    4.2 PRIMARY TRANSMISSION

    The electric power at 132 KV is transmitted by 3-phase 3-wire over head system to the outskirts

    of the city. This form is the primary transmission.

    4.2.1 GRID SYSTEM

    The entire AC network is interconnected network called national grid. Even neighboring national

    grid are interconnected to from sub grid. In power system when all generating station line with the

    operation of substation called grid system of electric power.

    In the grid system of Bangladesh power development board, mainly two types of transmission

    lines are used. These are 230KV and 132KV lines. Also there is another grid line of Bangladesh

    i.e. 66KV.

    4.2.2 GRID SUB-STATION

    As in Bangladesh there are two types of grid transmission line, one 132KV line and other 230KV

    line. So we have mainly two categories grid substation. The total number of grid substation

    operated as of 2012 is 95, of which13 number are 230KV and 82 numbers are 132KV. Capacity

    of 230KV grid substation is 6675MVA and 132KV is 8587MVA and their transmission length are

    2647.3 circuit km and 6071.34 circuit km

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    53/111

    53

    4.3 SECONDARY TRANSMISSION

    The primary transmission line terminates at the receiving station which usually lies as the

    outskirts of the city. At the receiving station, the voltages are reduced to 33KV by step down

    transformers. From this station, electric power is transmitted at 33KV by three phase three wire

    overhead system to various sub stations located at the strategic points in the city. This form is the

    secondary transmission.

    4.4 CLASSIFICATION OF OVERHEAD TRANSMISSION LINE

    The overhead transmission lines are classified as

    a) Short transmission line

    b) Medium transmission line

    c) Long transmission line

    a) Short transmission line:When the length of an overhead transmission line is up to 50km and

    the line voltage is comparatively high (20KV 100KV), it is usually considered as a Long

    transmission line.

    4.5 DEFINATION OF IMPORTANT TERMS:

    1. Earthling or grounding: Connecting to earth or ground.

    2. Neutral earthing: Connecting to earth, the neutral point i.e. the star point of generator,

    transformer, rotating machine, neutral point of grounding transformer.

    3. Reactance earthling: Connecting to the neutral point to earth through a reactance.

    4. Resistance earthling: Connecting to the neutral point to earth through a resistance.

    5. Non effecting earthling: when an intentional resistance or reactance is connected between

    neutral point and earth.

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    54/111

    54

    6. Solid earth or effective earth line: Connecting to the neutral point to earth without

    intentional resistance or reactance co-efficient earthling.

    7. Resonant earthing: Earthing through a reactance of such as value that power frequency

    current in the neutral to ground connection almost equal opposite to power frequency

    capacitance current between unsalted line and earth.

    8. Co-efficient of ear thing: it is defined as the ratio of highest r.m.s voltage of healthy line to

    earth to the line r.m.s voltage.

    9. Petersen coil, suppression coil, ground fault neutralized: All the three terms have the same

    meaning the adjustable reactor connected between neutral to earth.

    10.Underground system: The system whose neutral point is not earth.

    11.Earth fault factor: It is calculated at the selected point of the system for a given system. It

    is a ratio of fault factor =V1/V2.

    Where,

    V1 = highest r.m.s phase to phase power frequency voltage of sound

    phase during earth fault on another phase.

    V2= r.m.s phase to phase power frequency voltage at the same

    location with fault on the faulty removed.

    12.Bus coupling transformer: it is a special kind of transformer using in electric power

    transmission line. It is a bidirectional device that makes injection or taking electric power

    between two buses. It is also a matching or interfacing transformer between two buses.

    13. Bus: There are three kinds of buses in power system

    a) PQ bus b) PV bus and c) Stack or swing or reference bus.

    For studying and analyzing an electric bus, we have to need for important variables.They are:

    a) P-active power b) Q-reactive power

    c) V-voltage and d) -swing angle

    4.6 ADVANTAGE OF HIGH VOLTAGE TRANSMISSION LINE

    The transmission of electric power is carried at high voltage due to the following reason:

    a) To reduce the volume of conductor material.

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    55/111

    55

    b) To increase the transmission efficiency and

    c) To decrease the percentage line drop

    4.7 ADVANTAGES AND DISADVANTAGES OF HIGH VOLTAGE DC

    TRANSMISSION

    Advantages:

    i. It requires only two conductors as compared to three for ac transmission.

    ii. There is no inductance, capacitance, phase displacement and surge problem in dc

    transmission.

    iii. A dc transmission. Line has better voltage regulation as compared to the line for same load

    and sending voltage.

    iv. There is no skin effect in dc system.

    v. A dc line requires less insulation as compared to ac line for the same working voltage.

    vi. A dc line has less corona loss and interference with communication circuit.

    vii. The high voltage dc transmission is free from the dielectric losses, particularly in the case

    of cables and

    viii. In dc transmission, there is no stability problem and synchronizing difficulties.

    Disadvantages:

    i. Electric power cannot be generated at high voltage dc due to commutation problems.

    ii. The dc voltage cannot be stepped up for transmission of power at high voltages and

    iii. The dc switches and circuit breaker have their own limitations.

    4.8 TRANSMISSION SYSTEM OF DIFFERENT COUNTRIES

    4.8.1 TRANSMISSION SYSTEM OF INDIA:

    Bulk transmission system has increased to more than 165000 Circuit kmtoday. The entire country

    has been divided into five regions for transmission systems. Namely:

    1. Northern region

    2. North Eastern region

    3. Eastern region

  • 8/10/2019 STUDY OF ELECTRICAL POWER GENERATION,TRANSMISSION & DISTRIBUTION IN BANGLADESH

    56/111

    56

    4. Southern region

    5. Western region

    Indias transmission system comprises a 400KV network as the main and bulk transmission

    system at each region, 132KV and 110KV network as the main and support transmission systems

    in each state, 66KV, 33KV and 22KV network as sub transmission system, frequent power cuts,

    unscheduled shut downs and severe restrictions on industrial usage during summer months are

    constraint on industrial development and overall economic development of the country. In this

    context, POWERGRID is involved in along term plan for the development of an Indian national

    transmission network to make efficient usage of generating capacity. As part of this strengthening

    of the national grid, POWERGRID had developed series of high voltage direct current (HVDC)

    inter regional links between North, East, South and westerns of Indias power system.

    4.8.2 TRANSMISSION SYSTEM OF SRILANKA

    Transmission voltage levels:

    a) 220KV

    b) 132KV

    Transmission lines

    220 KV----------------331km

    132KV-----------------1684km

    Grid substations NO. MVA

    132/33KV 40 2570

    220/132/33KV 6 2205

    132/11KV 4 306

    4.8.3 TRANSMISSION SYSTEM OF NEPAL

    Nepal transmission voltage