20
Electronic scoring systems SIUS AG Im Langhag 1 | CH-8307 Effretikon | Switzerland Phone +41 52 354 60 60 www.sius.com | [email protected] • Installation • Start-up • Function control / updates / support STYX network

STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

  • Upload
    others

  • View
    14

  • Download
    0

Embed Size (px)

Citation preview

Page 1: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

Electronic scoring systems

SIUS AGIm Langhag 1 | CH-8307 Effretikon | Switzerland

Phone +41 52 354 60 60www.sius.com | [email protected]

• Installation• Start-up• Function control / updates / support

STYX network

Page 2: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

2

InstallationSTYX networkElectronic scoring systems

B-INST-STYX-en – 04/20

Table of contents PageSTYX/LON hybrid networkInstallation overview 3Description and connectors of STYX network components 4–8STYX cables 9

CablingTarget line 10Lane scoreboards 11Firing line 12Segment control (10-Lane-Command-Desk) 13Control room 14

Rack SR01 – structure and cabling 15–16

Start-up- pending 18

Function control / updates / support- pending 19–20

Table of contents

Page 3: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

B-INST-STYX-en – 04/20

3

Electronic scoring systemsInstallation

STYX network

Targ

et li

ne

Firin

g lin

e

Lane

sco

rebo

ards

Segm

ent c

ontr

ol

Con

trol

room

Wei

tere

Lan

e Sc

oreb

oard

sW

eite

re S

egm

entk

ontro

lle

STYX/LON hybrid network Installation overview

Installation overviewSegment with 20 lines

L

ON

Lege

ndC

ablin

g

110

V–24

0V

LO

N-B

ackb

one

U

SB

Eth

erne

t

STY

X

Page 4: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

4

InstallationSTYX networkElectronic scoring systems

B-INST-STYX-en – 04/20

STYX network components

Pos. 1SNC01 STYX network connector

The STYX network connector connects maximally 5 devices (targets or lane scoreboards) with the network. The installation should be made at an easily accessible place protected from ammunition fragments (e.g. in a cable duct) in the middle of the devices to be connected. In a STYX segment maximally 4 SNC01 STYX network connectors (for 20 devices) can be linked together. Following STYX segments must be connected separately direct to the rack in the control room.

Pos. A1.1SPS01 power supply for STYX network connector

Power supply for SNC01 STYX network connector and devices connected to it, equipped with a country-specific device plug and a corresponding connection cable.

SPS01 Power supply(48V)

FromSNC02 STYX network connector

(rack/control room)or previous

SNC01 STYX network connector

Tonext

SNC01 STYX network connector

STYX device 1

STYX device 2

STYX device 3

STYX device 4

STYX device 5

Do not remove the existing protective covers of unused

channels.

● On (green) = power

Control lamps

● Max (orange) = max. data speed

● Err (red) = error

● Link (green) = connection with device Device plug(power supply)

ToSNC01 STYX

network connector

Pos. Article no. DescriptionSTYX network components

1 SNC01 STYX network connector (for max. 5 targets resp. lane displays), Dimensions (WxHxD): 283x41x43mm, Weight: 0,5kg1.1 SPS01 Power supply for STYX network connector 48V/5A, Dimensions (WxHxD): 220x40x68mm, Weight: 1,3kg

Country-specific power supply cable > AA1**

Description and connectorsSTYX network components

Page 5: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

B-INST-STYX-en – 04/20

5

Electronic scoring systemsInstallation

STYX network

Description and connectorsSTYX network components

Pos. 2STE01 adapter STYX to ethernet

This adapter enables the connection of printers resp. PC’s/laptops to the STYX-network.

Pos. 3STL01 converter STYX to LON

The converter is the interface from the STYX to the LON network. By using it, devices, which only have a LON connec-tor can be integrated in the network.

ConnectorSTYX network

Connectorethernet

(to printer/PC/laptop) LON

connectorSTYX

connector

Control lamps

● ACT (orange) = communication activity

● Link (green) = connected to LON network

● Wink (green) = device identification

● Watchdog (yellow) = function monitoring

Pos. 4SLS01 STYX lane scoreboard

The SLS01 STYX lane scoreboard receives the data of the according lane and sends those as a video signal to the connected screen TV.

LON connector (not in use)

STYX connector (from SNC01 STYX network connector)

HDMI (to connected screen TV)

Pos. Article no. DescriptionSTYX network components

2 STE01 Adapter STYX to Ethernet, Dimensions (WxHxD): 69x44x40mm, Weight: 0,2kg3 STL01 Converter STYX to LON, Dimensions (WxHxD): 205x53x160mm, Weight: 0,6kg4 SLS01 STYX lane scoreboard incl. dowels/screws for wall mounting, Dimensions (WxHxD): 205x53x160mm, Weight: 0,6kg

Page 6: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

6

InstallationSTYX networkElectronic scoring systems

B-INST-STYX-en – 04/20

Pos. 5SR01 Rack 19"

STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack.

The rack is equipped with removable side panels on both sides which enables easy access, even with already moun-ted devices.

The rack has openings on top, bottom and in the rear for cable routing. The cover plates can be broken out.

top

rear

bottom

Mounting to a wall:

In the rear the rack is equipped with a mounting bracket, which enables the mounting to a wall.

The mounting bracket is fixed with screws to the rack. These must be removed from inside of the rack.

The mounting bracket can be removed now.

It can be mounted with screws and dowels at the required height to the wall.

The rack can be hooked up to the mounting bracket on the wall. Finally affix it with the screws from inside of the rack.

Pos. Article no. DescriptionSTYX network components

5 SR01 Rack 19" incl. 6 way power distribution cable, Dimensions (WxHxD): 600x450x505mm, Weight: 16kg

Country-specific power supply cable > AA1**

Description and connectorsSTYX network components

Page 7: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

B-INST-STYX-en – 04/20

7

Electronic scoring systemsInstallation

STYX network

Pos. 5.2SNS01 STYX network server

The SNS01 STYX network server is placed in the rack.It saves and manages all data and services.

Pos. 5.1SNC02 STYX network connector 19"

The SNC02 STYX network connector 19" is placed in the rack and establishes the connection with all used STYX devices in the network. If not enough free channels are available, further SNC02 STYX network connectors can be connected. STYX segments (of 20 targets / lane scoreboards) must be connected in ascending order, i.e. STYX segment 1 (1–20) > STYX segment 2 (21–40) > STYX segment 3 (41–60) etc.

Opening for cable (power supply)

from behindSTYX

device 1STYX

device 2STYX

device 3STYX

device 4STYX

device 5Power supply

FromSNM01 STYX network master

or previousSNC02 STYX network connector

(rack / control room)

ToSNS01 STYX network server

or nextSNC02 STYX network connector

Control lamps: same as SNC01 STYX network connector (see page 5).

Power supply110V / 230V

PC/laptop(SIUS support)

STYX connector(to «Out» connector of

SNC02 STYX network connector)USB

Description and connectorsSTYX network components

Pos. Article no. DescriptionSTYX network components

5.1 SNC02 STYX-Network-Connector 19" inkl. Montageschrauben/-muttern, Masse (BxHxT): 482x43x220mm, Gewicht: 2kg5.2 SNS01V2 STYX network server «Infrastructure» (Infrastruktur) incl. mounting screws/nuts

Dimensions (WxHxD): 482x43x220mm, Weight: 1,5kg SNS01V3 STYX network server «Themelia» (Scheiben) incl. mounting screws/nuts

Dimensions (WxHxD): 482x43x220mm, Weight: 1,5kg SNS01V4 STYX network server «Kanopus» (Lane Score Boards) incl. mounting screws/nuts

Dimensions (WxHxD): 482x43x220mm, Weight: 1,5kg SNS01V1 STYX network server (spare, unconfigured) incl. mounting screws/nuts

Dimensions (WxHxD): 482x43x220mm, Weight: 1,5kg

Country-specific power supply cable > AA1**

Page 8: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

8

InstallationSTYX networkElectronic scoring systems

B-INST-STYX-en – 04/20

PC/Laptop(SIUS support)

Telephone /Overvoltage protection for network

Power supply(UPS001)

Power supply(to devices)

Pos. 5.4UPS001 uninterruptible power supply (option)

We recommend the installation of an UPS001 (needed for ISSF competitions).It secures an uninterruptible power supply for all devices in the rack and protects from data loss.

Pos. 5.3SNM01 STYX-Network-Master

The SNS01 STYX network master is placed in the rack.It manages the network and the adressing of the devices.The ethernet connector enables the access to the internet.

Power supply110V / 230V

PC/Laptop(SIUS support)

Ethernet (internet access)

Actuallynot in use

STYX connector(to «In» connector of

SNC02 STYX network connector in rack / control room)

Pos. Article no. DescriptionSTYX network components

5.3 SNM01 STYX network master incl. mounting screws/nuts, Dimensions (WxHxD): 482x43x220mm, Weight: 1,5kg5.4 UPS001 Uninterruptible power supply (option) 450VA/280W, incl. brackets and mounting screws

Country-specific power supply cable > AA1**

Description and connectorsSTYX network components

Page 9: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

B-INST-STYX-en – 04/20

9

Electronic scoring systemsInstallation

STYX network

STYX cablesSTYX network components

KSN001 STYX cablesThe cables are equipped with a female connector and a male connector. The maximum distance from a network connector to another network connector is 130m (2x65.0m cable). If the distance is larger then 130m, an additional STYX network connector must be connected.

Female Male

6mm

15mm

The following cables (lengths) are available:KSN001-0.7 STYX cable 0.7mKSN001-2 STYX cable 2.0mKSN001-3 STYX cable 3.0mKSN001-10 STYX cable 10.0mKSN001-20 STYX cable 20.0mKSN001-40 STYX cable 40.0mKSN001-65 STYX cable 65.0m

cables with unpowered devicesmax. length of connection (device to device) 130mmax. number of plugs between devices 4

max 130m

1 2 3 4

powered devices, max 20WThe cable length reduces to a maximum of 100m, if powered devices (max 20W) like a Styx to LON Converter or Styx Lane Scoreboards are connected.

cables with powered devices, up to 20Wmax. length of connection (device to device) 100mmax. number of plugs between devices 4

max 100m

1 2 3 4

powered devices, max 50WIf for example targets (LS2550) or control units (BD95) with a maximum of 50W power are connected to the cables, the maximum calbe length is 40m.

cables with powered devices, up to 50Wmax. length of connection (device to device) 40mmax. number of plugs between devices 4

max 40m

1 2 3 4

Page 10: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

10

InstallationSTYX networkElectronic scoring systems

B-INST-STYX-en – 04/20

Cabling target line The cabling of the targets is made according to the illustration below. The targets LS25/50 are equipped with a STYX connection cable, which also provides the power supply.

• 5 targets can be connected to a single STYX network connector SNC01.

• The STYX network connector SNC01 should be placed well protected (e.g. in a cable duct) in the middle of these 5 targets.

• The provided STYX connection cable of the targets is 1,4m long. Depending on the situation, extension cables are needed. The outer targets on either side (1+5 / 6+10 etc.) need an extension cable of min. 2.0m. Both inner targets (2+4 / 7+9 etc.) need an extension cable of min. 0.7m.

• The individual STYX network connectors SNC01 has to be connected.

• It is possible to connect a maximum of 4 STYX network connectors SNC01 to a STYX segment (= 20 targets).

1 2 3 4 5 6 7 8 9 10

STYX cable2.0mKSN001-2.0

STYX cable0.7mKSN001-0.7

STYX cable2.0m

KSN001-2.0STYX cable

0.7mKSN001-0.7

STYX cable 65mKSN001-65

STYX network connectorSNC01

STYX Power supplySPS01

STYX cable 7mKSN001-7

toSTYX network connector SNC01 (Segment control / TLCDBOX)

toSTYX network connector

SNC01(next 5 lines)

Target lineCabling

Installation and cabling can differ. The according installation plans are relevant.

Page 11: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

B-INST-STYX-en – 04/20

11

Electronic scoring systemsInstallation

STYX network

Cabling lane scoreboards The cabling of the lane scoreboards is made according to the illustration below. The TV screens / HDMI cables are (if not ordered from SIUS) not included in delivery and must be provided by the customer himself.

• 5 STYX lane scoreboards SLS01 can be connected to a single STYX network connector SNC01.

• The STYX network connector SNC01 should be placed well protected (e.g. in a cable duct / behind a panel) depending on the situation. The length of the cables depends on the placement of the devices.

• The individual STYX network connectors SNC01 has to be connected.

• It is possible to connect a maximum of 4 STYX network connectors SNC01 to a STYX segment (= 20 lane scoreboards).

• The first STYX network connector SNC01 of a segment has to be connected to the STYX network connector SNC02 (rack / control room).

1 2 3 4 5 6 7 8 9 10

STYX cableKSN001-L* (L*=length)

STYX cable KSN001-L*(L*=length)

STYX network connectorSNC01

STYX power supplySPS01

STYX cable 7mKSN001-7

toSTYX network connector SNC02 (rack / control room)

toSTYX network connector

SNC01(next 5 lines)

HDMI cable

STYX-lanescoreboardSLS01

116

(39)

(44.5)(44.5)

205

160

54Wall mountingSTYX lane scoreboard SLS01

The device has 2 openings on the bottom side.It can be mounted to a wall with theprovided dowels/screws.

TV screenlane

scoreboard

Lane scoreboardsCabling

Installation and cabling can differ. The according installation plans are relevant.

Page 12: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

12

InstallationSTYX networkElectronic scoring systems

B-INST-STYX-en – 04/20

Cabling

Cabling firing line (control units) The cabling of the SA951 control units is made according to the illustration below. It is a standard LON cabling of 10 control units, which has to be connected with the segment control (10 lane command desk).

Line1

Line2

Line3

Line4

Line5

Line10

Remote controlRC211

LON cable 2mKL001-2.0

LON cable 2mKL001-2.0

tosegment control

(10 lane command desk)Line printerD112-USB-N

Power supplyNT211

LON cable 2mKL001-2.0

T adapterKL001-T

Y cableKL013

TerminatorKL001-R

LON cableKL001-L*(L*= length)

Barcode scannerAAG133-80SX

Firing line (control units)

Installation and cabling can differ. The according installation plans are relevant.

Page 13: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

B-INST-STYX-en – 04/20

13

Electronic scoring systemsInstallation

STYX network

Cabling Segment control (TLCDBOX)

STYX to LON converter STL01

LON cable 1mKL001-1.0

LON cableKL001-L*(L*=lenght)

STYX cable 20mKSN001-20.0

STYX cableKSN001-L*(L*=lenght)

Tocontrol units(firing line)

10 lane command desk

ToSTYX networkconnector SNC02(rack/control room)or previousTLCDBOX

ToSTYX networkconnector SNC01(target line)or nextTLCDBOX

RouterRTR5000

LON cable 1mKL001-1.0

STYX cable 0.7mKSN001-0.7

STYX toethernetadapterSTE01

STYX power supply SPS01

TonextTLCDBOX

STYX network connectorSNC01

Terminator KL001-R

Terminator KL001-R

Legend: STYX network LON / LTW network Ethernet/USB/HDMI

Cabling segment control (10 lane command desk) The cabling of the segment control is made according to the illustration below. It is a combination of STYX and LON cabling.

Installation and cabling can differ. The according installation plans are relevant.

Cabling of devices inside the TLCDBOX

Devices are cabled according to picture below and then placed in the TLCDBOX.

Connection of the router RTR5000

The router RTR5000 has two LON-connections:- Backbone (link to next TLCDBOX)- Segment (link to control units)

Page 14: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

14

InstallationSTYX networkElectronic scoring systems

B-INST-STYX-en – 04/20

Control roomCabling

Central computer(SIUSDATA/SIUSRANK)Ethernet cable

AA203-L*(L*=lenght)

Internet access

Rack 19" SR01

1x STYX network master SNM01

3x STYX network connector SNC02

3x STYX network server 1xSNS01V4, 1xSNS01V3, 1xSNS01V2

Uninterruptible power supply UPS001

01–20

Segment 01 (01–20)

21–40

Segment 02 (21–40)

41–60

Segment 03 (41–60)

61–80

Segment 04 (61–80)

4 x STYX cable4 x KSN001-L* (L*=lenght)

4 x STYX-Kabel4 x KSN001-L* (L*=lenght)

STYX to ethernetadapter STE01

STYX to ethernetadapter STE01

STYX cableKSN001-L* (L*=lenght)

Cabling control room The cabling of the control room is made according to the illustration below, but can differ depending on the circumstances and the size of the installation. We recommend internet access for broadcasting and support.

Legend: STYX network LON / LTW network Ethernet/USB

Installation, cabling and number of devices can differ. The according installation plans are relevant.

Tolane scoreboards

Tosegment control(TLCDBOX > targets)

Access to the Internet is provided by the STYX Network Master SNM01. The Ethernet connection of the central computer is exclusively for the STYX network (Ethernet DHCP network setting) and is connected via the STE01 adapter. The computer may not be logged in to an additional LAN (e.g. via second Ethernet connection, USB adapter, WiFi etc.).

If data exchange between central computer and further devices is requested, it must be done via internet cloud as Dropbox, iCloud, GDrive etc.

Page 15: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

B-INST-STYX-en – 04/20

15

Electronic scoring systemsInstallation

STYX network

Cabling Rack SR01 structure

The side panels can be removed by simultaneously pressing both locking buttoms inwards.

Depending on local circumstances the attaching of the door can be changed (left/right side of the rack).

The enclosed SIUS sticker can be placed in front on the glass door.

If installing the optional UPS001 for an uninterruptible power supply, the mounting angles must be screwed to the bottom rails first. The position of the device should ensure that the glass door of the rack still can be closed.

Side view:

Screw the UPS001 to the mounting angles.

Structure and cabling of rack SR01 The rack is delivered assembled (without devices). For wall mounting > see page 6.Screws/nuts/angles for the installation of the devices are included.

With the provided screws and nuts the devices can be attached to the mounting rails. The number of required devices depends on the size of the installation.

Arrangement of devicesfrom top to bottom:

• 1x SNM01 STYX network master• 3x SNC02 STYX network connector• 3x SNS01 STYX network server

Option:• UPS001 uninterruptible power supply

7x

The mounting rails for the devices are premounted at the 6th hole of the bottom rails. That ensures that in front is sufficient space for cable routing.

4x

8x

Page 16: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

16

InstallationSTYX networkElectronic scoring systems

B-INST-STYX-en – 04/20

Cabling Rack SR01 cabling

top

rear

bottom

CablingThe rack has openings on top, bottom and in the rear for cable routing. The cover plates can be broken out.

Remove the cover plate of the requested openingfor cable routing.

The cables can be connected according to the illustration.Front view:

01– 20

01– 20

21– 40

21– 40

41– 60

41– 60

61– 80

61– 80

To printer (control room)

To modem (control room)for internet access

To central computer (control room)

To socket

ABCD

A B C D

4x

4x

Power supply from UPS001 Power supply from 6 way distribution cable AA377

STYX cable

Ethernet cable (to modem for broadcasting and online support)

FGHI

F G H

E

I K

Cables of STYX segments(of 20 targets / lane scoreboards)must be connected in ascending orderto the Network Connectors.

A > B > C > D > E > F > G > H > I > K

etc.

It is possible to connect targets and lanescoreboards to the same Network Connector. This must be done in ascending order.

To lane scoreboards

To segment control(TLCDBOX > targets)

Network Server«Kanopus»(Lane Score Boards)

Network Server«Themelia»(Targets)

Network Server«Infrastructure»(Infrastructure)

Page 17: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

B-INST-STYX-en – 04/20

17

Electronic scoring systemsInstallation

STYX network

-Cabling Rack SR01 cabling

Cable routing

The 6 way distribution cable A377 for power supply is included.

It can be attached with the provided cable tie The cables can be routed/attached according to the exampleslaterally to the mounting rail. shown below.

Power supply from UPS001 Power supply from 6 way distribution cable AA377

Rear view (power supply):

Geräte

Steckdose

To socket

Page 18: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

18

InstallationSTYX networkElectronic scoring systems

B-INST-STYX-en – 04/20

- -

Start-up / function control / updates / support

pending

Page 19: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

B-INST-STYX-en – 04/20

19

Electronic scoring systemsInstallation

STYX network

- -

Page 20: STYX network - SIUS · STYX network master, STYX network connector, STYX network server and the optional UPS (uninterruptible power supply) can be placed in the rack. The rack is

B-INST-STYX-en – 04/20

SIUS AGIm Langhag 1 | CH-8307 Effretikon | Switzerland

Phone +41 52 354 60 60www.sius.com | [email protected]