28
Su-Taş Mining Istanbul Cebeci, Sultangazi

Su-Taş Mining Istanbul Cebeci, Sultangazi · Istanbul Cebeci, Sultangazi . Project Targets – Business Overview •Su-Tas faced with strong competition in the region •Preliminary

  • Upload
    others

  • View
    14

  • Download
    0

Embed Size (px)

Citation preview

Su-Taş Mining

Istanbul Cebeci, Sultangazi

Project Targets – Business Overview

• Su-Tas faced with strong competition in the region

• Preliminary project scope/estimates began in 2005

• Infrastructure in Istanbul projected to grow – Third Bridge – Northern Marmara

connection roadway – City Growth/Expansion – New Airport Project

Plant Location

Istanbul Airport

Project Targets – Production Requirements

• Establish a more modern facility – Produce Concrete and Asphalt materials – Increase productivity from 450 TPH to 1,000 TPH – Increased Product shape/quality

• Washed Aggregates

– Improved Safety – Environmentally Responsible

• Dust Suppression • Noise Pollution • Reclamation • Landscaping • Water Recovery

Projection Upgrade

• Old Plant

– 450 TPH

• New Plant

– 1,000 TPH

Old Plant

Equipment Selection & Considerations

• (2) 3352 Jaw Crushers

• (2) K400+Cone Crushers

• (3) 4500 VSI Impactors

• (5) Horizontal Screens

• Fully Automated

• Product Support by Dizel Turbo – Local Parts Inventory

– Local Service Support

• Installation, Plant Commissioning

New Plant Flow and Layout

Site preparations, February 2016

System Installation

System Installation

System Installation

Primary Station – Jaw Crushers

Secondary Station – Cone Crushers

Tertiary Station – VSI’s

Horizontal Screens

Plant Closure

Automation System

New Plant

New Plant

New Plant

Mine field

Mine field

Mine field

www.su-tas.com