Upload
lizbeth-rose
View
212
Download
0
Embed Size (px)
Citation preview
Subcommittee On Pressure Relief Systems
API CRE Update
Clark Shepard
Spring 2010
1
Standard/RP Title Current Edition DateNotes or
CommentsExpected Publication
Date
Std 520 Part 1 Sizing, Selection, and Installation of Pressure-
relieving Devices in Refineries Part I—Sizing and
Selection
8th Edition, December 2008
Work items beginning in Spring 2010
9th Edition 2013
RP 520 Part 2 Sizing, Selection, and Installation of Pressure-
relieving Devices in Refineries Part II—
Installation
5th Edition, August 2003
Ballot 1Q10 6th Edition 2010
Std 521(ISO 23251)
Pressure-relieving and Depressuring Systems
5th Edition, January 2007
Ballot August 2011 (DIS)
6th Edition November 2012 (FDIS)
Std 526 Flanged Steel Pressure Relief Valves
6th Edition, May 2009
7th Edition 2Q14
Std 527 Seat Tightness of Pressure Relief Valves
3rd Edition, July 1991
Re-affirmed July 2007
2012
Std 2000 (ISO 28300)
Venting Atmospheric and Low-Pressure Storage Tanks
Nonrefrigerated and Refrigerated
6th Edition, November 2009 (API adopt back);
ISO release 2008
DIS June 2011 December 2012
Standard/RP Issues Cost/Reliability Issues
Std 520 Part I Task Force focused on RP 520 Part II
None identified
RP 520 Part II Work on inlet pressure drop section
Potential Cost Improvement - Potential revision and inclusion of 5% into inlet pressure drop criteria
Std 521(ISO 23251)
Challenge to heat flux equations
Potential Additional Cost – Work nearing completion where detailed equations based on CFD and test data can be used to validate existing simple methodology
Std 526/527 No issues None identified
Std 2000 (ISO 28300)
1. In/Out Breathing – Working with SCAST with regards to equation revisions
2. Documenting the basis of the heat flux equations for sizing emergency venting
3. Deflagration venting
1. Potential Additional Cost – Clarifying text when to use equations in Annex A (past API 2000 equations)
2. Cost neutral - Work continues on heat flux basis
3. Potential Additional Cost – Working with SCAST to define when frangible roofs can be acceptable for venting vapors during internal deflagration
Projects
1. PERF 99-05 PRV Stability Project evaluating multiple factors that could lead to instability (chattering) including inlet pressure drop – Plans to complete during 4Q10– Data reviewed this week appeared random although not all test
information has been analyzed
2. Heat Recovery Steam Generators (Waste Heat Boiler) in Sulfur Recovery Units– Breakout team – PRS working with HTE and Sulfur Expert– Focus is on pressure relief requirements to address tube failure