Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
ARAB ACADEMY FOR SCIENCE, T ECHNOLOGY AND MARITIME TRANSPORT
College of Engineering and Technology
SUBSEA PROCESSING THE TODAY AND FUTURE
CHALLENGE by
Ahmed Osama Bedair
A Thesis Submitted in Partial Fulfillment to the Requirements
for the Master's Degree in
Marine Engineering
Under supervision of
Prof. Dr. Mohamed EI NOllr Abdelradi
SEPTEMBER 2006
~
-~-:>~,~~ ,{.,tA'~
AlWI ACADEMY FOR SCIENCE, TEcHNOLOGY AND MARITIME TRANSPORT
College of Engineering and Technology
SUBSEA PROCESSING THE TODAY AND FUTURE
CHALLENGE
by
Ahmed Osama Bedair
A Thesis Subm itted in Partial Fulfillment to the Requirements
for the Master's Degree in
Marine Engineering
Prof. Dr. Mohamed EI Nour Abdelradi Supervisor
Prof. Dr. Abdel-Alim Hashem EI-Sayed Examiner
Dr. Eng. Yousri Elmehd<lwi Examiner
SEPTEMBER 2006
GLOSSARY
ACKNOWLEDGEMENT Pagei
ABSTRACT Page ii
INDEX Page iv
LIST OF TABLES Page vi
LIST OF FIGURES Page vii
NOMENCLATURE Page x
CHAPTER I Page I
CHAPTER 2 Page 10
CHAPTER 3 Page 18
CHAPTER 4 Page 79
CHAPTERS Page 116
CHAPTER 6 Page 122
CHAPTER 7 Page 139
APPENDIX I Page 149
APPENDIX 2 Page 150
APPENDIX 3 Page 151
APPENDIX 4 Page 152
ACKNOWLEDGMENT
I would like to express my sincerest gratitude and
appreciation to Prof. Dr Mohamed EI Nour Abd EI Radi , my
advisor , for his valuate guidance , his support and his
patience in helping me bring this research to completion
ABSTRACT
The booming trend for oil and gas activities is that the production comes from new smaller
and marginal fields including tieback fields to existing infrastructure and also larger fields in
deep and ultra-deep waters.
The industry will be faced with several challenges both technical and economical as these
fields may be complex in nature, tieback distances can be significant and so can the water
depths. The very unstable oil prices have also had a great impact on how these fields must be
developed and operated. More cost effective solutions must be developed to meet the
challenges related to future exploration and production from existing and new fields. All
these new requirements have been the basis and background for the development of sub sea
pressure boosting and processing systems, which include several different technologies to
enhance the production from new and mature fields. Most of these different technology
building blocks are successfully being used by operators
As the potential economic benefits of subsea boosting increases with increased water depths;
the dependence on the operator became less effective and the need to utilize deepwater
equipment became a second to none option. However, the deeper the equipment the more
critical becomes its reliability due to high intervention cost and the long waiting time for the
required vessels.
The dream of subsea processing is to take processing of hydrocarbons to the sea bed and
producing straight to shore instead of depending on expensive surface (onshore or offshore)
facilities. Subsea offers several advantages compared to traditional ways of producing,
processing and transportation from well to onshore terminals. This is made possible today by
many advances in development of key elements such as multi phase pumps, multiphase
meters, and flow lines instrumentation.
The opportunities and possible benefits related to subsea processing technologies are many;
however, there are uncertainties related to the performance of these systems. Significant
development and testing work has been undertaken in the effort of qualifying subsea
processing technologies, and several systems have also been successfully deployed. While
the technology itself is perceived as mature, limited operational experience is available. As a
consequence, the anticipated reliability and risks related to applying these systems are
subject to uncertainty.
Operators hesitate to be the first users of subsea processing technology before the benefits
are fully understood, and currently there is no subsea processing equipment deployed in the
Gulf of Mexico. One of the main concerns for the operators is the uncertainty related to the
operating expenditures and inteIVention costs related to "unforeseen" events and equipment
failures. lnteIVentions and repair operations could potentially be very expensive; long
waiting times for the required inteIVention vessels and resources and complicated
inteIVention operations could be significant economical risk contributors.
Subsea processing equipment is characterized by use of novel technologies or extended
application of existing technologies, increased reliance on remote operations and control
systems and introduces additional complexity in a deepwater subsea production system.
Further, when moving into deeper waters, the uncertainty related to whether "unforeseen"
events would occur increases as the technology is introduced into an operating environment,
which is different compared to shallow water operations. These and other factors have
motivated the interest in a risk assessment and risk comparison of subsea versus surface
based processing.
Objectives and Scope of Study
This study will start initially with an oveIView of the current production systems followed by
a presentation of separation strategies used to manage the onshore fields and offshore
platforms with a focus on strategies and technologies that could be adopted to boost the sub
sea processing and in particular separation technologies. The study will then follow by brief
presentation of challenges related to process/flow assurance and other operability issues
followed by a detailed risk comparison for subsea processing versus surface processing,
finally the study will then conclude with a case study for the Rosetta / Egypt, Simian and
Sapphire field that is being developed recently in a very aggressive and promising manner.
III
INDEX
CHAPTER I OIL AND GAS INDUST RY
1.1 OIL AND GAS PRODUCTION SYSTEMS
CHAPTER 2 REMOVAL OF LIQUIDS AND SOLJUS FROM GAS STREAM AT ONSHORE PLANTS
2. 1 REMOVAL MECHANISMS 10
2.2 SEPARATION TECHNOLOGIES 12
2.2.1 LIQUJU/GAS CAOLESCERS 12
2.2.2 THREE PHASE ROTARY SEPARATOR TURBINE 14
2.2.3 SPIRA FLOW DEMISTING CYCLONE 15
CHAPTER 3 SUBSEA PROCESSING
3.1 REMOVAL OF LIQUJUS AN D SOLI DS FROM OIUGAS IS STREAM AT SUBSEA PROCESS PLANTS
3.1.1 DOWNHOLE OIL I GAS SEPARATOR IS
3.1.2 SUB SEA SEPARATION AND INJ ECTION SYSTEM (SUBSIS 20 CONCEP1)
3.1.3 COMPACT SUB SEA SEPARATOR WITH INEGRATED 23 SAND MANAGEMENT SYSTEM
3.1.4 ULTRADEE P WATER-GRAYITY DASED SEPARATOR 25
3.1.5 TWISTER SUB SEA SEPARATION MODEL 30
3.2 SUBSEA PIG LAUNCHER 32
3.3 TRANSFER PUMPS 35
3.4 DEHYDRATION SYSTEMS 40
3.5 HEATING OF DEEPWATER FLOW LINES 47
3.6 POWER SUPPLY AND CONTROL SYSTEM 52
3.7 SUBSEA MAN IFOLDS 63
3.S SUBSEA LEAKAGE MONITOR 72
3.9 SUBSEA FLOWMETERS 74
CHAPTER 4 RISK COMPARISON SUBSEA VS SURFACE PROCESSING
4.1 DEEP WATER CHALLENGES 79
4.2 SUBSEA PROCESSING TECHNOLOGY 84
4.3 RISK IDENTIFICATION 95
4.4 RISK CAMPARISON 105
CHAPTERS DEEPWATER INSTALLATION OF SUBSEA HARDWARE
5.1 DEEPWATER INSTALLATION ISSUES 116
5.2 THE CHALLENGES 116
CHAPTER 6 CASE STUDY
6.1 PROJECT INFORMATION 122
6.2 DESIGN AND INSTALLATION ASPECTS 123
6.3 EXISTING SUB SEA FACILITIES - DESCRIPTION OF THE 128 FIELD
6.4 EXISTING EQUIPMENT· ONSHORE FACILITIES 128
6.5 ASSUMPTIONS 129
6.6 SUBSEA PLANT 129
6.7 RISK COMPARISON 130
CHAPTER 7 CONCLUSIONS AND RECOMMENDATIONS 139
REFERENCES 147
v
Table I
Table2
Table3
Table 4
Table 5
Table 6
Table 7
Table 8
Table 9
Table 10
Table II
LIST OF TABLES
Types of liquid/gas separators
Retrofits summary
Overview of the project activities
Summary of HAZID review of subsea processing
Risk values for the base case
Breakdown of gas related process ri sks
Summaries of the subsea processing risks
Base case - Annual frequency of hydrocarbon release
Subsea processing - Annual frequency of hydrocarbon release
Onshore Faci lity - Equipment summary
Indicative cost comparison for surface equipment VS subsea
equipment
VI
Figure 1
Figure 2
Figure 3
Figure 4
Figure 5
Figure 6
Figure 7
Figure 8
Figure 9
Figure 10
Figure II
Figure 12
Figure 13
Figure 14
Figure 15
Figure 16
Figure 17
Figure 18
Figure 19
Figure 20
Figure 21
LIST OF FIGURES
Offshore production systems
Typical fixed platforms
Typical compliant tower
Semi submersible platfonn
Typical floating production unites
Tension leg platform
Examples of spar platforms
Subsea processing (multiple wells)
Global subsea total expenditure 2004 - 2008
Global subsea expenditure (%) 2004 • 2008
Coalescer cut-away View
Aerosol sizes
Three-phase rotary Separators (RST3)
Spiraflow cyclones
Typical in-l ine, bulk gas: liquid downhole separator
Schematic SUBSIS unite
SUBS IS unite ready for installation
New subsea separator concept
Subsea separator as part of subsea system
Full-scale separator installed in test rig
Production with and without subsea separation
Figure 22
Figure 23
Figure 24
Figure 2S
Figure 26
Figure 27
Figure 28
Figure 29
Figure 30
Figure 31
Figure 32
Figure 33
Figure 34
Figure 3S
Figure 36
Figure 37
Figure 38
Figure 39
Figure 40
Figure 41
Figure 42
Figure 43
Figure 44
Hydrate-formation curve
Deepwater gravity separator
Typica1 Twister sub sea module with up to six twister tubes
mounted vertically around a vertical liquid degassing vessel
Modular subsea gas processing system including a Twister
debydration unit
Subsea pig launcher overall assembly
injection pump cross section drawing
Multiphase pump
Deep Booster system
Deep separation module pump
ceo Compact cyclonic degasser
ROY operation on the D1PSIS module by 1500 m water depth
Pump manifold and control system
Typical XLPE power cable cross section
Control umbilical reel spooling at factory
NAXYS subsea leakage monitor
Wet gas flowmeter
Chocke bridge versions - MPFM CBV
Pressure boosting of the well
The Framo subsea multi phase booster pump
Schematic showing how the V ASP system works
The Subsea waler separator - Troll Pilot
Flow assurance risks for a typical deepwater development
Offshore field general lay out
r igur. 45
figure 46
Figure 47
Figure 48
Figure 49
Figure 50
Figure 5 1
PLEM (pipeline end manifold)
10" PLET (pipeline end terminal)
4 - Slot manifold horizontal at 106m water depth
4 - Slot manifold horizontal at 308m water depth
6 - Slot deepewater manifold
4 - Slot manifold with high pressure high temperature
2 - Slot overtrawlable manifold at 260 water depth
IX
hfpd
CAPEX
CT
CVC
DAPS
DGS
DGWS
DIPSlS
DMC
DOWS
ESP
FEED
FP
FPSO
GLCC
GOR
HAZID
HPIHT
HSE
lRPA
LDA
LLCC
NOMENCLATURES
Barrel fluid per day
Capital expenditure
Compliant tower
Cameron Vertica l Connector
Dual action pumping system
Downhole gravity segregation
Downhole gas I water separator
Deep integrated production, separation and injection system
Deep water managing contractor
Downhole oil I water separator
Encapsulated subsea pump
Front end engineering and design
Fixed platfonn
Floating production, storage and amoading system
Gas liquid cylindrical cyclone
Gas I Oil ratio
Hazard identification
High pressure / High temperature
Health , safety and environment
Individual risk per annum
Low dosage additives
Liquid liquid cylindrical cyclone
MARS
MEG
MPFM
MTBF
MW
NPV
OPEX
PLEM
PLET
QRA
ROV
RSTJ
sev
SDA
SEPDIS
SPL
SUBSIS
SWL
TLP
TDU
UTB
VASI'
ves
VDF
we
Multi application re- injection system
Mono ethylene glycol
Multi phase flowmeter
Mean time between failures
Mega watt
Net present value
Operational expenditure
Pipeline end manifold
Pipeline end terminal
Quantitative risk assessment
Remote operated vehicle
Three phases rotary separator
Subsea control valve
Subsea distribution assembly
Subsea electrical power distribution system
Subsea pig launcher
Subsea separation and injection system
Safe working load
Tension leg platform
Tool deployment unit
Umbil ical distribution box
Vertical annular separation and pumping system
Vertical connection system
Variable frequency drive
Water content
WGM
XLPE
Wet gas flowmeter
High vo ltage insulated cable
XII