SunGuide SunGuide TM TM Software Development Project Software Development Project Release 4.0 Kick-off Meeting Release 4.0 Kick-off Meeting October 15, 2007 October 15, 2007

SunGuide TM Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Embed Size (px)

DESCRIPTION

SunGuide TM Software Development Project Release 4.0 Kick-off Meeting October 15, 2007. Agenda. Introductions. Agenda. Meeting Objectives. Provide overview of: Development Team Software Architecture Components being implemented Schedule Not an objective: Discuss specific design details. - PowerPoint PPT Presentation

Citation preview

Page 1: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

SunGuideSunGuideTMTM Software Development Project Software Development Project

Release 4.0 Kick-off MeetingRelease 4.0 Kick-off MeetingOctober 15, 2007October 15, 2007

Page 2: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 2

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Heller

1:20 – 1:30 Project Team Heller

1:30 – 2:45

Data FusionGUI / Map

Admin Editor

TSS

Reporting Subsystem

C2C Plugin

General Subsystem Tasks

Data Fusion Engine Tasks

Database

Heller

2:45 – 3:00 Break

3:00 – 3:45Travel Time Enhancements

General Subsystem Tasks, Probe Fusion (driver to TSS),

Probe Fusion Drivers, TSS Modifications

Heller

3:45 – 4:10

General activities:ATIS Coordination TasksDocumentationFAT Deployments

Heller

4:10 – 4:30 Schedule Heller

4:30 – 5:00 Open Discussion / Action Item Summary All

Page 3: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 3

Introductions

Page 4: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 4

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Heller

1:20 – 1:30 Project Team Heller

1:30 – 2:45

Data FusionGUI / Map

Admin Editor

TSS

Reporting Subsystem

C2C Plugin

General Subsystem Tasks

Data Fusion Engine Tasks

Database

Heller

2:45 – 3:00 Break

3:00 – 3:45Travel Time Enhancements

General Subsystem Tasks, Probe Fusion (driver to TSS),

Probe Fusion Drivers, TSS Modifications

Heller

3:45 – 4:10

General activities:ATIS Coordination TasksDocumentationFAT Deployments

Heller

4:10 – 4:30 Schedule Heller

4:30 – 5:00 Open Discussion / Action Item Summary All

Page 5: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 5

Meeting ObjectivesMeeting Objectives

Provide overview of:

– Development Team

– Software Architecture

– Components being implemented

– Schedule

Not an objective:

– Discuss specific design details

Page 6: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 6

Release 4.0 Development ActivitiesRelease 4.0 Development Activities(includes 3.1 Managed Lane activities)(includes 3.1 Managed Lane activities)

Page 7: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 7

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Heller

1:20 – 1:30 Project Team Heller

1:30 – 2:45

Data FusionGUI / Map

Admin Editor

TSS

Reporting Subsystem

C2C Plugin

General Subsystem Tasks

Data Fusion Engine Tasks

Database

Heller

2:45 – 3:00 Break

3:00 – 3:45Travel Time Enhancements

General Subsystem Tasks, Probe Fusion (driver to TSS),

Probe Fusion Drivers, TSS Modifications

Heller

3:45 – 4:10

General activities:ATIS Coordination TasksDocumentationFAT Deployments

Heller

4:10 – 4:30 Schedule Heller

4:30 – 5:00 Open Discussion / Action Item Summary All

Page 8: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 8

Project TeamProject Team

Page 9: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 9

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Heller

1:20 – 1:30 Project Team Heller

1:30 – 2:45

Data FusionGUI / Map

Admin Editor

TSS

Reporting Subsystem

C2C Plugin

General Subsystem Tasks

Data Fusion Engine Tasks

Database

Heller

2:45 – 3:00 Break

3:00 – 3:45Travel Time Enhancements

General Subsystem Tasks, Probe Fusion (driver to TSS),

Probe Fusion Drivers, TSS Modifications

Heller

3:45 – 4:10

General activities:ATIS Coordination TasksDocumentationFAT Deployments

Heller

4:10 – 4:30 Schedule Heller

4:30 – 5:00 Open Discussion / Action Item Summary All

Page 10: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 10

What is the Data Fusion EffortWhat is the Data Fusion Effort(From the FDOT FLATIS 511 DFS Specification)(From the FDOT FLATIS 511 DFS Specification)

Page 11: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 11

Release 4.0 Development Release 4.0 Development ActivitiesActivities

Page 12: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 12

SunGuide Modifications / Data SunGuide Modifications / Data Fusion: GUI / MapFusion: GUI / Map

Floodgate Message Editor

Reports Query & Display

Updated TSS Link Data & Editor

Event Management:

– SAE J2540: Local phrase to code mapping

– Duplicate/Conflicting event resolution

External Data Edits

Page 13: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 13

Adding SAE J2540 to EMAdding SAE J2540 to EM

EM GUI will be modified so the operator can select SAE ITIS (International Traveler Information Systems) codes

ITIS codes provide efficient “coding” for transmission to wireless devices (e.g. automobile)

2047 “entries” (not all used)

Page 14: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 14

J2540: Extended PhrasesJ2540: Extended Phrases

253 Phrases

Page 15: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 15

SunGuide Modifications: SunGuide Modifications: Admin EditorAdmin Editor

Data Fusion Configuration

– Select data types to be archived

– Confidence Index Value editor

– TVT link configuration

– Wind Gust threshold editor

SAE J2540 Phrase Mapping Support

Updated TSS Link Editing

Page 16: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 16

SunGuide Modifications: SunGuide Modifications: TSSTSS

Add support for geographical information about links

Geographical information will be in Data Bus and published via C2C

Page 17: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 17

Reporting SubsystemReporting Subsystem

New Data Fusion reports

Page 18: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 18

C2C Plugin TasksC2C Plugin Tasks

Updated C2C Link and Node data

New C2C Travel Time data type

New C2C Floodgate Message data type

New C2C Event data type using SAE J2540

New C2C Location Table data type using FDOT-provided data

Page 19: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 19

Data Fusion Subsystem:Data Fusion Subsystem:General Subsystem TasksGeneral Subsystem Tasks

Create a new subsystem (schemas and objects) SunGuide event and travel time retrieval Weather information retrieval (NWS RSS feeds) District EOC data retrieval Strategic Intermodal System data retrieval convert to

Location table New handlers for new weather and event data sources (4

handlers) FDOT Location table format, parsing and storage Input data sanity checking Metadata and data source support Performance monitoring and status reporting

Page 20: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 20

Data Fusion Subsystem:Data Fusion Subsystem:Data Fusion Engine TasksData Fusion Engine Tasks

External weather data

External TSS and TVT data

FHP CAD data

District EOC data

FDOT Location Table data

Fused event information

Data archiving

Page 21: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 21

Data Fusion Subsystem:Data Fusion Subsystem:Database TasksDatabase Tasks

Fused event tables

Location data tables

New data archiving tables

Update tables for Data Fusion Support

Develop scripts for installation upgrades

Generate new DBDD

Page 22: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 22

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Heller

1:20 – 1:30 Project Team Heller

1:30 – 2:45

Data FusionGUI / Map

Admin Editor

TSS

Reporting Subsystem

C2C Plugin

General Subsystem Tasks

Data Fusion Engine Tasks

Database

Heller

2:45 – 3:00 Break

3:00 – 3:45Travel Time Enhancements

General Subsystem Tasks, Probe Fusion (driver to TSS),

Probe Fusion Drivers, TSS Modifications

Heller

3:45 – 4:10

General activities:ATIS Coordination TasksDocumentationFAT Deployments

Heller

4:10 – 4:30 Schedule Heller

4:30 – 5:00 Open Discussion / Action Item Summary All

Page 23: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 23

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Heller

1:20 – 1:30 Project Team Heller

1:30 – 2:45

Data FusionGUI / Map

Admin Editor

TSS

Reporting Subsystem

C2C Plugin

General Subsystem Tasks

Data Fusion Engine Tasks

Database

Heller

2:45 – 3:00 Break

3:00 – 3:45Travel Time Enhancements

General Subsystem Tasks, Probe Fusion (driver to TSS),

Probe Fusion Drivers, TSS Modifications

Heller

3:45 – 4:10

General activities:ATIS Coordination TasksDocumentationFAT Deployments

Heller

4:10 – 4:30 Schedule Heller

4:30 – 5:00 Open Discussion / Action Item Summary All

Page 24: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 24

Travel Time Modifications Travel Time Modifications OverviewOverview

The FDOT CO is planning to deploy an LPR system along Interstate 10 around the Tallahassee area in early 2008. The LPR system will collect probe data for the SunGuide Software System to calculate travel times and post on Dynamic Message Signs (DMS).

The enhancement of existing TvT subsystem to include the message template consists of two phases with different destinations. This requirement stems from the SunGuide Footprint issue #51 and 224, and SwRI will implement this as enhancement.

Travel time calculation will allow probe based and station based calculation for a single segment.

Add capability for SunGuide to acquire data from AVI and LPR devices.

Page 25: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 25

Travel Time: Major ActivitiesTravel Time: Major Activities

Least squares trending analysis: involves changing the structure of TVT to now store past travel times and perform computations.

Allowing 5 alternate routes and doing comparisons of travel times on routes to determine the message: this involves storing alternate route messages (involved extensive database and schema changes).  The upper/lower bounds also has alternate route messages. 

Probe fusion:– AVI and LPR drivers– Dynamic link redefinition

Page 26: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 26

Modifications to Travel Time Modifications to Travel Time SubsystemSubsystem

Functionality:– Allow grouped TvT tags – Alternate routes– Formatting message based on sign characteristics– Calculate delay time and allow use in messages– Display travel times on GUI – Least-squares trending– Support for either probe or station based computation

for a single segment– Limit Travel time to single source of data– Display Multiple times on GUI– GUI Alert for no data

Page 27: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 27

Modifications to Travel Time Modifications to Travel Time Subsystem – con’tSubsystem – con’t

Specific changes:– Database Modifications– Existing schema Modifications– Add type of link to TSS (AVL, LPR, or other detector):

• Limit travel time links to one type of detection link• Allow multiple links to be defined for each travel time

segment (mark one as primary)• Modify database tables to store links differently• Change schema structure o Change admin editor for

setting up TvT links

Page 28: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 28

Probe Fusion DriverProbe Fusion Driver

General capabilities:

– Configure system parameters

– Archive tag read data

– Tag Matching/Filtering

– Fusion aspect

– Dynamic link redefinition

Page 29: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 29

Probe Fusion Driver – con’tProbe Fusion Driver – con’t

Probe Fusion Input Driver (a driver to TSS)– Driver will “pair up” reads to determine travel times

– Travel times will be published to Data Bus (which TvT can then access for generating messages)

– AVI Drivers:• TransCore Allegro IT2020• Sirit Identity Flex Title 21

– LPR Drivers:• PIPS P357 Video Processor• I-10 Tallahassee [TBD]

– Note: SunGuide will talk to the above devices using a TCP/IP socket (implies terminal server connection)

Page 30: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 30

Probe Fusion Driver – con’tProbe Fusion Driver – con’t

TSS Modifications:

– Add ability to store number of vehicles

– Add new device types

– Add notification of no data

Page 31: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 31

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Heller

1:20 – 1:30 Project Team Heller

1:30 – 2:45

Data FusionGUI / Map

Admin Editor

TSS

Reporting Subsystem

C2C Plugin

General Subsystem Tasks

Data Fusion Engine Tasks

Database

Heller

2:45 – 3:00 Break

3:00 – 3:45Travel Time Enhancements

General Subsystem Tasks, Probe Fusion (driver to TSS),

Probe Fusion Drivers, TSS Modifications

Heller

3:45 – 4:10

General activities:ATIS Coordination TasksDocumentationFAT Deployments

Heller

4:10 – 4:30 Schedule Heller

4:30 – 5:00 Open Discussion / Action Item Summary All

Page 32: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 32

ATIS Coordination TasksATIS Coordination Tasks

Coordination with Districts– 12 meetings (teleconference)– Action item follow-up

ATIS Contractor Coordination meetings:– C2C Interface management:

• 6 one hour teleconferences• 6 one day meetings in Florida• Action item follow-up

– Additional “general” teleconferences:• 12 two hour teleconference• Action item follow-up

– 6 one day meetings in Florida

Page 33: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 33

DocumentationDocumentation

Documents to be updated:– Software Requirements Specification (SRS)– Software Design Document (SDD)– Interface Control Documents (ICDs)– Version Description Document (VDD):

• Release 4.0 specific implementation notes as appropriate

– Software User’s Manual (SUM)– Database Design Document (DBDD)– Software Integration Plan (SIP)– Software Integration Case Procedures (SICP)– Administrator training material

Other:– Rational RequisitePro (requirements) Database

Page 34: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 34

Factory Acceptance Testing (FAT)Factory Acceptance Testing (FAT)

Steps:

– Functional Configuration Audit (FCA)

– Test Readiness Review (TRR)

– FAT Execution:

• April 7-11, 2008 in San Antonio (dates will be solidified by January 15, 2008

Software will be installed at TERL for IV&V and deployed to existing RTMCs after the IV&V

Page 35: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 35

Deployments Planned Deployments Planned

Deployment to existing installations (dates can be adjusted):

– D1

– D2

– D3

– D4

– D5

– D6

– D7

– TERL Considerations

– TVT usable on installation

– DFS coordinated with Statewide ATIS

Page 36: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 36

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Heller

1:20 – 1:30 Project Team Heller

1:30 – 2:45

Data FusionGUI / Map

Admin Editor

TSS

Reporting Subsystem

C2C Plugin

General Subsystem Tasks

Data Fusion Engine Tasks

Database

Heller

2:45 – 3:00 Break

3:00 – 3:45Travel Time Enhancements

General Subsystem Tasks, Probe Fusion (driver to TSS),

Probe Fusion Drivers, TSS Modifications

Heller

3:45 – 4:10

General activities:ATIS Coordination TasksDocumentationFAT Deployments

Heller

4:10 – 4:30 Schedule Heller

4:30 – 5:00 Open Discussion / Action Item Summary All

Page 37: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 37

ScheduleSchedule

Important dates:– Design Reviews:– Design Reviews:

• In person design reviews (Orlando):– Travel Time Nov 6-7– Data Fusion Nov 7-8

• Follow-up (teleconference):– Travel Time Dec 11– Data Fusion Dec 13

– FAT: April 7-11, 2008 – SwRI, San Antonio– IV&V: May 5-9, 2008 – TERL, Tallahassee

Post-development dates:– Deployment:

• Districts (order TBD): May 2008• Coordinated with Statewide ATIS deployment

Page 38: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 38

AgendaAgenda

Time Item Lead

1:00 – 1:10 Introductions and Opening Remarks Tillander

1:10 – 1:20 High Level Overview – meeting objectives Heller

1:20 – 1:30 Project Team Heller

1:30 – 2:45

Data FusionGUI / Map

Admin Editor

TSS

Reporting Subsystem

C2C Plugin

General Subsystem Tasks

Data Fusion Engine Tasks

Database

Heller

2:45 – 3:00 Break

3:00 – 3:45Travel Time Enhancements

General Subsystem Tasks, Probe Fusion (driver to TSS),

Probe Fusion Drivers, TSS Modifications

Heller

3:45 – 4:10

General activities:ATIS Coordination TasksDocumentationFAT Deployments

Heller

4:10 – 4:30 Schedule Heller

4:30 – 5:00 Open Discussion / Action Item Summary All

Page 39: SunGuide TM  Software Development Project Release 4.0 Kick-off Meeting October 15, 2007

Oct 15, 2007Release 4.0 Kickoff Meeting 39

Discussion ?