Upload
others
View
7
Download
0
Embed Size (px)
Citation preview
Superconducting RF cavities activities for
the MAX project
OECD-NEA TCADS-2 Workshop
Nantes, 22 May 2013
Marouan El Yakoubi, CNRS / IPNO
1
TCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
Contents
• 352 MHz spoke Cryomodule design
• 700 MHz test area
• 700 MHz Power couplers
• 700 MHz Power couplers conditioning setup
• Conclusions & Roadmap
2
TCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
3
MYRRHA / XT-ADS Accelerator Scheme
Βg = 0.47 section of the Linac5 cell cavity Freq = 704.4 MHzNominal accelerating voltage Eacc(Βg ) = 8.5 MV/m
IntroductionTCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
TCADS-2 Workshop, Nantes
4
F 1200
Connection to
Valves Box
Warm Stop Valve
Cavity Train Put on adjustable Posts
One Thermal
Shield (40K/80K)
Coupler Barometric
Compensation
Supporting Frame
Sliding Blocks 2 Beta 0.37, 352 MHz Spoke Cavities
Op. Temperatures : 2 K, 5/10 K, 40/80 K
352 MHz Cryomodule overviewH. Saugnac (IPNO)
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
TCADS-2 Workshop, Nantes
5
Electro Magnetic Optimization : CST
Mechanical Optimization : ANSYS.
Mechanical/EM coupled Simulations :
ANSYS
Detailed Drawings OK
Cavity Wall: Nb RRR>250 (thck. 3 mm)
Helium Vessel Ti Grade 2 (thck. 3 mm)
Epk
Bpk
352 MHz Spoke Cavity Beta 0,37
Optimized Parameters Optimized Parameters
Eacc normal operation;
Eacc fault tolerance
6,2
8,2 MV/m
Lacc=optimal beta x c x f [m] 0,315
Epk/Eacc 4,29 Tuning Sensitivity [kHz/mm] 156
Bpk/Eacc [mT/MV/m] 7,32 Sensitivity to Pressure
[Hz/mbar]
7,6 < SP< 14
G [Ohm] 109 Lorentz Force Factor
[Hz/(MV/m)2]
-6 < KL< -5,28
r/Q [Ohm] 217 Approximated Bandwidth 150 Hz
Qo @ 2K for Rres=20 nΩ 5,2.109 b optimal 0.37
H. Saugnac (IPNO)
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
TCADS-2 Workshop, Nantes
6
The CTS (CEA ‘Soleil’ Type) for The MAX Spoke cavities is the Same as the one Designed for the ESS Spoke Cavities.
PiezoActuators
Stepping Motor
Cold Tuning SystemH. Saugnac (IPNO)
Cavity elongation along its Axis
Coarse Range (Stepping Motor) ~ 150 KHZ @2K Limited by Max Stress
Fine Range (Piezo) > 300 Hz
Stiffness > 100 KN/mm
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
TCADS-2 Workshop, Nantes
7
A Power Coupler 352MHz, 20 kW CW (designed), 50 W. WARM WINDOW
Was manufactured, in the framework of Eurotrans and successfully tested at 8 kW (amplifier limitation) CW on a 350 MHz, beta 0.15 Spoke cavity in a Cryomodule configuration.
Basis for design
2 CF16 ports for vacuum measurements.
1 port for electron emission measurement pick up
1 water cooling loop for the window
Plain Copper Antenna
CF 63 on cavity
Thermal interception at 70 K (~15 W solid conduction) and ~ 10 K (~3 W solid conduction)
The Design (SNS Type) will be kept as it for MAX
Power coupler
H. Saugnac (IPNO)
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
8
RF Source 80 kW CW
160 kW DC Power Supply + IOT
700 MHz Cryomodule
• Cavity & tuning system
• Power Coupler
• RF source 80 kW CW
• Cryogenic Valves Box
700 MHz area
Cavity 5-cells β=0.47 700MHz Cryomodule
Power coupler
TCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
9
Cavity (5 cells)
Cavity coupling port
Outer conductor (Lhe-cooled @4.5K)
Inner conductor / Antenna (water – cooled)
Doorknob: Transition coaxial (power coupler) to rectangular waveguide (towards the IOT)
Vacuum
Air
Ceramic (97% alumina ) disc window (water-cooled)
Power coupler main view
Power couplers
(I)
(II)
(III)
TCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
10
Power Couplers
Heat exchanger received, vacuum tests revealed no leak.
•2 prototypes of window + antenna were brazed & delivered.
•1 ceramic disc have TiNdeposit (20 nm)
1 ceramic disc without deposit.
2 Power Couplers manufactured by SCT SocietyAnd checked at IPN Orsay in May 2009
TCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
11
17th to 21st Spet.2012 : the IOT has beensuccessfully re-tested with its RF circulator in fullreflection until 80 kW. The current of the circulatorcoil had been tuned to enable fast RF power increase(J. Lesrel )
The DC power supply can now be control througha Labview program via Ethernet (C. Joly )
RF power supply
25th sept. 2012 : The coupler conditioning bench wasassembled to the IOT
Conditioning started in October 2012 (E. Rampnoux)
TCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
12
Power Couplers conditioning setupPower coupler conditioning : Experimental setup
Conditioning cavity
TCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
13
Pre -conditioning (1 kW) of the couplers
Power ramped-up to 880 W in 24 h
Automatic procedure and control programvalidated.
RF
po
we
r (W
)
Time
Cin
Cout
E. Rampnoux & S. Berthelot
IN OUT
Cavity
TCADS-2 Workshop, Nantes
No multipacting detected during the lowpower test
Vacuum leak rate remained at: 1.210-8
mbar.l.s-1
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
14
Couplers conditioning
RF power conditioning couplers in CW operation mode @ 30 kW.
1,80E-08
3,80E-08
5,80E-08
7,80E-08
9,80E-08
1,18E-07
1,38E-07
1,58E-07
1,78E-07
0
5
10
15
20
25
30
35
00: 00: 00 00: 50: 03 1: 40: 05 2: 30: 08 3: 20: 10 4: 10: 13 5: 00: 16 5: 50: 18
Pre
ssu
re (
mb
ar.
l.s-1
)
RF
Po
we
r (k
W)
Time (hh:mm:ss)
RF Power
Vacuum Pressure
• RF power reaches 30 kW in 6 hours
• No safety system at fault
• Degradation of vacuum level from 17 kW.
TCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
15
Couplers conditioning
RF power conditioning couplers in CW operation mode @ 42 kW.
high vacuum level: Input coupler ceramic broken !
Hypothesis :• TiN deposit have weakened the ceramic
window.• Heat stress• Coupler conditioning with CW mode is not suitable
Ongoing :•Analysis under progress to understand what happened.• Modification of the conditioning procedure: operating in pulsed mode, which is the safe state-of-the-art.•New coupler TOSHIBA was prepared.
1,00E-08
1,00E-07
1,00E-06
1,00E-05
1,00E-04
1,00E-03
1,00E-02
1,00E-01
1,00E+00
0,00E+00
5,00E+03
1,00E+04
1,50E+04
2,00E+04
2,50E+04
3,00E+04
3,50E+04
4,00E+04
4,50E+04
0:00:300:01:000:01:310:02:010:02:310:03:010:03:320:04:020:04:32
Ps3
Vide Cin
Vide Cout
November 8, 2012
TCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
16
New TOSHIBA coupler
end of the antenna
Power Coupler manufactured by TOSHIBA Society
Mechanical constructions were achieved at IPNO (D. Grolet) .
Electron beam welding was carried out by SAFEL society.
outer envelope
TOSHIBA coupler is ready and qualified
TOSHIBA window
Internal antenna
TCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
TCADS-2 Workshop, Nantes
17
Goal: Improve the surface condition of the antennaReduce scratch marks on the antenna.
• Electro-polishing bath: Phosphoric acid + alcohol (propanol)
• Voltage Generator (10 V / 30 A)
. Eliminating a thickness
of 200 μm matter
. Appearance close to the
mirrorBefore After
Coupler electro-polishing @ LPSC
• Y. Gomez Martinez, P. De Lamberterie, T. Cabanel (LPSC)• R. Martret (IPNO)
Materiel
Results
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
TCADS-2 Workshop, Nantes
18
Gate = 20 µs rise time = 1nsPk = 64 kW
Test with low pulse frequency= 1 Hz (J. Lesrel)
• To prevent the temperature of the RF power supply diodes exceed 30°C
• No disjunction of the power supply 40 kV
IOT output Power meter
Current security 3.9A (not to exceed)
Pulsed test IOT
Chanel 2 = I HV
(4A/10V)
Chanel 1 = U HV(40kV/10V)
We can work in Pulsed Wave if the rate is low
Tests sent to Brucker company for validation
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
19
Conclusion & Roadmap The Spoke Cryomodule design is in progress.
A new power coupler was prepared in short time.
The IOT was tested successfully pulsed mode.
Re-assembling the conditioning bench with the IOT is under progress .
The power coupler conditioning will restart very soon and we plan a 2 weeks period for the
test.
A clean room session is foreseen for the end of June 2013: for the power coupler assembly.
The Module preparation & wave guide installation will start soon.
First INTEGRATED high power test @ CRYOGENIC TEMPERATURE: Summer 2013.
Goal before end 2013: reliability-oriented experiment with Digital LLRF + Cold tuningsystem + ADEX smart control to validate the fast fault recovery procedure.
TCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
20
I’ Would to Thank you very much for your attention
TCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
21
TCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
22
Conditioning @ 18 kW
A first travelling wave (CW) conditioning at 18 kW was foreseen.
1,00E-08
1,00E-07
1,00E-06
1,00E-05
1,00E-04
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
00:00:0000:00:0000:00:0000:00:0000:00:0000:00:0000:00:00Temps (h:mm;ss)
Ps3
Vide Cin
TCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
23
Gate =1,8 ms with rise time = 100 µs
TCADS-2 Workshop, Nantes
EL Yakoubi M. TCADS-2 Workshop, Nantes May 22, 2013
MAX meeting, Louvain
24