Upload
dinhnhan
View
212
Download
0
Embed Size (px)
Citation preview
Court File No.: 2056/14
ERT Case No.: 13-097/13-098
ONTARIO
SUPERIOR COURT OF JUSTICE
(Divisional Court)
B E T W E E N:
SHAWN DRENNAN and TRICIA DRENNAN
Appellants/
Appellants on Appeal
-and-
THE DIRECTOR, MINISTRY OF THE ENVIRONMENT
Respondent/
Respondent on Appeal
-and-
K2 WIND ONTARIO INC. OPERATING AS
K2 WIND ONTARIO LIMITED PARTNERSHIP
Respondent/
Respondent on Appeal
A N D B E T W E E N:
Court File No.: 2055/14
ERT Case No.: 13-084-13-087
SCOTTY DIXON, JENNIFER DIXON, THOMAS RYAN and CATHERINE RYAN
Appellants/
Appellants on Appeal
-and-
THE DIRECTOR, MINISTRY OF THE ENVIRONMENT
Respondent/
Respondent on Appeal
-and-
ST. COLUMBAN ENERGY LP
Respondent/
Respondent on Appeal
APPEAL UNDER Section 142.1 of the Environmental Protection Act
FACTUM OF THE APPELLANTS
MOTION FOR STAY PENDING APPEAL
August 29, 2014 FALCONERS LLP
10 Alcorn Ave, Suite 204
Toronto, ON M4V 3A9
Julian N. Falconer (LSUC 29465R)
Asha James (LSUC 56817K)
Tel: (416) 964-0495
Fax: (416) 929-8179
Counsel for the Appellants
TO: This Honourable Court
AND TO: Borden Ladner Gervais
Scotia Plaza
40 King Street West
Toronto, ON M5H 3Y4
Tel: (416) 367-6165
Christopher Bredt
Counsel for the Approval Holder & K2 Wind Power Inc.
AND TO: Davies LLP
155 Wellington Street West
Toronto, ON M5V 3J7
Tel: (416) 863-0900
Sarah Powell, James Bunting and Alexandria Pike
Counsel for the Approval Holder & K2 Wind Power Inc.
AND TO: McCarthy Tetrault LLP
TD Bank Tower
66 Wellington Street West, Suite 5300
Toronto, ON M5K 1E6
Tel: (416) 362-1812
Darryl Cruz, Eric Pellegrino and Chris Wayland
Counsel for Approval Holder, St. Columban Energy LP
3
TABLE OF CONTENTS
Part I: Overview
4
Part II: Facts
6
A. The Parties
6
I. St. Columban Project
6
II. K2 Wind Project
7
B. Regulatory Scheme for Renewable Energy Approvals
8
C. Appeal of the Director’s Decision to Grant the REAs
9
D. Appeal of the ERT Decision to this Honourable Court
9
E. Stay Pending Appeal
10
Part III: Issues
13
Part IV: Law and Analysis
13
Overview of the Test for a Stay Pending Appeal
13
A. Serious Question
15
B. Irreparable Harm
16
C. Balance of Convenience
23
I. The Inconvenience of the Respondents
23
II. The Public Interest
29
III. Analysis of the Balance of Convenience
32
Part V: Order Sought
33
Schedule “A” – List of Authorities
34
Schedule “B” – Legislation
35
4
PART I: OVERVIEW
1. The Appellants seek a stay of the construction of the St. Columban Energy LP Wind
Project and the K2 Wind Project, pursuant to Rule 63.02 of the Rules of Civil Procedure,1 s. 106
of the Courts of Justice Act2 and s. 24(1) of the Canadian Charter of Rights and Freedoms
3
restraining the Respondents St. Columban Energy LP (“St. Columban”), and K2 Wind Ontario
Inc., K2 Wind Ontario Limited Partnership (“K2 Wind”) from all construction-related activities
until the resolution of the appeals.
2. The appeal to the Divisional Court is brought jointly by three Appellants in this
proceeding. However, this motion for a stay pending appeal is only brought by the Dixon-Ryan
Appellants in respect of the St. Columban Project and the Drennan Appellants in respect of the
K2 Wind Project. No motion for stay pending appeal has been brought by the third appellant,
the Kroeplins, in the appeal before this Honourable Court.
3. These submissions will therefore address the St. Columban Project and the K2 Wind
Project.
4. The Appellants respectfully submit that the tripartite test for a stay is met in this case:
A. This appeal raises a serious question. This appeal challenges the
constitutionality of a regulatory scheme. Far from being frivolous or
vexatious, it engages the constitutional rights of rural Ontarians in respect
of the commercial development of an emerging technology.
1 Rules of Civil Procedure, RRO 1990, Reg 194 at r.63.02.
2 Courts of Justice Act, RSO 1990, c C.43 at s. 106.
3 Canadian Charter of Rights and Freedoms, The Constitution Act, 1982, Schedule B to the Canada Act 1982 (UK),
1982, c 11.
5
B. The Appellants are raising a Charter issue. They are seeking a revocation
of the REA rather than damages. The harms suffered by the Appellants in
issuing the REAs without engaging in any analysis of the health effects
and the constitutionality of the Director’s decision cannot be adequately
remedied by the revocation of the REA, because it is an ongoing harm.
Even if the appellants sought damages, their harms that they would suffer
are incapable of being remedied by damages.
C. The balance of convenience favours the Appellants. In the event that a
stay is granted, the Respondents’ liabilities to the OPA would be limited
because the stay would constitute a force majeure according to the terms
of the Respondents’ agreements with the OPA. Furthermore, the public
interest and the harms that would be suffered by the Appellants strongly
favour granting a stay.
5. This stay is vital to preserving the Charter rights of the Appellants. Should a stay not be
granted, the Appellants would be subjected to a continued deprivation of their security of the
person interests. They will be subjected to the construction of a wind project in respect of which
government authorities are uncertain as to the health effects.
6. Accordingly, the Appellants submit that this Honourable Court should grant a stay to the
Appellants.
6
PART II: FACTS
The Parties A.
I. St. Columban Project
7. The Dixon-Ryan Appellants live in Seaforth, Ontario, which is in Huron East County.
This is the same county which is host to the St. Columban Wind Project. The Dixons live on a
96.8 acre farm with their two young children. The St. Columban Project will consist of 15
industrial wind turbines, with a total name plate capacity of 33MW. The Dixons will have one
turbine located 551 meters from their home, and they will have a second turbine located 552
meters from their home.4
8. The Dixon’s daughter suffers from hyper-sensitive hearing and gets headaches from
noises such as sirens. The Dixon’s are concerned that the audible and inaudible noise (low
frequency and infrasound noise) from the turbines will negatively impact the health of their
daughter. When a wind company positions a wind turbine it must be 550 meters from the center
of a residence. Unfortunately, in the Dixon’s case, their children’s bedroom will be closer to the
turbine than this permissible set back distance because of where the bedrooms are located in their
home.5
9. The Ryan Appellants also live in Huron East County and have a 150 acre farming
property on which they operate a dairy farm with approximately 70 milking cows and 150 head
of cattle. The Ryan farm has been in the family for nearly 150 years and the Ryan Appellants
4 Affidavit of Jennifer Dixon, sworn, June 11, 2014, paras 1-2.
5 Ibid at paras 5-6.
7
have lived on the property for 33 years. The Ryan Appellants will have one turbine 551 meters
from their home and a second turbine will be located about 800 meters from their home.6
10. The Respondent, St. Columban, is the owner/operator of the St. Columban Project and,
received a REA from the Respondent, Director of the Ministry of the Environment on July 2,
2013.
II. K2 Wind Project
11. The Drennan Appellants live in the Township of Ashfield-Colborne-Wawanosh, which is
the site of the K2 Wind Energy Project. The Project will consist of 140 industrial wind turbines,
a 270 MW substation and a 500 KW transformer station, the latter of which will be located
approximately 500 meters from the Drennan family home. The Drennans will also have a wind
turbine located approximately 715 meters from their home with another 11 turbines within a 2
kilometer radius of their home.7
12. The Drennan farm has been in the family since 1922 when Shawn Drennan’s grandfather,
Wilfred Drennan, moved to the farm. Shawn Drennan’s father, James Drennan, was raised on the
property and took over the farm operation in 1956. Shawn Drennan took over the farm operation
in 1983, and he and his wife Tricia represent the third generation of Drennans to live on and farm
this property, with their children being the fourth generation.8
13. The K2 Wind Project is owned/operated by the Respondent, K2 Wind. K2 Wind received
a REA from the Respondent, Director of the Ministry of the Environment on July 23, 2014.
6 Ibid at paras 9-10.
7 Affidavit of Shawn Drennan, sworn May 22, 2014, paras 1-2.
8 Ibid at paras 3-4.
8
Regulatory Scheme for Renewable Energy Approvals B.
14. Before a wind company begins construction on a wind project, it must obtain a REA from
the Ministry of the Environment (“MOE”), as outlined in Ontario Regulation 359/09 –
Renewable Energy Approvals under Part V.0.1 of the Environmental Protection Act, R.S.O. 1990
c. E.19 (“EPA”). Prior to submitting a REA application, an applicant is required to hold two
public meetings within the community. The wind company is required by the regulation to have
specified documents available at the public meetings. Once a submitted application is deemed
complete, the Director may, pursuant to section 47.5(1) of the EPA, if in his or her opinion it is
in the public interest to do so: (a) issue or renew a renewable energy approval; or (b) refuse to
issue or renew a renewable energy approval.
15. “Public interest” is not defined in the EPA or its regulations. The Director is not required
to provide reasons which outline why the wind project that receives the REA was deemed to be
in the public interest. Currently, Health Canada has undertaken a study to determine the risk
posed to residents living in close proximity to these industrial sized wind turbines. Health
Canada undertook this study because as the lead investigator for the study, Dr. David Michaud
testified, “there is a data gap between the dose-response relationship related to wind turbine
emissions.”9 Put quite simply, our governments have no idea how these large scale machines
impact on Ontario residents. Despite this fact that the MOE does not require a wind company to
produce a single document which addresses any possible health impacts associated with living in
close proximity to wind turbines.
9 Affidavit of Shawn Drennan, sworn May 22, 2014, paras 19-23; Affidavit of Jennifer Dixon, sworn June 11, 2014,
paras 31-35.
9
Appeal of the Director’s Decision to Grant the REAs C.
16. Under the EPA, once approval for a wind project is granted, an appeal of that decision
may be brought before the Tribunal. An appeal to the Tribunal can only be brought on two
grounds. The onus is on the Appellant to show that the renewable energy project will cause: a)
serious harm to human health, or b) serious and irreversible harm to plant life, animal life or the
natural environment.
17. The Dixon-Ryan Appellants filed a Notice of Appeal and Notice of Constitutional
Question before the Environmental Review Tribunal (the “ERT”) on July 16, 2013.
18. The Drennans filed a Notice of Appeal and Notice of Constitutional Question before the
ERT on August 6, 2013.
19. Both Appellants raised issues surrounding the constitutionality of the Director’s decision
along with the constitutionality of the test before the Tribunal.
20. On January 16, 2014, the ERT issued its decision dismissing the appeal in respect of the
St. Columban Project.
21. On February 6, 2014, the ERT issued its decision dismissing the appeal in respect of the
K2 Wind Project.
Appeal of the ERT Decision to this Honourable Court D.
22. The Drennans, and the Dixon-Ryans, jointly appealed their respective ERT decisions to
this Honourable Court. Notices of Appeal to this Honourable Court were filed on February 14,
2014 and February 28, 2014 in respect of the St. Columban Project and the K2 Wind Project,
respectively.
10
23. A third ERT decision involving an appeal by Kenneth George Kroeplin and Sharon Anne
Kroeplin in respect of the SP Armow Wind Project was also appealed to the Divisional Court.
24. On May 13, 2014, the Kroeplins filed a Notice of Appeal to this Honourable Court.
25. The Drennan appeal, the Dixon-Ryan appeal and the Kroeplin appeal involved the same
legal issues and each of the Appellants were represented by the same counsel. As a
consequence, the Appellants were successful in their motion to join the appeals into the herein
proceeding before this Honourable Court.
Stay Pending Appeal E.
26. In an effort to stem construction-related activities near their homes, the Drennans and the
Dixon-Ryans brought a motion for a stay pending appeal. The Dixon-Ryan notice of motion was
filed on June 17, 2014. The Drennans’ notice of motion was filed on May 28, 2014.
27. Both the Dixons and the Drennans gave evidence before the Tribunal and again in the
affidavits filed in support of this stay motion regarding the constant worry and anxiety
experienced related to the unknown effects the project could have on their family. This concern
is heightened by the fact that Health Canada is currently engaged in a study to understand the
effects that industrial wind projects have on residents living in close proximity to them.
28. Additionally, one of the very first decisions released by the Tribunal in respect of a wind
project, Erickson v. Director, Ministry of the Environment, the Tribunal held at page 206 of that
decision that:
This case has successfully shown that the debate should not be simplified to one about
whether wind turbines can cause harm to humans. The evidence presented to the Tribunal
demonstrates that they can, if facilities are placed too close to residents. The debate has
11
now evolved to one of degree. The question that should be asked is: What protections,
such as permissible noise levels or setback distances, are appropriate to protect human
health?
29. Currently, we do not have an answer to that question. That is precisely the question that
the Health Canada study seeks to answer. Despite knowing that harm will exist, and despite
knowing that the magnitude and degree of that harm is unknown to our government regulators,
the St. Columban and K2 Wind projects have been approved without any regard to the possible
health consequences for the Appellants. In effect, our government has relegated the Appellants to
guinea pigs in the name of green energy.
30. The fear and anxiety with being a guinea pig is only further heightened by the knowledge
that the Ontario Ministry of the Environment has placed a moratorium on off-shore wind turbines
because the environmental impact on the fish is unknown.10
In essence, the Appellants health
would have been more protected had they been fish.
31. The Dixon Appellants submit that the construction-related activities of St. Columban will
cause substantial and irreparable harm to them.
32. Jennifer Dixon’s eight year old daughter suffers from hyper-sensitive hearing which
causes her headaches. The intensity of her headaches varies based on the intensity and the
duration of the source of noise. The loud noise generated by construction activities of the St.
Columban Project will be a consistent source of discomfort for the Dixons’ daughter. In
addition, the Dixon’s daughter suffers from apneic periods at night and increased secretions.
10
Affidavit of Jennifer Dixon, sworn June 11, 2014 at para 30, Affidavit of Shawn Drennan, sworn May 22, 2014 at
para 18.
12
Disturbances during the night and the lingering effects of intense headaches could lead to a
permanent decrease in cognitive functioning. 11
33. The Drennan Appellants submit that the construction-related activities of the K2 Wind
Project will also cause substantial and irreparable harm to them.
34. The development of the K2 Wind Project creates a significant risk of serious and
irreversible damage to the Drennans’ property as a result of flooding. As part of its construction
activities, K2 has been illegally dumping drainage water onto the Drennans’ property.12
The
flooding of the Drennan property will cause deterioration in the quality of the soil as a result of
erosion. This in turn, results in lower crop yields.13
35. Furthermore, the construction activities are carried out in a manner that risks irreversibly
contaminating the region’s groundwater reserves.14
K2’s construction activities are undertaken
in areas where the depth to groundwater is less than 2 metres.15
36. Finally, in both cases, a decrease in property value is a real concern. The approval by the
Ministry of the Environment resulted in a decrease of 10% to the residential contributory value
of the Dixon’s property.16
Construction activities will inevitably result in a further decline in
property values. Attached as Exhibit “B” to the Affidavit of Jose Menendez, Vice-President of
St. Columban Energy, is a study by the Municipal Property Assessment Corporation.17
The
study is cited by Mr. Menendez as support for the proposition that wind turbines have no impact
on property values. The study in fact confirms the opposite. Mr. Menendez would be correct if
11
Affidavit of Jennifer Dixon sworn June 11, 2014 at paras 40 – 41. 12
Affidavit of Shawn Drennan sworn May 22, 2014 at para 38. 13
Affidavit of Shawn Drennan sworn May 22, 2014 at para 260. 14
Affidavit of Shawn Drennan sworn May 22, 2014 at para 28. 15
Transcript of Cross Examination of Paul Wendelgass, August 14, 2014 at page 73 16
Affidavit of Jennifer Dixon sworn June 11, 2014 at para 43. 17
Affidavit of Jose Menendez sworn July 21, 2014 at paras 24 – 25.
13
he confines the comparison to properties located within 1 kilometre of a wind turbine and
properties located between 2 and 5 kilometres of a wind turbines. The study concludes that there
is no statistically significant difference between property values in these two groups. However,
the study confirms that there is a significant difference in property values when comparing
properties located within 5 kilometres of a wind turbine and properties located more than 5
kilometres from a wind turbine.18
PART III: ISSUES
37. The issues before this Honourable Court is whether the Appellants meet the tripartite test
for granting a motion for stay, namely:
A. Is there a serious question to be tried?
B. Will irreparable harm result if a stay pending appeal is not granted?
C. Does the balance of convenience favour granting a stay pending appeal?
PART IV: LAW AND ANALYSIS
Overview of the Test for a Stay Pending Appeal
38. It is well-settled law that the tripartite test enunciated in RJR-MacDonald Inc. v. Canada
(Attorney General) applies in determining whether to grant a motion for a stay pending appeal.19
18
See Transcript of Cross-Examination of Jose Menendez dated August 15, 2014 at page 37 - 39. 19
RJR -- MacDonald Inc. v. Canada (Attorney General), [1994] 1 SCR 311, 111 DLR (4th) 385, 1994 CanLII 117
[RJR MacDonald].
14
39. In the first part of the test, a court must engage in a preliminary assessment of the
strength of the case by determining whether the applicant has demonstrated that there is a serious
question to be tried.
40. In the second part of the test, a court must determine if the applicant would suffer
irreparable harm if the application was refused.
41. In the third and final part of the test, a court must assess “which of the parties would
suffer greater harm from the granting or refusal of the remedy pending a decision on the
merits”.20
In addition, a court must account for the public interest in this part of the test.21
This is
known as the balance of convenience.
42. It is noteworthy that in Morguard Corporation v. InnVest Properties Ottawa GP Ltd., the
Ontario Superior Court held that:
There was a time when the courts tended to treat each of the three branches of the
test as requiring separate treatment, each independent of the others. The
preferable approach is to consider all three and assess their collective impact:
The terms ‘irreparable harm’, ‘status quo’ and ‘balance of convenience’
do not have a precise meaning. They are more properly seen as guides
which take colour and definition in the circumstances of each case. More
importantly, they ought not to be seen as separate, water-tight categories.
These factors relate to each other, and strength on one part of the test
ought to be permitted to compensate for weaknesses on another.
(Robert J. Sharpe, Injunctions and Specific Performance, loose-leaf
(Aurora: Canada Law Book, 2010) at para. 2.600)22
20
RJR MacDonald at para 43. 21
RJR MacDonald at para 80. 22
Morguard Corporation v. InnVest Properties Ottawa GP Ltd., 2012 ONSC 80 [This case considered whether to
grant an interlocutory injunction. It is trite law that the RJR MacDonald tripartite test applies to both stays and
injunctions. Accordingly, we rely on this case and other cases involving interlocutory injunctions as authority in
respect of stays pending appeal.].
15
43. In determining whether the test is met, a court must be careful to avoid determining
whether each of the three parts of the test is satisfied by the case. Instead, a court must assess the
three factors holistically.
Serious Question A.
44. The first branch of the test to determine whether a stay should be granted is whether the
case raises a serious question.
45. A court is not to enter into a rigorous analysis of the merits of the case. The threshold to
be met is simply that the claim is “not frivolous or vexatious”.23
The decision of a lower court
on Charter issues is relevant but it is not necessarily determinative of whether there is a serious
question to be tried.24
46. The Supreme Court of Canada has held that “[o]nce satisfied that the application is
neither vexatious nor frivolous, the motions judge should proceed to consider the second and
third tests”.25
47. Furthermore, this lower threshold is particularly suitable to cases where Charter rights
are engaged. The public interests engaged in Charter cases will often be sufficient to find that
there is a serious question to be considered by the Court. In RJR MacDonald, the Supreme Court
of Canada held that :
The Charter protects fundamental rights and freedoms. The importance of the
interests which, the applicants allege, have been adversely affected require every
court faced with an alleged Charter violation to review the matter carefully. This
is so even when other courts have concluded that no Charter breach has occurred.
Furthermore, the complex nature of most constitutional rights means that a motions
23
RJR MacDonald at para 44. 24
RJR MacDonald at para 49. 25
RJR MacDonald at para 50.
16
court will rarely have the time to engage in the requisite extensive analysis of the
merits of the applicant's claim. This is true of any application for interlocutory relief
whether or not a trial has been conducted.26
48. The Appellants raise a number of concerns regarding the constitutionality of the
procedure for approving the construction of wind projects. The number of such projects in
development will only increase as the government has declared that “green energy” is a priority
for Ontario. As a consequence, there will be an increasing number of Ontarians affected by the
scheme that regulates the development of wind farms.
49. The seriousness of the case is enhanced by the fact that the effects on human health are
not known by the regulatory authorities and they are not considered in the decision-making
processes for issuing a REA.
50. This appeal challenges the constitutionality of the regulatory scheme. Far from being
frivolous or vexatious, it engages the constitutional rights of rural Ontarians in respect of the
commercial development of an emerging technology.
Irreparable Harm B.
51. In RJR MacDonald, the Supreme Court of Canada held that the second part of the test for
granting a stay application is whether the applicant would suffer irreparable harm if the stay
application is not granted.
52. The Court further ruled that the harm suffered by the respondent is more appropriately
considered in the third part of the test.27
53. The Court elaborated on the second part of the test as follows:
26
RJR MacDonald at para 48. 27
RJR-MacDonald at para 57.
17
At this stage the only issue to be decided is whether a refusal to grant relief could
so adversely affect the applicants' own interests that the harm could not be
remedied if the eventual decision on the merits does not accord with the result of
the interlocutory application.
“Irreparable” refers to the nature of the harm suffered rather than its
magnitude. It is harm which either cannot be quantified in monetary terms or
which cannot be cured, usually because one party cannot collect damages from
the other.28
54. Courts have also emphasized that it is the nature of the harm, and not its magnitude, that
must be assessed in determining whether the harm is irreparable. In Buckland v. Prince Edward
Island, the Prince Edward Island Supreme Court held that:
In keeping with the Supreme Court of Canada’s ruling in R.J.R. MacDonald, I am
not to consider the extent of harm suffered by the applicants or any harm to the
defendant or the public interest at this stage, but must look only to the nature of
the harm suffered by the applicant. With those restrictions, I find that the
plaintiffs will suffer irreparable harm if their rights are affirmed after trial and
they have not been able to exercise those rights in the interim period.29
55. The nature of the harm assessed in that case was the exclusion of nine students from
French first language educational instruction pursuant to s. 23 of the Charter at the start of the
school year as opposed to at the conclusion of the trial. If successful at trial, students would be
eligible to receive French first language educational instruction. The Court ultimately found that
missed instruction constitutes irreparable harm because the relevant consideration is the nature of
the harm (i.e. missing out on instruction) and not the magnitude of the harm (i.e. the number of
days or months of missed instruction).
56. Crucially, the Supreme Court of Canada held that irreparable harm must be treated
differently in cases involving Charter rights than it would in a private law case.
28
RJR-MacDonald at para 59. 29
Buckland v. Prince Edward Island, 2004 PESCTD 66, 243 Nfld & PEIR 57 at para 24.
18
The assessment of irreparable harm in interlocutory applications
involving Charter rights is a task which will often be more difficult than a
comparable assessment in a private law application. One reason for this is that
the notion of irreparable harm is closely tied to the remedy of damages, but
damages are not the primary remedy in Charter cases.30
57. The Nunavut Court of Justice cited RJR MacDonald with approval in the 2003 case of
Nunavut Tunngavik Inc. v. Canada (Attorney General).31
In that case, the Court ruled that:
The same concerns identified by the Supreme Court of Canada with respect to
damage quantification for Charter breaches apply with equal, if not greater force
to alleged breaches of treaty rights protected by s. 35(1) of the Constitution Act
(1982). The law in this area remains very uncertain. On an interlocutory
application of this kind, this Court has no means of measuring the extent of
damage to "intangibles". For this reason, it is appropriate to follow the Supreme
Court's guidance in R.J.R. Macdonald and assume that the damage flowing from
the alleged breach of treaty rights will be irreparable.32
(emphasis added)
58. In this case, the Appellants do not seek a remedy of damages and so they cannot be
compensated for the harms that will inevitably result should the stay not be granted. The
Appellants are merely seeking a revocation of REAs issued by the Director of the Ministry of the
Environment and a declaration that the REAs are constitutionally invalid because they were
issued in a manner that is contrary to the Charter.
59. It would be difficult to quantify the harm resulting from the ongoing breach of the
Charter rights of the Appellants. The appeal before this Honourable Court raises issues about the
constitutionality of the Director’s decision in issuing the REA.
60. As outlined above in paragraphs 26-29, the REAs were issued in circumstances where
there is a “data-gap” relating to the distances and sound levels at which these industrial wind
30
RJR-MacDonald at para 60. 31
Nunavut Tunngavik Inc. v. Canada (Attorney General), [2003] Nu. J. No. 2, 1 WWR 122 [Nunavut Tunngavik]. 32
Nunavut Tunngavik at para 45.
19
turbines affect residents. The government has selected an arbitrary setback distance and sound
levels without any valid research to support these standards.
61. Subjecting the Appellants to further violations of their security of the person in this
regard cannot be remedied and constitutes irreparable harm.
62. Additionally, the Dixons’ eight-year old daughter suffers from hyper-sensitive hearing.
Her hyper-sensitive hearing causes her intense headaches when she is exposed to loud noises
such as sirens. The loud and constant noises generated by the construction activities of St.
Columban will cause their daughter to suffer intense headaches. 33
63. The Dixons are not comforted by the assurances by Jose Menendez in his affidavit that
the loudest noises would emanate from the operation of construction vehicles one-half of one
kilometre from the Appellants’ homes. In an urban environment, machinery and other
construction equipment can make noise that will be barely perceptible to those in the vicinity.
Noise emanating from that same equipment will be amplified in a rural environment with little
ambient noise that features no structures to block the propagation of the noise. The relevant
consideration in this second branch of the test is not the magnitude of the harm but rather the
nature of the harm suffered.34
It is no answer to assert that the harm suffered by the Dixon’s
daughter will be confined to certain periods of time or that it will be limited by distance. The
fact remains that irrespective of how great or minimal the harm to the Dixons’ daughter, that
harm is irreparable.
33
Affidavit of Jennifer Dixon sworn June 11, 2014 at paras 40. 34
RJR MacDonald at para 59.
20
64. Furthermore, the development of a project as complex as a wind farm can also lead to
expected or unexpected occurrences that may require the use of other machinery or prolonged
construction activities.
65. In the affidavit of Jose Menendez, St. Columban takes the position that construction will
be complete prior to the hearing of the appeal. While the laying of foundation may be complete,
this does not take into account the use of large scale cranes that will be used to erect the turbine
bases and blades. The turbine hub alone will be 99.5m in height. The Appellants respectfully
submit that it cannot be said that the construction in erecting these large scale machines will not
introduce a significant amount of noise into the Appellants environment.
66. In addition to hyper-sensitive hearing, the Dixons’ daughter suffers from sleep apnea.
She has also been having issues with increased secretions.35
The Dixons’ daughter is currently
consulting with an otolaryngologist and a pulmonologist to treat these conditions. The Dixons
are concerned that the effects of the construction activities will exacerbate these conditions and
cause her to suffer unnecessarily. Construction in the vicinity of the Dixon home will inevitably
generate dust and possibly toxins and contaminants over a prolonged period of time. These
particles will have an adverse effect on the health of a young child suffering from a respiratory
condition.
67. The harm to the Dixon’s eight-year old daughter, particularly at this key time in her
growth and development, cannot be quantified and would not be compensable by damages, even
if the Appellants were seeking damages as a remedy. In short, the harm suffered by the Dixons
would be irreparable by a declaration that the REA should be revoked.
35
Affidavit of Jennifer Dixon sworn June 11, 2014 at para 41.
21
68. The ongoing construction activities related to the K2 Wind Project has caused water
management issues that the Respondent, K2 Wind Ontario Inc., is unable to contain. This has
two consequences.
69. The first consequence is that the Drennans’ farm property has been repeatedly flooded by
water being dumped from K2 Wind Project lands. Flooding in this manner erodes soil and
results in lower quality soil. The effect of this is less productive areas of land and a reduction in
crop yields.36
The flooding is of particular concern to the Drennans because they have observed
that the water flooding their property is contaminated with an unknown substance. The water is
not clear but rather has a cloudy appearance.37
70. The second consequence of the Respondent’s demonstrated inability to contain the water
flowing from its land is the risk of contaminating the water supply of the Township of Ashfield-
Colborne-Wawanosh. This risk arises because the Project site is situated on a close-to-surface
water aquifer and it is located near a significant groundwater recharge area. These important
underground water structures are connected to the water supply of the Township of Ashfield-
Colborne-Wawanosh, in some cases they are located less than 2 metres of the surface.38
71. The Drennans’ concerns stem from the fact that none of the regulatory authorities,
including the Ministry of the Environment, the Maitland Valley Conservation Authority and
Hydro One, are aware of the proper permitting requirements for water use and drainage.39
This
is apparent from the Drennans’ repeated correspondence dating to 2011 to the regulatory
authorities expressing concern about the potential of construction activities to contaminate the
36
Affidavit of Shawn Drennan sworn May 22, 2014 at paras 28 and 60. 37
Affidavit of Shawn Drennan sworn May 22, 2014 at para 58. 38
Affidavit of Shawn Drennan sworn May 22, 2014 at paras 29 – 35. 39
Affidavit of Shawn Drennan sworn May 22, 2014 at para 62.
22
Township’s water supply.40
The Appellants have no choice but to raise the concern in these
proceedings because the regulatory authorities will not take the responsibility to protect the water
supply of the residents of the Township.
72. While the Respondent, K2 Wind, has taken steps to address some of the water issues, all
steps taken were only in relation to surface water and not ground water. During the cross
examination of Mr. Wendelgasss, he conceded that any efforts taken by K2 do not affect any
ground water issues, but rather only surface water issues.41
73. This position taken by K2 however, is contradictory to the positions taken in the
hydrological report prepared for K2 by its consultant Stantec, which indicates that “groundwater
is present in the sand pockets beneath the site and have found to be under pressurized conditions,
with groundwater within these deposits often rising to ground surface once the lower
permeability sandy to clayey silt overlying the sand has been removed.”42
K2 has conceded that
they have taken no steps to address this problem with the groundwater, which the Appellant
contends is the issue that is causing them the irreparable harm.
74. The harms to the Drennans arising from any contamination of their water supply or the
water supply of the Township cannot be calculated and could result in a variety unforeseeable of
harms to human health. In sum, these harms would be irreparable by a declaration that the REA
should be revoked or if the matter is remitted to the Tribunal for hearing and K2 is permitted to
continue construction.
40
Affidavit of Shawn Drennan sworn May 22, 2014 at paras 29 -65. 41
Transcript evidence of Paul Wendelgass, August 14, 2014, page 9. 42
Ibid, page 74.
23
Balance of Convenience C.
75. The third part of the test for a stay is referred to as the balance of convenience. In this
part of the test, a court must determine “which of the parties would suffer greater harm from the
granting or refusal of the remedy pending a decision on the merits”.43
76. The Supreme Court of Canada has held that “[t]he factors that must be considered in
assessing the ‘balance of convenience’ are numerous and will vary in each individual case”.44
Such factors may include the nature of the relief sought, the harm claimed by the parties, the
nature and purpose of the legislation involved, which of the parties acted to alter the status quo
and the nature and expectations of the parties.45
I. The Inconvenience of the Respondents
77. The inconvenience or harm cited by the Respondents is that a pause in construction of
four months in the form of a stay would amount to a multi-million dollar loss due to liquidated
damages clauses in agreements with the Ontario Power Authority (the “OPA”).46
78. In addition, the Respondents state that a pause in construction of four months could delay
the commercial operation of the project past the drop dead date for commercial operation. A
delay beyond the drop date for commercial operation would constitute an event of default that
would allow the Ontario Power Authority to terminate the agreement.
43
RJR MacDonald at para 43. 44
RJR MacDonald at para 63. 45
Merck & Co., Inc. v. Canada (Attorney General), 1999 CanLII 9185, 4 CPR (4th) 91; 179 FTR 247 at para 22;
J.A. Brink Investments Ltd. v. BCR Properties Ltd., 2009 BCSC 620 at para 24; CBS Canada Holdings co v. All
Vision Canada Company, 2012 ONSC 3679; Canada Post Corporation v. Canadian Union of Postal Workers, 2011
ONSC 38. 46
Affidavit of Jose Menendez sworn July 21, 2014 at para 42; Affidavit of Paul F. Wendelgass sworn July 21, 2014
at para 55.
24
79. In his affidavit, Jose Menendez, Vice President of St. Columban Energy Inc., states that
the drop dead date for commercial operation of the St. Columban Project is August 16, 2016,
nearly two full years from now.47
Paul F. Wendelgass, Director of Business Development,
Northeast for Capital Power Corporation (a partner in the K2 Wind Ontario Limited Partnership),
states in his affidavit that the drop dead date for commercial operation is January 3, 2017, nearly
two and a half years from now.
80. The affiants on behalf of each of the Respondents failed to disclose to this Honourable
Court material clauses that would mitigate the financial penalties and prevent an event of default
from occurring should a stay be granted.
81. In cross-examinations, Mr. Wendelgass and Mr. Menendez both conceded that their
companies’ agreements with the OPA (“the OPA Agreements”) contained force majeure clauses.
If the force majeure clauses in the OPA Agreements are triggered, the date that the Respondents
are required to have the projects prepared for commercial operation is delayed by the length of
time of the delay caused by the force majeure event.
82. “Relevant extracts” of the OPA Agreement are included as Exhibit “M” to the
Wendelgass affidavit. However, the portion of the OPA Agreement that is most relevant to these
proceedings was excluded from Exhibit “M”. The Appellants were able to obtain a copy of the
OPA Agreement that was filed in a related proceeding with the Ontario Energy Board. The full
OPA Agreement is filed as Exhibit 3 to the Cross-Examination of Mr. Wendelgass.
47
Affidavit of Jose Menendez sworn July 21, 2014 at para 45; Affidavit of Paul F. Wendelgass sworn July 21, 2014
at para 56.
25
83. Section 10 of the K2 OPA Agreement provides for a force majeure clause which allows
one party to be excused for non-performance of its obligations under certain limited
circumstances set out in the agreement. Section 10.1(a)(iii) provides as follows:
If, by reason of Force Majeure: …
(iii) either Party is unable, wholly or partially, to perform or comply with its other
obligations (other than payment obligations) hereunder, including the Supplier
being unable to achieve Commercial Operation by the Milestone Date for
Commercial Operation,
then the Party so affected by Force Majeure shall be excused and relieved from
performing or complying with such obligations (other than payment obligations)
and shall not be liable for any liabilities, damages, losses, payments, costs,
expenses (or Indemnifiable Losses, in the case of the Supplier affected by Force
Majeure) to, or incurred by, the other Party in respect of or relating to such Force
Majeure and such Party's failure to so perform or comply during the continuance
and to the extent of the inability so caused from and after the invocation of Force
Majeure.48
(emphasis added)
84. This section provides that if a force majeure event occurs, the party subject to the force
majeure is excused from performing its obligation. It explicitly includes among the obligations
excused, the obligation to achieve commercial operation by the milestone date for commercial
operation.
85. What constitutes a force majeure event is defined at s. 10.3 of the K2 OPA Agreement:
For the purposes of this Agreement, the term "Force Majeure" means any act,
event, cause or condition that prevents a Party from performing its obligations
(other than payment obligations) hereunder, that is beyond the affected Party's
reasonable control, and shall include: …
(g) an order, judgment, legislation, ruling or direction by Governmental
Authorities restraining a Party, provided that the affected Party has not applied for
48
Exhibit 3 to Cross-Examination of Paul F. Wendelgass, Power Purchase Agreement dated August 3, 2011
between Ontario Power Authority and K2 Ontario Limited Partnership at s. 10.1(a)(iii) [“K2 OPA Agreement”].
26
or assisted in the application for and has used Commercially Reasonable Efforts
to oppose such order, judgment, legislation, ruling or direction49
(emphasis added)
86. The terms of s. 10.3 are clear: an “order” by a court that “restrains” a party from
performing its obligations amounts to a force majeure. A court order would of course include an
order for a stay pending appeal.
87. Section 10.1(f) explicitly provides that if a force majeure causes K2 not to achieve
commercial operation by the milestone date for commercial operation, then the milestone date
for commercial operation would be extended for a period equivalent to the delay caused by the
force majeure:
If an event of Force Majeure causes the Supplier to not achieve Commercial
Operation by the Milestone Date for Commercial Operation, then the Milestone
Date for Commercial Operation shall be extended for such reasonable period of
delay directly resulting from such Force Majeure event. After the Commercial
Operation Date, an event of Force Majeure shall not extend the Term.50
(emphasis
added)
88. Finally, section 9.1(j) of the K2 OPA Agreement provides that it is an event of default if:
The Commercial Operation Date has not occurred on or before the date which is
18 months after the Milestone Date for Commercial Operation, or otherwise as
may be provided herein.51
89. In sum, a portion of the K2 OPA Agreement that was not disclosed to this Honourable
Court includes a clause that contradicts a large portion of the evidence of Mr. Wendelgass.
90. That clause would operate to extend the milestone date for commercial operation should
this Honourable Court order a stay precluding any liquidated damages from being assessed
against K2.
49
K2 OPA Agreement at s. 10.3. 50
K2 OPA Agreement at s. 10.1(f). 51
K2 OPA Agreement at s. 9.1(j).
27
91. Furthermore, the force majeure clause would operate to extend the drop dead date for
commercial operation. This is because the drop dead date for commercial operation is calculated
by reference to the milestone date for commercial operation. If the milestone date for
commercial operation is extended, the drop dead date for commercial operation would also be
extended.
92. By its terms, the force majeure clause would relieve K2 of any liability vis-à-vis the OPA
arising from a court-ordered stay.
93. The Menendez affidavit does not attach the St. Columban OPA Agreement. However, in
cross-examinations, Mr. Menendez and his counsel indicated that the terms and conditions of the
St. Columban OPA Agreement are available on the OPA website as FIT Contract version 1.5.52
FIT Contract version 1.5 was made Exhibit 1 to the Cross-Examination of Jose Menendez.
94. The force majeure provisions of the St. Columban OPA Agreement are identical to the
force majeure provisions of the K2 OPA Agreement.
95. Section 10.1(a)(iii) provides the general effect of invoking a force majeure which is that:
If, by reason of Force Majeure: …
either Party is unable, wholly or partially, to perform or comply with its other
obligations (other than payment obligations) hereunder, including the Supplier
being unable to achieve Commercial Operation by the Milestone Date for
Commercial Operation,
then the Party so affected by Force Majeure shall be excused and relieved from
performing or complying with such obligations (other than payment obligations)
and shall not be liable for any liabilities, damages, losses, payments, costs,
expenses (or Indemnifiable Losses, in the case of the Supplier affected by Force
Majeure) to, or incurred by, the other Party in respect of or relating to such Force
Majeure and such Party’s failure to so perform or comply during the continuance
52
Transcript of Cross-Examination of Jose Menendez dated August 15, 2014 at p 7, line 6 and p 11, line 11.
28
and to the extent of the inability so caused from and after the invocation of Force
Majeure.53
96. The various events that would constitute a force majeure event are described at s. 10.3 of
the St. Columban OPA Agreement:
For the purposes of this Agreement, the term "Force Majeure" means any act,
event, cause or condition that prevents a Party from performing its obligations
(other than payment obligations) hereunder, that is beyond the affected Party's
reasonable control, and shall include: …
(g) an order, judgment, legislation, ruling or direction by Governmental
Authorities restraining a Party, provided that the affected Party has not applied for
or assisted in the application for and has used Commercially Reasonable Efforts
to oppose such order, judgment, legislation, ruling or direction54
(emphasis added)
97. Section 10.1(f) of the St. Columban OPA Agreement, as with section 10.1(f) of the K2
OPA Agreement, explicitly provides that if a force majeure causes St. Columban not to achieve
commercial operation by the milestone date for commercial operation, then the milestone date
for commercial operation would be extended by a period of time equivalent to the delay caused
by the force majeure event:
If an event of Force Majeure causes the Supplier to not achieve Commercial
Operation by the Milestone Date for Commercial Operation, then the Milestone
Date for Commercial Operation shall be extended for such reasonable period of
delay directly resulting from such Force Majeure event. After the Commercial
Operation Date, an event of Force Majeure shall not extend the Term.55
(emphasis
added)
98. Finally, section 9.1(j) of the St. Columban OPA Agreement provides that it is an event of
default if:
53
Exhibit 1 to Cross-Examination of Jose Menendez, Relevant Excerpts of Feed-in-Tariff Contract version 1.5 dated
June 3, 2011) at s. 10.1(a)(iii) [“St. Columban OPA Agreement”]. 54
St. Columban OPA Agreement at s. 10.3. 55
K2 OPA Agreement at s. 10.1(f).
29
The Commercial Operation Date has not occurred on or before the date which is
18 months after the Milestone Date for Commercial Operation, or otherwise as
may be provided herein.56
99. In sum, the St. Columban OPA Agreement, like the K2 OPA Agreement, contradict key
portions of the evidence of Jose Menendez. Mr. Menendez’s states that a stay issued by this
Honourable Court would result in a liability of $3,000,000 in liquidated damages and the
likelihood that St. Columban will be forced into an event of default.
100. The force majeure clause significantly impacts the balance of convenience analysis
because the Respondents can no longer conclusively state that the projects will be jeopardized by
a motion to stay. The Respondents may suffer some financial consequences but these
consequences are a result of the bargain the Respondents voluntarily struck with service
providers and financiers. In other words, any adverse financial consequences are a cost of doing
business borne by the Respondents with knowledge of the legal challenges mounted by the
Appellants and many other rural Ontarians in respect of other wind farms.
II. The Public Interest
101. The public interest is a key factor in the balance of convenience analysis and must be
considered by a court. In RJR MacDonald, the Supreme Court of Canada ruled that “in all
constitutional cases, the public interest is a ‘special factor’ which must be considered in
assessing where the balance of convenience lies and which must be ‘given the weight it should
carry’”.
102. In Pembroke Civic Hospital v. Ontario (Health Services Restructuring Commission), the
Court of Appeal for Ontario expounded on the meaning of the public interest in the context of a
56
K2 OPA Agreement at s. 9.1(j).
30
balance of convenience analysis. That case arose as a result of a direction of the Health Services
Restructuring Commission that the emergency department of the Pembroke Civic Hospital be
required to close. The court held that:
In this circumstance, each party contending for opposite results on this motion can
legitimately claim to speak for a part of the public interest. In my view, however,
the overriding public interest is best served by recognizing that hospital
restructuring is a wrenching social experience for a community and that if
possible full legal debate be accorded before major change is undertaken.57
103. In Pembroke, the decision of an administrative tribunal tasked with promoting the public
interest was set aside in favour of a greater public interest identified by the court.
104. The question of what is in the public interest with respect to this motion is resolved by an
analysis of two factors. The first factor is the remedy sought by the Appellants. The second
factor is the objective of the legislation which the Appellants claim is unconstitutional.
105. The remedy sought by the Appellants is very narrow. The Appellants are seeking a stay
of construction for two wind projects. Unlike many constitutional cases, the Appellants do not
seek the suspension of legislation or another remedy of broad application.
106. In Rogers v. Sudbury (Administrator of Ontario Works), the Ontario Superior Court of
Justice found that the public interest is less likely to be endangered when the applicant merely
seeks a personal exemption as opposed to a suspension of a law:
There are two types of interlocutory orders that may be sought in
a Charter proceeding. An applicant may seek an order suspending the operation of
the impugned law pending determination of the case on the merits or may only
seek to be exempted personally from the operation of the law. The Supreme Court
has indicated that public interest considerations will weigh more heavily where
the applicant seeks suspension of the impugned law than in an exemption
57
Pembroke Civic Hospital v. Ontario (Health Services Restructuring Commission), [1997] OJ No 3167, 102 OAC
207 at para 12.
31
situation where she seeks personal exemption. Obviously, that is because
the public interest is much less likely to be detrimentally affected when a discrete
and limited number of applicants are exempted from the law in question.58
107. The Appellants in the case at bar seek a limited remedy that will affect two wind projects.
The consequence of staying these two wind projects, however, means that the hundreds of
individuals that live in the vicinity of these two projects will be relieved of the harms that will
result should a stay pending appeal not be granted.
108. In RJR MacDonald, the Supreme Court of Canada held that:
When the nature and declared purpose of legislation is to promote the public
interest, a motions court judge should not be concerned whether the legislation
actually has such an effect. It must be presumed to do so. In order to overcome
the assumed benefit to the public interest arising from the continued application of
the legislation, the applicant who relies on the public interest must demonstrate
that the suspension of the legislation would itself provide a public benefit.59
(emphasis added)
109. The legislation that provides for appeals of a REA to the ERT was enacted with a focus
on environmental protection and the promotion of renewable energy development. The
Appellants concede that there is a public interest in the protection of the environment and the
responsible development of renewable energy sources. However, that public interest must be
tempered by the public interest in meaningful access to justice.
110. Courts have held that the public perception of a court’s ruling is an important
consideration in determining the public interest.60
A failure to grant the stay would send a signal
to the public that both the legislature and the judiciary will allow economic interests to prevail
over the public interest in health and safety. This is particularly so in the context of the political
58
Rogers v. Sudbury (Administrator of Ontario Works), 2001 CanLII 28086 (ON SC), 57 OR (3d) 460; OJ No 2167
at para 15. 59
RJR MacDonald at para 80. 60
See e.g. Ontario (Attorney General) v. Ontario Teachers' Federation, 1997 CanLII 12182, 36 OR (3d) 367; OJ
No 4361.
32
controversy surrounding wind turbine development in Ontario. The public interest advanced by
the governing legislation is responsible development of renewable energy resources. The crux of
the appeal and this motion is that the Respondents have acted irresponsibly in developing the St.
Columban Project and the K2 Wind Project.
III. Analysis of the Balance of Convenience
111. The balance of convenience favours the Appellants.
112. Should a stay not be granted, the Appellants will suffer the irreparable harms canvassed
above. The Charter breach suffered by the Appellants will continue and will not be
compensated should they be successful on the appeal. In effect, the message that would be sent is
that the Appellants are to be guinea pigs until the court makes a determination on the main
appeal.
113. If the stay is granted, the Respondents may suffer a financial loss that they voluntarily
undertook in pursuing a business opportunity. Importantly, these risks were undertaken with
knowledge that the REAs were subject to a constitutional challenge by the Appellants.
114. Should the stay be granted, the Respondents may renegotiate their agreements, deploy
leased equipment for other uses or engage in a multitude of other strategies to mitigate their loss.
115. The Appellants have no reasonable options to mitigate their loss. The Dixons cannot
reasonably live elsewhere while St. Columban builds wind turbines. The Drennans have
exhausted their options to mitigate the flooding of their property as is evident from the long trail
of correspondence to regulatory authorities documented in the Affidavit of Shawn Drennan.
116. Finally, the public interest favours granting the stay.
33
PART V: ORDER SOUGHT
117. The Appellants respectfully request that this Honourable Court grant the Appellants’
motion to stay the construction of the St. Columban Project and the K2 Wind Project.
118. The Appellants further request that this Honourable Court order costs in respect of the
Appellants stay motion.
ALL OF WHICH IS RESPECTFULLY SUBMITTED
DATED at Toronto this 29th
day of August, 2014.
Julian N. Falconer (LSUC 29465R)
Asha James (LSUC 56817K)
Falconers LLP
10 Alcorn Avenue, Suite 204
Toronto, Ontario M4V 3A9
Tel: (416) 964-0495
Fax: (416) 929-8179
Lawyers for the Appellants
34
Schedule “A” – List of Authorities
1. Buckland v. Prince Edward Island, 2004 PESCTD 66, 243 Nfld & PEIR 57
2. Canada Post Corporation v. Canadian Union of Postal Workers, 2011 ONSC 38
3. CBS Canada Holdings co v. All Vision Canada Company, 2012 ONSC 3679
4. J.A. Brink Investments Ltd. v. BCR Properties Ltd., 2009 BCSC 620
5. Merck & Co., Inc. v. Canada (Attorney General), 1999 CanLII 9185, 4 CPR (4th) 91;
179 FTR 247
6. Morguard Corporation v. InnVest Properties Ottawa GP Ltd., 2012 ONSC 80
7. Nunavut Tunngavik Inc. v. Canada (Attorney General), [2003] Nu. J. No. 2, 1 WWR 122
8. Ontario (Attorney General) v. Ontario Teachers' Federation, 1997 CanLII 12182, 36 OR
(3d) 367; OJ No 4361.
9. Pawlowski v. Calgary (City of), 2007 ABQB 226, 75 Alta LR (4th) 241
10. Pembroke Civic Hospital v. Ontario (Health Services Restructuring Commission), [1997]
OJ No 3167, 102 OAC 207
11. RJR – MacDonald Inc. v. Canada (Attorney General), [1994] 1 SCR 311, 111 DLR (4th)
385, 1994 CanLII 117
12. Rogers v. Sudbury (Administrator of Ontario Works), 2001 CanLII 28086, 57 OR (3d)
460; OJ No 2167
35
Schedule “B” – Legislation
Canadian Charter of Rights and Freedoms, The Constitution Act, 1982, Schedule B to the
Canada Act 1982 (UK), 1982, c 11
Enforcement of guaranteed rights and freedoms
24. (1) Anyone whose rights or freedoms, as guaranteed by this Charter, have been
infringed or denied may apply to a court of competent jurisdiction to obtain such remedy
as the court considers appropriate and just in the circumstances.
Courts of Justice Act, RSO 1990, c C.43, s. 106
Stay of Proceedings
106. A court, on its own initiative or on motion by any person, whether or not a party, may
stay any proceeding in the court on such terms as are considered just. R.S.O. 1990,
c. C.43, s. 106.
Environmental Protection Act, RSO 1990, c E.19
Director’s powers
47.5 (1) After considering an application for the issue or renewal of a renewable energy
approval, the Director may, if in his or her opinion it is in the public interest to do so,
(a) issue or renew a renewable energy approval; or
(b) refuse to issue or renew a renewable energy approval. 2009, c. 12, Sched. G, s. 4 (1).
Rules of Civil Procedure; RRO 1990, Reg 194, Rule 63.02
Stay by Order
By Trial Court or Appeal Court
63.02 (1) An interlocutory or final order may be stayed on such terms as are just,
(a) by an order of the court whose decision is to be appealed;
(b) by an order of a judge of the court to which a motion for leave to appeal has been made
or to which an appeal has been taken. O. Reg. 465/93, s. 8.
36
Expiry of Trial Court Stay
(2) A stay granted under clause (1) (a) expires if no notice of motion for leave to appeal or
no notice of appeal, as the case may be, is delivered and the time for the delivery of the
relevant notice has expired. O. Reg. 534/95, s. 7.
Setting aside or Varying Stay
(3) A stay granted under subrule (1) may be set aside or varied, on such terms as are just,
by a judge of the court to which a motion for leave to appeal may be or has been made or
to which an appeal may be or has been taken. O. Reg. 465/93, s. 8.
Support Order
(4) A party who obtains a stay of a support order shall obtain a certificate of stay
under subrule 63.03 (4) and file it forthwith in the office of the Director of the Family
Responsibility Office. O. Reg. 292/98, s. 2.
w:\general\doc\d\drennan.shawn & tricia.1300-11\court\div. crt. appeal\motion for stay\factum\factum - stay - august 29 2014 draft 4.docx
Dixon et al.
-and- Director, Ministry of the Environment et al.
Court File No.: 2055/14, 2056/14
ONTARIO
SUPERIOR COURT OF JUSTICE
(DIVISIONAL COURT)
Proceedings Commenced in London
FACTUM OF THE APPELLANTS
MOTION FOR STAY PENDING APPEAL
FALCONERS LLP
10 Alcorn Ave, Suite 204
Toronto, ON M4V 3A9
Julian N. Falconer (LSUC #29465R)
Asha James (LSUC #56817K)
Tel: (416) 964-0495
Fax: (416) 929-8179
Counsel for the Appellants