35
Learning Legacy Document © Crossrail Limited CRL RESTRICTED SUSTAINABILITY & CONSENTS Environment Manual Document Number: CR-XRL-T1-GMN-CR001-00001 Document History: Version: Date: Prepared by: Checked by: Authorised by: Reason for Revision: 2.0 17/5/10 Updated hyperlinks for documentum and updated document history only 3.0 27/10/11 Revised for integrated organisation and general update 4.0 26/04/12 Revised due to audit findings 5.0 04/05/12 General update 6.0 03/07/13 General update This document contains proprietary information. No part of this document may be reproduced without prior written consent from the chief executive of Crossrail Ltd.

SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

  • Upload
    others

  • View
    30

  • Download
    0

Embed Size (px)

Citation preview

Page 1: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

© Crossrail Limited CRL RESTRICTED

SUSTAINABILITY & CONSENTS Environment Manual

Document Number: CR-XRL-T1-GMN-CR001-00001

Document History: Version: Date: Prepared by: Checked by: Authorised by: Reason for Revision:

2.0 17/5/10 Updated hyperlinks for documentum and updated

document history only

3.0 27/10/11 Revised for integrated organisation and general

update

4.0 26/04/12 Revised due to audit findings

5.0 04/05/12 General update

6.0 03/07/13 General update

This document contains proprietary information. No part of this document may be reproduced without prior written consent from the chief executive of Crossrail Ltd.

karen elson
Typewritten Text
karen elson
Typewritten Text
This document is shared for the purposes of learning legacy. It is a snapshot in time and hence many of the links within the document will become obsolete over time. Some links may refer to a document storage location that isn't accessible. Users should refer to the learning legacy website where these documents may be published separately.
karen elson
Typewritten Text
karen elson
Typewritten Text
Page 2: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 2 of 35

Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

Contents 1 Introduction ............................................................................................................... 3

2 Scope ......................................................................................................................... 3

3 Environmental Policy ................................................................................................ 3

4 Planning ..................................................................................................................... 6

4.1 Environmental aspects ............................................................................................ 6

4.2 Legal and other requirements ................................................................................. 6

4.3 Objectives, targets and programmes ...................................................................... 7

5 Implementation and Operation ................................................................................. 8

5.1 Resources, roles, responsibility and authority ...................................................... 8

5.2 Competence, training and awareness ..................................................................... 9

5.3 Communication ...................................................................................................... 10

5.4 Documentation ....................................................................................................... 12

5.5 Control of documents ............................................................................................ 12

5.6 Operational Control ................................................................................................ 14

5.7 Emergency preparedness & response .................................................................. 17

6 Checking .................................................................................................................. 17

6.1 Monitoring and measurement ............................................................................... 17

6.2 Evaluation of compliance ...................................................................................... 17

6.3 Nonconformity, corrective action and preventive action .................................... 19

6.4 Control of records .................................................................................................. 19

6.5 Internal Audit .......................................................................................................... 20

7 Management Review ............................................................................................... 20

Appendix A – Environmental Roles and Responsibilities ....................................... 21

Appendix B – Definitions and Abbreviations ............................................................ 27

Appendix C – EMS Document Register ..................................................................... 28

Appendix D –Environmental Management During Design ....................................... 32

Appendix E –Environmental Management During Construction ............................ 33

Appendix F – Design History ...................................................................................... 34

Page 3: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 3 of 35

Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

1 Introduction

Crossrail is required to develop and implement an Environmental Management System (EMS) under the Crossrail Environmental Minimum Requirements1 (EMR). The Crossrail EMS is certified to ISO14001, the International Standard for Environmental Management Systems.

This Environment Manual describes the main elements of the Crossrail EMS and their interaction and signposts all EMS documentation.

The Crossrail EMS forms part of the Crossrail Management System (CMS) and all documents referred to in this Manual are available on the CMS via the Crossrail intranet, with the exception of commercial documents which are maintained on eB.

The EMS delivers the environmental part of the Sustainability Strategy. The Crossrail Sustainability Strategy (CR-XRL-T1-GST-CR001-00001) provides a shared understanding of sustainable development, a vision of what Crossrail is seeking to achieve, the sustainable development priorities for the project and the critical success factors required to achieve them.

2 Scope

The Crossrail EMS applies to all activities undertaken by the Crossrail Team for “programme management of Crossrail including procurement, design, construction, testing and commissioning” (ISO 14001 certificate).

Designers are required to have environmental management procedures in place for design and contractors are required to develop and implement their own EMS’s and obtain certification to ISO14001. Industry Partners are required to comply with the Crossrail EMR as specified in their individual contract arrangements. Further details are given in section 5.6.

Crossrail’s EMS includes mechanisms to gain assurance that designers, contractors and Industry Partners are complying with their respective contractual requirements – see section 6.2 for details.

Compliance with Undertakings and Assurances is not managed under the Crossrail EMS – it is however managed within the CMS.

3 Environmental Policy

Crossrail considers Environmental Management as fundamental in all its activities. Thus, the Environmental Policy must be understood as a priority by all Crossrail personnel and adhered

1 See Environmental Minimum Requirements: General Principles 3.10; Annex 1: Construction Code 2.2; Annex 3 Environmental Memorandum 3.1.1, 3.5.

Page 4: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 4 of 35

Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

to throughout the course of the works, to ensure legal compliance and continuous improvement. Crossrail’s Policy Statement is given below.

Page 5: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 5 of 35

Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

The Crossrail Environmental Policy (CR-XRL-T1-PCY-CR001_Z-50001) is posted on noticeboards, available on the Crossrail intranet via the CMS and available to the public via the Crossrail website.

In addition to this policy, the Crossrail Executive has endorsed a Carbon Footprint Corporate Statement (CR-XRL-Z-UPP-CR001-00005), demonstrating the Crossrail Team’s commitment to supporting the UK Government’s and the Mayor of London’s vision for tackling climate change.

Page 6: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 6 of 35

Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

4 Planning

4.1 Environmental aspects

4.1.1 Design, construction and operation The Crossrail Environmental Statement identifies the significant environmental aspects and impacts for design, construction and operation of Crossrail. The impacts and aspects associated with construction are controlled and managed by contractors. The impacts and aspects associated with design are controlled and managed by designers.

As the design is developed into detailed design, or if there are any changes, designers are required to identify any new potential significant impacts and the Crossrail Team undertakes assurance of this – see section 6.2.

4.1.2 Business Premises Environmental aspects and impacts associated with business premises activities are determined using the Environmental Aspects and Impacts Register (CR-XRL-T1-ZFO-CR001-00008) which includes control measures. In addition, the Safety, Health, Environment and Facility (SHEF) Inspection procedure has been established for business premises. This procedure includes an inspection checklist to ensure all business premises have provisions in place for all aspects of safety, health, environment and facilities and is completed every quarter. Completed SHEF Inspections are recorded and entered on RIVO Safeguard and managed by the following people: Facilities Manager; Project Manager; and/or Premises Manager. In addition, environmental inspections are conducted between the EMS Manager and Facility Manager on Crossrail’s business premises. The schedule can be found on eB (CR-XRL-T1-LRG-CR001-50002).

4.1.3 Industry Partners All Industry Partners are required to comply with the EMR in accordance with their contractual agreements.

4.2 Legal and other requirements

Legal and other requirements that apply to the Crossrail Programme are given in the Legal and Other Requirements Register (CR-XRL-T1-GPR-CR001-00005), which is updated every 6 months.

A review is undertaken monthly to identify any changes to legal and other requirements using various sources (e.g. the Government’s legislation website, CEDREC, ENDS Report and the Institute of Environmental Management and Assessment’s “The Environmentalist” magazine). If changes affect the Crossrail Team’s activities then action is taken to ensure compliance, such as briefing staff on new processes or procedures and/or updating EMS documents.

Crossrail EMS procedures include relevant legal requirements.

Designers, contractors and Industry Partners are responsible for identifying and complying with legal requirements in accordance with their own systems/ procedures.

Page 7: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 7 of 35

Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

4.3 Objectives, targets and programmes

Crossrail has established environmental objectives and targets, approved by the Environment Committee, to help manage and improve environmental performance.

These six environmental objectives were developed some years ago and are intended to be enduring the whole programme and are cascaded to Industry Partners, Designers and Contractors who set their own targets and actions as relevant to their own specific scope of works. Crossrail has also set specific targets on an annual basis to meet the objectives.

Progress against meeting the objectives and targets will be reviewed at EMS Management Review in line with the Management Review Procedure (CR-XRL-O4-GPR-CR001-00005). Progress will also be measured as part of this process through periodic reports.

The objectives and targets and the programme for their achievement are documented in the Objectives and Targets Register (CRL1-XRL-T1-LRG-CRG03_Z-50001) and listed below and also posted on notice boards.

In line with the Management Review Procedure (CR-XRL-O4-GPR-CR001-00005), the status of objectives and targets is reviewed and new objectives and targets are set as appropriate on an annual basis (refer Section 7 Management Review).

Page 8: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 8 of 35

Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

5 Implementation and Operation

5.1 Resources, roles, responsibility and authority

Key environmental roles are identified in the following organisational chart and in Appendix A-Environmental Roles and Responsibilities. In addition, frameworks have been developed for Environmental Reporting (CR-XRL-T1-GUI-CR001_Z-50001); Noise (CR-XRL-T1-GUI-CRG03_Z-50004), Environmental Consents (CR-XRL-T1-GUI-CRG03_Z-50002), Air Quality Emission Control (CR-XRL-T1-GUI-CRG03_Z-50001) and Contaminated Land (CR-XRL-T1-GUI-CRG03_Z-50003).

Technical Director

Head of Sustainability and Consents

· Accountable for EMS being developed and implemented for CRL

EMS Advisor· Manage, monitor, evaluate and

coordinate the environmental management system

Chief Executive· Signatory to Health, Safety and Environment

Policy

Environment Manager · Responsible for EMS being developed and

implemented for CRL

Sustainability Committee

Environmental Advisors

Environment Team

Environmental PlannerEnvironmental Assurance

Manager and Environmental Assurance

Advisor Technical Specialists

Page 9: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 9 of 35

Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

5.2 Competence, training and awareness

Competencies for employees are identified via the Competency Management Procedure for Delivery Team (CRL1-XRL-Z2-GPD-CR001-50001)2 and through the Crossrail’s performance Management system where competency frameworks for other functions are visible. .This procedure includes employee competencies, including environmental competencies.

All Crossrail staff receive an induction which provides an overview of environmental management on Crossrail and specifically highlights the significant aspects and impacts of the design, construction and operation of Crossrail. Additionally, as part of the 6 month new starter training, a Sustainability and Consents training session is provided each month and delivered by the EMS team. This course aims to provide an understanding of the team’s role within Crossrail.

An environmental Training Needs Matrix (CR-XRL-T1-LRG-CR001-50001) has been developed and is currently being updated to include the training requirements of employees across the organisation. The training needs are based on a review of personnel responsibilities in each key project area. The matrix sets out specific training modules, Crossrail target audience and dates of training. Delivery of the training is conducted jointly between the EMS Team and the Environmental Advisors.

Crossrail’s process and policy for providing staff with training is described in the Learning and Development Procedure and Policy (CR-XRL-Z2-GPR-CR001-00033).

Attendance at training is recorded and tracked on Crosstrain and records are maintained with the EMS Manager in conjunction with L&D.

Environmental awareness is maintained via internal communication (refer Section 5.3.1 Internal Communication), induction and specific training.

Designers, contractors and Industry Partners are responsible for developing and providing training to all their own personnel as specified in their contractual requirements.

Although Crossrail is not responsible for providing training to contractors, designers and Industry Partners this is provided as required in relation to Crossrail’s specific environmental requirements.

2 This procedure states the following in the Scope:

This procedure is intended to be used for an interim period until a Crossrail procedure is implemented for managing competency across all positions.

Page 10: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 10 of 35

Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

5.3 Communication

5.3.1 Internal communication Internal communication means communication within the Crossrail Programme including designers, contractors and Industry Partners. Information related to our environmental aspects and our EMS is communicated internally via a number of mechanisms:

· Reporting – Periodic reporting is undertaken in accordance with the Reporting Procedures Handbook (CR-XRL-Z9-GPR-CR001-00012). Reports prepared as part of this process, and additional environmental reports are presented in the table below. Environmental Reporting guidance (CR-XRL-T1-GUI-CR001_Z-50001) has also been developed which aims to clarify reporting requirements for inclusion in the Technical Director Report (TDR), Area Director Report (ADR), Crossrail Corporate Objectives and Target Reporting and Board reporting.

Report Frequency Prepared by Submitted to

Periodic Reporting 4 weekly Refer Programme Management Reporting Procedures Handbook – Terms of Reference

Semi Annual Construction Report

6 monthly Environment Manager Sponsors

Environment report to Sustainability Committee

2 monthly Environment Manager Sustainability Committee

TfL SSP Report Quarterly Environment Manager Transport for London

TfL HSE Report Annual Environment Manager Transport for London

Management Review Report

Annual EMS Advisor Environment Committee

Sustainability Report Annual Sustainability Manager Sustainability Committee

Progress report Quarterly Contractor Project Manager

Dashboard report 4 weekly Contractor Project Manager

Supplier Performance Assurance

6 monthly EMS Advisor and Environment Assurance Manager

Project Manager

· News – via the newsletters, weekly news (Connect In-Brief)

· Meetings – Regular meetings at which environmental issues are discussed are presented in the table below. There are also meetings held with statutory bodies (e.g. Environment Agency, Environmental Health Officers) and between contractors and advisors.

Page 11: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 11 of 35

Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

Meeting Frequency Key Environment Attendees

Sustainability Committee Meeting

2 monthly Environment Manager

Sustainability Coordination Group

As required Sustainability Manager

Senior Staff Meeting Weekly Environment Manager

Environment Team Meeting Monthly Environment team members

Environmental Advisors Workshop

monthly Environmental Advisors

Environment Assurance Manager

Environment Assurance Advisors

Environmental Manager, as required

EMS Advisor as required

Specialists, as required

Environmental Focus Meetings

6 weekly Environment Advisor and Contractor Environment Managers

Contractor Environment Manager Forum

6 weekly Contractor Environment Managers

Environment Manager, as required

Environmental Assurance Manager

Environment Team, as required

EMS Manager

Environmental Advisors

Various Delivery Team and contractor meetings including contract progress meetings, construction meetings, consents meetings

Various Environmental Advisers

Delivery Team

Contractors

Management Review Meeting

Annually Technical Director

Environment Manager

EMS Manager

Head of Sustainability and Consents

Total Facilities Management contractor

As set out in the Estate Management Plan (CR-XRL-T2-GPL-CR001-00001

Network Rail Environment Meeting

Monthly Environment Manager

Principal Environmental Planner with responsibility for Network Rail

Network Rail Environment Manager and Environmental Specialists

London Underground As required Environment Manager

Page 12: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 12 of 35

Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

Meeting Frequency Key Environment Attendees

Environment Meeting Environmental Advisors Project wide with responsibility for London Underground

London Underground Single Point of Contact for Environment

Utilities Steering Group and Utilities Working Group

Monthly Environment Manager or Environmental Advisor Project wide with responsibility for Utilities attends as required

Berkeley Homes Joint Working Group

Monthly Principal Environmental Planner with responsibility for Berkerley Homes attends as required

Canary Wharf Joint Working Group

2 weekly Principal Environmental Planner with responsibility for Canary Wharf attends as required

5.3.2 External communication External communication means communication outside the Crossrail Programme including stakeholders such as local communities and consent granting bodies. The Crossrail Team communicates the significant environmental aspects relating to the programme externally via its website. All documentation pertaining to the hybrid bill process and ES is also available publicly on the internet.

The procedure for communicating externally is documented within the Crossrail Communications Strategy (CR-XRL-Z1-GST-CR001-00004) and Community Relations Procedure (CR-XRL-Z1-GPR-CR001-00005).

5.4 Documentation

A list of EMS Documents is provided in Appendix C- EMS Document Register.

Designers and contractors are required to develop and implement environmental management documents as set out in their contract documents (see section 5.6) Designers documents required are listed in the Technical Assurance Master List for each designer. Contractor documents required are listed in the Works Information and summarized in the Contractor Master Document List. Industry partners are responsible for producing their own environmental documentation.

5.5 Control of documents

CMS documents are controlled as set out in the Procedure for the Preparation and Control of Crossrail Management System (CMS) Documents (CR-XRL-O4-GPR-CR001-00003). All key EMS and environmental documents are held in the Crossrail electronic document management system, eB, in accordance with the Document Management Procedure (CRL1-XRL-Z3-GPD-CR001-50001). Any documents not managed through these two processes are ‘uncontrolled’.

Page 13: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 13 of 35

Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

Designers and contractors are required to include their documents in the Crossrail electronic document management system; eB and submission of documents to the Crossrail Team are tracked through the Technical Assurance Master Documents List for each designer and the Construction Master Deliverables List for each contractor. Industry Partners operate their own systems for control of documents.

Its the Environment Advisors responsibility to review contractor documents. A Sustainability and Consents document review matrix (CR-XRL-T1-LST-CRG03_Z-50001) sets out which documents the Environment Advisor’s need to refer to when reviewing contractor documents.

Page 14: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

© Crossrail Limited CRL RESTRICTED

5.6 Operational Control

Crossrail Team activities and operations that give rise, or may give rise, to significant environmental aspects are controlled by the processes outlined below, 5.6.1 Design, construction and operation Sustainability credentials of all suppliers for design, construction and operation of the railway, including designers and contractors, are evaluated during prequalification and tender stages and environmental requirements are included in all tender and contract documents as appropriate. Procurement is managed as set out in the Procurement Code:

· Section 1: General (CRL1-XRL-V3-GUI-CR001_Z-50004) · Section 2: Procurement Deliverables (CRL1-XRL-V3-GUI-CR001-50001-500013) · Section 3: Purchasing Deliverables (CRL1-XRL-V3-GUI-CR001-50005).

Design of the main works is generally procured from the Framework Design Consultants and the environmental requirements are included in Engineering Design Framework Agreement Scope Part A and B, which includes the requirement to comply with the Crossrail Environmental Minimum Requirements. Construction and some elements of detailed design are procured from contractors. Generic environmental requirements for all contractors are included in Volume 2B of the Works Information, with contract-specific requirements in Volume 2A of the Works Information, using standard templates. The Crossrail EMRs that are applicable to contractors and the particular scope of work have been included in these volumes of the Works Information.

Designers and contractors are required to identify environmental consents for their works and prepare consents applications which are then reviewed by the Crossrail Team. Certain consents, known as Employer’s Consents, are signed by the Crossrail Team as set out in the Planning, Environment and Traffic Consents (Central Section) Procedure (CR-XRL-T1-GPR-CR001-00001). A list of environmental consents required and obtained is contained within the Environmental Consents Register (CRL1-XRL-T1-LCR-CR001-00001).

Industry Partners are responsible for obtaining environmental consents except for consents required under the Crossrail Act 2008 which are signed by the Crossrail Team.

All potential changes from the agreed programme and project baselines including the EMR are managed in accordance with the Trend and Change Control Procedure (CR-XRL-Z9-GPR-CR001-00002). This includes changes made by designers, contractors and Industry Partners.

Best practice items can be found in the Lessons Learnt Procedure (CRL1-XRL-Z-GPD-CR001-50015) and Innovate 18 website (https://www.innovate18.co.uk/connect.ti?) as well as the GreenLine Recognition Scheme (CR-XRL-T1-GPD-CRG03_Z-50001) which is currently being finalised.

Page 15: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 15 of 35 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

5.6.2 Business Premises Sustainability credentials of suppliers of products and services are evaluated during the selection stages and environmental requirements are included in all tender and contract documents as appropriate. Procurement is managed as set out in the Procurement Code:

· Section 1: General (CRL1-XRL-V3-GUI-CR001_Z-50004) · Section 2: Procurement Deliverables (CRL1-XRL-V3-GUI-CR001-50001-500013) · Section 3: Purchasing Deliverables (CRL1-XRL-V3-GUI-CR001-50005).

Environmental requirements for the acquisition of land and property are given in the Estate Management Plan (CR-XRL-T2-GPL-CR001-00001). This Plan also covers the situation where land and property will be acquired in advance of demolition or the appointment of a main works Principal Contractor, when the Crossrail Estates Department will set up and manage the land/ property using the facilities management contractor. The Crossrail Team acquires all land and property required for the Crossrail railway, with the exception of some land needed temporarily by contractors which they are responsible for acquiring in accordance with their own EMSs.

Environmental requirements for facilities managed by the Crossrail Team are given in the Environmental Facilities Management Procedure (CR-XRL-F-GPD-CR001-50001).

Environmental controls related to disposal of IT equipment are included within Fujitsu’s Secure Disposal or Reuse of IT Equipment Procedure (CR-XRL-Z3-GPR-CR001-00019).

Environmental requirements for Crossrail’s warehouse facility at Canning Town are managed in accordance with the Canning Town Warehouse Procedure (CR-XRL-Z2-GPR-CR001-00019).

5.6.3 Industry Partners The Crossrail Team has agreed with each of the industry partner organisations different arrangements for compliance with the EMR during design and construction (see table below). These arrangements are tailored to the nature of the works being undertaken. Partner Operational Controls

Canary Wharf Group (CWG)

The Development Agreement requires Canary Wharf Group to ensure that “any reviewable design data must…. comply with the environmental minimum requirements” (paragraph 16.3) and to “procure that the Works are carried out and completed in accordance with: ….the Environmental Minimum Requirements” (Schedule 1 paragraph 1.2).

Crossrail worked with CWG in relation to the design for the Canary Wharf Station, which was finalised and submitted to the Crossrail Team in November 2009. The design was accompanied by an Environmental Design Statement that was reviewed by Crossrail.

There is a requirement for a Joint Working Group meeting, which is held weekly and is used to discuss any relevant environmental issues. Crossrail and CWG have completed an EMR Tracker document which clarifies responsibilities under the EMR.

Berkeley Homes The Woolwich Station Box Agreement requires the design, construction and completion of the Station Box to be in accordance with Environmental Minimum Requirements (paragraph 13.1). The Station Box design is submitted to the Crossrail Team for review at each RIBA stage. Joint Working Group Meetings are held and environmental issues are discussed as necessary as well as in specific environmental progress meetings being arranged as required. Progress reports are provided every period.

London Underground London Underground is undertaking a number of interface works for Crossrail. The LUL Development Agreement states that in relation to interface works LUL will “use its reasonable endeavours to procure that the Works Documents in respect of each Works

Page 16: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 16 of 35 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

Package …contain provisions whereby the relevant LUL Contractor agrees that it will comply with the Environmental Minimum Requirements” (see part C 1 h). A specific set of project requirements have been prepared for the works undertaken by London Underground at Goslett Yard (Project Requirements Specification Tottenham Court Road Eastern Entrance Hall Doc No CR-EG-PRW-X-RQ-00002).

Crossrail provided the environmental design checklist (CRL/EMS/F/1306), the relevant part of the register of mitigation, assumptions and opportunities for improvement, Part A of the Scope for Framework Design Consultants and Works Information Volume 1 and 2. LUL has utilised these as considered appropriate, to ensure their own process and procedures deliver compliance with the EMR.

Crossrail’s responsibilities for instructing work and reviewing deliverables are set out in LU Works Package Plan Procedure (CRL1-XRL-O4-STP-CR001-50002).

Network Rail In relation to the on-network works, the Network Rail Protocol states that “Network Rail will develop and deliver the On Network Works Baseline Plan in accordance with …(b) relevant provisions of the Environmental Minimum Requirements” (Draft Crossrail Network Rail Programme protocol paragraph 8.11).

Crossrail provided the environmental design checklist (CRL/EMS/F/1306), the relevant part of the register of mitigation, assumptions and opportunities for improvement, Part A of the Scope for Framework Design Consultants and Works Information Volume 1 and 2.. Network Rail has utilised these as considered appropriate, to ensure that their own processes and procedures deliver compliance with the EMR.

The interface between the Crossrail Environment Team and Network Rail’s Environment Team is set out in the Crossrail / Network Rail Interface Document for Planning, Environment and Traffic Consents (CR-XRL-T1-GPR-CRG04-00001) and the Crossrail / Network Rail Interface Document for Environment (CR-XRL-T1-GPR-CRG04-00002). Regular liaison meetings are held between Crossrail and NR to discuss environmental issues.

Network Rail is also undertaking interface works at Royal Oak Portal, Pudding Mill Lane Portal and Plumstead Portal. Paragraph 7.1 of the Network Rail Implementation Framework Agreement states that “Network Rail will carry out and perform and procure the carrying out and Completion of the Works in respect of each IA Remit… (d) in accordance with the Environmental Minimum Requirements…”. A list of interface works is managed by the Interface Manager DLR/NR. Environmental issues for interface works are discussed directly between Network Rail’s Environment team and the relevant Environmental Advisor and progress is discussed at the regular liaison meetings.

Utilities Companies The Memorandum of Understanding relating to Utility Diversion and Enabling Works relating to the Crossrail Project contains an objective to design the utility diversion works in accordance with the EMR and to undertake the works in accordance with regard for the environmental impact of those works (paragraph 4.1 (p)).

Utilities deliver compliance with the EMR through their own processes and procedures. Crossrail and UKPN jointly developed a template Environmental Management Plan for utility construction works which has been provided to other utility companies which they are free to adopt or use.

Crossrail’s responsibilities for instructing work and reviewing deliverables are set out in the Procedure for the Coordination on Utilities Work Performed by the Statutory Utility Company (CRL1-XRL-U-GPD-CRG03-50001).

Environmental issues for utility works are discussed at the Utilities Steering Group and Utilities Working Group as necessary.

Docklands Light Railway (DLR)

The DLR Works Agreement requires that works undertaken for Crossrail by DLR contractors will comply with the Environmental Minimum Requirements (Agreement paragraph 6.3 (a) (ii) (b) (gg)).

A list of DLR works is managed by the Interface Manager DLR/NR. The nature and scale of the proposed DLR works are not sufficient to result in significant environmental impacts. They comprise mainly cabling works (all civils work is being undertaken by Crossrail contractors).

Page 17: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 17 of 35 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

5.7 Emergency preparedness & response

Environmental incidents are managed in accordance with the Crossrail Incident Management Plan (CRL1-XRL-Z7-GPD-CR001-50001) and Incident Investigation Procedure (CR-XRL-Z7-GPR-CR001-00014The person(s) responsible for the premises/ sites where the incident has occurred notify the Incident Response Desk and record the incident in the RIVO Safeguard database. The Crossrail team responds and investigates as appropriate to the type and nature of the incident.

To ensure a consistent approach to environmental incidents programme-wide, guidance is given in the Crossrail Guidance on Environmental, Traffic and Planning Incidents (CR-XRL-T1-GGG-CR001-00002).

Contractors are required to manage incidents in accordance with their EMSs, using the Crossrail definitions, levels and framework specified in the Works Information. Environmental incidents on Industry Partner’s works are either notified at the regular working group meetings (for Berkeley Homes, Canary Wharf Group, Utilities and Network Rail) or directly to the Crossrail Team’s Environment Manager (for London Underground).

6 Checking

6.1 Monitoring and measurement

6.1.1 Design, Construction and Operation Environmental data is required to be measured by the contractor and provided to the Crossrail EMS Team as part of the contractor’s 4 weekly dashboard progress report, period submissions of environmental data on Rivo Safeguard and Crossrail Smartwaste, incident reports and investigations on Rivo Safeguard, quarterly objectives progress report, monitoring data (e.g. noise and vibration, dust monitoring, water monitoring). Data is analysed by the –Environment Assurance Team and presented through a variety of reporting requirements in line with the Reporting Procedures Handbook (CR-XRL-Z9-GPR-CR001-00012)–see section 5.3.1 for a list of internal reports.

6.1.2 Business Activities and Industry Partners Environmental data is collected (e.g. energy consumption) and stored by the Environment Assurance Team. Data is analysed by the Environment Assurance Team and presented through a variety of reporting requirements in line with the Reporting Procedures Handbook (CR-XRL-Z9-GPR-CR001-00012)–see section 5.3.1 for a list of internal reports.

6.2 Evaluation of compliance

6.2.1 Design, construction and operation Compliance with legal and other requirements (including the EMR) during design and construction is regularly assessed through the following activities:

· Audits of designers and contractors against their contractual requirements and Crossrail Team’s compliance with Crossrail procedures, which are carried out in accordance with

Page 18: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 18 of 35 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

the Crossrail Audit Strategy (CR-XRL-Z-STP-CR001-50002 ) and Audit Procedure (CR-XRL-Z-GPD-CR001-50001).

· Management Review undertaken in accordance with the Management System Review Procedure (CR-XRL-O4-GPR-CR001-00005. This is currently in the process of being revised due to the change to an annual review rather than 6 monthly.

· Review of contractor submissions of environmental data. Frameworks have developed to provide guidelines and criteria for reporting environmental data. These include: Environmental Reporting (CR-XRL-T1-GUI-CR001_Z-50001); Noise (CR-XRL-T1-GUI-CRG03_Z-50004), Environmental Consents (CR-XRL-T1-GUI-CRG03_Z-50002), Air Quality Emission Control (CR-XRL-T1-GUI-CRG03_Z-50001) and Contaminated Land (CR-XRL-T1-GUI-CRG03_Z-50003)

· Review of findings of monthly joint contractor and Crossrail site inspections

· Review of Contractors Supplier Performance Assurance results

The Crossrail Team undertakes assurance to ensure that design meets environmental requirements, including the EMR, as outlined in the diagram in Appendix D.

The Crossrail Team undertakes assurance to ensure that construction works meet the environmental requirements of a contractor’s contract, which incorporate the EMR. An overview of the processes followed is given in the diagram Appendix E.

The detailed history of the design assurance process during previous stages of the project is included in Appendix F.

Where land and property is acquired in advance of demolition or the appointment of a main works Principal Contractor, and is therefore managed by the facilities management contractor, that contractor highlights any environmental issues at the locations that they are managing using the Environmental Checklist (in the Estate Management Plan (CR-XRL-T2-GPL-CR001-00001)) which the Crossrail Team reviews for assurance purposes.

6.2.2 Business Activities Compliance with legal and other requirements (including the EMR) for Crossrail’s business activities is regularly assessed through the following activities:

· Audits of the Crossrail Team’s compliance with Crossrail procedures, which are carried out in accordance with the Crossrail Audit Strategy (CR-XRL-Z-STP-CR001-50002), Audit Procedure (CR-XRL-Z-GPD-CR001-50001).

· Management Review undertaken in accordance with the Management System Review Procedure (CR-XRL-O4-GPR-CR001-00005)

· Review of submissions of environmental data

· Site inspections as per the Environmental Inspection Schedule for CRL Business Premises (CR-XRL-T1-LRG-CR001-50002)

6.2.3 Industry Partners Compliance with legal and other requirements (including the EMR) by Industry Partners is assessed through review of submissions of environmental data and regular review meetings in line with their contractual agreements – see section 5.6.

Page 19: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 19 of 35 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

6.3 Nonconformity, corrective action and preventive action

Actual nonconformities with the Crossrail EMS are managed either as:

· incidents – see section 5.7 above; or

· Non-conformance Report as per the Project Technical Report (PTR) Procedure (CRL1-XRL-Z-GPD-CR001-500063 or where in most cases, through the Project Managers Communication (PMC) route.

Contractors are required to raise nonconformities as set out in their EMSs and if a contractor fails to raise a non-conformity then the Crossrail Team may do so in accordance with the PTR Procedure which include RFIs, FCDs and NCRs (CRL1-XRL-Z-GPD-CR001-50006) and through the PMC route. Management of Crossrail nonconformities will be checked as part of the Crossrail audits.

Potential nonconformities with the Crossrail EMS are raised as risks - where specific environmental requirements are at risk at specific locations – and managed in compliance with the Risk Management Plan (CR-DV-PRC-X-PL-00001)) and Risk Management Procedure (CR-XRL-Z9-GPR-CR001-00009). Risks are managed using the Crossrail Risk Register. Monthly meetings are currently being set up with each area where environment risks are reviewed. Environment risks are escalated via the ADR.

Lesson learnt may be raised at any time by any member of the Crossrail Team and activities or processes may undergo a lessons learnt review to improve performance as set out in the Lessons Learned Procedure (CRL1-XRL-Z-GPD-CR001-50015).

Industry Partners operate their own systems/ procedures for managing nonconformities, corrective and preventive action.

6.4 Control of records

All key EMS and environmental records are held in the Crossrail electronic document management system, eB, in accordance with the Document Management Procedure (CRL1-XRL-Z3-GPD-CR001-50001). Environmental Advisers ensure that environmental records, including key emails, are kept in their project filing system.

Records are identified, stored, protected, retrieved, retained and disposed of in accordance with the Control of Records (Procedure) (CR-XRL-O4-GPR-CR001-00002) and the Record Archiving, Retrieval and Disposal Procedure (CR-XRL-N1-GPR-CR001-00004).

3 After investigation into the PTR system, it was found that most Non-conformities are raised through the PMC route. It is likely however that the PTR system will be used to track non-conformities in relation to contractor emission control requirements associated with Non Road Mobile Machinery (NRMM).

Page 20: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 20 of 35 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

Designers and contractors are required to include their records in the Crossrail electronic document management system, eB Industry Partners operate their own systems for control of records.

6.5 Internal Audit

The Audit Team undertakes environmental audits of the Crossrail Team to evaluate compliance and to provide assurance that environmental requirements are being met. The approach to audits is set out in the Audit Strategy (CR-XRL-Z-STP-CR001-50002). The process for undertaking audits is given in The Audit Procedure (CR-XRL-Z-GPD-CR001-50001).

Designers, contractors and Industry Partners are responsible for undertaking their own internal audits.

7 Management Review

The management review of the Crossrail Management System takes place annually in accordance with the Management System Review Procedure (CR-XRL-O4-GPR-CR001-00005). This is an integrated management system review and is carried out in accordance with the requirements of Management Reviews as defined by:

· BS EN ISO 9001 Quality Management Systems;

· BS EN ISO 14001 Environmental Management Systems; and

· BS OHSAS 18001 Occupational Health and Safety Assessment Series

Contractors are required to undertake Management Reviews as part of their EMSs and a representative of the Crossrail Team is invited. Designers and Industry Partners operate their own systems for management review.

Page 21: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 21 of 35 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

Appendix A – Environmental Roles and Responsibilities

1. All Personnel All personnel are responsible for:

· complying with the Crossrail EMS and all environmental requirements applicable to their activities

· seeking advice from a member of the Sustainability and Consents Team or Delivery team Environmental Adviser when unsure of requirements

· seeking to reduce the environmental impact of their activities.

2. Line Managers Crossrail Line Managers are responsible for ensuring that their team complies with the Crossrail EMS and all environmental requirements applicable to their activities

3. Corporate Functions Chief Executive and Executive Directors The Crossrail Chief Executive and Directors are responsible for:

· ensuring delivery of the Project Development Agreement in accordance with the EMR

· leading Crossrail in delivery of the Crossrail Environment Policy

· providing visible leadership and commitment to high environmental standards.

4. Delivery Directorate Delivery Directors The Crossrail Delivery Director and Area Delivery Directors are responsible for:

· ensuring contractor compliance with the EMR via execution of the Works Information.

· ensuring that the Crossrail Environmental Management System is implemented (in their Areas)

· providing adequate resources for environmental management in the Delivery Teams

· ensuring that construction works do not start until environmental requirements are in place

· ensuring environmental incidents are dealt with rapidly and effectively

· providing visible leadership and commitment to high environmental standards.

· provide representation at the Management Review of the Crossrail EMS.

· Reporting to Chief Executive and Executive Directors on environmental performance on their projects

Page 22: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 22 of 35 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

Area Construction Managers The Crossrail Area Construction Managers are responsible for line managing the Crossrail Environmental Advisers to ensure that the Crossrail Environmental Management System is implemented in their Areas. Roles and Responsibilities are clarified with the Project Managers.

Project Managers The Crossrail Project Managers are responsible for:

· ensuring contractor compliance with the EMR via execution of the Works Information.

· ensuring that Delivery Team workplaces comply with environmental legislation (for Crossrail Business premises only).

· ensuring that the Crossrail Environmental Management System is implemented on their projects

· advise on the level of adequate resources required for environmental management for their projects

· ensuring that construction works do not start until environmental requirements are in place

· ensuring that environmental consents are identified; applications are reviewed and, for Employer’s consents signed-off by the Crossrail Team; and consents complied with

· manage the works to ensure environmental incidents are dealt with rapidly and effectively

· providing visible leadership and commitment to high environmental standards

· reporting to the Delivery Directors on environmental performance on their projects.

Environmental Advisors The Crossrail Environmental Advisers are responsible for:

· supporting the PM to achieve contractor compliance with the EMR via execution of the Works Information.

· Supporting PM in ensuring that the Crossrail Environmental Management System is implemented on their projects including that Crossrail environmental objectives and targets applicable to their projects are met and inputting to the Crossrail EMS Management Review

· ensuring that environmental consents are identified; applications are reviewed and, for Employer’s consents signed-off by the Crossrail Team; and consents complied with

· supporting and advising the Project Manager that environmental requirements are in place during construction.

· attending meetings with their Delivery Team, the Crossrail Sustainability and Consents Team and external stakeholders as per Section 5.3.

· developing and delivering environmental training in conjunction with the Crossrail EMS Advisor

· When necessary, undertaking environmental audits of parts of the Crossrail Programme that are outside their Area (Nb: only if advisor is qualified as a lead auditor)

Page 23: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 23 of 35 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

· communicating environmental information to the Delivery Teams and, if appropriate, contractors – including the Crossrail Environmental Policy, Objectives and Targets, Legal and other requirements and Environmental Alerts

· supporting the PM in reviewing the curriculum vitae of the contractor’s environmental personnel and the contractor’s Environmental Plan, Site Waste Management Plan, Incident Plan, other environmental documents

· as appropriate to the project risk, support Crossrail PM in the review of method statements, temporary works documents, Inspection and Test Plans.

· Reviewing 4-weekly dashboard report, quarterly objectives progress report and monitoring data

· Providing support to Crossrail’s Project Manager and Contractor’s Environment Manager to report environmental incidents rapidly and effectively and review and accept investigation reports

· accompanying the Contractor’s Environmental Manager on their environmental site inspections at least monthly. A record that both the Crossrail Environmental Advisor and Contractor’s Environmental Manager undertook the site inspection must be made on the site inspection form which must be saved into eB. The Environmental Advisor reviews the environmental inspection findings and checks that all actions have been completed adequately and in a timeframe proportionate to the risk.

· ensuring environmental documents are controlled and records are held in eB or Rivo Safeguard or Crossrail Smartwaste

· reporting to the Crossrail Project Managers and Crossrail Environment Manager on environmental performance

· Participate and support Contractor’s Environment Manager in Crossrail’s Supplier Performance Assurance process and update Crossrail’s Project Manager on environmental performance

· raising and responding to early warnings and nonconformities

· ensuring that all environmental completion records have been met by the contractor prior to the Crossrail Team accepting the works.

· Supporting Crossrail Engineering Manager in review of design documents to ensure environment requirements (e.g. environment assessment, D25 etc.) are addressed.

· Ensuring functional review of contractor documents as set out in the Sustainability and Consents Document Review Matrix (CR-XRL-T1-LST-CRG03_Z-50001).

Surface Works Director and Interface Managers for Industry Partners The Surface Works Director and Interface Managers for Industry Partners are responsible for ensuring that the Crossrail EMS is implemented for Crossrail’s interfaces with Industry Partners and for gaining assurance that Industry Partners are complying with the EMR in accordance with their Development Agreements.

Page 24: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 24 of 35 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

6. Technical Directorate Technical Director The Crossrail Technical Director is the director with specific responsibility for environmental management and is responsible for:

· ensuring that an effective Crossrail Environmental Management System is implemented

· providing adequate resources for environmental management

· providing visible leadership and commitment to high environmental standards, including undertaking leadership tours.

· reporting to other Directors and the Chief Executive on environmental performance

Chief Engineer The Crossrail Chief Engineer is responsible for ensuring that the Crossrail Environmental Management System is implemented for all design to ensure that design complies with the EMR.

Systemwide Director The Crossrail Systemwide Director is responsible for:

· ensuring contractor compliance with the EMR via execution of the Works Information.

· ensuring that the Crossrail Environmental Management System is implemented on their projects

· ensuring that technical specifications include environmental requirements

· assuring that design complies with environmental requirements including the EMR

· ensuring that construction works do not start until environmental requirements are in place

· ensuring that environmental consents are identified; applications are reviewed and, for Employer’s consents signed-off by the Crossrail Team; and consents complied with

· ensuring environmental incidents are dealt with rapidly and effectively

· providing visible leadership and commitment to high environmental standards

· reporting to the Technical Director and the Chief Executive on environmental performance on their projects.

Head of Sustainability and Consents The Crossrail Head of Sustainability and Consents is responsible for:

· providing visible leadership and commitment to high environmental standards

· ensuring that an effective Crossrail Environmental Management System is implemented

· providing adequate resources for environmental management

Page 25: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 25 of 35 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

· providing environmental advice and support to any member of the Crossrail Team particularly in the event of an environmental incident

· promoting best practise to Crossrail team

· creating strong relationships with statutory bodies.

Environment Manager The Crossrail Environment Manager is responsible for:

· providing visible leadership and commitment to high environmental standards

· ensuring that an effective Crossrail Environmental Management System is implemented

· setting environmental objectives and targets for each financial year

· providing reports on environmental performance to the Technical Director

· liaison with Industry Partners to ensure compliance with the Environmental Minimum Requirements

· providing assurance that all contractors are complying with their environmental requirements

· promoting best practise to all Crossrail Team

· providing environmental input to prequalification and tender evaluations and tender and contract documents

· providing assurance that all design complies with environmental requirements, including the EMR.

· ensuring that environmental consents are reviewed and, for Employer’s consents signed-off by the Crossrail Team

· effective communication with key stakeholders, including the Environment Agency

· providing environmental advice and support to any member of the Crossrail Team particularly in the event of an environmental incident.

EMS Advisor The Crossrail EMS Manager is responsible for:

· developing and implementing an effective EMS that complies with the Environmental Minimum Requirements and is certified to ISO14001

· providing support and advice to any member of the Crossrail Team on implementation of the Crossrail EMS and particularly in the event of an environmental incident.

· supporting the Chief Executive in the review of the Crossrail Environment Policy

· providing visible leadership and commitment to high environmental standards

· keeping up-to-date with changes in legal and other environmental requirements including updating the Legal and Other Requirements Register

· developing training sessions and delivering them to Delivery Teams in conjunction with the Environmental Advisers

Page 26: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 26 of 35 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

· maintaining the environmental parts of the Rivo Safeguard databases and the Crossrail Smartwaste database

· ensuring all documents including procedures, policies and guidelines are maintained and updated as needed

· ensuring that environmental audits of the Crossrail Team, designers and contractors are scheduled, undertaken and actions completed

· leading the management review of the Crossrail EMS, including progress in achieving environmental objectives and targets.

· Developing and implementing the Supplier Performance Assurance Process for Environment

Environmental Team The Crossrail Environmental Team supports the Crossrail Environment Manager. For assurance of Systemwide contracts (post-contract award) they will also undertake the responsibilities as for Environmental Adviser above.

Environmental Technical Specialists The Crossrail Noise and Vibration Specialists, Archaeologist and other specialists as required:

· provide expert input and advice to all parts of the Crossrail EMS including procedures, tender and contract documents and site inspections

· implement the Crossrail EMS

· effective communication with key stakeholders.

7. Support Functions Facilities Manager The Crossrail Facilities Manager is responsible for ensuring that the Crossrail Environmental Management System is implemented at Crossrail premises.

Land and Property Director The Crossrail Land and Property Director is responsible for ensuring that the Crossrail Environmental Management System is implemented during the acquisition of land and property and the facilities management of any land and property.

Page 27: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

© Crossrail Limited CRL RESTRICTED

Appendix B – Definitions and Abbreviations

CEDREC Provider of Legal update bulletins

CMS Crossrail Management System

CRL Crossrail Ltd

Crossrail ES Crossrail Environmental Statement (Volumes 1 – 9), (February 2005) and Supplementary Environmental Statements and Amendment of Provisions Environmental Statements published subsequently

Crossrail Programme (Crossrail)

The Crossrail Programme includes all the works and activities necessary to construct and commission a new railway from Maidenhead in the west to Shenfield and Abbey Wood in the east, including provision of the rolling stock and train maintenance depot.

EMR Environmental Minimum Requirements

ENDS Environmental Data Services

Designer Framework Design Consultant (FDC), Contractor, Design & Build Contractor. Any party undertaking design

IEMA Institute of Environmental Management and Assessment

IPs Industry Partners – Network Rail, London Underground, Canary Wharf Group, Berkley Homes, DLR

Netregs Environment Agency web based legislation website

Nominated Undertaker The organisation or organisations which will be appointed by the Secretary of State to design, construct, operate and maintain Crossrail

SAP Curl’s Procurement system

Scope Part A Design Contract Documentation

TfL Transport for London

TfL SHEAC Report TfL Safety, Health Environment & Assurance Committee Report; which is issued to TfL quarterly to report CRL’s HS&E performance over the last quarter.

Works Information Construction Contract Documentation

Page 28: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

© Crossrail Limited CRL RESTRICTED

Appendix C – EMS Document Register

ISO14001 Reference Procedure or key document Document Number

4.2 Environmental Policy

Crossrail Environmental Policy CR-XRL-T1-PCY-CR001_Z-50001

Crossrail Carbon Footprint Policy CR-XRL-Z-UPP-CR001-00005

4.3.1 Environmental aspects

Environmental Aspects and Impacts Register

CR-XRL-T1-ZFO-CR01-00008

Trend and Change Control Procedure CR-XRL-Z9-GPR-CR001-00002

Environmental Aspects Identification Form CR-XRL-T1-ZFO-CR001-00004

4.3.2 Legal and other requirements

Legal and Other Requirement Register CR-XRL-T1-GPR-CR001-00005

4.3.3 Objectives, targets and programme(s)

Environmental Objectives and Targets Register 2013/14

CRL1-XRL-T1-LRG-CRG03_Z-50001

4.4.2 Competence, training and awareness

Learning and Development Procedure and Policy

CR-XRL-Z2-GPR-CR001-00033

Competency Management Procedure for Delivery Team

CRL1-XRL-Z2-GPD-CR001-50001

Training Needs Matrix -

EMS Training Attendance Form

4.4.3 Communication Crossrail Communications Strategy CR-XRL-Z1-GST-CR001-00004

Community Relations Procedure CR-XRL-Z1-GPR-CR001-00005

Reporting Procedures Handbook

CR-XRL-Z9-GPR-CR001-00012

4.4.4 Documentation Environment Manual

CR-XRL-T1-GMN-CR001-00001

Technical Assurance Master Documents List

-

Construction Master Documents List - 4.4.5 Control of documents

Procedure for the Preparation and Control of Crossrail Management System (CMS)

CR-XRL-O4-GPR-CR001-00003

Document Management Procedure CRL1-XRL-Z3-GPD-CR001-50001

Sustainability and Consents Document Review Matrix

CR-XRL-T1-LST-CRG03_Z-50001

Page 29: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 29 of 35 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

ISO14001 Reference Procedure or key document Document Number

4.4.6 Operational Control

Procurement Code: Section 1: General CRL1-XRL-V3-GUI-CR001_Z-50004

Procurement Code: Section 2: Procurement Deliverables

CRL1-XRL-V3-GUI-CR001_Z-50007

Procurement Code: Section 3: Purchasing Deliverables

CRL1-XRL-V3-GUI-CR001_Z-50005

FDC Contract Documents - Scope A and Scope B

Works Information Volumes 2B and 2A

Planning Environment and Traffic Consents (Central Section) Procedure

CR-XRL-T1-GPR-CR001-00001

Trend and Change Control Procedure CR-XRL-Z9-GPR-CR001-00002

Estate Management Plan

CR-XRL-T2-GPL-CR001-00001

Environmental Facilities Management Procedure

CR-XRL-F-GPD-CR001-50001

Secure Disposal or Reuse of IT equipment Procedure

CR-XRL-Z3-GPR-CR001-00019

Canning Town Warehouse Procedure

CR-XRL-Z2-GPR-CR001-00019

Canary Wharf Group Development Agreement

Berkeley Homes Woolwich Station Box Agreement

LUL Development Agreement LU Works Package Plan Procedure

CRL1-XRL-04-STP-CR001-50002

Crossrail Network Rail Programme Protocol Crossrail Network Rail Implementation

Agreement Framework Crossrail / Network Rail Interface

Document for Environment CR-XRL-T1-GPR-CRG04-00002

Crossrail / Network Rail Interface Document for Planning, Environment and Traffic Consents

CR-XRL-T1-GPR-CRG04-00001

Memorandum of Understanding relating to Utility Diversion and Enabling Works

Procedure for the Coordination on Utilities Work Performed by the Statutory Utility Company

CRL1-XRL-U-GPD-CRG03-50001

Page 30: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 30 of 35 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

ISO14001 Reference Procedure or key document Document Number

DLR Works Agreement. Temporary Works Procedure CRL1-XRL-Z-GPD-CR001-50009

GreenLine Recognition Scheme CR-XRL-T1-GPD-CRG03_Z-50001

4.4.7 Emergency preparedness and response

Incident Management Plan CRL1-XRL-Z7-GPD-CR001-50001

Incident Investigation Procedure CR-XRL-Z7-GPR-CR001-00014

Guidance on Environmental Traffic and Planning Incidents

CR-XRL-T1-GGG-CR001-00002

4.5.1 Monitoring and measurement

Reporting Procedures Handbook CR-XRL-Z9-GPR-CR001-00012

4.5.2 Evaluation of Compliance

Audit Strategy

CR-XRL-Z-STP-CR001-50002

Audit Procedure CR-XRL-Z-GPD-CR001-50001 Management Review Procedure CR-XRL-O4-GPR-CR001-00005 Design Review Procedure CRL1-XRL-O4-GPD-CR001-

50003) Environmental Design Management

Procedure CRL1-XRL-N2-GPD-CR001-50001)

Engineering Design Assurance Gates Procedure

CRL1-XRL-O4-GPD-CR001-50002)

Issue of Design Documentation for Construction

CRL1-XRL-O4-GPD-CR001-50007)

Management and Acceptance of Field Documentation Procedure

CRL1-XRL-N2-GPD-CRG03-50001

Central Section Planning, Environment, Traffic Consents Procedure

CR-XRL-T1-GPR-CR001-0000

Review and Acceptance of Safe Systems of Work Procedure

CRL1-XRL-Z-GPD-CR001-50003

Site Mobilisation, Start-Up and Critical Activity Readiness Procedure

CRL1-XRL-Z-GPD-CR001-50007

Project Technical Requests (RFI, FCD, NCR) Procedure

CRL1-XRL-Z-GPD-CR001-50006

Contract Administration Manual

CRL1-XRL-W-GML-CR001-50001

Monitoring and Surveillance Procedure

CRL1-XRL-Z-GPD-CR001-50001

Employer’s Completion Process CRL1-XRL-04-GPD-CR001-50018

Page 31: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 31 of 35 Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited CRL RESTRICTED

ISO14001 Reference Procedure or key document Document Number

Estate Management Plan

CR-XRL-T2-GPL-CR001-00001

Environmental Consents Framework CR-XRL-T1-GUI-CRG03_Z-50002

Contaminated Land Framework CR-XRL-T1-GUI-CRG03_Z-50003

Noise Framework CR-XRL-T1-GUI-CRG03_Z-50004

Air Quality Emission Control Framework CR-XRL-T1-GUI-CRG03_Z-50001

Environmental Reporting Guidance CR-XRL-T1-GUI-CR001_Z-50001 4.5.3 Nonconformity, corrective action and preventive action

Project Technical Requests (RFI, NCR, FCD) Procedure

CRL1–XRL–Z-GPD-CR001- 50006

Risk Management Plan CR/QMS/COM/S/0811

Risk Management Procedure CR-XRL-Z9-GPR-CR001-00009

Lessons Learned Procedure CRL1-XRL-Z-GPD-CR001-50015

4.5.4 Control of records

Document Management Procedure CRL1-XRL-Z3-GPD-CR001-50001

Record Archiving, Retrieval and Disposal Procedure

CR-XRL-N1-GPR-CR001-00004

4.5.5 Internal audit

Audit Strategy

CR-XRL-Z-STP-CR001-50002

Audit Procedure

CR-XRL-Z-GPD-CR001-50001

4.6 Management review

Management Review Procedure CR-XRL-O4-GPR-CR001-00005

Page 32: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

© Crossrail Limited CRL RESTRICTED

Appendix D –Environmental Management During Design

Designer produces design including environmental deliverables

Gate Review

Engineering Design Assurance Gates

Procedure

Achieve assured Design

Issue of Design Documentation for

Construction

Temporary works Procedure

Contractor produces design including environmental deliverables

Temporary works

Permanent works

Review design including environmental deliverables

Contractor proposed change/development to

temporary works

Designer proposed change/development to

permanent works

Designer produces design environmental deliverables

Gate Review

If not accepted

Design Phase

Construction Phase

Design Management and Environment

Achieve Assured Design

Contractor

Crossrail Team

Designer

Contract document

If affects permanent

works

Design Review procedure

Crossrail Procedure

Issue Design Documentation for

Construction

Issue Design Documentation for

Construction

Achieve assured Design

Issue of Design Documentation for

Construction

Engineering Design Assurance Gates

Procedure

Desig

n cha

nges

will

also g

o thr

ough

the T

rend

and C

hang

e Con

trol P

roce

dure

of th

ey ha

ve po

tentia

l to af

fect th

e agr

eed p

rogr

amme

and/o

r pro

ject b

aseli

ne

Designer undertakes design reviews

Designer and Crossrail Team

Minor Change

Major Change

Review impact of change and deal with

any specific issues

If not accepted

Engineering Design Assurance Gates

Procedure

Audit

s

Mana

geme

nt Re

view

Page 33: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Page 33 of 35

Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited RESTRICTED

Appendix E –Environmental Management During Construction

Mobilisation

Operation

Project Stage

Environmental Management during Construction

Accept

Procedure/Document

Accept CVs for Contractor’s

environmental personnel

Submit environmental personnel CVs for acceptance

Submit Environmental Plan, Incident Plan and Site Waste

Management Plan for acceptance

Undertake works in accordance with Works Information

Close-out

Completion of requirements as defined in the Works Information

Confirm all environmental requirements complete

Attend site inspections

Manage requests for Information, Field

Change Documents & Non-Conformities

Attend meetings

Review Contractor’s reports & data

Manage consents

Review method statements

Management & Acceptance of Field Documentation Procedure

Central Section Planning, Environment, Traffic Consents Procedure

Review and Acceptance of Safe Systems of Work Procedure

Environment Manual

Project Technical Requests (RFI NCR FCD) Procedure

Site Mobilisation, Start-Up and Critical Activity Readiness Procedure

Contractual Requirement Task

Reporting Procedures Handbook

Manage early warnings

Review incident notifications and reports and investigate where

required

Incident Manual

Incident Investigation Procedure

Contract Administration Manual

Review Contractor Inspections and Test

PlanMonitoring and Surveillance Procedure

Environment Manual

Contractor

Crossrail Team

Procedure/Document

Employer’s Completion Process

Contract Master Deliverables List

Ensure all environmental requirements in place for

mobilisation start-up & critical activities

Check all environmental requirements in place for

mobilisation start-up & critical activities

Aud

its

Man

agem

ent R

evie

w

Sup

ply

Cha

in P

erfo

rman

ce M

anag

emen

t

Page 34: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Document Number

Page 34 of 35

Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited RESTRICTED

Appendix F – Design History

Scheme Design During the progress of the hybrid Bill through Parliament design work was begun to further develop the hybrid Bill design. This was undertaken by a combined management team consisting of CRL and a Development Manager (DM). Four consultants referred to as Multidisciplinary Design Consultants (MDCs), were awarded the contracts for the design of the architectural and civil engineering works. The design work on the systems was carried out by a further consultant, the Systems and Rolling Stock consultant (SRC), and the design of the enabling works was managed by an Enabling Works Managing Agent (EWMA). The work of these consultants culminated in the delivery of Scheme Design (ultimately Scheme Design 3). The environmental deliverables for Scheme Design 3 (SD3) reflecting the EMR were incorporated into each of the MDCs’ and SRC’s scope of works. During the development of Scheme Design the ES was reviewed and all significant aspects and impacts identified, together with all assumed mitigation, and entered into a register: the Register of Environmental Mitigation, Assumptions and Opportunities for Improvement (REMAOI). The REMAOI was given to the design consultants thereby ensuring that the significant aspects and impacts of the project and the associated assumed mitigation were considered during the design process. In addition, where the development of Scheme Design resulted in a change to the hybrid Bill scheme (either the permanent or temporary works i.e. physical structures or construction planning) the design teams were required to follow the Environmental Design Management Procedure (CR-DV-MGT-X-PD-00015, now withdrawn) to evaluate the change to establish the position of the design against paragraph 1.3 of the EMR General Principles. A key output for each work package associated with Scheme Design was a statement of compliance with the EMR based upon a completed and updated REMAOI and supported by completed checklists and reports pursuant to the Environmental Design Management Procedure.

Page 35: SUSTAINABILITY & CONSENTS Environment Manual Legacy … · Legacy Document Environment Manual CR-XRL-T1-GMN-CR001-00001 Rev 6.0 Page 2 of 35 Document uncontrolled once printed. All

Learn

ing Le

gacy

Doc

umen

t

Environment Manual

CR-XRL-T1-GMN-CR001-00001 Rev 6.0

Document Number

Page 35 of 35

Document uncontrolled once printed. All controlled documents are saved on the CRL Document System

© Crossrail Limited RESTRICTED

Detailed Design At the end of Scheme Design 3 the contracts with the design consultants essentially ended and new contracts were tendered and awarded to carry out the detailed design. The environmental requirements for detailed design were reviewed and captured in the new contracts under the Engineering Design Framework Agreement Scope Part A. As part of that review it was identified that there was no longer a need to maintain the REMAOI because the requirements of the EMR would be met through the deliverables under Scope Part A and through the continued use of an environmental design management procedure. As the original environmental design management procedure (CR-DV-MGT-X-PD-00015) was written under different contractual arrangements and with a different organisational structure it was withdrawn. However, the key element of the procedure was a checklist that provides a tool for evaluating a design against the general principles of the EMR, and this was retained as part of the EMS Not all design work ceased between the delivery of SD3 and the start of the detailed design under the new Framework Design Contractors. In order to preserve the Crossrail schedule (PCS03) certain detailed design pertaining to demolitions, utility diversions and some early shaft construction continued under the pre-Framework contract arrangements. This post SD3 design work (also referred to as post purple diamond design work due to the delivery date of SD3 being referred to as ‘Purple Diamond’) was carried out subject to continuation instructions. The environmental deliverables for these post purple diamond design works were defined as part of the continuation instruction. Prior to April 2011, the management of the production for the detailed design of the central section was undertaken by the Project Delivery Partner (PDP). The PDP had responsibility for delivering the design of the central section in accordance with the EMR through a contract with CRL (Project Delivery Partner Services Contract No. 2166). Under that contract the PDP was required to deliver compliance with the EMR and to ensure that the central section design complied with the EMS requirements and to develop an EMS. The PDP had an environmental design compliance procedure under its EMS which incorporates the checklist (CRL/EMS/F/1306). As noted above, detailed design was being undertaken by the Framework Design Consultants (FDCs) who were directly managed by the PDP. These FDCs were required to comply with and provide deliverables pursuant to Scope Part A