DESCRIPTION

Sustainable Energy Ireland. Exploiting the Resource David Raubenheimer March 2004. Fibrowatt Overview. Developer owner operator Power from agricultural residues 65 MW operational 2,650,000 MWh produced, 3.7 million tonnes fuel Overview of Fibrowatt’s plants. The Carbon Cycle. - PowerPoint PPT Presentation

Citation preview

Page 1: Sustainable Energy Ireland

Sustainable Energy Sustainable Energy IrelandIreland

Exploiting the Resource

David Raubenheimer

March 2004

Page 2: Sustainable Energy Ireland

2

Fibrowatt OverviewFibrowatt Overview

• Developer owner operator• Power from agricultural residues• 65 MW operational• 2,650,000 MWh produced, 3.7

million tonnes fuel• Overview of Fibrowatt’s plants

Page 3: Sustainable Energy Ireland

3

NUTRIENTS

CARBON (CO2)

Flue Gases

Ash

ELECTRICITY

EN

ER

GY

BIOMASSBEDDING

& FEED

MANURE

The Carbon CycleThe Carbon Cycle

Page 4: Sustainable Energy Ireland

4

Power StationsPower Stations

Power Station

Company MW Location

Eye (World’s first)

Fibropower 12.7MW Suffolk

Glanford Fibrogen 13.5MW N Lincs

Thetford Fibrothetford 38.5MW Norfolk

Page 5: Sustainable Energy Ireland

FibropowerFibropower

Commissioned Jul 1992 Design output 12.7MW

Burns 150,000 t/yr of poultry litter & other biomass

Page 6: Sustainable Energy Ireland

6

Fibropower - Operational Fibropower - Operational ExperienceExperience

• Development of know-how• Fuel characterisation difficult• Biomass knowledge fragmented• No available standards• Now runs exceptionally well• New fuels trialled

Page 7: Sustainable Energy Ireland

FibrogenFibrogen

Commissioned Nov 1993Design output 13.5MW

3-5 yr Govt contract for 85,000 t/yr of meat & bone meal

Page 8: Sustainable Energy Ireland

8

FibrogenFibrogen

• Commercially similar to Fibropower

• 8% larger• New fuel handling – design trials• Technically very successful• Achieves 90 – 100% availability• Converted to burn MBM

Page 9: Sustainable Energy Ireland

FibrothetfordFibrothetford

Commissioned 1998 Design output 38.5MWBurns 460,000 t/yr of poultry litter & other biomass

Page 10: Sustainable Energy Ireland

10

FibrothetfordFibrothetford

• Significant scale up – 3x• New fuel storage – design trial• Environmentally sensitive site• Environmental standards changed• Construction contractors more

cautious• Scale up caused technical

problems• Now running well

Page 11: Sustainable Energy Ireland

11

How it Works – How it Works – in the plantin the plant

Page 12: Sustainable Energy Ireland

12

Technology – Current Technology – Current PlantsPlants

Fibropower Fibrogen Fibrothetford

Fuel Handling Cranes Cranes Augers/Conveyors

Fuel Feeding Mass Pneumatic Air Distributor

Grate Reciprocating Chain Grate Chain Grate

Boiler ‘Folded’ ‘Folded’ Bi-Drum

Balance Conventional Conventional Conventional – Ash more complex

Emissions Control

Electrostatic Precipitator

Bag Filter/

Semi dry scrubber

Bag Filter/

Dry line injection

Steam Conditions - 65 Bar, 450°C to 475°C – all plants

Page 13: Sustainable Energy Ireland

13

Fuel Pits at FibrogenFuel Pits at Fibrogen

Page 14: Sustainable Energy Ireland

14

Thetford Fuel HallThetford Fuel Hall

Page 15: Sustainable Energy Ireland

15

Fuel Trucks UnloadingFuel Trucks Unloading

Page 16: Sustainable Energy Ireland

16

Fibrogen - MBM Fibrogen - MBM ConversionConversion

Page 17: Sustainable Energy Ireland

17

Inside Inside the the

BoilerBoiler

Page 18: Sustainable Energy Ireland

18

Technology - ResultsTechnology - Results

• Poultry litter burns very well• Characterisation is difficult• Handling needs care• Combustion performance• Certain arrangements excluded

Page 19: Sustainable Energy Ireland

19

Technologies ReviewedTechnologies Reviewed

• Have reviewed a number• Stepwise development strategy• Fluidised Bed• Gasification• Digestion• High tech may be

counterproductive

Page 20: Sustainable Energy Ireland

20

What a Project NeedsWhat a Project Needs

• Available, contactable & characterised fuel supply

• Affordable electrical connection• €4+ million to develop• 2 - 5 yrs development, 2 yrs

construction• Incentivised construction

contractors• Available land and local support

Page 21: Sustainable Energy Ireland

21

What a Project Needs (2)What a Project Needs (2)

• Power Purchase Agreement– Bankable

– Long term (construction +15 years)

– Technology specific

• Ash fertiliser sales routes• Abundant political support

Page 22: Sustainable Energy Ireland

22

SummarySummary

• 2,650,000 MWh• 3,700,000 tonnes of fuel • Significant teething problems

overcome• Structure new market with care• Particularly the Power Sale

arrangements• Consistent and broad political