SW101

Large and Small Construction

Denise Hamilton, EPA Region 6

8th Annual Region 6 MS4 Operators Conference

June 26, 2006

Page 2: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 3: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

Source: NCTCOG Storm Water Pollution Prevention Storm Water Pollution Prevention

Practices for Practices for Construction

Page 4: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 5: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

Source: NCTCOG Storm Water Pollution Prevention Storm Water Pollution Prevention

Practices for Practices for Construction

Page 6: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 7: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

Regulated Industrial Activities:Construction

• Found under Category (x) of “Industrial Activity” and in “Small Construction”

• Land Disturbance of one or more acres– Clearing, grading or excavation

• Activities part of a larger common plan of development– Multiple activities within a contiguous area

– Includes activities taking place on different schedules

Page 8: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

“Common Plan”

EX: 8-¼ acre lots in subdivision = 2 acre small construction project

Page 9: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

“Common Plan”

EX: 32-¼ acre lots in subdivision = 8 acre large construction project

Page 10: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

Part of “Common Plan”

EX: First ¼ acre lot = part of larger development project

Page 11: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

“Common Plan” - Infill

EX: ¼ acre lot, 4 left = part of 1 acre small construction project

Page 12: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

“Common Plan” - Infill

EX: ¼ acre lot, 2 left = part of ½ acre project

Page 13: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

“Common Plan” – New Plan

POOL

EX: ¼ acre lot later adding pool => only count pool disturbance

Page 14: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

“Common Plan” – ¼ Mile

EX: Existing road, projects ¼ apart = part of 1/4 acre project

Page 15: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

“Common Plan” – Future Plans

EX: If college grows, we have area we could put new dorm someday

Page 16: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

Who Needs a Permit – “Operators”

. . . any party associated with the construction project that meets either of the following criteria:

(1) The party has operational control over project specifications (including the ability to make modifications in specifications), or

(2) the party has day-to-day operational control of those activities at a project site which are necessary to ensure compliance with the storm water pollution prevention plan or other permit conditions (e. g., they are authorized to direct workers at the site to carry out activities identified in the storm water pollution prevention plan or comply with other permit conditions).

Page 17: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

Large Construction (Phase I) Permitting

• Construction General Permit (CGP)

• No waivers available

• Requires storm water pollution prevention plan and NOI

Page 18: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

Small Construction (Phase II) Permitting

• EPA has one CGP, some states have separate large vs. small general permits

• Potential permit coverage for:– Construction activity that disturbs less than 1 acre of

land may be designated based on water quality impact

Page 19: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

Waivers for Small Construction Activities

• Rainfall erosivity factor less than 5 (“low rainfall erosivity”)

• Storm water controls are not needed based on a TMDL or equivalent assessment that addresses the pollutants of concern

Page 20: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

Overview of Storm Water Construction General Permits & BMPs

Page 21: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

How Do General Permits Work?

• Permit issued and then eligible dischargers “register” with a Notice of Intent (NOI)

• STEPS:– Get copy of permit– Make sure you are eligible– Prepare Pollution Prevention Plan (SWP3)– THEN submit NOI

Page 22: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

How Could MS4 Permits Impact Construction?

• Requirement for MS4 controls on construction

• Requirement for MS4 controls on development and redevelopment

• Requirements for public involvement and participation in MS4 Storm Water Management Program

• QLPs?

Page 23: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

CGP in a Nutshell

City of Greater Bendigo, Victoria, Australia

Page 24: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

What Discharges are Covered by the Permit?

• Storm water discharges associated with large construction (5+ acres)

• Storm water discharges associated with small construction (1-5 acres)

• Certain incidental non-storm water discharges associated with construction sites

Page 25: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

What Discharges are NOT Covered by the Permit?

• Most non-storm water

• Post construction storm water discharges

• Discharges under another permit

• Discharges that would cause or contribute to non-attainment of water quality standards

• Discharges not consistent with a TMDL

Page 26: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

Endangered Species Act and the CGP

• Permittees must certify on the NOI that no impacts to endangered species are likely or have previous ESA authorization for adverse effects

• Addendum contains guidance

Page 27: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

National Historic Preservation Act and the CGP

• Must certify: – That discharges do not affect property that is listed,

or eligible for listing, under the NHPA; or – That facility can obtain, and maintain compliance

with, a written agreement with the State or Tribal Historic Preservation Officer

• Addendum contains guidance

Page 28: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

What Goes Into a SWP3?

• Site information and map• Best Management Practices (BMPs) you will use• Records/Inspections• Feedback loop on effectiveness – the SWP3 is

supposed to be a “living” document

Page 29: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

What BMPs must be in a SWP3?

• LOTS of flexibility• Must include:

– Site and activity description– Controls to reduce pollutants during construction– Stabilization of disturbed areas– Description of post-construction controls

Page 30: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 31: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 32: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 33: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 34: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 35: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 36: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 37: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 38: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 39: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 40: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 41: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 42: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 43: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 44: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 45: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 46: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 47: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 48: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 49: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 50: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 51: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 52: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 53: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

I’ve got permit coverage, now what?

• Post your site sign

• Implement the SWP3 you developed

• Conduct and document your inspections – addressing any maintenance or SWP3 revisions as necessary

• Option to inspect every other week plus after 0.5” rain OR simply once per week – document your choice in your SWP3 (1/wk option not available in all States)

Page 54: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

When can I terminate my permit?

• Earth disturbing activities finished and site has been finally stabilized

• Someone else has replaced you as the “operator”

• For residential construction, once site is temporarily stabilized and occupied by the homeowner (e.g, wants to put in their own lawn).

Page 55: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006

What are my“final stabilization” options?

• 70% of background vegetative cover (semi-permanent practices leading to final stabilization allowed in some states)

• Non-vegetative stabilization (riprap, gabions, etc.) –impervious cover used simply for stabilization should be avoided

• On agricultural land, return to pre-construction agricultural use (e.g., row crops, etc.)

Page 56: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006
Page 57: SW101 Large and Small Construction Denise Hamilton, EPA Region 6 8 th Annual Region 6 MS4 Operators Conference June 26, 2006