59
ii SYLLABUS This emergency plan outlines procedures to be used as a guide in the event that critical conditions develop which may lead to failure of the dam at Otter Brook Lake or an uncontrolled release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel to take necessary and immediate remedial action to prevent or minimize loss of life and property damage.

SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

ii

SYLLABUS This emergency plan outlines procedures to be used as a guide in the event that critical conditions develop which may lead to failure of the dam at Otter Brook Lake or an uncontrolled release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel to take necessary and immediate remedial action to prevent or minimize loss of life and property damage.

Page 2: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

iii

OTTER BROOK LAKE FLOOD EMERGENCY PLAN TABLE OF CONTENTS Section Page 1. INTRODUCTION ......................................................................................................... 1-1

a. Purpose ............................................................................................................... 1-1 b. Authority ............................................................................................................ 1-1 c. Applicability ...................................................................................................... 1-1 d. References ......................................................................................................... 1-1 e. Scope .................................................................................................................. 1-2 f. Periodic review and update ................................................................................ 1-2

2. DESCRIPTION OF PROJECT AREA .......................................................................... 2-1

a. Location ............................................................................................................. 2-1 b. Topography ........................................................................................................ 2-1 c. Geology/Soils ..................................................................................................... 2-1 d. Seismicity ........................................................................................................... 2-1 e. Climate ............................................................................................................... 2-1 f. Project Features .................................................................................................. 2-1 g. Project Lands ..................................................................................................... 2-2 h. Instrumentation ................................................................................................. 2-2 i. Downstream Valley & Towns ........................................................................... 2-4

3. PROJECT STAFF .......................................................................................................... 3-1 4. COMMUNICATIONS .................................................................................................. 4-1

a. Reports from Corps Projects .............................................................................. 4-1 b. Cooperation with Downstream Water Users ..................................................... 4-1 c. Precipitation Reporting Network ....................................................................... 4-1 d. River Reporting Network ................................................................................... 4-2 e. Automatic Data Collection ................................................................................ 4-2

5. EMERGENCY IDENTIFICATION SUBPLAN ........................................................... 5-1

a. General ............................................................................................................... 5-1 b. Possible Cause of Emergencies and Recent Studies .......................................... 5-1 c. Surveillance and Inspection ............................................................................... 5-3

Page 3: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

iv

6. EMERGENCY OPERATIONS AND REPAIR SUBPLAN ......................................... 6-1 a. General ............................................................................................................... 6-1 b. Responsibilities .................................................................................................. 6-1 c. Safety of Personnel and Equipment ................................................................... 6-1 d. Inventory of Equipment, Materials and Suppliers ............................................. 6-1 e. Emergency Contract Authority .......................................................................... 6-2 f. Dewatering ......................................................................................................... 6-2 g. Guide for Repair/Response to Distress .............................................................. 6-3

7. NOTIFICATION SUBPLAN ........................................................................................ 7-1

a. General ............................................................................................................... 7-1 b. Rapidly Developing Condition .......................................................................... 7-1 c. Large Reservoir Release and/or Reservoir Impoundment ................................. 7-2 d. Dam Failure in Progress .................................................................................... 7-3 e. Notification of the Corps, Office of the Chief of Engineers (OCE) .................. 7-4 f. Inquiries and Press Releases .............................................................................. 7-4

8. EVACUATION SUBPLAN .......................................................................................... 8-1

Page 4: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

v

TABLE OF CONTENTS (CONTINUED) TABLES Number Page

Page 5: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

vi

Page 6: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

vii

1 Pertinent Data - Otter Brook Lake ................................................................................. 2-3 LIST OF PLATES Plate Title Plate 2-1 Basin Map Plate 2-2 Reservoir Map Plate 2-3 General Plan of the Dam Plate 2-4 Project Lands & Road Barricades Plate 2-5 Location of Strong Motion Instrumentation Plate 4-1 Mobile Radio Operating Instructions Plate 5-1 Required Reconnaissance Inspection for Predetermined Elevations at 35

Dams Plate 5-2a Signs of Distress through Plate 5-2g Plate 5-3a Inspection Checklist through Plate 5-3d Plate 5-4 Description of Characteristic Effects for Earthquakes Plate 6-1a Inventory of Equipment, Materials and Suppliers through Plate 6-1c Plate 6-2a Emergency Drawdown Curves Plate 6-2b Area & Capacity Curves Plate 6-2c Area Capacity Table Plate 6-2d Percent Full Curve Plate 6-2e Spillway Rating Curve Plate 6-2f Outlet Rating Curve for One Gate Plate 6-2g Outlet Rating Curves for All Gates Fully Open Plate 6-2h Inflow Curves Plate 6-3 Ringing a Boil Plate 6-4 Bomb Threat

Page 7: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

viii

LIST OF PLATES (CONTINUED) Plate Title Plate 7-1 Rapidly Developing Condition/Notification Subplan Plate 7-2 Large Reservoir Releases and/or Reservoir Impoundment Above

Spillway/Notification Subplan Plate 7-3 Dam Failure in Progress/Notification Subplan Plate 7-4 Situation Report Guideline Plate 7-5a District Notification List/Emergency Response Team and 7-5b Plate 7-6a District Notification List/Field Personnel and 7-6b Plate 7-7 Notification List for Local and State Officials and Other Federal

Agencies Plate 7-8 HQUSACE Civil Works Project/Distress Notification List Plate 7-9a Sample News Release and 7-9b Plate 7-10 Media Notification List Plate 7-11 Index Map Plate 7-12a Inundation Maps through Plate 7-12c

Page 8: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

ix

Page 9: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

1-1

1. INTRODUCTION

a. Purpose - This plan provides a guide for actions to identify and mitigate or respond to various types of emergencies which, while rare, could occur in the operation of the Otter Brook Lake Project. The resulting actions are intended to protect the public from possible property damage or loss of life from the particular emergency situation.

b. Authority - The authority for this work is set forth in Corps of Engineers Regulation ER 1130-2-419: Dam Operation Management Policy.

c. Applicability - The emergency plan is applicable to all Corps elements and field offices involved with the operation of Otter Brook Lake.

d. References

1. Flood Emergency Plans, June, 1980, Hydrologic Engineering Center.

2. Federal Guidelines for Dam Safety, June, 1979, Federal Coordinating Council for Science, Engineering and Technology.

3. ER 500-1-1 Natural Disaster Procedures, 11 March 1991, U.S. Army Corps of Engineers.

4. Earthquake Design and Analysis for Corps of Engineers Dams, August, 1980, Department of Army, New England District.

5. Liquification and Cyclic Mobility Potential, Phase I, September, 1980, Department of Army, New England District.

6. Liquification and Cyclic Mobility Potential, February, 1981, Department of Army, New England District.

7. ER-1130-2-419, Dam Operations Management Policy, May 18, 1978, Department of Army.

8. ER-1110-2-101, Reporting of Evidence of Distress of Civil Works Projects, Department of Army, U.S. Army Corps of Engineers.

9. Operations and Maintenance Manual, Otter Brook Lake, March 1971, Department of Army, New England District.

10. Periodic Inspection Report No. 5, Otter Brook Lake, October 1997, Department of Army, New England District.

11. Dam-Break Flood Analysis, Otter Brook Lake, June, 1985, Department of Army, New England District.

Page 10: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

1-2

12. Design Memorandum No. 11, Otter Brook Lake, September 1967,

Department of Army, New England District.

13. Appendix E, Master Manual of Reservoir Regulation, Connecticut River Basin, January 1972, Department of Army, Corp of Engineers.

e. Scope - This plan covers identification of impending or existing emergencies, notification of other parties concerning impending or existing emergencies, and repair operations and repairs. It addresses emergencies related to reservoir water levels above spillway crest and/or the rapid release of large volumes of water past the dam.

This flood emergency plan presently includes the following three subplans:

(a) EMERGENCY IDENTIFICATION SUBPLAN - SECTION 5

(b) EMERGENCY OPERATIONS AND REPAIR SUBPLAN - SECTION 6

(c) NOTIFICATION SUBPLAN - SECTION 7 THE EVACUATION SUBPLAN WILL BE PREPARED BY STATE AND/OR LOCAL CIVIL PREPAREDNESS OFFICIALS AT A LATER DATE.

f. Periodic review and update - In accordance with ER 1130-2-419, the notification and reporting procedures prescribed in this Flood Emergency Plan should be reviewed at least annually with local, State and Federal agencies at the field level with updates as required.

In addition, the COE will periodically review and update this Flood Emergency Plan to keep it current. The MINIMUM specific items to be reviewed and updated are:

Section 1: INTRODUCTION d. Reference

Section 2: DESCRIPTION OF PROJECT AREA

h. Instrumentation

Section 4: COMMUNICATIONS e. Automatic Data Collection

Section 5: EMERGENCY IDENTIFICATION SUBPLAN

b. Possible Cause of Emergencies and Recent Studies

1. Structural Stability of Concrete Structures 2. Embankment Stability Re-evaluation 3. Seismic Stability

Page 11: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

1-3

4. Periodic Inspection

c. Surveillance and Inspection 1. Inspection of Floods

Section 6: EMERGENCY OPERATIONS AND REPAIR SUBPLAN

e. Emergency Contract Authority

Section 7: NOTIFICATION SUBPLAN

f. Inquiries and Press Releases

Plates Titles

5-1 Required Reconnaissance Inspection for Predetermined Elevations at 35

dams

6-1a Inventory of Equipment, Materials and Suppliers through 6-1c

7-5a and District Notification List/Emergency Response Team 7-5b

7-6a and District Notification List/Field Personnel 7-6b

7-7 Notification List for Local and State Officials and Other Federal

Agencies

7-8 HQUSACE Civil Works Project/Distress Notification List

7-10 Media Notification List

Page 12: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

2-1

2. DESCRIPTION OF PROJECT AREA

a. Location - The Otter Brook Reservoir is located between the city of Keene and the town of Roxbury, Cheshire County, in the Monadnock region of Southern New Hampshire. Full pool elevation of the reservoir at 781.0 feet NGVD extends 2.3 miles upstream from the dam site through Keene and Roxbury and controls a drainage area of 47 sq. miles. See Plate 2-1 for location of Otter Brook Lake.

b. Topography - The topography of the area is characterized by hilly land with moderate relief. In the reservoir area the valley is steep-sided and narrow. The valley floor is about- 300 feet wide at the dam, about 1200 feet wide at the widest point, at the upstream limit of the permanent pool and it narrows rapidly to 200 feet or less in the next haft mile. The hills on the east side reach an elevation of 1400 feet NGVD.

c. Geology/Soils - The thin overburden on the right abutment consists of gravelly, silty sand and forest debris. On the left abutment where the rock is deeply buried, overburden is glacial till underlain by variable deposits of outwash materials. In the valley bottom the overburden is variable silty, gravelly sand. A shallow layer of silt occurs throughout the narrow flood plain on the easterly side of the stream.

d. Seismicity - The dam is located in Seismic Zone 2 which has a seismic coefficient of 0.10.

e. Climate - The climate of the area is variable, characterized by frequent but short periods of heavy precipitation with a mean annual temperature of 45 degrees F. The average monthly temperature varies from about 70 degrees F. in July to about 20 degrees F. in January. Freezing temperatures may be expected from the latter part of September through early May. Extreme temperatures of record are - 32 degrees and l04 degrees F. The mean annual precipitation is about 39 inches, with a record maximum of 51.2 inches in 1951. The average snowfall is about 60 inches in a year. The summer season is warm and pleasant and is attractive for outdoor activities.

f. Project Features - The important physical components consist of a rolled earth dam with rock slope protection, chute spillway, outlet works, storage for flood control and facilities for recreational purposes. A reservoir map is shown on Plate 2-2 with a general plan of the dam on Plate 2-3.

The dam embankment consists of compacted earth and rock slope protection and is 1,288 feet long with a maximum height above the streambed of 133 feet. The top of dam at elevation 802.0 feet NGVD provided 17.3 feet of spillway surcharge and 3.7 feet of freeboard (based on review of the design criteria in 1967). The top width of 25 feet accommodates an 18-foot paved access road. The embankment slones are 1 on 2.5.

The spillway is located in a rock cut at the west abutment. The 145-foot length of the ogee-shaped weir has its crest at elevation 781 feet NGVD which is 5 feet above the

Page 13: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

2-2

approach channel. The chute has a width of 142 feet at the spillway apron and transitions uniformly to a width of 60 feet in its 600-foot length.

The outlet works consist of a gate chamber, control tower and operating house on the upstream side of the dam. A 6-foot diameter Boston Horseshoe discharge tunnel passes through the foundation and empties into Otter Brook at the downstream toe of the dam. The gate structure contains three 2'-6" x 4'-6" hydraulically operated vertical slide gates used for regulation purposes. The inlet elevation is 683.0 feet NGVD. The recreation pool, located immediately upstream of the center flood control gate, is controlled by a weir with crest elevation of 701 feet NGVD Pertinent data is contained in Table 1.

g. Project Lands - Otter Brook Lake is a flood control project. Its primary purpose is to provide flood protection for the community of Keene, New Hampshire, and secondly to reduce flood stages at other downstream communities on the Ashuelot and Connecticut Rivers. In addition, the Otter Brook Lake project provides water-based recreational facilities. The recreational facilities for public use include picnicking, hiking, swimming, fishing, hunting and boating.

There are several roads that pass through the reservoir area that are subject to inundation during the storage of floodwaters. Inasmuch as public safety is involved in the use of the roads, the dam operators are responsible for seeing that these roads are barricaded whenever necessary. The access road to the recreation area is barricaded by the Corps during the fall, winter and spring months, and during the summer months on rainy days and every evening. In addition, when a rising pool is expected to reach a stage of 27 feet, the dam operator will consider barricading the road to the lowest parking area, stage about 30 feet. Refer to Plate 2-4 for barrier locations.

h. Instrumentation

1. General - Instrumentation related to the regulation of the project includes equipment to measure hydrologic conditions, reservoir outflow and reservoir levels.

2. Hydrologic Instrumentation

a. Rain Gage -The project is equipped with a standard weighing and recording National Weather Service precipitation gage.

b) Reservoir Pool Stage Recorder - The project is equipped with a continuous float type pool stage recorder located in the control tower.

c) Tailwater Gage - A USGS gaging station downstream of the dam provides a continuous record of releases from the project.

Page 14: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

2-3

TABLE 1 PERTINENT DATA OTTER BROOK LAKE

LOCATION: DRAINAGE AREA: STORAGE USES:

Otter Brook, Keene, New Hampshire 47 Square Miles Flood Control, Recreational Uses

RESERVOIR STORAGE CAPACITY

Elevation (ft NGVD)

Stage (ft)

Area (acres)

Acre- Feet

Inches on Drainage

Area

Inlet Elevation Conservation Uses Flood Control Total @ Spillway Crest Maximum Surcharge Top of Dam

683.0 701.0 781.0 781.0 797.1 802.0

0 18 98 98

114.1 119

0 70

375 375 444

--

0 700

17,600 17,600 6,500

--

0 0.3 7.0 7.0 2.6 --

EMBANKMENT FEATURES

Main Dam Dike

Type

Rolled Earth Fill with Rock Slope

Protection

None

Length (ft) Top Width (ft) Top Elevation (ft NGVD) Maximum Height (ft) Total Volume (cu yd)

1,288

25 802 133

988,800

SPILLWAY

Location Type Crest Length (ft) Crest Elevation (ft NGVD) Maximum Surcharge (ft above crest) Maximum Discharge Capacity (cfs)

Rock cut at the west abutment Uncontrolled, Ogee Weir and Chute in Rock 145 781.0 16.1 34,500

OUTLET WORKS

Type Tunnel Inside Diameter (ft) Tunnel Length (feet) Service Gate Type Size Emergency Gate Type Size Downstream Channel Capacity (cfs) Max. Discharge Capacity at Spillway Crest Elevation (cfs) Stilling Basin Length (ft) Width (ft) Elevation (NGVD)

Conduit on Rock foundation-Boston Horseshoe Section 6 589 Hydraulic Sluice Three, 4'6" high x 2'6" wide None 600 1500 35 (also baffles and 4 ft. end sill) 25 658.0

Page 15: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

2-4

3. Geotechnical Instrumentation

a) Piezometers - A total of twelve piezometers were installed in 1989 to monitor embankment and foundation conditions.

b) Crest Monumentation - Seven survey crest monuments and five control points were installed in 1985 to monitor horizontal and vertical movements of the embankment. Note: Plate 2-5 shows locations of dams with strong motion instrumentation.

i. Downstream Valley & Towns - Otter Brook joins Minnewawa Brook about 2.4 miles downstream from Otter Brook Dam to form the Branch River. The Branch joins the Ashuelot River just downstream from its confluence with Beaver Brook and nearly 5 miles downstream from the dam. The Ashuelot River travels through three communities, Keene, Swanzey and Winchester, in downstream order, prior to reaching the Connecticut at Hinsdale. Through this reach, the river normally ranges from 50 to 100 feet in width. The flood plain is generally less than 1,000 feet in width except for the reach about 7 miles before Dickinson Dam, which is as wide as 13,000 feet.

The channel of Otter Brook and the Branch is steep and conducive to rapid runoff, falling about 210 feet in the first 5 miles downstream from Otter Brook Dam, with an average gradient of 53 feet/mile. An unnamed dam at river mile 3.5 is breached at elevation 499.8 feet NGVD. This structure would have no effect on the dam failure flood wave levels and was therefore ignored.

Between river miles 5 and 9 the Ashuelot River channel meanders with a relatively small channel cross sectional area and significantly flatter gradient forming the Keene flood plain, the most predominant feature of the Ashuelot River watershed. Average gradient in this area is about 2.5 feet/mile. Additionally, inflows from Ash Swamp Brook and the South Branch Ashuelot River contribute to discharges on the Ashuelot River in the Keene flood plain area. Incoming floodwaters are ponded in the flood plain, attenuating resultant flows downstream.

The average Ashuelot River gradient remains about 2.5 feet/mile until river mile 24.2 where the invert drops 245 feet in the last 5.3 miles for an average slope of 46 feet/mile to the Connecticut River. The Connecticut River from the Ashuelot River to Turners Falls Dam in Turners Falls, Massachusetts is much flatter with an average slope of about 2 feet/mile. Turners Falls Dam and the adjacent French King Gorge create a backwater effect which extends upstream into the Ashuelot River and controls stages at its lower end, below the Hinsdale and Fiske Paper Company Dam.

Otter Brook, the Branch River and the Ashuelot River are crossed by numerous state highways, railroad lines and local roads.

Page 16: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

3-1

3. PROJECT STAFF

Otter Brook Lake is one of seven projects located in the Corps of Engineers Upper Connecticut River Basin. It is operated jointly with the Surry Mountain Lake Project. The staff includes a Project Manager and a Park Ranger. The staff can always be reached at one of the two projects. The Basin Manager is located in Springfield, Vermont which is approximately 40 miles distant. Future reference to "Project Manager" in this report means the designated Project Manager or an individual in charge (i.e. Basin Manager, Park Ranger or other designated representative) of Otter Brook Lake.

Page 17: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

4-1

4. COMMUNICATIONS

a. Reports from Corps Projects - The New England District radio network, shown on the enclosed Mobile Radio Operating Instructions, Plate 4-1, consists of a link from District Headquarters in Concord to various transmitters and relay facilities, which transmit voice signals to and from staffed reservoirs.

In addition to those base station radios, Corps projects are equipped with mobile radios to permit contact with Concord Headquarters by field personnel during reconnaissance activities. Likewise, Headquarters is also equipped with mobile radios.

Voice communication between Project Managers and Reservoir Regulation Team are normally made via the District radio network during normal work hours or whenever Headquarters is staffed. Whenever the radio network is inoperative or during nonwork hours, reports and instructions are issued via telephone (See Plates 7-6a & 7-6b). In the event of failure of the radio network and telephone service, emergency communications will be attempted through State Police or Civil Preparedness radio facilities (see Plates 7-7).

In the event of complete communication failure with Reservoir Regulation Team, the Project Manager can perform limited operations as referenced in the Connecticut River Basin, Master Water Control Manual, Appendix E, paragraph 29.

b. Cooperation with Downstream Water Users - It is the policy of the Corps of Engineers to cooperate with downstream water users and other interested parties or agencies. The Project Manager may be requested by downstream users to deviate from normal regulations for short periods of time. Whenever a request for such a modification is received, the Manager shall ascertain the validity of the request and require the individual making the request to obtain assurance from other downstream water users that they are agreeable to the proposed operation. The manager will then relay the information to RRT for consideration. A minimum release from all projects for downstream fish life shall be maintained during periods of regulation.

c. Precipitation Reporting Network - Reports of precipitation data from the Connecticut River Basin are used primarily for the purpose of alerting regulation personnel and providing a basis for appraising the severity of the storm. Collection and reporting of precipitation data are the responsibility of the Project Managers who also receive calls from observers in the basin.

The Reservoir Regulation Team periodically reviews network arrangements to insure that an adequate reporting network is maintained. The River Forecast Center in Taunton, Massachusetts receives precipitation reports from observers in and near the Connecticut River Basin, which are available to RRT upon request. In addition, cooperative reporting procedures from many Corps dams have been established with the River Forecast Center and have been detailed in separate memos to each Project Manager.

Page 18: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

4-2

d. River Reporting Network - A network of river stage observation stations, which is part of an overall river reporting system for the Connecticut River basin, has been established. This network assists in the execution of the reservoir regulation plan by permitting personnel in RRT or at the dams to obtain river stages at selected key index stations located either on tributaries or on the Connecticut River.

The river reporting system in the Ashuelot River watershed consists principally of the following station in downstream order:

Staff Gage Island Street Bridge, Keene, New Hampshire: USGS telemark gage, Keene Pumping Station (telemark #603-352-8810)

Staff Gage, Downstream of Highway Bridge, Winchester, New Hampshire: USGS telemark, Montague City on Connecticut River, Staff gage at MacKenzies' Bridge, Court Street, Keene, New Hampshire.

These observations are obtained either by the dam operators or by local observers.

Complete information concerning other key locations on the Connecticut River and its tributaries are obtained from other operators of flood control projects and the NWS River Forecast Center at Taunton, Massachusetts.

e. Automatic Data Collection - The effective regulation of 35 flood control dams in the New England District requires a rapid method of collecting and coordinating hydrologic data by the Reservoir Regulation Team (RRT). Consistent with this requirement, RRT maintains an Automatic Data Collection and Reporting Network (NEDSAT). NEDSAT presently consists of 75 remote reporting stations and one ground receive station at New England District headquarters. The remote reporting stations are situated at selected USGS and NWS gages monitoring streamflow and precipitation data as well as at all 35 flood control dams. This information is transmitted to NOAA's Geostationary Operational Environmental Satellite (GOES), and then retransmitted to the ground receive station in Concord.

During normal conditions, data transmission from the stations will occur about 2 to 5 times a day. However, the frequency of data transmission increases as hydrologic conditions worsen, occurring as often as several times an hour for severe conditions. Data collection platforms (DCP's) at the reporting stations contain uninterruptible power supplies (UPS). The UPS allows the station to continue to operate after the normal power supply is interrupted, as in the case of major storms or hurricanes. Batteries used in the UPS are charged by commercial AC power, thermoelectric generators, or solar panels, and can provide sufficient energy to operate up to 3 weeks, depending on system activities.

In addition, NED also maintains a DOMSAT ground receive station with capability to collect all DCP transmissions on a random and self time mode of operation. It's primary purpose is to provide a backup to the existing GOES ground receive station.

Page 19: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

5-1

5. EMERGENCY IDENTIFICATION SUBPLAN

a. General - The object of this subplan is to describe procedures and means for assuring reliable identification and evaluation of existing or potential emergencies. The failure of Teton Dam and other non-Corps dams has demonstrated the alarmingly short period of time it takes for a dam to breach, the destructive potential of the uncontrolled release of water and the importance of an effective and expeditious notification of the public in minimizing loss of life and/or property. The Corps is committed to a program of dam safety, which includes the preparation of Flood Emergency Plans for our completed dam projects.

b. Possible Cause of Emergencies and Recent Studies -Various emergency situations may occur which adversely affect the dam's primary function of impounding water. As suggested by the 1980 Hydrologic Engineering Center guidelines on Flood Emergency Plans, these emergencies may be caused by one or a combination of the following events:

• Earthquake • Landslide • Extreme Storm • Piping • Equipment Malfunction • Structural Damage • Foundation Failure • Sabotage or Enemy Attack

Recently completed studies indicate that the Otter Brook Lake project is in good

condition.

1) Structural Stability of Concrete Structures - A structural stability analysis of the principal concrete structures at Otter Brook Lake was performed for New England District by Vollmer Associates. The principal features, analyzed to determine whether they satisfy current criteria, consisted of the following: spillway weir, intake structure, intake channel walls, stilling basin walls, and service bridge piers and abutments. This analysis was completed in June, 1986. All remedial measures identified in the qualitative results of the analysis have been completed.

2) Embankment Stability Re-evaluation - The embankment stability of the dam has not been re-evaluated based upon current criteria as contained in EM 1110-2-1902, dated April 1, 1970.

3) Seismic Stability - A preliminary seismic stability analysis was completed in August, 1980 for the dam. This effort consisted of a pseudo-static earthquake stability analysis using three seismic coefficients based upon the seismic risk map in ER 1110-2-1806, 1977 edition. The seismic coefficient of 0.05 assigned for the seismic risk map zone 2 in which the dam is located resulted in a minimum factor of safety of 1.34. For the seismic coefficient of 0.10 assigned for the next higher risk zone, a computed factor of safety of 1.16 was determined.

Page 20: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

5-2

Lastly, for a predicted peak acceleration of 0.18, which was based on historical epicenter data, resulted in a factor of safety of 0.93.

Since the completion of this preliminary seismic stability, the engineering regulation (ER 1110-2-1806) on earthquake analysis has been revised. The new regulation the pseudo-static method used in the preliminary seismic stability is no longer regarded as being appropriate for analysis of embankment of foundation response to seismic loading and therefore should be discontinued. However, at this time, no further earthquake analysis is planned for the Otter Brook Lake project.

4) Periodic Inspection - The periodic inspection of Otter Brook Lake and appurtenant structures was performed on October 1997.

(a). Concrete/Structural. Based on observations made during the inspection, the concrete condition and structural features of Otter Brook Lake are considered good. The deficiencies noted are not of a critical nature and do not present a hazard to safety and operation of the project at this time.

(b). Mechanical. The inspection of the mechanical features of the dam did not reveal any serious deficiencies which might hamper the operation of the dam during flood emergencies.

(c). Electrical. Inspection of the electrical features of the project did not indicate any deficiencies which would hamper operation of the dam during flood control and flood emergencies.

(d). Hydrology/Hydraulics. Overall condition of the hydrologic/hydraulic features of the project was considered good. No major deficiencies or abnormal hydraulic phenomena were observed or reported. All hydrologic monitoring equipment was in good working condition.

(e). Geotechnical. Based on the visual inspection of Otter Brook Lake, the geotechnical features of the dam, and appurtenant structures are in good condition.

5) Seismic Evaluation of Intake Tower - New England District has performed a dynamic analysis of the intake tower at Otter Brook Lake, Keene, New Hampshire. This analysis was submitted to Headquarters, U.S. Army Corps of Engineers, on 25 September 1990. The analysis was submitted in draft form since guidance had been in a state of flux; final criteria were published in ETL 1110-2-339, "Seismic Design and Evaluation of Intake Towers," dated 31 March 1993.

Based on preliminary guidance, the analysis indicated that the 138-foot-high tower at Otter Brook Lake did not satisfy criteria. This analysis will have to be updated to incorporate the requirements contained in ETL 1110-2-339.

Page 21: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

5-3

c. Surveillance and Inspection

(1) Inspection of Floods - A condition which is of minor importance with relatively low reservoir levels may assume serious proportions with increasing pool levels, and the Project Manager must be constantly on alert to note and report even minor failures or changes in the conditions of the embankment.

The Operations and Maintenance Manual for Otter Brook Lake in chapter 2, paragraph 2, states the Inspection During Floods requirement. The manual states that when the reservoir is filling or storing water, the Project Manager will inspect the exposed faces of the dam, and dam abutments, particularly the downstream faces, for sloughs and springs. When the reservoir is being drawn down, the Project Manager will inspect the exposed faces of the dam, and dam abutments, particularly the upstream faces for slides. During any subsequent filling, storage and drawdown periods, inspection of the embankments shall be performed. Visual inspections and piezometer readings shall be performed at least once a day when the pool is above elevation 715 feet NGVD. Piezometer readings shall be taken daily until 5 days after the pool reaches its normal elevation 703 feet NGVD. Finally, the Operation and Maintenance Manual requires that each time the reservoir is filling to a higher level than previously experienced (pool of record, elevation 782.4 feet NGVD, 100+ percent full, April, 1987), inspection of the downstream face of the dam shall be conducted at least twice daily during storage and at least three times weekly during drawdown until two weeks after completion of drawdown.

A practice is established within the District whereby the experiencing of a certain pool elevation at a project will require that a reconnaissance of the project be performed by the geotechnical engineering staff of New England District. Plate 5-1 shows the pool elevations requiring a reconnaissance inspection for all 35 New England District projects. The pool elevation for Otter Brook Lake is 770 feet NGVD.

(2) Unusual Event Other than Floods - Inspections should be made after the occurrence of an unusual event, such as, but not limited to, earthquake, sabotage, equipment malfunction, and other emergency conditions. However, often times the creation of the condition may at the time be unknown, and, therefore, it is important to recognize signs of distress and the necessary action to be implemented.

(3) Guidance on Inspection Action - Plates 5-2a through 5-2g entitled "Signs of Distress" are to be used as a guide by the Project Manager for various types of observed conditions. Unless the dam is in imminent danger of failure, the Project Manager must coordinate all actions and notification with the Emergency Operations Center staff. Notification should follow procedures as outlined in the NOTIFICATION SUBPLAN (Section 7) of this report.

Plates 5-3a through 5-3d are an Inspection Checklist to be utilized by the predesignated technical Emergency Response Team which would inspect the dam for the emergency condition experienced. Due to the severity of a specific emergency condition, the

Page 22: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

5-4

Project Manager could be directed by Emergency Operations Center to complete this Inspection Checklist.

Plate 5-4 entitled "Description of Characteristic Effects for Earthquakes" is included to supplement the Inspection Checklist for descriptive categories on reporting an earthquake. Strong motion instruments which measure events greater than the triggering acceleration of 0.01g are available at Surry Mountain Lake and Hodges Village Dam (approximately 65 miles distance). See Plate 2-5 for the location of these and other strong motion instruments in New England.

Page 23: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

SIGNS OF DISTRESS

ACTION ON REPAIRS SHOULD ONLY BE INITIATED IF TIME IS OF ESSENCE DUE TO OBSERVED DISTRESS, FOLLOW NOTIFICATION SUBPLAN

Observed Conditions

How to Evaluate

Severity of Condition Guide

For Action Data to be Reported in Situation Report

Remarks

1. SEEPAGE

a. Wet area on embankment slope or any other area downstream of the embankment, with very little or no surface water, or minor seeps.

This may be caused by infiltration of rain water which is not serious, or may be the start of a serious problem, which would be indicated by a quick change to one of the conditions below.

None required. Size and location of seepage area and approximate time condition is noted and quantity of surface water.

Observe periodically until sure that seepage does not change into one of the conditions noted below.

b. Same wet area as above, with moderate seeps of clear or relatively clear.

Not serious - Clear seep water and rate of flow not increasing.

Try to measure rate of flow, inspect all downstream areas, and report any new seeps.

Size and location of seepage areas and time condition noted and approximate time flow rate. Notify Emergency Operations Center (EOC).

When project is not storing flood waters and is acting as a dry reservoir, failure of the dam is very remote. During flood stages, the seepage area must be periodically watched for critical developments.

Could lead to failure relatively clear seep water, but rate of flow increasing.

Same as above. Size and location of seepage area, time condition noted, and approximate flow rate. Notify EOC.

Same as above. During stages, observe condition periodically, until otherwise notified.

c. Piping (Seepage with removal of material from foundation or embankment),

Could lead to failure. Cloudy to muddy water and rate of flow is increasing.

Same as above. Place Inverted Filter over seepage area. If needed, use larger stones on top of filter. Use filter cloth at bottom if available. (Don't try to plug or stop the flow of water.) Also, consider lowering pool.

Size and location of seepage area, time that condition was noted and approximate rate of flow. Notify EOC.

Observe problem periodically until otherwise notified.

Failure imminent - If along with piping there is an upstream swirl (whirlpool)

Same as above. If discharge tends to displace filter material, use larger stones to control velocity; then place filter material and top with larger stones. Plugging of

Size and location of seepage area, time condition was noted and approximate flow rate; and

Observe periodically.

Page 24: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

SIGNS OF DISTRESS

ACTION ON REPAIRS SHOULD ONLY BE INITIATED IF TIME IS OF ESSENCE DUE TO OBSERVED DISTRESS, FOLLOW NOTIFICATION SUBPLAN

Observed Conditions

How to Evaluate

Severity of Condition Guide

For Action Data to be Reported in Situation Report

Remarks

caused by water entering at the abutments or through the embankment.

the upstream entrance of the pipe should be attempted (See Observed Condition 3 below.) Also, consider lowering the pool.

location and approximate site of whirlpool. Notify EOC and if failure is in progress, notify local officials and downstream residents.

d. Boils - Soil particles deposited around water forming a cone. (Boils can vary from a few inches in diameter spaced 2 to 3 feet apart to isolated boils several feet in diameter.)

Not Serious - Emerging water in developed cone is clear and rate of flow is not increasing.

Check all downstream areas, other boils or seeps, and report to EOC.

Size and location of seepage area, time condition was noted and approximate flow rate.

Observe periodically until otherwise notified.

Could lead to failure - If emerging water is muddy and rate of flow is increasing.

Consider lowering the pool. Temporarily control the seepage by ringing the area with a sandbag dike. (See Plate 6-3 for schematic of ringing a boil.) The dike should be constructed to provide sufficient flow reduction to prevent loss of material at surface. a low place must be left on the dike for a spillway on the side toward natural drainage. If boils become so large that it is not practical to dike around them, place an inverted filter over the area, but do not stop the flow of water. ERT to consider installing well points or other system to relieve below ground pressures.

Size and location of seepage area, time condition was noted and approximate flow rate. Notify EOC.

Observe constantly until otherwise notified.

Failure Imminent - If emerging water is muddy, rate of flow increasing, and if there is an upstream swirl (whirlpool) caused by water entering at the abutments or through the embankment.

Same as above. Plugging of the upstream entrance of the pipe should be attempted (See observed condition 5 below). Lower the pool.

Size & Location of seepage area, time condition was noted and approximate flow rate; and location and approximate size of whirlpool. Notify EOC and if failure is in progress notify local officials.

Observe constantly.

2. SINKHOLES

a. Above piping tunnel in foundation or embankment.

Could lead to failure - If problem occurs in conjunction with piping or boils problem.

If in conjunction with boils problem, place inverted filter material in sinkhole. (See 1.c and 1.d above.) Check area for other sinkholes or seeps, and report to

Size and location of sinkhole and seepage area and approximate flow rate. Notify

Observe periodically until otherwise notified.

Page 25: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

SIGNS OF DISTRESS

ACTION ON REPAIRS SHOULD ONLY BE INITIATED IF TIME IS OF ESSENCE DUE TO OBSERVED DISTRESS, FOLLOW NOTIFICATION SUBPLAN

Observed Conditions

How to Evaluate

Severity of Condition Guide

For Action Data to be Reported in Situation Report

Remarks

EOC. EOC. b. Above outlet works conduit.

Could lead to failure - If conduit cracks or structural damage.

Check conduit or cracks or damage and repair as soon as possible in coordination with guidance provided by Emergency Response Team (ERT).

Same as above plus description and size of cracks or damage and seepage into conduit.

Observe periodically.

3. RESERVOIR/WHIRLPOOLS

Usually caused by water flowing through a piping tunnel through the embankment or abutment.

Open outlet gates to lower the pool after contacting EOC. An attempt should be made to plug the entrance with large rocks or anything else that is available.

Time condition noted, location noted, location, and approximate size of whirlpool and the exit area downstream.

Observe constantly for changes in the reservoir and/or the exit area.

Note: During high pools when completely submerged, debris may come together above the intake, due to intake flow, and move in a rotating motion. If there is no evident downstream exit of piping, and the rotating debris is over the intake structure, then it can be assumed there is no piping failure

Use Rip-Rap from the face of the dam, or any large rock, or other large material. If the large material placed in the hole appears to have reduced the flow, follow with progressively smaller material. When flow is sufficiently reduced, place inverted filer over the downstream outlet of piping as noted in problem i.c, Piping. Search abutments dam, and downstream of dam for seepage areas, sinkholes, boils, etc.

Notify EOC and if failure is in progress, notify local officials and downstream residents.

4. SLIDES

a. Upstream or downstream slope of embankment for dams and dikes.

Not serious - If slide does not obstruct normal flow or intersect the crest and does not extend into the embankment more than five feet (measured perpendicular to the slope).

Coordinate any necessary work with Emergency Response Team (ERT).

Location, time first noticed, subsidence or bulging, whether water is emerging from slope, whether any movement can be visually detected and pool elevation.

Observe periodically.

Could lead to failure - If slide passes through the crest, and water surface is more than 10

Coordinate with EOC or ERT as to the proper remedial action. Start lowering pool by coordinating with RRT.

Report same data as above. Notify EOC.

Observe periodically until necessary repairs

Page 26: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

SIGNS OF DISTRESS

ACTION ON REPAIRS SHOULD ONLY BE INITIATED IF TIME IS OF ESSENCE DUE TO OBSERVED DISTRESS, FOLLOW NOTIFICATION SUBPLAN

Observed Conditions

How to Evaluate

Severity of Condition Guide

For Action Data to be Reported in Situation Report

Remarks

feet below the lowered crest. are completed.

Failure Imminent - If 1) the slide passes the crest; and 2) the water surface is at or near (less than 10 feet) the top of the lowered crest.

Start lowering the pool. Use every means possible to armor the crest and to restore loose freeboard.

Location, time first noticed, whether water is emerging from slope, whether any movement can be visually detected and pool elevation. Notify EOC and if failure is in progress, notify local officials and downstream residents.

Same as above.

5. CRACKS

a. Embankment

Not serious - If minor longitudinal crack in crest. If crack does not extend completely through the dam and lake water is more than ten feet below the base of the cracks.

Coordinate repair work with ERT. Location, width, length and pattern (horizontal, vertical or in some intermediate direction), pool elevation.

Observe periodically until repair work is complete. NOTE: Although cracks can develop anywhere in the embankment, the most likely location is in the area over the valley abutment contact zone.

Could cause failure - If crack extends completely through the dam and lake water is at or near (less than 10 feet) the base of the crack.

Coordinate repair work with ERT. Backfilling or other means of filling the crack will be required after the extent of the crack is determined.

Same as above. Notify EOC. Observe periodically until repair work is completed.

Failure Imminent - If crack extends completely through the dam and water is entering the crack and emerging on the downstream side.

Plug the crack on the upstream side to the extent possible using spalls and gravel before adding bentonite or impervious material. This procedure will help prevent the washing out of the finer materials through the crack. The work should be started nearest the water surface on the upstream side. If the crack cannot be

Location, width, lengths and pattern of crack; also flow rate at downstream exit. Notify EOC and if failure in progress, notify local officials and downstream residents.

Same as above.

Page 27: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

SIGNS OF DISTRESS

ACTION ON REPAIRS SHOULD ONLY BE INITIATED IF TIME IS OF ESSENCE DUE TO OBSERVED DISTRESS, FOLLOW NOTIFICATION SUBPLAN

Observed Conditions

How to Evaluate

Severity of Condition Guide

For Action Data to be Reported in Situation Report

Remarks

plugged from the upstream side, then plugging should be attempted from the downstream side with an inverted filter to prevent erosion of embankment materials. Start lowering the pool if 1) the water is less than 10 feet below the base of the crack or 2) if the water is entering the crack and emerging on the downstream side.

b. Concrete Structures

Not serious - If cracks in conduit are 1/8 inch or less and are not changing. Seepage is constant and water clear.

Coordinate any necessary repair work with ERT. Location, width, length and seepage conditions. Notify EOC.

Observe periodically.

Could lead to failure - If width of crack or hole is changing, seepage is increasing and water carrying material.

Crack should be plugged with oakum or other suitable materials until final repairs can be made.

Report same as above along with an estimate of the material being carried. Notify EOC.

Observe periodically until flow is controlled.

Failure Imminent - Width of crack is increasing. Seepage is increasing and water carrying embankment material

Plug the crack to the extent possible. Initial material should be larger than the crack width. Lower the pool as soon as possible.

Location, when noticed, estimate of water flow and material being carried. Possible sources of material and if water inlet is visible in pool area and pool elevation. Notify EOC and if failure is in progress, notify local officials and downstream residents.

Same as above.

6. RIP-RAP OR OTHER SLOPE PROTECTION FAILURE

Not serious - If erosion is minor and pool is at a low level.

Repair work to be coordinated with ERT. Elevation of damage; length of damage, in feet; pool elevation when damage occurred.

Observe daily until repair is completed.

Could lead to failure - If Repair using Rip-Rap. Rip-Rap may be dumped Same as above, except notify Same as above.

Page 28: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

SIGNS OF DISTRESS

ACTION ON REPAIRS SHOULD ONLY BE INITIATED IF TIME IS OF ESSENCE DUE TO OBSERVED DISTRESS, FOLLOW NOTIFICATION SUBPLAN

Observed Conditions

How to Evaluate

Severity of Condition Guide

For Action Data to be Reported in Situation Report

Remarks

erosion at low or high pool level is severe.

directly into the erosion scarp. The smaller stones will tend to settle to the lower portion of the stone mass, essentially creating a protective filter over the embankment soil. Coordinate repair with ERT.

EOC.

Temporary Repair Using Sandbags if Rip-Rap is

depleted, sandbags may be placed in the scarped area. Each bag should be filled with sand and tied to prevent loss of material. Placements should be by hand, sling or other methods that would prevent tearing of the bags. Bags filled with clay silts may be used only if sand is not readily available and other methods of repair cannot be implemented.

7. GATE FAILURE FOR OUTLET WORKS

If commercial power unavailable, switch over to Emergency Generator. No hand crank is available at the site to operate the gates. If unable to lower gate, install stoplogs. Three gates are installed on the project, so if only one gate is inoperable, the other gates could be used for regulation purposes.

Coordinate any necessary repair work with Emergency Response Team (ERT).

Cause of failure and condition of gate. Notify EOC.

Observe periodically until repairs are completed.

8. EARTHQUAKE

Consult Plate 5-4 for characteristic effects of various earthquakes. Utilize Checklist provided in Plates 5-3a through 5-3d.

Check other problem areas cited. Notify EOC with checklist results. If failure is in progress, notify local officials.

Observe continuously.

Page 29: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

OTTER BROOK LAKE INSPECTION CHECKLIST Inspectors Date Time Pool Stage Tailwater Elevation

Item

Yes

No

Description

Insp. Init.

1. Dam

A. Crest

(1)

Misalignment

(2)

Settlement

(3)

Heaving

(4)

Cracks

B. Upstream Face

(1) Misalignment

(2)

Cracks

(3)

Reservoir Surface Disturbance (eddy, vortex, etc.)

C. Downstream Face

(1)

Misalignment

(2)

Cracks

(3)

Seepage*

(a)

Location

(b)

Quantity

(c)

Clear or Turbid

Page 30: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

Plate 5-3a

Page 31: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

OTTER BROOK LAKE INSPECTION CHECKLIST

Item

Yes

No

Description

Insp. Init.

2.

Control Tower, Conduit and Outlet Structure

A.

Control Tower

(1)

Misalignment

(2)

Settlement

(3)

Heaving

(4)

Joints

(a)

Offsets

(b)

Cracks

(5)

Cracks

(6)

Exposed Reinforcement

B.

Conduit, Outlet Structure

(1)

Misalignment

(2)

Joints

(a)

Offsets

(b)

Cracks

(3)

Cracks

(4)

Exposed Reinforcement

Page 32: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

Plate 5-3b

Page 33: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

OTTER BROOK LAKE INSPECTION CHECKLIST

Item

Yes

No

Description

Insp. Init.

3.

Spillway

A.

Misalignment

B.

Cracks

C.

Exposed Reinforcement

4.

Service Bridge to Control Tower

A.

Misalignment

B.

Settlement

C.

Heaving

D.

Cracks

E.

Joints

(1)

Offsets

(2)

Cracks

F.

Exposed Reinforcement

5.

Instrumentation Monitoring

Monitor and Record

(1)

Dam Piezometers

(2)

Downstream Tail - Water Gage

(3)

Reservoir Level Recorder

(4)

Crest Monumentation

Plate 5-3c

Page 34: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

OTTER BROOK LAKE INSPECTION CHECKLIST

Item

Yes

No

Description

Insp. Init.

6.

Downstream Left and Right Valley Slopes & Outlet Channel

A.

Slides

B.

Cracks

C.

Signs of Movement

7.

Dam Access Roads and Parking Areas

A.

Signs of Movement

B.

Cracks

8.

Reservoir Surveillance, (signs of new sliding, fresh fallen trees, cracking, etc.) and Inlet Channel

9.

Electrical-Mechanical

A.

Service Gates (3) Operable

B.

Emergency Stoplogs Operable

C.

Emergency Power Operable

*Since it may take time for a seepage condition(s) to occur, visually inspect for seepage immediately after an earthquake. If no seepage or if no new or increased seepage (relative to condition(s) prior to earthquake) are detected, reinspect for seepage within 2-4 hours, 6-8 hours, 18-24 hours, and 48 hours after the earthquake unless otherwise instructed by District. If a new or increased seepage condition(s) is detected during an inspection after the earthquake, monitor and record seepage hourly until instructed otherwise by District. Plate 5-3d

Page 35: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

DESCRIPTION OF CHARACTERISTIC EFFECTS FOR EARTHQUAKES Instrumental Detected only by seismography. Feeble Noticed only by sensitive people. Slight Like the vibrations due to a passing truck, felt by people at rest, especially

on upper floors. Moderate Felt by people while walking; rocking of loose objects, including standing

vehicles. Rather Strong Felt generally, most sleepers are wakened and bells ring. Strong Trees sway and all suspended objects swing; damage by overturning and falling

of loose objects. Very Strong General alarm; walls crack; plaster falls. Destructive Car drivers seriously disturbed; masonry fissured; chimneys fall; poorly

constructed buildings damaged. Ruinous Some houses collapse where ground begins to crack, and pipes break

open. Disastrous Ground cracks badly; many buildings destroyed and railway lines bent;

landslides on steep slopes. Very Disastrous Few buildings remain standing; bridges destroyed; all services (railway,

pipes and cables) out of action; great landslides and floods. Catastrophic Total destruction; objects thrown into air; ground rises and falls in waves.

Plate 5-4

Page 36: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

6-1

6. EMERGENCY OPERATIONS AND REPAIR SUBPLAN

a. General - This subplan provides guidance for emergency operations and repairs to deal with impending and existing emergencies affecting the operation and safety of the Otter Brook Lake project.

b. Responsibilities - The Project Manager is designated as the responsible Corps of Engineers staff member to report the nature and magnitude of a specific problem. Minor remedial repairs will be handled through normal operating procedures. However, should an emergency situation occur at the site, the Project Manager should furnish information for the Situation Report as described in the NOTIFICATION SUBPLAN of this report. Where sufficient notification time exists, technical guidance will be furnished to the Project Manager by the predesignated Emergency Response Team for emergency repairs. The team leader and/or members will normally provide on-site guidance during the initial stages of repair work. An emergency condition such as the resulting effects from an earthquake might preclude this on-site presence by the Emergency Response Team due to other hazardous conditions that prevent travelling to the site. The Emergency Response Team leader and/or members will be on site during the final inspection to insure that all work has been satisfactorily completed and remain in contact with the Project Manager through the follow-up monitoring stage.

When an emergency situation exists or is impending where sufficient notification time does not exist, Emergency Operations Center may direct a temporary emergency measure to be implemented by the Project Manager. As noted in the following Notification Subplan, when failure is in progress or is imminent, action will be taken by the Project Manager utilizing government resources at his disposal to try to save human life, prevent immediate human suffering, or mitigate major property damage or destruction.

Reservoir regulation changes due to emergency conditions will be directed to the Project Manager by the Reservoir Regulation Team.

c. Safety of Personnel and Equipment - Utmost care should be given to the safety of the personnel engaged in all remedial activities. When it is evident that failure is at hand and that the failure cannot be effectively delayed, all personnel will be ordered from the unsafe area at the discretion of the Emergency Response Team leader or the Project Manager if the Emergency Response Team has not arrived. Equipment should be moved to a safe area, but only to the degree practical as safety to personnel and time allows.

d. Inventory of Equipment, Materials and Suppliers - In order that various emergency situations can be addressed, it is necessary to preplan resources, such as equipment and material that may be required. Plates 6-1a through 6-1c are a list indicating where the following resources are available:

- Equipment and Materials Available at the Site - Sources of Sand, Gravel, Stone and Concrete - Contractors and Equipment - Grouting Suppliers

Page 37: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

6-2

- Drilling Equipment Contractors and Suppliers - Military Construction Support - Aircraft Support

e. Emergency Contract Authority In an emergency situation, the District

Commander can activate emergency contracting authority for the following persons in the listed amounts (excluding architect-engineer work):

NAME CAPACITY AMOUNT

F. J. Fedele Resident Engineer $100,000 Construction Dir. Office: (508) 759-8360 FAX: (508) 759-9774 Home: (508) 888-6595

John Winmill Area Engineer $100,000

Construction Dir. Office: (978) 318-8691 Home: (508) 393-3455

If additional equipment, contractual support, or supplies are needed, contract procedures

and staff support shall be administered by the District Contracting Division.

f. Dewatering - Releases by the Project Manager must be coordinated with the Reservoir Regulation Team. For Otter Brook Lake, the maximum nondamaging channel capacity immediately downstream is about 600 cfs. The rate of reservoir drawdown for an emergency condition depends on the urgency of the situation. When major structural damage has occurred to the embankment, such as piping or sloughing, the most effective action almost always involves lowering the pool. However, too rapid lowering of the reservoir may have adverse effects on the stability of the dam embankment. Specified rates of drawdown must be observed unless embankment failure is occurring or imminent. A controlled release will relieve the pressure on the structure and minimize the downstream risk of possible loss of life.

The procedure for dewatering will consider the rate required and duration of the release. Dependent upon the rate of release required, warnings for downstream areas along the Naugatuck River should be issued in accordance with the NOTIFICATION SUBPLAN. It is recognized that for all but the most serious conditions to judge "imminent" failure is determined by the best available data within a limited timeframe. To assist in the decision for emergency breakdown, the following plates are provided:

Plate 6-2a - Emergency Drawdown Curves Plate 6-2b - Area & Capacity Curves Plate 6-2c - Area Capacity Table

Plate 6-2d - Percent Full Curve Plate 6-2e - Spillway Rating Curve

Page 38: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

6-3

Plate 6-2f - Outlet Rating Curves For One Gate Plate 6-2g - Outlet Rating Curves For All Gates Fully Open Plate 6-2h - Inflow Curve

Consideration to opening all gates and exceeding downstream channel capacity will be

made by Reservoir Regulation Team in the event of an existing or imminent failure of the embankment.

g. Guide for Repair/Response to Distress - The Otter Brook Lake project was designed and constructed to withstand possible conditions that it may be subject to in the future. It is unlikely that an emergency condition would develop resulting in distress which would seriously threaten the project and ultimately endanger life and/or property downstream. For the distress experienced at the project, excluding significant downstream releases, the Project Manager is to provide a SITUATION REPORT as described in the NOTIFICATION SUBPLAN. The degree of the distress and estimate of response time before catastrophe could occur dictates the type and quality of repair and/or temporary solution to be implemented. Preferably, the technical assistance of the Emergency Response Team members or direction from District staff should be utilized to address the specific distress. With the specific distress resulting from one of the possible events cited in the Emergency Identification Subplan, many variables would be involved which would affect the nature of the repair or solution. The following paragraphs suggest emergency actions and/or treatments to be considered and supplement information in the matrix entitled "Signs of Distress" (Plates 5-2a through 5-2g) in the Emergency Identification Subplan. These are meant as a guide only.

(1) Ringing a Boil or Use of Granular Blanket - Seepage on the face of the embankment, large amounts of seepage, and seepage carrying fines are especially serious signs of distress. Excess seepage problems are most likely to occur when the lake water level is at higher than normal elevations. Thus, a driving force for this unusual seepage is the head of water imposed by the reservoir. To alleviate the above, consideration should be given to implement the guide to dewatering as discussed in Section 6f to decrease the head.

Individual boils or small areas of seepage can be controlled on a temporary basis by ringing them with sandbags or other materials. See Plate 6-3 for a schematic of ringing a boil, Technical directions for ringing boils are as follows:

Page 39: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

6-4

-The entire base of the sack ring is cleared of debris in order to provide a watertight bond between the natural ground and the sack ring. Multiple nearby boils or soft areas in vicinity of the boil should be included within the sandbag ring.

-The base of the sandbag ring should be at least one and one-half times the contemplated height. The sacks are laid in a ring around the boil with joints staggered.

-The ring should be built only high enough to slow water flow to a point that no fines are carried. Do not shut flow of seepage completely off. The ring shall be of sufficient size to permit sacking operations to keep ahead of the flow of water.

-As shown on Plate 6-3, a low point of emergency spillway is provided on the top of the ring to carry off the water.

Longer term control and control of large areas of seepage can be effected by covering the

area with a deep granular blanket graded from coarse sands at the bottom to coarse gravels at the top.

(2) Overtopping - Although the spillway was designed to accommodate a Probable Maximum Flood, it is remotely possible for the discharge capacity to be exceeded under certain circumstances.

Despite the conservative efforts by designers to eliminate the danger of overtopping, certain unpredictable events, such as a landslide or earthquake could cause enough disturbance in the reservoir for overtopping of the dam to occur. Since landslides have not been experienced in the project's life (placed in operation in 1958), occurrence of this event is remote. If the earthquake's magnitude was high enough, a "large wave" could be created in the reservoir which could send water over the top of the dam. Also, a large landslide could displace enough water to raise the level of the reservoir in a short timeframe by a wave.

However, the dam was constructed with a rock-fill downstream face, which would make it somewhat resistant to erosion due to overtopping. Certainly, a corrective action, if the gates are operable, is to increase releases and thus consult the dewatering plan. If erosion to the slope has occurred due to overtopping, consideration should be given to filling the areas with rip-rap, sandbags, or a granular blanket. The preferred method depends on materials and labor available and the urgency of the action. When the situation permits, the Emergency Response Team will provide direction on the type of repair.

3) Operator Absence or Disablement - As discussed in Section 3, should the Project Manager (Operator) be unavailable, then the Park Ranger or Basin Manager and his staff could substitute to operate the project. The Upper Connecticut River Basin Manager will designate the individual who will assume control of the project.

Page 40: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

6-5

4) Equipment Malfunction - Should commercial electric power become unavailable, the Project Manager would utilize the diesel engine-generator set in the gate house. If the emergency engine is inoperable, the gate house for Otter Brook Lake contains emergency stoplogs to manually stop flow. If unable to raise to lower the gate (e.g. earthquake has caused damage to stem or seating), preferably Emergency Response Team guidance is desired depending on the urgency of the situation.

(5) Sabotage - Threats are to be taken seriously. Should a threat occur, the staff member receiving the call should attempt to obtain information similar to acquired for a BOMB THREAT (Plate 6-4). The information should be reported to Emergency Operations Center and the Chief of Security and Law Enforcement (SLEO).

An actual act of sabotage may range from minor disruptions to quasi-military attacks by knowledgeable and well-equipped professionals. The effect of sabotage fall into one of three categories: a) not affecting safety of the dam; b) posing a minor or future safety problem; and c) posing an immediate, serious safety problem. All threats or acts of sabotage will be reported immediately to Emergency Operations Center and the Chief of Security and Law Enforcement.

Depending on the severity of the sabotage act and the resulting urgency of action, remedial repair work could be directed by the Emergency Response Team or alternatively dependent on information provided in the SITUATION REPORT, the Project Manager may be directed to initiate some temporary remedial action.

Page 41: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

6-6

INVENTORY OF EQUIPMENT, MATERIALS, AND SUPPLIERS 1. Equipment and Materials Available at Otter Brook Lake

1-1/2 Ton Dump Truck 2 Ton Dump Truck Ford 445 Diesel Tractor with Front End Loader 2 Pick Up Trucks

2. Sources of Sand, Gravel, Stone and Concrete

On-Project Sources -

-There are no on site sources of material.

-Gravel is located at the Surrey Mountain Project which is approximately 10 miles distant.

Off-Project Sources -

Gravel & Fill

Keene Sand & Gravel (603) 352-0101 Swanzey, NH (only processed supplier)

Frank Whitcomb (603) 445-5555 North Walpole, NH

Cersosimo Lumber Co. Inc. (802) 254-4508 Brattleboro, VT

Brattleboro Sand & Gravel (802) 254-5213 Brattleboro, VT

Bretwood (603) 352-7626 Keene, NH

Qualters (603) 239-4793 Winchester, NH

Plate 6-1a INVENTORY OF EQUIPMENT, MATERIALS, AND SUPPLIERS (Cont'd)

Page 42: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

6-7

Concrete:

Arthur Whitcomb Inc. (603) 352-0101 Keene, NH

F & S Transit Mix Co. Inc. (603) 627-7665 Manchester, NH

Cullen Concrete Pumping Service (603) 286-8057 Tilton, NH

Monadnock Concrete Pumping (603) 878-3315 New Ipswich, NH

3. Contractors and Equipment

The following companies can supply heavy equipment, including but not limited to: loaders, backhoes, dump trucks, trailers, shovels, cranes, gradalls and rock drills.

Arthur Whitcomb Inc. (603) 352-0101 Keene, NH

Brook’s Construction Company (603) 357-2270 112 Pond Road Surry NH 03431

A.E. Hill (603) 352-9595 Keene, NH

E.W. Blood (603) 352-2561 Swanzey Ctr., NH

Harvey Construction Co. (603) 668-3100 Bedford, NH

4. Grouting Suppliers

ED Swett (603) 224-7401 Concord, NH

Monadnock Concrete Pumping (603) 878-3315 New Ipswich, NH

Plate 6-1b

Page 43: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

6-8

INVENTORY OF EQUIPMENT, MATERIALS, AND SUPPLIERS (Cont'd)

Morse Block, Inc. (802) 442-2260 Bennington, VT

Northeast Gunite & Grouting (617) 387-4840 Everett, MA

5. Drilling Equipment Contractors and Suppliers

Con-Tec Inc. (603) 224-0020 Hooksett, NH

Soils Engineering Inc. (603) 826-5873 Charlestown, NH

Carl Thomas Construction (603) 363-4410 Spofford, NH

6. Military Construction Support

All required military support will be coordinated by EOC. 7. Aircraft Support

Military Contact Flight Operations Officer at Moore Army Airfield, Devens, MA (508) 796-3261/3130

Utility helicopters (8-9) persons or observation helicopters (2 persons) are located at airfield.

Private Jaffrey Airport (603) 532-7763/8870 Jaffrey, NH

Northern Airways (802) 658-2200 South Burlington, VT

Silver Ranch Airpark (603) 532-7763 Jaffrey, NH

LADCO Air Center (603) 298-8728 W. Lebanon, NH

Southern Vermont Helicopter (802) 257-4354 W. Brattleboro, VT

Plate 6-1c 7. NOTIFICATION SUBPLAN

Page 44: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

7-9

a. General - The objective of this subplan is to describe the procedures and means

for prompt notification of parties concerning an existing or potential emergency at the project. Prompt notification is essential for minimizing hazards to life and property.

Notification will consist of but not be limited to the following: - Internal Corps of Engineers notification. - State and local officials and other Federal agencies. - Downstream officials. - Media.

To assure timely notification, it is mandatory to minimize its complexity in order to

assure prompt action. Thus, three notification subplans (Plates 7-1, 7-2, 7-3) are selected to cover a wide range of eventualities which could cause the possible emergency. These three emergency situations are: 1) rapidly developing condition; 2) significant reservoir releases and/or impoundment above spillway crest; and 3) dam failure in progress.

b. Rapidly Developing Condition - This situation is one in which the dam has not failed , but the project has experienced an emergency condition such as, but not limited to, the following: sabotage, earthquake, landslide, foundation or abutment failure, slope failure or equipment failure.

The method of notification, as depicted in Plate 7-1, is dependent upon whether the situation report by the on-site Project Manager allows sufficient notification time before there is a hazard to life or significant property damage downstream. The Emergency Operations Center reviews the data in the Situation Report and decides whether to notify: 1) internal Corps elements, or 2) State Civil Preparedness and local officials. The Project Manager is defined as the on-site Corps staff member responsible for operation and maintenance of the project. When local officials (e.g. police) need to be notified or coordinated with on a flood emergency, project personnel should continue to notify the EOC first, in all situations except those where dam failure has occurred for is imminent. However, in all instanced, project personnel – not the EOC – will be the ones to coordinate with locals. In the very rare instance where emergency contact with local officials must be initiated before contacting the EOC, the EOC should be told of the contact ASAP, so that they can alert the State Civil Preparedness personnel as well as the appropriate internal people.In order for Emergency Operations Center to assess the intensity and magnitude of the emergency, the PROJECT MANAGER will expeditiously furnish information in the SITUATION REPORT to Emergency Operations Center. If Emergency Operations Center cannot be readily contacted, the PROJECT MANAGER will contact the CHIEF CONSTRUCTION/OPERATIONS DIVISION. Plate 7-4 suggests information to be furnished in the Situation Report. Use of photographs and/or video is encouraged. A more detailed assessment of the emergency condition will normally be made by the Emergency Response Team completing the Inspection Checklist (Plates 5-3a through 5-3d).

The time available for action is one of the most critical elements to be considered and will generally govern the procedural notification scheme selected by Emergency Operations Center in accordance with Plate 7-1.

Page 45: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

7-10

(1) Rapidly Developing Conditions (Sufficient Notification Time - A rapidly

developing condition with sufficient notification time is one in which the occurrence of a significant hazard to life and/or property is possible unless timely repairs and/or modifications to operational procedures can be conducted to prevent dam failure. Based on the situation report furnished by the Project Manager, sufficient notification time exists such that Emergency Operations Center can contact the Emergency Response Team Leader. The Emergency Response Team is a predesignated interdisciplinary team responsible for assessing the emergency situation and recommending the next course of action. The Emergency Response Team Leader will mobilize those team members needed and expeditiously proceed either to the project site or the District Office. The selected initial point of destination will be decided by the Team Leader by considering the safety of the team in traveling and the specific emergency condition being experienced at the project site. The designated team member and alternates with their respective office and home phone numbers are found on Plates 7-5a and 7-5b.

The procedural notification chain illustrated on Plate 7-1 indicates the Emergency Operations Center will also contact: a) District Engineer; b) Chief of Engineering/Planning; c) Chief Construction/Operations Division and d) the Public Affairs Officer. Since timely notification is of the essence, Emergency Operations Center will proceed to contact the next party to be notified in the chain, should a designated contact point not be readily reached. The District Notification List, consisting of the Emergency Response Team and the District Personnel, is found on Plates 7-5a, 7-5b, 7-6a and 7-6b. The Office of the Chief of Engineers Notification List is found on Plate 7-8. The selected notification chain is designed for the adverse circumstances which could prevail in the middle of the night or on a weekend.

The Chief of Engineering/Planning is the designated DAM SAFETY OFFICER.

(2) Rapidly Developing Condition (Insufficient Notification Time) - Based upon the Project Manager's situation report, the time available to correct the emergency is very limited under this condition. Thus, the potential threat to downstream residents and/or property damage is heightened. Emergency Operations Center decides that with this limited notification time, the situation warrants that the State Civil Preparedness be contacted directly. Following notification of the State Civil Preparedness as indicated on Plate 7-1, internal Corps notification is initiated. Telephone numbers for non-Corps points of contact are listed on Plate 7-7.

c. Large Reservoir Release and/or Reservoir Impoundment - The Reservoir Regulation Team is designated as the element responsible for the initiation and coordination of this subplan. This plan applies to either impoundments above spillway crest elevation 781 feet NGVD which would result in uncontrolled releases or controlled releases by gates that exceed downstream channel capacity. Reservoir regulation procedures are described in Appendix E of Master Water Control Manual, Connecticut River Basin. For either situation depicted in Plate 7-2, considerable judgment and experience would be used to vary the regulation in accordance with the amount of residual reservoir storage at Otter Brook Lake, River Stages and anticipated runoff in the watershed and weather forecasts.

During a major flood, the gates will not ordinarily be opened to avoid spillway discharge.

Page 46: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

7-11

Surcharge storage above the spillway crest will be utilized if the down stream channel capacity continues to be exceeded by runoff from uncontrolled areas. If the stored floodwaters in Otter Brook continued to rise above the spillway crest with the possibility of the pool exceeding the maximum design surcharge, the gates will be gradually opened. The gates will be fully open when the pool has reached about two-thirds design surcharge. See table below.

Elevation

(ft. NGVD)

Pool Stage

(ft.) Gate 1

(ft.) Gate 2

(ft.) Gate 3

(ft.)

781 792 793 794 795

98 109 110 111 112

0 0 2 3

4.5

0 0 2 3

4.5

0 0 2 3

4.5 (4.5 is Fully Open)

For reservoir impoundments, expected to exceed spillway crest elevation 781 feet NGVD, Reservoir Regulation Team will contact Emergency Operations Center (Plate 7-2), and subsequent State and local officials will be notified by Emergency Operations Center. Alternatively, if sufficient time does not exist, the Project Manager at the direction of the Reservoir Regulation Team may contact directly the appropriate officials (i.e., Police Chiefs of Keene, New Hampshire, State Police at the Keene Barracks, Concord Barracks if after working hours). See Plate 7-7.

Similarly, for conduit releases that exceed downstream channel capacity, Reservoir Regulation Team will contact Emergency Operations Center. In turn, EOC will contact the State Civil Preparedness and the appropriate internal personal. If sufficient notification time is not available, the Project Manger at the direction of Reservoir Regulation Team will contact directly the Police Chiefs in the downstream community of Keene, New Hampshire and the State Police at the Keene Barracks (Concord Barracks if after working hours).

d. Dam Failure in Progress - When dam failure is in progress or imminently about to occur, action will be taken by the Project Manager utilizing governmental resources at his disposal to save human life, prevent immediate human suffering or mitigate major property damage or destruction.

When failure has occurred or is imminent, the Project Manager's first action should be to notify the local official (Plate 7-3) then the EOC. As depicted in Plates 7-11 and 7-12a through 7-12c, the blue shaded areas indicate areas which could be inundated, assuming a hypothetical dam break at Otter Brook Lake with pool full to spillway crest. Since a dam break and the ensuing events are a highly unpredictable happening to precisely quantify, the plates are presented to provide information for emergency planning of potential areas to be evacuated. The map reflects conditions of an extreme nature with a very small probability of occurring and does not reflect in any way upon the integrity of the dam.

For details on the development of the dam-break analysis, which quantified the flood

Page 47: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

7-12

potential based on certain assumptions, see "Otter Brook Lake - Dam Break Flood Analysis" dated August, 1985. Full size mylar drawings (30″x42″) of the inundation mapping are located at the New England District, Corps of Engineers (Engineering/Planning Division – Reservoir Regulation Team)

e. Notification of the Corps, Office of the Chief of Engineers (OCE) - In accordance with ER 1110-2-101, "Reporting of Evidence of Distress of Civil Works Projects" dated January 31, 1984, the Director of Engineering will immediately report conditions to Office of the Chief of Engineers, whereby an engineering evaluation of the evidence of distress indicates the need for immediate remedial action or the potential of failure. The Chief of Engineering/Planning will report such conditions through command channels to the HQUSACE Dam Safety Officer. If the Dam Safety Officer cannot be contacted, the District will follow the notification sequence as outlined on Plate 7-8.

f. Inquiries and Press Releases - District personnel should refer all inquiries from the news media and general public regarding an "emergency condition" to the District Public Affairs Office, (978) 318-8657. The District Public Affairs Office will be responsible for responding to these inquiries. Examples of press releases for both emergency conditions are presented in Plates 7-9a and 7-9b for information only. A notification list of radio and television stations serving the communities in the vicinity of Otter Brook Lake is also included in Plate 7-10 for notification by Public Affairs Office.

Page 48: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

GUIDELINE FOR SITUATION REPORT 1. Project Location: 2. Name and Position: 3. Telephone Where You Can Be Reached: 4. Alternate Source of Communication: 5. Nature and Severity of Problem - Use Photographs and/or Video

a. Physical Dimensions (e.g., current dimensions, rate of flow, etc.)

b. Time and Progression of Problem

c. Probable Cause

d. Current and Predicted Reservoir Condition 6. Remedial Action: (if applicable)

a. Type of Corrective Action Initiated

b. Possible and Proposed Action (noting available sources, equipment, etc.) 7. Staff at Dam Site: 8. Are Authorities or Private citizens Aware of Problem? Plate 7-4

Page 49: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

DISTRICT NOTIFICATION LIST/EMERGENCY RESPONSE TEAM OTTER BROOK LAKE Based upon the information provided in the Situation Report, Emergency Operations Center will decide whether to activate the Emergency Response Team to proceed to the project. Emergency Operations Center will contact the designated Team leader or alternate listed below in order to activate the team. The Team leader will be responsible for notifying the other team members or alternates inasmuch as the urgency of the "emergency condition" permits. Geotechnical Representative, Team Leader - Office: 978-318-8179 Mark Vance Home: 508-222-5687 Alternate Geotechnical Representative Office: 978-318-8177 Team Leader –Terry Wong Home: 617-782-5985 Hydrology/Hydraulics Representative - Office: 978-318-8450 Mark Geib Home: 781-647-9941 Alternate Hydrology/Hydraulics Office: 978-318-8524 Representative –Patrick Blumeris Home: 978-441-2751 Structural Representative - Office: 978-318-8802 John Kedzierski Home: 978-363-5826 Alternate Structural Representative - Office: 978-318-8204 Joe Colucci Home: 781-935-8376 Construction Representative - Office: 978-318-8027 Neil Beliveau Home: 508-877-1612 Alternate Construction Representative - Office: 413-593-6791 Ray Goff Home: 413-323-8593 Mechanical Representative Office: 978-318-8466 Deb Gabrielson Home: 508-358-5338 Alternate Mechanical Office: 978-318-8739 Representative – Ken Paton Home: 978-582-9358 Electrical Representative - Office: 978-318-8489 Frank Turner Home: 781-275-2317 Alternate Electrical Representative - Office: 978-318-8680 Tom Ayau Home: 508-765-0401

Plate 7-5a

Page 50: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

DISTRICT NOTIFICATION LIST/EMERGENCY RESPONSE TEAM (Cont.)

Photographic Specialist - Office: 978-318-8358 Mark McInerny Home: 617-596-0318 Alternate Photographic Specialist Office:

Home: EOC Representative - Office: 978-318-8273 Dave Schafer Home: 508-620-0692 Alternate EOC Representative - Office: 978-318-8271 Rachel Fisher Home: 978-446-0220 Chief, Security & Law Enforcement - Office: 978-318-8794 Bill Mahan Home: 617-325-1274 CONTACT EOC FOR A SUBSTITUTION OR ERT MEMBER, DISTRICT PERSONNEL, AND/OR PHONE NO. Plate 7-5b

Page 51: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

DISTRICT NOTIFICATION LIST/FIELD PERSONNEL OTTER BROOK LAKE

Commander Office: (978) 318-8220 COL. Brian Osterndforf Home: (781) 274-9840 Deputy Commander Office: (978) 318-8222 Lt. Col. John Rovero Home: (978) 433-2659 Acting Chief of Eng/Plng. Office: (978) 318-8500 Mr. H. Farrell McMillan Home: (401) 762-4724 Chief of Con/Ops Office: (978) 318-8321 Mr. Richard Carlson Home: (508) 238-4191 Chief, Public Affairs Office Office: (978) 318-8657 Mr. Larry Rosenberg Home: (978) 250-3965 Chief, Water Management Section Office: (978) 318-8686 Mr. Charles Wener Home: (781) 643-9501 Chief, Reservoir Regulation Team Office: (978) 318-8630 Mr. Paul Marinelli Home: (508) 460-9567 Chief, Emergency Operations Center Office: (978) 318-8274 Mr. Dave Schafer Home: (508) 620-0692 Emergency Manager Office: (978) 318-8273 Mr. Dave Schafer Home: (508) 620-0692 Security Guard for Concord Park Office: (978) 318-8078 Chief of Contracting Office: (978) 318-8415 Mr. Charles W. Coe Home: (781) 933-5788 Basin Manager Office: (802) 886-8111 Michael Curran Home: (802) 885-4939 Basin Park Ranger Office: (802) 886-8111 Gary Pelton Home: (802) 885-3548 Project Manager Office: (603) 352-4130/2447 James Lewis Home: (802) 875-4654 Park Rangers Office: (603) 352-4130/2447 Dan Davis Home: (603) 363-8147 John Asseng Home: (603) 446-9474 Christie Baker Home: (413) 498-5180

Plate 7-6b

Page 52: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

OTTER BROOK LAKE NOTIFICATION LIST FOR LOCAL AND STATE OFFICIALS AND OTHER FEDERAL AGENCIES Local Officials Keene, NH

Police Department 603-352-2222 Department of Public Works 603-352-6650

Swanzey, NH (Includes West Swanzey) Police Department 603-352-2869 Department of Public Works 603-352-7116 Board of Selectmen 603-352-5143

Winchester, NH (Includes Ashuelot)

Police Department 603-239-4814 Board of Selectmen 603-239-4951 Highway Department 603-239-4811

Hinsdale, NH

Police Department 603-336-7766 Board of Selectmen 603-336-5710

Surry, NH

Police Department 603-357-2209 Board of Selectmen 603-352-3075

Primary Point of Contact

Southwestern Fire Mutual Aid 603-352-1100 Dispatch, Keene 603-352-1291

County

Cheshire County Sheriffs 603-352-4238 State

State Police - Keene Barracks 603-352-3343 Civil Preparedness - Concord Office 603-271-2231 Dam Safety Official - Concord Office 603-271-3406

Federal

Northeast River Forecast Center Taunton, MA 508-824-4847

FEMA Region I, Boston (Duty Hours) 617-223-9540 Maynard (Non-duty Hours) 978-461-5501

Plate 7-7

Page 53: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel
Page 54: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

HQUSACE CIVIL WORKS PROJECT DISTRESS NOTIFICATION LIST-3/01

1`. Dwight A Beranek HQUSACE Dam Safety Officer Office: (703) 428-7302 Home: (703) 278-8110 2. Charles Pearre HQUSACE Dam Safety Prog Mgr Office: (703) 428-7343 Home: (703) 590-7571 3. Barry Holliday Project O&M Expert Office: (202) 761-4741 4. Jim Chang Geotechnical Expert Office: (703) 428-7151 5. Ming Tseng Hydraulics/Hydrology Expert Office: (703) 428-7218 6. Dan Casapulla Mech/Elec Equip Expert Office: (703) 428-7258 Office (703) 428-7344 7. Robert Chesi Dam Construction Expert Office: (703) 428- 7283 8. Joseph Hartman Structural Expert Home (703) 709-8079 9. Hari Singh General Eng Policy Expert Office (703) 428-6843 10. Jerry Foster Risk Assess/Research Expert Office (703) 428-7339 Home (703) 410-551-4211 11. Harry Kitch Planning and Policy Expert Office (202) 761-4574 12. Bill Augustine Programs/Project Mmgt Expert Office (202) 761-4117 Plate 7-8a

Page 55: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

13. Robert Bank National Inventory of Dams Office (202) 761-4243 Home (301) 854-0164 Note: For notification, the Corps, New England District, Dam Safety Officer or his designee will contact the HQUSACE Dam Safety officer who will notify the Chiefs of Engineering and Construction, the Director of Civil Works and the Chief of Engineers. In the event that the reporting field office is unable to contact the HQUSACE Dam Safety Officer, the field officer will continue down the list until a contact is made with HQUSACE. The HQUSACE contact will then be responsible for notifying the Director and the Chief of Engineers.

Plate 7-8b

Page 56: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

NEWS RELEASE FOR RAPIDLY DEVELOPING CONDITION OTTER BROOK LAKE has been detected at Otter Brook Lake by (Problem) the U.S. Army Corp of Engineers, New England District. A team of engineers from the Corps' New England District will be investigating the and evaluating corrective measures to be taken. (Problem) The team will continue to monitor the situation and will be keeping officials in downstream communities apprised of developments. Evacuation plans would be implemented only if there was a likelihood for serious downstream damage from a failure of the dam at Otter Brook Lake. Based on available data concerning the , the (Problem) situation is . Further information will be made available as developments occur. Plate 7-9a

Page 57: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

NEWS RELEASE FOR SIGNIFICANT RESERVOIR RELEASE AND/OR IMPOUNDMENT ABOVE SPILLWAY CREST Flooding along the Ashuelot River, is occurring as a result of uncontrolled releases from the dam at Otter Brook Lake according to the U.S. Army Corps of Engineers, New England District. These releases are caused by . Due to , flooding is being (nature of problem causing impoundment) experienced in the community of Keene according to the U.S. Army Corps of Engineers, New England District. The Army Engineers will continue to monitor the situation and will provide further information. Plate 7-9b

Page 58: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

MEDIA NOTIFICATION LIST OTTER BROOK LAKE Media Name Telephone # Fax # Keene Sentinel 603-352-1234 603-352-0437 The Union Leader Corp. 603-668-4321 603-668-0382 WKBK (AM) 603-352-6113 603-357-4582 WKNE (AM & FM) 603-352-9230 603-357-3926 WKNH-FM 603-358-2417 603-358-2417 WFEA-AM 603-669-5777 603-669-4641 WGIR (AM & FM) 603-625-6915 603-625-9255 WNDS-TV 603-434-8850 603-434-8627 WMUR-TV 603-669-9999 603-641-9044 Associated Press 603-224-3327 603-226-0883 WYRY-FM 603-357-5000 603-239-6203 WEKW-TV, WENH-TV, WLED-T 603-868-1100 603-868-7552 WKVT (AM & FM) 802-254-2343 802-254-6683 WTSA (AM & FM) 802-254-4577 802-257-4644 WXOD-FM 603-252-6113 603-357-4852 Concord Monitor 603-224-5301 603-224-8120

Plate 7-10

Page 59: SYLLABUS release of water resulting in downstream damage ... · release of water resulting in downstream damage. The plan directs responsibilities of Corps of Engineers personnel

8-1

8. EVACUATION SUBPLAN

Evacuation plans are to be prepared by state and/or local Civil Preparedness officials. Upon completion, these plans will be included in this subplan. The plans should include the following elements or any other appropriate element, as required:

a. Delineation of areas to be evacuated. b. Warning dissemination. c. Routes to be used. d. Traffic control measures. e. Shelters to be activated for the care of the evacuees. f. Methods for the movement of people without their own transportation. g. Identification of particular areas or facilities within the flood zones which will not require evacuation because of their location on high ground or similar circumstances. h. Identification and development of special procedures for the evacuation and care of people from institutions, such as hospitals, nursing homes and prisons. i. Procedures for the perimeter and interior security of the area, including such things as passes, identification requirements and anti-looting patrols. j. Procedures for the lifting of the evacuation and re-entry of the area. k. Details indicating which organizations are responsible for specific functions and for furnishing the material, equipment and personnel resources required.

The local jurisdiction should consider requesting the assistance of local Civil Preparedness

Personnel, if available, who may have experience in emergency work. State and local law enforcement agencies usually will be responsible for the execution of much of the plan and should be represented in the planning effort. State and local laws and ordinances may require that other state, county and local government agencies will have a role in the preparation, review, approval or execution of the plan. Before finalization, a copy of the plan should be furnished to the Corps for information and comment.