1
Da Nhim Hydropower Plant Expansion Project Bidding documents Package 12.02 – (DNE-D2) SCHEDULE T-12 Health, Safety, and Security Control, and Environmental Monitoring and Management Name Of Bidder: LILAMA 18/LILAMA 45.4 JOINT VENTURE. The following documents to be attached herewith: 1. HSE POLICY 2. CERTIFICATE OF REGISTRATION 3. ORGANIZATION CHART OF HEALTH, SAFETY AND ENVIRONMENTAL 4. HEALTH MANAGEMENT PLAN 5. HEALTH & SAFETY AND ENVIRONMENTAL PLAN 6. SAFETY CONTROL PLAN 7. SECURITY MANAGEMENT PLAN 8. SITE ENVIRONMENTAL PROTECTION PLAN 9. WORKERS ACCOMMODATION MANAGEMENT PLAN 10. SAFETY TRANSPORTATION MANAGEMENT PLAN 11. EMERGENCY EVACUATION PROCEDURE Bidder’s Official Representative: Signature: Name: Trần Sỹ Quỳnh Position: General Director Date: Company: LILAMA 18 Joint Stock Company. Company Stamp:

T-12 Health, Safety, And Security Control, And Environmental Monitoring and Management

Embed Size (px)

DESCRIPTION

T-12 Health, Safety, And Security Control, And Environmental Monitoring and Management

Citation preview

Da Nhim Hydropower Plant Expansion ProjectBidding documents Package 12.02 (DNE-D2)

SCHEDULE T-12 Health, Safety, and Security Control, and Environmental Monitoring and Management

Name Of Bidder: LILAMA 18/LILAMA 45.4 JOINT VENTURE.

The following documents to be attached herewith:1. HSE POLICY 2. CERTIFICATE OF REGISTRATION3. ORGANIZATION CHART OF HEALTH, SAFETY AND ENVIRONMENTAL4. HEALTH MANAGEMENT PLAN5. HEALTH & SAFETY AND ENVIRONMENTAL PLAN6. SAFETY CONTROL PLAN7. SECURITY MANAGEMENT PLAN8. SITE ENVIRONMENTAL PROTECTION PLAN9. WORKERS ACCOMMODATION MANAGEMENT PLAN10. SAFETY TRANSPORTATION MANAGEMENT PLAN11. EMERGENCY EVACUATION PROCEDURE

Bidders Official Representative:

Signature:

Name: Trn S Qunh

Position: General Director

Date:

Company: LILAMA 18 Joint Stock Company.

Company Stamp: