Upload
irma-jacobs
View
218
Download
2
Tags:
Embed Size (px)
Citation preview
[T6.4] Assessment of damping pressure wave inside SG
Technical meeting – KIT - Karlsruhe, 22/11/2012
A. Del Nevo, A. Ciampichetti
Presented by Mariano Tarantino
LEADER ProjectWorking Package 6
List of contents
Introductory remarks: LIFUS 5
Objectives and status of deliverables and milestones
Outline of Task 6.4
Status of deliverables and milestones
Refurbishment of LIFUS5: LIFUS5/Mod2
Design of the test section - (Task 3.2)
Test section layout and instrumentation
Preliminary TM specifications
Conclusive remarks, issues & new plan schedule
2/15LEADER Project Working Package 6 Task 4 - Technical meeting – KIT - Karlsruhe, 22/11/2012
Introductory remarks: LIFUS 5
Experimental facility for HLM/water interaction investigations (i.e. PbLi, LBE, Pb)
Designed to operate in a wide range of conditions: up to 200 bar and 500 °C
Operated for supporting LFR and ADS technology development
Suitable for code validation, models development, safety analysis studies, testing engineering solutions, …
Reaction vessel S1
Pressurised water vessel S2
Safety vessel S3
Liquid metal storage tank
LEADER Project Working Package 6 Task 4 - Technical meeting – KIT - Karlsruhe, 22/11/2012 3/15
Objectives and status of deliverables and milestones
With reference LFR and ETDR configurations
Investigate and asses the damping of pressure waves by SGTR event (3 tests planned).
Cooperation (exchange of knowledge and joint technological efforts) with the ROSATOM project in specific topics
MILESTONES (T0 = April 2010)
M06 - SG test facility commissioned (T0 + 24) Delay of 10 months
DELIVERABLES (T0 = April 2010)
D23 - Tests report on the performance of the proposed pressure wave damping system (T0 +36) Delay of 6 months
LEADER Project Working Package 6 Task 4 - Technical meeting – KIT - Karlsruhe, 22/11/2012 4/15
Outline of Task 6.4
Definition of an experimental configuration representative of the SG of LFR reference configuration in conjunction with Task 3.2
Execution of the experimental campaign in LIFUS 5 test facility
The tests will be performed in LBE on a mock up representative (mainly diameter and pitch of the tubes and their support) of the bundle of the SG of LFR reference configuration with perforated outer thin and main shells, immersed in a vessel.
Pressure evolution inside and outside the bundle at different elevation will be measured, as well the final deformation, if any, of the bundle.
Connection with Working Package 3 – Task 3.2 “Conceptual design: SG damping pressure waves system design”
Connection with Working Package 6 – Task 6.5“Scientific and technology collaboration with ROSATOM institutions”
Comparison with Russian design and the connected experimental work
LEADER Project Working Package 6 Task 4 - Technical meeting – KIT - Karlsruhe, 22/11/2012 5/15
Refurbishment of LIFUS-5
LIFUS-5/Mod2 for LFR and ADS technology development
New support frame New injection line New test procedure New control room New DAS and I&CS New instrumentation
Objectives:
Procedure for preparing and operating the facility simplified
Reliable and controlled boundary and initial conditions (repeatability)
Reliable and highly instrumented for detailed experimental data
LEADER Project Working Package 6 Task 4 - Technical meeting – KIT - Karlsruhe, 22/11/2012 6/15
Refurbishment of LIFUS5: new DACS & instrumentation
Instrumentation available for DAS (installed in…):
up to 15 strain gauges (LBE system)
70 TCs for fast acquisition (LBE and water systems)
8 fast pressure transducers (LBE and water systems)
1 Coriolis flowmeter (water system)
1 Level gauge (water system)
Acquisition @ 1 kHz
High temperature strain gauge
Level gauge
LEADER Project Working Package 6 Task 4 - Technical meeting – KIT - Karlsruhe, 22/11/2012 7/15
NEW DACS available
Refurbishment of LIFUS-5
LIFUS5/Mod2 is a new facility, set up at ENEA CR Brasimone:4 main vessels and few components have been recycled from LIFUS5
LEADER Project Working Package 6 Task 4 - Technical meeting – KIT - Karlsruhe, 22/11/2012
Water flow meter
Workshop activities on S1
8/15
Design of the test section - (Task 3.2)
Ref. design of ELSY SG
22.22 mm OD tube, 3 mm thick, axial and radial pitch of 24 mm.
Max flow rate is 15 kg/s, about 1 kg in 0.1s and 3,4 kg in 1s
LIFUS 5 limits
Small dimension and geometrical shape (scaled down test section required)
Achievable operating conditions of the tube to be ruptured (max flow rate, duration of the test, water in the tube is stagnant etc…)
Design of a test section in order to reproduce the velocity field of the displaced molten lead in the very first moments after tube rupture
Max. flow rate estimated 50-60% of the reference flow rate
Tests relevant for code validation
LEADER Project Working Package 6 Task 4 - Technical meeting – KIT - Karlsruhe, 22/11/2012 9/15
Design of the test section - (Task 3.2)
The test section consists of Straight-tube bundle arranged in 13 tube rows by 8 columns
Dimensions and description are providedas preliminary information (Draft report of Task 3.2 in preparation)
The plates provide the path to thepressure surge buffering S3 dump tank.
The tubes are fixed to the tube sheets by means of rod caps at both ends
The tube prepared to be ruptured is the 7th row-4th column-tube,
LEADER Project Working Package 6 Task 4 - Technical meeting – KIT - Karlsruhe, 22/11/2012 11/15
Test section layout and instrumentation
Perforated shell
The test section layout: placed in vertical position with the injector in the center in order to
To simplify the construction and to speed up the activities
To keep the axi-symmetry (code validation)
To increase the tube length
No influence on the objectives
LEADER Project Working Package 6 Task 4 - Technical meeting – KIT - Karlsruhe, 22/11/2012
Planned instrumentation for LEADER campaign inside the reaction vessel (S1):
Up to 70 TCs for fast acquisition
Inside and outside the perforated shell
Up to 8 fast pressure transducers
Inside and outside the perforated shell
Up to 15 strain gauges
6 on the vessel wall (5 inside and 1 outside)
3 planned on the test section
12/15
Preliminary TM specifications
# Parameter T#1 T#2 T#3
1 Reaction system S1 (+S3) S1 (+S3) S1 (+S3)2 LBE temp. [°C] 400 400 4003 Water pressure [bar] 180 180 1804 Water temp. [°C] 330 330 3305 Argon vol./LBE vol. [%] TBD TBD TBD
6Lasting time of the injection valve on [s]
TBD TBD TBD
7 Injector orifice diam. [mm] TBD TBD TBD
Three tests planned
10%, 50%, 100% of reference flow rate
Test section design supported by MERIVUS
Pre-test calculations (NPP and LIFUS5) by SIMMER code by CIRTEN
Support calculations for evaluating the tube thickness by CIRTEN
Support calculations for the design of the new water injection line by ANSALDO
LEADER Project Working Package 6 Task 4 - Technical meeting – KIT - Karlsruhe, 22/11/2012 13/15
Conclusive remarks, issues & new plan schedule
LIFUS5/Mod2 is a new facility set up at ENEA CR. Brasimone)
Delays accumulated certification issues (activities stopped from Feb. to June 2012 )
The layout of the facility, the instrumentation and the performances of the acquisition system are consistent with the specifications
February 2012. [Problem] The safety office of ENEA raised the issue that LIFUS5 facility (constructed in 1998) was not in accordance with the PED.
March 2012. [Corrective actions] Actions started to solve the issue: i.e. review of the design, new documentation of the facility components, of the facility as system, qualification of all welding processes, check (RX and PT) of all weldings including those already existing, verification of all RX weldings by a certified external body, risk assessment and installation of safety valves, etc.
June 2012. [Problem solved] Construction of the facility, design and realization of the new I&C system and DAS restarted
Sept. 2012. Construction of LIFUS5/Mod2 completed. New control system available
October 2012. Checking heating wires, sensors, etc. Insulation placed. Fast aqcquisition system available. Commissioning tests on overall system (procedure tests, pressure tests, instrumentation and control tests)
LEADER Project Working Package 6 Task 4 - Technical meeting – KIT - Karlsruhe, 22/11/2012 14/15
Conclusive remarks, issues & new plan schedule
New plan schedule
discussed in Madrid 10/05/2012 and according with the letter ENEA/2012/39527/UTIS sent 30 July 2012
Certification of the experimental facility in progress
LIFUS5/Mod2 LEADER test section construction in progress
Performing the LEADER experimental campaign
According with the new time scheduleLEADER Project Working Package 6 Task 4 - Technical meeting – KIT - Karlsruhe, 22/11/2012 15/15
16
Support to the Steam Generator Tube Rupture (SGTR) Experimental activity in LIFUS 5
CIRTENInteruniversity Consortium for Technological Nuclear Research
Rosa Lo Frano
INTRODUCTION
LIFUS 5 EXPERIMENTAL ACTIVITY
BUCKLING ANALYSIS
BUCKLING ANALYSIS RESULTS
CONCLUSIONS
17
Introduction
The intent of this study is to provide a contribution to the development of a LIFUS 5 mock up to be developed to the evaluation of the SGTR. In particular in agreement with the proposed experimental configuration, it was analyzed the conditions for which the rupture of SG tube could occur.
Scheme of two spiral tubes arrangement (Alemberti et al., 2012)
The reference design of SG features a 22,22 mm OD tube, 3 mm thick with axial and radial pitch of 24 mm
18
LIFUS 5 EXPERIMENTAL ACTIVITY
The LIFUS 5 test rig has been designed to investigate the SGTR dynamical interaction involving molten heavy metal and water injected into it, influenced by the temperature of the interacting coolants and the pressure of the secondary coolant, of about 190 bar.
Considering the limits of LIFUS facility, related to the small dimensions of the test vessel, the geometrical shape and achievable operating conditions, a full scale testing is not possible. Therefore, a simplified scaled mock up with tube 17,2 OD and 2 mm thick with bore cross section of about 60% of that of the ELFR-Option A reference SG will be used.
19
The test section consists of a 17.2 mm OD straight-tube bundle arranged in 13 tube rows by 8 columns, and of its enclosure. The tube is about 220 mm long (in literature classified as short tube) and hanged between two perforated plates, which serve as the inner and outer shell of the steam generator makeup. The vertical plates are 18,5 mm apart from each other, and of section tapered from the base edge of 17.2 mm to a thin top edge of 5 mm.
How to foresee the tube to be ruptured ??
Buckling analysis
LIFUS 5 EXPERIMENTAL ACTIVITY
20
Buckling Analysis
The buckling is influenced not only by the pressure load but mainly by the nature and magnitude of the imperfections invariably caused by various manufacturing processes (strongly dependent on that).
The load carrying capacity is recognized to be strongly influenced by the yield load.
tube 17,2 OD and 2 mm thick
21
Hypotheses:
•Cylindrical/spiral shell with radius R, length L and thickness t;
•Homogeneous and Isotropic material;.•Uniform internal/external pressure p
The shell is assumed to be “thin” so that the buckling occurs below yield. For short-moderate length isotropic cylindrical shells pressure buckling loads a simply supported boundary condition may be considered:
w = 0, M = 0, N = 0, v = 0
In practice, a clamped boundary is used, represented by: 0 ; 0
0' ; 0
N
ww
Buckling Analysis
22
1) Material is homogeneous, isotropic and elasto-plastic A 304L/316.
2) The model consists of solid 3-D finite elements. The mesh involves five elements on the thickness and 160 over the tube circumference; a suitable elements number capable to assure the convergence of results.
FEM model characteristics:
Size of model: 8800 Elements
3-D Solid Element Brick type: Hex 8
Nonlinear analyses as function of the first change in the slope (i.e. stiffness) in the load deflection curve were performed adopting the Lanczos method.
Buckling Analysis
23
l/D t/D t (mm) l (mm) Pcr (MPa)
12.79 0.11 2 220 66.37
25.81 0.11 2 440 15.85
38.37 0.11 2 660 3.16
The load carrying capacity is also dependent by D/l and t/D ratio.
Buckling value under external pressure
The obtained values referred to perfect shell. The real buckling value, if a real shape of the tube is considered (eccentricity, ovality, etc.), would be 10- 15% lower than numerical Pcr.
l/D t/D t (mm) l (mm) Pcr (MPa)
12.79 0.06 1 220 52.68
25.81 0.06 1 440 4.5
38.37 0.06 1 660 1.12
Buckling value under external pressure
Buckling Analysis Results
24
t (mm) l (mm) Pcr (MPa)
1.5 220 62.5
1 220 52.68
0.75 220 41.4
0.5 220 35.77
0.25 220 5.02
Buckling load vs. reduced thickness
Buckling Analysis Results
25
Conclusions
The 1st buckling mode was m = 1 (bending mode along the longitudinal direction): the tube is influenced by the edge effects, its wavy form is not damped out and contribute to the magnitude of the critical load.
As for as the proposed simplified scaled mock up concerned, the conditions for which the rupture of SG tube could occur is obtained at very small thickness of tube that is very difficult to obtain by means of mechanical machinery treatment.
To reach the failure condition it is therefore suggested to intentionally reduce the thickness of the short tube (reduced strength) in order to attain low buckling values