15
19-083 Task Order No. 3 Page 1 TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR MILL TRUNK JENKINS TO BEAVERTON INTERCEPTOR PROJECT NO. 6882 CLEAN WATER SERVICES AND MURRAYSMITH, INC. This Task Order, dated ____________________________, is between Clean Water Services (District) and Murraysmith, Inc. (Consultant) and amends the parties’ Master Contract dated effective December 15, 2017 and any amendments to the Master Contract (collectively, Contract). RECITALS 1. District and Consultant previously entered into the Master Contract. 2. The parties now wish to amend the Master Contract to provide Conveyance Engineering services related to the Cedar Mill Trunk Jenkins to Beaverton Interceptor Project No. 6882 (Project). TERMS AND CONDITIONS 1. Scope of Work Consultant will perform the services described in Exhibit A. 2. Compensation District will pay Consultant as set forth in the Contract. District's total payment to Consultant, including expense reimbursement, will not exceed $604,716. Consultant will invoice District monthly. Consultant's invoices must contain a description of any task performed during the billing period, the hourly rates applicable to each task, the hours spent on each task, an itemized description of the expenses incurred during the billing period, and the total amount billed. Consultant must indicate the total amount of the Contract, the total of the invoice, the total invoiced to date and the remaining Contract balance. 3. Schedule / Duration Consultant will complete Specific Work by Task Deadlines for that work as indicated. Specific Work Task Deadline Tasks 1-7 March 31, 2020 Task 8 December 31, 2022 The Contract will be effective from the date written on page one and shall expire June 30, 2023 unless terminated earlier pursuant to the terms of the Contract.

TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

19-083 Task Order No. 3

Page 1

TASK ORDER NO. 3

CONVEYANCE ENGINEERING FOR CEDAR MILL TRUNK JENKINS TO

BEAVERTON INTERCEPTOR PROJECT NO. 6882

CLEAN WATER SERVICES AND MURRAYSMITH, INC.

This Task Order, dated ____________________________, is between Clean Water Services

(District) and Murraysmith, Inc. (Consultant) and amends the parties’ Master Contract dated

effective December 15, 2017 and any amendments to the Master Contract (collectively,

Contract).

RECITALS

1. District and Consultant previously entered into the Master Contract.

2. The parties now wish to amend the Master Contract to provide Conveyance Engineering

services related to the Cedar Mill Trunk Jenkins to Beaverton Interceptor Project No.

6882 (Project).

TERMS AND CONDITIONS

1. Scope of Work

Consultant will perform the services described in Exhibit A.

2. Compensation

District will pay Consultant as set forth in the Contract. District's total payment to

Consultant, including expense reimbursement, will not exceed $604,716.

Consultant will invoice District monthly. Consultant's invoices must contain a

description of any task performed during the billing period, the hourly rates applicable to

each task, the hours spent on each task, an itemized description of the expenses incurred

during the billing period, and the total amount billed. Consultant must indicate the total

amount of the Contract, the total of the invoice, the total invoiced to date and the

remaining Contract balance.

3. Schedule / Duration

Consultant will complete Specific Work by Task Deadlines for that work as indicated.

Specific Work Task Deadline

Tasks 1-7 March 31, 2020

Task 8 December 31, 2022

The Contract will be effective from the date written on page one and shall expire June 30,

2023 unless terminated earlier pursuant to the terms of the Contract.

Page 2: TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

19-083 Task Order No. 3

Page 2

4. Electronic Signature

This Contract and any future amendments to it may be executed in several counterparts,

each of which will be an original, all of which will constitute one and the same

instrument. An electronic signature will be considered an original. The individuals

signing this Contract certify that they are authorized to execute this Contract on behalf of

Consultant and District, respectively.

5. Tax Law Compliance

Consultant represents, warrants and covenants that Consultant has complied with, and

agrees that during the term of this Contract shall comply with Oregon Tax Laws and

applicable tax laws of political subdivisions of this State including, but not limited to,

ORS 305.620 and ORS chapters 316, 317 and 318. Consultant’s failure to comply with

Oregon Tax Laws or the applicable tax laws of political subdivisions of this State for the

six years prior to the date Consultant executes this Contract or the period of time

Consultant has been in business, whichever is less, or during the term of the Contract is a

default for which District may terminate the Contract and seek damages and other relief

available under the terms of the Contract or under applicable law.

6. Effect of Task Order

Except as amended herein, the Contract will remain in full force and effect.

Murraysmith, Inc. Clean Water Services

By: By:

Troy L. Bowers, Executive Vice President Chief Executive Officer or Designee

Approved as to Form

District Counsel

Page 3: TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

19-083 Exhibit A – Scope of Work

Page 3

EXHIBIT A

SCOPE OF WORK AND SPECIAL TERMS AND CONDITIONS

CONVEYANCE ENGINEERING SERVICES

FOR THE CEDAR MILL TRUNK JENKINS TO BEAVERTON INTERCEPTOR

PROJECT NO. 6882

I. PROJECT DESCRIPTION

The District’s calibrated sanitary sewer model indicates the Cedar Mill Sanitary Trunk (which is

located within the Cedar Mill Creek corridor) will be capacity-deficient by 2025. However,

flowmeter data has shown significant surcharging during recent storm events suggesting the

improvements may be needed sooner. Additional modeling conducted by the District

demonstrated upgrading approximately 4,900 feet of the trunk to 48-inches (through the Cedar

Mill Creek corridor south of Jenkins) would eliminate the need to upgrade the upstream portion

of the trunk sewer through the Nike campus in the near future. The proposed enhancement

actions associated with Washington County’s Jenkins Road improvement make this the ideal

time to collaboratively upgrade the Cedar Mill Sanitary Trunk as part of the road improvements

project.

An alternatives analysis has identified a preferred alignment to construct a new 48-inch trunk

line. Concurrently, the Project team has identified a suite of enhancement actions within the

Cedar Mill Creek corridor to improve stream and floodplain resilience and improve storage and

attenuation to mitigate the incremental increase in flows from the Washington County Jenkins

Road improvement project. This scope of wok covers project management, design services,

geotechnical engineering, permitting support, bidding and construction support. The scope also

includes detailed survey work, erosion control plans, and coordination for both the sanitary

sewer and enhancement Projects.

II. SCOPE OF WORK

Task 1 – Project Management

Consultant shall:

1. Provide a qualified cohesive Project team to deliver a technically sound work product

completed on schedule and within budget. Activities shall include planning, scheduling,

communication, coordination, quality control, Project status reporting and Project invoicing.

2. Coordinate and attend a Project kick-off meeting with District Project management staff to

discuss Project elements, background, scope, schedule, design criteria, operation and

maintenance concerns, and District preferences. District will provide Consultant copies of

as-built or record drawings of the system, as requested by Consultant.

3. Develop a schedule identifying critical tasks to meet the Project completion date. The

schedule shall be updated as necessary and reflect the resources required to meet Project

deadlines.

Page 4: TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

19-083 Exhibit A – Scope of Work

Page 4

4. Perform Project management duties including regular phone updates, monthly invoicing, and

monthly Project status reports, management of schedule, budget and scope to meet Project

requirements. Project status reports shall list activities completed, Project challenges,

proposed solutions to challenges, current schedule, goals for the coming month, and Project

budget conditions. Identify and describe potential changes to the Project scope of work that

occur during the reporting period that influence Project budget or schedule in the Project

status report.

5. Schedule and coordinate work conducted by subconsultants. Manage subconsultant billing,

planning, schedule and budget management, quality control, cost tracking and

invoicing. Subconsultant activities shall be detailed in the monthly Project status report.

6. Coordinate and manage the Project Team at each phase of design. Coordinate design

reviews and implementation of design review comments. For each deliverable Consultant

shall review and compile all review comments received and provide a response to each

comment in a comment-response log.

7. Coordinate communication and work tasks with the team, District, and subconsultants to

meet the Project schedule.

Task 1 Deliverables

Meeting agenda and meeting minutes. Consultant will submit meeting agendas to

District within five business days before each meeting and meeting minutes within five

business days following each meeting documenting action items and decisions.

Initial Project schedule in Microsoft Project format due within ten business days of

District’s Notice to Proceed (NTP).

Monthly Project status reports no later than the twenty-fifth of each month for services

performed the previous month. Bi-weekly e-mail Project progress updates as needed.

Comment and Response logs to be submitted with each Task Deliverable.

Task 2 – Topographic Base Map

Consultant shall:

1. Field Survey: Perform a comprehensive field survey of existing conditions within the

Project area shown on the map attached hereto as Exhibit A-1 (Project Area) and develop a

Project topographic base map to District standards. Depict all man-made and natural features

necessary for Project design and provide accurate and representative one-foot ground

contours within the Project Area on the base map. Mapping shall be oriented to the Oregon

State Plane NAD_1983_HARN_StatePlane_Oregon_North_FIPS_3601_Feet_Intl coordinate

system and stamped by a Professional Land Surveyor registered in the State of Oregon.

2. Integrate Previous Survey Data: The District has performed survey work within the Project

Area, including placing survey control, locating structures, and creek cross-sectional data. In

addition to District survey work, Washington County (County) has performed survey work

along Jenkins road and SW 153rd Drive. Consultant shall integrate previous survey efforts

and combine them on the topographic base map to form a single comprehensive map all on

the same horizontal and vertical coordinate system. This may require Consultant to transpose

previous survey efforts.

Page 5: TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

19-083 Exhibit A – Scope of Work

Page 5

3. Research Materials: Obtain all property and/or survey research materials for use in field

investigation, proposal preparation, topographic surveying, and easement preparation.

Research materials may include property deeds and legal descriptions, recorded easements,

records of surveys, plats, partitions, vacations, road and/or highway maps, vertical datum

benchmark information, and any other record documents necessary to support the survey and

mapping.

4. Utility Locations: Request field utility locates from the “Utility Notification Center”

(503/246-6699) prior to beginning survey field work. Tie all existing utility locations

marked in the required survey area by surveying and accurately depicting them on the

topographic map. Make every effort to confirm utility locates are complete and accurate

during field investigations. Seek clarification from the appropriate utility owner and advise

the District Project Manager if omissions or discrepancies are noted in the field.

5. Survey Control Network: Establish a network of horizontal and vertical survey control

throughout the Project Area. This network shall incorporate control from previous survey

efforts to serve as a baseline to transpose previous survey information. Install all control

monumentation to withstand movement and/or deterioration by seasonal weather influences

for a minimum of two years. Select control locations to minimize the probability of

disturbance by construction activities and allow for easy location and recovery at a later

date. Reference, horizontally and vertically, all field survey information collected to the base

control network. Provide a list of computed XYZ coordinates with descriptions for all

control points, survey points, and property monuments associated with the surveys to

District.

Establish temporary Project benchmark(s) for vertical control by closed-loop level

surveying. Base vertical datum upon County record Datum. Datum shall be National

Geodetic Vertical Datum 1929 (NGVD) unless otherwise directed by District. Assumed

elevation datum is not acceptable. Clearly depict and note County permanent

benchmark(s) referenced for the Project with a record description on the survey base

map. Identify and describe Benchmarks beyond the immediate Project mapping area by

narrative on the survey base map.

Control network points may be a combination of scribes or P.K. nails in hard surfaces,

wooden hubs with tacks, or iron rods designated as control points with red plastic or

aluminum caps. All points shall be clearly marked with durable marking paint in hard

surface or traveled ways and with four-foot lath and ribbon in areas outside pavement,

traveled ways, or other hard surface areas.

6. Property Line Identification: Tie all viable property monuments found in the Project Area

to the Project horizontal control network. Locate and tie to Project control a sufficient

number of monuments to accurately determine property boundaries and/or

alignments. Depict all tied monuments on survey base map. Collect and tie survey

information sufficient to generate accurate permanent and temporary construction easements

and support development of legal descriptions. Incorporate all associated map and tax lot

numbers, property owner names, addresses, plat names and lot numbers into the map by

notation or table.

7. Field Planimetric Data: Collect field topographic information to accurately and clearly

depict all-important planimetric features within the Project Area. Collect information of

Page 6: TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

19-083 Exhibit A – Scope of Work

Page 6

sufficient quantity and density to generate and depict accurate one-foot ground contours.

Measure ground elevations to the nearest tenth of one foot and accurately reflect all

significant grade changes, breaks and terrain characteristics. Measure hard structure

elevations to the nearest one-hundredth of a foot. Clearly label all features, structures, or

improvements on the map.

Overall planimetric information collected during the field survey to be depicted and

annotated on the mapping shall include, but not be limited to the following:

a. Property lot lines.

b. Right-of-way lines.

c. Property monuments found including description and condition.

d. All street and roadway features including material type, centerlines, edges of

pavement, traffic control devices, striping, speed cushions, and signage.

e. Driveways, driveway let-downs, and sidewalks, landscape strips including material

type.

f. Significant structures or landscaping features likely to be impacted by construction

(e.g. retaining walls, patios, pathways, yard structures, lawns, planting areas, high

value ornamental shrubbery or trees).

g. Location and footprint configuration of all residences, buildings, or structures.

h. Lowest floor elevation of structures served by sanitary and/or storm sewer lateral and

cleanout locations if available. Structure characteristics shall be noted on mapping if

discernible (i.e., full basement, half-basement, daylight basement, single level, etc.).

i. Trees as described in the tree survey.

j. Fences by type, material, and height.

k. Key landscaping features including significant shrubs or high-value ornamental trees,

retaining walls, planters, lawn and landscaping areas.

l. Creeks, drainages, water courses, or water bodies defined by toe and top of bank,

channel configuration, and thalwegs.

m. Staking established by environmental subconsultant or owner delineating specific

areas of environmental concern including wetland delineations, Vegetated

Corridor limits, and/or significant natural resource areas.

n. Utilities, including water, gas, power, telephone and cable utility lines. Includes all

valves, meters, hydrants, poles, pedestals, guy anchors, or other appurtenances

associated with each system.

o. Sanitary sewer system piping, manholes, and cleanouts including structure and pipe

sizes and materials, invert and rim elevations.

p. Storm sewer system piping, manholes, culverts, inlets and catch basins including

structure and pipe sizes and materials, invert and rim elevations.

q. All other major topographic features likely to impact or be impacted by the design or

construction of this Project.

Page 7: TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

19-083 Exhibit A – Scope of Work

Page 7

r. Subdivision plat names, partition information, lot numbers, tax lot designations,

owner names, property addresses.

s. Easements of record associated with all Project parcels.

8. Conveyance System Structures – Survey Data: Locate manholes (sanitary and storm) by

center of manhole structure (not cover) and measure and record inside diameter. All other

conveyance structures shall be identified dimensionally. All pipe connections to manholes

and/or structures shall be identified by diameter, material (if determinable), flow direction (in

and out) including compass direction, and invert elevation. Special attention shall be paid to

determine the presence of any inside and/or outside drop connections, flow diversion

structures, weirs or other non-standard features relevant to engineering design.

All elevations relating to structures including, manhole and catch basin rims, invert

elevations, and pavement shall be measured and recorded accurately in hundredths of one

foot. Pipe invert elevations at manhole shall be projected to the center of the structure and

measured accurately to allow for accurate fabrication of precast manhole bases used in retro-

fit applications. Diameters of all pipe penetrations shall be accurately measured and

recorded.

Where manhole and/or other structure rim elevations are not representative of adjacent

ground surface, additional ground shot(s) adjacent to the structure shall be recorded.

Determine the location and pipe invert elevations at the next contiguous structure of the

sanitary or storm system outside the immediate Project Area if connected to a structure

within the Project Area.

9. Wetland Delineation Survey: Collect and integrate the wetland delineation staking on the

Topographic Base Map. Wetland Delineation flagging shall be placed/located by others. A

sketch map of approximate wetland boundaries and flagging will be provided to the

Consultant to assist with subsequent surveying. Coordinate and schedule topographic survey

field work with environmental field work to ensure accurate collection and depiction of

wetland delineation on the Topographic Base Map. Wetland flagging may not be available

during the initial topographic survey, requiring a separate data collection.

10. Utility Potholing and Verification: Coordinate, schedule, and provide vacuum excavation

of utilities and conduct field surveying necessary to determine accurate horizontal and

vertical locations of excavated utilities and incorporate information into the Project

Topographic Base Map. Establish sufficient stable reference points during field surveying to

allow for verifications at a later date if required. Update topographic base map and electronic

drawing files identifying the utility owner, size, material (if determinable), horizontal

location, and vertical elevation. Include field survey notes of potholing, reference points and

measurements.

11. Tree Survey: Locate the drip line canopy of individual trees or grove trees within the Project

Area. Provide the location, quantities, size in diameter breast height (dbh), condition, genus

and species of all trees, including snags, within the Project Area that are 6-inch dbh or

greater. Locate any Pacific Yew (Taxus brevifolia) regardless of DBH. All trees within the

Project Area shall be tagged. Tree tags are to be located so they are facing away from trails

and the general public. Tree identification shall be performed by a certified arborist.

Page 8: TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

19-083 Exhibit A – Scope of Work

Page 8

Prepare a tree removal table demonstrating the dbh of the surveyed trees within the Project

Area, separated into conifer and deciduous categories.

12. Easements: Prepare legal descriptions and maps for temporary construction easement(s) and

permanent easement(s) for the Project as directed by District. Easements will be required for

the Sanitary Sewer, Water Quality Facility, and Water Quality Preservation and Storm and

Surface Water Drainage. District will provide direction to Consultant on dimensional

configurations and types of Project easements required for each affected property.

Develop an easement packet consisting of a map and legal description for each individual

parcel which the Project crosses. District will provide Consultant with District approved

examples and guidelines for developing the easement exhibits. Strip easements are not

acceptable.

Develop right-of-way base map showing existing and proposed right-of-way line and

permanent and temporary easement lines. Scale of the map will be 1”=40’. Map shall show

map and taxlot number, site address number, owner, and a file number for each parcel.

13. Alignment Staking: Stake the selected pipeline alignment and construction limits in the field

to assist with other field data collection tasks and easement acquisitions when requested by

the District (one time only).

Task 2 Deliverables

Electronic copy of comprehensive topographic base map including previous survey

efforts by District and County prepared in AutoCAD Civil 3D 2014.

Field survey notes including XYZ coordinate list with descriptors for all points surveyed.

Tree mitigation table in Excel and PDF formats.

Easement packet per property parcel consisting of easement map and legal descriptions

including the square footage for the easements stamped and signed by a Professional

Land Surveyor currently registered in the State of Oregon.

Task 3 – Geotechnical Investigation and Report

Consultant shall:

1. Perform a geotechnical investigation of the proposed alignment to support the design of

the Project. Consultant shall prepare a geotechnical data report (GDR) to be included in

the bid documents and a Geotechnical Engineering Report (GER) to support the design

team. A field exploration program will be completed for the Project and will include the

following:

a. Sewer Alignments. Conduct a minimum of six borings along the alignment in

approximately 800- to 1,000-ft increments to obtain information for design and

construction of the gravity sewer. Conduct two additional borings at each

trenchless crossing (TriMet, Reser’s bridge) at both receiving and boring pit

locations. The borings will generally extend to at least 10 feet below the

anticipated invert of the proposed sewer pipe.

Page 9: TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

19-083 Exhibit A – Scope of Work

Page 9

Place a vibrating wire in four boreholes to permit measurement of the depth to

groundwater. The piezometer cables will be protected at the ground surface with

a metal monument. At least three measurements of ground water shall be made,

one at the initial installation, one during low water summer conditions, and one

during the winter with wet conditions.

b. Drilling and Sampling. Borings shall be made with a track-mounted drill rig, if

possible. If not possible, boring shall be made with a man-power maneuverable

drill rig capable of attaining a bore depth of 25 feet below grade. Borings will be

made with solid-stem or hollow-stem drilling methods. Borings made in

pavement may be made with either mud-rotary or hollow-stem auger drilling

techniques. Disturbed split-spoon samples and undisturbed Shelby tube samples

of soil will be obtained from the borings at about 2.5-feet intervals of depth in the

upper 15 feet and 5-feet intervals of depth below a depth of 15 ft. The Standard

Penetration Test will be conducted while the disturbed split-spoon samples are

being taken. Rock, if encountered, shall be continuously cored, particularly if it is

within the depth of planned excavation.

The drilling spoils from borings will be placed in metal drums and removed from

the site. Bore holes will be backfilled with bentonite chips in natural areas. Where

borings penetrate pavement, the existing pavement section shall be restored and

bore hole backfilled with grout.

The borings will be subcontracted to a drilling contractor experienced in drilling

and sampling soils for engineering purposes. The drilling and sampling will be

accomplished under the direction of a geotechnical engineer or engineering

geologist licensed in the State of Oregon who will maintain a detailed log of the

materials and conditions uncovered during the course of drilling and sampling.

All borings will be constructed, reported to Oregon Water Resources Department

(ORWD), and abandoned per the requirements of OAR 690-240, including

piezometers.

All boring located within regulated wetlands will be properly permitted prior to

commencement of the work. Consultant shall coordinate with and support District

staffs’ efforts in obtaining necessary general authorizations from permitting

agencies to facilitate investigations.

Access. Drilling shall be performed during the drier late spring or summer

months when access can be readily made. Consultant along with the geotechnical

engineer or geologist in charge of the drilling operation shall meet with the

District and Property owners in the field to identify drilling locations prior to

developing an exploration work plan. When required, this work plan shall also be

submitted to Washington County in order to obtain the required permits to work

in the right-of-way prior to the commencement of field work. The exploration

work plan memorandum for the planned work will include a scope of work,

drilling and sampling procedures, access routes, working areas and bore locations,

Page 10: TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

19-083 Exhibit A – Scope of Work

Page 10

bore hole diameters and depths, equipment used, traffic control plan (if needed),

wetlands/waters, trails, and a site health and safety plan.

Consultant shall obtain any necessary permits from the County for shoulder and

lane closures required for the drilling work along with any necessary flagging or

traffic control. District will manage permitting for regulated wetlands and will

acquire necessary site access permission based upon the approved exploration

work plan.

c. Utility Locates and Notifications. A request to the Utility Notification Center

will be made at least 48 hours prior to the start of drilling. Appropriate timely

notifications will be made to the District, Washington County, and others as

required prior to the start of work. A private utility locator will also be used to

clear the borings.

2. Conduct laboratory tests to provide data on the important physical characteristics of the

subsoils, essential for engineering studies and analyses. The laboratory tests will include

standard classification tests, such as natural water content, washed sieve analyses, and

unit weight determinations, as well as strength and consolidation testing. Perform rock

core strength tests where suitable rock core samples are obtained.

3. Conduct engineering studies and analyses. Prepare conclusions and recommendations

concerning:

a. Earthwork, including cut and fill slopes, wet-weather construction, and the suitability

of on-site soils for use as structural fill;

b. Design criteria for design water level;

c. Slope stability considerations;

d. Design criteria for temporary excavation, shoring, and dewatering considerations;

e. Rock excavation considerations;

f. Design and construction criteria for trenchless crossings, including estimated physical

soil strength properties; and

g. Trench excavation and subgrade preparation and stabilization recommendations.

Task 3 – Deliverables

Draft GDR and GER in Word format.

Final GDR and GER in Word format and stamped GDR and GER in PDF format.

Three original copies of final GDR and GER with wet stamped signatures.

Task 4 Public and Other Agency Coordination

Consultant shall:

1. Provide support to District with public coordination to include the following:

Page 11: TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

19-083 Exhibit A – Scope of Work

Page 11

a. Neighborhood Meeting – Consultant shall attend a single neighborhood meeting and

develop displays depicting the sanitary alignment and work zone limits along with

staging and access routes. The exhibit shall also depict natural features, trails, detour

routes (traffic and pedestrian) parking lots and existing structures.

b. Other Agency Coordination – Consultant shall attend up to three meetings and

provide exhibits to support District coordination efforts with Washington County,

Tualatin Hills Park and Recreation District, DSL, CORPS, Reser’s Fine Foods, and

Nike.

Task 4 Deliverables

Two ANSI size E displays adhered to poster board or other suitable media.

11 x 17 exhibits for Other Agency Coordination.

Task 5 - Preliminary Design

Consultant shall:

1. Create preliminary designs for the new gravity sewers. The proposed gravity sewer

routing work shall include:

a. Analysis of the proposed pipeline routing;

b. Identification of permitting and property/right-of-way acquisition requirements

necessary to support proposed pipeline construction;

c. Confirmation calculation of hydraulic capacity based on pipe alignment and slope;

d. Review any identified alignment options with respect to constructability, costs,

permitting, right-of-way/easement acquisition needs, and other potential special

interests;

e. Develop preliminary overview maps and conceptual plan and profile drawings for

detailed analysis and review with District staff and other interested parties. These

large-scale composite mapping worksheets will serve as key tools from which any

identified alternatives may be analyzed and compared. The preliminary drawings will

include composite utility information, wetland boundaries, vegetated corridor

boundaries, trails, boardwalks, and trees along prospective pipeline routes to assist

with localized routing recommendations.

f. Meet with District staff to review preliminary alignment drawings and mapping.

g. Prepare a technical memorandum to summarize the results of any analysis performed,

hydraulic calculations, and decisions made.

Task 5 Deliverables

Preliminary alignment overview map and conceptual plan and profile drawings at

standard D sized sheets (22” x 34”) at a scale of approximately 1 inch = 40 feet.

Draft and Final Technical Memorandum in Word and PDF formats.

Page 12: TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

19-083 Exhibit A – Scope of Work

Page 12

Task 6 - Permitting Support

Consultant shall:

1. Assist the District in obtaining approvals and permits for the Project.

a. Design Approval Support. Coordinate with District, providing figures, selecting

locations of anticipated construction ingress and egress, and participate in up to two

meetings and work sessions to support design approval efforts.

b. Washington County Right-of-Way Permits. Conduct informal preliminary

consultations, submit preliminary design drawings for permitting staff review, and

prepare permit applications. Incorporate final conditions of approval into the final

design. District will pay permit fees.

c. Additional Permitting Support. Engineering assistance needed for environmental and

land use permit applications being prepared by others. Coordination with District,

providing CADD line work, planned locations of anticipated ingress and egress, and

calculation of areas of disturbance including cut and fill volumes. Participate in up to

two meetings and work sessions to support permitting effort.

2. Prepare and submit 1200-C application. The permit application will be submitted for plan

review during the design phase, and the issued permit will be transferred to the

construction contractor following Project bidding and award. Conditions of obtaining the

1200-C permit will be incorporated into the final design. District will pay permit fees.

District will provide signed LUCS, permit fees, and obtain owner signatures.

Task 6 Deliverables

Disturbance area calculations for JPA application including cut and fill volumes.

1200-C permit application materials.

Task 7 - Final Design

Consultant shall:

1. Perform the final design and develop and produce final plans, specifications and details

necessary to construct the Project in compliance with District standards. The final plans

shall consist of:

a. General Plans - Vicinity map, drawing index, general notes, key map, survey

control/geotechnical exploration map, construction access and staging overview.

b. Cedar Mill Trunk Sewer Plans and Profiles - Single strip, plan and profile drawings,

at a scale of 1 inch = 20 feet horizontal and 1 inch = 5 feet vertical.

c. Special Detail Plans - Various details for manhole connections, cased creek crossings,

work area limits, trench and backfill configurations.

d. Boardwalk and Trail Plans – plan and details for temporary trails, permanent trail

restoration and replacement boardwalks.

e. Stream Crossing Plan – Typical plan for crossing creeks with construction traffic.

Creek dewatering and aquatic life salvage by others.

Page 13: TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

19-083 Exhibit A – Scope of Work

Page 13

f. Road and Street Restoration Plans - Roadway and street restoration plans, notes and

details as required by permitting agencies.

g. Traffic Control Plans - Details, layouts and notes regarding special traffic control

measures required by permitting agencies. Traffic control plans will also include

pedestrian detours within the THPRD park to facilitate safe movement around the

construction work zone.

h. Erosion Control Plans - Details, layouts and notes needed for special erosion control

measures and 1200-C permit. Erosion control plans shall incorporate sanitary work,

stream work, and water quality features associated with the overall Project.

2. Prepare special provisions to technical specification. Special provisions will be developed

following District standards. District will prepare the construction contract, standards

specifications and assemble the bidding document.

3. Obtain requirements for and develop design specifications and details for third-party

restoration requirements including a replacement boardwalk through the THPRD Nature

Park.

4. Develop a technical memorandum to document the evaluation and design of casings under

TriMet tracks and embankment, and Reser’s bridge to be used for the TriMet permit

application.

5. Prepare estimate of quantities for use in the construction and prepare engineer’s opinion of

probable construction cost.

6. Prepare 60%, 90%, and 100% design submittals in accordance with District requirements

presented in the District Design and Construction Standards for Sanitary Sewer and Storm

Water Management. Review comments for the design submittals will be submitted by

District to Consultant via e-mail in a single comment log.

7. Assemble electronic files of final approved bidding documents (Microsoft Word and PDF)

and construction drawings (AutoCAD and PDF) and deliver them to District. Coordinate

with District’s stormwater design team to ensure plan set uniformity as it relates to

formatting and numbering of plans sheets. District will provide final stamped stormwater

design for the adjacent project.

Task 7 Deliverables

Special provisions to technical specifications in Word and PDF formats.

Design specifications for THPRD Boardwalk.

Technical Memorandum regarding casings for TriMet tracks and embankments and

Reser’s Bridge.

Bid tab including breakdown of quantities and Engineer’s Estimate.

60%, 90%, and 100% design plans in PDF one week in advance of each review meeting.

Page 14: TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

19-083 Exhibit A – Scope of Work

Page 14

Task 8 – Engineering Services during Bidding and Construction

Consultant shall:

1. Provide engineering support to the District during the bidding process. District will be the

primary contact during the bidding phase. District will perform all procurement-related

activities, including advertising, reproducing, and distributing bidding documents to bidders

and plan centers, maintaining a plan holders list, and arranging all bid-phase meetings such

as the bid opening. Engineering support shall be at District’s request, and shall include:

a. Input for responding to bidders’ questions.

b. Input in preparation of up to two addenda.

c. Attendance at the pre-bid conference.

2. Provide engineering support services during construction. The District will perform all

construction management tasks and activities. Consultant will provide engineering support to

the District’s Construction Manager during construction including:

a. Attendance at the pre-construction conference.

b. Responses to requests for clarification and requests for information.

c. Review up to 20 material/product submittals and shop drawings as requested by the

District.

d. Attend up to 12 progress meetings with the District and the construction contractor, as

required.

e. Perform arborist’s inspections as requested by District.

f. Consult with the construction manager when the punch list is developed.

g. Geotechnical site visits if poor soil or water is encountered and up to two separate

calendar day visits while boring.

3. Submit a full set of reproducible as-built drawings of the Project based upon contractor and

District mark-ups, stamped and signed by the Engineer of Record. District will reconcile

differences that may exist between District and contractor mark-ups.

4. Assist District in obtaining and closing out County Grading and Access permits by

submitting necessary forms, reports, plans and responding to additional information requests.

Task 8 Deliverables

Full set of reproducible as-built drawings of the Project submitted in AutoCAD/Civil 3D

2014 and PDF as approved by the District and one hard copy plotted on bond paper

stamped by a Professional Engineer licensed in the state of Oregon.

Geotechnical and Civil permit closeout documents including geotechnical summary

report meeting County requirements.

Page 15: TASK ORDER NO. 3 CONVEYANCE ENGINEERING FOR CEDAR …€¦ · Electronic Signature ... Project status reporting and Project invoicing. 2. Coordinate and attend a Project kick-off

EXHIBIT A-1

19-083 Exhibit A-1 – Survey Area

Page 15