M I S S I S S I P P I C A N Y O N 2 0
TAYLOR ENERGY COMPANY LLC
12.18.15
CONDUCTORS: PROFILE VIEW
12.18.15
MC20 A WELLS • 28 Platform & 6 Exploration Wells • Directional: 24° to 60° Inc • Relatively shallow, <12000’ TVD • Normal pressure: 9.5-10ppg TD • No known blowouts in field • Gas lift required on most wells • Oil, gas & water produced • Multiple reservoirs • Drilling Campaigns early 80’s, 90’s Wells prioritized by flow risk
12.18.15
12.18.15
MC20 WELLS - OVERHEAD
12.18.15
MC20 WELL MODEL
12.18.15
“Cone” of Uncertainty
12.18.15
Based on completion type or components
MC20 Wells – Intervention Targets
Sump Packer In Place
Wells: A-17ST, A-19ST, A-23
No Sump Packer In Place Current & Future ProductionInterval In Place
Wells: A-1 Wells: A-11 & A-2112.18.15
Plugging Requirements
12.18.15
Normal Well IW-19 • Depth 9300’ 9301.2’ • Pressure 3800 psi 3810 psi • Volumes two hundred bbls 205 bbls • Strokes couple of thousand 1995 strokes • Survey Intervals Each 93’ stand 30.0’ • Inclination 48 degrees 48.1 degrees • Azimuth 135 degrees 135.2 degrees • Slides 30’ at High Side 7.5’ at 5-7 Right
‘Add a Decimal Point’
12.18.15
ACTUAL WELL EXAMPLES FROM
SPEARFISH PROJECT
12.18.15
Surface Constraints
12.18.15
MC20 Anti-Collision: IW-4 13-3/8” Shoe to TD
12.18.15
MC20 Anti-Collision: Same – with Uncertainty
12.18.15
IW-19 Proximity to A-19
48° Inclination 136° Azimuth
IW19 Proximity to A19
A - 1 9 7 " C a s i n g
3 . 7 '
9 3 0 0 ' M D
I W - 1 9 1 2 - 1 / 4 " H o l e
A - 1 9 7 " C a s i n g
I W - 1 9 8 - 1 / 2 " H o l e
0 . 7 '
9 5 0 0 ' M D
A - 1 9 7 " C a s i n g
I W - 1 9 8 - 1 / 2 " H o l e
9 6 0 0 ' M D
A - 1 9 7 " C a s i n g
I W - 1 9 8 - 1 / 2 " H o l e
3 . 0 '
9 4 0 0 ' M D
I n t e r s e c t i o n I n t e r v a l 12.18.15
• 9 Wells Successfully Plugged • Oil Plume elimination
• Exceptional Performance • No well control events • No pollution events • No lost circulation events • Extensive Pre-Spud Survey modeling
• Complexity increasing in future wells
FACT SHEET - WELLS
12.18.15
FACT SHEET - PIPELINE
• Started late Summer 2008
• Utilized divers & coiled tubing
• Parted Pipeline sections located
• Contents flushed
• Ends plugged
• One of five sections unable to be located – sediment flow as a result of Hurricane Gustav
12.18.15
FACT SHEET - SALVAGE
Deck Preparation for Lift • Started March 2010, July 2010
• Cut Decks for rigging access
• Install 8 lift connections
• Cut 6 of 8 Jacket Legs
• Install 400 ton Debris Basket
• Begin Debris Collection – focusing on large/heavy items
12.18.15
VB-10,000 Lift System
12.18.15
12.18.15
12.18.15
FACT SHEET - SALVAGE
Deck Lift • Completed mid-June 2011
• VB 10,000 – new build “shakeout”
• Multiple lifts prior to TEC work
• Connect pre-installed lift points
• Cut last 2 Jacket Legs
{Entire Lift - 4 days}
12.18.15
MC20 DEBRIS FIELD
12.18.15
FACT SHEET - SALVAGE
Debris Collection • Phase I prior to Deck Lift
• Phase II after Deck Lift
• 2-400 Ton Debris Baskets
• Completed late June 2011
• All site clearance certificates
have been accepted
12.18.15
12.18.15