Upload
upesddn2010
View
214
Download
0
Embed Size (px)
Citation preview
8/11/2019 Tcp Docs Rkpl
1/113
REV DATE DESCRIPTION BY APPD REVIEWD
01 07/06/2014 ISSUED FOR APPROVAL
00 15/04/2014 ISSUED FOR APPROVAL
NAME YOGESH JAYRAJ
RAYCHEM RPG KSS
TITLEDESIGN DOCUMENT FOR TEMPORARY
CATHODIC PROTECTION SYSTEM FOR PHASE-ICONTRACT NO- DOCUMENT NO-
R1WORK ORDER NO- MH2145-C000-EL-SPC-SPC-0025, DATED 2/5/13 06-10-1403-DD-PH1
EPMC SERVICES FOR REWARI-KANPUR
PIPELINE PROJECT
OWNER
HINDUSTAN PETROLEUM CORPORATION LIMITED
MAIN CONTRACTOR
KSS Petron Private Limited
Formerly KazStroy Service Infrastructure India Pvt.Ltd)
CONSULTANT
WORLEYPARSONS SEA INDIA PVT. LTD.
CP CONTRACTOR
RAYCHEM RPG P) LIMITED
WORLEYPARSONS APPROVAL
Approved by
NAME SIGN
8/11/2019 Tcp Docs Rkpl
2/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 2 of 113
Contents1.0 INTRODUCTION .................................................................................................................................. 4
2.0 SCOPE ................................................................................................................................................. 4
3.0 ABBREVATIONS ................................................................................................................................. 5
4.0 SYSTEM OVERVIEW .......................................................................................................................... 7
5.0 CORROSION SURVEY REPORT ....................................................................................................... 8
5.1 OBJECTIVE OF THE SURVEY ........................................................................................................... 8
5.2 SCOPE OF WORK .............................................................................................................................. 8
5.3 SOIL RESISTIVITY SURVEY .............................................................................................................. 8
5.4 SOIL RESISTIVITY VS. DEGREE OF CORROSIVITY ....................................................................... 9
5.5SOIL SAMPLES................................................................................................................................... 9
5.6 ADDITIONAL DATA COLLECTION ................................................................................................... 11
5.7 SURVEY RESULT ............................................................................................................................. 13
6.0 DESIGN DATA & CRITERIA ............................................................................................................. 13
6.1 INTRODUCTION ................................................................................................................................ 13
6.2 PIPELINE DETAILS ........................................................................................................................... 13
6.3 CATHODIC PROTECTION SYSTEM DESIGN LIFE ........................................................................ 13
6.4 CODES AND STANDARDS .............................................................................................................. 13
6.5 PHILOSOPHY OF CATHODIC PROTECTION SYSTEM ................................................................. 14
6.6 PROTECTION CURRENT DENSITY ................................................................................................ 15
6.7 CATHODIC PROTECTION DESIGN CRITERIA ............................................................................... 15
7.0 DESIGN CALCULATION ................................................................................................................... 16
7.1 TOTAL CURRENT REQUIREMENT ................................................................................................. 16
7.2 CURRENT REQUIREMENT .............................................................................................................. 17
7.3 ANODE WEIGHT REQUIREMENT ................................................................................................... 18
7.4 HORIZONTAL GROUNDBED RESISTANCE ................................................................................... 19
8.0 EHV / HV CROSSINGS ..................................................................................................................... 23
9.0 CATHODIC PROTECTION AT CASED CROSSINGS ...................................................................... 27
9.1CATHODIC PROTECTION FOR CARRIER PIPE ............................................................................ 27
10.0 INSULATION JOINTS ...................................................................................................................... 30
11.0 EARTHING ELECTRODE ............................................................................................................... 30
12.0 POLARISATION COUPONS ........................................................................................................... 31
13.0 REFERENCE CELL ACCESS POINTS........................................................................................... 31
14.0 ER PROBE & READER ................................................................................................................... 31
8/11/2019 Tcp Docs Rkpl
3/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 3 of 113
15.0 TEST STATION ............................................................................................................................... 32
16.0 CABLE LAYING DETAILS ............................................................................................................... 50
17.0 CABLE TO PIPE CONNECTIONS .................................................................................................. 50
18.0 INSTALLATION PROCEDURE ....................................................................................................... 51
18.1 FOR TEST STATION ....................................................................................................................... 51
18.2 FOR SACRIFICIAL ANODES .......................................................................................................... 55
18.3 FOR CABLE LAYING....................................................................................................................... 59
18.4 FOR SURGE DIVERTER ................................................................................................................ 63
18.5 FOR THERMIT WELD ..................................................................................................................... 66
18.6 FOR PIN BRAZING .......................................................................................................................... 71
18.7 FOR POLARISATION CELL ............................................................................................................ 75
18.8 FOR PERMANENT REFERENCE CELL......................................................................................... 78
18.9 FOR POLARISATION COUPON ..................................................................................................... 82
18.10 FOR ZINC RIBBON ANODES ....................................................................................................... 85
18.11 FOR ER PROBE ............................................................................................................................ 88
19.0 INCOMING MATERIAL INSPECTION REPORT ............................................................................ 91
20.0 STANDARD QAP ............................................................................................................................. 92
21.0 RECORD OF CALIBRATION OF MEASURING INSTRUMENTS .................................................. 94
22.0 INTERFERENCE DETECTION AND MITIGATION ........................................................................ 95
22.1 PROCEDURE FOR AC INTERFERENCE SURVEY ...................................................................... 96
22.2 PROCEDURE FOR DC INTERFERENCE SURVEY ...................................................................... 99
23.0 TESTING AND COMMISIONING .................................................................................................. 105
24.0 SYSTEM MONITORING ................................................................................................................ 109
25.0 BILL OF MATERIAL ....................................................................................................................... 111
26.0 REFERENCE DRAWING LIST ..................................................................................................... 113
8/11/2019 Tcp Docs Rkpl
4/113
8/11/2019 Tcp Docs Rkpl
5/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 5 of 113
3.0 ABBREVATIONS
SN Terms Description
1 AnodeAn electrode placed in the electrolyte to apply Cathodic
protection to the structure
2 BackfillLow resistance material surrounding the anode to reduce the
anode to electrolyte resistance
3 Cathode The structure that is to be protected by Cathodic protection
4Cathodic
Protection
The prevention or reduction of corrosion of metal by making the
metal the cathode in a galvanic or electrolytic cell
5 CorrosionThe deterioration of metal caused by its electrochemical reaction
with its environment
6Corrosion
Current
The current flowing in a corrosion cell & which is
electrochemically equivalent to the anode & cathode reactions
7 Current DensityCurrent flowing into the cathode divided by cathode surface
area.
8 ElectrolyteA liquid or the liquid component in a composite material such assoil, in which electric current may flow by ionic charge transfer
9 Instantaneousoff potential
A potential substantially free of voltage gradients
10 PolarizationA change in the potential of a metal from its natural steady state
value as a result of current flow
11Polarized
Potential
The potential value of a metal after polarization reaches the
steady state
12ReferenceElectrode
An electrode that has a stable potential in one or more
electrolytes at a given temperature, thus enabling it to be usedfor the measurement of other reference electrode
13 Structure A metal which has a surface in contact with an electrolyte
14 Dia Diameter
15 Ch Chainage
16 Km Kilometer
17 m Meter
18 mm Millimeter
19 Nos Number
20 V Voltage
8/11/2019 Tcp Docs Rkpl
6/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 6 of 113
SN Terms Description
21 mV Milivolts
21 m2 Square meter
22 mg miligrams
23 Amps Ampere
24 PSP Pipe to Soil potential
25 CPS Cathodic Protection Station
26 HPCL Hindustan Petroleum Corporation Limited
27 KazStroy KSS Petron Private Limited
28 Raychem RPG Raychem RPG Pvt. Ltd.
8/11/2019 Tcp Docs Rkpl
7/113
8/11/2019 Tcp Docs Rkpl
8/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 8 of 113
5.0 CORROSION SURVEY REPORT5.1 OBJECTIVE OF THE SURVEY
The survey aim to generate sufficient data and correlated information which will provide the
basis for designing of cathodic protection system. The same information shall be used as
input parameters with which the C.P. system has to eventually cope with.
The basic data and generated information shall be comprehensively analysied and
interpreted to lay down the guidelines for the C.P. system Design and Engineering.
5.2 SCOPE OF WORK
The Corrosion Survey includes,
Soil Resisitivity survey
Additional data collection to generate design data for evaluation of interaction
possibilities due to presence of other services in ROU.
Soil samples shall be collected on an average for every 10 km along ROU.
5.3 SOIL RESISTIVITY SURVEYThe Soil resistivity measurements have been carried out using 4 pins WENNER method. The
measurements were carried out at pin spacing of 1, 1.5 and 2.5 m.
INSTRUMENT USED FOR THE SURVEYSoil Resistivity meter
Make: Nilsson Electrical Lab, INC. USA/MC Miller USA, NILSSON 400 & Motwane-DET-20
RESISTIVITY CALCULATIONSd = 2 x x a x R
Where:
a = Consecutive distance in cm
R = Resistance measured as indicated by unit in ohms
d = Resistivity (ohm-cm)
8/11/2019 Tcp Docs Rkpl
9/113
8/11/2019 Tcp Docs Rkpl
10/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 10 of 113
Chainage wise chemical analysis report readings are tabulated below:
Sr.No.
Chainage(Km)
Chloride (ppm) Sulphate (ppm) pH (Digital mtr)
1.0 Mtr 2.0 Mtr 1.0 Mtr 2.0 Mtr 1.0 Mtr 2.0 Mtr
1 0 749 649 93 86 7.13 6.95
2 10 949 949 33 17 7.18 7.23
3 20 1199 1449 123 153 6.93 7.48
4 30 200 150 167 93 7.03 7.96
5 40 120 180 123 153 6.93 7.48
6 50 250 210 167 93 7.03 7.96
7 60 135 140 123 153 6.93 7.48
8 70 899 949 167 93 7.03 7.96
9 80 749 899 123 153 6.93 7.48
10 90 300 450 33 27 7.18 7.23
11 100 227 230 123 153 6.93 7.48
12 110 999 1049 18 9 7.4 4.14
13 120 1199 1449 123 153 6.93 7.48
14 130 200 250 167 93 7.03 7.69
15 140 649 699 227 212 7.6 7.5816 150 600 500 19 41 7.01 7.05
17 160 200 150 5 6 8.08 8.03
18 170 250 899 17 95 7.31 7.21
19 180 500 350 123 153 6.93 7.48
20 190 150 150 123 153 6.93 7.48
21 200 250 253 167 93 7.03 7.96
22 210 200 300 123 153 6.93 7.48
23 220 200 250 167 93 7.03 7.96
24 228 699 550 123 153 6.93 7.48
As per the chemical analysis report attached in Annexure A we can conclude the following
points:
The Chloride content was less than 520 PPM.
The Sulphate content was less than 109 PPM.
The pH value varies from 6.93 to 8.8
The soil resistivity report, its graphs and soil samples chemical analysis report and
its graph are attached in Annexure A.
8/11/2019 Tcp Docs Rkpl
11/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 11 of 113
5.6 ADDITIONAL DATA COLLECTIONAdditional data has been collected from Various sources like owner, consultant, contractor,
aligment sheet and from the field survey.
List of Major Road, River & Canal Crossings IN Phase-1 are as follows:
1) RKPL Ph-1 Rewari Dispatch Terminal to SV-4, Ch:228 km:
MAJOR RAILWAY CROSSING
Sr.No.
Chainage(km)
DESCRIPTIONLength Of
Crossing (Km)
1 98.111 RAILWAY XING (NCR) 35
2 141.972 WEASTERN CENTRAL RAILWAY 55
3 158.470 MATHUTA ACHNERA RAILWAY XING 30
4 162.395 CENTRAL RAILWAY CROSSING 47
5 163.213 RAILWAY XING-MATHURA TO FARAH 47
6 164.731 RAILWAY XING-MATHURA TO FARAH 47
7 165.759 RAILWAY XING-MATHURA TO FARAH 47
8 216.534 NORTHAN RAILWAY MAINLINE XING 74
2) RKPL Ph-1 Rewari Dispatch Terminal to SV-4, Ch:228 km:
MAJOR HT LINE CROSSING
Sr. No. Chainage (km) DESCRIPTION
1 2.885 110 KVA HT CROSSING
2 5.151 132 KVA HT LINE CROSSING
3 10.765ASPHALTED ROAD GUJAR MAJARI TO GUJARI & 132 KVA
CROSSING
4 19.774 220 KVA HT LINE XING
5 33.054 220 KVA HT LINE XING NEAR BRICK KILN
6 34.248 220 KVA HT XING
7 34.850 110 KVA HT CROSSING, NEAR CHAMBORDA VILLAGE
8 63.010 400 KVA HT LINE XING
9 134.851 220KVA LINE XING NEAR ASPHALTED ROAD
8/11/2019 Tcp Docs Rkpl
12/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 12 of 113
MAJOR HT LINE CROSSING
Sr. No. Chainage (km) DESCRIPTION
10 145.049 400KV HT LINE XING
11 158.270 400 KV HT LINE XING
12 166.385 440KVA HT LINE XING
13 177.354 220KV HT XING NEAR KHADERA VILLAGE
14 197.417 400 KVA HT LINE XING
15 199.079 200 KV HT LINE XING
16 201.754 220 KVA HT LINE XING17 217.007 400KVA HT XING, NEAR GOWAL VILLAGE
3) RKPL Ph-1 Rewari Dispatch Terminal to SV-4, Ch:228 km:
MAJOR ROAD CROSSING
Sr. No. Chainage (km) Crossing
1 0.577 NH-71
2 3.387 NH-08
3 4.018 NATIONAL HIGHWAY JAIPUR-DELHI
4 33.876 STATE HIGHWAY-25
5 62.608 SH-35 XING
6 82.564 SH-45
7 92.680 STATE HIGHWAY-22
8 99.961 SH-14 XING
9 122.770 STATE HIGHWAY-14
10 136.215 STATE HIGHWAY-43
11 140.377 STATE HIGHWAY-24
12 161.957 NH-02 Farah To Mathura
13 226.000 STATE HIGHWAY-31
8/11/2019 Tcp Docs Rkpl
13/113
8/11/2019 Tcp Docs Rkpl
14/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 14 of 113
NACE RP-10A190 Measurement technique related to criteria for CP of Undergroundor Submerged steel piping system
NACE RP-0177 Recommended Practice Mitigation of AC and Lighting Effects
on Metallic Structures and Corrosion Control Systems
NACE No. 54276 Cathodic Protection Monitoring For Buried Pipelines
NACE RP-0572 Recommended Practice Design, Installation, Operation and of
Impressed Current Deep Ground Beds
DNV RP-B403 Recommended Practice Monitoring of CP System
DNV RP-B401 Recommended Practice Cathodic Protection Design
IS 8062 Recommended Practice ICCP for Underground Pipe
VDE 0150 Protection against Corrosion due to stray current from DC
Installation
IS: 1554 Part1 PVC insulated (Heavy Duty) Cables.
BS:7361 Part I Code of Practice for Cathodic Protection for Land and
Marine applications
6.5 PHILOSOPHY OF CATHODIC PROTECTION SYSTEMAs provided in the enquiry specifications, the cathodic protection system shall be a Galvanic/
Sacrificial Anodes system and shall be designed using pre-packed Magnesium anodes. The
prepacked Magnesium anodes shall be installed in a horizontal configuration in a trench of
depth 2 M. to ensure that it reach moist soil and it should be 2 to 5 M. away from the edge of
pipeline.Considering Minimum 2 Nos. of 2.5 Kg prepacked magnesium anode for soil
resistivity upto 90 ohm-M. and Minimum 3 Nos. of 2.5 Kg prepacked magnesium anode for
soil resistivity above 90 ohm-M. and upto 110 ohm-M.,for carrier pipe protection along the
pipeline route at every 1 km interval. However any unprotected Pipeline area is observedduring construction the same shall be protected by providing additional anodes.
8/11/2019 Tcp Docs Rkpl
15/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 15 of 113
6.6 PROTECTION CURRENT DENSITYThe Pipeline is coated with 3 layer PE Coating and the minimum protective current density for
Temporary Cathodic Protection system as per the Specification no: MH2145-C000-EL-SPC-
0025 RevA is as given below.
Pipeline SurroundingMinimum Protection
Current Density (mA / m2)
Soil Resistivity < 10 ohm-m 0.075
Soil Resistivity 10 ohm-m to 100 ohm-m 0.055
Soil Resistivity > 100 ohm-m 0.035
A safety margin of 1.3 i.e. 30% has been provided for in the current calculations over and
above the specified protective current density.
Soil Resistivity in phase 1 of RKPL is in the range of 10 ohm-m to 100 ohm-m, The Average
soil resistivity at 2 m depth is 22.23 ohms-m in Phase1 of RKPL, hence current density of
0.055 mA / m2 is considered.
6.7 CATHODIC PROTECTION DESIGN CRITERIA
Cathodic Protection system shall be designed to meet the following any one of the criteria: The pipe to Soil Potential measurements shall be in between (-) 0. 95 V ON to (-) 1.5
V ON as measured between the pipe surface and a saturated copper - copper sulfate
reference electrode.
The pipe to Soil Potential measurements shall be in between (-) 0. 95 V (IR Free) to (-)
1.18 V (IR Free) as measured between the pipe surface and a saturated copper -
copper sulfate reference electrode.
A positive potential swing of 100 mV or more shall be considered as the criteria for
presence of an interaction / interference situation requiring investigation and
incorporation of mitigation measures.
8/11/2019 Tcp Docs Rkpl
16/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 16 of 113
7.0 DESIGN CALCULATIONThe following calculations have been used to design the Temporary Cathodic Protection
system.
7.1 TOTAL CURRENT REQUIREMENT
Surface Area
Where:Sa =Surface area of Pipeline (m
2)
D = Diameter of pipeline (m)
L = Length of pipeline (m)
The surface area calculations are tabulated as under:
Pipeline SectionDia.(m)
PipelineLength (m)
CoatingSurface
Area (m2)
Rewari Dispatch terminal to SV-
6(Ch:228 km)0.457 228000 3LPE 327341.3
8/11/2019 Tcp Docs Rkpl
17/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 17 of 113
7.2 CURRENT REQUIREMENT
The Pipeline is coated with 3 layer PE Coating and the current density considered for the
Temporary Cathodic Protection design is 0.055 mA / m2
Based on the above current density, the total current requirement as per soil resistivity span is
calculated as follows:
WhereIt = C.P. current requirement (Amp)
Sa = Surface area of Pipeline (m2)
Cd= C.P. protective current density (mA/m2)
1.3 = Safety Margin
ChainageSpan
Soilresistivity(Ohms-m)
Dia(m)
PipelineLength (m)
SurfaceArea (m2)
ProtectiveCurrent Density
(mA/ m2)
CurrentRequired(Amp.)
Rewari Dispatch terminal to SV-6(Ch:228 km)
.00-228 Km 22.23 0.457 228000 327341.3 0.055 23.40
8/11/2019 Tcp Docs Rkpl
18/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 18 of 113
7.3 ANODE WEIGHT REQUIREMENTThe total anode weight requirement is calculated using the following formula:
Where
Wt= Total Anode Weight (Kg.)
It = C.P. current requirement (Amps)
Ct=Consumption Rate of Anode (7.9 Kg/Amp-Year)
L = Design Life (2 years)
Uf= Anode Utilisation factor (0.85)
PipelineSection
Individual
AnodeWeight
(Kgs) (W)
Total
Current(Amp)
(It)
Total Anode
Requirement(Kgs)(Wt)
Total Anode
Requirement(Nos)(Na)
Total No.
of AnodeProposed
(Nos)
Rewari Dispatch terminalto SV-6(Ch:228 km)
2.5 23.40 434.96 174 458
8/11/2019 Tcp Docs Rkpl
19/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 19 of 113
7.4 HORIZONTAL GROUNDBED RESISTANCEa) Resistance of Single horizontal anode
Where:
Rah= Resistance of Single horizontal anode
Ps = Soil Resistivity in (5 ohm-m)
L= Length of prepackaged anode in (1.5 m)
d = diameter of prepackaged anode in (0.15 m)
t = Depth of Anode in (2 m)
Rah = 1.068 ohms
b) Resistance of multiple horizontal
Where
Rgbh= Resistance of multiple horizontal anodes in (ohms)
Rah = Resistivity of single horizontal anode in (1.068 ohms)
N = Number of anodes (2 Nos.)
F = Crowding Factor (1.134)
Rgbh=0.606 ohms
c) Crowing Factor
Where:
F = Crowding Factor
Rah= Resistance of Single horizontal anodes (1.068 ohms)
Ps = Soil Resistivity in (5 ohm-mtr.)
S = End to End spacing of Anode (3 mtr.)
N = Number of Anodes (2 Nos.)
F=1.134
8/11/2019 Tcp Docs Rkpl
20/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 20 of 113
d) Cable ResistanceFor the ground bed using 1 horizontal anode, the longest anode tail cable of 9 m ofPVC/PVC
single core copper conductor 6mm2cable shall be used.
The cable resistance of copper conductor single core 6 mm2size is 3.08 ohm/Km.
Therefore the cable resistance for 1 No. Anode tail cables of 9 mtr. Length shall be,
Where:
RC = Total Cable Resistance (ohms)
Ra = Cable Resistance (0.00308 ohm-m)
L = Length of the Cable (9 m)
N = Number of anodes (2 Nos.)
RC = 0.0139 ohms
e) Total Circuit Resistance
The total circuit resistance for each anode bed
Where:
Rt = Total circuit resistance (ohms)
Rgbh= Resistance of multiple horizontal anodes (0.606 ohms)
RC = Total Cable Resistance (0.0139 ohms)
Rt= 0.620 ohms
f) The current output at each ground bed
Where:
I= Current Output per anode bed (Amps.)
V= Driving potential for Mg anodes with line polarized is
=1.55 - 0.95 = 0.6 V
Rt= Total circuit resistance (0.620 ohms)
I=0.967 Amps
8/11/2019 Tcp Docs Rkpl
21/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 21 of 113
Pipeline Coverage by Anodes at various Soil Resistivities for RKPL is as below:
Soil Resistivityrange Ohm-m
Using 2Nos of MG anode Using 3Nos of MG anode
Total Circuit
Resistance
CurrentO/P of
Anode(Amps)
KMCoverageof Pipeline
Total Circuit
Resistance
CurrentO/P of
Anode(Amps)
KMCoverageof Pipeline
1 0.135 4.439 43.26 0.104 5.74 55.98
1-3 0.377 1.58 15.48 0.294 2.034 19.83
3-5 0.620 0.967 9.42 0.485 1.23 12.05
5-8 0.984 0.610 5.94 0.771 0.778 7.59
8-10 1.227 0.489 4.77 0.961 0.624 6.08
10-15 1.833 0.327 3.19 1.43 0.417 4.07
15-20 2.44 0.246 2.40 1.91 0.314 3.06
20-25 3.04 0.197 1.92 2.389 0.251 2.45
25-30 3.65 0.164 1.60 2.86 0.209 2.04
30-35 4.25 0.141 1.37 3.34 0.180 1.75
35-40 4.86 0.123 1.20 3.81 0.157 1.53
40-50 6.07 0.099 0.96 4.77 0.126 1.23
50-60 7.29 0.082 0.80 5.722 0.105 1.02
Hence, The anode ground bed locations and the number of anodes to be used for each location
has been decided considering 2 Nos. of 2.5 Kg prepacked magnesium anode for soil resistivity
upto 90 ohm-m. and 3 Nos. of 2.5 Kg prpacked magnesium anode for soil resistivity above 90
ohm-m and upto 110 ohm-m, for carrier pipe protection along the pipeline route at every 1
km interval.
However any unprotected pipeline area is obsreved during construction time, The same shall
be protected by providing additional anodes.
R-1
8/11/2019 Tcp Docs Rkpl
22/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 22 of 113
The ground bed details are mentioned in the enclosed Schedule. The actual chainages mayvary as per actual site conditions at the time of selection of locations during installation.
8/11/2019 Tcp Docs Rkpl
23/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 23 of 113
8.0 EHV / HV CROSSINGSZinc earthing anode & polarization cell shall be provided as per Project Specification MH2145-
C000-EL-SPC-0025 RevA.
For earthing of pipeline at the 66KV and above HT Line crossings, at 1 km interval of parallel
run (if horizontal distance of HT line is within 25 m. of the pipeline) and at the departure
points from the parallel run for earthing purpose Zinc ribbon anode so that the earthing
resistance is restricted within acceptable limit of 5 ohm.
The total meter of Zinc ribbon anode proposed (Size 12.7 X 14.28 mm) = 110 m
Sample calculation of resistance of Horizontal anode bed for Zinc Ribbon anode:
Where:
Rb= Anode to Earth resistance (ohm)
Ps = Soil Resistivity in ohm-M (2.885 ohm-m)
L = Length of prepackaged anode in m (3 m)
D = Diameter of prepackaged anode in m (0.15 m)
S = Twice the Depth of Anode (4 m)
Rb=2.425 ohms
ii) Resistance of the anode to backfill:
Where:Rbs = Resistance of anode to backfill in ohms (ohms)
Ps = Resistivity of backfill material (0.5 ohm-m)
L = Length of anode in m (3 m)
d = Effective diameter of anode in m (0.0151 m)
Rbs=0.108 ohms
8/11/2019 Tcp Docs Rkpl
24/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 24 of 113
iii) Cable resistance:For the groundbed using 1 Zinc Ribbon anode of 10 m. Length, the anode tail cable of 8 m.
Of PVC/PVC single core copper conductor 25 mm2cable shall be used.
The cable resistance of copper conductor single core 25 mm2size is 0.727 ohm/Km.
Therefore, the cable resistance for 1 No. anode tail cables of 8 m. Length shall be calculated
as follow:
Where:
RC = Total Cable Resistance (ohms)
Ra = Cable Resistance (0.000727 ohm-m)
L = Length of the Cable (8 m)
Rc=0.0058 ohms
iv) Total circuit resistance:
Where:
RT= Total circuit resistance (ohms)
Rb= Resistance of horizontal anode to electrolyte (2.425 ohms)
Rbs= Resistance of Anode to backfill (0.108 ohms)
RC= Cable Resistance (0.0058 ohms)
N = Number of Anodes (2 No)
RT=1.270 ohms
R-1
8/11/2019 Tcp Docs Rkpl
25/113
8/11/2019 Tcp Docs Rkpl
26/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 26 of 113
Detail calculation for zinc grounding anode for HT Line Xings are tabulated below:
SNChainage
(km)
SoilResistivity (Ohm-
M)
No. ofAnode
s (Zn)
Lengthof thePre-
Packe
dAnode
(Mt)
AnodeDia
(mt)
Lengthof
Bare
Anode(mt)
Dia ofBare
Anode(mt)
Twicethe
Depth
ofAnode
Anode toearth
Resistance (ohm
Anode tobackfill
Resistance (ohms)
CableResistanc
e (ohms)
Totalcircuit
Resistance
No of Zinc
anode
Totalweigh
t of
Anode
Polarisation cell(Solid
State-5.0KA)
N L D l d S Rb Rbs Rc RT Nos (Kg) Nos
1 2.885 12.230 2 3 0.150 3 0.151 4.0 2.425 0.108 0.0058 1.270 3mtr x 2Nos 5.1 1
2 5.151 64.995 2 5 0.150 5 0.151 4.0 9.218 0.073 0.0058 4.648 5mtr x 2Nos 8.5 1
3 10.765 32.905 2 3 0.150 3 0.151 4.0 6.526 0.108 0.0058 3.320 3mtr x 2Nos 5.1 1
4 19.774 31.870 2 3 0.150 3 0.151 4.0 6.320 0.108 0.0058 3.217 3mtr x 2Nos 5.1 15 33.054 26.875 2 3 0.150 3 0.151 4.0 5.330 0.108 0.0058 2.722 3mtr x 2Nos 5.1 1
6 34.248 19.310 2 3 0.150 3 0.151 4.0 3.830 0.108 0.0058 1.972 3mtr x 2Nos 5.1 1
7 34.850 27.315 2 3 0.150 3 0.151 4.0 5.417 0.108 0.0058 2.765 3mtr x 2Nos 5.1 1
8 63.010 51.855 2 5 0.150 5 0.151 4.0 7.354 0.073 0.0058 3.716 5mtr x 2Nos 8.5 1
9 134.851 20.515 2 3 0.150 3 0.151 4.0 4.068 0.108 0.0058 2.091 3mtr x 2Nos 5.1 1
10 145.049 15.840 2 3 0.150 3 0.151 4.0 3.141 0.108 0.0058 1.627 3mtr x 2Nos 5.1 1
11 158.270 19.090 2 3 0.150 3 0.151 4.0 3.786 0.108 0.0058 1.950 3mtr x 2Nos 5.1 1
12 166.385 13.655 2 3 0.150 3 0.151 4.0 2.708 0.108 0.0058 1.411 3mtr x 2Nos 5.1 1
13 177.354 8.895 2 3 0.150 3 0.151 4.0 1.764 0.108 0.0058 0.939 3mtr x 2Nos 5.1 114 197.417 18.550 2 3 0.150 3 0.151 4.0 3.679 0.108 0.0058 1.896 3mtr x 2Nos 5.1 1
15 199.079 25.900 2 3 0.150 3 0.151 4.0 5.136 0.108 0.0058 2.625 3mtr x 2Nos 5.1 1
16 201.754 24.565 2 3 0.150 3 0.151 4.0 4.872 0.108 0.0058 2.493 3mtr x 2Nos 5.1 1
17 217.007 9.370 2 3 0.150 3 0.151 4.0 1.858 0.108 0.0058 0.986 3mtr x 2Nos 5.1 1
Total Length of Zinc Ribbon anode=110Mtrs
-
8/11/2019 Tcp Docs Rkpl
27/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 27 of 113
9.0 CATHODIC PROTECTION AT CASED CROSSINGSAs per specification no MH2145-C000-EL-SPC-0025 RevA, Cathodic protection to casing shall
be provided if casing is coated. In This project all cased crossing are uncoated, therefore
additional protection is not Provided.
9.1 CATHODIC PROTECTION FOR CARRIER PIPE
Carrier pipe inside casing shall be protected by Zinc ribbon anodes well connected to the
outer surface of bottom of carrier pipe extending between hour hand positions of 4 and 8 o
clock. The anodes shall be placed at close intervals as per design calculations and sized
based on the permanent CP design parameters for 35 years.
The calculations are as below,
i)Surface Area
Where:
Sa =Surface area of Pipeline(m2)
D = Diameter of pipeline (m)
L = Length of pipeline (m)
ii) Current requirement
Where:
It = Current requirement (Amps)
Sa =Surface area of Pipeline(m2)
Cd = CP protective current density (mA/m2)
1.3 = Safety factor
8/11/2019 Tcp Docs Rkpl
28/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 28 of 113
The surface area & current requirement calculations are tabulated as under:
Chainage(km)
Dia.(m)
PipelineLength (m.)
Surface Area(m2)
CurrentDensity (mA/m2)
Current Required(Amps)
0.577 0.457 27 38.76 0.055 0.0028
3.387 0.457 74 106.24 0.055 0.0076
10.747 0.457 18 25.84 0.055 0.0018
22.865 0.457 18 25.84 0.055 0.0018
33.876 0.457 25 35.89 0.055 0.0026
62.608 0.457 32 45.94 0.055 0.0033
82.564 0.457 14 20.10 0.055 0.0014
92.680 0.457 20 28.71 0.055 0.0021
98.076 0.457 35 50.25 0.055 0.0036
99.961 0.457 22 31.59 0.055 0.0023
122.770 0.457 17 24.41 0.055 0.0017
127.241 0.457 16 22.97 0.055 0.0016
136.215 0.457 22 31.59 0.055 0.0023
140.377 0.457 36 51.69 0.055 0.0037
141.917 0.457 55 78.96 0.055 0.0056
158.440 0.457 30 43.07 0.055 0.0031
161.957 0.457 30 43.07 0.055 0.0031
162.348 0.457 47 67.48 0.055 0.0048
163.166 0.457 47 67.48 0.055 0.0048
164.684 0.457 47 67.48 0.055 0.0048
165.712 0.457 47 67.48 0.055 0.0048
216.460 0.457 74 106.24 0.055 0.0076
226.000 0.457 29 41.64 0.055 0.0030
8/11/2019 Tcp Docs Rkpl
29/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 29 of 113
iii) Anode required by weight
Where:
Wt = Weight of anode required (kg)
It = Current requirement (Amps)
Ct =Consumption rate of anode(11.24 Kg/Amp-Year)
L = Design Life (35 years)
Uf = Anode Utilisation factor (0.5)
Type of anode: Zinc Ribbon Anode
Totalcurrentrequired(Amps)
AnodeWeight as per
design (Kgs)
WeightOf Anode
per mtr.
Total Length ofAnode required as
per design (m)
Individual lengthof Anode proposed(Between 2 spacer)
(m)
Total Length of Ribbonproposed considering
1no zinc ribbon inbetween 2 spacer (m)
0.0028 2.18 0.850 2.57 0.48 6.46
0.0076 5.98 0.850 7.03 0.48 17.71
0.0018 1.45 0.850 1.71 0.48 4.31
0.0018 1.45 0.850 1.71 0.48 4.310.0026 2.02 0.850 2.38 0.48 5.98
0.0033 2.58 0.850 3.04 0.48 7.66
0.0014 1.13 0.850 1.33 0.48 3.35
0.0021 1.62 0.850 1.90 0.48 4.79
0.0036 2.83 0.850 3.33 0.48 8.37
0.0023 1.78 0.850 2.09 0.48 5.26
0.0017 1.37 0.850 1.62 0.48 4.07
0.0016 1.29 0.850 1.52 0.48 3.83
0.0023 1.78 0.850 2.09 0.48 5.26
0.0037 2.91 0.850 3.42 0.48 8.61
0.0056 4.44 0.850 5.23 0.48 13.16
0.0031 2.42 0.850 2.85 0.48 7.18
0.0031 2.42 0.850 2.85 0.48 7.18
0.0048 3.80 0.850 4.47 0.48 11.25
0.0048 3.80 0.850 4.47 0.48 11.25
0.0048 3.80 0.850 4.47 0.48 11.25
0.0048 3.80 0.850 4.47 0.48 11.25
0.0076 5.98 0.850 7.03 0.48 17.71
0.0030 2.34 0.850 2.76 0.48 6.94
Total 187.12
8/11/2019 Tcp Docs Rkpl
30/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 30 of 113
10.0 INSULATION JOINTSThe Surge Diverter Flame Proof type shall be connected across each Isolation Joints.
The proposed locations of IJ are as follows:
Sr.No.
Pipeline SectionChainage
(Km)Location
Qty(Nos.)
1
RKPL-Phase I
00 Rewari Dispatch Terminal 1
2 141.80 Bharatpur Terminal Receiver Side 1
3 141.80 Bharatpur Terminal Launcher Side 1
4 164.378 Mathura Terminal Receiver Side 1
5 164.378 Mathura Terminal Launcher Side 1
11.0 EARTHING ELECTRODE
The above ground unprotected portion of the pipeline at the pipeline terminal and
intermediate station shall be earthed through earthing system consisting of earth electrodes
and earthing conductor. All flanges on unprotected pipe shall be shorted with 25 Sq. mm
copper cables.The resistance of grounding shall be limited to 5 ohms.
The motor operated valves located on cathodically protected pipeline shall be separately
grounded with the help of 20kg zinc anode.
8/11/2019 Tcp Docs Rkpl
31/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 31 of 113
12.0 POLARISATION COUPONSThe Polarisation coupons of pipeline material shall be provided along the pipeline to monitor
the adequacy of the cathodic protection. The Polarisation coupon shall be made as per
drawing no 06-10-1403-PCC & specification MH2145-C000-EL-SPC-0025 RevA
The coupon shall be installed as per table given below:
RKPL Ph-1 Pipeline Section:
Sr.
No.
Chainage
(Km)Location
Test Station
Type
Qty
(Nos.)
1 5.151 132 KVA HT LINE CROSSING ML 1
2 158.270 400 KV HT LINE XING ML 1
13.0 REFERENCE CELL ACCESS POINTS
Reference cell access points shall be provided near insulating joint locations at SV stations
where the ground is paved, for measurement of pipe to soil potentials. A perforated PVC
pipe filled with native soil and buried at the location shall be provided for measurement
purpose. The length of the PVC pipe shall be adequate to reach the native soil below the
paving.
14.0 ER PROBE & READER
Electrical Resistance Probe and Reader shall be provided along the pipeline ROU for
monitoring the rate of metal loss due to corrosion. The ER Probes shall be implemented for
external corrosion monitoring. The lead wires of the probe shall be connected to pipeline
through test station and terminated inside test station enabling periodic resistancemeasurement of the probe using a portable probe-measuring instrument.
The material of the E/R probe element shall be of same alloy as of the pipeline material.
Probe shall be provided preferably at the bottom portion of pipeline.
2 Nos ER Probe shall be considered with 2 Nos. Of Reader for pipeline in Phase I.
The location for installation of ER probe has been proposed, however exact location shall be
decided at site after post commissioning survey in consultation with consultant/owner.
The Proposed location of ER probe is as below:
8/11/2019 Tcp Docs Rkpl
32/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 32 of 113
RKPL Ph-1 Pipeline Section:
SNChainage
(Km)Location
Test StationType
Qty (Nos.)
1 33.054 220 KVA HT LINE XING NEAR BRICK KILN M 1
2 217.007 400KVA HT XING, NEAR GOWAL VILLAGE ML 1
15.0 TEST STATION
Test Station shall be provided along the pipeline ROU for monitoring the performance of the
Cathodic protection system at an interval of about 1000 m in inhabited areas and 2000 m in
Un-inhabited areas such as forests / deserts etc.
In addition to the above Test Stations shall be provided at the following points,
At the locations of Anode ground beds.
At all Insulation Joints.
At vulnerable locations with drastic changes in Soil Resistivity.
At locations of Surge diverters, Polarisation Coupons, pipeline grounding through
polarization cells, Zinc & Mg Anodes.
At EHV/HV AC/DC overhead line crossings and selected locations where EHV/HV
overhead lines are in the vicinity of the pipeline.
At Railway Line crossing and at selected location along lines running parallel to
pipeline.
At both sides of major river crossings.
At EHV/HV cable crossings or along routes where EHV/HV cables are running in
parallel.
In the vicinity of DC network or grounding systems and HVDC grounding systems
where interference problems are suspected. At crossing of other pipelines / structures
At the Location of Reference cell and ER Probe Installation.
At both sides of Cased crossings.
Locations where interference is expected.
At locations of Sectionalizing Valves (SV) Stations.
At any other locations considered necessary by Owner/Owners Representative.
8/11/2019 Tcp Docs Rkpl
33/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 33 of 113
Test Station Connection Scheme as given below:
Purpose Type
Pipe to soil potential measurement A
Pipe to soil potential measurement with Galvanic Anode Connection AL
Line Current measurement B
Line Current measurement with Galvanic Anode Connection BL
Isolating Joint, Line Current measurement with Galvanic Anode Connection BFL
Cased crossing with uncoated casing C
Uncoated cased crossing with Galvanic Anode Connection CL
Cased crossing with coated casing D
coated cased crossing with Galvanic Anode Connection DL
Insulating Joint F
Intermediate CP station impressed current drainage point. G
Intermediate CP station impressed current drainage point with galvanic anodeconnection.
GL
Intermediate CP station impressed current drainage point with Insulating Jointand galvanic anode connection.
GFL
Foreign pipeline crossing E
Foreign pipeline crossing with Galvanic Anode Connection EL
HT Line crossings Grounding Through Polarisation Cell and Zinc ribbon anode M
HT Line crossings Grounding Through Polarisation Cell, Zinc ribbon anode withGalvanic Anode Connection
ML
HT line crossing & cased crossing with uncoated casing CM
HT line crossing & cased crossing with coated casing DM
HT Line crossings Grounding Through Polarisation Cell, Zinc ribbon anode &foreign pipeline crossing
ME
Cased Crossing with uncoated casing & foreign pipeline crossing CE
8/11/2019 Tcp Docs Rkpl
34/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 34 of 113
Cased Crossing with coated casing & foreign pipeline crossing DE
HT Line crossings Grounding Through Polarisation Cell and Zinc ribbon anode
& Foreign pipeline crossing with Galvanic Anode ConnectionMEL
Coated cased crossing with HT Line crossings Grounding Through PolarisationCell, Zinc ribbon anode with Galvanic Anode Connection
DML
Un-Coated cased crossing with HT Line crossings Grounding ThroughPolarisation Cell, Zinc ribbon anode with Galvanic Anode Connection
CML
Test Station installation chainage & types are mentioned in the schedule. All the chainage are
indicative only. The test stations shall be installed as per the actual details like HT Line/
Pipeline crossings, cased crossings, MOV etc., at site during actual execution of the job.
8/11/2019 Tcp Docs Rkpl
35/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 35 of 113
1) The Schedule of Test stations for RKPL Ph-1 are as follows:
SN LocationChainage
(km)
Test
StationType
(TS)
CPStatio
n SizeTest
station(ICTS)
(Nos.)
NormalSize
Teststation
(TS)(Nos.)
Polcell
SizeTest
Station(PCTS)
(Nos.)
CTSUSize
TestStation
(CTS)(Nos.)
Perman
ent Ref.Cell
CuCuSo4 (Nos)
Mg
Anode(2.5KG)
(Nos.)
Mg
Anode(10KG)
(Nos.)
Bare ZnRibbon
Anodefor HTLine
crossing
(m.)
ZN
Anode(20KG)
(Nos.)
Polarisa
tion cell(solidstate)(Nos.)
Polaris
ationCoupon
(Nos.)
ERprobe(Nos.)
1 HPCL Rewari Terminal 0.000 GFL 1 2 2 1
2 NH-71 0.577 C 1
3 NH-71 0.604 C 1
4 IN FIELD 1.000 AL 1 2
5 KARNAWAS TO DODHI ROAD XING 2.000 AL 1 2
6 110 KVA HT CROSSING 2.885 M 1 4 1
7 IN FIELD 3.000 AL 1 2
8 NH-08 3.387 C 1
9 NH-08 3.461 C 1
10 NATIONAL HIGHWAY JAIPUR-DELHI 4.018 AL 1 3
11 132 KVA HT LINE CROSSING 5.151 ML 1 1 3 24 1 1
12 IN FIELD NEAR DHANI VILLAGE 6.151 AL 1 3
13 KHERIMOLTA DISTRIBUTORY 7.167 AL 1 2
14 IN FIELD 8.167 AL 1 2
15 IN FIELD 9.167 AL 1 2
16 NEAR GUJRAS CART TRACK 10.000 AL 1 2
17ASPHALTED ROAD GUJAR MAJARI
TO GUJARI10.747 C 1
19HPCL PIPELINE CROSSING, NEAR
GUJARI BUS11.851 EL 1 2
8/11/2019 Tcp Docs Rkpl
36/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 36 of 113
SN LocationChainage
(km)
TestStation Type(TS)
CPStation SizeTest
station
(ICTS)(Nos.)
NormalSizeTest
station(TS)
(Nos.)
PolcellSizeTest
Station
(PCTS)(Nos.)
CTSUSizeTest
Station(CTS)
(Nos.)
Permanent Ref.
Cell
CuCuSo
4 (Nos)
MgAnode(2.5
KG)
(Nos.)
MgAnode
(10
KG)
(Nos.)
Bare ZnRibbonAnodefor HT
Line
crossing(m.)
ZNAnode
(20
KG)
(Nos.)
Polarisation cell(solid
state)
(Nos.)
Polarisation
Coupon(Nos.)
ERprobe
(Nos.)
20 IN FIELD 12.851 AL 1 2
21 CART TRACK JAKAPUR BHAGANA 13.778 AL 1 2
22 IN FIELD 14.778 AL 1 2
23 IN FIELD 15.778 AL 1 2
24 IN FIELD 16.778 AL 1 2
25 IN FIELD 17.778 BL 1 1 2
26 NEAR SAHIBI RIVER 18.691 AL 1 3
27 220 KVA HT LINE XING 19.774 ML 1 2 8 1
28 IN FIELD 20.774 AL 1 2
29 IN FIELD 21.774 AL 1 2
30 MAJOR DISTRICT ROAD XING-61 22.865 CL 1 3
31 MAJOR DISTRICT ROAD XING-61 22.883 C 1
32 CART TRACK JAKAPUR BHAGANA 23.883 AL 1 2
33IN FIELD NEAR PUR VILLAGE &
BHADUKA24.883 AL 1 2
34 IN FIELD 25.883 AL 1 2
35 IN FIELD NEAR KASWAR VILAGE 26.883 AL 1 2
36 NEAR NALLAH XING 27.883 AL 1 2
37 HPCL PIPELINE CROSSING, NEAR 28.754 EL 1 2
38 IN FIELD 29.754 AL 1 2
39 IN FIELD 30.754 AL 1 2
R-1
-
8/11/2019 Tcp Docs Rkpl
37/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 37 of 113
SN LocationChainage
(km)
Test
Station Type(TS)
CPStatio
n SizeTest
station(ICTS)
(Nos.)
NormalSize
Teststation
(TS)
(Nos.)
Polcell
SizeTest
Station(PCTS)
(Nos.)
CTSUSize
TestStation(CTS)
(Nos.)
Perman
ent Ref.Cell
CuCuSo4 (Nos)
Mg
Anode(2.5KG)
(Nos.)
Mg
Anode(10KG)
(Nos.)
Bare ZnRibbon
Anodefor HTLine
crossing
(m.)
ZN
Anode(20KG)
(Nos.)
Polarisa
tion cell(solidstate)(Nos.)
Polarisa
tionCoupon(Nos.)
ERprobe(Nos.)
40 IN FIELD AFTER METALLED ROAD 31.754 AL 1 2
41 IN FIELD 32.754 AL 1 2
42220 KVA HT LINE XING NEAR BRICK
KILN33.054 M 1 1 6 1 1
43 STATE HIGHWAY-25 33.876 CL 1 2
44 STATE HIGHWAY-25 33.901 C 1
45 220 KVA HT XING 34.248 M 1 4 1
46110 KVA HT CROSSING, NEAR
CHAMBORDA VILLAGE34.850 M 1 6 1
47 SV-1 34.913 GL 1 2 2 1
48 IN FIELD 35.913 AL 1 2
49 IN FIELD 36.913 AL 1 2
50 IN FIELD 37.913 AL 1 2
51IN FIELD NEAR BAMBREADY
VILLAGE38.913 AL 1 2
52 IN FIELD NEAR MANDPUR VILLAGE 39.913 AL 1 2
53IN FIELD BEFOR MANPUR VILLAGE
RD40.913 AL 1 2
54 NEAR DHAMUKAD VILLAGE 41.913 AL 1 2
55 DHAMUKAD VILLAGE NER MASJID 42.913 AL 1 2
56 DHAMUKAD VILLAGE 43.913 AL 1 2
57 IN FIELD NEAR CHACHARA VILLAGE 44.913 AL 1 2
58 IN FIELD NEAR BAGODA VILLAGE 45.913 AL 1 2
59IN FIELD NEAR BAYADIWAS 7
JHAMPADIWAS VILLAGE46.913 BL 1 1 2
8/11/2019 Tcp Docs Rkpl
38/113
8/11/2019 Tcp Docs Rkpl
39/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 39 of 113
SN LocationChainage
(km)
TestStationType(TS)
CPStation SizeTest
station
(ICTS)(Nos.)
NormalSizeTest
station(TS)
(Nos.)
PolcellSizeTest
Station
(PCTS)(Nos.)
CTSUSizeTest
Station(CTS)
(Nos.)
Permanent Ref.
Cell
CuCuSo
4 (Nos)
MgAnode(2.5
KG)
(Nos.)
MgAnode
(10
KG)
(Nos.)
Bare ZnRibbonAnodefor HT
Line
crossing(m.)
ZNAnode
(20
KG)
(Nos.)
Polarisation cell(solid
state)
(Nos.)
Polarisation
Coupon(Nos.)
ERprobe
(Nos.)
80 IN FIELD NEAR TIKRI VILLAGE 66.022 AL 1 2
81ASPHALTED RD XING, NEAR
SHERPUR VILLAGE67.008 AL 1 2
82 IN FIELD NEAR SUNERA VILLAGE 68.022 AL 1 2
83IN FIELD NEAR BORE WELL &
SUNERA VILLAGE69.022 AL 1 2
84 IN FIELD NEAR RAWAKA VILLAGE 70.022 AL 1 2
85ASPHALTED ROAD, NEAR RAWAKA
VILLAGE71.128 AL 1 2
86 IN FIELD NEAR INDPWARA VILLAGE 72.128 AL 1 2
87CART TRACK NEAR INDPWARA
VILLAGE73.128 AL 1 2
88ASPHALTED ROAD, NEAR SHERPURA
VILLAGE74.235 AL 1 2
89NEAR ASPHATED RD XING
(JOTHPUR-SHERPUR)75.165 AL 1 2
90 IN FIELD DAYANA KAWAS VILLAGE 76.165 BL 1 1 2
91IN FIELD DAYANA KAWAS VILLAGE
AFETR METALICA RD XING77.165 AL 1 2
92 METEL ROAD, KHELI VILLAGE 78.087 AL 1 2
93 IN FIELD KHELI VILLAGE 79.165 AL 1 2
94 METEL ROAD, KHELI VILLAGE 80.129 AL 1 2
95 RUPARE RIVER 80.522 B 1 1 2
96 RUPARE RIVER 80.742 B 1 2
8/11/2019 Tcp Docs Rkpl
40/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 40 of 113
SN
LocationChainage
(km)
Test
StationType(TS)
CPStatio
n SizeTest
station(ICTS)
(Nos.)
NormalSize
Teststation
(TS)
(Nos.)
Polcell
SizeTest
Station(PCTS)
(Nos.)
CTSUSize
TestStation(CTS)
(Nos.)
Perman
ent Ref.Cell
CuCuSo4 (Nos)
Mg
Anode(2.5KG)
(Nos.)
Mg
Anode(10KG)
(Nos.)
Bare ZnRibbon
Anodefor HTLine
crossing
(m.)
ZN
Anode(20KG)
(Nos.)
Polarisa
tion cell(solidstate)(Nos.)
Polaris
ationCoupon(Nos.)
ERprobe(Nos.)
97 NEAR CHAMARBARA VILLAGE 81.342 AL 1 3
98IN FIELD BETWEEN BARDI-
CHAMARBARA VILLAGE82.378 AL 1 3
99 SH-45 82.564 C 1
100 SH-45 82.578 C 1
101AFTER SH-4X, NEAR BAROLI
VILLAGE83.478 AL 1 2
102 IN FIELD NEAR DOMRAKI VILLAGE 84.578 AL 1 2
103BFOR METALIC ROAD XING NEAR
KHESTI VILLAGE85.578 AL 1 2
104ASPHALTED ROAD XING NEAR
KHESTI VILLAGE86.500 AL 1 2
105 IN FIELD NEAR KHESTI VILLAGE 87.500 AL 1 2
106 IN FIELD NEAR DHUTKA VILLAGE 88.500 AL 1 2
107 IN FIELD BEFORE REVER 89.400 AL 1 2
108 RUPARE RIVER 89.485 B 1 1 2
109 RUPARE RIVER 89.695 B 1 2
110 IN FIELD AFTER RIVER 90.395 AL 1 2
111 MUD ROAD XING NEAR BOARWELL 91.448 AL 1 2
112 IN FIELD 92.448 AL 1 2
113 STATE HIGHWAY-22 92.680 C 1
114 STATE HIGHWAY-22 92.700 C 1
8/11/2019 Tcp Docs Rkpl
41/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 41 of 113
SN LocationChainage
(km)
TestStationType(TS)
CPStation SizeTest
station
(ICTS)(Nos.)
NormalSizeTest
station(TS)
(Nos.)
PolcellSizeTest
Station
(PCTS)(Nos.)
CTSUSizeTest
Station(CTS)
(Nos.)
Permanent Ref.
Cell
CuCuSo
4 (Nos)
MgAnode(2.5
KG)
(Nos.)
MgAnode
(10
KG)
(Nos.)
Bare ZnRibbonAnodefor HT
Line
crossing(m.)
ZNAnode
(20
KG)
(Nos.)
Polarisation cell(solid
state)
(Nos.)
Polarisation
Coupon(Nos.)
ERprobe
(Nos.)
115 SV-3 93.532 GL 1 2 2 1
116IN FIELD KUTAKPUR TO ARSI
VILLAGE94.532 AL 1 2
117ASPLATED ROAD XING ARSI TO
NAGAR MARKET95.643 AL 1 2
118METAL ROAD XING BHUKI TO ARSI
VILLAGE96.678 AL 1 2
119 IN FIELD 97.700 AL 1 2
120 RAILWAY XING (NCR) 98.076 C 1
121 RAILWAY XING (NCR) 98.111 C 1
122 METAL ROAD XING 98.805 AL 1 2
123 SH-14 XING 99.961 CL 1 2
124 SH-14 XING 99.983 C 1
125IN FIELD AFTER SH-14, NEAR BURJA
VILLAGE
100.983 AL 1 2
126 IN FIELD NEAR GANGABAK VILLAGE 101.983 AL 1 2
127IN FIELD AFTER RD, NR GANGABAK
VILLAGE102.983 AL 1 2
128 KENDALE TO MOBAI RD XIG 103.933 AL 1 2
129METAL ROAD XING DABHARA TO
WOBAI105.088 BL 1 1 2
130NEAR MORLI VILLAGE & BADESRA
ROAD106.000 AL 1 2
131NEAR MOBAIT TOMORALI
ASPHALTED RD107.000 AL 1 2
8/11/2019 Tcp Docs Rkpl
42/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 42 of 113
SN LocationChainage
(km)
Test
StationType(TS)
CPStatio
n SizeTest
station(ICTS)
(Nos.)
NormalSize
Teststation
(TS)
(Nos.)
Polcell
SizeTest
Station(PCTS)
(Nos.)
CTSUSize
TestStation(CTS)
(Nos.)
Perman
ent Ref.Cell
CuCuSo4 (Nos)
Mg
Anode(2.5KG)
(Nos.)
Mg
Anode(10KG)
(Nos.)
Bare ZnRibbon
Anodefor HTLine
crossing
(m.)
ZN
Anode(20KG)
(Nos.)
Polarisa
tion cell(solidstate)(Nos.)
Polaris
ationCoupon(Nos.)
ERprobe(Nos.)
132 NEAR BOAR WELL 108.000 AL 1 2
133 IN FIELD NEAR 11 KV LINE 109.000 AL 1 2
134 IN FIELD NEAR JANUTHER VILLAGE 110.000 AL 1 2
135 IN FIELD NEAR JANUTHER VILLAGE 111.000 AL 1 2
136 METALICA ROAD XING 111.958 AL 1 2
137 METALED ROAD XING 113.184 AL 1 2
138 IN FIELD SINSINI VILLAGE 114.184 AL 1 2
139 IN FIELD NEAR SONGAANB VILLAGE 115.184 AL 1 2
140 IN FIELD NEAR SONGAANB VILLAGE 116.184 AL 1 2
141IN FIELD NEAR BADANGASH
VILLAGE117.184 AL 1 2
142 SV-4 118.254 GL 1 2 2 1
143 IN FIELD 119.190 AL 1 2
144 IN FIELD PALA VILLAGE 120.190 AL 1 2145 IN FIELD PALA VILLAGE 121.190 AL 1 2
146 NEAR CART TRACK PALA VILLAGE 122.190 AL 1 2
147 STATE HIGHWAY-14 122.770 C 1
148 STATE HIGHWAY-14 122.787 C 1 2
149 ASPHALTED ROAD XING 123.190 AL 1 2
150 IN FIELD, NEAR SAINTHRI VILLAGE 124.190 AL 1 2
151AFTER MUD ROAD, NEAR KUMHER
VILLAGE125.190 AL 1 2
8/11/2019 Tcp Docs Rkpl
43/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 43 of 113
SN LocationChainage
(km)
TestStationType(TS)
CPStation SizeTest
station
(ICTS)(Nos.)
NormalSizeTest
station(TS)
(Nos.)
PolcellSizeTest
Station
(PCTS)(Nos.)
CTSUSizeTest
Station(CTS)
(Nos.)
Permanent Ref.
Cell
CuCuSo
4 (Nos)
MgAnode(2.5
KG)
(Nos.)
MgAnode
(10
KG)
(Nos.)
Bare ZnRibbonAnodefor HT
Line
crossing(m.)
ZNAnode
(20
KG)
(Nos.)
Polarisation cell(solid
state)
(Nos.)
Polarisation
Coupon(Nos.)
ERprobe
(Nos.)
152 IN FIELD, NEAR SAINTHRI VILLAGE 126.100 AL 1 2
153 MAJOR DISTRICT ROAD-71 127.241 CL 1 2
154 MAJOR DISTRICT ROAD-71 127.257 C 1
155 IN FIELD BEFORE ASPHALTED ROAD 128.257 AL 1 2
156 IN FIELD 129.257 AL 1 2
157NAAR ALEYA VILLAGE & BOMBO
PLACE130.024 B 1 1
158 IN FIELD 130.257 AL 1 2
159 IN FIELD NEAR DERAA VILLAGE 131.257 AL 1 2
160 DERAA VILLAGE ROAD XING 132.159 AL 1 2
161 IN FIELD 133.159 AL 1 2
162 ASPHALTED ROAD 134.057 AL 1 2
163
220KVA LINE XING NEAR
ASPHALTED ROAD 134.851 ML 1 2 4 1164 ASPHLATED ROAD XING 135.894 AL 1 2
165 STATE HIGHWAY-43 136.215 C 1
166 STATE HIGHWAY-43 136.237 C 1
167 IN FIELD NEAR MEGHAYA VILLAGE 136.894 AL 1 2
168 FOREGIN PL XING (WRPL IOCL) 137.705 EL 1 2
169 CART TRACK 138.724 AL 1 2
170 IN FIELD 139.724 AL 1 2
8/11/2019 Tcp Docs Rkpl
44/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 44 of 113
SN LocationChainage
(km)
TestStationType(TS)
CPStation SizeTest
station
(ICTS)(Nos.)
NormalSizeTest
station(TS)
(Nos.)
PolcellSizeTest
Station
(PCTS)(Nos.)
CTSUSizeTest
Station(CTS)
(Nos.)
Permanent Ref.
Cell
CuCuSo
4 (Nos)
MgAnode(2.5
KG)
(Nos.)
MgAnode
(10
KG)
(Nos.)
Bare ZnRibbonAnodefor HT
Line
crossing(m.)
ZNAnode
(20
KG)
(Nos.)
Polarisation cell(solid
state)
(Nos.)
Polarisation
Coupon(Nos.)
ERprobe
(Nos.)
171 STATE HIGHWAY-24 140.377 C 1
172 STATE HIGHWAY-24 140.413 CL 1 2
173 IOCL MBPL P/L XING 141.136 E 1
174 BPCL MBPL P/L XING 141.369 EL 1 2
175 BHARATPUR TERMINAL 141.800 GF 1 2
176 BHARATPUR TERMINAL 141.800 GF 1 2
177 WEASTERN CENTRAL RAILWAY 141.917 C 1
178 WEASTERN CENTRAL RAILWAY 141.972 CL 1 2
179 NEAR DAURAMKI VILLAGE 142.972 AL 1 2
180 NEAR DAURAMKI VILLAGE 143.972 AL 1 2
181 400KV HT LINE XING 145.049 ML 1 2 4 1
182 NEAR BILOTHI VILLAGE 146.049 AL 1 2
183 HPCL P/L XING 147.051 EL 1 2
184NEAR KARAUTI VILLAGE &
BILWATHI VILLAGE148.051 AL 1 2
185 IN FIELD 149.051 AL 1 2
186 NEAR SANTRAUK VILLAGE 150.051 AL 1 2
187 NEAR OLL VILLAGE 151.051 AL 1 2
188 NEAR HASANPUR VILLAGE 152.051 AL 1 2
189 NEAR HASANPUR VILLAGE 153.051 BL 1 1 2
190 NEAR IKDONIA VILLAGE 154.051 AL 1 2
8/11/2019 Tcp Docs Rkpl
45/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 45 of 113
SN LocationChainage
(km)
Test
StationType(TS)
CPStatio
n SizeTest
station(ICTS)
(Nos.)
NormalSize
Teststation
(TS)
(Nos.)
Polcell
SizeTest
Station(PCTS)
(Nos.)
CTSUSize
TestStation(CTS)
(Nos.)
Perman
ent Ref.Cell
CuCuSo4 (Nos)
Mg
Anode(2.5KG)
(Nos.)
Mg
Anode(10KG)
(Nos.)
Bare ZnRibbon
Anodefor HTLine
crossing
(m.)
ZN
Anode(20KG)
(Nos.)
Polarisa
tion cell(solidstate)(Nos.)
Polaris
ationCoupon(Nos.)
ERprobe(Nos.)
191 NEAR PILWA VILLAGE 155.051 AL 1 2
192 NEAR PILWA VILLAGE 156.051 AL 1 2
193 NEAR BORI VILLAGE 157.150 AL 1 2
194 400 KV HT LINE XING 158.270 ML 1 1 2 4 1 1
195 MATHUTA ACHNERA RAILWAY XING 158.440 C 1
196 MATHUTA ACHNERA RAILWAY XING 158.470 C 1
197 IN FIELD 159.261 AL 1 2
198 NEAR DHAMA SHASABAD VILLAGE 160.261 AL 1 2
199 ASPHALTED ROAD XING 161.289 AL 1 2
200 NH-02 Farah To Mathura 161.957 C 1
201 NH-02 Farah To Mathura 161.987 C 1
202 CENTRAL RAILWAY CROSSING 162.348 CL 1 2
203 CENTRAL RAILWAY CROSSING 162.395 C 1204 RAILWAY XING-MATHURA TO FARAH 163.166 C 1
205 RAILWAY XING-MATHURA TO FARAH 163.213 CL 1 2
206 NEAR LADPUR VILLAGE 164.213 AL 1 2
207 MATHURA TERMINAL 164.378 GF 1 2
208 MATHURA TERMINAL 164.378 GF 1 2
209 RAILWAY XING-MATHURA TO FARAH 164.684 C 1
210 RAILWAY XING-MATHURA TO FARAH 164.731 C 1
8/11/2019 Tcp Docs Rkpl
46/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 46 of 113
SN LocationChainage
(km)
Test
Station
Type(TS)
CPStatio
n SizeTest
station(ICTS)
(Nos.)
NormalSize
Teststation
(TS)
(Nos.)
Polcell
SizeTest
Station(PCTS)
(Nos.)
CTSUSize
TestStation(CTS)
(Nos.)
Perman
ent Ref.Cell
CuCuSo4 (Nos)
Mg
Anode(2.5KG)
(Nos.)
Mg
Anode(10KG)
(Nos.)
Bare ZnRibbon
Anodefor HTLine
crossing
(m.)
ZN
Anode(20KG)
(Nos.)
Polarisa
tion cell(solidstate)(Nos.)
Polarisa
tionCoupon(Nos.)
ERprobe(Nos.)
211 NEAR LADPUR VILLAGE 165.213 AL 1 2
212RAILWAY XING-MATHURA TO
FARAH165.712 C 1
213RAILWAY XING-MATHURA TO
FARAH165.759 C 1
214 IOCL P/L CROSSING 166.018 E 1
215 440KVA HT LINE XING 166.385 ML 1 2 4 1
216 NEAR BHADURI VILLAGE 167.385 AL 1 2
217BEFORE ASPHALTED ROAD
NATHALA-LADPUR168.385 AL 1 2
218 KARNAWAL MINOR CANEL 169.426 AL 1 2
219 ASPHALTED ROAD XING 170.400 AL 1 2
220 YAMUNA RIVER XING 170.486 B 1 1 2
221 YAMUNA RIVER XING 170.876 B 1 2
222 AFTER YAMUNA RIVER XING 171.400 AL 1 2
223 BEFORE NABIPUR MINOR CANAL 172.400 AL 1 2
224AFTER ASPHALTED RD XIN
HAIBPUR-NABIPPUR173.400 AL 1 2
225 NEAR PIMPARI VILLAGE 174.400 AL 1 2
226 NEAR PIMPARI VILLAGE 175.400 AL 1 2
227BEFORE YAMUNA EXPRESS
HIGHWAY176.400 BL 1 1 2
228220KV HT XING NEAR KHADERA
VILLAGE177.354 ML 1 2 4 1
229 AFTER CANEL, KHANGARI GRAM 178.354 AL 1 2
8/11/2019 Tcp Docs Rkpl
47/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 47 of 113
SN LocationChainage
(km)
Test
Station
Type(TS)
CPStatio
n SizeTest
station(ICTS)
(Nos.)
NormalSize
Teststation
(TS)
(Nos.)
Polcell
SizeTest
Station(PCTS)
(Nos.)
CTSUSize
TestStation(CTS)
(Nos.)
Perman
ent Ref.Cell
CuCuSo4 (Nos)
Mg
Anode(2.5KG)
(Nos.)
Mg
Anode(10KG)
(Nos.)
Bare ZnRibbon
Anodefor HTLine
crossing
(m.)
ZN
Anode(20KG)
(Nos.)
Polarisa
tion cell(solidstate)(Nos.)
Polarisa
tionCoupon(Nos.)
ERprobe(Nos.)
230ASPHALTED ROAD XING KILONI-
PATLONI VILLAGE179.354 AL 1 2
231 IN FIELD 180.354 AL 1 2
232 NEAR JATERA KILONI VILLAGE 181.354 AL 1 2
233ASPHALTED ROAD XING NEAR
BAMARASPUR VILLAGE182.214 AL 1 2
234 NEAR PATLONI VILLAGE 183.214 AL 1 2
235 NEAR PATLONI VILLAGE 184.214 AL 1 2
236 AWERNI MINOR CANEL 185.271 AL 1 2
237 NEARM BAHARATIYA VILLAGE 186.271 AL 1 2
238ASPHALTED ROAD XING NEAR
PAUCHAVARI VILLAGE187.382 AL 1 2
239 SV-5 188.058 G 1 2 1
240AFTER ROAD XING, PANCHWARI-
BISAWAR188.382 AL 1 2
241 METTALLED ROAD XING 189.233 AL 1 2242 NEAR BHILAHAR VILLAGE 190.233 AL 1 2
243ASPHALTD ROAD, BHILARAH-
GARHI191.331 AL 1 2
244 IN FIELD 192.331 AL 1 2
245 NEAR CHIRAWALI VILLAGE 193.331 AL 1 2
246NEAR MAI VILLAGE BEFORE
ASPHALTED RD194.331 AL 1 2
247 ASPHALTED RD XING 195.337 AL 1 2
248 KHANDAULI DISTRIBUTION 196.442 AL 1 2
8/11/2019 Tcp Docs Rkpl
48/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 48 of 113
SN LocationChainage
(km)
Test
Station
Type(TS)
CPStatio
n SizeTest
station(ICTS)
(Nos.)
NormalSize
Teststation
(TS)
(Nos.)
Polcell
SizeTest
Station(PCTS)
(Nos.)
CTSUSize
TestStation(CTS)
(Nos.)
Perman
ent Ref.Cell
CuCuSo4 (Nos)
Mg
Anode(2.5KG)
(Nos.)
Mg
Anode(10KG)
(Nos.)
Bare ZnRibbon
Anodefor HTLine
crossing
(m.)
ZN
Anode(20KG)
(Nos.)
Polarisa
tion cell(solidstate)(Nos.)
Polarisa
tionCoupon(Nos.)
ERprobe(Nos.)
249 400 KVA HT LINE XING 197.417 ML 1 2 4 1
250 NEAR NAGIRIA VILLAGE 198.417 AL 1 2
251 200 KV HT LINE XING 199.079 M 1 6 1
252 ASPHALTED ROAD XING 199.557 AL 1 2
253 IN FIELD AFTER NH 200.600 AL 1 2
254 220 KVA HT LINE XING 201.754 ML 1 2 6 1
255 IN FIELD NEAR SEMRA VILLAGE 202.754 AL 1 2
256 IN FIELD 203.754 BL 1 1 2
257ASPHALTED ROAD NEAR MAHARA
GHARI VILLAGE204.839 AL 1 2
258IN FIELD NEAR RAGALA RAMBAL
VILLAGE205.839 AL 1 2
259 IN FIELD NEAR SIRAIKA VILLAGE 206.839 AL 1 2
260ASPHALTED ROAD NEAR SIRAKA
VILLAGE
207.941 AL 1 2
261IN FIELD NEAR AKBAR BURJ
VILLAGE209.000 AL 1 2
262 IN FIELD USMANPUR VILLAGE 210.000 AL 1 2
263IN FIELD NEAR HOGIGHARI
VILLAGE211.000 AL 1 2
264 IN FIELD NEAR BENAI VLLAGE 212.000 AL 1 2
265IN FIELD AFTER ASPHALTED RD,
NEAR BENAI VLLAGE213.000 AL 1 2
266IN FIELD NEAR GHARI HARPAL
VILLAGE214.000 AL 1 2
8/11/2019 Tcp Docs Rkpl
49/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 49 of 113
SN LocationChainage
(km)
Test
StationType(TS)
CPStatio
n SizeTest
station(ICTS)
(Nos.)
NormalSize
Teststation
(TS)
(Nos.)
Polcell
SizeTest
Station(PCTS)
(Nos.)
CTSUSize
TestStation(CTS)
(Nos.)
Perman
ent Ref.Cell
CuCuSo4 (Nos)
Mg
Anode(2.5KG)
(Nos.)
Mg
Anode(10KG)
(Nos.)
Bare ZnRibbon
Anodefor HTLine
crossing
(m.)
ZN
Anode(20KG)
(Nos.)
Polarisa
tion cell(solidstate)(Nos.)
Polaris
ationCoupon(Nos.)
ERprobe(Nos.)
267 IN FIELD NEAR MUKHBAR VILLAGE 215.000 AL 1 2
268 IN FIELD NEAR GOWAL VILLAGE 216.000 AL 1 2
269 NORTHAN RAILWAY MAINLINE XING 216.460 C 1
270 NORTHAN RAILWAY MAINLINE XING 216.534 C 1
271400KVA HT XING, NEAR GOWAL
VILLAGE217.007 ML 1 1 2 4 1 1
272ASPHALTED ROAD, NEAR
HEMRAJPUR VILLAGE218.039 AL 1 2
273 SV-6 218.859 G 1 2 1
274 IN FIELD, NEAR ETA VILLAGE 219.000 AL 1 2
275 IN FIELD NEAR SALEMPUR VILLAGE 220.000 AL 1 2
276IN FIELD DEVKHERA VILLAGE
BEFORE ASPHALTED RD221.000 AL 1 2
277 IN FIELD DEVKHERA VILLAGE 222.000 AL 1 2
278 IN FIELD DEVKHERA VILLAGE 223.000 AL 1 2
279 NEAR DYAGHARI VILLAGE 224.000 AL 1 2
280NEAR DYAGHARI VILLAGE MINOR
CANNEL225.016 AL 1 2
281 STATE HIGHWAY-31 226.000 CL 1 2
282 STATE HIGHWAY-31 226.029 C 1
283 IN FIELD NEAR GHARIJORI VILLAGE 227.029 AL 1 2
284IN FIELD NEAR TARANAGAR
VILLAGE228.000 AL 1 2
TOTAL 10 245 17 12 36 468 12 116 7 17 2 2
8/11/2019 Tcp Docs Rkpl
50/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 50 of 113
16.0 CABLE LAYING DETAILSAll cables shall be laid in accordance with approved layout drawings. Half-meter cable slack
shall be provided near anodes, pipeline and test station in account for any settling.
All cable inside plant/station area shall be laid at a depth of 0.75 m and cables outside
station area shall be laid at a depth of minimum 1.5 m.
The buried cables laid outside the Station area shall be mark with Polyethylene warning mats
placed at 60 % of depth from the finished ground.
All cable shall be laid in sand under brick cover and back filled with normal soil as per cable
laying details drawing no. 06-10-1403-CLD.
17.0 CABLE TO PIPE CONNECTIONS
Connections of all CP cables to the charged pipelines shall be made by Pin Brazing and for
uncharged pipeline by Thermit weld.
Pipe coating shall be repaired after connection of cable to pipeline and the coating repair
material shall cover, exposed portion of the pipeline against ingress of water/moisture.
8/11/2019 Tcp Docs Rkpl
51/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 51 of 113
18.0 INSTALLATION PROCEDURE
18.1 FOR TEST STATION
a) Introduction This procedure covers installation of the Test Station.
b) Materials and reference
Sr. No. Material/Tool Make Application/Purpose
1 Test Station along with Bend RaychemFor Erection of teststation
2 Pharma Standard For Casting
3PCC materials like cement, Stonechips & sand
Standard For Casting
4MS Sheet for Mixing of PCCmaterials
Standard For Mixing PCC material
5Tools such as Hammer, Spannersets, Pliers
Standard For Casting
6 Water cans Standard For Casting
Drawings:06-10-1403-TS, 06-10-1403-PCTS, 06-10-1403-CTSUTS
WORLEYPARSONS Reference MH2145-C000-EL-SPC-0025 RevA.
c) ProcedureThe location of the test stations shall be marked on row as per approved design with their
connection scheme and other related information on alignment sheet.
Foundation shall be cast at site location. The overall dimensions of foundations shall
be 600 mm x 600 mm x 800 mm. As shown in the standard drawing No. 06-10-1403-
TS. The foundation cast should be properly watered and cured.
Excavate 1m x 1 m x 1 m where the foundation is to cast.
Prepare PCC for height of 600+200 mm as per installation drawing &
WORLEYPARSONS standard drawing.
Placed TS bend (Bottom) above PCC.
Take MS shuttering and placed it in right position.
The PCC (M-15) mixture shall be constantly rammed for proper compaction.
Remove the shuttering after 24 hrs.
The foundation shall be cured by proper curing for minimum 7 days
Placed the TS boxes on the studs of the bend cast in concrete foundation and tighten
the bolts.
50 mm PCC shall be done on the top of foundation after installation of Test Station.
8/11/2019 Tcp Docs Rkpl
52/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 52 of 113
The bolts shall then be distorted by hitting with a heavy hammer to make theinstallation vandal proof and also to ensure that the installation becomes theft proof.
Bottom Cable entry of Test station Foundation shall be closed/Sealed by using
Bitumen Compound to prevent water entry.
The test station shall be installed in front side of the test station facing the pipeline &
left hand side of the product flow in the pipeline.
The name plate of test station (Black background with white letters) shall in min.
carry following information:
Test Station Number, Chainage in Km
Test Station Connection Scheme Type
Distance from Pipeline in mtrs
Direction of Product flow
d) PRECAUTIONS:
Cables used shall be of sufficient length so as to reach termination point without any
joint. Provide sufficient slack for future maintenance purpose (Loop shall be 1mtr
before Test station).
All the connections should be checked for proper tightening and tagged.
Cable tags are to be provided at end before final termination
Cable should be neatly dressed inside the trench and to be terminated inside test
station.
In case of location, where sacrificial anode is to be installed, the same should be
taken parallel and the anode cable to be terminated at test station.
20% of Spare terminal shall be provided in Test Stations.
Test station used for sacrificial anodes shall have shunt for measurement of anodes
current and provision for resistance insertion to limit the anode current output.
Test Station shall be installed at left side of the pipeline towards flow.
Test report Record and document all the inspection results obtained in the below
inspection report format.
e) FORMATS
Inspection & Test Plan :06-10-1403-ITP-TS,
Installation report : 06-10-1403-IR-TS,
NOTE: In case of any conflict between the above procedures and contract specifications, thelater shall be governed.
8/11/2019 Tcp Docs Rkpl
53/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 53 of 113
INSPECTION AND TEST PLAN FOR TEST STATION
PROJECT EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
OWNER HINDUSTAN PETROLEUM CORPORATION LIMITED.
CONSULTANT WORLEYPARSONS SEA INDIA PVT. LTD.
CONTRACTOR KSS PETRON PRIVATE LIMITED
CP CONTRACTOR RAYCHEM RPG PVT. LTD.
REF. DRG. 06-10-1403-TS, 06-10-1403-PCTS, 06-10-1403-CTSUTS
REPORT NO. 06-10-1403-ITP-TS
WORLEYPARSONS STD. DWG
2-D-109-P CEL TS/ 2-D-110-TS
PERSONNELRESPONSIBLE
RAYCHEM RPG: SITE ENGINEER / SUPERVISOR
HPCL/WORLEYPARSONS: INSPECTOR
SR.NO.
ACTIVITYRAYCHEM
RPG
WORLEYP
ARSONS/KSS
HPCL
1 Check Location P RM RM
2 Concrete Foundation Size, PCC Mixture, & Curing P S RM
3 Installation Test Post Mounting Above Foundation P S RM
4 Termination Of Cables In The Test Station P S RM
5 Check Proper Sealing Of Cable Entry At Foundation P RM RM
6 Cable Height Above Ground Level P RM RM
LEGEND:
A : APPROVAL R : REVIEW OF RECORD
P : PERFORM RM : RANDOM CHECK
W : WITNESS ALL S : SUBMISSION
RAYCHEM RPG WORLEYPARSONS KSS HPCL
Name: Name: Name: Name:
Sign: Sign: Sign: Sign:
Date: Date: Date: Date:
8/11/2019 Tcp Docs Rkpl
54/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 54 of 113
INSTALLATION REPORT FOR TEST STATION
PROJECT EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
OWNER HINDUSTAN PETROLEUM CORPORATION LIMITED.
CONSULTANT WORLEYPARSONS SEA INDIA PVT. LTD.
CONTRACTOR KSS PETRON PRIVATE LIMITED
CP CONTRACTOR RAYCHEM RPG PVT. LTD.
REF. DRG. 06-10-1403-TS, 06-10-1403-PCTS, 06-10-1403-CTSUTS
WORLEYPARSON
S STD. DWG
2-D-109-P CEL TS/
2-D-110-TS
REF. SPECIFICATION
REPORT NO. 06-10-1403-IR-TS, Date
Test station Location (Chainage in Km)
Test Station Type
Distance from the pipeline (m)
Foundation
Test Station Mounting
Test station Doors / Locks /Gasket
Cable entry sealing
Cable Termination
NOTES:
RAYCHEM RPG WORLEYPARSONS KSS HPCL
Name: Name: Name: Name:
Sign: Sign: Sign: Sign:
Date: Date: Date: Date:
8/11/2019 Tcp Docs Rkpl
55/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 55 of 113
18.2 FOR SACRIFICIAL ANODES
a) Introduction:
This procedure covers installation of the prepackaged Sacrificial Anode assemblies.
b) Materials required
Sr. No. Material/Tool Make Application/Purpose
1Magnesium Anode with
cotton bag
Scientific Metal / YuxiChina/Xiang Metal,China
For Protection of Pipeline
2 Backfill Powder Standard For Installation
3 Water can Standard For Installation
4 Excavation tools Standard For excavation
Drawings:06-10-1403-MG2.5, 06-10-1403-MG10, 06-10-1403-ZN20 & 06-10-1403-
GAI
c) Responsibility:
It is the responsibility of the contractors engineer to ensure that the Anodes, cables and the
associated test station are correctly installed. The responsibility shall also cover the proper
supervision in excavation, backfilling and concreting work as required.
d) Detailed Procedure:
The Anodes shall be suitably located as enumerated in the Design Package to provide
the adequate levels of corrosion protection.
The installation procedure is as follows:
The Mg anode groundbed shall be located at 5 mtrs away from the pipeline
For Zinc anode groundbed shall be located at 2 mtrs away from the pipeline.
For Zinc anode installed for HT line crossing shall be located at 5 mtrs away from the
pipeline.
The anodes shall be installed in Horizontal configuration perpendicular to the pipeline.
The anodes shall be installed in suitable trench at min 1.5 Mtrs depth. The Spacing
between consecutive Anodes shall be 5 Mtrs as per the standard procedure.
The top of the anode shall be at the bottom of the pipeline
The prepacked anodes shall be lowered inside the trench and the balance spaced
around the anodes shall be filled with native soil. After installing the anode the soil
surrounding the anode shall be compacted. While lowering, the anode should not be
suspended or lowered by its lead wire. In dry locations water shall be poured directly
on the anode.
8/11/2019 Tcp Docs Rkpl
56/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 56 of 113
Wherever Hard Rock / Hard Soil Observed Depth of Anode bed shall be installed at aminimum depth equal to bottom level of the pipeline.
The anode installation shall be checked by measuring the potential of the pipeline
against a standard Cu-Cu So4 reference cell before and after connection of the
anodes.
e) Backfill:
Anodes shall be packaged in a cotton bag and shall be surrounded by a low resistivity rapid
wetting chemical backfill of the following composition:
Gypsum : 75%
Bentonite : 20%Sodium Sulphate : 5%
f) Precautions:
Cables used shall be of sufficient length so as to reach termination point without any
joint. Provide sufficient slack for future maintenance purpose.
All the connections should be checked for proper tightening and tagged.
Cable tags are to be provided at end before final termination
Cable should be neatly dressed inside the trench and to be terminated inside test
station
e) FORMATS
Inspection & Test Plan :06-10-1403-ITP-ANODES,
Installation report :06-10-1403-IR-ANODES,
NOTE: In case of any conflict between the above procedures and contract specifications, thelater shall be governed.
8/11/2019 Tcp Docs Rkpl
57/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 57 of 113
INSPECTION AND TEST PLAN FOR ANODES
PROJECT EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
OWNER HINDUSTAN PETROLEUM CORPORATION LIMITED.
CONSULTANT WORLEYPARSONS SEA INDIA PVT. LTD.
CONTRACTOR KSS PETRON PRIVATE LIMITED
CP CONTRACTOR RAYCHEM RPG PVT. LTD.
REF. DRG. 06-10-1403-MG2.5, 06-10-1403-MG10, 06-10-1403-ZN20 & 06-10-1403-GAI
REPORT NO. 06-10-1403-ITP-ANODES
WORLEYPARSONS STD. DWG
2-D-103-106-MG 2.5 KG/ 2-D-107-MG 20-10KG
PERSONNELRESPONSIBLE
RAYCHEM RPG: SITE ENGINEER / SUPERVISOR
HPCL/WORLEYPARSONS: INSPECTOR
SRNO
ACTIVITYRAYCHEM
RPG
WORLEYPARSONS/
KSS
HPCL
1 Check Location P RM RM
2 Check Depth P RM RM
3 Open Circuit Potential Measurement P S RM
4 Natural PSP Measurement P S RM
5 Anode Open circuit potential(Before Connecting With PL) P RM RM
6 PSP Measurement (After Connecting With Anode) P RM RM
7 Anode Condition (Backfill, Cable, Bag) P S RM
8 Spacing Between Anodes P RM RM
9Cable Connection & Connector Assembly With Anode Continuity Check
P S RM
10 Check cable termination & tagging P RM RM
LEGEND:
A : APPROVAL R : REVIEW OF RECORD
P : PERFORM RM : RANDOM CHECK
W : WITNESS ALL S : SUBMISSION
RAYCHEM RPG WORLEYPARSONS KSS HPCL
Name: Name: Name: Name:
Sign: Sign: Sign: Sign:
Date: Date: Date: Date:
R-1
8/11/2019 Tcp Docs Rkpl
58/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 58 of 113
INSTALLATION REPORT FOR ANODES
PROJECT EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
OWNER HINDUSTAN PETROLEUM CORPORATION LIMITED.
CONSULTANT WORLEYPARSONS SEA INDIA PVT. LTD.
CONTRACTOR KSS PETRON PRIVATE LIMITED
CP CONTRACTOR RAYCHEM RPG PVT. LTD.
WORLEYPARSONS STD. DWG
2-D-103-106-MG 2.5 KG/ 2-D-107-MG 20-10KG
REF. DRG. 06-10-1403-MG2.5, 06-10-1403-MG10,06-10-1403-ZN20 & 06-10-1403-GAI
REPORT NO. 06-10-1403-IR-ANODES, DATE
Anode Location (Chainage in Km)
Test Station Type
Test Station No.
Type of Sacrificial Anode Mg Anode/ Zinc Anode
Distance from Pipeline (Mtr)
No. Of AnodesSpacing Between Anodes
Current Output of Anode mA
Anode Condition & Anode Laying &Termination with Test station
OK/NOT OK
Anode Tail Cable Length (Mtr) A1 A2 A3
Anode Open circuit potential w.r.tCu / CuSO4Ref. Cell ( Before connecting to PL)
PSP w.r.to Cu/CuSO4Ref.Cell (Before Connecting Anode)
PSP w.r.to Cu/CuSO4Ref. Cell
(After Connecting Anode)
Instrument Details (Make/ model / Sr. No.) Calibration certificate. No. & validity
RAYCHEM RPG WORLEYPARSONS KSS HPCL
Name: Name: Name: Name:
Sign: Sign: Sign: Sign:
Date: Date: Date: Date:
R-1
8/11/2019 Tcp Docs Rkpl
59/113
DESIGN DOCUMENT FOR TEMPORARYCATHODIC PROTECTION SYSTEM FOR
PHASE-I
EPMC SERVICES FOR REWARI-KANPUR PIPELINE PROJECT
06-10-1403-DD-PH1, Rev-01 Page 59 of 113
18.3 FOR CABLE LAYINGa) Introduction:
This procedure covers the method of under ground cable laying with proper related activities
to be performed.
b) Materials
Sr. No Material/Tool Make Application/Purpose
1 Crimping Tool Standard For Crimping of cable
2 Sand, Bricks Standard For Installation
3 Excavation tools Standard For Excavation
Drawings:06-10-1403-CLD
c) Procedure:
All cables shall be laid in accordance with approved layout drawings. There shall be
no joints in a single run of cable.
Warning Mats should be placed at 60% of depth from finished ground level.
The cables shall be laid at a depth of 0.75 m inside Station / Plant area and at 1.5 m
outside station / Plant area with a layer of sand or soft soil as per spec A027-010-06-
45-SW-01, Rev.4
Second Class Bricks shall be placed over the sand spread as per the drawing and
backfill with normal soil.
Cable tags for buried cables/PVC ferrule are attached to each cable at termination
point for identification of individual cable.
Crimping the cable to proper sized crimping lugs does termination of cable. Before