Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
TWENTIETH ANNUAL
INTERNATIONAL MARITIME LAW ARBITRATION MOOT
2019
UNIVERSITAS DIPONEGORO
TEAM 18
MEMORANDUM FOR RESPONDENT’S
IN THE MATTER OF THE ARBITRATION HELD IN ROTTERDAM
ON BEHALF OF AGAINST
PANTER SHIPPING INC OMEGA CHARTERING LTD
CLAIMANT / OWNERS RESPONDENT / CHARTERERS
COUNSEL
NATANAEL DAUD VENDRA WAHID RAKA PERMANA
RESTY SUTRAINY RUTH ARTHASYA DANIEL KANDOU
Team 18 Memorandum for Respondent
ii
INDEX OF ABBREVIATIONS ........................................................................................................................ III
INDEX OF AUTHORITIES .............................................................................................................................IV
1. CASES ......................................................................................................................................................... IV 2. BOOKS AND ARTICLES .............................................................................................................................. VI 3. LEGISLATIONS .......................................................................................................................................... VII
ARGUMENTS ON JURISDICTION ................................................................................................................ 4
I. THIS TRIBUNAL HAS NO JURISDICTION OVER THE PRESENT DISPUTE .................................................... 4 A. There is a valid Arbitration Agreement ................................................................................................ 4 B. The Tribunal has the authority to determine its own jurisdiction ....................................................... 4 C. This Tribunal was not properly constituted .......................................................................................... 4
a. Owners’ appoinment of arbitrators have failed to meet the requirements of the Charterparty ............... 5 b. In any event, Owners have failed to commenced the proceedings appropriately ....................................... 6
D. Alternatively, the Tribunal has the authority to grant Charterers’ claim for damages ......................... 7
ARGUMENTS ON THE MERITS OF CLAIM ..................................................................................................... 8
II. CHARTERERS ARE NOT LIABLE TO THE CLAIMS ARISES OUT OF THE HULL CLEANING ........................ 8 A. Owners were deemed to agree to bear the risk for the hull cleaning cost on its own ......................... 8 B. Alternatively, Charterers would only be liable for the reasonable cost for the hull cleaning ............... 9
a. The reasonable cost for the hull cleaning is USD 33,000. .............................................................................. 9 b. The Charterers are not liable for the travel cost for the hull cleaning ....................................................... 10
III. CHARTERERS ARE NOT RESPONSIBLE TO THE DAMAGES ARISES OUT OF THE LATE RE-DELIVERY ..........................................................................................................................................................11
A. Charterers were only liable for the lost in the period of the overrun ................................................11 a. There isn’t any applicable market rate for differences in the period of overrun...................................... 11 b. In any event, Charterers have already paid hire for the period of overrun accordingly ......................... 11
B. Charterers are not liable to the loss arises out of the Lost Fixture ...................................................12 a. The loss was not under Charterers’ assumed responsibility arises out of the Charterparty ................... 12 b. Charterers had no particular knowledge of the Next Fixture ..................................................................... 13
C. Alternatively, the maximum period of 4 years was too remote ..........................................................14 D. Further in the alternative, Owners must give credit for the profit realized by the Replacement Fixture...........................................................................................................................................................15
IV. ALTERNATIVELY, CHARTERERS ARE ENTITLED TO SET OFF ITS COUNTERCLAIM AGAINST ANY SUMS THEY FOUND IS LIABLE TO THE OWNERS ................................................................................15
ARGUMENTS ON THE MERITS OF COUNTER-CLAIM ................................................................................... 16
V. CHARTERERS ARE ENTITLED TO BE INDEMNFIED FOR THE CARGO CLAIM...............................16 A. The Cargo Claim has been validly raised ...........................................................................................16 B. The Cargo Claim was not time-barred................................................................................................17 C. Owners is liable for 100% of the Cargo Claim ...................................................................................19 D. Alternatively, Owners is liable for the Cargo Claim in like amounts ................................................20 E. Further in the alternative, Owners is liable for 50% of the Cargo Claim .........................................20
VI. CHARTERERS ARE ENTITLED TO RECOVER THE OVERPAID HIRE FOR THE VESSEL HAS BEEN OFF-HIRE .........................................................................................................................................................21
A. The Vessel was off-hire from 07.05.2016 untill 26.06.2016 ..............................................................21 B. The off hire would not be caused by the Charterer’s fault ................................................................22 C. In any event, Charterers is entitled to recover the overpaid hire .......................................................23 D. Alternatively, the Owners are liable to damages arises out of the off hire ........................................24
REQUEST FOR RELIEF ................................................................................................................................ 25
Team 18 Memorandum for Respondent
iii
INDEX OF ABBREVIATIONS
Abbreviations Terms
Moot Scenario IMLAM 2019 Moot Scenario
Procedural Order No. 2 IMLAM 2019 Clarification for Procedural Order No. 2
Charterparty Time Charter Agreement dated 18.03.2016
(Comprises of Fixture Recap incorporating NYPE 2015, Rider
Clause, Inter-Club Agreement)
Claimant/Owners Panther Shipping Inc.
Respondent/Charterers Omega Chartering Limited
Charterparties/Parties Owners and Charterers
Vessel M/V Thanos Quest
Managers Hulk Hulls
Brokers Clark Kent & Sons
Champion Champion Chartering Corp
Fairwind Fairwind International
Fixture Recap Omega Chartering Limited Fixture Recap dated 18.03.2016
Rider Clause Omega Chatering Rider Clauses
Next Fixture Champion Chartering Corp Fixture Recap dated 15.06.2016
Replacement Fixture Fairwind International Fixture Recap dated 04.07.2016
NYPE 2015 New York Produce Exchange Time Charter Form 2015
ICA Inter-Club New York Produce Exchange Agreement 1996
(As Amended September 2011)
LMAA Terms 2017 London Maritime Arbitration Act Terms 2017
Cargo (1720 x 5mt big bags) English Breakfast Tea in Bags
FHS Final Hire Statement dated 01.08.2016
Mekon Report Mekon Surveyors Inc Preliminary Survey Report dated
30.06.2016
Receivers Hawkeye Import & Export Pty
P Page
para Paragraph
Team 18 Memorandum for Respondent
iv
INDEX OF AUTHORITIES
1. Cases
A/B Helsingfors Steamship Co. v. Rederiaktiebolaget Rex ("The White Rose"), [1969]
1 W.L.R. 1098.
Action Navigation inc v. Bottiglieri Navigation sp, [2005] EWHC 177 (Comm) Case
No: 2004 F. 617
Actis Co. Ltd.V. The Sanko Steamship Co. Ltd. (The "Aquacharm") [1980] 2 Lloyd’s
Rep. 237
Allianz Versicherungs-AG v. Fortuna Co Inc (The ‘Baltic Universal’) [1999] 1 Lloyd’s
Rep. 497
AMEC Civil Engineering Ltd v. Secretary of State for Transport [2015] 1 WLR 2339
Andre & Cie S.A. .v. Orient Shipping (Rotterdam) B.V. (“The Laconian Confidence”)
[1997] 1 Lloyd’s Rep. 139
Ashville Investments Ltd v. Elmer Construction Ltd [1989] QB 488
Banco de Portugal v Waterlow & Sons Ltd [1932] AC 452
Board of Trade v. Temperley (1927) 27 Ll.L.Rep. 230
Boston Bank of Connecticut v European Grain and Shipping Ltd (The Dominique)
[1989] 1 Lloyd’s Rep 431
Capital Trust Investments Ltd v. Radio Design TJ AB [2002] CLC 787
CAHarbour Assurance Co (UK) Ltd v. Kansa General International Insurance Co Ltd
[1993] QB 701
C Czarnikow Ltd v Koufos (The Heron II) [1969] 1 AC 350
Channel Tunnel Group Ltd v Balfour Beatty Construction Ltd [1993] AC 334
Channel Island Ferries Ltd. V. Cenargo Navigation Ltd. (The "Rozel") [1994] 2
Lloyd’s Rep. 161
Charles M Willie & Co (Shipping) Ltd v Ocean Laser Shipping Ltd (The ‘Smaro’)
[1999] 1 Lloyd’s Rep 225
Compania Financiera "Soleada" S.A., Netherlands Antilles Ships Management
Continental Pacific Shipping Ltd.v. Deemand Shipping Co. Ltd. (The Lendoudis
Evangelos II) [1997] 1 Lloyd’s Rep. 404
Corporation Ltd. And Dammers And Van Der Heide's Shipping And Trading Co.
Ltd.V. Hamoor Tanker Corporation Inc (“The Borag") [1981] 1 Lloyd’s Rep. 483
Darbishire v. Warrin [1963] 1 W.L.R. 1067
Team 18 Memorandum for Respondent
v
Duke of Westminster v. Swinton, [1948] 1 K.B. 524
Empresa Cubana de Fletes v. Aviation & Shipping [1969] 2 Lloyd’s Rep. 257
Federal Commerce LTD v Molena Alpha INC (The” Nanfri”) [1978] 2 Lloyd’s Rep.
132,
Fiona Trust and Holding Corporation v. Privalov [2007] 2 Lloyd’s Rep 267
Flamenco) [2014] EWHC 1547[64].
Fulton Shipping Inc of Panama v Globalia Business Travel SAU (The New
Galoo Ltd v Bright Grahame Murray [1994] 1 WLR 1360.
Geldof Metaalconstructie NV v Simon Carves Ltd. [2011] 1 Lloyd’s Rep 517
Government of Newfoundland v The Newfoundland Ry Co. (1888) 13 App Cas 199
Hadley v Baxendale (1854) 9 Exch 341
Ipsos S.A. v Dentsu Aegis Network Limited [2015] EWCH 1171 (Comm).
Laminates Acquisitions v BTR Australia Limited [2004] 1 All ER (Comm) 737
Marbienes Cia. Nav. v. Ferrostaal A.G. (“The Democritos”) [1975] 1 Lloyd’s Rep.
386
Minermet SpA Milan v Luckyfi eld Shipping Corporation SA [2004] 2 Lloyd’s Rep 348
(Comm)
Monarch Steamship Co Ltd v Karlshamns Oljefabriker (A/B) [1949] AC 196,
Mulvenna v Royal Bank of Scotland plc [2003] EWCA Civ 1112.
Pan Ocean Co. Ltd. v. Creditcorp Ltd. (The “Trident Beauty”) [1994] 1 Lloyd’s Rep.
365 (H.L.),
Petroleum Shipping Ltd. v, Vatis (trading as Kronos Management) (“The Riza and The
Sun”) [1997] 2 Lloyd’s Rep. 314
Read v. Page, [1927] 1 K.B. 743,
Robophone Facilities Ltd v Blank [1966] 1 WLR 1428
Satef-Huttenes Albertus SpA v Paloma Tercera Shipping Co SA (The Pegase) [1981]
Lloyd’s Rep 175
Schiffahrtsgesellschaft M.B.H & Co. (The “Black Falcon”) [1991] 1 Lloyd’s Rep. 77
Shipping Corporation of India Ltd. v. NSB Niederelbe Schiffahrtsgesellschaft M.B.H
& Co. (The “Black Falcon”) [1991] 1 Lloyd’s Rep. 77
SIG Berdesen DY and Co. v. Mobile Shipping (“The Berge Sund”) [1993] 2 Lloyd’s
Rep. 453
Team 18 Memorandum for Respondent
vi
SL Sethia Liners Ltd. v. Naviagro Maritime Corporation (The "Kostas Melas") [1981]
1 Lloyd’s Rep. 18
Sotiros Shipping Inc. And Aeco Maritime S.A.V.Sameiet Solholt (The "Solholt") [1983]
1 Lloyd’s Rep. 605
South Australia Asset Management Corpn v York Montague Ltd) [1997] AC 191
Standard Oil v Clan Line [1924] AC 100,
Stewart v. Van Ommeren [1918] 2 K.B. 560
Storer v. Manchester City Council [1974] 1 W.L.R. 1403
Torvald Klaveness A/S V. Arni Maritime Corporation (The "Gregos") [1995] 1 Lloyd’s
Rep 1
Transfield Shipping v. Mercator Shipping (The Achilleas) [2008] 2 Lloyd’s Rep. 275
(H.L.)
Triad Shipping Co. v. Stellar Chartering and Brokerage Inc. (The "Island Archon"),
[1994] 2 Lloyd’s Rep. 227, (C.A.) 237
Victoria Laundry (Windsor) Ltd v Newman Industries Ltd [1949] 2 KB 528
Villa Denizcilik Sanayi ve Ticaret AS v. Longen SA (The ‘Villa’) [1998] 1 Lloyd’s Rep.
195
Vosnoc Ltd v Trans Global Projects Ltd [1998] 1 Lloyd’s Rep 711
Weir and Others v. Union Steamship Co. Ltd. [1900] A.C. 525
Whistler International Ltd. v. Kawasaki Kisen Kaisha Ltd. ("The Hill Harmony"),
[2001] 1 Lloyd’s Rep. 147
2. Books and Articles
Ahmad Hussam Kassem, The Legal Aspects of Seaworthiness: Current Law and
Development, (Swansea University, 2006)
Alexis Mourre, “The Set-Off Paradox In International Arbitration”, (2008) Arbitration
International, Vol. 24, No.3 LCIA
Bruce Harris, Arbitration Act 1996 Commentary, (Blackwell Publishing, 4th ed., 2007)
Clare Ambrose, London Maritime Arbitration(Routledge, fourth edition, 2018)
International Publishing, Switzerland, 2016)
John Wilson, Carriage of Goods by Sea, (Longman, seventh edition, 2010),
Neil Andrews, Arbitration and Contract Law Common Law Perspectives, (Springer
Team 18 Memorandum for Respondent
vii
Peter Aeberli, “Jurisdictional Disputes under the Arbitration Act 1996: A Procedural
Route Map”, (2005) ARBITRATION INTERNATIONAL Vol. 21 No. 3
Terence Coghlin et.al, Time Charters, (Informa Routledge, seventh edition, 2014)
3. Legislations
Arbitration Act 1996
Inter-Club New York Produce Exchange Agreement 1996 (As Amended September
2011)
London Maritime Arbitration Association Terms 2015
Team 18 Memorandum for Respondent
1
STATEMENT OF FACTS
1. By a Charterparty dated 18.03.2016 (the “Charterparty”), the Claimant (“Owners”)
chartered the M/V “THANOS QUEST” (the “Vessel”) to the Respondent (“Charterers”) for
a time charter trip of about 50-55 days from West Coast to Wahanda carrying a cargo of
harmless bulk products. The Vessel was delivered into the Charterparty on 29.03.2016 and
loading of the cargo was completed on 20.04.2016, whereupon the Vessel sailed for Wahanda.
2. On 07.05.2016, the Vessel arrived at the discharge port of Wahanda, but she was unable
to proceed immediately to berth and instead waited at the anchorage.
3. On 08.06.2016, an e-mail was sent to Charterers by Owners (via the Vessel’s Managers
and Brokers), respectively Hulk Hulls (“Managers”) and Clark Kent & Sons (“Brokers”)
noting that the Vessel was expected to spend more than thirty days at the port of Wahanda.
4. Owners requested that Charterers confirm the arrangements for cleaning the Vessel’s
hull in accordance with clause 83 of the Charterparty.
5. On the same day, Charterers responded to Owners by e-mail (via Managers and
Brokers) stating that underwater hull cleaning could not be performed at Wahanda and offered
to pay Owners USD 15,000 in lieu of cleaning.
6. On 09.06.2016, an email was sent to Charterers by Owners (via Managers and Brokers)
stating that the extent of any fouling was not possible to know, since no inspection was done.
Therefore, an inspection and cleaning at the next convenient port would be arranged by
Owners, since Owners also could not agree a lump sum for cleaning.
7. On the same day, Charterers responded (via Brokers and Managers) by stating that
Charterers would pay the cost of underwater cleaning against an original invoice.
Team 18 Memorandum for Respondent
2
8. On 15.06.2016, the Vessel to Champion Chartering Corp (“Champion”) for a period
of two years, plus a further two years in charterers’ option (the “Next Fixture”) was chartered
by Owners. Delivery under the Next Fixture was to be DLOSP Wahanda with a laycan of 22-
28 June 2016 with daily rate of hire USD10,500.
9. On 18.06.2016, an e-mail was sent to Charterers by Owners (via Managers and Brokers)
reserving their right to claim against Charterers for losses incurred as a result of the Vessel
being redelivered without hull cleaning having been performed.
10. On 26.06.2016, a further e-mail was sent to Charterers by Owners (via Brokers) stating
that the Vessel had been thoroughly fouled during her extended stay at Wahanda and that no
cleaning could take place in East Coast ports and asked Charterers to confirm their intention
with regard to cleaning in accordance with clause 83 of the Charterparty.
11. On 27.06.2016, Charterers responded to Owners (via Brokers and Managers) stating
that Charterers could arrange cleaning at North Titan port if Owners were sailing north and
offered to pay a lump sum of USD20,000 in lieu of cleaning for the alternative.
12. On 28.06.2016, Champion gave notice to Owners that they were cancelling the Next
Fixture, since the Vessel had missed the laycan.
14. On 29.06.2016, an e-mail was sent to Charterers by Owners (via Brokers) calling upon
Charterers to arrange for the Vessel’s hull to be cleaned at South Island following the
completion of discharge at Wahanda.
15. On 30.06.2016, Charterers responded to Owners (via Brokers and Managers) stating
that any voyage to South Island would be non-contractual and that cleaning could not be
performed at Wahanda and offered to pay USD30,000 in lieu of cleaning.
16. In response to Charterers (via Brokers), Owners gave one final opportunity to comply
with the contractual obligations under clause 83 of the Charterparty by arranging for
underwater cleaning prior to re-delivery.
Team 18 Memorandum for Respondent
3
17. The Vessel was re-delivered and discharge of the chargo is completed on 30.06.2016.
The Vessel’s hull was cleaned at South Island between 01.07.2016 and 03.07.2016 at a total
cost of USD41,000.
18. On 01.08.2016, Owners presented their Final Hire Statement to Charterers (the “FHS”).
The FHS includes costs of USD97,766.64 in relation to cleaning the Vessel’s hull at South
Island after re-delivery of the Vessel. Charterers have paid the sums USD1,199.22 due under
the FHS.
19. On 04.07.2016, the Vessel to Fairwind International (“Fairwind”) for a time charter trip
of about 50-55 days (the “Replacement Fixture”) was being chartered by the Owners. Delivery
under the Replacement Fixture was to be DLOSP South Island with a laycan of 4-6 July 2016
with daily rate of hire was USD11,000.
Team 18 Memorandum for Respondent
4
ARGUMENTS ON JURISDICTION
I. THIS TRIBUNAL HAS NO JURISDICTION OVER THE PRESENT DISPUTE
A. There is a valid Arbitration Agreement
20. Clause 80 of the Charterparty asserts that any disputes arises between Owners and
Charterers shall be referred to “three persons at London”, and that the “arbitration to be in
London”. Consequently, when London is the intended seat for the tribunal, the supplementing
provisions of English law, particularly the Arbitration Act 1996,1 (subject to the agreement has
been concluded in writing)2 and the governing London Maritime Arbitration Association
(LMAA) Terms applies in the present dispute.3
21. Furthermore, the Charterparty incorporates the fixture recap and the Rider Clause with
the New York Produce Form 2015 (NYPE)4 which nevertheless also signify that English Law
in accordance to the Arbitration Act 1996 and the LMAA terms, subject to the intended London
is selected by the parties, is applicable in the present dispute.5 Therefore, the arbitration
agreement has been valid.
B. The Tribunal has the authority to determine its own jurisdiction
22. Under the assertion of Clause 30 (1) of Arbitration Act, the tribunal may rule on the
basis of principle kompetenz-kompetenz, which enables them make at least a provisional
assessment of its own competence or the substantive jurisdiction in the relevant matter.6
Therefore, this Tribunal has the authority to determine its own jurisdiction.
C. This Tribunal was not properly constituted
1 Channel Tunnel Group Ltd v Balfour Beatty Construction Ltd [1993] AC 334, P.357-8, [1993] 1 Lloyd’s Rep
291 (H.L.), P.303–4. 2 Arbitration Act 1996, Section 5 (1). 3 LMAATerms 2017, Section 6. 4 Moot Scenario, Fixture Recap, P.5. 5 NYPE 2015, Clause 54 (b). 6 Arbitration Act 1996, section 30 (1); Bruce Harris, Arbitration Act 1996 Commentary, (Blackwell Publishing,
4th ed., 2007), P.151; Neil Andrews, Arbitration and Contract Law Common Law Perspectives, (Springer
International Publishing, Switzerland, 2016) , P.11, P.40; Peter Aeberli, “Jurisdictional Disputes under the
Arbitration Act 1996: A Procedural Route Map”, (2005) ARBITRATION INTERNATIONAL Vol. 21 No. 3, P.253.
Team 18 Memorandum for Respondent
5
23. Party may raise any jurisdictional issue and challenge for the lacking of the substantive
jurisdiction of the tribunal if they have not been properly constituted,7 which in any event
would involve the concerns of whether the contractual or statutory requirements governing
appointment of the tribunal have been complied with.8 In the matter at hand, the Charterers
submit that this Tribunal has not been properly constituted for that the Owners have failed to
meet the requirements to properly; (a) appoint the arbitrators and in any event to (b)
commenced the proceedings appropriately.
a. Owners’ appoinment of arbitrators have failed to meet the requirements
of the Charterparty
24. As stipulated in Clause 80 of the Charterparty, the Parties agreed that any disputes
between them: “shall be referred to three persons, one to be appointed by each of the parties
hereto”.9
25. Admitedly, where the arbitration agreemet is to agree on the appointment of three
person, each party shall serves request in writings to the other party to appoint one arbitrator
for themselves.10 The Owners had provided the Charterers with the notice to arbitrate, however
such notice was merely to invite the Charterers to agreed into the appoinment of their
arbitrators, as the sole arbitrator to settle the dispute at hand.11 Therefore, the notice of
arbitration which was sent by the Owners inviting the Charterers to agreed on the nomination
of sole arbitrator has been disregarding the provision of Clause 80 for that the tribunal should
be adjourned by three persons, not a sole arbitrator.
7 Clare Ambrose, London Maritime Arbitration(Routledge, fourth edition, 2018), para. 6.9-10, P.79; Arbitration
Act 1996, Section 31 (1). 8 Clare Ambrose, London Maritime Arbitration(Routledge, fourth edition, 2018), para. 6. 17, P.81; Minermet SpA
Milan v Luckyfi eld Shipping Corporation SA [2004] 2 Lloyd’s Rep 348 (Comm) 9 Moot Scenario, Rider Clause, P.15. 10 Arbitration Act 1996, Section 16 para. 5 (a); LMAA 2015, Section 8 (b) (i). 11 Moot Scenario, Email of 16 October 2018, P.61.
Team 18 Memorandum for Respondent
6
26. In any event, if the Owners argues that the appoinment of sole arbitrator was intended
to “limit the cost involved in arbitrating (parties’) disputes” through the Small Claims
Procedure’s mechanism under Clause 102 of the Charterparty,12 the Charterers contends that
in any event Owners would not still be able to resolve the dispute at hand in such manner for
that the value of damages it claimed (worth USD 15,426,567.42)13 would surpassed the
required limits of USD 100,000 under the LMAA Small Claims Procedure.14 Therefore,
Owners’ intended appoinment of sole arbitrators would not be justifiable in any way.
b. In any event, Owners have failed to commenced the proceedings
appropriately
27. Clause 14 (1) of the Arbitration Act 1996 asserts that: parties are free to agree when
arbitral proceedings are to be regarded as commenced15 and, nevertheless, if no such agreement
has been made, the remainings of Clause 14 is to apply.16
28. Accordingly, where the arbitrators are to be appointed by the parties, Clause 14 (4) of
the Arbitration Act 1996 affirms that: “arbitral proceedings are commenced in respect of a
matter when one party serves on the other party or parties notice in writing requiring him or
them to appoint an arbitrator or to agree to the appointment of an arbitrator in respect of that
matter.”17 Nevertheless what lies in the notice of arbitration would have to be in accordance
with the construed composition of the arbitrators which already been agreed.18
29. Consequently a notice in writing that was sent by the parties is to be regarded that they
were invoking the arbitration agreement and requires the other party to take steps in response
12 Moot Scenario, Rider Clause, P.18. 13 Moot Scenario, Claim Submission, para.22, P.69. 14 Moot Scenario, Rider Clause, P.18; LMAA Small Claims Procedure 2017, Section 1 (a), P.2. 15 Arbitration Act 1996, Section 14 (1). 16 Arbitration Act 1996, Section 14 (2). 17 Arbitration Act 1996, Section 14 (4). 18 Villa Denizcilik Sanayi ve Ticaret AS v. Longen SA (The ‘Villa’) [1998] 1 Lloyd’s Rep. 195; Bruce Harris,
Arbitration Act 1996 Commentary, (Blackwell Publishing, 4th ed., 2007), P.88.
Team 18 Memorandum for Respondent
7
to enable the tribunal to be constituted,19 and thus failure to invite the other party to appoint
their arbitrators renders the notice to be invalid.20
30. The Charterers argues that the Owners have failed to properly notify them in initiating
the arbitration for that the notice of arbitration which was sent was merely to invite them to
agreed on the appoinment of Ms. Walker as the sole arbitrator,21 while the agreed terms under
Clause 80 of the Charterparty requires any dispute arises among the Charterparties to be settled
by three persons.22 Therefore, the Owners had failed to properly commenced the proceedings
for that the notice of arbitration that was sent to the Charterers was invalid.
D. Alternatively, the Tribunal has the authority to grant Charterers’ claim for
damages
31. If nevertheless, this Tribunal decided for themselves that they bear the substantive
jurisdiction to rule and to settle this present dispute, the Charterers submit that Clause 80 of the
Charterparty would extend to any “dispute arise between Owners and the Charterers”.
Accordingly, an arbitration agreement would needed to be seen as a agreement to submit
present or future dispute to arbitration, whether they are contractual or not.23 Furthermore,
English law consolidates a modern pattern of liberal interpretation of arbitration agreements
which consequently would allow to covers a wide set of disputes concerning contract and its
19 Allianz Versicherungs-AG v. Fortuna Co Inc (The ‘Baltic Universal’) [1999] 1 Lloyd’s Rep. 497 20 Vosnoc Ltd v Trans Global Projects Ltd [1998] 1 Lloyd’s Rep 711, P.712; Allianz Versicherungs-AG v. Fortuna
Co Inc (“The Baltic Universal”) [1999] 1 Lloyd’s Rep 497, P.503; Charles M Willie & Co (Shipping) Ltd v Ocean
Laser Shipping Ltd (The ‘Smaro’) [1999] 1 Lloyd’s Rep 225. 21 Moot Scenario, Email of 16 October 2018, P.61. 22 Moot Scenario, Rider Clause, P.15. 23 Arbitration Act 1996, Section 6 (1).
Team 18 Memorandum for Respondent
8
performance.24 Hence, in this Case, the claims for damages raised by the Charterers, including
to raise set-off against Owners’,25 are arbitrable before this Tribunal.
ARGUMENTS ON THE MERITS OF CLAIM
II. CHARTERERS ARE NOT LIABLE TO THE CLAIMS ARISES OUT OF THE HULL
CLEANING
A. Owners were deemed to agree to bear the risk for the hull cleaning cost on its
own
32. Shipowners may sought to be indemnified for damages suffered as consequences of
complying with the charterers’ order so long as it would only be extended to orders that exposes
them to risks it have not been consented to bear.26 Nonetheless, what risks that the Owners be
reckoned to bear must be depend on the true construction of the Charterparty.27
33. Clause 83 (d) of the Charterparty asserts that if the Charterers are to ever been prevented
from performing the hull cleaning prior to the redelivery, both parties shall “agreed a lump
sum in full and final settlement of Owners’ expenses” in lieu for the cost arises from the
aforementioned.28
24 Capital Trust Investments Ltd v. Radio Design TJ AB [2002] CLC 787, para.[50] -[52]; Fiona Trust and
Holding Corporation v. Privalov [2007] 2 Lloyd’s Rep 267, para. [17]; Ashville Investments Ltd v. Elmer
Construction Ltd [1989] QB 488; CAHarbour Assurance Co (UK) Ltd v. Kansa General International
Insurance Co Ltd [1993] QB 701, CA; AMEC Civil Engineering Ltd v. Secretary of State for Transport [2015] 1
WLR 2339, P. 31. 25 Alexis Mourre, “The Set-Off Paradox In International Arbitration”, (2008) Arbitration International, Vol. 24,
No.3 LCIA, P.396. 26 Triad Shipping Co. v. Stellar Chartering and Brokerage Inc. (The "Island Archon"), [1994] 2 Lloyd’s Rep. 227,
(C.A.), P.237, Action Navigation inc v. Bottiglieri Navigation sp, [2005] EWHC 177 (Comm) Case No: 2004 F.
617, para. [25]-[30], Whistler International Ltd. v. Kawasaki Kisen Kaisha Ltd. ("The Hill Harmony"), [2001] 1
Lloyd’s Rep. 147, P.158, A/B Helsingfors Steamship Co. v. Rederiaktiebolaget Rex ("The White Rose"), [1969] 1
W.L.R. 1098. 27 Triad Shipping Co v Stellar Chartering & Brokerage Inc (The Island Archon) (CA) [1994] 2 Lloyd’s Rep 227,
P.236. 28 Moot Scenario, Rider Clause, P.16
Team 18 Memorandum for Respondent
9
34. The Charterers were indeed been prevented from performing the hull cleaning
obligations for the Wahanda port was unable to do so,29 and further, the Owners had never
acknowledged Charterers’ offer to have the Vessel be cleaned at the North Titan Port.30
Furthermore, the Owners had been repeatedly rejected the preposition which Charterers had
made for the lump sump in lieu for the cleaning of the Vessel.31 As both parties have been
explicitly consented to the terms governed under the Charterparty,32 the Owners are deemed to
agreed to bear the costs for the hull cleaning by themself and was not entitled to be indemnified
for such costs.
B. Alternatively, Charterers would only be liable for the reasonable cost for the
hull cleaning
a. The reasonable cost for the hull cleaning is USD 33,000.
35. Damages accrued for the purpose of making good of the loss should be based on
‘reasonableness’ and if the interest charges were unreasonable, they were not damages for
which the other party is to be liable.33 Furthermore, damage would not be reasonable if it was
charged in greater sum than those which he reasonably needs to expend for the purpose of
making good the loss.34
36. The Owners submit that the proper cost for the hull cleaning of the Vessel would be
those which they’ve spent for the service of such in the South Island at the price of USD
41,000.00 (and an additional USD55,567.42 for the cost to travel there), while they would have
29 Moot Scenario, First and Second Email of 25 May 2016, P.26; Procedural Order No.2, para.6, P.81. 30 Moot Scenario, Third Email of 27 June 2016, P.39. 31 Moot Scenario, Second Email of 8 June 2016, Third Email of 27 June 2016, First Email of 30 June 2016, P.29,
P.39, P.42-3. 32 Storer v. Manchester City Council [1974] 1 W.L.R. 1403, P.1408H. 33 Compania Financiera "Soleada" S.A., Netherlands Antilles Ships Management Corporation Ltd. And Dammers
And Van Der Heide's Shipping And Trading Co. Ltd .v. Hamoor Tanker Corporation Inc (“The Borag") [1981] 1
Lloyd’s Rep. 483, P.488, P.491; [1981] 1 W.L.R. 274, P.281, P.285. 34 Darbishire v. Warrin [1963] 1 W.L.R. 1067, P.1075
Team 18 Memorandum for Respondent
10
been able to done the same in the North Titan at the lower price of USD 33,000.35 Under the
consideration that both South Island and North Titan would have been able to provide hull
cleaning service of the Vessel,36 and the fact that North Titan would’ve been able to provide
such service at a much reasonable price of USD 33,000, the Charterers submit that they would
only be liable to the reasonable cost of the hull cleaning at the price of USD 33,000.
37. Further, if the Owners wish to assert that the proper cost of the hull cleaning would
worth USD 41,000.00 (and an additional USD55,567.42 for the cost to South Island) under the
basis of ‘cost of cure’, the Charterers submit that they would have not be able recover those
damages on a ‘cost of cure’ basis if that cost is disproportionate to the financial consequences
of the deficiency.37
b. The Charterers are not liable for the travel cost for the hull cleaning
38. Shipowners are not entitled to recover expenses incurred for the course of ordinary
navigation eventhough such expenses would be those which arises out of its compliance to the
charterers orders, for such connection are deemed to be too remote.38 The Owners argues that
the Charterers are liable for the USD55,567.42 expenses arises out of the cost of the voyage to
South Island in order to perform hull cleaning,39 however the loss in such amount is not
recoverable since it would only be incurred as usual expenses in its ordinary course.
39. Furthermore, the recoverable loss in any case is limited to that which can be said to be
"properly caused by the defendant’s breach of duty”.40 In this Case, the loss arises out of the
cost to the South Island would not be properly caused by the failure of the Charterers to perform
35 Moot Scenario, Email of 23 June 2016, P.35. 36 Procedural Order No.2, para.6, P.81. 37 Channel Island Ferries Ltd. V. Cenargo Navigation Ltd. (The "Rozel") [1994] 2 Lloyd’s Rep. 161, P.168, 38 Actis Co. Ltd.V. The Sanko Steamship Co. Ltd. (The "Aquacharm") [1980] 2 Lloyd’s Rep. 237, P.244-P.245;
Weir and Others v. Union Steamship Co. Ltd. [1900] A.C. 525; Triad Shipping Co.V. Stellar Chartering &
Brokerage Inc. (The "Island Archon") [1994] 2 Lloyd’s Rep. 227, P.235. 39 Moot Scenario, Claim Submission, para.22(2), P.69. 40 Sotiros Shipping Inc. And Aeco Maritime S.A.V.Sameiet Solholt (The "Solholt") [1983] 1 Lloyd’s Rep. 605,
P.608; Duke of Westminster v. Swinton, [1948] 1 K.B. 524, P.534.
Team 18 Memorandum for Respondent
11
the hull cleaning of the Vessel, but merely arises out of the Owners’ own intention to have the
Vessel be cleaned at the South Island, after it has been re-delivered.41 Hence, the Charterers
are not liable to the travelling cost for the South Island.
III. CHARTERERS ARE NOT RESPONSIBLE TO THE DAMAGES ARISES OUT OF THE LATE
RE-DELIVERY
A. Charterers were only liable for the lost in the period of the overrun
a. There isn’t any applicable market rate for differences in the period of
overrun
40. Damages incurred out of late re-delivery of a vessel shall be restricted to those arises
from the differences out of the charter hire rate and the market hire rate for the overrun period.42
Particularly, such differences shall only be construed upon the market hire rate similar to the
voyage on which the ship was engaged at period of the overrun.43 In the Case at hand, with
absence of plea from the Owners to such applicable market rate, such estimation should not be
stand.
b. In any event, Charterers have already paid hire for the period of overrun
accordingly
41. Nevertheless, where there are no equivalent market hire rate to be compared during a
certain period of the overrun, the damages shall be extend in the same financial position as if
the charter had been performed, as if the vessel had been re-delivered on the last permissible
day.44 Consequently, as evinced by the Full Hire Statement,45 the Charterers have appropriately
completed the payment for the hire up to the period where the Vessel had been re-delivered
on the 30.06.206.
41 Moot Scenario,FHS, P.52. 42 Transfield Shipping v. Mercator Shipping (The Achilleas) [2008] 2 Lloyd’s Rep. 275 (H.L.) , P.2. 43 Ibid. 44 Terence Coghlin et.al, Time Charters, (Informa Routledge, seventh edition, 2014), P.103. 45 Moot Scenario, FHS, P.52.
Team 18 Memorandum for Respondent
12
B. Charterers are not liable to the loss arises out of the Lost Fixture
42. The Owners argues that Charterers were to be held liable for the loss resulted from the
Lost Fixture. However, for a breaching party to be deemed liable for such damages, it must
be held that; (a) such loss was within the assumed reponsibility arises out of the Charterparty
from the start,46 and (b) such loss would be within their particular knowledge.
a. The loss was not under Charterers’ assumed responsibility arises out of
the Charterparty
43. The extent of responsibility shall only be implied upon the expressed contractual
obligation47 construed at the making of the contract.48 Such liability in any way cannot be
imposed to a breaching party on greater risk than what they could reasonably have thought be
undertaken.49
44. The express contractual duty of the Charterparty, precisely stipulates that the period of
trip was for about “50-55 days WOG”,50 hence it must be seen that their assumption of
responsibility the Charterers had been undertaken was restricted to the fixing of the trip in such
duration.51 Nowherere in the Charterparty that governs any additional responsibility for the
Charterers should there been any breach of obligations that would affects Owners’ performance
of its future fixture.
45. Assuming otherwise that there would be any occurence of late re-delivery, the
Charterers submit that, at best, such obligations would only be restricted to the reponsibility
46 Transfield Shipping v. Mercator Shipping (The Achilleas) [2008] 2 Lloyd’s Rep. 275 (H.L.) para.12, P.8; South
Australia Asset Management Corpn v York Montague Ltd [1997] AC 191,P.211-2; Satef-Huttenes Albertus SpA
v Paloma Tercera Shipping Co SA (The Pegase) [1981] Lloyd’s Rep 175, P.183; Mulvenna v Royal Bank of
Scotland plc [2003] EWCA Civ 1112. 47 South Australia Asset Management Corpn v York Montague Ltd [1997] AC 191, P.212. 48 Satef-Huttenes Albertus SpA v Paloma Tercera Shipping Co SA (The Pegase) [1981] Lloyd’s Rep 175, P.183. 49 South Australia Asset Management Corpn v York Montague Ltd [1997] AC 191, at 212.; C Czarnikow Ltd v
Koufos (The Heron II) [1969] 1 AC 350, P.382-3. 50 Moot Scenario, Fixture Recap, P.4. 51 Continental Pacific Shipping Ltd.v. Deemand Shipping Co. Ltd. (The Lendoudis Evangelos II) [1997] 1 Lloyd’s
Rep. 404, P.406.
Team 18 Memorandum for Respondent
13
arises out of the ordinary circumstances from the occurence of the breach iself,52 which would
extend merely to the liability for the hire in the period of overrun.53 Hence, the Charterers are
not to be held liable for the loss arises out of the Lost Fixture, since it was beyond its assumption
of responsibility it was undertaking.
b. Charterers had no particular knowledge of the Next Fixture
46. Charterers might be held liable to the loss arises out of special circumstances, i.e,
extraordinary circumstances beyond the reasonable prevision of the parties,54 only if they had
particular knowledge to the occurence of such circumstances, which would have been
communicated between the parties.55
47. Particularly, knowledge for the special circumstances should be those which enables
them to reasonably foresse loss that would arises as a result from a breach,56 which usually can
be seen if the Owners drews the Charterers’ attention to the existence of a forward charter of
many months’ duration for which the vessel had to be delivered on a particular date.57
48. The only information the Charterers had acquired on the fixing of the Vessel for the
Next Fixture was the one that provided on the 26.06.2016, which merely asserted that the
Vessel would be “fixed for her next voyage (to load East Coast range)".58 Nowhere however
that it expressly asserts any particular laycan date of the Next Fixture, or even to notify the
duration of the Next Fixture and the potential loss of fixture it might harm from the late re-
delivery.
52 Hadley v Baxendale (1854) 9 Exch 341, P.354; Transfield Shipping v. Mercator Shipping (The Achilleas) [2008]
2 Lloyd’s Rep. 275 (H.L.) para.36., P.14; Victoria Laundry (Windsor) Ltd v Newman Industries Ltd [1949] 2 KB
528, P.539-40.
Transfield Shipping v. Mercator Shipping (The Achilleas) [2008] 2 Lloyd’s Rep. 275 (H.L.), P.2. 54 Monarch Steamship Co Ltd v Karlshamns Oljefabriker (A/B) [1949] AC 196, P.221. 55 C Czarnikow Ltd v Koufos (The Heron II) [1969] 1 AC 350, P.411A-C; Hadley v Baxendale (1854) 9 Exch 341,
P.354-6; Banco de Portugal v Waterlow & Sons Ltd [1932] AC 452, P.474-5. 56 Robophone Facilities Ltd v Blank [1966] 1 WLR 1428, P.1448 57 Transfield v Mercator (House of Lords), [2008], para.59 58 Moot Scenario, Email of 26 June 2016, P.34.
Team 18 Memorandum for Respondent
14
49. Furthermore, eventhough the fixture had been concluded by the Owners long before at
15.06.2016, the information was merely provided to the Charterers two days before the laycan
would have elapsed, which was on 28.06.2016. Therefore, the Charterers submit that they could
not have reasonably foreseen the loss arises out of the Next Fixture for they doesn’t have any
particular knowledge of it.
C. Alternatively, the maximum period of 4 years was too remote
50. In any event, if this Tribunal wish to asserts that the Charterers are to be held liable to
the loss arises out of the Next Fixture, the Charterers argues that they would only be liable for
the loss in the relevant period of the minimum of two years and not to the maximum period of
four year, for that such damage in the latter will be deemed as too remote.59
51. For certain loss to be deemed not too remote, there must exist direct causative
connection between the breach occurs to the benefits realized,60 and it cannot be for merely
provides such opportunity to occurs.61 The contracts undertaken by the Owners under the Next
Fixtures asserts that the fixing of the trip would be “FOR 2 YR CHARTER WITH 2 YR
EXTENSION IN CHOPT”.62 In the case where, the charter period was described as two
alternative lengths of time it was generally assumed that the the shorther period was the primary
or default period.63
52. Here, eventhough the occurence of late re-delivery of the Vessel corresponds to the
performance of the Next Fixture, it would only directly affects the certain fixing for the
minimum period of 2 years. The maximum period of 4 is not directly affected by such
occurence of late re-delivery since the fixing of trip is likely to occurs only if Champions chose
59 Mulvenna v Royal Bank of Scotland Plc [2003] EWCA Civ 1112; [2004] CP Rep 8, para.[33]. 60 Fulton Shipping Inc of Panama v Globalia Business Travel SAU (The New Flamenco) [2014] EWHC 1547,
para.[64]. 61 Galoo Ltd v Bright Grahame Murray [1994] 1 WLR 1360. 62 Moot Scenario, Next Fixture, P.31. 63 Empresa Cubana de Fletes v. Aviation & Shipping [1969] 2 Lloyd’s Rep. 257; Shipping Corporation of India
Ltd. v. NSB Niederelbe Schiffahrtsgesellschaft M.B.H & Co. (The “Black Falcon”) [1991] 1 Lloyd’s Rep. 77
Team 18 Memorandum for Respondent
15
to asserts so.64 Hence, the Charterers are not liable since such breach are not directly affects
the benefits realized in the maximum period.
D. Further in the alternative, Owners must give credit for the profit realized by
the Replacement Fixture
53. Shipowners is not entitled to recover any damages incurred a consequences for
repudiation by the charterers when the wrongful acts would have enabled the shipowners to
make a profit on a more lucrative subsequent fixture or even having their ship free in the right
place at the right time to take a spot fixture on a rising market.65 Accordingly, as the results of
missing the hiring for the Next Fixture to the Champion in the daily hire rate of USD 10,500,66
the Owners have been able manage to secure a more lucrative Replacement Fixture from the
Fairwind at the daily hire rate of USD 11,000.67 Therefore, the Owners are not entitled to
charges the Charterers for the loss incurred for they should have take credits for the profit
realized from the Replacement Fixtures.
IV. ALTERNATIVELY, CHARTERERS ARE ENTITLED TO SET OFF ITS COUNTERCLAIM
AGAINST ANY SUMS THEY FOUND IS LIABLE TO THE OWNERS
54. Charterers have the rights to deduct or set off against claims for damages brought by
the Owners where there is a breach of the Charterparty, on the Owners’ account, which had
deprived them or prejudiced them in their use of the ship in whole or in part.68 In this Case, the
Charterers have the right to set off its claim for damages against Owners’ for the fact that; first,
64 Moot Scenario, Next Fixture, P.31. 65 Torvald Klaveness A/S V. Arni Maritime Corporation (The "Gregos") [1995] 1 Lloyd’s Rep 1, P.10; Transfield
Shipping v. Mercator Shipping (The Achilleas) [2008] 2 Lloyd’s Rep. 275 (H.L.), para.57,P.21. 66 Moot Scenario, Next Fixture, P.32. 67 Moot Scenario, Replacement Fixture, P.55. 68 SL Sethia Liners Ltd. v. Naviagro Maritime Corporation (The "Kostas Melas") [1981] 1 Lloyd’s Rep. 18, P.26
Team 18 Memorandum for Respondent
16
such claims arises out of the same transaction69 and second, they have been deprived or
prejudiced in the use of the Vessel.70
55. First, claims for set off would only be invoked to the cross-claim which was flowed out
of and was inseparably connected with the dealings and arise out of the same transactions
giving rise to the claim,71 and in any event it would be manifestly unjust to allow him to enforce
payment without taking into account the cross-claim.72 In this Case, similar to the claims
brought by the Owners, the Charterers wish to set off its counter-claim against Owners’ which
were resulted from the transactions under the Charterparty, particularly, for the occurence of
off hire, under the assertion of Clause 17 of the Charterparty, and to the Cargo Claims, which
arises under Clause 27 and 53 of the Charterparty.
56. Second, that the charterers have been deprived or prejudiced in the use of the ship.73 In
the Case at hand, Owners have been acting in breach of the Charterparty which resulting into
the the Charterers to deprived and subsequently claiming for damage for the occurence of off-
hire and damage to the cargo.74
ARGUMENTS ON THE MERITS OF COUNTER-CLAIM
V. CHARTERERS ARE ENTITLED TO BE INDEMNFIED FOR THE CARGO CLAIM
A. The Cargo Claim has been validly raised
57. Clause 4 of the ICA stipulates provision for which cargo claims are to be deemed as
validly apportioned. Accordingly, under the assertion of Clause 4 (a), (b) and (c), a cargo claim
would be validly raised where, in sequence, first, such claim was; “made under a contract of
69 Boston Bank of Connecticut v European Grain and Shipping Ltd (The Dominique) [1989] 1 Lloyd’s Rep 431,
P.438. 70 Federal Commerce LTD v Molena Alpha INC (The” Nanfri) [1978] 2 Lloyd’s Rep. 132, P.140. 71 Government of Newfoundland v The Newfoundland Ry Co. (1888) 13 App Cas 199.; Boston Bank of Connecticut
v European Grain and Shipping Ltd (The Dominique) [1989] 1 Lloyd’s Rep 431, P.438. 72 Federal Commerce & Navigation Co Ltd v Molena Alpha Inc (The Nanfri) [1978] 2 Lloyd’s Rep 132, P.140.;
Geldof Metaalconstructie NV v Simon Carves Ltd. [2011] 1 Lloyd’s Rep 517, para 43. 73 Federal Commerce Ltd. v. Molena Alpha INC (The” Nanfri”) [1978] 2 Lloyd’s Rep. 132, P.140-1 74 Moot Scenario, Counterclaim, para. 15 (1) and (2), P.74.
Team 18 Memorandum for Respondent
17
carriage, whatever its form”75, second, that “the cargo responsibility clauses in the
charterparty have not been materially amended…”,76 and third, that such claim has been
“properly settled or compromised and paid.”77 Here, the Charterers are to submit that the
Cargo Claim which was to be raised against the Owners has been in compliance with such
requirements.
58. First, that the claim was made under the assertion of contract of carriage. In the present
Case, the Cargo Claims has been validly purported by both the Charterers and the Receivers,
under the agreed terms of the Bills of Ladings.78
59. Second, that cargo responsibility has not been materially amended. Accordingly, only
amended terms such as the addition of “cargo claims” to the second sentence of clause 26 of
the Charterparty would only be regarded as such materially amandment which prevail a cargo
claim,79 and accordingly such amandment has not been done so in the present dispute.
60. Third, that the claim has been properly settled and paid. As governed under the
provision of Clause 3 (c) of the ICA, “settlement of the claim made by the original person”
would be regarded as sufficient for a cargo claim to be validly raised.80 In this Case, the
Receivers had validly raise the cargo claim within the granted provided by the Charterers and
in doing so the Charterers and the Receivers had both agreed on the quantum of Receivers’
claim in respect of the claims which are to be raised by the Charterers against the Owners.
B. The Cargo Claim was not time-barred
61. Under the assertion of Clause 6 of the ICA, recovery under the provision is deemed to
be waived if it has not been properly served with the written notification in doing so under the
24 months limitations of the re-delivery, which shall comprises of the“details of the contract
75 ICA, Clause 4 (a). 76 ICA, Clause 4 (b). 77 Ibid., Clause 4 (c). 78 Moot Scenario, Email of 23 November 2017, P.57. 79 ICA, Clause 4 (b) (ii). 80 Ibid., Clause 3 (c).
Team 18 Memorandum for Respondent
18
of carriage, the nature of the claim and the amount claimed.”81 In the Case at hand, the
Charterers submit that they have validly invoke such written notification just before the
limitation for such had elapsed, on the 30th of June 2018, by the means of the Mekon Report’s
attached, the bills of ladings and the letters provided to the Owners, which all have been sent
as latest as 23 November 2017.82
62. Accordingly, nature of the claim is to be seen where the notification provide “what is
being claimed and the basis of it by reference to – namely the form and substance of the
claim”.83 In this case, the Charterers have already explicitly mentioned, and also attached a
report, that the extent of the damage of the cargo and those being being claimed are to be
referred to the based on the findings of the Mekon Report.84 Furthermore, the Charterers and
Owners have already agreed that the Cargo Claim is to be settled under the references of the
mechanisms for Cargo Claims recognized under the Charterparty which is the ICA.85
63. Furthermore, what is regarded as amount claimed refers to calculation on the part of
of the loss which is allegedly suffered.86 Wherein even if cargo interests have not been
accompanied with details of the claim amount, the estimation for the extent of damage can be
calculated from alternative sources of the information, such as market price information for the
cargo.87. In this case, the figure of the damage claimed had been had been calculcated at the
estimation of USD 60 to USD 65 per kilo, by the findings of the Mekon Report.88
64. Therefore, proving that the written notification have been delivered just before the time
extension expires and the written notification provided had been in compliance extent to the
nature of the requirement under provision of Clause 6 of the ICA.
81 Ibid., Clause (6). 82 Moot Scenario, Email of 7 July 2016, Mekon Reports, Emails of 23 May-23 November 2017, P.45-6, P.57-8. 83 Laminates Acquisitions v BTR Australia Limited [2004] 1 All ER (Comm) 737. 84 Moot Scenario, Email of 7 July 2016, P.45. 85 Moot Scenario, Rider Clause, para.53, P.10. 86 Laminates Acquisitions v BTR Australia Limited [2004] 1 All ER (Comm) 737 87 Ipsos S.A. v Dentsu Aegis Network Limited [2015] EWCH 1171 (Comm). 88 Moot Scenario, Mekon Report, P.46
Team 18 Memorandum for Respondent
19
C. Owners is liable for 100% of the Cargo Claim
65. Pursuant to Article 8 (a) of the Inter-Club NYPE Agreement (ICA), in case of a
“unseaworthiness and/or error or fault in navigation or management of the vessel”, the cargo
claims shall be apportioned 100% for the Owners’s account.89
66. Accordingly, a seaworthiness is to be regarded when the vessel, her crew and her
equipment is sound and able in encountering and withstanding the ordinary perils of the sea
during the contemplated voyage, which particullarly can be seen where the damages to the
cargo arose out of the negligence of the crew, in failing to perform at the standard reasonably
expected on them,90 and that the vessel shall be suitable to carry the contract cargo, or cargo-
worthy.91 Whereas presence of seawater in the hold are normally treated as prima facie
evidence of unseaworthiness.92
67. The fact that seaworthiness is a combination of two factor, can mean that the vessel is
seaworthy with regards to physical, human and documentary seaworthiness but is uncargo-
worthy93 or vice versa, therefore if such vessel was delivered at the port of loading, the fact
that it is seaworthy in one respect but not the other will mean that the shipowners has failed to
exercise his duty to make the vessel seaworthy.94
68. In the Case at hand, the damage to the cargo occurs due to the improper use of ballasting
system by the crew wherein the crew opened the wrong valves during the ballasting operation
prior to the discharhing of the cargo, resulting into water ingress towards the lower hold No.2,
causing damage towards the cargo.95 Therefore, the Charterers submit that the Owners are to
liable for 100% of the Cargo Claim under the provision of Clause 8 (a) of the ICA.
89 ICA , Clause 8 (a). 90 Standard Oil v Clan Line [1924] AC 100, P.121. 91 Actis Co. Ltd.V. The Sanko Steamship Co. Ltd. (“The Aquacharm”) [1982] 1 Lloyd’s Rep. 7, P.11 92 John Wilson, Carriage of Goods by Sea, (Longman, seventh edition, 2010), P.13 93 Read v. Page, [1927] 1 K.B. 743, P. 754 94 Ahmad Hussam Kassem, The Legal Aspects of Seaworthiness: Current Law and Development, (Swansea
University, 2006), P.53. 95 Moot Scenario, First Email of 27 June 2016,P.38, Mekon Report, P.46.
Team 18 Memorandum for Respondent
20
D. Alternatively, Owners is liable for the Cargo Claim in like amounts
69. If this Tribunal is to find that the Owners are not liable to the apportionment for 100%
of the Cargo Claims under the provision of Clause 8 (a) of the ICA, the Charterers contended
that in any event the Owners would still be liable to damages in like amount.
70. Pursuant to Clause 27 and Clause 53 of the Charterparty both the Owners and the
Charterers agreed that any liability for cargo claims “shall be apportioned as specified” under
the mechanisms of the ICA.96 Accordingly, as asserted in the sub-argument VI (B) of this
written submission, the Respondent submits that the Cargo Claims solemnly arise out of
damages to the cargo97 resulting from the unseaworthiness of the Vessel for which, under the
provision of Clause 8(a) of the ICA, shall be apportioned 100% for the Owners’ account.98
Consequently, Owners are liable towards the damage of the cargo in like amounts (to be
quantified) for the unseaworthiness and/or error or fault in management or the navigation of
the vessel, pursuant to the agreed provision of Clause 27 and 53 of the Charterparty.
E. Further in the alternative, Owners is liable for 50% of the Cargo Claim
71. The liability for the cargo claims under the provision of Clause 8(b) of the ICA incurs
where claims in fact arising due to the: “loading, stowage, lashing, discharge, storage or other
handling of the Cargo.”
72. Furthermore, Clause 8 (b) of the ICA asserts that where there is an amandment to the
Charterparty, adding words "and responsibility" to Clause 8 of the Charterparty or any similar
amendment making the Master responsible for cargo handling, hence the shipowners were
deemed liable to the 50% of the cargo claim.99 Accordingly, the addition of these words
resulted into a prima facie transfer of liability from the charterers back to the shipowners if
there was ever any case of negligence occurs during the process of loading, stowage, trimming
96 NYPE 2015, Clause 27; Moot Scenario, Rider Clause, P.10. 97 Moot Scenario, Mekon Report, P. 46. 98 ICA, Clause 8 (a). 99 ICA, Clause 8 (b).
Team 18 Memorandum for Respondent
21
or discharging of the cargo, unless it shown otherwise that the charterers have in fact intervened
and in doing so have caused the relevant loss or damage.100
73. In the Case at hand, the Charterparty has been amended with the words “and
responsibility” added after “under the supervision”101 making the Owners liable under the
apportionment of Clause 8 (b). Subsequently, the damage to the cargo was resulted due to the
negligence of the crew during the process of ballasting prior to the discharging of the cargo
and the Charterers have not caused any intervention in the process of such. Consequently, the
Owners are liable for 50% of the Cargo Claim.
VI. CHARTERERS ARE ENTITLED TO RECOVER THE OVERPAID HIRE FOR THE VESSEL
HAS BEEN OFF-HIRE
A. The Vessel was off-hire from 07.05.2016 untill 26.06.2016
74. Clause 17 of the Charterparty asserts that in the case of “loss of time from deficiency
and/or default and/or strike of officers or ratings… or detention by Port State control or other
competent authority for Vessel deficiencies… or by any similar cause preventing the full
working of the Vessel”, the payment of hire shall cease.102 Admittedly, in asserting that the
Vessel would be off-hire under the operative of Clause 17, the Charterers are to elucidate three
reasons:103
75. First, that the Vessel has been prevented from fully working for one of the causes listed
in the Clause 17,104 which in this Case arises from the“detention by Port State control or other
100 Terence Coghlin et.al, Time Charters, (Informa Routledge, seventh edition, 2014), P.361 101 Moot Scenario, Rider Clause, P.5. 102 NYPE 2015, Clause 17. 103 Terence Coghlin et.al, Time Charters, (Informa Routledge, seventh edition, 2014), para.25.6, P.442. 104 Ibid.
Team 18 Memorandum for Respondent
22
competent authority for Vessel deficiencies”,105 reflected through the order to quarantine the
Vessel under the authorization of Wahanda’s Port State Control.106
76. Second, that the full working of the Vessel have been prevented.107 The Charterers
submit that as a result of the quarantine ordered by the Wahanda’s Port State Control, the
Vessel have been prevented from fully working on 07.05.206 up to 26.06.2016.108
77. If nevertheless this Tribunal would not be satisfied with the latter, the Charterers
submits that the operative clause “or by any similar cause preventing the full working of the
Vessel” would also extend to legal or administrative action by a port or other lawful authority
properly or reasonably pursuant to the (suspected) ineficiency or incapacity of the vessel or her
crew.109 Hence, the decision of Wahanda’s Port State Control to having Vessel be quarantined
after the findings of numbers of crew which have been carrying such diseases110 would fell into
the ambit of “by any similar cause preventing the full working of the Vessel”.
78. Third, there has been loss of time as to the occurence of such events.111 Loss of time is
to be understood as interruption or delay in the performance of the service immediately
required.112 Accordingly,the discharging of the cargo in Wahanda was not yet to began from
the moment the Vessel was berthed on 07.05 untill 26.06, where it finally obtain the free
pratique and was finally proceed to discharged the cargo.113 Therefore, such period would
amount to ‘loss of time’.
B. The off hire would not be caused by the Charterer’s fault
105 NYPE 2015, Clause 17. 106 Moot Scenario, First Email of 11 May 206, P.24. 107 Terence Coghlin et.al, Time Charters, (Informa Routledge, seventh edition, 2014), para.25.6, P.442. 108 Moot Scenario, Email of 7 May 2016, P.25; Procedural Order No.2, para.7, P.81. 109 Andre & Cie S.A. .v. Orient Shipping (Rotterdam) B.V. (“The Laconian Confidence”) [1997] 1 Lloyd’s Rep.
139, P.151; Terence Coghlin et.al, Time Charters, (Informa Routledge, seventh edition, 2014), para 25.39.P.450. 110 Moot Scenario, First Email of 11 May 2016, P.24. 111 Terence Coghlin et.al, Time Charters, (Informa Routledge, seventh edition, 2014), para 25.6, P.442. 112 Ibid., para 25.55, P.454. 113 Moot Scenario, Email of 7 May 2016, P.25; Procedural Order No.2, para.7, P.81.
Team 18 Memorandum for Respondent
23
79. The Charterers may not rely on an off-hire clause only if there had been breach of an
express or implied term of the contract properly caused by them which resulted into the loss of
time,114 or if the Charterers was to properly responsible by ommiting to a breach.115
80. Accordingly, a breach of an express or implied term of the contract on the narrower
position would means that the working of the Vessel has been prevented by something which,
under the Charterparty, was the Charterers’ duty to supply.116 In the Case at hand, the
Charterers had accordingly complied with all of their required obligations “to Provide” under
Clause 7 of the Charteparty.
81. If nevertheless this Tribunal would find that the Charterers are ommitting to the fact
that spreading of ebola in the West Coast would have been properly known by them,117 the
Charterers accordingly submit that fault which prevail its off hire claim would only refers to
those which causally connected to the time thereby lost118 which would not be the case here
since the fact of the dissemination of the ebola among the crew was not properly known right
until the Wahanda’s Port Control finally declared so and subsequently took the Vessel to be
quarantined.119 Therefore, the off-hire was not been properly caused by Charterers’ fault.
C. In any event, Charterers is entitled to recover the overpaid hire
82. Subject to Clause 20 of the Charterparty: “should the Vessel be lost, money paid in
advance and not earned (reckoning from the date of loss or being last heard of) shall be
returned to the Charterers at once.”120
83. Accordingly, in the occurence of an off-hire, the Charterers are entitled to recover the
unearned hire on the ground that the consideration for the unearned hire has wholly failed under
114 Board of Trade v. Temperley (1927) 27 Ll.L.Rep. 230, P.232. 115 SIG Berdesen DY and Co. v. Mobile Shipping (“The Berge Sund”) [1993] 2 Lloyd’s Rep. 453, P.462. 116 Terence Coghlin et.al, Time Charters, (Informa Routledge, seventh edition, 2014), para 25.49, P.452. 117 Moot Scenario, News of 18 and 21 April 2016, P.22-3. 118 SIG Berdesen DY and Co. v. Mobile Shipping (“The Berge Sund”) [1993] 2 Lloyd’s Rep. 453, P.462. 119 Moot Scenario, First Email of 11 May 2016, P.24. 120 NYPE 2015,Clause 20.
Team 18 Memorandum for Respondent
24
the occurence of Clause 20.121 Furthermore, if the Owners argues that hire is not recoverable
for the fact that it has been paid in advance, the operative of Clause 20 asserts that hire in
advance is a ‘conditional’ which would means no more than that the payment is not final since
under the contract there is an obligation, express or implied, to repay to the Charterers any part
of the hire payment which has not been earned,122 and give rise to contractual debt in relevant
circumstances by the Owners to the Charterers.123 Therefore, the Charterers are entitled to
recover those overpaid hire, under the provision of Clause 20, for that the hire of the Vessel
which has been paid in advance, in the period where it was been off-hire, was deemed to be
failed.
D. Alternatively, the Owners are liable to damages arises out of the off hire
84. Alternatively, if this Tribunal found that the Charterers would not be able to recover
the overpaid hire under the terms of Clause 20 of the Charterparty, the Charterers submit that
an off-hire which arises out of the breach would in law be entitled to damages.124 Accordingly,
an off- hire clause would not cut down any right that the charterers might have to claim
damages from the Owners if an off hire event has been caused by the Owners’ breach of
charter.125 In the matter at hand, the Charterers submit that the Owners bears with the obligation
to “maintain the Vessel’s class and keep her in a thoroughly efficient state in hull, machinery
and equipment for and during the service”126 and that in the occurence of an off-hire “the
payment of hire and overtime, if any, shall cease for the time thereby lost.”127 Therefore,
121 Stewart v. Van Ommeren [1918] 2 K.B. 560, P.564; Pan Ocean Co. Ltd. v. Creditcorp Ltd. (The “Trident
Beauty”) [1994] 1 Lloyd’s Rep. 365 (H.L.), P.368; Petroleum Shipping Ltd. v, Vatis (trading as Kronos
Management) (“The Riza and The Sun”) [1997] 2 Lloyd’s Rep. 314, P.320-1. 122 Pan Ocean Co. Ltd. v. Creditcorp Ltd. (The “Trident Beauty”) [1994] 1 Lloyd’s Rep. 365 (H.L.), P.369. 123 Terence Coghlin et.al, Time Charters, (Informa Routledge, seventh edition, 2014), P.280. 124 Marbienes Cia. Nav. v. Ferrostaal A.G. (“The Democritos”) [1975] 1 Lloyd’s Rep. 386, P.401. 125 Terence Coghlin et.al, Time Charters, (Informa Routledge, seventh edition, 2014), para 25.74, P.459. 126 NYPE 2015, Section 6 (a). 127 NYPE 2015, Section 17.
Team 18 Memorandum for Respondent
25
Charterers are entitled to claim damages arises out of the Owners’ breach of the Charterparty
in the occurence of an off-hire.
REQUEST FOR RELIEF
For the reasons set out above, the Charterers requests this Tribunal to:
DECLARE that this Tribunal has no jurisdiction to hear the merits of the Owners’s claims;
FIND that the Charterers are not liable to the damages arises out of the hull cleaning cost and
the damages arises out of the late re-delivery, and that the Charterers is entitled to set off its
claims.
FIND that the Owners is liable 100% of the Cargo Claim (to be quantified), alternatively
damages in like amount, and liable the overpaid hire or alternatively damages in like amount
for the occurence of off hire; and
AWARD claims for liability to the Charterers, or alternatively damages, and interest on the
amounts claimed.
INDEX OF ABBREVIATIONSINDEX OF AUTHORITIES1. Cases2. Books and Articles3. Legislations
ARGUMENTS ON JURISDICTIONI. This Tribunal has no Jurisdiction over the Present DisputeA. There is a valid Arbitration AgreementB. The Tribunal has the authority to determine its own jurisdictionC. This Tribunal was not properly constituteda. Owners’ appoinment of arbitrators have failed to meet the requirements of the Charterpartyb. In any event, Owners have failed to commenced the proceedings appropriately
D. Alternatively, the Tribunal has the authority to grant Charterers’ claim for damages
ARGUMENTS ON THE MERITS OF CLAIMII. Charterers are Not Liable to the Claims arises out of the Hull CleaningA. Owners were deemed to agree to bear the risk for the hull cleaning cost on its ownB. Alternatively, Charterers would only be liable for the reasonable cost for the hull cleaninga. The reasonable cost for the hull cleaning is USD 33,000.b. The Charterers are not liable for the travel cost for the hull cleaning
III. Charterers are Not Responsible to the Damages arises out of the Late Re-deliveryA. Charterers were only liable for the lost in the period of the overruna. There isn’t any applicable market rate for differences in the period of overrunb. In any event, Charterers have already paid hire for the period of overrun accordingly
B. Charterers are not liable to the loss arises out of the Lost Fixturea. The loss was not under Charterers’ assumed responsibility arises out of the Charterpartyb. Charterers had no particular knowledge of the Next Fixture
C. Alternatively, the maximum period of 4 years was too remoteD. Further in the alternative, Owners must give credit for the profit realized by the Replacement Fixture
IV. Alternatively, Charterers are Entitled to Set Off its Counterclaim Against Any Sums They Found is Liable to the Owners
ARGUMENTS ON THE MERITS OF COUNTER-CLAIMV. Charterers are Entitled to be Indemnfied for the Cargo ClaimA. The Cargo Claim has been validly raisedB. The Cargo Claim was not time-barredC. Owners is liable for 100% of the Cargo ClaimD. Alternatively, Owners is liable for the Cargo Claim in like amountsE. Further in the alternative, Owners is liable for 50% of the Cargo Claim
VI. Charterers are Entitled to Recover the Overpaid Hire for the Vessel has been Off-HireA. The Vessel was off-hire from 07.05.2016 untill 26.06.2016B. The off hire would not be caused by the Charterer’s faultC. In any event, Charterers is entitled to recover the overpaid hireD. Alternatively, the Owners are liable to damages arises out of the off hire
REQUEST FOR RELIEF