The Henderson HomeTeam B
8/6/2019 Team B Final Presentation
2/19
Background Information
The Hendersons, a young couple are expecting
their first child and in need of a larger home to
facilitate their family
The family desires a home outside of the citylimits
The home must accommodate the future of
the family
The home must have 3 bedrooms, span twofloors and have a 3 car garage
8/6/2019 Team B Final Presentation
3/19
Project Stakeholders
Person or group directly affected by
organizational actions
Project Customer
Mr. and Mrs. Henderson
Managers
Project manager of Team B
Employees
Additional members of Team B Bank
Who has financed project
8/6/2019 Team B Final Presentation
4/19
8/6/2019 Team B Final Presentation
5/19
Project Timeline
May -Inspections
June Site preparation
July - Construction Begins
November Construction Complete
April - Landscaping
8/6/2019 Team B Final Presentation
6/19
Project Budget
Design ($2,500)
Building permits fees ($7,430)
Water & sewage inspections ($3,800)
Basic Construction ($160,350)
Sub-contractor
Foundation ($11,000)
Electrical ($21,650)
Plumbing ($11,850)
8/6/2019 Team B Final Presentation
7/19
ProjectPerformance
Phase One
Design floor plans & elevations
Landscaping
Exterior fixtures Phase Two
Submit plans
Obtain permits
Identify Sub-contractors
Order building materials
8/6/2019 Team B Final Presentation
8/19
ProjectPerformance
Phase Three
Site preparation
Foundation
Framing Phase Four
Determine paint colors
Paint interior
Carpet installation
Tile installation
Phase Five
Landscaping preparation
8/6/2019 Team B Final Presentation
9/19
Statement of Work
Start Date
April 11, 2011
End Date
November 30, 2011
Phases
Planning
Preparation
Building
Interior Design
Landscaping
8/6/2019 Team B Final Presentation
10/19
Project Summary
Provide the Henderson family with the house
that meets their need
The house will be within their budget
The house will be completed within 5-7months
The house will provide adequate room for
the growth of their family
8/6/2019 Team B Final Presentation
11/19
Communication Management
Effective project communications ensure
that we get the right information to the
right person at the right time and in a
cost-effective manner
8/6/2019 Team B Final Presentation
12/19
8/6/2019 Team B Final Presentation
13/19
Matrix Organization Chart
8/6/2019 Team B Final Presentation
14/19
Responsibility Allocation Matrix
Project Manager
Primary Responsibilities
Has Signature
Project Control Manager
Must be Consulted
Team Leaders
May be Consulted
Subcontract Manager
May be Consulted
Design Engineers
May be Consulted
8/6/2019 Team B Final Presentation
15/19
Resource Allocation MatrixID NAME
RESOURCE
Team B SFC GIB RJ ROB KEL
1 Site Work X
2 Foundation X
3
Rough
Carpentry X
4
Concrete
Slabs X
5 HVAC X
6
Plumbing
Rough-In X
7
Electrical
Rough-In X
8 Roofing X
9
Exterior
Finsihes X
10 Insulation X
11 Drywall X X
12
Floor
Finishes X
13 Paint X X
14 Interior Trim X X
15 Landscaping X X
8/6/2019 Team B Final Presentation
16/19
ProjectRevisions
Initial Planning
Surveying of the Land
Procurement of Building Materials
Framing of the House
Plumbing and Electrical Infrastructure
Drywall and Painting
Landscaping
8/6/2019 Team B Final Presentation
17/19
8/6/2019 Team B Final Presentation
18/19
Future Projects
What went right with the project
What went wrong with the project
8/6/2019 Team B Final Presentation
19/19
Conclusion
Successful Project
Satisfied Customer
On Time project
Within in Budget