Team B Final Presentation

Embed Size (px)

Citation preview

  • 8/6/2019 Team B Final Presentation

    1/19

    The Henderson HomeTeam B

  • 8/6/2019 Team B Final Presentation

    2/19

    Background Information

    The Hendersons, a young couple are expecting

    their first child and in need of a larger home to

    facilitate their family

    The family desires a home outside of the citylimits

    The home must accommodate the future of

    the family

    The home must have 3 bedrooms, span twofloors and have a 3 car garage

  • 8/6/2019 Team B Final Presentation

    3/19

    Project Stakeholders

    Person or group directly affected by

    organizational actions

    Project Customer

    Mr. and Mrs. Henderson

    Managers

    Project manager of Team B

    Employees

    Additional members of Team B Bank

    Who has financed project

  • 8/6/2019 Team B Final Presentation

    4/19

  • 8/6/2019 Team B Final Presentation

    5/19

    Project Timeline

    May -Inspections

    June Site preparation

    July - Construction Begins

    November Construction Complete

    April - Landscaping

  • 8/6/2019 Team B Final Presentation

    6/19

    Project Budget

    Design ($2,500)

    Building permits fees ($7,430)

    Water & sewage inspections ($3,800)

    Basic Construction ($160,350)

    Sub-contractor

    Foundation ($11,000)

    Electrical ($21,650)

    Plumbing ($11,850)

  • 8/6/2019 Team B Final Presentation

    7/19

    ProjectPerformance

    Phase One

    Design floor plans & elevations

    Landscaping

    Exterior fixtures Phase Two

    Submit plans

    Obtain permits

    Identify Sub-contractors

    Order building materials

  • 8/6/2019 Team B Final Presentation

    8/19

    ProjectPerformance

    Phase Three

    Site preparation

    Foundation

    Framing Phase Four

    Determine paint colors

    Paint interior

    Carpet installation

    Tile installation

    Phase Five

    Landscaping preparation

  • 8/6/2019 Team B Final Presentation

    9/19

    Statement of Work

    Start Date

    April 11, 2011

    End Date

    November 30, 2011

    Phases

    Planning

    Preparation

    Building

    Interior Design

    Landscaping

  • 8/6/2019 Team B Final Presentation

    10/19

    Project Summary

    Provide the Henderson family with the house

    that meets their need

    The house will be within their budget

    The house will be completed within 5-7months

    The house will provide adequate room for

    the growth of their family

  • 8/6/2019 Team B Final Presentation

    11/19

    Communication Management

    Effective project communications ensure

    that we get the right information to the

    right person at the right time and in a

    cost-effective manner

  • 8/6/2019 Team B Final Presentation

    12/19

  • 8/6/2019 Team B Final Presentation

    13/19

    Matrix Organization Chart

  • 8/6/2019 Team B Final Presentation

    14/19

    Responsibility Allocation Matrix

    Project Manager

    Primary Responsibilities

    Has Signature

    Project Control Manager

    Must be Consulted

    Team Leaders

    May be Consulted

    Subcontract Manager

    May be Consulted

    Design Engineers

    May be Consulted

  • 8/6/2019 Team B Final Presentation

    15/19

    Resource Allocation MatrixID NAME

    RESOURCE

    Team B SFC GIB RJ ROB KEL

    1 Site Work X

    2 Foundation X

    3

    Rough

    Carpentry X

    4

    Concrete

    Slabs X

    5 HVAC X

    6

    Plumbing

    Rough-In X

    7

    Electrical

    Rough-In X

    8 Roofing X

    9

    Exterior

    Finsihes X

    10 Insulation X

    11 Drywall X X

    12

    Floor

    Finishes X

    13 Paint X X

    14 Interior Trim X X

    15 Landscaping X X

  • 8/6/2019 Team B Final Presentation

    16/19

    ProjectRevisions

    Initial Planning

    Surveying of the Land

    Procurement of Building Materials

    Framing of the House

    Plumbing and Electrical Infrastructure

    Drywall and Painting

    Landscaping

  • 8/6/2019 Team B Final Presentation

    17/19

  • 8/6/2019 Team B Final Presentation

    18/19

    Future Projects

    What went right with the project

    What went wrong with the project

  • 8/6/2019 Team B Final Presentation

    19/19

    Conclusion

    Successful Project

    Satisfied Customer

    On Time project

    Within in Budget