PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-010-PP Thursday, February 23, 2017
Rev.1
VENDOR / SUPPLIER RESPONSE
PT. YOKOGAWA INDONESIA PT. PACIFIC PROCESS ENGINEERING
1.0 GENERAL
1.1 BIDDER'S QUOTATION NUMBER QSA17N0003 Rev 4, 9th February 2017 16362-QTN-PPE-II-2017 REV.0, 12th February 2017
1.2 DELIVERY To be specified (Unit : Month) Month of Mei 2017 at site after approval engineering document
12 weeks after PO or 16 weeks if all item as per AML
1.3 VALIDITY To be specified (Unit : Month) 30 days from proposal date 30 days from proposal date1.4 FOB To be specified (Unit : Month)1.5 TERMS OF PAYMENT Engineering Approval 5 %
Fabrication Progress 20 %Factory Acceptance 20 %Material On Site 30 %
After Installation Complete 10 %Site Acceptance Test 10 %
Retention 5 %
Engineering Approval 5 %Fabrication Progress 20 %Factory Acceptance 20 %Material On Site 30 %
After Installation Complete 10 %Site Acceptance Test 10 %
Retention 5 %
5% after Major Engineering Submission (PID, Datasheet, GA Drawing)10% after Raw Material (Pipe, Flange, Fittings, Structural parts) arrived at Fabrication Shop15% after Factory Acceptance Test at Fabrication Shop30% after Material arrival on Site25% after Installation on Foundation or max 1-month after Arrival on Site10% after Testing & Commissioning or max. 2-months after Material Installation5% Retention, can be replaced by 5%-Retention Bond
1.6 COMPLIANCE LIST TO SPECIFICATION Confirmation by Vendor YES YES1.7 DEVIATION LIST Confirmation by Vendor YES YES
2.0 SCOPE OF SUPPLY2.1 GAS SCRUBBER As per technical requirement YES YES2.2 ELECTRICAL & INSTRUMENT ASSEMBLY As per technical requirement YES YES2.3 FLOW COMPUTER As per technical requirement YES YES2.4 PIPE, VALVE & FITTING ASSEMBLY As per technical requirement YES YES2.5 MISCELLANEOUS EQUIPMENT As per technical requirement YES YES2.6 SPARE PARTS FOR 2 YEARS YES YES, as optional NO2.7 FABRICATION & INSTALLATION YES YES, only on skid of YIN YES
3.0 SCOPE OF WORK
3.1 PROJECT DOCUMENTATION YES YES YES Document shall be submitted using PP format
3.2 ENGINEERING SERVICES (BASIC & DETAIL) YES YES YES3.3 PROCUREMENT YES YES YES3.4 FABRICATION & TEST SUPPORT YES YES YES3.5 ASSEMBLY & START UP SUPPORT YES YES YES
4.0 GENERAL REQUIREMENT4.1 Domestic Contents List and Percentage YES YES, domestic content around 10-30% YES4.2 Sub Supplier and Standardization YES YES YES4.3 Document to be submitted with Proposal YES YES YES4.4 Construction Work Volume for Package Item YES YES YES
5.0 DETAIL TECHNICAL REQUIREMENT
TECHNICAL BID EVALUATION TABULATION SHEET FOR METERING AND REGULATING STATION
NO DESCRIPTION Specification & Requirements REMARKS (By PP)
NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 1 of 5
PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-010-PP Thursday, February 23, 2017
Rev.1
VENDOR / SUPPLIER RESPONSE
PT. YOKOGAWA INDONESIA PT. PACIFIC PROCESS ENGINEERING
TECHNICAL BID EVALUATION TABULATION SHEET FOR METERING AND REGULATING STATION
NO DESCRIPTION Specification & Requirements REMARKS (By PP)
5.1 System Design Condition
Service Natural Gas Comply ComplyDesign Flow Capacity 18 MMSCFD Comply ComplyDesign Pressure 25.3 kg/cm2g Comply ComplyOperating Pressure 22 kg/cm2g Comply ComplyDesign Temperature 80 °C Comply ComplyOperating Temperature 15.5-48.9 °C Comply ComplyInlet Piping (inch) 8 inch Comply ComplyGas Outlet Piping (inch) 8 inch Comply ComplyLiquid Outlet piping (inch) 8 inch Comply Comply
5.2 ScrubberQuantity 1 Nos Comply ComplyProcess Requirement:
Design Pressure & Temperature (kg/cm2g; °C) 25.3 kg/cm2g; 80 °C Comply ComplyOperating Pressure & Temperature (kg/cm2g; °C) 21-22 kg/cm2g; 15.5-48.9 °C Comply ComplyDesign Flow Capacity (MMSCFD) 18 Comply Comply
Mechanical Data:
Fabricator Confirmed by Vendor Confirm after engineering process PT Prakarsalanggeng Majubersama or other ASME Fabricator
Size ( m D x m H T/T ) 0.8 m x 2.5 m Comply ComplyInternal part Demister Comply ComplyInlet Nozzle (inch) 10 inch Comply ComplyGas Outlet Nozzle (inch) 8 inch Comply ComplyLiquid Outlet Nozzle (inch) 2 inch Comply ComplyBriddle Connection Nozzle (inch) 2 inch (2 nozzle) Comply ComplyPSV connection nozzle (inch) 3 inch or as per vendor calculation Comply ComplyHandhole nozzle (inch) 8 inch Comply ComplyPressure Gage connection nozzle & Spare Nozzle (inch) 3/4 inch Comply ComplyHead type Elipsoidal (2:1) Comply ComplyShell thickness (mm) & Head Thickness (mm) 12 mm Comply ComplyPainting (internal/ external) No/ Yes (as per painting specification) [1] YES (as per painting spec) ComplySupport Leg Comply Comply
Skirt Support dimension Confirmed by Vendor Confirm after engineering process 800 mmOD x 1091 mmH or confirm after engineering
Material of Construction:Shell / Head SA 516 Gr 70 Comply ComplyReinforcing Pad SA 516 Gr 70 Comply ComplyNozzle neck pipe SA 106 Gr.B Comply ComplyNozzle flange SA 105 Comply ComplyBlind flange SA 105 Comply ComplyFitting SA 234 Gr. WPB Comply ComplySkirt Support SA 516 Gr 70 / SA 36 Comply ComplyBase Ring Plate SA 516 Gr 70 / SA 36 Comply Not supplyExternal Attachment SA 516 Gr 70 Comply Not supplyInternal Removable SA 240 Gr. 304 Comply ComplyGasket NON ASBESTOS Comply ComplyBolts (Internal/ External) SA 193-B8/ SA 193-B7 Comply ComplyNuts (Internal/ External) SA 194-B8/ SA 194-2H Comply ComplyLifting Lugs/ Tailing Lugs SA 516 Gr.70 Comply ComplyEarthing Lugs SA 240 Gr. 304 Comply, SS304 ComplyNameplate SA 240 Gr. 304 Comply, SS304 Comply
System design condition for Natural Gas Scrubber system as below:
NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 2 of 5
PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-010-PP Thursday, February 23, 2017
Rev.1
VENDOR / SUPPLIER RESPONSE
PT. YOKOGAWA INDONESIA PT. PACIFIC PROCESS ENGINEERING
TECHNICAL BID EVALUATION TABULATION SHEET FOR METERING AND REGULATING STATION
NO DESCRIPTION Specification & Requirements REMARKS (By PP)
Anchor Bolts SA 307 Gr. B Comply InclusionDemister Vendor to Advise SS316 SS304
Fabrication & Inspection:Inspection/ Certifying Yes Comply ComplyHydrotest Yes Comply ComplyNDT:
Radiography Yes Yes YesDry Penetrant Yes Yes YesUltrasonic Test As per code/ Spec As per code/ Spec As per code/ SpecMagnetic Test As per code/ Spec As per code/ Spec As per code/ Spec
MiscellaneousReducer at Inlet nozzle 8" x 10" Comply Comply
5.3 Flow ComputerQuantity 1 Nos Comply ComplyManufacturer Confirmed by Vendor OMNI or Floboss Dynamic Flow computer, USAService Fluid Natural Gas Comply Comply
5.4 Level Control ValveQuantity 1 Nos Comply ComplyManufacturer as per AML Comply ComplyValve Type Globe Valve Comply GlobeSize & Rating 1" - 300# or as per calculation Comply ComplyBody & Bonnet Material CS A105 A216W CB ComplyActuator:
Type Single acting diapraghm Single acting diapraghm Single acting diapraghmFail Position Fail close Fail close Fail CloseFlow action Flow to open Flow to open Flow to open
Trim:Plug/ Ball/ Disk 316 SS 316 SS SUS 316Seat Material 316 SS 316 SS SUS 316Stem Material 316 SS 316 SS S
Positioner:Type Smart with HART Protocol Smart with HART Protocol Smart with HART ProtocolInput Signal 4-20 mA 4-20 mA 4-20 mAOn increase signal output Increase Increase IncreaseEnclosure IP 65 IP 65 IP 65Rated CV Confirmed by Vendor as per sizing calculation 0.01
Other Specification: Vendor to Advise - Linear Characteristic
5.5 Field InstrumentPressure Gauge:
Quantity 1 Nos Comply ComplyManufacturer As per AML Comply, Aschroff ComplyRange 0-40 kg/cm2g Comply, 0-50 kg/cm2g 0-60 kg/cm2gDial Confirmed by Vendor 3.5" - 4" 6"
Connection Confirmed by Vendor 1/2" NPT M Bottom c/w isolation valve 3/4" NPT 3/4"
Nozzle size 3/4 inch Comply ComplyElement Material 316 SS 316 SS ComplyWindow Material Borosilicate Shatter Proof Glass Safety Glass ComplyElement Type Bourdon type Bourdon type Comply
NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 3 of 5
PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-010-PP Thursday, February 23, 2017
Rev.1
VENDOR / SUPPLIER RESPONSE
PT. YOKOGAWA INDONESIA PT. PACIFIC PROCESS ENGINEERING
TECHNICAL BID EVALUATION TABULATION SHEET FOR METERING AND REGULATING STATION
NO DESCRIPTION Specification & Requirements REMARKS (By PP)
Movement Material 316 SS 316 SS ComplyEnclosure IPW 65, Weather Proof Weather proof Weather proofCase Material Die-Cast Aluminium Die Cast Aluminium SS
Level Gauge:Quantity 1 Nos Comply ComplyManufacturer As per AML Penberthy ComplyMaterial Carbon Steel Comply ComplyOther Specification Vendor to Advise Confirm after engineering process 3/4" NPT Side-Side Connection
Level Transmitter:Quantity 1 Nos Comply ComplyManufacturer As per AML Comply ComplyOther Specification Vendor to Advise Confirm after engineering process Magnetic Level Transmitter
5.6 PSVQuantity 1 Nos Comply ComplyManufacturer as per AML Comply ComplyService Fluid Natural Gas Comply Comply
Size 3-300# K 4-100# or as per update calculation from vendor Comply Comply
Set pressure 25 kg/cm2.g Comply Comply
5.7 Drip LegQuantity 1 Nos Comply ComplyManufacturer as per AML Fabrication or as per AML Fabricated itemMaterial A53 or as per piping specification A53 or as piping specification ComplySize 4" (diameter) - 4' (length) 4" (diameter) - 4' (length) Comply
5.8 Manual ValveGate Valve 2" - 300# :
Quantity 5 Nos Comply ComplyMaterial Carbon Steel Comply ComplyManufacturer as per AML Comply Comply
Ball Valve 8" - 300# :Quantity 2 Nos Comply ComplyMaterial Carbon Steel Comply ComplyManufacturer as per AML Comply Comply
Ball Valve 3" - 300# :Quantity 1 Nos Comply ComplyMaterial Carbon Steel Comply ComplyManufacturer as per AML Comply Comply
Ball Valve 2" - 300# :Quantity 2 Nos Comply ComplyMaterial Carbon Steel Comply ComplyManufacturer as per AML Comply Comply
Ball Valve 3/4" :Quantity 11 Nos Comply ComplyMaterial Carbon Steel Comply ComplyManufacturer as per AML Comply Comply
Check Valve :Size 8" Comply Comply
NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 4 of 5
PROJECT : GRESIK GAS COGENERATION PLANT PROJECTDOC. NUMBER : GGCP-00-I0-TE-010-PP Thursday, February 23, 2017
Rev.1
VENDOR / SUPPLIER RESPONSE
PT. YOKOGAWA INDONESIA PT. PACIFIC PROCESS ENGINEERING
TECHNICAL BID EVALUATION TABULATION SHEET FOR METERING AND REGULATING STATION
NO DESCRIPTION Specification & Requirements REMARKS (By PP)
Quantity 1 Nos Comply ComplyMaterial Carbon Steel Comply ComplyManufacturer as per AML Comply Comply
5.9 Piping, Fitting & AccessoriesQuantity Confirmed by Vendor as per battery limit as per battery limit as per battery limitMaterial Carbon Steel Comply ComplyManufacturer as per AML Comply Comply
6.0 DOCUMENTATION6.1
1) Deviation and Clarification List YES YES YES2) Complete B.O.M YES YES YES3) System Configuration Diagram YES YES YES4) Dimensional Outline Drawing with Loading Data YES YES YES5) List of Spare Parts for Construction & Precommissining YES YES N/A6) List of Spare Parts for Start-up & Commissining YES YES N/A7) List of Spare Parts for Two (2) Years Operation YES YES N/A8) List of Consumables Utilities YES YES N/A9) List of Special Tools YES YES N/A10) Power Consumption List and Heat Dissipation List YES YES N/A11) Technical Leaflet and/or Catalogue YES YES YES
7.07.1
At Vendor shop & site(1) Training of Engineers in all aspects of system configuration YES YES, as per YIN scope of supply & work YES(2) Training of technicians in all aspects of system maintenance YES YES, as per YIN scope of supply & work YES(3) Training of operators in all aspects if system operation YES YES, as per YIN scope of supply & work YES
8.08.1 TYPICAL ACCEPTANCE TEST Required YES, will be provided Yes, to be specified8.2 PRE-FAT (PRE-FACTORY ACCEPTANCE TEST) Required YES, will be provided Yes8.3 FAT (FACTORY ACCEPTANCE TEST) YES YES, will be provided Yes
8.4 YES No, since total configuration systems not only by YIN Yes
8.5 SAT (SITE ACCEPTANCE TEST) YES YES, as per scope of supply & work Yes8.6 SITE SUPERVISION YES YES, as per scope of supply & work Yes
CONCLUSION OF TECHNICAL EVALUATION Accepted Accepted
9.0TOTAL BUDGET To be specified (exclude VAT 10%)DISCOUNT
TRAINING
TEST AND INSPECTION
IFAT (INTEGRATED FACTORY ACCEPTANCE TEST) AT VENDOR'S SHOP
COMMERCIAL
NOTES:1. Legend : YES (Comply), NO (Not Comply), ? (To Be Clarified), NS (Not Specified)2. Acceptability : A (Accepted), AC (Accepted with Comment), NA (Not Accepted) 5 of 5
BUDGETARY COMMERCIAL PROPOSAL
Date : Monday, February 20, 2017
Project : Gresik Co-Generation Plant
Location : Gresik, East Java
Material : Gas Metering Packages
End user : PT.PUPUK INDONESIA ENERGI
Quotation No : QSA17N0003 REV 05
Delivery : 14 weeks
Validity : 30 days
Page 1 of 16
To : PT.PP (Persero) Tbk - Divisi EPC
East Jakarta
Attn : Mr.Fuad
Project Manager
Date : Monday, February 20, 2017
Project : Gresik Co-Generation Plant
Location : Gresik, East Java
Material : Gas Metering Packages
End user : PT.PUPUK INDONESIA ENERGI
Quotation No : QSA17N0003 REV 05
Delivery : 14 weeks
COMMERCIAL PROPOSAL
Dear Sir/ Madam,
We are pleased to submit our proposal for the above mentioned project.
Should there's any technical revision kindly please contacted us.
Thanks for the kind attention .
Best Regards,
PT. Yokogawa Indonesia
PT. YOKOGAWA INDONESIA
PLAZA OLEOS, 3rd Floor, Suite A-H
Jl. TB Simatupang Kav. 53 Jakarta 12520
Tel : 021-2972600 Telefax : 021-22780148
Page 2 of 16
The conditions stated below shall constitute a part of the agreement resulting from an order for the whole or any part
of the apparatus covered by this quotation unless expressly excepted herein. The word “YIN” used herein shall mean
and represent PT. YOKOGAWA INDONESIA.
The words Purchaser used herein shall mean : PT.PP (Persero) Tbk - Divisi EPC
* ACCEPTANCE
All orders based on this proposal shall be subject to the approval and acceptance of YIN as to price,
quantity, delivery and other conditions not stated herein.
* SCOPE OF SUPPLY AND WORK
No equipment nor service other than expressly stated in and covered by this proposal is included in the
scope of supply of YIN.
* PRICE
3.1) All price pertaining to an order shall be based on YIN written quotation.
3.2) All quoted prices are in US Dollars unless specified otherwise in the quotation.
* TERMS OF VALIDITY
If an extension of validity period is required, the purchaser shall make this request in writing to YIN.
YIN reserves the right to alter this proposal whether in whole or in part, upon such request.
Validity shall be 30 days from this proposal date.
* SPECIFICATION CHANGES AND CANCELLATIONS
Upon confirmation of order, no addition to or modification of any of the specification shall be binding
upon YIN unless made in writing and signed by a duly authorised officer of YIN.
Any change from the original specification on which YIN quotation is based shall be documented and
advised to YIN in the form of a revision of Purchase Order. All charges by Purchaser are binding only
if accepted by YIN.
5.1) Additional cost due to such specification change shall be quoted by YIN within 30 days after
receipt of revision of order.
5.2) The following table indicates the rate of cancellation charges at various stages of progress of
factory orders.
* Time of Cancellation Rate
Prior to start of engineering 10%
After the start of engineering but prior to release of production 30%
After release of production but prior to completion of manufacture 60%
After completion of manufacture but prior to shipping 100%
Whenever there are item in this proposal that are subcontracted by YIN to a third party, the terms
involving changes in specification and for cancellation between YIN and the third party shall apply to
the purchaser.
* TYPING ERRORS
YIN reserves the right to correct at typographical or clerical errors which may be present in the prices or
specifications in this proposal.
* TERMS OF PAYMENT
as per TBE
* DELIVERY SCHEDULE
PT. Yokogawa IndonesiaGeneral Term and Condition of Sale for Quotation
Page 3 of 16
PT. Yokogawa IndonesiaGeneral Term and Condition of Sale for Quotation
Time of shipment stated herein is approximate and subject to prompt receipt of Purchase Order, and
all necessary system design and engineering information by YIN at its factory.
14 weeks
* DELIVERY OF PLACE
Delivery of place Free On Truck at Site Gresik East Java ( Exclude Loading & Unloading at Site )
* SUSPENSION OF THE WORKS
In the event that the Purchase requires, after establishment of the contract, to temporarily suspend the
work order processing for some time or indefinitely or requires to defer the agreed delivery time, and
that YIN accepts such request, YIN RESERVES THE RIGHT TO CLAIM FROM THE Purchaser an
equitable compensation for all the expenses directly or indirectly caused by such suspension of the work
or postponement.
* WARRANTY
YIN warrants that all its manufactured equipment shall be free from defects in material or workmanship
under normal or proper usage. YIN’s obligation is limited to replacing, free of charge, any part of an
instrument or apparatus which shall be returned, transportation charges prepaid, by the purchasers
within twelve (12) months after starting-up or otherwise eighteen (18) months from shipment by YIN
whichever comes first, and which examination proves not to be within the specified limit of calibration
or to be defective in material or workmanship. In no event shall YIN be liable for consequential damages.
However, consumable item and fragile item, thermo-couples, resistance bulbs are not subject to
replacement unless returned unused.
On equipment other than YIN manufactured, supplied by YIN the Warranty of the original manufacturer
applies.
* INSPECTION
All equipment shall be tested before shipment by YIN or its sub-contractors. The inspection or test by
Purchaser or purchaser nominated inspector is acceptable, provided that the costs for such inspection
such as man-hour rate, travel expenses, etc.,. shall be borne by Purchaser nominated inspector. Timing
for such inspection shall be by prior agreement between YIN and Purchaser.
* DOCUMENTATION
The document to be submitted by YIN shall be in YIN standard form.
* LANGUAGE
All documents and working language for this contract shall be in English.
* EXPORT PACKAGING
Export Packing, if required will be made in accordance with YIN standard procedure.
* FORCE MAJEURE
YIN shall not be liable for loss, damage, detention or delay caused by fire, strike, civil or military authority,
insurrection or riot, or for any other course beyond its reasonable control.
* DISPUTES
All disputes and differences in opinions arising our of or in connection with orders based on his proposal
shall be settled between Purchaser and YIN in an amicable way. The validity, performance and construction
of these terms and conditions and any sale made shall be governed by the laws of Republic Indonesia and
subject to the exclusive jurisdiction of the courts of Repulic Indonesia.
* OTHERS
All other item and conditions shall be subject to mutual agreement. The definitions and understanding
of works used herein and in the contract, resulting from this quotation shall be subject to
INCOTERM 1980 (International Rules for the Interpretation or Trade Terms) by the international
Chamber of Commerce.
Page 4 of 16
PT. Yokogawa IndonesiaGeneral Term and Condition of Sale for Quotation
* TERMS AND DUTIES
Prices do not include any foreign or local taxes or duties, new or hereafter enacted, applicable to the
Equipment sold where YIN is obliged to pay these taxes or duties in the first instance, the Purchaser
shall reimburse YIN the same amount.
Page 5 of 16
1 TAG NO
2 P&ID REFERENCE DOC NO.
3 FLUID
4 CAPACITY FLOW MAX
5 DESIGN PRESSURE MIN/NOR/MAX
6 DESIGN TEMPERATURE MIN/NOR
DESIGN TEMPERATURE
7 MOLECULAR WEIGHT
8 VISCOSITY @ FT
9 Density LB/CUFT
10 Z FACTOR
11 NUMBER OF STREAM
12 INLET/OULET HEADER
15 PIPE MATERIAL
16 SKID STRUCTURE & MATERIAL
17 VESSEL MATERIAL
18 VALVE & OTHER MATERIAL
19 CODE AND STANDARDS
15006 KG/H
19.6
01-HD-12702-A
HC GAS
0.0102 cP
20/ 21.8/ 25.3 KG/C2
15.5/ 27 DEG C
80 DEG C
ASME STANDARD
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
GGCP-04-P0-PI-001-PP
CARBON STEEL
BEAM STRUCTURE SUPPORT
TYPE, SS400/A36
1.68
0.97
1 X 100%
8 INCH SCH 40 A106 Gr B +
REDUCER 8"X10"
CARBON STEEL
BASIC DESIGN
CARBON STEEL
Page 6 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
20 HAZARDOUS CERTIFICATION
DESCRIPTION REMARK
1 FUEL GAS SCRUBBER VESSEL 1 EA
TAG NO: 01-HD-12702-A/B
Fluid: Hydrocarbon Gas
Operating Pressure: 25/21.8/20 kg/cm2
Temperature Max/Nor/Min: 48.9/27/25.5 Deg C
Viscosity: 0.0103 cP
Design Pressure: 25.3 kg/cm2
Design Temp: 80 Deg C
CAPACITY: 15006 kg/h
Design Code: ASME Sect VIII Div.1
Dimension Vessel: 800 mm ID x 2500 mm T/T
Orientation: Vertical
Thickness:
Shell: 12 mm
Head: 12 mm
Type of head: Ellipsoidal head
Type of support: Leg, 4 pc
Corr.Allow: 1.7 mm
Joint Efficiency: 0.85
Material Specification:
Shell: SA516 Gr 70
VOLUME
FUEL GAS SCRUBBER PACKAGES
I. FUEL GAS SCRUBBER MATERIAL
CLASS 1 DIV 2
INCLUDED
ITEM
Page 7 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
Ellipsoidal head: SA516 Gr70
Nozzle neck pipe: SA106 Gr B
Nozzle flange: SA105
Blind flange: SA105
Support: A36/SS400
Fitting: SA 234 WPB
Reinforcement pad: SA516 Gr 70
Gasket: Spiral wound 304SS, inner & outer CS ring, Graphite
filler
Bolt & nuts: SA 193 Gr B7/ SA 194 gr 2H, Fuorocarbon
Coated
Anchor bolt: A 307 Gr B
External:
Pipe clip: SA 516 Gr 70
Fireproofing clip: SA 516 Gr 70
Internal:
Demister: SS316
Support: SS316
Name Plate: SS304
Lifting Lug: SA 516 Gr 70
Earthing Lug: SS304
Design Code for Piping: ASME B31.8
Skid size: 2200 mm x 3500 mm
Platform size: 1500 mm x 2200 mm x 3000 mm
Include with:
Hydrotest, Radiography Test, Ultrasonic Test, Penetrant Test
and Magnetic test
Include Reducer 8" x 10" Sch 40
2 SKID, PIPING, LADDER & PLATFORM 1 Set INCLUDED
Page 8 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
Design Code: ASME B31.8
Estimation Skid size: 2200 mm W x 3500 mm L
Estimation Platform size: 1500 mm W x 2200 mm L x 3000 mm
H
Material Specification:
Pipe : SA 106 Gr B
Flange: SA 105
Gasket: Spiral wound 304SS, inner & outer CS ring, Graphite
filler
Bolt & nuts: SA 193 Gr B7/ SA 194 gr 2H, Fuorocarbon Coated
Fitting: SA 234 WPB
Skid: SS400, IWF 200 mm
Support pipe: SS400, UNP 150 mm w/ U Bolt Carbon steel
Grating: Galvanized, WA 253 or equal
Ladder side bar: Flat Bar 12 x 65 mm
Ladderr step: C-Steel ( round bar Dia 19 mm )
Safety cage: Flat Bar 5 x 50 mm
Post rail: SGP Medium Black Dia 1"
Handrail: SGP Medium Black Dia 1"
Midrail: Flat Bar 5 x 50 mm
Kick plate: Flat Bar 6 x 75 mm
Lifitng Lug: A36/SS400 or equal
Page 9 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
3
1 PRESSURE GAUGE INDICATOR 1 EA
TAG NO: 12-PG-703A
Range: 0 - 50 Bar
Dial : 3.5-4"
Connection: 1/2" NPT M Bottom c/w isolation valve 3/4" NPT
2 LEVEL / DP TRANSMITTER 1 EA
TAG NO: 12-LT-701A
Type: EJA110E
Cal range: 0 - 400 in H2O
Output: 4-20 mA, 24 VDC, HART Protocol
Indicator: LCD type
Enclosure: Explosion Proof
Accuracy: 0.055% of span
Process connection: 1/2" NPT + Manifold
3 LEVEL GAUGE GLASS 1 EA
TAG NO: 12-LG-701A
Material : Carbon Steel
Size: 3/4" NPT
4
1.A MAIN ISOLATION VALVES INLET & OUTLET SCRUBBER 2 EA
TAG NO: V5-12705/V5-121711
Type: Trunnion Mounted Ball Valve Full bore
AS PER AML
WIKA/ASCHROFF
PENBERTHY
YOKOGAWA
INSTRUMENT TRANSMITTER & GAUGES
VALVES
Page 10 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
Size: 8” ANSI 300 RF
3-Piece Body Design
Body Material : A216WCB
BALL Material : A105/ENP
1.B BY PASS TRUNNION BALL VALVE 8" # 300 RF 1 EA
2 CHECK VALVES ( OUTLET GAS SCRUBBER ) 1 EA
Type: SWING CHECK VALVES
Size: 8” ANSI 300 RF
Body Material : A216WCB
3SMALL ISOLATION BALL VALVES
( Gas Scrubber Vessel In/Out )
Type: Floating Ball Valve Full bore
Body Material : A216WCB
BALL Material : A105/ENP
Size: 2"#300 RF 3 pcs
Size: 3/4" CL800 INLET SW X OUTLET 3/4 " NPT ( LG) 4 pcs
Size: 3/4" CL800 INLET SW X OUTLET 1/2" NPT ( PG /PT/LT) 4 pcs
Size: 3/4" CL800 INLET SW X 3/4" OUTLET NPT
(DRAIN CV / PURGING/ PSV) 3 pcs
4 SPECTACLE BLIND FLANGE 2 pcs GALPITRI , ITALY
Material: A216WCB
Size: 8 inch # 300
5SMALL ISOLATION GATE VALVES
( output Liquid bottom scrubber )5 pcs
Type: Gate Valves
Body Material : A216WCB
Size: 2"#300 RF
AS PER AML
AS PER AML
AS PER AML
EXCLUDES
Page 11 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
6CONTROL VALVES
( output Liquid bottom scrubber )1 pcs
TAG NO: 12-LV-701A
Size: 2"#300 RF or as sizing calculation
Type: Globe Valves
Body Material : A216WCB
c/w Smart Positioner and Position Indication, Filter Regulator,
Tubing & fitting ( accessories )
7 PRESSURE SAFETY VALVE 1 EA
TAG NO: 12-PSV-701A
Size: 3#300 RF x 4#150 RF or as per Sizing Calculation from Mfg
Set @ range:25 kg/cm2
5
1 DRIP LEG TANK 1 EA
TAG NO: 01-FC-12704
2 LEVEL GAUGE GLASS 1 EA
TAG NO; 12-LG-702
Material : Carbon Steel
Size: 3/4" NPT
Exclude Supply Pipeline
2"-FG-2A-014 & 2"-FG-2A-017
to PSV 12-PSV-701A/B .
And Included if pipelines
assembly on the skid not
from other safe area
AS PER AML
DRIP LEG
FABRICATION
PENBERTHY
FARRIS ENGINEERING
Page 12 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
3 Piping Lines 2"-V-2A-005
Exclude and shall be PP
Scope since install from
Vertical Pipe Rack to
Down drip leg
Piping lines 2"-V-2A-006
Included YIN Scope from
Condesate Drain Tank to
Line Drip Leg on the Skid.
( Drip Leg installed on the
Skid between Scrubber
and condesate Drain tank
)
Piping Lines 2"-V-2A-007
Included from Condesate
Drain Tank to Line Drip
Leg on the Skid
Piping Lines 4"-V-2A-008
Included from output Drip
Leg until tapping on the
Skid, then output drip leg
pipeline to Safe Area by
PP
4 Piping Line 2"-LD-1A-012 to Condensate Tank
Included install and
assembly on the Skid
Scrubber
5 Piping Line 4"-V-2A-008 up to safe area
YIN Scope until tapping
on the Skid, and then
from tapping to Safe Area
by PP Scope
6SIGNAL FROM LEVEL TRANSMITTER, CONTROL VALVES, PSV
& OTHERS ELETRICAL/INSTRUMENT TO PCS / CONTROL
ROOM
OUT OF SCOPE,
SHALL BE PP SCOPE
YIN will be supply Junction Box from Field Instrument on the
Skid Piping Scrubber
Page 13 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
7 FLOW COMPUTER 1 UNIT
panel mount, 240VAC/24VDC, with flash
Modbus RS485 ( 2 wire as multi master ) 4 EA
Analog Input 12 EA
Analog Output 4 EA
Pulse Input 2 EA
Pulse Output 5 EA
Digital Input 16 EA
Digital Output 12 EA
Modbus TCP/IP 2 EA
1 Project / Engineering Service 1 LOT
Consist of :
Detail Engineering Design and Documentation
YOKOGAWA
AS PER OPTIONAL PRICES
II. ENGINEERING & PROJECT SERVICES
Page 14 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
Approval Document Engineering
FAT (Factory Acceptance Test) at
JAKARTA
SAT (Site Acceptance Test) &
Commissioning Work at site
SAT (Site Acceptance Test) &
Commissioning Work at site
If SAT more than 7 working
days , PP will be paid as per
manday rate
Maximum 3 working days
Maximum 7 working days
Comment/return documents
from PP max 5 days,
if no return within 5 days The
Document automatic
approved
Page 15 of 16
No Description QtyAmount
(IDR)
A
1FUEL GAS SCRUBBER
PACKAGES1 X 100%
2Freight Cost Free On Truck
Gresik East Java 1 Lot
Detail refer to Bill Of Material
Exclude VAT 10%
OPTIONAL PRICES
1 Spare-parts for start up - commissioning 1 Set
2 2 years spare-parts 1 Set
3 Flow Computer 1 Set
4 Panel for Flow Computer 1 Set
C Exclude of this proposal
Loading & Unloanding at Site Gresik
Pasuruan
1 Tie-In Pipeline from Inlet/Outlet Header:
Upstream & Downstream Metering Systems,
Scrubber, Inlet outlet Condensate Tank, Inlet
outlet Control Valve HRSG, Inlet outlet Control
Valve Boiler, Inlet Outlet SDV GTG
2 Cable Instrument & Power from JB Field to
Control room Safe area
3 Grounding Systems
4 Civil Works ( Such as: Foundation Works, Floor
and etc )
5 Air Facility
6 Fire Systems
7 A/C & D/C Power Facility
8 Lighting Protection & Lightening
9 Cabinet/Cover of SKID
10 Hot Tapping Upstream & Downstream
12 Air Conditioning Systems
SITE WORK
MANDAYS RATE:
(1) Onshore Mon-Fri : 08.00 - 17.00 : USD 700/Day
Mon-Fri : 17.00 - 22.00 : USD 80/Hour
Mon-Fri : 22.00 - 08.00
Sat, Sun, Public Holiday : 08.00 -17.00 -> US$ 800/day
Air Ticket Jakarta - Site to be borned by customer
Local Transport USD 100/day
# The above price is subject to 10% VAT
(2) Offshore
Mon-Fri : 08.00 - 19.00 : USD 950/Day Mon-Fri : 22.00 - 08.00 : USSD 200/Day
Mon-Fri : 17.00 - 22.00 ; USD 150/Day Sat, Sun, Public Holiday : 08.00 -17.00 -> US$ 1,500/day
Air Ticket Jakarta - Site to be borned by customer # The above price is subject to 10% VAT
Local Transportation, USD 100/Day - Hotel, ticket, meals and other expenses are billed at cost
SUMMARY
SCOPE OF WORK
TOTAL
Page 16 of 16
BUDGETARY COMMERCIAL PROPOSAL
Date : Monday, February 20, 2017
Project : Gresik Co-Generation Plant
Location : Gresik, East Java
Material : Gas Metering Packages
End user : PT.PUPUK INDONESIA ENERGI
Quotation No : QSA17N0003 REV 05
Delivery : 14 weeks
Validity : 30 days
Page 1 of 16
To : PT.PP (Persero) Tbk - Divisi EPC
East Jakarta
Attn : Mr.Fuad
Project Manager
Date : Monday, February 20, 2017
Project : Gresik Co-Generation Plant
Location : Gresik, East Java
Material : Gas Metering Packages
End user : PT.PUPUK INDONESIA ENERGI
Quotation No : QSA17N0003 REV 05
Delivery : 14 weeks
COMMERCIAL PROPOSAL
Dear Sir/ Madam,
We are pleased to submit our proposal for the above mentioned project.
Should there's any technical revision kindly please contacted us.
Thanks for the kind attention .
Best Regards,
PT. Yokogawa Indonesia
PT. YOKOGAWA INDONESIA
PLAZA OLEOS, 3rd Floor, Suite A-H
Jl. TB Simatupang Kav. 53 Jakarta 12520
Tel : 021-2972600 Telefax : 021-22780148
Page 2 of 16
The conditions stated below shall constitute a part of the agreement resulting from an order for the whole or any part
of the apparatus covered by this quotation unless expressly excepted herein. The word “YIN” used herein shall mean
and represent PT. YOKOGAWA INDONESIA.
The words Purchaser used herein shall mean : PT.PP (Persero) Tbk - Divisi EPC
* ACCEPTANCE
All orders based on this proposal shall be subject to the approval and acceptance of YIN as to price,
quantity, delivery and other conditions not stated herein.
* SCOPE OF SUPPLY AND WORK
No equipment nor service other than expressly stated in and covered by this proposal is included in the
scope of supply of YIN.
* PRICE
3.1) All price pertaining to an order shall be based on YIN written quotation.
3.2) All quoted prices are in US Dollars unless specified otherwise in the quotation.
* TERMS OF VALIDITY
If an extension of validity period is required, the purchaser shall make this request in writing to YIN.
YIN reserves the right to alter this proposal whether in whole or in part, upon such request.
Validity shall be 30 days from this proposal date.
* SPECIFICATION CHANGES AND CANCELLATIONS
Upon confirmation of order, no addition to or modification of any of the specification shall be binding
upon YIN unless made in writing and signed by a duly authorised officer of YIN.
Any change from the original specification on which YIN quotation is based shall be documented and
advised to YIN in the form of a revision of Purchase Order. All charges by Purchaser are binding only
if accepted by YIN.
5.1) Additional cost due to such specification change shall be quoted by YIN within 30 days after
receipt of revision of order.
5.2) The following table indicates the rate of cancellation charges at various stages of progress of
factory orders.
* Time of Cancellation Rate
Prior to start of engineering 10%
After the start of engineering but prior to release of production 30%
After release of production but prior to completion of manufacture 60%
After completion of manufacture but prior to shipping 100%
Whenever there are item in this proposal that are subcontracted by YIN to a third party, the terms
involving changes in specification and for cancellation between YIN and the third party shall apply to
the purchaser.
* TYPING ERRORS
YIN reserves the right to correct at typographical or clerical errors which may be present in the prices or
specifications in this proposal.
* TERMS OF PAYMENT
as per TBE
* DELIVERY SCHEDULE
PT. Yokogawa IndonesiaGeneral Term and Condition of Sale for Quotation
Page 3 of 16
PT. Yokogawa IndonesiaGeneral Term and Condition of Sale for Quotation
Time of shipment stated herein is approximate and subject to prompt receipt of Purchase Order, and
all necessary system design and engineering information by YIN at its factory.
14 weeks
* DELIVERY OF PLACE
Delivery of place Free On Truck at Site Gresik East Java ( Exclude Loading & Unloading at Site )
* SUSPENSION OF THE WORKS
In the event that the Purchase requires, after establishment of the contract, to temporarily suspend the
work order processing for some time or indefinitely or requires to defer the agreed delivery time, and
that YIN accepts such request, YIN RESERVES THE RIGHT TO CLAIM FROM THE Purchaser an
equitable compensation for all the expenses directly or indirectly caused by such suspension of the work
or postponement.
* WARRANTY
YIN warrants that all its manufactured equipment shall be free from defects in material or workmanship
under normal or proper usage. YIN’s obligation is limited to replacing, free of charge, any part of an
instrument or apparatus which shall be returned, transportation charges prepaid, by the purchasers
within twelve (12) months after starting-up or otherwise eighteen (18) months from shipment by YIN
whichever comes first, and which examination proves not to be within the specified limit of calibration
or to be defective in material or workmanship. In no event shall YIN be liable for consequential damages.
However, consumable item and fragile item, thermo-couples, resistance bulbs are not subject to
replacement unless returned unused.
On equipment other than YIN manufactured, supplied by YIN the Warranty of the original manufacturer
applies.
* INSPECTION
All equipment shall be tested before shipment by YIN or its sub-contractors. The inspection or test by
Purchaser or purchaser nominated inspector is acceptable, provided that the costs for such inspection
such as man-hour rate, travel expenses, etc.,. shall be borne by Purchaser nominated inspector. Timing
for such inspection shall be by prior agreement between YIN and Purchaser.
* DOCUMENTATION
The document to be submitted by YIN shall be in YIN standard form.
* LANGUAGE
All documents and working language for this contract shall be in English.
* EXPORT PACKAGING
Export Packing, if required will be made in accordance with YIN standard procedure.
* FORCE MAJEURE
YIN shall not be liable for loss, damage, detention or delay caused by fire, strike, civil or military authority,
insurrection or riot, or for any other course beyond its reasonable control.
* DISPUTES
All disputes and differences in opinions arising our of or in connection with orders based on his proposal
shall be settled between Purchaser and YIN in an amicable way. The validity, performance and construction
of these terms and conditions and any sale made shall be governed by the laws of Republic Indonesia and
subject to the exclusive jurisdiction of the courts of Repulic Indonesia.
* OTHERS
All other item and conditions shall be subject to mutual agreement. The definitions and understanding
of works used herein and in the contract, resulting from this quotation shall be subject to
INCOTERM 1980 (International Rules for the Interpretation or Trade Terms) by the international
Chamber of Commerce.
Page 4 of 16
PT. Yokogawa IndonesiaGeneral Term and Condition of Sale for Quotation
* TERMS AND DUTIES
Prices do not include any foreign or local taxes or duties, new or hereafter enacted, applicable to the
Equipment sold where YIN is obliged to pay these taxes or duties in the first instance, the Purchaser
shall reimburse YIN the same amount.
Page 5 of 16
1 TAG NO
2 P&ID REFERENCE DOC NO.
3 FLUID
4 CAPACITY FLOW MAX
5 DESIGN PRESSURE MIN/NOR/MAX
6 DESIGN TEMPERATURE MIN/NOR
DESIGN TEMPERATURE
7 MOLECULAR WEIGHT
8 VISCOSITY @ FT
9 Density LB/CUFT
10 Z FACTOR
11 NUMBER OF STREAM
12 INLET/OULET HEADER
15 PIPE MATERIAL
16 SKID STRUCTURE & MATERIAL
17 VESSEL MATERIAL
18 VALVE & OTHER MATERIAL
19 CODE AND STANDARDS
15006 KG/H
19.6
01-HD-12702-A
HC GAS
0.0102 cP
20/ 21.8/ 25.3 KG/C2
15.5/ 27 DEG C
80 DEG C
ASME STANDARD
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
GGCP-04-P0-PI-001-PP
CARBON STEEL
BEAM STRUCTURE SUPPORT
TYPE, SS400/A36
1.68
0.97
1 X 100%
8 INCH SCH 40 A106 Gr B +
REDUCER 8"X10"
CARBON STEEL
BASIC DESIGN
CARBON STEEL
Page 6 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
20 HAZARDOUS CERTIFICATION
DESCRIPTION REMARK
1 FUEL GAS SCRUBBER VESSEL 1 EA
TAG NO: 01-HD-12702-A/B
Fluid: Hydrocarbon Gas
Operating Pressure: 25/21.8/20 kg/cm2
Temperature Max/Nor/Min: 48.9/27/25.5 Deg C
Viscosity: 0.0103 cP
Design Pressure: 25.3 kg/cm2
Design Temp: 80 Deg C
CAPACITY: 15006 kg/h
Design Code: ASME Sect VIII Div.1
Dimension Vessel: 800 mm ID x 2500 mm T/T
Orientation: Vertical
Thickness:
Shell: 12 mm
Head: 12 mm
Type of head: Ellipsoidal head
Type of support: Leg, 4 pc
Corr.Allow: 1.7 mm
Joint Efficiency: 0.85
Material Specification:
Shell: SA516 Gr 70
VOLUME
FUEL GAS SCRUBBER PACKAGES
I. FUEL GAS SCRUBBER MATERIAL
CLASS 1 DIV 2
INCLUDED
ITEM
Page 7 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
Ellipsoidal head: SA516 Gr70
Nozzle neck pipe: SA106 Gr B
Nozzle flange: SA105
Blind flange: SA105
Support: A36/SS400
Fitting: SA 234 WPB
Reinforcement pad: SA516 Gr 70
Gasket: Spiral wound 304SS, inner & outer CS ring, Graphite
filler
Bolt & nuts: SA 193 Gr B7/ SA 194 gr 2H, Fuorocarbon
Coated
Anchor bolt: A 307 Gr B
External:
Pipe clip: SA 516 Gr 70
Fireproofing clip: SA 516 Gr 70
Internal:
Demister: SS316
Support: SS316
Name Plate: SS304
Lifting Lug: SA 516 Gr 70
Earthing Lug: SS304
Design Code for Piping: ASME B31.8
Skid size: 2200 mm x 3500 mm
Platform size: 1500 mm x 2200 mm x 3000 mm
Include with:
Hydrotest, Radiography Test, Ultrasonic Test, Penetrant Test
and Magnetic test
Include Reducer 8" x 10" Sch 40
2 SKID, PIPING, LADDER & PLATFORM 1 Set INCLUDED
Page 8 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
Design Code: ASME B31.8
Estimation Skid size: 2200 mm W x 3500 mm L
Estimation Platform size: 1500 mm W x 2200 mm L x 3000 mm
H
Material Specification:
Pipe : SA 106 Gr B
Flange: SA 105
Gasket: Spiral wound 304SS, inner & outer CS ring, Graphite
filler
Bolt & nuts: SA 193 Gr B7/ SA 194 gr 2H, Fuorocarbon Coated
Fitting: SA 234 WPB
Skid: SS400, IWF 200 mm
Support pipe: SS400, UNP 150 mm w/ U Bolt Carbon steel
Grating: Galvanized, WA 253 or equal
Ladder side bar: Flat Bar 12 x 65 mm
Ladderr step: C-Steel ( round bar Dia 19 mm )
Safety cage: Flat Bar 5 x 50 mm
Post rail: SGP Medium Black Dia 1"
Handrail: SGP Medium Black Dia 1"
Midrail: Flat Bar 5 x 50 mm
Kick plate: Flat Bar 6 x 75 mm
Lifitng Lug: A36/SS400 or equal
Page 9 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
3
1 PRESSURE GAUGE INDICATOR 1 EA
TAG NO: 12-PG-703A
Range: 0 - 50 Bar
Dial : 3.5-4"
Connection: 1/2" NPT M Bottom c/w isolation valve 3/4" NPT
2 LEVEL / DP TRANSMITTER 1 EA
TAG NO: 12-LT-701A
Type: EJA110E
Cal range: 0 - 400 in H2O
Output: 4-20 mA, 24 VDC, HART Protocol
Indicator: LCD type
Enclosure: Explosion Proof
Accuracy: 0.055% of span
Process connection: 1/2" NPT + Manifold
3 LEVEL GAUGE GLASS 1 EA
TAG NO: 12-LG-701A
Material : Carbon Steel
Size: 3/4" NPT
4
1.A MAIN ISOLATION VALVES INLET & OUTLET SCRUBBER 2 EA
TAG NO: V5-12705/V5-121711
Type: Trunnion Mounted Ball Valve Full bore
AS PER AML
WIKA/ASCHROFF
PENBERTHY
YOKOGAWA
INSTRUMENT TRANSMITTER & GAUGES
VALVES
Page 10 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
Size: 8” ANSI 300 RF
3-Piece Body Design
Body Material : A216WCB
BALL Material : A105/ENP
1.B BY PASS TRUNNION BALL VALVE 8" # 300 RF 1 EA
2 CHECK VALVES ( OUTLET GAS SCRUBBER ) 1 EA
Type: SWING CHECK VALVES
Size: 8” ANSI 300 RF
Body Material : A216WCB
3SMALL ISOLATION BALL VALVES
( Gas Scrubber Vessel In/Out )
Type: Floating Ball Valve Full bore
Body Material : A216WCB
BALL Material : A105/ENP
Size: 2"#300 RF 3 pcs
Size: 3/4" CL800 INLET SW X OUTLET 3/4 " NPT ( LG) 4 pcs
Size: 3/4" CL800 INLET SW X OUTLET 1/2" NPT ( PG /PT/LT) 4 pcs
Size: 3/4" CL800 INLET SW X 3/4" OUTLET NPT
(DRAIN CV / PURGING/ PSV) 3 pcs
4 SPECTACLE BLIND FLANGE 2 pcs GALPITRI , ITALY
Material: A216WCB
Size: 8 inch # 300
5SMALL ISOLATION GATE VALVES
( output Liquid bottom scrubber )5 pcs
Type: Gate Valves
Body Material : A216WCB
Size: 2"#300 RF
AS PER AML
AS PER AML
AS PER AML
EXCLUDES
Page 11 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
6CONTROL VALVES
( output Liquid bottom scrubber )1 pcs
TAG NO: 12-LV-701A
Size: 2"#300 RF or as sizing calculation
Type: Globe Valves
Body Material : A216WCB
c/w Smart Positioner and Position Indication, Filter Regulator,
Tubing & fitting ( accessories )
7 PRESSURE SAFETY VALVE 1 EA
TAG NO: 12-PSV-701A
Size: 3#300 RF x 4#150 RF or as per Sizing Calculation from Mfg
Set @ range:25 kg/cm2
5
1 DRIP LEG TANK 1 EA
TAG NO: 01-FC-12704
2 LEVEL GAUGE GLASS 1 EA
TAG NO; 12-LG-702
Material : Carbon Steel
Size: 3/4" NPT
Exclude Supply Pipeline
2"-FG-2A-014 & 2"-FG-2A-017
to PSV 12-PSV-701A/B .
And Included if pipelines
assembly on the skid not
from other safe area
AS PER AML
DRIP LEG
FABRICATION
PENBERTHY
FARRIS ENGINEERING
Page 12 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
3 Piping Lines 2"-V-2A-005
Exclude and shall be PP
Scope since install from
Vertical Pipe Rack to
Down drip leg
Piping lines 2"-V-2A-006
Included YIN Scope from
Condesate Drain Tank to
Line Drip Leg on the Skid.
( Drip Leg installed on the
Skid between Scrubber
and condesate Drain tank
)
Piping Lines 2"-V-2A-007
Included from Condesate
Drain Tank to Line Drip
Leg on the Skid
Piping Lines 4"-V-2A-008
Included from output Drip
Leg until tapping on the
Skid, then output drip leg
pipeline to Safe Area by
PP
4 Piping Line 2"-LD-1A-012 to Condensate Tank
Included install and
assembly on the Skid
Scrubber
5 Piping Line 4"-V-2A-008 up to safe area
YIN Scope until tapping
on the Skid, and then
from tapping to Safe Area
by PP Scope
6SIGNAL FROM LEVEL TRANSMITTER, CONTROL VALVES, PSV
& OTHERS ELETRICAL/INSTRUMENT TO PCS / CONTROL
ROOM
OUT OF SCOPE,
SHALL BE PP SCOPE
YIN will be supply Junction Box from Field Instrument on the
Skid Piping Scrubber
Page 13 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
7 FLOW COMPUTER 1 UNIT
panel mount, 240VAC/24VDC, with flash
Modbus RS485 ( 2 wire as multi master ) 4 EA
Analog Input 12 EA
Analog Output 4 EA
Pulse Input 2 EA
Pulse Output 5 EA
Digital Input 16 EA
Digital Output 12 EA
Modbus TCP/IP 2 EA
1 Project / Engineering Service 1 LOT
Consist of :
Detail Engineering Design and Documentation
YOKOGAWA
AS PER OPTIONAL PRICES
II. ENGINEERING & PROJECT SERVICES
Page 14 of 16
BILL OF MATERIAL
Gas Metering Packages
Gresik Gas Cogeneration Plant Project
East Java, Indonesia
Approval Document Engineering
FAT (Factory Acceptance Test) at
JAKARTA
SAT (Site Acceptance Test) &
Commissioning Work at site
SAT (Site Acceptance Test) &
Commissioning Work at site
If SAT more than 7 working
days , PP will be paid as per
manday rate
Maximum 3 working days
Maximum 7 working days
Comment/return documents
from PP max 5 days,
if no return within 5 days The
Document automatic
approved
Page 15 of 16
No Description QtyAmount
(IDR)
A
1FUEL GAS SCRUBBER
PACKAGES1 X 100% 1,144,699,000.00IDR
2Freight Cost Free On Truck
Gresik East Java 1 Lot included
Detail refer to Bill Of Material
1,144,699,000.00IDR Exclude VAT 10%
OPTIONAL PRICES
1 Spare-parts for start up - commissioning 1 Set IDR 22,893,980.00
2 2 years spare-parts 1 Set IDR 114,469,900.00
3 Flow Computer 1 Set IDR 210,000,000.00
4 PANEL FLOW COMPUTER 1 Set IDR 84,000,000.00
C Exclude of this proposal
Loading & Unloanding at Site Gresik
Pasuruan
1 Tie-In Pipeline from Inlet/Outlet Header:
Upstream & Downstream Metering Systems,
Scrubber, Inlet outlet Condensate Tank, Inlet
outlet Control Valve HRSG, Inlet outlet Control
Valve Boiler, Inlet Outlet SDV GTG
2 Tubing & fitting from Analyzer to Sampling
systems
3 Cable Instrument & Power from JB Field to
Control room Safe area
4 Grounding Systems
5 Civil Works ( Such as: Foundation Works, Floor
and etc )
6 Air Facility
7 Fire Systems
8 A/C & D/C Power Facility
9 Lighting Protection & Lightening
10 Cabinet/Cover of SKID
11 Hot Tapping Upstream & Downstream
12 Air Conditioning Systems
SITE WORK
MANDAYS RATE:
(1) Onshore Mon-Fri : 08.00 - 17.00 : USD 700/Day
Mon-Fri : 17.00 - 22.00 : USD 80/Hour
Mon-Fri : 22.00 - 08.00
Sat, Sun, Public Holiday : 08.00 -17.00 -> US$ 800/day
Air Ticket Jakarta - Site to be borned by customer
Local Transport USD 100/day
# The above price is subject to 10% VAT
(2) Offshore
Mon-Fri : 08.00 - 19.00 : USD 950/Day Mon-Fri : 22.00 - 08.00 : USSD 200/Day
Mon-Fri : 17.00 - 22.00 ; USD 150/Day Sat, Sun, Public Holiday : 08.00 -17.00 -> US$ 1,500/day
Air Ticket Jakarta - Site to be borned by customer # The above price is subject to 10% VAT
Local Transportation, USD 100/Day - Hotel, ticket, meals and other expenses are billed at cost
SUMMARY
TOTAL
SCOPE OF WORK
Page 16 of 16
GRESIK GAS COGENERATION PLANT PROJECT
COMMERCIAL PROPOSAL
ONE (1) UNIT GAS SCRUBBER PACKAGE
PT PACIFIC PROCESS ENGINEERING
OUR REF. NO.
16362-QTN-PPE-II-2017 REV.1
1 IFB 20-02-2017 Re-Issued For Bid HM PI AS
0 IFB 12-02-2017 Issued For Bid HM PI AS
Rev. Status Date Revision memo Issued by
Checked by
Approved by
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Commercial Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 2 of 7
TABLE OF CONTENT TABLE OF CONTENT ............................................................................................................................................................ 2
1. SCOPE OF SUPPLY ...................................................................................................................................................... 3
2. SCOPE OF WORKS ...................................................................................................................................................... 3
3. DELIVERY ..................................................................................................................................................................... 5
4. COMMERCIAL OFFER .................................................................................................................................................. 6
4.1. PRICE OF EQUIPMENT ....................................................................................................................................... 6
4.2. PAYMENT TERMS ............................................................................................................................................... 7
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Commercial Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 3 of 7
1. SCOPE OF SUPPLY
Supply of One (1) Set of Fuel Gas Scrubber Package, consist of:
- 1 Unit of Fuel Gas Scrubber Vessel, CS Material - 1 set of Drip Leg at Vent Header - 1 lot of Field Instrumentation, as per PID & Technical Specification - 1 lot of Manual Valves, as per PID & Technical Specification - 1 lot of Pipe Spool inside-skid limit, Carbon Steel Material, as per PID & Technical Specification - 1 lot of Structural Skid Base and Support, Carbon Steel Material
Additional Supply: (LOOSE SUPPLY)
- Supply Raw Material for Interconnecting Piping from Scrubber to Condensate Tank: o Pipe, 2”-Sch.40, A53, SMLS, Qty 3 length (@ 6 meter) o Flange, 2”-ANSI 150,A105, Qty 6 ea o Stud Bolts/Nuts, A193-B7/A194-2H, For Flange 2”-ANSI 150, Qty. 6 sets o Gasket, Spiral Wound, SS316, For Flange 2”-ANSI 150, Qty. 6 sets o Elbow, 2”-Sch.40,LR, A234-WPB, Qty 3 ea
- Supply Raw Material for Interconnecting Piping from Scrubber to Vent line: o Pipe, 4”-Sch.40, A53, SMLS, Qty 3 length (@ 6 meter) o Flange, 4”-ANSI 150,A105, Qty 1 ea o Stud Bolts/Nuts, A193-B7/A194-2H, For Flange 4”-ANSI 150, Qty. 1 set o Gasket, Spiral Wound, SS316, For Flange 4”-ANSI 150, Qty. 1 set o Elbow, 4”-Sch.40,LR, A234-WPB, Qty 3 ea
OPTIONAL (LOOSE SUPPLY)
- Supply One (1) Unit Flow Computer, Field Mounted type, Single Meter Run, for Orifice Flow Meter
2. SCOPE OF WORKS
6.1. ENGINEERING
Provide dicipline engineer (Process, Mechanical, Piping & Instrument engineer) Perform basic engineering design covering process simulation, equipment sizing, pipe sizing, and other
related process engineering activity Provide detail design covering system design, piping design, structural design, Instrumentation design,
and other detail design Manage engineering document submission and approval Provide engineering activity control Provide manufacturing data book and operating manual Assist client during engineering meeting / review with end end user (if required)
6.2. PROCUREMENT
Prepare material procurement plan Prepare Request for Quotation to sub vendor Prepare Purchase Order (PO) to sub vendor Expedite on every purchased material Arrange shipment and custom clearance for imported material (if any)
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Commercial Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 4 of 7
Perform material receiving inspection Compile for all manufacture material & Test certificate
6.3. FABRICATION Prepare Fabrication schedule Prepare all document required for fabrication activity Conduct pre-inspection meeting prior start fabrication Procure raw material and consumable Provide all equipment and tools required during fabrication process Prepare man power for fabrication Perform fabrication activity (Marking, Cutting, Rolling, Forming, Setting, Welding, etc.) Perform blasting and painting as per approved procedure and spec. Perform assembly and installation of all component / parts Perform flushing and cleaning Prepare packing for safe transportation and provide disassembly part for transportation purpose Prepare packing list Prepare QC dossier for certification Prepare fabrication manufacturing data book (MDR) Provide support during installation and assembly and testing and commissioning
6.4. ASSEMBLY
Installation of main equipment on skid base Installation of interconnecting valve and piping on skid boundary Installation of field instrument
6.5. TESTING & INSPECTION
Perform on progress fabrication inspection as per approved ITP (Material receiving inspection, NDT, Hydrotest, and etc.)
Perform instrument calibration
6.6. CERTIFICATION AND WARRANTY
Certification only applies for Pressure Vessel and PSV Supply. (Certification provide from DEPNAKER ) Mechanical Warranty will provide for period 18-months from Installation or 12-months from
Commissioning. Mechanical Warranty cover only for manufacturing defect. Other defect cause by Installation are excluded
Process Warranty will cover 12-months after Installation, subject to Inlet Process Data as per our Proposal. Any change on inlet process data will make our warranty to be review based on change of data.
6.7. INCLUSION
Anchor Bolt (Supply Loose) Delivery to Site Gresik Supervision for Installation, Start-Up and Commissioning, (for max. 5-days duration)
Beyond 5-days, Daily Rates will be applied
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Commercial Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 5 of 7
6.8. EXCLUSION
All material outside battery limit Civil Foundation Level Controller & Interconnecting Cable to Control Panel / Control Room Lifting Device and Unloading at Site. Installation of Scrubber on Foundation Installation Loose Supply Item & Interconnecting Pipe from Scrubber to Vent/Condensate Line Supply and Installation of Pipe Support of Interconnecting Pipe Other Scopes which not mentioned above
3. DELIVERY
Delivery Time : 16 (Sixteen) weeks after received Order Delivery Point : DDP Project Site Gresik
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Commercial Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 6 of 7
4. COMMERCIAL OFFER
We propose our commercial proposal and our standard Terms and Conditions for further clarification and/or negotiation as follows:
4.1. PRICE OF EQUIPMENT
All prices are based on scope of work above as clearly described in Technical Proposal. Any separation or deletion of singularly priced, will impact pricing
GAS SCRUBBER PACKAGE
ITEM QTY UNIT DESCRIPTION PRICE
1 1 LOT GAS SCRUBBER PACKAGE LUMPSUM PRICE
Consist of :
1 Unit GAS Scrubber Vessel
1 Lot Field Instrumentation- Inside Skid Limit
1 Lot Manual Valves- Inside Skid Limit
1 Lot Piping Spool- Inside Skid Limit
1 Skid Structural Skid Base & Support
As per Technical Proposal
2 1 LOT RAW MATERIAL FOR INTERCONNECTING PIPE
From Scrubber to Condensate Tank
Pipe 2”-sch.40, A53 Smls, Qty 3 length (@ 6 m)
Flange 2”-ANSI 150, A105, Qty 6 ea
Gasket, Sp. Wound, SS316 for Flange 2”-150#, Qty 6 ea
Bolt/Nuts, A193-B7/A194-2H for Flange 2”-150#, Qty 6 set
Elbow, 2”-sch.40, A234-WPB, Qty 3 ea
3 1 LOT RAW MATERIAL FOR INTERCONNECTING PIPE
From Scrubber to Vent Line
Pipe 4”-sch.40, A53 Smls, Qty 3 length (@ 6 m)
Flange 4”-ANSI 150, A105, Qty 1 ea
Gasket, Sp. Wound, SS316 for Flange 4”-150#, Qty 1 ea
Bolt/Nuts, A193-B7/A194-2H for Flange 2”-150#, Qty 1 set
Elbow, 4”-sch.40, A234-WPB, Qty 3 ea
TOTAL PRICE – DDP SITE GRESIK, EAST JAVA : IDR 1,190,000,000.00
In words: One Billion One Hundred and Ninety Million Rupiah only
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Commercial Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 7 of 7
OPTIONAL QUOTE:
ITEM QTY UNIT DESCRIPTION PRICE
1 1 UNIT FLOW COMPUTER FOR ORIFICE FLOW METER IDR 90,000,000.00
Field Mounted type, AGA-3, Single Meter Run
4-20mA Input, RTD Input
Mfr/Model: Dynamics Flow Computers, USA / E-Lite
TOTAL PRICE – DDP SITE GRESIK, EAST JAVA : IDR 90,000,000.00 4.2. PAYMENT TERMS
Payment Milestone :
o 5% after Major Engineering Submission (PID, Datasheet, GA Drawing) o 10% after Raw Material (Pipe, Flange, Fittings, Structural parts) arrived at Fabrication Shop o 15% after Factory Acceptance Test at Fabrication Shop o 30% after Material arrival on Site o 25% after Installation on Foundation or max 1-month after Arrival on Site o 10% after Testing & Commissioning or max. 2-months after Material Installation o 5% Retention, can be replaced by 5%-Retention Bond
Payment Terms : by T/T net 30 days or SKBDN Ussance 90 days
NOTE : This price is valid for 30 days after date of offer Price in Indonesian Rupiah Price exclude VAT 10% and other applied taxes
GRESIK GAS COGENERATION PLANT PROJECT
TECHNICAL PROPOSAL
ONE (1) UNIT GAS SCRUBBER PACKAGE
PT PACIFIC PROCESS ENGINEERING
OUR REF. NO.
16362-QTN-PPE-II-2017 REV.1
1 IFB 20-02-2017 Re-Issued For Bid HM PI AS
0 IFB 12-02-2017 Issued For Bid HM PI AS
Rev. Status Date Revision memo Issued by
Checked by
Approved by
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Technical Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 2 of 11
TABLE OF CONTENT TABLE OF CONTENT ............................................................................................................................................................ 2
1. GENERAL ..................................................................................................................................................................... 3
2. DESIGN BASIS .............................................................................................................................................................. 3
2.1 Reference Document ................................................................................................................................................ 3
2.2 Design Data ............................................................................................................................................................. 3
3. TECHNICAL SPECIFICATION OF GAS SCRUBBER PACKAGE ...................................................................................... 3
4. PROPOSED MANUFACTURE / VENDOR ....................................................................................................................... 7
5. SCOPE OF SUPPLY ...................................................................................................................................................... 9
6. SCOPE OF WORKS ...................................................................................................................................................... 9
7. DELIVERY ................................................................................................................................................................... 11
8. ATTACHMENT ............................................................................................................................................................ 11
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Technical Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 3 of 11
1. GENERAL
PT. Pupuk Indonesia Energi plan to build Gresik Gas Cogeneration Plant Project. Fuel Gas Scrubber is part of Natural feed Gas system that installed upstream of Gas Metering.
This document covers technical specification of One (1) unit Fuel gas Scrubber and accessories.
2. DESIGN BASIS
2.1 Reference Document
GGCP-04-P0-PI-001-PP Rev.6 PID Natural Gas Feed System – (Sheet 1 of 2) GGCP-04-M2-DS-002-PP Rev.2 Mechanical Data Sheet for Fuel Gas Scrubber
(01-HD-12702-A/B)
2.2 Design Data
Design Data : Design Pressure : 25.3 kg/cm2.G Design Temperature : 80 ⁰C Operating Pressure : 21.8 kg/cm2.G Operating Temperature : 15.6 – 48.9 ⁰C Gas Flowrate : 15004 kg/hr Gas Density @ T,P : 15.7 kg/m3 Gas Viscosity @ T,P : 0.0178 cP Liquid Flowrate : 3.4 kg/hr Liquid Density @ T,P : 849.1 kg/m3 Liquid Viscosity @ T,P : 0.78 cP
3. TECHNICAL SPECIFICATION OF GAS SCRUBBER PACKAGE
3.1. FUEL GAS SCRUBBER
Service : Fuel Gas Scrubber Tag No. : 01-HD-12702 A Qty : 1 unit Type : Vertical Design Data : Design Code. : ASME Section VIII Div.1 Latest edition Design Pressure : 25.3 kg/cm2.G Design Temperature : 80 ⁰C Operating Pressure : 21.8 kg/cm2.G Operating Temperature : 15.6 – 48.9 ⁰C Gas Flowrate : 15004 kg/hr Gas Density @ T,P : 15.7 kg/m3 Gas Viscosity @ T,P : 0.0178 cP Liquid Flowrate : 3.4 kg/hr Liquid Density @ T,P : 849.1 kg/m3 Liquid Viscosity @ T,P : 0.78 cP
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Technical Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 4 of 11
Vessel Data Shell Diameter (ID) : 800 mm Shell Length (T/T) : 2500 mm Shell Thickness : 12 mm Head Thickness : 12 mm Head Type : 2:1 Ellipsoidal Orientation : Vertical Support Type : Skirt Internal Manufacture : Rhine Ruhr or equals Internal
Mist Eliminator type : Demister Inlet Device : No Vortex Breaker : Yes
Performance Particle to be remove : Liquid droplet Particle Size : 10 micron and larger liquid droplet Removal Efficiency : 98% Material : Shell : SA-516 Gr.70 Head (Bottom) : SA-516 Gr.70 Flanges : SA-105 Nozzle Neck / Pipe : SA-106 Gr. B Pipe Fittings : SA-234 Gr.WPB Support (Skirt) : SA-516 Gr.70 / SA-36 External Bolts / Nuts : SA 193 Gr.B7 / SA 194 Gr.2H Internals Bolts / Nuts : SA 193 Gr.B8 / SA 194 Gr.B8 Internals Removable : SA-240 Gr. 304 Earthing Lugs : SA-240 Gr. 304 Lifting Lugs / Tailing Lugs : SA-516 Gr. 70 Name Plate / Bracket : SA-240 Gr. 304 / SA-516 Gr.70 Painting Specification
Internal : None External
o Surface Preparation : Blast Clean Sa 2.5 o Painting System (Shop Painting) : Primer : Organic Silicate Zinc Primer, DFT 75 Intermediate : Two pack epoxy micaceous Iron Oxide Undercoat, DFT 100 Total DFT : 275
Nozzles Schedule:
MARK SERVICE QTY SIZE CONN. TYPE RATING SCH.
N1 Gas In 1 10" SO RF 300# 40
N2 Gas Outlet 1 8" SO RF 300# 40
N3 Liquid Outlet 1 2” SO RF 300# 40
N4 PSV Connection 1 3” SO RF 300# 40
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Technical Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 5 of 11
MARK SERVICE QTY SIZE CONN. TYPE RATING SCH.
N5A/B LG/LT Connection 2 2” SO RF 300# 40
N6 PG Connection 1 3/4” SO RF 300# 80
N7 Spare 1 3/4” SO RF 300# 80
M1 Hand hole 1 8” - 300# -
3.2. DRIP LEG
Service : Drip Leg at Vent Tag No. : 01-FC-12704 Qty : 1 unit Size : 100 ID x 1220 mm H Material : Carbon Steel
3.3. INSTRUMENTATION
No. Description Specification Qty Remarks
1
Pressure Gauge (12-PG-703A)
Bourdon Tube, 6 Inch Dial Diameter, Case Stainless Steel, Material Tube & Socket SS316, Shattered Proof, Body Material : steel Brand : Ashcroft or equal
1 set
Install at Gas Scrubber
2
Level Transmitter
(12-LT-701A)
Smart Level Transmitter, Output Signal : Output Signal : 4-20 mA with Digital Signal based on HART protocol, Case Material : Aluminum , Power Source : 24 VDC, Element Material : 316SS, Process connection : 1/2” NPT & 5 Way Valve manifold Brand: Rosemount or equal
1 set
Install at Gas Scrubber
3
Level Control Valve
(12-LV/ZT-701A)
Body Type : Body Material : A105 WCB, Seat Material : 316 SS. diaphragm Spring Return Actuator, Pneumatic Type c/w positioner Brand: Fisher or equal
1 Set
Install at Gas Scrubber Liq Outlet
4
Level Gauge (12-LG-701A) (12-LG-702)
Gauge Column, Reflex Type, Armored, ½” NPT, Carbon Steel, Vessel Connection ¾” Gauge Chock Offset c/w Vent & drain. Brand: Jerguson or equal
2 set
Install at Gas Scrubber & Drip Leg
5
Pressure Safety
Valve (12-PSV-701A)
Carbon Steel Body & Bonnet, 316Ss Seat & Disc, Guide, Ring and Spring, Size 3”-300# x 4”-150# Brand: Farris or equal
1 set
Install at Gas Scrubber
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Technical Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 6 of 11
INSTRUMENTATION – OPTIONAL (LOOSE SUPPLY ITEM)
No. Description Specification Qty Remarks
1
Flow Computer
Field-mounted type Flow Computer, Aluminum housing, NEMA 4X, 64x128 pixel Graphic Display, 4-20mA Analog Input, RTD input, Communication RS-232 & MODBUS, Single Meter Run, Metric & US Units, Brand: Dynamics Flow Computer - USA
1 unit
Field Instrument
only
3.4. MANUAL VALVES
No Type Qty Size Class Specification Install at
1 BALL 2 8" 300# A216-WCB, ANSI Cl. 300, RF, SS304 Ball, PTFE Seat, Fire Safe, API 608, ASME B16.10, ASME B16.34
Inlet/Outlet Scrubber Isolation Valve
2 CHECK 1 8” 300# A216 WCB, ANSI Cl. 300, RF, Trim #1, Bolted Cover, Swing, API 594, ASME B16.10, ASME B16.34
Outlet Scrubber Isolation Valve
3 BALL 1 3" 300# A216-WCB, ANSI Cl. 300, RF, SS304 Ball, PTFE Seat, Fire Safe, API 608, ASME B16.10, ASME B16.34
Inlet PSV Isolation Valve
4 GATE 2 2" 300# A216 WCB, ANSI Cl. 300, RF, Trim #1, Bolted Bonnet, OS&Y, API 600, ASME B16.10, ASME B16.34
Level Bridle Isolation Valve
5 GATE 3 2" 300# A216 WCB, ANSI Cl. 300, RF, Trim #1, Bolted Bonnet, OS&Y, API 600, ASME B16.10, ASME B16.34
Inlet/Outlet Control Valve Isolation Valve & Bypass
6 GATE 1 2" 150#
A216 WCB, ANSI Cl. 300, RF, Trim #1, Bolted Bonnet, OS&Y, API 600, ASME B16.10, ASME B16.34
Drip Leg Drain Valve
7 BALL 1 3/4” 800# A105, 800 lb, 304SS Ball, PTFE Seat, Full Port, SW, Fire Safe, API 608, ASME B16.10, ASME B16.34
PI Isolation valve
8 BALL 2 3/4” 800# A105, 800 lb, 304SS Ball, PTFE Seat, Full Port, SW, Fire Safe, API 608, ASME B16.10, ASME B16.34
PSV Upstream / Downstream Vent valve
9 BALL 1 3/4” 800# A105, 800 lb, 304SS Ball, PTFE Seat, Full Port, SW, Fire Safe, API 608, ASME B16.10, ASME B16.34
Scerubber Vent valve
10 GATE 4 3/4" 800# A105, 800 lb, SW, Trim #8, Bolted Bonnet, OS&Y, API 602, ASME B16.10, ASME B16.34 LG Isolation Valve
11 GATE 2 3/4" 800# A105, 800 lb, SW, Trim #8, Bolted Bonnet, OS&Y, API 602, ASME B16.10, ASME B16.34
LT Isolation Valve
12 GATE 2 3/4" 800# A105, 800 lb, SW, Trim #8, Bolted Bonnet, OS&Y, API 602, ASME B16.10, ASME B16.34
Bridle Vent/Drain Valve
13 GATE 2 3/4" 800# A105, 800 lb, SW, Trim #8, Bolted Bonnet, OS&Y, API 602, ASME B16.10, ASME B16.34
Control Valve Vent/Drain Valve
14 GATE 6 1/2" 800# A105, 800 lb, SW, Trim #8, Bolted Bonnet, OS&Y, API 602, ASME B16.10, ASME B16.34 LG/LT Vent/Drain Valve
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Technical Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 7 of 11
3.5. PIPING TIE-IN
Inlet to Fuel Gas Scrubber Size : 8 inch – Sch.40 Material : Carbon Steel, A-53, SMLS Outlet to Gas Metering Size : 8 Inch – Sch.40 Material : Carbon Steel, A-53, SMLS Drain Line to Condensate Tank Size : 2 inch – Sch.80 Material : Carbon Steel, A-53, SMLS
Vent Line to Venting header Size : 4 inch – Sch.80 Material : Carbon Steel, A-53, SMLS
3.6. STRUCTURAL SKID
Material : Carbon Steel, SA 36 / SS400 Lifting Lugs : 4-points on edge skid Grounding Lugs : 2-points, installed on skid corner Est. Dimension : 3000 mm L x 2000 mm W x 4450 mm H
4. PROPOSED MANUFACTURE / VENDOR
Fabricator :
PT. Prakarsalanggeng Majubersama PT. Gemala Sarana Upaya PT. Multifabrindo Gemilang PT. Envicon Ekatama
Gate / Ball / Check Valve : KVC - UK Alphacon (APDN) SPV Valve (APDN) Crane Tomoe GLT
Control Valve (Globe) : Fisher Samson Yamatake (Azbil) CCI Valtek /Flowserve
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Technical Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 8 of 11
Level Transmitter : Rosemount Yamatake (Azbil) Honeywell Magnetrol
Level Gauge : Jerguson Penberthy Daniel (Quest-Tec)
Pressure Gauge : WIKA - Germany Ashcroft - USA Rueger -Switzerland Bourdon - France Nuovo Fima - Italy
Pressure Safety Valve : Farris-USA Crosby - USA Dresser (Consolidated)-USA LESER – Germany ARI Armaturen - Germany
Flow Computer : Dynamic Flow - USA
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Technical Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 9 of 11
5. SCOPE OF SUPPLY
Supply of One (1) Set of Fuel Gas Scrubber Package, consist of:
- 1 Unit of Fuel Gas Scrubber Vessel, CS Material - 1 set of Drip Leg at Vent Header - 1 lot of Field Instrumentation, as per PID & Technical Specification - 1 lot of Manual Valves, as per PID & Technical Specification - 1 lot of Pipe Spool inside-skid limit, Carbon Steel Material, as per PID & Technical Specification - 1 lot of Structural Skid Base and Support, Carbon Steel Material
Additional Supply: (LOOSE SUPPLY)
- Supply Raw Material for Interconnecting Piping from Scrubber to Condensate Tank: o Pipe, 2”-Sch.40, A53, SMLS, Qty 3 length (@ 6 meter) o Flange, 2”-ANSI 150,A105, Qty 6 ea o Stud Bolts/Nuts, A193-B7/A194-2H, For Flange 2”-ANSI 150, Qty. 6 sets o Gasket, Spiral Wound, SS316, For Flange 2”-ANSI 150, Qty. 6 sets o Elbow, 2”-Sch.40,LR, A234-WPB, Qty 3 ea
- Supply Raw Material for Interconnecting Piping from Scrubber to Vent line: o Pipe, 4”-Sch.40, A53, SMLS, Qty 3 length (@ 6 meter) o Flange, 4”-ANSI 150,A105, Qty 1 ea o Stud Bolts/Nuts, A193-B7/A194-2H, For Flange 4”-ANSI 150, Qty. 1 set o Gasket, Spiral Wound, SS316, For Flange 4”-ANSI 150, Qty. 1 set o Elbow, 4”-Sch.40,LR, A234-WPB, Qty 3 ea
OPTIONAL (LOOSE SUPPLY)
- Supply One (1) Unit Flow Computer, Field Mounted type, Single Meter Run, for Orifice Flow Meter
6. SCOPE OF WORKS
6.1. ENGINEERING
Provide dicipline engineer (Process, Mechanical, Piping & Instrument engineer) Perform basic engineering design covering process simulation, equipment sizing, pipe sizing, and other
related process engineering activity Provide detail design covering system design, piping design, structural design, Instrumentation design,
and other detail design Manage engineering document submission and approval Provide engineering activity control Provide manufacturing data book and operating manual Assist client during engineering meeting / review with end end user (if required)
6.2. PROCUREMENT
Prepare material procurement plan Prepare Request for Quotation to sub vendor Prepare Purchase Order (PO) to sub vendor Expedite on every purchased material Arrange shipment and custom clearance for imported material (if any)
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Technical Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 10 of 11
Perform material receiving inspection Compile for all manufacture material & Test certificate
6.3. FABRICATION Prepare Fabrication schedule Prepare all document required for fabrication activity Conduct pre-inspection meeting prior start fabrication Procure raw material and consumable Provide all equipment and tools required during fabrication process Prepare man power for fabrication Perform fabrication activity (Marking, Cutting, Rolling, Forming, Setting, Welding, etc.) Perform blasting and painting as per approved procedure and spec. Perform assembly and installation of all component / parts Perform flushing and cleaning Prepare packing for safe transportation and provide disassembly part for transportation purpose Prepare packing list Prepare QC dossier for certification Prepare fabrication manufacturing data book (MDR) Provide support during installation and assembly and testing and commissioning
6.4. ASSEMBLY
Installation of main equipment on skid base Installation of interconnecting valve and piping on skid boundary Installation of field instrument
6.5. TESTING & INSPECTION
Perform on progress fabrication inspection as per approved ITP (Material receiving inspection, NDT, Hydrotest, and etc.)
Perform instrument calibration
6.6. CERTIFICATION AND WARRANTY
Certification only applies for Pressure Vessel and PSV Supply. (Certification provide from DEPNAKER ) Mechanical Warranty will provide for period 18-months from Installation or 12-months from
Commissioning. Mechanical Warranty cover only for manufacturing defect. Other defect cause by Installation are excluded
Process Warranty will cover 12-months after Installation, subject to Inlet Process Data as per our Proposal. Any change on inlet process data will make our warranty to be review based on change of data.
6.7. INCLUSION
Anchor Bolt (Supply Loose) Delivery to Site Gresik Supervision for Installation, Start-Up and Commissioning, (for max. 5-days duration)
Beyond 5-days, Daily Rates will be applied
GRESIK GAS COGENERATION PLANT PROJECT NATURAL GAS FEED SYSTEM
Technical Proposal – GAS Scrubber Package Rev.1 (20-Feb-2017)) Page 11 of 11
6.8. EXCLUSION
All material outside battery limit Civil Foundation Level Controller & Interconnecting Cable to Control Panel / Control Room Lifting Device and Unloading at Site. Installation of Scrubber on Foundation Installation Loose Supply Item & Interconnecting Pipe from Scrubber Supply and Installation of Pipe Support of Interconnecting Pipe Other Scopes which not mentioned above
7. DELIVERY
Delivery Time : 16 (Sixteen) weeks after received Order Delivery Point : DDP Project Site Gresik
8. ATTACHMENT
Same as previous revision