Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Quanta Technology Page 1 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
1/19/08
Consulting Project #08T001
White Paper on
Technical Issues Related to NCUC Net Metering Docket 100, Sub 83
Prepared for: North Carolina Sustainable Energy Assoc. Prepared by: Quanta Technology, LLC Authors: Donald J. Morrow, PE [email protected] 919 334 3023
H. Lee Willis, PE [email protected] 919 334 3020
Quanta Technology Page 2 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
Table of Contents
1 INTRODUCTION ...................................................................................................................................... 3
1.1 NCUC NET METERING DOCKET........................................................................................................... 3 1.2 SPECIFIC QUESTIONS ............................................................................................................................ 3
2 T&D RELIABILITY CHALLENGES ..................................................................................................... 5
2.1 SAFETY ................................................................................................................................................. 6 2.2 INCREASING UNIT SIZE ......................................................................................................................... 6
2.2.1 Equipment Upgrades ....................................................................................................................... 7 2.2.2 Metering Upgrades .......................................................................................................................... 7 2.2.3 Protection and Control .................................................................................................................... 7 2.2.4 Standby Capacity ............................................................................................................................. 7 2.2.5 Power Quality .................................................................................................................................. 8
2.3 INCREASING AGGREGATE SIZE ............................................................................................................. 9 2.3.1 Adequacy & Definition of Aggregate Limit ..................................................................................... 9 2.3.2 Equipment Upgrades ..................................................................................................................... 10 2.3.3 Stand-by Capacity.......................................................................................................................... 10 2.3.4 Power Quality ................................................................................................................................ 11 2.3.5 Islanding ........................................................................................................................................ 11 2.3.6 Concentrations of Generation by Type .......................................................................................... 11
2.4 SMART GRID SYSTEMS ....................................................................................................................... 11 2.5 AGGREGATE NET EFFECT ON THE UTILITY ......................................................................................... 13
3 CONCLUSIONS ....................................................................................................................................... 15
4 ABOUT THE AUTHORS ........................................................................................................................ 17
5 BIBLIOGRAPHY..................................................................................................................................... 18
APPENDIX: CATALOG OF T&D RELIABILITY ISSUES RELATED TO DG..................................... 19
Quanta Technology Page 3 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
1 Introduction
The North Carolina Sustainable Energy Association (“NCSEA”) has engaged Quanta Technology,
LLC (“QT”) to assist them with technical issues related to Net-metering Docket E-100, Sub 83 open
before the North Carolina Utilities Commission (“NCUC”).
This project draws upon the collective knowledge, experience and expertise of several QT advisors in
the areas of distributed generation, T&D engineering, T&D standards, electric system maintenance,
electric system operation, and resource planning.
1.1 NCUC Net Metering Docket
On October 20, 2005 the NCUC issued its Order Adopting Net Metering. In this Order, the NCUC
made net metering available to “a utility customer that owns and operates a solar PV, wind-powered,
or biomass-fueled renewable energy facility without battery storage.”
Among other requirements identified in this Order, NCUC allowed for generating facilities with
capacity up to 20 kW for residential customer and up to 100 kW for non-residential customers. In
addition to these individual facility limits, the NCUC adopted “an aggregate limit of 0.2% of the
utility’s North Carolina jurisdictional retail peak load for the previous year.”
Subsequent to this Order becoming effective, the NCUC in December 2007 issued an Order
Requesting Comments to address questions related to the need for specific service riders to sell excess
energy, as well as to explore the need for additional metering if the customer is not seeking credit for
sale of such excess energy. In issuing the Order Requesting Comments, the NCUC noted “the
Commission has seen tremendous growth in the number of small customer-owned electric generating
faculties and anticipates continued growth as a result of the enactment of the Renewable energy and
Energy Efficiency Portfolio standard (REPS) provisions.”
Comments are due to the NCUC in response to the December, 2007 Order Requesting Comments on
or before January 18, 2008. NCSEA intends to issue comments on this December, 2007 request.
1.2 Specific Questions
Given the recent passage of Senate Bill 3, NCSEA anticipates significant growth of sustainable
energy resources in the State. To achieve this legislative mandate, they anticipate that the
requirements related to generating facility size and aggregate system load from the Docket 100, Sub
83 may need to be increased. Indeed, NCSEA in the earlier, 2005 process had advocated for larger
net aggregate generation eligible for net metering of 1% of utility growth. As NCSEA develops their
comments on the December, 2007 Order Requesting Comments, they have requested the assistance of
QT to sort through reliability issues related to increase per facility size and the aggregate limit.
The specifically questions NCSEA asks are:
� How should the term “Aggregate Limit” discussed in the docket be defined?
Quanta Technology Page 4 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
� Given the above definition and the current state of the NC electric system, what is the
maximum limit for the net system capacity for aggregated net-metering necessary to preserve
system reliability? What is the maximize size limit for individual generators eligible for net-
metering?
� Given these limits, what system upgrades may be necessary to maintain reliability?
� Please quantify this investment in terms of type of investment
During the kick-off meeting on January 10, 2008, NCSEA indicated they are contemplating
individual facility size of 1 to 2 MWs and aggregate limit of 2%
Quanta Technology Page 5 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
2 T&D Reliability Challenges
Electric system reliability is a complex issue. There are several components that must be considered
as one contemplates impacts of certain changes to the electric system. These issues include:
� Continuity of service to the customer
� Quality of power delivered to the customer
� Impacts on customer equipment
� Impacts on neighboring systems (i.e., utility A’s actions impacting utility B’s reliability)
� Maintaining common interconnection standards (e.g. frequency and time standards)
� Ensuring adequacy of supply during times of peak
� System resonance conditions that transcend customer, or even utility, boundaries
Utilities utilize a variety of techniques to maintain reliability. Following are some commonly applied
methods used by utilities for maintaining the reliability of the electric system:
� Formal work practices and safety rules.
� Industry standards to ensure consistency from system to system (e.g., ANSI, NESC, IEEE,
NEC, etc.)
� Manufacturing standards to ensure consistency of device operations (e.g., ANSI, UAL, IEEE,
NEMA, etc.)
� Federal Mandated Reliability Standards implemented through the North American Electric
Reliability Corporation (“NERC”) to ensure reliable operation and capacity adequacy of the
three interconnections in the USA.
� Rates and rules set by States to ensure minimal standards are met for customer
interconnections.
� Utility design standards which reinforce, augment, and apply the above within the utility.
� Maintenance practices to ensure equipment is operating properly.
� Work practices to ensure safe operation for customers and utility workers.
� Protection schemes which monitor the performance of portions of the electric system and act
to protect equipment and restore service when incidents occur.
� Control centers which collect system data, evaluate conditions and issue controls to maintain
and ensure reliable service to the customers.
When distributed generation (“DG”) is added to the system (including sustainable facilities eligible
for net metering in North Carolina), care must be taken to ensure that reliability is maintained.
However, these methods are often adequate to maintain reliability even as the individual facility size
and the aggregate limit are increase.
In the following sections, we discuss safety as it relates to DG, the impacts to reliability based upon
increasing the size of facilities eligible for net metering, and impacts based upon increasing the
aggregate size.
Quanta Technology Page 6 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
2.1 Safety
The most important issue with the electric system is safety. Working near energized electrical
equipment can be hazardous if safe equipment and design are not used, and if good work practices are
not followed. The energy present in most parts of an electric utility system is sufficient to burn, maim
or kill a human being if not properly handled. Adding generation behind the meter (i.e., at the
customer location) adds to the amount of energy present and can increase safety concerns in some
situations, particularly if there is a potential for “back-feeding” into the utility system. This occurs
when the utility’s equipment has been de-energized so that it is not feeding power to its equipment,
but customer-owned facilities are still feeding power, perhaps sufficient to cause hazardous
conditions for any field personnel caught unawares because they expect the utility equipment to be
completely de-energized.
A concern with any size and amount of customer-owned generation is that it can be difficult, and in
some cases impossible, for utility field personnel to determine if there is customer-owned generation
installed at a particular site based on only a visual inspection of the service interface. Increasing the
permitted size of customer-owned generation will increase the “reach” or extent (the portion of the
system) over such which customer-generation concerns would be an issue, and would increase also
the magnitude of any safety-related issues associated with fault current contributions such generation
would makes under back-feeding conditions1.
To address these safety issues utilities have developed work practices and safety rules which make
work on utility systems with customer-owned generation safe and efficient. These safety practices
include testing for backfeed voltage, formal tagging and clearance processes, grounding practices, use
of regularly tested protective gear (e.g., rubber cloves, hot sticks), requirements for flame retardant
clothing, etc. These practices - when rigorously followed by field crews, operators and their
supervision - ensure their safety and protection.
One may argue that increasing penetration of DG installations (including those covered to the NCUC
net metering docket) will increase the probability of exposure to back feeding, and therefore
negatively impact safety. However, consistency of method and process is a hallmark of sound safety
programs. These practices need to be followed routinely whenever there is any customer-owned
generation that could be operating on the utility system, be it units limited to 20 kW in size or 2 MW,
and regardless of whether they constitute only .2% or 2% of system generation. Thus, when safety
rules and work practices are followed rigorously and accurately, individual unit size and aggregate
total limits are not really an issue for field worker safety.
2.2 Increasing Unit Size
This section discusses the specific reliability impacts due to increasing facility size.
1 A back-feed condition exists when the utility breaker is open on a feeder, but a customer generation is on and
connected to the feeder. The generator “back-feeds” the feeder and maintains voltage on the feeder.
Quanta Technology Page 7 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
2.2.1 Equipment Upgrades
While unique situations are certain to exist, generally it is not anticipated that equipment upgrades
will be needed for increasing facilities eligible for net metering to 1 or 2 MWs in size.
2.2.2 Metering Upgrades
Much of the metering and customer-connection equipment in use by utilities throughout North
Carolina is unidirectional: specified, designed, and installed based on an assumption that electricity
only flows from the utility into the customer facilities. This was a very reasonable assumption to
make in the past, when no customer-owned generation was expected to be present on the system.
Bi-directional meters and other revised equipment may need to be installed for any DG installations,
whether net metered or otherwise. The “metering” and equipment under discussion is not that
required for billing purposes but that which are required for measurement of current flows so that the
utility can operate its power system safely, efficiently, and to acceptable standards of power quality
2.2.3 Protection and Control
Owners of generation facilities eligible for net metering will often desire to sell their excess energy
(energy produced by the facility and which exceeds what is required to meet their own needs) into the
utility grid. Technically, production of excess energy requires the utility to have the ability to detect
and measure flows bidirectionally (in and out of the customer site) in order to monitor power flow
and fault protection so it can control voltage and service quality for its customers. From a practical
standpoint, however, only very limited equipment, consisting of cutout fuses, may be required for
really small generators, in the range of 5 kW up to perhaps 20 kW, because such small units do not
have the capability to alter voltage or power flow on a utility circuit by a substantial amount.
Increasing the permitted generation limit to 1 or 2 MW would require monitoring and protection
equipment that is both rated at higher current levels than that required for generators in the 10 to 100
kW class facilities, and in some cases capable of more extensive measurement and control functions.
As unit size is increased, this may involve installation of additional or more precise voltage, current,
and harmonics measurement equipment, along with voltage regulators, switching or fixed capacitors,
circuit reclosers or breakers, and two-way real-time communications equipment to the utility’s
distribution control center.
2.2.4 Standby Capacity
Increasing facility size (permitted limit for customer owned generation) for net metering will likely
decrease the peak demands measured by the utility on its distribution circuits (power being feed into
distribution circuits by one customer services demand of nearby customers, reducing the amount the
utility must provide). However, the utility will still have an obligation to serve the total customer
load as imposed by the NCUC. It will have to accumulate data on gross and net installed customer-
owned generation on its system (in part by using the monitoring systems discussed in 2.2.3) and
combine that with its circuit-level peak demand readings in order to track and plan the system
capabilities needed to meet its obligations. However, such recording and planning is routinely done
by many electric utilities for other reasons (tracking large transient industrial loads), and is needed
regardless of the size and amount of generation installed.
Quanta Technology Page 8 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
2.2.5 Power Quality
Many electric customers can be inconvenienced by voltage surges and dips, high voltage, voltage
flicker, or harmonics affecting their sensitive electrical equipment. As any local generation facility
increases in size, it’s potential to create noticeable power surges in the circuit area nearby increases.
Particularly upon starting and stopping the unit, as size of the unit increases, the effect of surges and
“voltage flicker” becomes more noticeable for neighboring customers. Voltage regulation on the area
of the system nearby becomes more of a potential issue, too.
To address these issues, many utilities have established rules that specify times, conditions, and the
type of startup and shut-down sequences the generator must follow to provide voltage control and
manage power surges. These rules and the process to work with them are not materially different in
any way due to increasing facility or aggregate limit size. Further, the sustainable energy resources
will typically operate on a continuous basis and will not subject the system or other customers to such
conditions.
Wind turbines can create voltage flicker conditions2 due to the fact that smaller generators may use
synchronous generators which vary in their output by the variation of the wind. In these cases, the
utility may establish a rule for power factor range on small wind scale wind facilities to prevent this
type of impact on neighboring customers. Customers may be required to install certain dynamic
power factor correction equipment such as DSTATCOMs or Dynamic Var Compensator devices to
maintain voltages at acceptable levels for the utility. This case assumes that no pre-existing voltage
flicker issues exist on the feeder so that the cause of voltage flicker can be appropriately determined.
For sustainable resources that use DC-AC converters (variable speed wind turbines, solar
installations, etc.) harmonics may become an issue. Harmonics exist when energy is injected into the
grid at frequencies that are multiples of 60 hertz. Harmonic questions are often difficult to sort out as
to what causes them: often any negative affects are the cumulative result of many harmonic sources
including computer power supplies, overloaded utility or customer-owned transformers, worn or
corroded electrical equipment grounding, certain types of lighting and industrial processes, as well as
DC-AC converters.
Utilities manage these issues with regard to customer owned generation by requiring generators to
satisfy interconnection standards. The Institute for Electric and Electronic Engineers (“IEEE”), a
professional engineering organization, has addressed these concerns by developing maximum
standards for harmonic current injections by DG (distributed generation) sources through IEEE 1547.
These standards are used by manufacturers in their designs and customers are required to adhere to
their specifications. Utilities in North Carolina may enforce this standard with their service rules filed
with the NCUC. If a particular installation results in harmonic issues, these issues can be managed by
installation of harmonic filters that remove the problem before it is injected on the grid. In cases
where it is clear customer installed equipment is the cause, those customers will be required to install
harmonic filtering on their installations or make other changes or equipment installation.
2 Voltage flicker is the term used for noticeable illumination changes from lighting equipment due to voltage
fluctuations on the power system. This issue is addressed in IEEE Standard 1453.
Quanta Technology Page 9 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
Once again, it should be noted that these power quality issues may be present regardless of unit size.
Nonetheless, increasing generator size could intensify the power quality impacts of customer
generation facilities that are poorly-designed, installed, or operated. However, the utility’s
requirements as based on IEEE 1547 or similar guidelines will be effective in all cases if enforced
consistently. Therefore, the harmonic issue should be effectively managed.
2.3 Increasing Aggregate Size
This section discusses the specific reliability impacts due to increasing aggregate limit size.
2.3.1 Adequacy & Definition of Aggregate Limit
Currently the aggregate limit for net metered customer-owned generation in North Carolina has been
set to 0.2% of the utilities' peak load. Assuming a 20,000 MW peak demand level for North Carolina,
this aggregate limit is equal to 40 MWs of customer-owned, net metered generation throughout the
state. NCSEA is contemplating a 2% aggregate limit, which is equal to 400 MWs of sustainable
generation.
Utilities in North Carolina, like those in the rest of the US, are required to have firm capacity reserves
based upon a certain percentage of their firm load; SERC currently has guideline requirements for
planning reserve margins of just under 15% for utilities in the SE US. Nationally, according to page 4
of the NERC Summer Assessment for 2007, "capacity margins are intended to mitigate the higher
load levels associated with extreme weather events, the unplanned loss of generation capacity, and
provide sufficient operating margins." These limits are set to maintain a loss of load probability of 1
day every 10 years.
If sustainable resources are installed that provide high output during peak times (e.g., solar) or
facilities with stable output (e.g., gen-sets that run on methane fuel derived from farm waste), then
adequacy concerns are minimized. However, care must be taken with sustainable resources that can
radically vary their outputs when determining their capacity allocation. This is especially relevant as
parties contemplate increasing the aggregate limit.
First, if the aggregate limit is increased, it is possible that some of this anticipated supply would not
be available to the utility at the time of system peak. If that occurred, the result would be a realized
planning reserve margin reduction. Depending upon the amount of a reduction, such a reduction may
be sufficient to result in a measurable decrease in adequacy, resulting in electric customers throughout
North Carolina having a higher probability of a supply shortage. Even if a measurable reduction
were sufficient, however, it should also be noted that this measurable increased risk of a supply
shortage may still satisfy the one day in ten year NERC requirement. Only detailed analysis can
determine if that is the case.
Second, if capacity in the Docket 100, Sub 83 is taken to be the same that is used for wholesale
capacity planning, then the actual energy production potential from net metering facilities could be
higher than a limit anticipated by the NCUC. If care is not taken with the definition of capacity, then
unanticipated energy may enter the system, which may impact system operations if these amounts
significantly exceed the anticipated aggregate limit of 2%.
Quanta Technology Page 10 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
Fortunately, it is relatively easy to resolve a possible mismatch in assumed capacity and use of the
appropriate amount for use in resource planning at the wholesale level by following these steps:
1. Define capacity in Docket 100, Sub 83 as the name plate rating of the facility
2. Increase firm load requirement in planning reserve calculation as follows:
Reserve = (1 - capacity contribution factor) x aggregate sustainable capacity
eligible for net metering
Using the name plate rating as the basis for capacity in Docket E100, Sub 83 will prevent the situation
where unanticipated, large amounts of sustainable energy are produced. Adjusting the firm load
calculation will align the actual anticipated output of facilities at the time of system peak with the
amount assumed during resource planning.
If these steps are taken, then increasing the aggregate limit to 2% of system peak will result in
manageable adequacy and planning issues. Operation voltage and power swings should be
manageable at these levels of sustainable energy.
2.3.2 Equipment Upgrades
Much of the equipment used at the distribution level in a utility system is based upon specific current
ratings, most often limited to no more than 400 or 600 amps. This current limit is usually standard
for the type of equipment regardless of the distribution voltage level. However, very often, and by
design, the wire or cable and other equipment used at the ends of neighborhood feeder circuits has far
less capacity than this, often only 100 amps (the nominal rating of #6 size ACSR conductor) on small
laterals at the end of feeder circuits.
As the facility size and/or aggregate limit increase, heavy concentrations of DG near the end of a
circuit, if used for the sale of excess energy (that not needed by the customer) feed back into the grid
could cause current flows to exceed the rating of this equipment. Some equipment types are not
affected, including typically instrumentation metering, lightning arresters, and breakers will not
typically be impacted by either increasing facility size or the aggregate limit.
2.3.3 Stand-by Capacity
As discussed in section 2.2.4, increasing facility size for net metering will likely decrease the load
service measured by the utility. However, the utility may still have an obligation to serve that
customer imposed by the NCUC. Care must taken in the utility design standards to take this
condition into account as new facilities are developed, especially as the aggregate limit is increased
and individual feeders become more loaded – perhaps favoring certain types of sustainable energy
due to local area resource concentrations.
Quanta Technology Page 11 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
2.3.4 Power Quality
Increasing the aggregate limit for customer generation will increase the intensity of the potential
power quality problems, however rigorous application of standards and interconnection rules by the
utility should resolve these issues.
2.3.5 Islanding
As the aggregate limit is increased, the potential for “islanding” will as well. Islanding occurs when
local generation is serving all local customer energy use, and the area of the power system somehow
becomes disconnected from the electric grid (there is a blackout or other problem with the utility
power feed).
While islanding may appear advantageous to local customers (they are receiving power during a time
the utility has outage problems) islanding is nearly always problematic, because without utility
connection there is no local control of voltage, current, surges, and power flow: customer-owned DG
equipment cannot provide this function. As a result, an islanding configuration can often result in
low or high voltage, large and frequent transient voltage swings, and increased power quality
problems.
All of these issues can be addressed using standard utility grid sensing methods and equipment with
provisions to open the customer breaker (disconnect their generator) when the grid is not connected.
Sensing methods are improved greatly when advanced metering infrastructure (“AMI”) or Smart Grid
technology is used and may be required in certain instances.
2.3.6 Concentrations of Generation by Type
It is possible that while the overall diversity of sustainable resources by type may be significant, local
pockets within the North Carolina power grid may contain concentrations of only one type. For
example, it is likely that bio-mass processes will be concentrated on feeders that serve multiple hog
farms, solar will be concentrated in areas with high insolation, and wind will be concentrated in areas
with relatively, consistently steady wind resources.
As a result, the utility may experience an intensification of the issues identified in this report in a
given area of the system or even specific feeders. The technical resolution of the reliability issues are
the same. Utilities current methods discussed in other sections of this white paper should be
sufficient to manage these issues. However, it is conceivable that certain configurations may require
more advanced monitoring and control. In these cases, Smart Grid technologies may be warranted.
2.4 Smart Grid Systems
New technologies, products and control schemes permitting improved monitoring and control of local
distribution system performance and status are being brought into the electric power system
equipment market on an almost daily basis. These many new devices and systems are often referred
to jointly as “Smart Grid” technology. Smart Grid consists of combined use of technical
developments in several new technology areas (Figure 1).
Quanta Technology Page 12 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
Figure 1: Smart Grid Technology Overview
Smart Grid systems use a diverse range of local measurement sensors installed at many key points
throughout a utility distribution system to measure voltage, current, and perhaps equipment status and
condition on a moment to moment basis. “Smart” local equipment (voltage regulators, switches, etc.)
reacts automatically to control voltage, restore power flow if there are equipment outages, and
maintain good service to customers based on local readings and “knowledge” stored in their
computers about how they should react to various situations. Low cost data communications is used
to transmit key data on distribution system status and the actions of this automatic equipment back to
the utility control center.
Industry experience with these systems is evolving rapidly, driven by a number of trends and forces
(Figure 2) that have combined to both drive the industry to use this technology and to encourage
R&D to create new devices and systems to fill in “gaps” in needed capabilities of Smart Grid
systems. Overall, potential improvements in safety, efficiency, lower cost and improved reliability
and service quality are the benefits being sought.
Quanta Technology Page 13 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
Figure 2: Smart Grid Landscape
Smart Grid technology would enable an electric utility to monitor and adjust its distribution system
locally on an as-needed basis to best accommodate the output of sustainable customer owned
sustainable generation into its distribution grid on a moment-to-moment and location-to-location
basis, improving reliability, service quality, and potentially improving its ability to synergistically
combine cost-effective use of its existing distribution system with that of customer owned sustainable
generation, to improve reliability and to defer the need to add other resources on its system. The
degree to which utilities can install and utilitize such a system and gain these benefits will depend in
good measure on the support they get for use of such technologies from regulators and their rate
structure.
2.5 Aggregate Net Effect on the Utility
Sections 2.2.1 through 2.2.5, and 2.3.2 through 2.4 outlined various technical issues which a utility
might confront if limits are increased. These sections also identify equipment upgrades and/or other
additions utilities may need to make to address these technical issues.
The net effect of these changes in aggregate, along with increased size and totals for customer-owned
sustainable generation on the utility system’s performance and reliability, would depend greatly on
Quanta Technology Page 14 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
how well those issues were addressed in the engineering designs and standards followed by the utility
and the performance of the facilities being installed. Assuming that utilities are permitted to justify,
add, and pay for that needed additional equipment, including newer technologies (Section 2.4) in the
manner similar to how they have invested in their past systems, there is every reason to expect the net
impact would even be positive. First, the equipment and additions discussed here can potentially
alleviate all negative issues with respect to safety, reliability of service, power quality, equipment
utilization and operation, and overall utility performance. Second, availability of such local
generation has the potential to reduce electrical loses many hours of the year, actually boost voltage
and power factor (if combined with the correct added equipment, an assumption here) and to reduce
or defer future capital investment required for T&D expansion as consumer demand for power
continues to grow.
Finally, much of the equipment added because of customer-owned generation will have ancillary or
additional benefits to the utility. For example, harmonics monitoring and control devices, and
additional voltage regulation and power factor controllers that might be needed to accommodate
customer-owned sustainable generation could improve power quality all hours of the year, regardless
of whether that customer generation is operating. Utilization of Smart Grid technology has the
possibility of further enhancing a utility’s ability to monitor and control its own and customer
equipment and improves the operation and reliability of its system.
Quanta Technology Page 15 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
3 Conclusions
QT investigated the technical issues related to the T&D system resulting from increasing individual
sustainable resource size of customer-owned generation operated on a net-metered basis to the 1 to 2
MW range and increasing the aggregate limit to 2% of total system peak load. To summarize:
1. How should the term “Aggregate Limit” discussed in the docket be defined?
Answer: Based upon our review, safety, reliability and operating issues are manageable as long as
the definition of aggregate capacity in Docket 100, Sub 83 is taken as name plate capacity and
utilities adjust their firm load calculation for capacity planning as discussed in section 2.3.1.
2. Given the above definition and the current state of the NC electric system, what is the
maximum limit for the net system capacity for aggregated net-metering necessary to preserve
system reliability? What is the maximize size limit for individual generators eligible for net-
metering?
Answer: Assuming that utilities are permitted to justify, add, and pay for needed additional
equipment, including newer technologies, in a manner compatible with their traditional levels
of comprehensive engineering and equipment coordination, there is reason to expect the net
impact of customer-owned sustainable generation in the 1 to 2 MW class and aggregate total
of 2% of system peak on the North Carolina electric grid is manageable. The potential exists
that net impact could even be positive with regard to reliability, power quality, and system
efficiency.
3. Given these limits, what system upgrades may be necessary to maintain reliability?
Answer: The following are anticipated adjustments to utility systems as result of these contemplated
increases to facility size and aggregate limit:
� Investment in cable, wire and certain related equipment upgrades may be required on some
portions of distribution feeders.
� Additional or upgraded distribution equipment may need to be upgraded or new feeders
added in rare cases.
� Additional monitoring and protection equipment for bi-directional measurement, response,
and control of the distribution system in selected places of the system in which there are large
and/or heavy local concentrations of customer-owned generation.
� Bi-directional control metering and protection equipment may need to be installed.
� Operating procedures and standards may need to be revised, particularly in any local areas
with high concentrations of DG.
Quanta Technology Page 16 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
� Utility design standards and planning methods may need to be modified to take into account
the obligation to serve requirements for net metering facilities.
� Advanced metering infrastructure, Smart Grid methodologies and local area communications
may be required to manage coordination of increased concentrations of net metered facilities
on individual feeders.
4. Please quantify this investment in terms of type of investment
Answer: See question 3 summary.
Quanta Technology Page 17 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
4 About the Authors
H. Lee Willis, PE, Senior Vice President, is internationally recognized innovator and
practitioner of electric T&D systems planning and engineering. During his 35 years of professional
experience he has been transmission planning manager at a major investor-owned utility, an executive
with a major equipment supplier, and a senior consultant who has directly performed or supervised
more than 400 system planning and asset management projects for utilities around the world. . Lee is
an IEEE Fellow, and served on the National Research Council, which advises the US Congress on the
nation’s civilian technology needs through input to the National Labs system. He has published more
than 230 technical papers including 57 in peer-reviewed engineering journals, as well as seven books
on power systems engineering, which include Power Distribution Planning Reference Book (now it
its Second Edition) and Distributed Power Generation, both by CRC Press.
Donald J. Morrow, P.E., VP Transmission. Mr. Morrow has held a variety of engineering and
management responsibilities including: transmission planning, transmission operations, control area
operations, generation operations, energy market operations, distribution operations, and natural gas
distribution dispatch. Don and his team at Quanta technology have led a variety of projects to study
the transmission designs necessary to reliably deliver renewable energy to the interconnected grid.
Previous to joining Quanta Technology, Don was responsible for the start up and management of
system operations at American Transmission Company. He has been actively involved in many
industry organizations including NERC, MRO, RFC, MAPP, MISO, and Power Systems Engineering
Research Consortium. Mr. Morrow is a registered professional engineer in the States of Wisconsin
and Arkansas.
Quanta Technology Page 18 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
5 Bibliography
1. H. Lee Willis, Power Distribution Planning Reference Book, 2nd
edition, CRC Press, New
York, 2004.
2. Lorrin Philipson and H. Lee Willis, Understanding Electric Utilities and De-Regulation, 2nd
edition, CRC Press, New York, 2005.
3. H. Lee Willis & Walter G. Scott, Distributed Power Generation – Planning and Evaluation,
CRC Press, New York, 2001.
4. Jim Burke, Power Distribution engineering – Fundamentals and Applications, CRC Press,
New York, 1994.
5. Standardization of Small Generator Interconnection Agreements and Procedures, Order no.
2006, 18 CFR Part 35, Federal Energy Regulatory Commission, May 12, 2005.
6. Order Adopting Net Metering, Docket No. E-100, Sub 83, North Carolina Utilities
Commission, Oct. 20, 2005.
7. http://www.ncuc.commerce.state.nc.us/ncrules/Chapter08.pdf
8. IEEE Standard 1547 on Distributed Generation Interconnection Standards
9. IEEE Standard 1453 on Voltage Flicker.
10. NERC 2007 Summer Assessment.
Quanta Technology Page 19 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
Appendix: Catalog of T&D Reliability Issues related to DG
The following table is a catalogue of reliability issues related to DG. The table identifies current
industry practices and techniques for resolution. Thee issues are not necessarily related to unit or
aggregated size and, therefore, they are included as an appendix to the report.
T&D Reliability Issues
Related to DG
Discussion Typical Resolution
Safety Concern over back-feeding of customer generation
during circuit outages.
Work Practices (tagging & clear-
ance protocols), AMI & Smart
Grid coordination.
Equipment Overloads Certain equipment rated for specific current carrying
capability (e.g., elbows typically rated at 600 amps)
Upgrade equipment, add addi-
tional circuits or current pathways
Protection Coordina-
tion
Interaction of generators on radial feeders appear like
a network configuration, necessitating new standards
& revised protection design. Possible increased fault
currents due to additional sources.
System studies, reverse power
relays, protection schemes ori-
ented to network-like operation
Islanding Unintended operation of feeder when disconnected
from utility grid. Concern is safety and customer
power quality (e.g., low or high voltage, flicker, etc.).
Protection coordination, utility
grid sensing, AMI & Smart Grid
coordination
Harmonics & Tran-
sients
DG installation of sustainable energy often have
power converters that could introduce harmonics
(continuous electrical energy at multiples of 60 hz) or
transients (short duration, high power surges)
Planning studies using currently
available SW, manufacturer’s
standards, AMI & Smart Grid
monitoring & control
Voltage Flicker Periodic variation of voltage which results in lighting
variation often disturbing nearby customers.
Dynamic VAR Compensation,
manufacturer’s standards, system
studies
Resonance Heavy concentrations of uncoordinated generation on
a feeder may have control systems that interact in a
way that they fight each other in a continuous manner
AMI & Smart Grid, coordinated
protection schemes
Substation and
Feeder Design Stan-
dards
Heavier concentrations of generation will change the
commonly accepted design principles used by utilities
– e.g., bi-directionality, fault current levels, loading
profiles.
Revision to standards
Voltage Profile Radial distribution designs presume decreasing volt-
age as one moves away from the utility substation.
DG reduces this profile and, if heavy supply to the
grid is occurring, may reverse this profile.
Protection coordination, AMI &
Smart Grid coordination, revised
design standards, revised field
power factor-compensation
schemes.
Meter Directionality Instrumentation metering (voltage, current, power) has
been sometimes been assumed to be unidirectional.
DG creates the potential for bi-directionality.
New Meters
Quanta Technology Page 20 of 20 1/19/2008
Technical Issues w/ Net-Metering
Q U A N T A
SERVICES
Adequacy: Resource
Planning
If there is a high degree of DG penetration, concern
exists about resource adequacy if wholesale resources
are acquired with presumption of DG utilization – this
is a particular concern if DG is concentrated as wind
or solar which has high variability.
Defined Rules at Regional Level,
Increased Planning Reserve Mar-
gins; change planning guidelines
Adequacy: Obliga-
tion to Serve
If a utility is obligated to serve if DG is down, un-
anticipated loading may occur on distribution level
equipment
Distribution planning criteria