41
BMT Western Australia Pty Ltd PO Box 2305, Churchlands WA 6018 Western Australia Tel: +61 (08) 6163 4900 Fax: +61 (08) 6163 4979 www.bmt.org ABN 093 752 811 Rev Issue Prepared by Submitted to Date Copies A Internal Review S Mettam H Sunarko 05/03/2019 1 elec. B Internal Review S Mettam T Green 06/03/2019 1 elec. C Internal Review S Mettam A Gartner / I Teakle 08/03/2019 1 elec 0 Draft for Client Review S Mettam B Atkinson / A McCreath 12/03/2019 1 elec Tn-WAT_1334_10_003-02 Rev 0 12/03/2019 Page 1 Technical Note Project Number: 1334_10_003 Project Name: Perth Seawater Desalination Plant 2: Dredging Engineering Advice Date: 12/03/2019 Doc Ref: Tn-WAT_1334_10_003-02 Client: Water Corporation Subject: Perth Seawater Desalination Plant 2: Dredging Plume Modelling Input 1 Introduction The proposed Perth Seawater Desalination Plant 2 (PSDP2) will be located in Kwinana, approximately 30 kilometres south of Perth. Dredging works are required at the new PSDP2 area to create two trenches to accommodate a seawater intake pipe and a brine outfall pipe (~250 m and ~580 m, respective). BMT has been engaged by the Water Corporation to assess for dredging works in the PSDP2 area and provide plume modelling input to inform the Environmental Impact Assessment process. The purpose of this assessment to assess the required dredging and provide indicative production rates to enable dredge plume modelling analysis. 2 Dredged Material 2.1 Dredging Volume The in situ dredging volume for PSDP2 pipe trenches were determined by BMT on the basis of bathymetric survey data collected in April/May 2009 and January 2010. The pipe trench design was provided by Water Corporation to cater for the intake and outfall piping requirements (refer to Attachment 2). The calculated volumes are presented in Table 2-1, and the associated PSDP2 difference plot drawing is provided in Attachment 1. Table 2-1: PSDP2 Dredging Volumes # Values may vary due to current bathymetry/seabed condition, particularly in the nearshore area Description Units Value # Surface Area m 2 62,906 Volume to Design m 3 130,459 Volume to Design + 0.5m Over-dredge Allowance m 3 154,362 Volume to Design + 1.0m Over-dredge Allowance m 3 180,341

Technical Note - epa.wa.gov.au G... · A Internal Review S Mettam H Sunarko 05/03/2019 1 elec. B Internal Review S Mettam T Green 06/03/2019 1 elec. C Internal Review S Mettam A Gartner

  • Upload
    lamphuc

  • View
    214

  • Download
    0

Embed Size (px)

Citation preview

BMT Western Australia Pty Ltd PO Box 2305, Churchlands WA 6018 Western Australia Tel: +61 (08) 6163 4900 Fax: +61 (08) 6163 4979 www.bmt.org ABN 093 752 811

Rev Issue Prepared by Submitted to Date Copies

A Internal Review S Mettam H Sunarko 05/03/2019 1 elec.

B Internal Review S Mettam T Green 06/03/2019 1 elec.

C Internal Review S Mettam A Gartner / I Teakle 08/03/2019 1 elec

0 Draft for Client Review S Mettam B Atkinson / A McCreath 12/03/2019 1 elec

Tn-WAT_1334_10_003-02 Rev 0 12/03/2019 Page 1

Technical Note

Project Number: 1334_10_003 Project Name: Perth Seawater Desalination Plant 2: Dredging Engineering Advice

Date: 12/03/2019 Doc Ref: Tn-WAT_1334_10_003-02

Client: Water Corporation

Subject: Perth Seawater Desalination Plant 2: Dredging Plume Modelling Input

1 Introduction

The proposed Perth Seawater Desalination Plant 2 (PSDP2) will be located in Kwinana,

approximately 30 kilometres south of Perth. Dredging works are required at the new PSDP2

area to create two trenches to accommodate a seawater intake pipe and a brine outfall pipe

(~250 m and ~580 m, respective). BMT has been engaged by the Water Corporation to assess

for dredging works in the PSDP2 area and provide plume modelling input to inform the

Environmental Impact Assessment process.

The purpose of this assessment to assess the required dredging and provide indicative

production rates to enable dredge plume modelling analysis.

2 Dredged Material

2.1 Dredging Volume

The in situ dredging volume for PSDP2 pipe trenches were determined by BMT on the basis

of bathymetric survey data collected in April/May 2009 and January 2010. The pipe trench

design was provided by Water Corporation to cater for the intake and outfall piping

requirements (refer to Attachment 2). The calculated volumes are presented in Table 2-1, and

the associated PSDP2 difference plot drawing is provided in Attachment 1.

Table 2-1: PSDP2 Dredging Volumes

# Values may vary due to current bathymetry/seabed condition, particularly in the nearshore area

Description Units Value#

Surface Area m2 62,906

Volume to Design m3 130,459

Volume to Design + 0.5m Over-dredge Allowance m3 154,362

Volume to Design + 1.0m Over-dredge Allowance m3 180,341

Page 2

2.2 Rock Protection Volume

The calculated placed bank volumes for the pipeline protection are presented in Table 2-2.

Table 2-2: PSDP2 Rock Protection Volumes

Description Units Value#

Pea Gravel m3 30,174

Filter Rock m3 9,151

Armour Rock m3 20,197

Sand Backfill m3 79,260

# Tonnages for each material will vary depending on required detailed design specifications

2.3 Dredged Material Characteristics

The in-situ material property assessments have been based on the information provided in the

following reports:

• Oceanica (2009), Fremantle Ports, Sediment Sampling and Analysis Implementation

Report: Diver and Geotechnical Survey (Reference no. 560_005/4)

• Golder Associates (2009), Fremantle Ports, Outer Harbour Geotechnical Investigation

Factual Report (Reference no. 087642339 002 R Rev1)

2.3.1 Sediment Sampling and Analysis Implementation Report

Sediment sampling and analysis was undertaken by Oceanica in 2008/09 for Fremantle Ports

proposed Kwinana Quay Development and Kwinana Bulk Berth No.1 projects for Fremantle

Ports. The purpose of this investigation was to assess the suitability of sediment for use in land

reclamation and offshore disposal.

Two different sampling techniques were used to obtain material from the seabed surface down

to below dredge design depths. A diver survey was undertaken in August 2008 to assess the

top 1m of sediment using a PVC core. A geotechnical survey undertaken in late 2008 and early

2009 was carried out using a ‘PQ3 triple tube’ drill string set up.

Based on Oceanica’s field observations, the dredged material characteristic was described as

follows (underlining by BMT; Attachment 3):

• The sediment in all areas was generally free of metal contaminants. Results also indicate

that there is no risk of acid sulphates soil development if the material is exposed to

oxygen during land reclamation

• Particles in the top 0-50 cm and bottom 50-100 cm across the area were mainly silt and

clay, followed by fine sand with some shell, occasional rocks and seagrass rhizome

remnants. The cores were not layered, and most samples had a sulphurous odour.

Page 3

Particle size distribution (PSD) data are presented in Table 2-3.

Table 2-3: PSD data

Fines (%) Coarse (%)

<38µm >38µm >63µm >125µm >250µm >500µm >1000µm >2000µm

BH1_top 53.1 7.0 16.8 8.3 4.9 2.9 2.3 4.7

BH1_bot 63.0 6.8 7.4 4.0 3.6 3.5 6.2 5.5

BH2_top 56.8 10.3 13.6 4.4 3.4 2.1 1.7 7.6

BH15_top 51.7 13.1 21.1 6.5 1.7 0.5 0.3 5.1

BH16_top 39.0 9.2 18.2 8 6.7 3.9 2.5 12.6

BH16_bot 32.7 7.0 22.2 7.2 5.3 4.9 4.0 16.6

BH17_top 25.2 3.7 8.2 4.3 4.2 4.1 4.0 46.3

Average 45.93 8.16 15.36 6.10 4.26 3.13 3.00 14.06

2.3.2 Outer Harbour Geotechnical Investigation Factual Report

The Golder Associates geotechnical site investigation was undertaken in 2009 for the

proposed Outer Harbour development at the Port of Fremantle. The purpose of this

investigation was to determine the subsurface conditions in the channel and berthing areas

known to be shallower than the design depths.

J&S Drilling were commissioned directly to carry out the drilling programme using an Edson

3000 drilling rig and jack up barge.

The site geotechnical condition can be described as follows (underlining by BMT):

The marine sediment observed over the site were generally up to 2.5m thick and composed

of sandy clay with low plasticity, fine grained sand and abundant shell fragments. Below the

marine sediments, a siliceous calcarenite, calcarenite and calcisiltite (limestone) layer was

encountered. These sediments were very weakly to well cemented, fine to medium grain

with abundant large shell fragments and pale grey to pale yellow in colour.

Unconfined compressive strength (UCS) ranges up to 2.33MPa

Page 4

PSD data are presented in Table 2-4

Table 2-4: PSD data

Fines (%)

Coarse (%)

Depth

(m) <75 µm

<150 µm

<300 µm

<425 µm

<600 µm

<1180 µm

<2360 µm

<4750 µm

<9500 µm

<19000 µm

<37500 µm

K3 -12.25 82 7 3 1 1 3 1 1 1 0 0

OH17 -13.2 46 27 8 2 3 4 3 2 1 4 0

OH18 -12.3 45 29 17 3 2 2 1 1 0 0 0

OH18 -13.5 25 12 8 3 5 10 8 7 10 7 5

Average 49.50 18.75 9.00 2.25 2.75 4.75 3.25 2.75 3.00 2.75 1.25

3 Dredging Method

Dredge plume modelling was initially used to assess the relative impact to water quality

(turbidity) of a backhoe dredge (BHD) versus cutter suction dredge, where it was determined

that the BHD approach would induce far less impact, Accordingly, a BHD will form the basis

for the plume modelling inputs:

• Backhoe Dredging - using a backhoe to excavate/remove marine sediment to the

required designed dredging depth. Excavated material is placed onto a barge which

travels to an approved nearby harbour location or temporary facility for offloading.

3.1.1 Assumptions and Exclusions

The dredging methodologies provided in this technical note are based on the following

assumptions:

• As directed by the Client, dredged material will not be placed in an offshore placement

area (i.e. no sea dumping)

• Dredged material characteristics have been assumed based on historical geotechnical

and sediment data (Fremantle Outer Harbour – Golder, 2009 & Oceanica, 2009)

• Dredged material from BHD will be transferred to land via a land back wharf facility,

such as those available in Henderson. The dredged material will be placed in an

onshore placement area. The location and management of dredged material are

excluded from the scope of this services. The BHD will be supported by adequate

number of barges to enable continuous dredging operation, i.e. BHD won’t be required

to sit on standby while the Hopper Barges travels and being unloaded in a wharf facility

• This report only considers the use of BHD. Other options or combination of options

have not been assessed, which may include the use of different sizes BHD and hopper

barges, use of a grab dredger and offshore dredged material placement. The use of

Cutter Suction Dredge (CSD) was assess in Technical Note No. Tn-

WAT_1334_10_003-01.

• Soil improvement works following the completion of reclamation works have not been

included in this study

Page 5

• Assessment for suitable reuse of the dredged material is not included in this study

• A project specific geotechnical site investigation campaign should be undertaken in the

future as part of detailed design phase. BMT wish to highlight that a calcisiltite limestone

layer with UCS of 30.6MPa was recorded in KP5 at depth of ~17m CD (Golder, 2009).

Geotechnical site investigation should be carried out to confirm that this hard limestone

layer is not within the design envelope as it will significantly impact the selection of

appropriate dredge plant.

3.2 Backhoe Dredging

3.2.1 General Methodology

A BHD is a combination of equipment consisting of a backhoe/excavator mounted on a barge

and equipped with a spud system to control the stability of the equipment. A picture of a BHD

vessel is shown in Figure 3-1 below.

Figure 3-1: Backhoe Dredger Vessel

A general working methodology of a BHD is outlined below:

• BHD will be positioned using its spud and can maneuver to the required dredging

location using its excavator arm or with support tugs (for longer distances)

• Excavated material will be placed onto hopper barges moored alongside the BHD

• The loaded barges can then be towed to a nearby land back wharf facility for

off-loading. Self-propelled barges may also be used

• BHD is also anticipated to be used for the placement of pipeline rock protection system.

3.2.2 Indicative BHD Dredging Production Parameters

The following dredging parameters have been adopted to estimate the proposed staged

dredging duration:

• 24-hour operations are assumed

• 4.8 – 7.2 hours per day for standby time (for delay due to sea state, maintenance and

repair)

• 3 m3 BHD bucket size

• Estimated dredging production rate of 60 - 82 m3/operational hour.

Page 6

The above are the key parameters for determining the scope, and timeframe required to

complete the proposed dredging works. BHD sequencing should commence in Area A and

progress towards Area C, followed by Area D.

Table 3-1: Backhoe Dredging Duration

Estimated Dredging Duration

Work Area Design Volume +1.0m

Overdredge (m3) High (days) Low (days)

Area A 41,519 22.4 29.1

Area B 45,928 24.7 32.1

Area C 22,018 11.9 15.4

Area D 70,875 38.2 49.6

Total: 180,341 ~97 ~126

3.2.3 Indicative BHD Rock Placement Production Parameters

In both dredging scenarios a BHD will be required once the pipe trench dredging is completed

to install the intake and outfall pipelines. The BHD will facilitate the placement of pea gravel,

filter rock, armour rock and sand backfill in that order to restore the natural seabed surface.

The following dredging parameters have been adopted to estimate the proposed rock

placement and backfill duration:

• 24-hour operations are assumed

• 4.8 – 7.2 hours per day for standby time (for delay due to sea state, maintenance and

repair)

• 3 m3 BHD bucket size

• Estimated rock placement production rate of 44 - 55 m3/operational hour

• Estimated backfill production rate of 59 - 73 m3/operational hour.

The above are the key parameters for determining the scope, and timeframe required to

complete the proposed rock placement and backfill works.

Table 3-2: Backhoe Dredging Duration

Estimated Dredging Duration

Work Area Design Volume (m3) High (days) Low (days)

Pea Gravel 30,174 23.5 30.2

Filter Rock 9,151 7.1 9.2

Armour Rock 20,197 15.7 20.2

Sand Backfill 79,260 46.2 61.6

Total: 138,781 ~93 ~121

Page 7

4 References

Golder Associates (2009), Fremantle Ports, Outer Harbour Geotechnical Investigation Factual

Report (Reference no. 087642339 002 R Rev1)

Oceanica (2009), Fremantle Ports, Sediment sampling and analysis implementation report:

Diver and geotechnical survey (Reference no. 560_005/4)

Page 8

ATTACHMENT 1:

DREDGING WORK AREAS

Drg No. Revision Title

WAT-1334-10-01-01 A

Perth Seawater Desalination Plant 2

Intake and Outfall Dredging Options

Colour Coded Differences

Natural Surface to Trench Design

0

SCALE 1 : 1000

METRES

10 0 100

0.0

-1.0

-2.0-3.0-4.0

-5.0-1

0.0

0.0

-1.0

-2.0-3.0

-4.0

-5.0-1

0.0

-11.0 AREA D

AREA C

AREA B

AREA A

LEGEND

K 3

K 4

K 5

B16

B2

B1

K 6

643580

0 mN

643600

0 mN

643620

0 mN

383400 m

E

383400 m

E

383600 m

E

383800 m

E

384000 m

E

384000 m

E

643580

0 mN

643600

0 mN

643620

0 mN

383400 m

E

383400 m

E

383600 m

E

383800 m

E

2.

DoW LIDAR SURVEY 2008

NATURAL SURFACE CONTOURS FROM COMBINED DoT SURVEYS 2003 TO 2012 INCLUDINGS.MOUCHEMORE

INTAKE AND OUTFALL DREDGING OPTIONS

WATER CORPORATION

PERTH SEAWATER DESALINATION PLANT 2

COLOUR CODED DIFFERENCES

NATURAL SURFACE TO TRENCH DESIGN

WAT 1334 10 - 01 - 01

S.METTAM 06/03/2019

06/03/2019

06/03/2019

06/03/2019

DRAWING NUMBER

CHECK

DRAFTING

REV

DRAWN

ENGINEER

PROJECT MGR

APPROVED

CHECK

ENGINEERING

C.LIVINGSTONE

H.SUNARKO

DATUM

NOTES

REV DATE AMENDMENT

06/03/19

APP

INITIAL ISSUE

DRN

SM

ORIG SIZE

A1WAT_1334_10-01-01A.dgnARCHIVE

MAP GRID OF AUSTRALIA BASED ON GDA 94, ZONE 50

VERTICAL

HORIZONTAL BebbCart

CLIENT

PROJECT

TITLE

A

A

1.AERIAL PHOTOGRAPHY JANUARY 2018

AHD

3.

IMPLEMENTATION REPORT: DIVER AND GEOTECHNICAL SURVEY (REFERENCE NO. 560_005/4)

OCEANICA (2009), FREMANTLE PORTS, SEDIMENT SAMPLING AND ANALYSIS

4.

GEOTECHNICAL INVESTIGATION FACTUAL REPORT (REFERENCE NO. 087642339 002 R REV1)

BOREHOLE DATA FROM GOLDER ASSOCIATES (2009), FREMANTLE PORTS, OUTER HARBOUR

K 4

B16 (REFER NOTE 3)

SEDIMENT SAMPLING SITES

(REFER NOTE 4)

BOREHOLES

GENERAL

FROM THE ORIGINAL SURVEYS

CALCULATED USING DATA INTERPOLATED

THE VALUES ON THE PLAN HAVE BEEN

GRIDDING PARAMETERS 2.0m GRID

TH

AN D

ESIG

N

DE

EP

ER

TH

AN D

ESIG

N

SH

ALL

OW

ER

-5.0

-4.0

-3.0

-2.0

-1.0

-0.7

-0.2

0.0

0.2

0.7

1.0

2.0

3.0

4.0

5.0

5.

MR93-096-004-01A4

FOR TRENCH DESIGN AND LOCATION REFER GHD PLANS MR93-096-003-02A2 AND

Page 9

ATTACHMENT 2:

REFERENCE DRAWINGS

Drg No. Revision Title

MR93-096-003-02 A2

Perth Seawater Desalination Plant

Expansion Investigation

Perth Seawater Desalination Plant 2

Intake and Outfall – Plan and Longitudinal Sections

MR93-096-004-01 A4

Perth Seawater Desalination Plant

Expansion Investigation

Perth Seawater Desalination Plant 2

Intake and Outfall –Sections

Level 10, 999 Hay Street Perth WA 6000 Australia

T 61 8 6222 8222 F 61 8 6222 8555

E [email protected] W www.ghd.com.au

PR

EL

IM

IN

AR

Y - N

OT

F

OR

C

ON

ST

RU

CT

IO

N

AutoCAD SHX Text
(c) 2018 Transoft Solutions, Inc. All rights reserved.
AutoCAD SHX Text
OUTLET PIPE
AutoCAD SHX Text
INTAKE PIPE
AutoCAD SHX Text
DN1200 GRP
AutoCAD SHX Text
25 DIFFUSERS AT 5m CENTRES
AutoCAD SHX Text
25 DIFFUSERS AT 5m CENTRES
AutoCAD SHX Text
25 DIFFUSERS AT 5m CENTRES
AutoCAD SHX Text
-10.0
AutoCAD SHX Text
-9.0
AutoCAD SHX Text
-8.0
AutoCAD SHX Text
-7.0
AutoCAD SHX Text
-6.0
AutoCAD SHX Text
-5.0
AutoCAD SHX Text
-4.0
AutoCAD SHX Text
-3.0
AutoCAD SHX Text
-2.0
AutoCAD SHX Text
-1.0
AutoCAD SHX Text
0.0
AutoCAD SHX Text
1.0
AutoCAD SHX Text
2.0
AutoCAD SHX Text
-11.0
AutoCAD SHX Text
3.0
AutoCAD SHX Text
-10.0
AutoCAD SHX Text
50m EXCLUSIVE ZONE AROUND HIGH ENERGY DIFFUSERS MARKED WITH BUOYS TO BE CONSIDERED & CONFIRMED DURING ENGINEERING DESIGN
AutoCAD SHX Text
25 DIFFUSERS AT 5m CENTRES
AutoCAD SHX Text
25 DIFFUSERS AT 5m CENTRES
AutoCAD SHX Text
25 DIFFUSERS AT 5m CENTRES
AutoCAD SHX Text
PORT No.1 E. 383346.50m N. 6436288.00m
AutoCAD SHX Text
PORT No.50 E. 383566.00m N. 6436179.20m
AutoCAD SHX Text
NATURAL SURFACE
AutoCAD SHX Text
LEVEL
AutoCAD SHX Text
DEPTH TO INVERT
AutoCAD SHX Text
INVERT LEVEL
AutoCAD SHX Text
RUNNING DISTANCE
AutoCAD SHX Text
R.L. -17.00
AutoCAD SHX Text
0.0
AutoCAD SHX Text
4.50
AutoCAD SHX Text
17.3
AutoCAD SHX Text
4.00
AutoCAD SHX Text
32.8
AutoCAD SHX Text
3.00
AutoCAD SHX Text
36.8
AutoCAD SHX Text
2.00
AutoCAD SHX Text
40.9
AutoCAD SHX Text
1.00
AutoCAD SHX Text
50.0
AutoCAD SHX Text
0.00
AutoCAD SHX Text
67.3
AutoCAD SHX Text
-1.00
AutoCAD SHX Text
81.8
AutoCAD SHX Text
-2.00
AutoCAD SHX Text
120.4
AutoCAD SHX Text
-3.00
AutoCAD SHX Text
148.5
AutoCAD SHX Text
-4.00
AutoCAD SHX Text
164.3
AutoCAD SHX Text
-5.00
AutoCAD SHX Text
180.1
AutoCAD SHX Text
-6.00
AutoCAD SHX Text
195.9
AutoCAD SHX Text
-7.00
AutoCAD SHX Text
211.7
AutoCAD SHX Text
-8.00
AutoCAD SHX Text
227.4
AutoCAD SHX Text
-9.00
AutoCAD SHX Text
243.2
AutoCAD SHX Text
-10.00
AutoCAD SHX Text
297.5
AutoCAD SHX Text
-10.00
AutoCAD SHX Text
367.5
AutoCAD SHX Text
-15.8
AutoCAD SHX Text
MOL
AutoCAD SHX Text
9.3m
AutoCAD SHX Text
DISCHARGE CHAMBER
AutoCAD SHX Text
MSL
AutoCAD SHX Text
0.0m
AutoCAD SHX Text
HHAT + STORM SURGE + SEA LEVEL RISE
AutoCAD SHX Text
2.12m
AutoCAD SHX Text
DN1600 PN6 GRP OUTLET PIPE
AutoCAD SHX Text
NATURAL SURFACE
AutoCAD SHX Text
LEVEL
AutoCAD SHX Text
DEPTH TO INVERT
AutoCAD SHX Text
INVERT LEVEL
AutoCAD SHX Text
RUNNING DISTANCE
AutoCAD SHX Text
R.L. -17.00
AutoCAD SHX Text
0.0
AutoCAD SHX Text
317.2
AutoCAD SHX Text
4.50
AutoCAD SHX Text
16.8
AutoCAD SHX Text
4.00
AutoCAD SHX Text
37.0
AutoCAD SHX Text
3.00
AutoCAD SHX Text
37.5
AutoCAD SHX Text
2.00
AutoCAD SHX Text
42.7
AutoCAD SHX Text
1.00
AutoCAD SHX Text
53.8
AutoCAD SHX Text
0.00
AutoCAD SHX Text
68.0
AutoCAD SHX Text
-1.00
AutoCAD SHX Text
81.4
AutoCAD SHX Text
-2.00
AutoCAD SHX Text
124.6
AutoCAD SHX Text
-3.00
AutoCAD SHX Text
143.8
AutoCAD SHX Text
-4.00
AutoCAD SHX Text
159.3
AutoCAD SHX Text
-5.00
AutoCAD SHX Text
173.7
AutoCAD SHX Text
-6.00
AutoCAD SHX Text
187.1
AutoCAD SHX Text
-7.00
AutoCAD SHX Text
200.6
AutoCAD SHX Text
-8.00
AutoCAD SHX Text
214.0
AutoCAD SHX Text
-9.00
AutoCAD SHX Text
227.4
AutoCAD SHX Text
-10.00
AutoCAD SHX Text
302.5
AutoCAD SHX Text
MOL
AutoCAD SHX Text
-0.9m
AutoCAD SHX Text
BWL
AutoCAD SHX Text
-1.8m
AutoCAD SHX Text
SEA WATER INTAKE WET WELL
AutoCAD SHX Text
BOTTOM OF
AutoCAD SHX Text
-5.0m
AutoCAD SHX Text
WET WELL
AutoCAD SHX Text
-5.0m
AutoCAD SHX Text
I.L.
AutoCAD SHX Text
MSL
AutoCAD SHX Text
0.0m
AutoCAD SHX Text
DN2600 PN6 GRP INTAKE PIPE
AutoCAD SHX Text
4.5m
AutoCAD SHX Text
LLAT
AutoCAD SHX Text
-0.92m
AutoCAD SHX Text
-19.0
AutoCAD SHX Text
END CAP & TEE CONNECTION TO DIFFUSER ARRAY
AutoCAD SHX Text
679.2
AutoCAD SHX Text
ASCON SURVEY
AutoCAD SHX Text
DESIGN SURVEY
AutoCAD SHX Text
RECOMMENDED
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
COORDINATE SYS
AutoCAD SHX Text
810
AutoCAD SHX Text
ISSUE
AutoCAD SHX Text
566
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
GRID
AutoCAD SHX Text
DATE
AutoCAD SHX Text
DES CHD
AutoCAD SHX Text
Q.C. CHD
AutoCAD SHX Text
DES CALC
AutoCAD SHX Text
DRN
AutoCAD SHX Text
APPD
AutoCAD SHX Text
REC
AutoCAD SHX Text
DES REF
AutoCAD SHX Text
VERTICAL DATUM
AutoCAD SHX Text
DRN
AutoCAD SHX Text
THIS DRAWING IS THE PROPERTY OF THE WATER CORPORATION.
AutoCAD SHX Text
C
AutoCAD SHX Text
NORTH POINT
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
3
AutoCAD SHX Text
4
AutoCAD SHX Text
5
AutoCAD SHX Text
6
AutoCAD SHX Text
IT SHALL NOT BE COPIED WITHOUT PERMISSION.
AutoCAD SHX Text
PROJECT
AutoCAD SHX Text
FILE
AutoCAD SHX Text
A1
AutoCAD SHX Text
SIZE
AutoCAD SHX Text
SHEET
AutoCAD SHX Text
ORIGINAL
AutoCAD SHX Text
MF
AutoCAD SHX Text
PLAN
AutoCAD SHX Text
CAD
AutoCAD SHX Text
ISSUE
AutoCAD SHX Text
H
AutoCAD SHX Text
G
AutoCAD SHX Text
F
AutoCAD SHX Text
E
AutoCAD SHX Text
7
AutoCAD SHX Text
8
AutoCAD SHX Text
9
AutoCAD SHX Text
10
AutoCAD SHX Text
D
AutoCAD SHX Text
C
AutoCAD SHX Text
B
AutoCAD SHX Text
11
AutoCAD SHX Text
12
AutoCAD SHX Text
A
AutoCAD SHX Text
MR93-96-3-2
AutoCAD SHX Text
A2
AutoCAD SHX Text
PERTH SEAWATER DESALINATION PLANT
AutoCAD SHX Text
EXPANSION INVESTIGATION
AutoCAD SHX Text
PERTH SEAWATER DESALINATION PLANT 2
AutoCAD SHX Text
INTAKE AND OUTFALL - PLAN AND LONGITUDINAL SECTIONS
AutoCAD SHX Text
CONSULTANT PROJECT MANAGER
AutoCAD SHX Text
CONSULTANT PROJECT DIRECTOR
AutoCAD SHX Text
M.PARK
AutoCAD SHX Text
B.SHACKLETON
AutoCAD SHX Text
S.TULLY
AutoCAD SHX Text
T.KENT
AutoCAD SHX Text
AHD
AutoCAD SHX Text
MGA94-50
AutoCAD SHX Text
GHD
AutoCAD SHX Text
61-36503
AutoCAD SHX Text
61-36503-V01
AutoCAD SHX Text
NONE
AutoCAD SHX Text
A2
AutoCAD SHX Text
01/2019
AutoCAD SHX Text
DIFFUSER LOCATION REVISED
AutoCAD SHX Text
SMT
AutoCAD SHX Text
61\36503\CADD\DRAWINGS\MR93\MR93-096-003-02A2 23/01/2019
AutoCAD SHX Text
70 m
AutoCAD SHX Text
60
AutoCAD SHX Text
50
AutoCAD SHX Text
40
AutoCAD SHX Text
30
AutoCAD SHX Text
20
AutoCAD SHX Text
10
AutoCAD SHX Text
0
AutoCAD SHX Text
10
AutoCAD SHX Text
5
AutoCAD SHX Text
(1:1000)
AutoCAD SHX Text
DATE : 30-Jan-201930-Jan-2019
AutoCAD SHX Text
PLAN SCALE 1:2000
AutoCAD SHX Text
INTAKE LONGITUDINAL SECTION
AutoCAD SHX Text
OUTLET LONGITUDINAL SECTION
AutoCAD SHX Text
HORIZONTAL 1:1000 VERTICAL 1:200
AutoCAD SHX Text
HORIZONTAL 1:1000 VERTICAL 1:200
AutoCAD SHX Text
10 m
AutoCAD SHX Text
5
AutoCAD SHX Text
0
AutoCAD SHX Text
1
AutoCAD SHX Text
2
AutoCAD SHX Text
3
AutoCAD SHX Text
4
AutoCAD SHX Text
5
AutoCAD SHX Text
(1:200)
AutoCAD SHX Text
NOTES: 1.PIPE ACCESS POINTS TO BE CONSIDERED DURING PIPE ACCESS POINTS TO BE CONSIDERED DURING ENGINEERING DESIGN.
AutoCAD SHX Text
100 m
AutoCAD SHX Text
50
AutoCAD SHX Text
50
AutoCAD SHX Text
40
AutoCAD SHX Text
30
AutoCAD SHX Text
20
AutoCAD SHX Text
10
AutoCAD SHX Text
0
AutoCAD SHX Text
(1:2000)

Page 10

ATTACHMENT 3:

SEDIMENT QUALITY ASSESSMENT

D0c No. Revision Title

WAT-1334-10-03-01 0 Perth Seawater Desalination Plan 2: Sediment Quality

Report

Perth Seawater Desalination Plan 2: Sediment

Quality Report

1334_10_003_Rev0 October 2018

P:\WaterCorp\1334_10PSDP EIA\003_PSDP2DredgingAdvice\Reports\Sediment Report\PD_Sediment_Report_Rev0_20181024.docm

Perth Seawater Desalination Plan 2: Sediment Quality Report

Prepared for

The Water Corporation (Western Australia)

Prepared by

BMT

October 2018

Report No. 1334_10_003_Rev0

Client: The Water Corporation (Western Australia)

Document history

Distribution

Revision Author Recipients Organisation No. copies

& format Date

A G Cummins B Davis BMT 1 x docm 22/10/18

B G Cummins A Gartner BMT 1 x docm 23/10/18

0 G Cummins B Atkinson Water Corporation 1 x pdf 24/10/18

Review

Revision Reviewer Intent Date

A B Davis Technical 22/10/18

B A Gartner Technical and editorial 24/10/18

Status

This report is 'Draft' until approved for final release, as indicated below by inclusion of signatures from: (i) the author and

(ii) a Director of BMT Western Australia Pty Ltd (BMT) or their authorised delegate. A Draft report may be issued for

review with intent to generate a 'Final' version, but must not be used for any other purpose.

Approved for final release:

Author Director (or delegate) Date: 23/10/18 Date: 23/10/18

Disclaimer

This report has been prepared on behalf of and for the exclusive use of The Water Corporation (Western Australia), and

is subject to and issued in accordance with the agreed terms and scope between The Water Corporation (Western

Australia) and BMT Western Australia Pty Ltd (BMT). BMT accepts no liability or responsibility for it in respect of any

use of or reliance upon this report by any third party.

Copying this report without prior written consent of The Water Corporation (Western Australia) or BMT is not permitted.

© Copyright 2018 BMT

BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report i

Contents

Acronyms ................................................................................................................................... iii

1. Introduction ....................................................................................................................... 1

2. Sediment Sampling and Analysis .................................................................................... 2

Sediment sampling methods ................................................................................ 2

2.1.1 Quality assurance and quality control ........................................................... 3

Sediment analysis methods .................................................................................. 3

2.2.1 Sediment analytes ........................................................................................ 3

Data analysis methods .......................................................................................... 3

2.3.1 Normalisation of organics ............................................................................. 4

2.3.2 Computation of test statistics and assessment against guidelines ................ 4

3. Sediment Analysis Results ............................................................................................... 6

Physical sediment characteristics ........................................................................ 6

3.1.1 Particle size distribution ................................................................................ 6

3.1.2 Visual and odour characterisation ................................................................. 6

Metals ..................................................................................................................... 9

Hydrocarbons ...................................................................................................... 13

Organotins............................................................................................................ 14

3.5 Acid Sulfate Soils ................................................................................................. 14

Quality assurance/quality control ....................................................................... 15

4. Conclusions ..................................................................................................................... 16

5. References ....................................................................................................................... 17

ii BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report

List of Figures

Figure 1.1 Perth Seawater Desalination Plant 2 dredge footprint and sediment sites

selected for analysis ............................................... Error! Bookmark not defined.

Figure 3.1 Particle size distribution of sediment samples collected in August 2008 ................ 6

List of Tables

Table 1.1 Sediment sites coordinates .................................... Error! Bookmark not defined.

Table 3.1 Wentworth scale ................................................................................................... 6

Table 3.2 Sediment characteristics and penetration depth of diver cores sampled in

August 2008 .......................................................................................................... 7

Table 3.3 Total metal concentrations in sediments sampled in August 2008 ........................11

Table 3.4 Polycyclic aromatic hydrocarbons concentrations normalised in sediment

samples collected at Kwinana Quay in 2008 ........................................................13

Table 3.5 Total organotin concentrations in sediment samples collected at Kwinana

Quay in 2008 ........................................................................................................14

Table 3.6 Acid sulfate soil analysis and acid base accounting for sediment samples

collected at Kwinana Quay in 2008 ......................................................................15

BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report iii

Acronyms

ASS Acid sulfate soils

CSIRO Commonwealth Scientific and Industrial Research Organisation

EILs Ecological Investigation Levels

HILs Health Investigation Levels

LoR Limit of reporting

NAGD National Assessment Guidelines for Dredging

PAHs Polycyclic aromatic hydrocarbons

PSD Particle size distribution

SAP Sediment sampling and analysis plan

TOC Total organic carbon

TPH Total petroleum hydrocarbons

QA/QC Quality assurance and quality control

UCL Upper confidence limit

BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report 1

1. Introduction

Water Corporation of Western Australia is proposing a second seawater desalination plant (Perth

Seawater Desalination Plan 2, PSDP2) adjacent to the existing PSDP1 in Kwinana, south of

Fremantle Western Australia. Construction of the PSDP2 outfall and intake pipelines requires

dredging and infilling of a trench, ~ 550 m long and 70 m wide (Error! Reference source not

found.).

Extensive sediment sampling and analyses have previously been undertaken in Cockburn Sound

to assess the suitability of sediment for use in land reclamation and offshore disposal. One

example is the Fremantle Port Kwinana Quay Development and Kwinana Bulk Berth No. 1 projects

(Oceanica 2009). Results available from a subset of selected sites from Oceanica (2009) that are

close in alignment with the PSDP2 dredge footprint (Figure 1.1) have been summarised in this

report to determine potential risk of contamination in sediments in the planned PSDP2 dredge area.

To ensure this assessment is contemporary, results were compared against current guidelines.

Figure 1.1 Perth Seawater Desalination Plant 2, Kwinana

2 BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report

2. Sediment Sampling and Analysis

Site selection

A subset of ten sites (out of 94), located closest to the planned dredge area alignment

(Figure 2.1,Table 2.1), were selected from the broader sediment quality sampling program

undertaken by Oceanica (2009).

Note:

1. Sites were sampled by Oceania (2009)

Figure 2.1 Perth Seawater Desalination Plant 2 planned dredge footprint and sediment

sites selected for analysis

Table 2.1 Sediment sites coordinates

Site Easting Northing

A3 383713 6435812

A5 383612 6435868

A7 383550 6435897

B1 383644 6435987

B15 383075 6436250

B16 383331 6436250

B17 383158 6436227

B18 382906 6436436

B19 383152 6436513

B20 383372 6436582

Note:

1. Sites were by Oceanica (2009)

BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report 3

Sediment sampling methods

Sediment sampling was completed between 11—20 August 2008 (Oceanica 2009) inline with

methods described in the Fremantle Port Kwinana Quay Development sediment Sampling and

Analysis Plan (SAP; Oceanica 2008). At each site, a diver hammered a PVC core into the sediment

until the target depth of 100 cm or until core refusal. Once target depth was reached the core was

sealed and retrieved to the vessel. The core was de-watered and extracted into a core tray, so

that the sediment profile was retained. Once extracted, the core was photographed, length

recorded, and sediment characteristics noted. The cores were sub-sampled at 50 cm increments

for laboratory analysis (Oceanica 2008).

All sampling equipment was cleaned with Decon 90 and rinsed in clean seawater between each

sampling event. Samples were placed in glass jars and zip-lock bags as described in the SAP

(Oceanica 2008) and stored on ice. At the end of each field day the samples were transported in

eskies to a freezer for storage prior to transport to the laboratory.

2.2.1 Quality assurance and quality control

Two types of field quality assurance/quality control (QA/QC) samples were recovered in the

broader program (Oceanica 2008):

• Triplicates, where three cores were obtained at the same location and analysed individually

• Replicates, where one sample was collected, homogenised, split into two in the field and

analysed individually in the laboratory.

Of the subset of sites selected for this review, two triplicate samples were analysed

Sediment analysis methods

2.3.1 Sediment analytes

Sediment samples from each of the ten sites (Figure 1.1,Table 2.1, were analysed for the

contaminants of concern listed in the SAP (Oceanica 2008):

• metals (Sb, As, Ba, Cd, Cr, Co, Cu, Pb, Mn, Mo, Ni, Ag, Sn, Hg and Zn)

• total petroleum hydrocarbons (TPH)

• polycyclic aromatic hydrocarbons (PAHs)

• benzene, toluene, ethylene and xylene (BTEX)

• organotins (monobutyltin: MBT, dibutyltin: DBT, tributyltin: TBT)

• total organic carbon (TOC)

• particle size distribution (PSD)

• acid sulphate soils (ASS; only 20% of the original 94 sites sampled in Oceanica 2009 were

analysed for ASS. This included 4 of the 10 sites from Error! Reference source not found.,

Error! Reference source not found.).

PSD analysis was completed at the Division of Minerals/Particle Analysis Service at CSIRO.

National Measurement Institute completed analysis of remaining contaminants of concern using

standard methods in National Association of Testing Authorities accredited methods.

Data analysis methods

Data analysis was completed as per Oceanica 2009, with the following amendments:

• test and summary statistics were computed across the ten sites (Figure 1.1,Table 2.1)

4 BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report

• current guidelines were used (the National Assessment Guidelines for Dredging: CA 2009,

NEPC 2013 and DER 2014).

2.4.1 Normalisation of organics

As TOC is the main binding constituent for organic substances in marine sediments, CA (2009)

requires organics (TBT, TPH, PAH and BTEX) to be normalised to 1% TOC for comparison with

the NAGD Screening Levels. The normalised results provide a measure of the bioavailability of

the organic analytes. When TOC is significantly greater than 1%, the additional binding capacity

will result in organics being less biologically available, and therefore, normalisation will reduce the

measured value proportionally (the reverse also applies). Normalisation is only appropriate over a

TOC range of 0.2–10%. In accordance with the NAGD (CA 2009), if the organic data were below

the laboratory limit of reporting (LoR), half the LoR value was used for normalisation purposes.

2.4.2 Computation of test statistics and assessment against guidelines

Test statistics were computed from the analyte datasets (where possible) for comparison with the

relevant guidelines. The different guidelines stipulate different types of statistical analysis; each of

which is summarised below.

National Assessment Guidelines for Dredging Screening Levels

Concentrations of metals and organics in sediments were compared to the NAGD Screening Levels

(CA 2009). This comparison required calculation of the 95% upper confidence limit (UCL) of the

mean (CA 2009). Where there were not enough samples to complete the calculations, the

maximum concentrations were compared to the relevant NAGD Screening Levels (CA 2009).

Ecological investigation levels and health investigation levels

Concentrations of metals in sediment samples were assessed against the ecological investigation

levels (EILs) and health investigation levels (HILs) from the National Environmental Protection

Council (NEPC) guidelines (NEPC 2013) that are referenced in the contaminated sites guidelines

(DER 2014). Sediment contaminant concentration levels were compared to the EILs for "urban

residential/public open space" and HIL "C" which is acceptable for public open space (NEPC 2013).

The maximum concentration value and the 95% UCL of the arithmetic mean was used for

comparison against the EILs and HILs (NEPC 2013). For assessment against the relevant levels,

the following criteria are also specified in NEPC (2013):

• the standard deviation of the sample data must be less than 50% of the relevant value

• no single value must exceed 250% of the relevant value.

The EILs (for chromium III, copper, nickel and zinc) are typically derived by the addition of the

ambient water quality background analyte concentrations (determined from reference site data) to

the guideline values which represent added contaminant levels. However, sampling was

completed to different guidelines, and therefore there was no collection of reference site data or

ambient background data required for EIL calculation. As such, metal concentration results were

compared to the EILs range. Once the onshore disposal area location has been determined,

background reference site data will be collected and EILs calculated prior to dredging..

Analysis of analyte concentrations below the limit of reporting

Analyte concentrations that are too low to be detected using laboratory methods were recorded as

below the LoR. Generally, CA (2009) recommend that half the laboratory LoR value should be be

used as a substitute for data below the LoR; however, a large proportion of the data below the LoR

has the capacity to bias subsequent analyses. The USEPA (2007) does not consider a 95% UCL

BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report 5

of the mean calculated based upon few detected values to be reliable. Therefore, where the data

contain values below the LoR, the following protocol was applied:

• Where >25% of values are below the LoR, descriptive statistics (means and percentiles) or

inferential analysis (including the calculation of confidence limits) were not calculated. Instead,

individual results were compared to the triggers and discussed accordingly.

• Where ≤25% but >0% of values are below the LoR, confidence limits were calculated based on

half the LoR as the replacement value.

6 BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report

3. Sediment Quality Results

Physical sediment characteristics

3.1.1 Particle size distribution

Sediment was classified according to the Wentworth Scale sediment classifications (Table 3.2).

Sediments at the majority of sites were predominantly comprised of silts and clay, followed by fine

sands, with the exception of sites B17 and B19, which were predominantly comprised of gravel

(Figure 3.1).

Table 3.1 Wentworth scale

Particle size Description

<63 µm silt and clay

63-250 µm fine sand

250-500 µm medium sand

500-2000 µm coarse sand

>2000 µm gravel

Note:

1. A3 & B18= mean of a triplicate

Source: Oceanica (2009)

Figure 3.1 Particle size distribution of sediment samples collected in August 2008

3.1.2 Visual and odour characterisation

Sediment characteristics, core penetration depth and photographs of the cored are detailed in

Table 3.2. Core penetration varied from refusal at 10 cm to full recovery of 100 cm (Table 3.2).

The sediments samples were predominantly grey silts and fine sands (Table 3.2). Seagrass

rhizomes were observed in samples collected at sites A3, B18 and B20, and seagrass matting was

found in the site B16 sample. More than half of the sites had sulphur odour associated with the

sediment samples (Table 3.2).

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

gravel coarse sand medium sand fine sand silt and clay

0-50 cm 50-100 cm

BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report 7

Table 3.2 Sediment characteristics and penetration depth of diver cores sampled in August 2008

Site Date Core length (cm)

Section

Top = 0-50cm

Bottom = 50-100cm

Sample characteristics - type of material, colour, odour Photograph

A3 Triplicate A 15/08/08 100

Top Grey fine silt, rhizome at about 30 cm, some smell

Bottom As above, small amount of rhizome, thick, very dark grey clay, light grey

limestone at bottom

A3 Triplicate B 15/08/08 100

Top Grey fine silt, rhizome at about 30 cm, some smell

Bottom As above, small amount of rhizome, thick, very dark grey clay, light grey

limestone at bottom

A3 Triplicate C 15/08/08 100

Top Grey fine silt, rhizome at about 30 cm, some smell

Bottom

As above, small amount of rhizome, thick, very dark grey clay, light grey

limestone at bottom

A5 15/08/08 10 (surface scrape)

Top Grey silt, no smell

Bottom NA

A7 (replicate sample) 15/08/08 30 (surface scrape)

Top Dark grey/black silt, some smell

Bottom NA

B1 11/08/08 100

Top

Corer did not reach compacted material, soft, grey fines, compacted

during coring, sulphur smell

Bottom No layering but deeper was slightly coarser

B15 12/08/08 50

Top Grey fine silt. Some sulphur smell

Bottom NA

B16 12/08/08 100

Top Grey silt/sand, shell layer at 30 cm, seagrass matt at 20 cm

Bottom Grey silt/sand, some shells

8 BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report

Site Date Core length (cm)

Section

Top = 0-50cm

Bottom = 50-100cm

Sample characteristics - type of material, colour, odour Photograph

B17 12/08/08 10 (surface scrape)

Top Grey sand, lots of shell grit

Bottom NA

B18 Triplicate A 12/08/08 100

Top

Light grey sand/silt and shell, some sulphur smell, some rhizome mat

Bottom

B18 Triplicate B 12/08/08 100

Top

Light grey sand/silt and shell, some sulphur smell, some rhizome mat

Bottom

B18 Triplicate C 12/08/08 100 Top

Light grey sand/silt and shell, some sulphur smell, some rhizome mat See above photograph Bottom

B19 12/08/08 10 (surface scrape)

Top Shell, coarse sand and grit

Bottom NA

B20 12/08/08 100

Top Grey sand, sulphur smell, rhizome at 20 cm

Bottom Grey sand, sulphur smell, some shell

Source: Oceanica (2009)

BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report 9

Metals

Test statistics (95% UCL, maximum, mean and standard deviation) were calculated for all metal

analyte concentrations in the surface layer (0–50 cm) sediments, with the exception of antimony

and cadmium (Table 3.3) as antimony and cadmium concentrations were below the LoR for all or

>25% of sites (Table 3.3). For surface sediments (0–50 cm), the 95% UCL of total metals was

below the respective NAGD Screening Levels for each analyte (Table 3.3). Individual mercury

surface sample concentrations exceeded the NAGD Screening Levels at sites A3 and A5

(Table 3.3).

The sample size was too small (n=5) to calculate a meaningful 95% UCL in the bottom layer (50-

100 cm) of sediments, and as such, individual concentrations were compared to the NAGD

Screening Levels (CA 2009). All maximum concentration for total metals in bottom sediments were

below the respective NAGD Screening Levels, with the exception of arsenic, which was equal to

the NAGD Screening Level at site B1

The 95% UCL concentrations for arsenic, total chromium, copper, lead, zinc and nickel, for surface

sediment samples were below their respective EILs, or within acceptable EIL ranges for disposal

to 'urban residential and public open space' requirements (Table 3.3, NEPC 2013). All individual

metal concentrations in surface samples and bottom samples were below their respective HILs "C"

for public open spaces, satisfying the conditions of the NEPC (2013; Table 3.3).

BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report 11

Table 3.3 Total metal concentrations in sediments sampled in August 2008

Analyte/Site Sb As Ba Cd Total Cr Co Cu Pb Mn Hg Mo Ni Sn Ag Zn

Unit mg/kg

NAGD Screening Level1 2 20 – 1.5 80 – 65 50 – 0.15 – 21 – 1 200

EIL2 – 50 – – 75-160 – 30-120 270 – – – 10-170 – – 25-500

HIL2 – 300 – 90 – 300 17000 600 19000 80 – 1200 – – –

LoR 0.2 0.5 0.2 0.1 0.2 0.2 0.2 0.2 0.2 0.01 0.2 0.2 0.2 0.2 0.2

A3_S* 0.2 7.5 8.9 0.24 46.0 1.5 35.0 14.0 77.3 0.167 2.6 10.3 0.9 0.1 75.7

A5_S <0.2 8.9 11.0 0.23 51.0 1.7 40.0 16.0 72.0 0.160 1.4 11.0 1.0 0.1 80.0

A7_S <0.2 11.0 11.0 0.17 47.0 1.8 25.0 12.0 78.0 0.110 3.7 10.0 0.8 0.1 55.0

B1_S <0.2 7.7 7.6 0.20 27.0 1.2 14.0 26.0 42.0 0.028 2.0 6.6 0.5 0.1 46.0

B15_S <0.2 6.3 8.9 0.14 28.0 1.1 8.8 17.0 25.0 0.110 1.5 5.4 0.1 0.1 29.0

B16_S <0.2 4.7 7.7 <0.05 20.0 1.0 6.1 9.3 16.0 0.054 1.9 4.3 0.1 0.1 45.0

B17_S <0.2 6.6 8.0 <0.05 20.0 1.1 3.3 6.6 20.0 0.032 1.1 3.9 0.1 0.1 9.9

B18_S* <0.2 3.4 8.4 <0.05 14.1 0.8 2.0 4.7 9.6 0.016 2.0 2.3 0.1 0.1 6.7

B19_S <0.2 1.2 12.0 <0.05 7.0 0.7 19.0 4.1 8.2 0.014 0.4 0.7 0.1 0.1 7.2

B20_S <0.2 4.5 6.2 <0.05 17.0 1.0 4.2 6.6 12.0 0.045 1.4 3.3 0.1 0.1 9.3

Maximum NA 11.0 12.0 NA 51.0 1.8 40.0 26.0 78.0 0.167 3.7 11.0 1.0 NA 80.0

Mean NA 6.2 9.0 NA 27.7 1.2 15.7 11.6 36.0 0.074 1.8 5.8 0.4 NA 36.4

Standard deviation NA 2.84 1.82 NA 15.27 0.36 13.65 6.84 29.11 0.058 0.89 3.59 0.36 NA 28.25

95% ProUCL3 NA 7.82 10.03 NA 36.56 1.395 23.65 15.6 52.89 0.107 2.32 7.86 0.58 NA 52.75

A3_0.5-1.0* 0.15 9.2 8.6 0.22 29 1.24 9.1 5.8 57.7 0.039 5.4 6.5 0.3 0.1 23.0

B1_0.5-1.0 0.20 20.0 13.0 0.05 50 2.4 6.4 9.3 94 0.005 15 11 0.3 0.1 8.5

B16_0.5-1.0 0.20 9.8 10.0 0.05 23 1.4 1.6 4.4 29 0.005 3 5 0.1 0.1 2.7

B18_0.5-1.0* <0.2 5.3 5.9 0.05 15.7 0.9 0.8 2 10.7 0.005 3.4 2.7 0.1 0.1 1.4

B20_0.5-1.0 0.16 8.3 8.5 0.05 21.5 1.4 1.6 4.05 23.5 0.005 4.5 4.6 0.1 0.1 1.4

Maximum 0.20 20.0 13.0 0.22 50 2.4 9.1 9.3 94 0.039 15.0 11.0 0.3 NA 23.0

Mean 0.16 10.52 9.18 0.08 27.83 1.47 3.90 5.12 42.97 0.012 6.28 5.97 0.2 NA 7.4

Standard Deviation 0.04 5.57 2.60 0.08 13.27 0.55 3.65 2.71 33.31 0.015 4.97 3.12 0.12 NA 9.2

Notes:

1. NAGD Screening Levels from CA (2009).

2. EIL = range of Ecological Screening Levels for "urban residential/public open spaces" (NEPC 2013)

3. HIL = health investigation level "C" for commercial/industrial areas (NEPC 2013)

4. Calculation of 95% UCL only possible or surface data (not possible for bottom data due to small dataset size).

5. Bold text indicated exceedance of NAGD Screening Level, italicised text indicates exceedance of Ecological Investigation Level (EIL) for public open space.

6. * = triplicate results which were averaged for inclusion in this table.

7. NA = not applicable; test statistics were not calculated for analytes with >25% below LoR.

8. LoR = limit of reporting.

BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report 13

Hydrocarbons

Concentrations of TPH and BTEX were below the LoR in all samples (Oceanica 2009). Therefore,

results were not normalised and sediments are considered to be uncontaminated by TPHs and

BTEX.

While there were low concentrations of PAHs recorded in all sediment samples (results for PAH

sum ranged from 0.0466–0.5896 mg/kg; Table 3.4), numerous PAH species were below the LoR,

and not all PAH species now required for comparison to the NAGD (CA 2009) Screening Level

(10 000 mg/kg) were originally analysed by Oceanica (2009). This prohibited a meaningful

comparison to the NAGD (CA 2009) Screening Levels. Given the extremely low concentrations of

PAHs in sediments, the risk of contamination to the marine environment due to disturbance

associated with dredging is considered extremely low.

Table 3.4 Polycyclic aromatic hydrocarbons concentrations normalised in sediment

samples collected at Kwinana Quay in 2008

Analyte/Site Total organic carbon Sum 15 PAHs1

Unit % mg/kg

NAGD Screening Level2 – 10 000

A3* 5.0 0.1196

A5 3.9 0.0918

A7 2.8 0.1911

B1 2.4 0.5896

B15 1.9 0.2711

B16 1.9 0.1389

B17 1.2 0.0792

B18* 1.5 0.0682

B19 1.0 0.0910

B20 1.3 0.0869

A3* 3.7 0.0466

B1 2.1 0.0610

B16 1.0 0.0750

B18* 1.1 0.0714

B20 0.8 0.0938

Notes:

1. 95% UCL could not be calculated as >25% results were below the limit of reporting (LoR). Only 15 PAHs (napthalene,

acenaphthalene, acenaphtene, fluorene, phenanthrene, anthracene, fluoranthene, pyrene, benzo(a)anthracene,

chrysene, benzo(b)fluoranthene and benzo(k)fluoranthene, benzo(a)pyrene, indeno(1,2,3-c,d)pyrene,

dibenzo(a,h)anthracene and benzo(g,h,i)perylene) were analysed, therefore the sum of these is compared to the 18

PAHs NAGD Screening Level

2. NAGD Screening Levels from CA (2009)

3. Italicised results = non-normalised result was below the LoR and half the LoR was used in calculation purposes

4. * = triplicate samples which were averaged for inclusion in this table

14 BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report

Organotins

Normalised TBT concentrations were below both the NAGD (CA 2009) Screening Level and the at

all sites in both the top and bottom sediment samples (Table 3.5).

Table 3.5 Total organotin concentrations in sediment samples collected at Kwinana

Quay in 2008

Organotin TOC MBT DBT TBT Normalised TBT2

Unit % μgSn/kg μgSn/kg μgSn/kg μgSn/kg

Screening Level1 – – – – 9

Top samples 0–50 cm

A3_Top* 5.0 3.1 4.4 2.2 0.44

A5_Top 3.9 3 4.7 2.4 0.62

A7_Top 2.8 3.1 4.8 2.7 1.13

B1_Top 2.4 <0.5 1.4 0.79 0.33

B15_Top 1.9 <0.5 1.5 0.64 0.34

B16_Top 1.9 <0.5 0.97 0.59 0.31

B17_Top 1.2 <0.5 0.77 0.60 0.50

B18_Top* 1.5 <0.5 0.67 <0.5 0.17^

B19_Top 1.0 0.83 0.74 0.87 0.87

B20_Top 1.3 0.62 <0.5 <0.5 0.19^

Bottom samples 50–100 cm

A3_Bottom* 3.7 1.1 1.4 0.85 0.43

B1_Bottom 2.1 <0.5 <0.5 <0.5 0.12^

B16_Bottom 1.0 <0.5 <0.5 <0.5 0.25^

B18_Bottom* 1.1 <0.5 <0.5 0.31 0.30

B20_Bottom 0.8 <0.5 <0.5 <0.5 0.32^

Notes:

1. As per NAGD (CA 2009)

2. TBT was normalised to 1% total organic carbon. Normalisation is only appropriate over the total organic carbon

range 0.2–10% (equates to multiplication factors of 5 times –0.1 times, respectively)

3. * = triplicate samples which were averaged for inclusion in this table

4. ^= half limit of reporting used in calculation

5. TOC = total organic carbon, MBT = monobutyltin, DBT = dibutyltin, TBT = tributyltin, - = no guideline value

3.5 Acid Sulfate Soils

A subsection (20%) of the original sites sampled were analysed for ASS (Oceanica 2009). Of the

ten sites examined within this report, four were included in the 20% analysed for ASS (Table 3.6).

At each site, the sulfur (%S) was above the potential sulfidic acidity Action Criteria of 0.03%

(DER 2015) and therefore identified as potential ASS.

However, the acid-based accounting completed for these sediment samples indicated that the

potential acidity was sufficiently buffered by the acid neutralising capacity of the sediment and

therefore the total net acidity for every sample was negative (Table 3.6). Therefore, the samples

exhibited sufficient neutralising capacity within the sediments to result in no net acidity formation

after disturbance of the sediments during dredging within the water column.

BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report 15

Table 3.6 Acid sulfate soil analysis and acid base accounting for sediment samples

collected at Kwinana Quay in 2008

Analyte/Site pHKCl %S (SCr) Equivalent

Acidity

Existing

Acidity

ANC

existing %

ANC (mol

H+/tonne)

Net

Acidity

(mol

H+/tonne)

Action

Criteria1 – 0.03 18.7 – – – –

A3c_Bottom 9.0 0.45 280.7 none 63 12587.4 -8110.9

B15_Top 9.2 0.18 112.3 none 57 11388.6 -7480.1

B18a_Bottom 9.3 0.11 68.6 none 66 13186.8 -8722.6

B20_Top 9.1 0.10 62.4 none 48 9590.4 -6331.2

Notes:

1. Samples assigned DER (2015) action criteria for >1000t material.

2. pHKCL = pH in potassium chloride suspension, S = sulfur, SCr = chromium reducible sulfur, ANC = acid neutralising

capacity

3. – = no guidelines available

4. A positive net acidity indicates excess acid

Quality assurance/quality control

QA/QC analyses was completed on the full set of sediment data (n=94) collected by Oceanica

(2009), and laboratory duplicate and blank samples had a relative percentage difference of within

±35% between results, which is considered acceptable (Oceanica 2009). Further QA/QC

assessment was not completed in this report.

16 BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report

4. Conclusions

The unconsolidated surface material in the upper 1 m of the seabed from sampling in 2008 was

considered to be clean and met NAGD (CA 2009) Screening Levels.

BMT: The Water Corporation (Western Australia): Perth Seawater Desalination Plan 2: Sediment Quality Report 17

5. References

CA (2009) National Assessment Guidelines for Dredging. Commonwealth of Australia, Canberra,

ACT

DER (2014) Assessment and management of contaminated sites. Contaminated sites guidelines.

Department of Environment Regulation, Perth, Western Australia, December 2014

DER (2015) Identification and Investigation of Acid Sulfate Soils and Acidic Landscapes.

Department of Environment Regulation, Perth, Western Australia, June 2015

NEPC (2013) National Environment Protection (Assessment of Site Contamination) Amendment

Measure 2013 (No. 1) National Environment Protection Council, April 2013

Oceanica (2008) Fremantle Ports Kwinana Quay Project Sediment Sampling and Analysis Plan.

Prepared for Fremantle Ports by Oceanica Consulting Pty Ltd. Report No. 560/1 Draft,

Perth, Western Australia, July 2008

Oceanica (2009) Fremantle Ports Kwinana Quay Sediment sampling and analysis implementation

report diver and geotechnical survey. Prepared for Fremantle Ports by Oceanica Consulting

Pty Ltd. Report No. 560_005/4_Rev0, Perth, Western Australia, October 2009

USEPA (2007) ProUCL version 4.0. Available from <http://www.epa.gov/esd/tsc/ software.htm>.

United States Environmental Protection Authority

PO Box 2305 Churchlands

WA 6018 Australia

Tel: +61 8 6163 4900

www.bmt.org

Page 11