27
Technical Note - TN 052: 2016 Technical Note - TN 052: 2016 Subject: Withdrawal of RailCorp Network Management Plans Chapters 1 to 4 Issued date: 08 July 2016 Effective date: 08 July 2016 For queries regarding this document [email protected] www.asa.transport.nsw.gov.au This technical note has been issued by the Asset Standards Authority (ASA) to notify that the RailCorp Network Management Plans - Chapter 1, Chapter 2, Chapter 3 and Chapter 4 on the ASA website are withdrawn and have been replaced by Sydney Trains Network Management Plans. The Sydney Trains Network Management Plans are available on the RailSafe website (railsafe.org.au/electrical-safety-sms-documents). Table 1 provides the list of RailCorp Network Management Plans that are withdrawn and their corresponding Sydney Trains Network Management Plans that replace them. Table 1 – List of RailCorp network management plans and Sydney Trains network management plans Withdrawn RailCorp specifications Replaced by Sydney Trains specifications EP 95 00 30 06 SP RailCorp Network Management Plan Chapter 1 Network Safety and Reliability, version 3.4 SP E 70953 Sydney Trains Network Management Plan Chapter 1 Distribution Network Safety and Reliability, version 1.0 EP 95 00 30 03 SP RailCorp Network Management Plan Chapter 2 Customer Installation Safety, version 3.3 SP E 70954 Sydney Trains Network Management Plan Chapter 2 Customer Installation Safety, version 1.0 EP 95 00 30 04 SP RailCorp Network Management Plan Chapter 3 Public Electrical Safety Awareness, version 1.0 SP E 70955 Sydney Trains Network Management Plan Chapter 3 Public Electrical Safety Awareness, version 1.0 EP 95 00 30 05 SP RailCorp Network Management Plan Chapter 4 Bush Fire Risk Management, version 3.3 SP E 70956 Sydney Trains Network Management Plan Chapter 4 Bush Fire Risk Management, version 1.0 © State of NSW through Transport for NSW Page 1 of 2

Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

Technical Note - TN 052: 2016

Technical Note - TN 052: 2016

Subject: Withdrawal of RailCorp Network Management Plans Chapters 1 to 4

Issued date: 08 July 2016

Effective date: 08 July 2016

For queries regarding this document [email protected]

www.asa.transport.nsw.gov.au

This technical note has been issued by the Asset Standards Authority (ASA) to notify that the

RailCorp Network Management Plans - Chapter 1, Chapter 2, Chapter 3 and Chapter 4 on the

ASA website are withdrawn and have been replaced by Sydney Trains Network Management

Plans.

The Sydney Trains Network Management Plans are available on the RailSafe website

(railsafe.org.au/electrical-safety-sms-documents).

Table 1 provides the list of RailCorp Network Management Plans that are withdrawn and their

corresponding Sydney Trains Network Management Plans that replace them.

Table 1 – List of RailCorp network management plans and Sydney Trains network management plans

Withdrawn RailCorp specifications Replaced by Sydney Trains specifications

EP 95 00 30 06 SP RailCorp Network Management Plan Chapter 1 Network Safety and Reliability, version 3.4

SP E 70953 Sydney Trains Network Management Plan Chapter 1 Distribution Network Safety and Reliability, version 1.0

EP 95 00 30 03 SP RailCorp Network Management Plan Chapter 2 Customer Installation Safety, version 3.3

SP E 70954 Sydney Trains Network Management Plan Chapter 2 Customer Installation Safety, version 1.0

EP 95 00 30 04 SP RailCorp Network Management Plan Chapter 3 Public Electrical Safety Awareness, version 1.0

SP E 70955 Sydney Trains Network Management Plan Chapter 3 Public Electrical Safety Awareness, version 1.0

EP 95 00 30 05 SP RailCorp Network Management Plan Chapter 4 Bush Fire Risk Management, version 3.3

SP E 70956 Sydney Trains Network Management Plan Chapter 4 Bush Fire Risk Management, version 1.0

© State of NSW through Transport for NSW Page 1 of 2

Page 2: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

Technical Note - TN 052: 2016

The RailCorp Network Management Plans are referred in other ASA standards and any conflict in

Sydney Trains Network Management Plans should be referred to the Lead Electrical Engineer,

ASA.

Authorisation:

Technical content prepared by

Checked and approved by

Interdisciplinary coordination checked by

Authorised for release

Signature

Date

Name Wes Burgess Neal Hook Andrea Parker Graham Bradshaw

Position Technical Specialist Electrical Network

Lead Electrical Engineer

Chief Engineer Director Network Standards and Services

© State of NSW through Transport for NSW Page 2 of 2

Page 3: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

Engi

neer

ing

Stan

dard

With

draw

n - f

or re

fere

nce

only

RAILCORP NETWORK MANAGEMENT PLAN CHAPTER 1 -

NETWORK SAFETY AND RELIABILITY

EP 95 00 30 06 SP

Engineering Standard Electrical

Version 3.4

Issued May 2013

Owner: Chief Engineer Electrical

Approved by:

Neal Hook Chief Engineer Electrical

Authorised by:

Neal Hook Chief Engineer Electrical

Disclaimer This document was prepared for use on the RailCorp Network only. RailCorp makes no warranties, express or implied, that compliance with the contents of this document shall be sufficient to ensure safe systems or work or operation. It is the document user’s sole responsibility to ensure that the copy of the document it is viewing is the current version of the document as in use by RailCorp. RailCorp accepts no liability whatsoever in relation to the use of this document by any party, and RailCorp excludes any liability which arises in any manner by the use of this document. Copyright The information in this document is protected by Copyright and no part of this document may be reproduced, altered, stored or transmitted by any person without the prior consent of RailCorp.

UNCONTROLLED WHEN PRINTED Page 1 of 25

Page 4: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 2 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

With

draw

n - f

or re

fere

nce

only

Document control

Version Date Summary of change 3.0 May 2010 Application of TMA 400 format 3.1 February 2011 All references reviewed and updated as applicable.

Editorial changes to all sections to provide uniformity across all chapters and reflect changes implemented via organisational restructure. Clause 6 updated to reflect new work project. Appendix A and B updated to reflect suite of current documents Other minor editorials.

3.2 March 2011 Inclusion of reference to Public Electrical Safety Awareness in Section 1. Inclusion of reference to NSW Maritime and associated protocols for exchange of GIS data and incident reporting and analysis for crossings of NSW navigable waters.

3.3 August 2011 Clause 6 amended to reflect revised Safety Risk Register process and inclusion of standard EP 11 03 00 02 SP in Appendix A.

3.4 May 2013 Update SMS reference documents

Page 5: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 3 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

Contents

1 Introduction .............................................................................................................................5 2 Scope and Application ...........................................................................................................5 2.1 Background ...............................................................................................................................5 2.2 Objectives .................................................................................................................................5 3 RailCorp and other References .............................................................................................6 4 General .....................................................................................................................................6 4.1 Introduction ...............................................................................................................................6 4.2 Responsibility within RailCorp...................................................................................................7

4.2.1 Safety & Environment Group.....................................................................................7 4.2.2 Service Delivery Group..............................................................................................7 4.2.3 Asset Operations Group ............................................................................................7 4.2.4 Engineering & Projects Group ...................................................................................8 4.2.5 General Counsel and Governance Group.................................................................9

4.3 RailCorp as an Electricity Distributor and a Rail Operator........................................................9 4.4 Relationship of 1500V OHW System to the Electrical Network Management

Plan ...........................................................................................................................................9 4.5 Audit of Electrical Network Management Plan........................................................................10

4.5.1 Nomination of Auditor ..............................................................................................10 4.5.2 Periodical Audits ......................................................................................................10

4.6 Measurement of Safety Performance: Performance Indicators..............................................10 4.7 Compliance with the Network Management Plan ...................................................................10

4.7.1 Work On or Near the RailCorp Distribution System ................................................10 4.7.2 Compliance Audits...................................................................................................10

5 Description of RailCorp’s Distribution System..................................................................10 5.1 Maps of the Distribution System .............................................................................................10 5.2 Design and Construction Standards .......................................................................................11

5.2.1 Aerial Lines and Cables...........................................................................................11 5.2.2 Substations ..............................................................................................................11 5.2.3 Low Voltage Distribution Assets ..............................................................................11

5.3 Maintenance Plans and Standards .........................................................................................11 5.4 Operation and Work Procedures ............................................................................................12

5.4.1 Additional Operation Procedures.............................................................................12 5.4.2 Reporting Incidents and Unsafe Conditions ............................................................12

5.5 Engineering Records, Drawings and Maps.............................................................................13 5.5.1 Electricity Works ......................................................................................................13 5.5.2 Operating Diagrams.................................................................................................13 5.5.3 Crossings of NSW Navigable Waters......................................................................13

6 Analysis Of Hazardous Events ............................................................................................14 7 Emergency Procedures........................................................................................................14 8 Asset Management Strategies.............................................................................................14 9 Reports to the Director-General ..........................................................................................15 10 Standards and Codes ...........................................................................................................16 W

ithdr

awn

- for

refe

renc

e on

ly

Page 6: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 4 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

10.1 RailCorp Electrical publications ..............................................................................................16 10.2 Other RailCorp publications ....................................................................................................16

10.2.1 Electrical Network Safety Rules (ENSR) .................................................................16 10.2.2 Other SMS Documents............................................................................................16

10.3 Codes of Practice....................................................................................................................16 10.4 Departures from Codes of Practice.........................................................................................16

10.4.1 Service and Installation Rules .................................................................................16 10.4.2 Contestable works ...................................................................................................17 10.4.3 Electricity Service Standards...................................................................................17

11 Managing of persons working on or near RailCorp Electricity Network.........................18 11.1 Training ...................................................................................................................................18 11.2 Authorisation ...........................................................................................................................18 Appendix A RailCorp Electrical Publications ..........................................................................19 Appendix B Other RailCorp Publications.................................................................................22 Appendix C Training Matrix .......................................................................................................24

With

draw

n - f

or re

fere

nce

only

Page 7: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 5 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

1 Introduction The RailCorp Network Management Plan is the primary instrument by which the requirements of the Electricity Supply (Safety and Network Management) Regulation 2008 are implemented.

This document is one of three documents that together comprise RailCorp’s Network Management Plan. These documents are as follows:

EP 95 00 30 06 SP RailCorp Network Management Plan - Chapter 1 - Network Safety and Reliability (this document)

EP 95 00 30 03 SP RailCorp Network Management Plan - Chapter 2 - Customer Installation Safety

EP 95 00 30 04 SP RailCorp Network Management Plan - Chapter 3 – Public Electrical Safety Awareness

EP 95 00 00 30 05 SP RailCorp Network Management Plan - Chapter 4 - Bush Fire Risk Management

RailCorp commits to ensuring that safety is given the highest priority over all other aspects of network management and the Network Management Plan aims to provide a platform to support this commitment.

2 Scope and Application

2.1 Background RailCorp is a NSW Government Agency constituted under the Transport Administration Act 1988 (NSW). RailCorp aims to deliver safe, clean and reliable services that are efficient, sustainable and to the satisfaction of all customers. Sydney metropolitan passenger rail services are delivered via CityRail and interstate passenger services via CountryLink.

RailCorp is responsible for the safe operation, crewing and maintenance of passenger trains and stations and provides access to freight and passenger operators in the Sydney metropolitan area.

RailCorp owns and maintains the Sydney metropolitan rail network. This network includes track, bridges, signalling systems, communications systems, an electricity distribution system, and other infrastructure. RailCorp also owns and maintains country based infrastructure such as operational country stations.

2.2 Objectives The objective of this document is to ensure that the RailCorp Distribution system provides an adequate, safe and reliable supply of electricity to RailCorp customers.

This document provides details of RailCorp policies and procedures with regard to:

• the design, construction, operation and maintenance of the electricity network; • the planning process; • asset management; • analysis of hazardous events; • the procedures to be implemented in emergency situations; • competency requirements for anyone who works on or near the electricity network;

and • the reporting requirements in relation to maintenance, reliability and safety.

With

draw

n - f

or re

fere

nce

only

Page 8: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 6 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

3 RailCorp and other References The following documents contain provisions that, through reference in this text, provide further information and constitute provisions of this document where applicable. At the time of publication, the editions indicated below were valid.

ENA DOC 001-2008 National Electricity Network Safety Code ENA NENS 04 – 2006 National Guidelines for Safe Approach Distances to Electrical

and Mechanical Apparatus Code of Practice - Electricity transmission and distribution asset management (February 2009) Code of Practice - Demand Management for Electricity Distributors (September 2004) Code of Practice - Contestable works (April 2007) Crossings of Navigable Waters: Electricity Industry Code (Version 3/2010) ISSC 14 - Guide to electrical workers’ safety equipment (October 2010) ISSC 31 - Guideline for the Management of private Overhead Lines (July 2004) Premier's Memoranda M 2002-10 Total Asset Management Transport Administration Act 1988 (NSW) Rail Safety (Adoption of National Law) Act 2012 Electricity Supply (Safety and Network Management) Regulation 2008 EP 00 00 00 00 MP Technical Maintenance Plan SMS-01-SR-2000 Safety Management System Requirements SMS-06-GD-0268 Working Around Electrical EquipmentSMS-06-SP-2089 Manage Operational Safety Risk SMS-06-EN-0555 Locking Systems for Electrical Equipment SMS-04-SP-2064 Asset Lifecycle Management SMS-11-SP-2011 Training and Competence SMS-11-GD-0244 Personnel Certifications – Electrical Authorisations SMS-15-OP-2132 Develop and Implement Site Incident Management Plan SMS-15-SP-2075 Emergency Preparedness SMS-15-GD-0638 Incident Response Guide SMS-19-SP-2079 Safety Audit SMS-19-OP-2122 Conduct Safety Audits AS/NZS 3000:2007 Electrical installations (known as the Australian/New Zealand

Wiring Rules)

Additional references to Australian Standards and other RailCorp documents are listed within the various sections of this document.

4 General

4.1 Introduction This section contains explanatory material necessary to clarify the unique nature of RailCorp and RailCorp distribution system in comparison with the distribution systems managed and operated by the other NSW electricity distributors around which the legislation has been primarily based.

Rail Corporation New South Wales was formed by an act of Parliament on 1 January 2004. It was formed by an amalgamation of the State Rail Authority of NSW and the metropolitan section of the Rail Infrastructure Corporation. With

draw

n - f

or re

fere

nce

only

Page 9: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 7 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

The Rail Infrastructure Corporation was formed in January 2001 when the previous Rail Access Corporation (RAC) and the Rail Services Australia Corporation (RSA) were merged. RAC previously was the owner of the rail infrastructure, and RSA was the prime provider of infrastructure services (the maintainer).

In 1997 the rail system was geographically divided into 13 areas, and the provision of infrastructure services was to be made contestable. Four areas were tendered, and contracts awarded. A fourteenth area was also created in May 2000 with the opening of the New Southern Railway (the Airport Rail Line).

In 2003, the Government suspended indefinitely contestability within the rail maintenance industry and external contracts that have expired have not been renewed. This has resulted in RailCorp being the prime provider of infrastructure services in all of the areas, with Transfield Maintenance in 1 area.

4.2 Responsibility within RailCorp RailCorp has produced a Safety Management System which is summarised in Publication SMS-01-SR-2000 Safety Management System Requirements. Management of RailCorp’s Electrical Distribution Network falls under this Safety Management System.

RailCorp’s responsibilities are reflected in the three broad areas of organisation structure as follows:

4.2.1 Safety & Environment Group Within this group, the General Manager Safety Systems is responsible for providing the safety systems for work (both WH&S and electrical), for ensuring compliance throughout the Corporation with the systems and standards via an audit process, and for investigation of incidents and accidents. The prime responsibility for legislative compliance associated with the Electrical Network is with the General Manager, Corporate Safety Division. This involves coordinating the production of the Electrical Network Management Plan as required by the Regulation.

4.2.2 Service Delivery Group The Service Delivery Group focus on the delivery of; clean, safe, secure and reliable passenger services that are efficient, sustainable and to the satisfaction of our customers through effective and efficient practices. This includes customer service, security, station operations, cleaning service (internal trains and stations), passenger information, CountryLink, train operations, train crewing and network control of train services.

4.2.3 Asset Operations Group The Asset Operations Group focus on maintaining the infrastructure, delivering the major periodic maintenance program, and ensuring the performance of our rollingstock, infrastructure and communications and control assets.

Within the Asset Operations Group:

The General Manager Infrastructure Maintenance Division is responsible for the implementation of plans compliant with the relevant safety plans and standards. Within this Division a district structure has been created with field offices providing the inspection, routine maintenance, certification and emergency response functions. The existing contract with Transfield does not come under this district structure but the personnel working on this contract are classed as employees for the purpose of the Network Management Plan. W

ithdr

awn

- for

refe

renc

e on

ly

Page 10: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 8 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

The General Manager Asset Planning and Performance Division is responsible for defining effective asset performance targets and effective asset strategies and controlling planning and programming via long term asset management plans and programmes.

The General Manager Infrastructure Renewals Division is responsible for the provision of products or services from RailCorp businesses or through external commercial arrangements and to generate external revenue to support RailCorp by realising opportunities to exploit under utilised assets and surplus capability

The day to day operation of the electricity distribution system (electrical network) is the responsibility of the Electrical System Control area under the System Control Engineer, managed by the Manager Infrastructure Operations. Electrical System Control also provides Protection and SCADA functions.

4.2.4 Engineering & Projects Group Engineering & Projects Group focus on the future rail network and ensuring delivery of the capital program.

Within the Engineering & Projects Group:

The Chief Engineers Division’s role is to:

Provide the technical vision for future development of the railway assets including strategic technical input into policy, objectives, development strategies, and ongoing operation of the rail network.

Develop and maintain current a suite of technical criteria that define the mandatory standards to which all new equipment of the particular asset classification must comply.

Develop and maintain the minimum standards to which equipment in an asset classification must comply throughout its life.

Maintain an assurance framework:

– for assessing and reporting on the integrity of existing assets; – to ensure appropriate delegation of technical authority to competent people; – for technical acceptance of new and altered assets.

The General Manager of the Chief Engineers Division is the Approver of Electrical Network Safety Rules (ENSR) suite of documents.

The Chief Engineer Electrical business unit reports primarily to the Chief Executive, via the General Manager of the Chief Engineers Division, on the integrity of the electrical network and on the adequacy of systems implemented to manage and operate the electrical network. The Chief Engineer Electrical is responsible for the delegation of Electrical Engineering Authority throughout the organisation and provides centralised engineering expertise and support. This includes production of the relevant engineering standards and electrical design schemes

The General Manager, Professional Services Division provides technical input to RailCorp infrastructure projects, from the planning stage, concept and feasibility design, through to commissioning, operations and maintenance. The structure includes six discipline-based design teams, which contain designers and project design managers working together. W

ithdr

awn

- for

refe

renc

e on

ly

Page 11: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 9 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

4.2.5 General Counsel and Governance Group Communications, Company Secretary and Corporate Counsel, business services, property, finance, human resources, information and communication technology, product development, safety and environment, strategy, performance and access.

4.3 RailCorp as an Electricity Distributor and a Rail Operator The prime purpose of the RailCorp electricity distribution network is to supply electricity to the NSW rail network. In this context RailCorp operates as an exempt Network Operator and an exempt Network Retailer.

For the purpose of The RailCorp Electrical Network Management Plan the 1500V Overhead Wiring is in effect excluded.

The management of safety associated with the 1500V Overhead Wiring system is captured by the Rail Safety (Adoption of National Law) Act 2012 and is included in publication SMS-01-SR-2000 Safety Management System Requirements which is submitted to the Independent Transport Safety and Reliability Regulator (ITSRR) as part of RailCorp's rail safety accreditation. The format of that publication is similar to that required for the Network Management Plan. It should be noted that the ITSRR also regulates some aspects of the safety and operation of the RailCorp electricity distribution system.

4.4 Relationship of 1500V OHW System to the Electrical Network Management Plan The RailCorp 1500V OHW system is a unique type of distribution system.

The key issue of its uniqueness is its intimate and exclusive association with a railway which is regulated by the Rail Safety (Adoption of National Law) Act 2012.

The Code of Practice for Electricity Transmission and Distribution Asset Management specifically excludes 1500V OHW.

The Code of Practice for Contestable Works is not applicable because 1500V OHW does not fall within the definition of contestable works as defined in the Electricity Supply (General) Regulation 2001.

The Code of Practice for Service and Installation Rules does not apply because neither 1500V OHW nor electric rolling stock falls within the definition of an installation.

RailCorp will report to NSW Trade and Investment, any safety incidents associated with the 1500V OHW which are considered to be appropriate and relevant to the electricity distribution industry.

It is also relevant to note that if a person is to be at risk from the 1500V OHW system, the person will also be at risk from train operations, which then becomes a Rail Safety management issue and is regulated by the Rail Safety (Adoption of National Law) Act 2012.

With

draw

n - f

or re

fere

nce

only

Page 12: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 10 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

4.5 Audit of Electrical Network Management Plan

4.5.1 Nomination of Auditor RailCorp nominates an auditor who is independent of RailCorp and is competent to exercise the functions of an auditor under the Regulation in respect of this plan.

The Director General of NSW Trade and Investment will be notified in writing of this nomination.

4.5.2 Periodical Audits The nominated auditor will be engaged to carry out periodical audits in accordance with Section 15 and 17 of the Regulation. The results of the audits and a copy of the Network Management Plan, if it has been updated since the last audit, will be submitted to the Director General of NSW Trade and Investment.

4.6 Measurement of Safety Performance: Performance Indicators Safety performance is measured and reported in accordance with regulatory and NSW Trade and Investment guidelines, namely:

• Section 17 of the Regulation audit requirements • Significant Electricity Network Incident (SENI) guidelines • Electricity Network Performance Report Outline

4.7 Compliance with the Network Management Plan

4.7.1 Work On or Near the RailCorp Distribution System All work on or near the RailCorp Electrical distribution system is carried out in accordance with the RailCorp:

• Safety Management System, • suite of Electrical Standards, and • Electrical Technical Maintenance Plan.

4.7.2 Compliance Audits RailCorp audits each District for compliance with the Network Management Plan in accordance with documents SMS-19-SP-2079 Safety Audits and SMS-19-OP-2122 Conduct Safety Audit.

5 Description of RailCorp’s Distribution System

5.1 Maps of the Distribution System Maps showing the location of the RailCorp distribution system electricity works are held by the RailCorp Plan room on Level 1, 477 Pitt St, Sydney. Access to those maps may be gained on application to the Officer in Charge of the Plan room. Some maps are also held locally at each District office and access to these maps can be arranged through the respective District office. With

draw

n - f

or re

fere

nce

only

Page 13: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 11 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

Most of these maps have been digitised and can be downloaded from RailCorp Intranet and printed as hard copy by RailCorp workers with access to this Intranet.

RailCorp is in the process of digitising all geographic information concerning its distribution system. Currently, all information concerning the geographic location of RailCorp’s high voltage aerial lines and cables has been digitised and this information is available to both RailCorp and non-RailCorp personnel. The extent of use of this GIS information varies from RailCorp District to District where reliance is still being placed in the former documents in some cases.

Cable search information for high voltage underground cables is generally obtained, on a fee for service basis, from the relevant District office for the area concerned. RailCorp is also registered with the “Dial Before You Dig” service.

A description of the RailCorp distribution system is contained in publication EP 00 00 00 01 TI RailCorp Electrical System General Description.

5.2 Design and Construction Standards RailCorp Distribution Network design and construction standards are developed, implemented and configuration managed in accordance with a suite of Configuration Standards located on the Engineering Intranet. The relevant Electrical Standards are contained within the following categories published on the RailCorp website as “EP” standards.

5.2.1 Aerial Lines and Cables • Transmission Lines • HV AC and Traction Cables • Surge Protection • Earthing, Bonding and Electrolysis • Fault Protection

5.2.2 Substations • Earthing, Bonding and Electrolysis • Fault Protection • System Substations • AC Auxiliary supplies • Distribution Transformers • Power Transformers • Surge Protection • System Requirements • SCADA

5.2.3 Low Voltage Distribution Assets • Earthing, Bonding and Electrolysis • Low Voltage

5.3 Maintenance Plans and Standards RailCorp Distribution Network maintenance plans are developed, implemented and configuration managed in accordance with the standard EP 00 00 00 00 MP Technical Maintenance Plan. With

draw

n - f

or re

fere

nce

only

Page 14: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 12 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

Technical Maintenance Plans (TMP’s) for key distribution and low voltage assets and have been split into distinct categories:

• High Voltage Aerial Lines • Protective Earthing, Bonding and Electrolysis Mitigation • Distribution Transformers • Low Voltage Distribution • Fault Protection • High Voltage AC and Traction Cables • Low Voltage Installations • Distribution Substations • System Substations

RailCorp maintenance standards for electrical workers safety equipment are contained in the Electrical Network Safety Rules (ENSR) or published as “EP 15” Standards on the Engineering Internet. Such documents comply with the ISSC 14 Guide to electrical workers’ safety equipment.

RailCorp carries out audits in accordance with documents SMS-19-SP-2079 Safety Audits and SMS-19-OP-2122 Conduct Safety Audits to ensure that the District’s compliance and verification to maintenance plans and standards.

5.4 Operation and Work Procedures Within the operating environment, Network documentation such as the Network Rules and Network Procedures is used to manage railway specific hazards. Network documentation is applicable throughout the organisation, and to contractors and operators accessing the RailCorp Network. These documents are managed in accordance with publication SMS-12-SP-2072 Operational Standards.

Standards covering Operation and Work Procedures on RailCorp’s Distribution Network are primarily contained in the Electrical Network Safety Rules (ENSR) Manual. This manual is a subset of RailCorp’s Safety Management System (SMS) documents that specifically provide electrical work instructions for those persons who are authorised to work on or near RailCorp Electrical Distribution System. These procedures include, for example, procedures for work on or near both de-energised and live electricity works.

RailCorp SMS also includes a number of such work procedure documents that are not included in ENSR because these documents also have relevance to non-Authorised persons who are working around RailCorp’s Electrical Distribution System.

5.4.1 Additional Operation Procedures Additional Operation Procedures are contained in the following hard copy document held at the Electrical Operating Centre and at the office of the Chief Engineer Electrical:

RailCorp, Infrastructure Operation, Electrical Operating Centre – Trouble Instructions.

5.4.2 Reporting Incidents and Unsafe Conditions Incidents and unsafe condition reporting is implemented in accordance with publication SMS-17-SP-2077 Incident Reporting and Investigation. Incident reports from workplaces and the field are captured in at least one of five RailCorp systems. Electrical network, signalling and civil incidents are captured in the IFMS system (FPe (SKMS) database).

Safety incidents are classified according to their severity, or potential severity, from Level 1 (major) to Level 5 (minor) and initiate the appropriate action. With

draw

n - f

or re

fere

nce

only

Page 15: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 13 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

Incident reports to the NSW Trade and Investment are in accordance with the Significant Electricity Network Incident (SENI) guidelines.

Incident reports to NSW Maritime for crossings of NSW navigable waters are in accordance with the Protocol for Incident Reporting and Analysis

5.5 Engineering Records, Drawings and Maps

5.5.1 Electricity Works Drawings and maps associated with the RailCorp distribution system electricity works are managed by RailCorp GIS and CAD Unit, Professional Services Division of Engineering and Projects Group, and include:

• Layouts, • Cross sections, • Design arrangements, and • Cable Routes.

RailCorp GIS and CAD Unit has digitised all geographic information concerning its distribution system. Currently, all digitised information concerning the geographic location of RailCorp’s high voltage lines and cables is located in the GIS database.

RailCorp District Offices maintain records relating to asset condition and reliability. RailCorp audits those records in accordance with the documents SMS-19-SP-2079 Safety Audits and SMS-19-OP-2122 Conduct Safety Audits.

The Asset Information and Register Unit, Asset Planning and Performance Division of Asset Operations Group maintain records on registered files associated with assets owned by RailCorp.

5.5.2 Operating Diagrams Diagrams associated with the operation of the RailCorp distribution system are maintained by RailCorp GIS and CAD Unit. The relevant diagrams are contained within the following categories on the Electrical Operating Diagrams (EOD) section of the Engineering Intranet:

• 1500 Volt Sectioning Diagrams • AC Substation Diagrams • DC Substation Diagrams • 11kV System Diagrams • 33, 66 and 132kV System Diagrams • Reticulation and 2kV Diagrams

5.5.3 Crossings of NSW Navigable Waters Records of crossings of NSW navigable waters are managed by RailCorp GIS and CAD Unit, Professional Services Division of Engineering and Projects Group in accordance with the Protocol for Exchange of GIS Data

With

draw

n - f

or re

fere

nce

only

Page 16: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 14 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

6 Analysis Of Hazardous Events RailCorp has a Safety Management System (SMS) for managing the safety risk from hazardous events. SMS-07-SP-2089 Manage Operational Safety Risk is the relevant system requirement from the SMS. This document contains the key requirement to manage RailCorp operational safety risks to a level that is either broadly acceptable or tolerable and So Far As Is Reasonably Practicable.

Knowledge about safety risk is captured and managed in the Safety Risk Register which is a structured representation of the causes and consequences of potential hazards, referred to as Specific Hazards, arising from the operation and maintenance of the RailCorp railway. The Safety Risk Register enables the safety risk profile to passengers, employees and members of the public associated with RailCorp’s operations to be determined. The controls designed to reduce the risk from these Specific Hazards have been identified and reside in the structure of the Safety Risk Register. Responsibility for managing the effective implementation and maintenance of these controls has been assigned to Control Owners and is delegated to Control Implementers. The responsibility for managing the Safety Risk Register itself resides with Risk Division.

The collaboration between RailCorp Electrical Engineers and Risk Division to identify and incorporate the hazards, causes, consequences and controls associated with RailCorp’s electrical distribution network into the Safety Risk Register is complete. An Electrical Hazard Register now exists as part of RailCorp’s Safety Risk Register within its risk management tool First Priority Enterprise and will be used as the foundation for future risk management activities associated with electrical distribution.

7 Emergency Procedures The procedures for the management of emergencies, including verification of effectiveness, are outlined in the “Incident Management and Emergency Response” section of RailCorp SMS which includes, in particular, the following publications :–

SMS-15-OP-2132 - Develop and Implement Site Incident Management Plan SMS-15-SP-2075 - Emergency Preparedness SMS-15-GD-0638 - Incident Response Guide The Incident Response Guide standardises the approach adopted by RailCorp for all types of emergencies, including those associated with the electrical network.

The manual requires each district to have detailed procedures for electrical incidents tailored for their work locations.

8 Asset Management Strategies All RailCorp assets, including those associated with the Electrical Distribution Network, are managed in accordance with publication SMS-04-SP-2064 Asset Lifecycle Management.

This publication sets out the requirements for the specification and management of RailCorp assets that could impact safety of, or safety upon, the RailCorp Network. RailCorp complies with the Code of Practice – Electricity transmission and distribution asset management requirements and applies systems engineering and life cycle science to decisions relating to its assets.

RailCorp holds insurance covering legal liability to third parties for personal injury and/or property damage arising out of the business and/or products as a result of an occurrence. With

draw

n - f

or re

fere

nce

only

Page 17: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 15 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

9 Reports to the Director-General RailCorp reports to the Director General of the NSW Trade and Investment in relation to maintenance, reliability and safety aspects of the RailCorp distribution system in accordance with the accepted protocols and formats as produced by the Ministry. These reports are summarised in the following table.

Schedule of Reports to the Director-General Report Report Prepared in Accordance With Due Date

AS/NZS ISO 9001 Certificate

Third party endorsed Quality Management System certificate Annually

Audit Certificate Electricity Supply (Safety and Network Management) Regulation 2008 Part 4 Section 17

Upon issue and then Tri-annually

Electrical Network Performance Report

Electricity Supply (Safety and Network Management) Regulation 2008 Part 5 Section 21

As required by Director General

Further Reports to be submitted to Director-General

Electricity Supply (Safety and Network Management) Regulation 2008 Part 5 Section 22

As required by Director General

SENI Reports SENI Reporting Guidelines As required

Table 1 - Schedule of Reports to the Director-General

RailCorp also reports to the NSW Roads and Maritime Services for crossings associated with NSW navigable waters as follows.

Schedule of Reports to NSW Road and Maritime Services Report Report Prepared in Accordance With Due Date

Annual Report Contained as part of the Electrical Network Performance Report Annually

Incident Reporting Protocol for Incident Reporting and Analysis As required

Table 2 - Schedule of Reports to NSW Road and Maritime Services

With

draw

n - f

or re

fere

nce

only

Page 18: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 16 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

10 Standards and Codes

10.1 RailCorp Electrical publications The standards which are published by the Chief Engineer Electrical and which RailCorp conforms to for the design, installation, operation and maintenance of its distribution system, are listed in Appendix A.

10.2 Other RailCorp publications

10.2.1 Electrical Network Safety Rules (ENSR) The ENSR Manual is part of RailCorp’s Safety Management System (SMS) which is published by RailCorp’s Safety and Environment Group.

RailCorp conforms to all SMS documents. The ENSR Manual documents applicable to the design, installation, operation and maintenance of its distribution system, are listed in Appendix B.

10.2.2 Other SMS Documents Other SMS documents outside of the ENSR Manual which are applicable to the design, installation, operation and maintenance of RailCorp distribution system, are included in RailCorp’s SMS system which is structured as described in document SMS-01-SD-2000 Safety Management System.

For example,

• Element 11 Training and Competence includes guide SMS-11-GD-0244 Personnel Certifications – Electrical Authorisations.

• Element 6 Work Health & Safety includes guide SMS-06-GD-0268 Working around Electrical Equipment.

10.3 Codes of Practice RailCorp has incorporated the Codes of Practice listed in Section 3 of each Chapter of the Network Management Plan in the design, installation, operation and maintenance of its distribution system; except as indicated in Section 10.4.

10.4 Departures from Codes of Practice

10.4.1 Service and Installation Rules RailCorp departs from this code in the manner specified in Section 8 of document EP 95 00 30 03 SP RailCorp Network Management Plan – Chapter 2 - Customer Installation Safety.

With

draw

n - f

or re

fere

nce

only

Page 19: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 17 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

10.4.2 Contestable works This document does not comply with the Code of Practice Contestable Works in that RailCorp does not have an accreditation system for providers of contestable works on its distribution system.

The primary function of the RailCorp distribution system is the supply of electricity for electric traction and for signalling and the risks associated with the connection of installation work in RailCorp DC traction area are considered to be best managed at this time by limiting the works to be carried out only by RailCorp Authorised staff. This is primarily due to the risk of DC traction return and fault current returning to RailCorp Traction Substations via neutral conductors and earthing systems instead of the rails. This risk is increased with the use of the Multiple Earthed Neutral (MEN) System of Earthing (See AS/NZS 3000:2007 Fig 5.1) on installations in RailCorp DC Traction area. RailCorp distribution system earthing design is specifically configured to minimise the risk of this occurring and RailCorp Authorised staff are specifically trained in these unique requirements.

Accreditation may be considered in individual cases, for instance a large project, for which accreditation requirements will be covered by a contract specification.

The small volume of connection work, and the aforementioned risks, renders the development of an accreditation system that encourages numerous service providers technically and commercially inappropriate at this time.

10.4.3 Electricity Service Standards The RailCorp electrical network has interfaces with three other Distributors’ HV networks. These HV connections supply all of the energy to the RailCorp system. Two of the electrical distributors are Ausgrid and Endeavour Energy. The third organisation is TransGrid’s with a connection to their HV network at Wallerawang. RailCorp will continue to purchase its bulk energy from the abovementioned licensed network service providers.

Proportion of electricity end usage for the RailCorp network is generally as follows:

• 1500V DC Traction Supply to Trains – 82% • Signals & other rail critical Loads – 3% • Railway Stations – 10% (mainly RailCorp with some private tenant shops) • RailCorp Workshops – 5% • Others – 1%

The majority of the above supplies (traction, railway stations, signals, offices, and workshops) are not individually metered.

On some railway stations there are tenant customers (kiosks, small newsagencies etc) that derive their electricity from the railway station supply. RailCorp separately meters and bills these customers. These customers are generally connected to the RailCorp electricity network as a matter of historical convenience and ease of connection. All these customers are covered by a standard RailCorp customer connection contract.

RailCorp will not be implementing this code for these customers. The small number of customers (at present 261) and the unique nature of our network render implementing this code impracticable.

With

draw

n - f

or re

fere

nce

only

Page 20: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 18 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

11 Managing of persons working on or near RailCorp Electricity Network

11.1 Training RailCorp ensures that personnel carrying out work on the RailCorp distribution system have been trained in accordance with the requirements of publication SMS-11-SP-2011 Training and Competence. This includes work which requires specific electrical authorisations as defined in publication SMS-11-GD-0244 Personnel Certifications – Electrical Authorisations. RailCorp conducts audits on the Districts training records in accordance with documents SMS-19-SP-2079 Safety Audit and SMS-19-OP-2122 Conduct Safety Audits.

As a guide a training/competencies matrix has been developed to support the industry publication EA 18 Guide to the Training of Personnel Working on or near Electricity Works and is attached as Appendix C.

11.2 Authorisation The types of work on the RailCorp distribution system for which electrical authorisation is required are specified in document SMS-11-GD-0244 Personnel Certifications – Electrical Authorisations.

The responsibility for granting of authorisation rests primarily with RailCorp’s Chief Engineer, Electrical (CEE) of the Chief Engineers Division. However the CEE may delegate a person to certify persons as defined in section 6 of SMS-11-GD-0244 Personnel Certifications – Electrical Authorisations. Accordingly, RailCorp’s System Control Engineer, Electrical System Control, also has responsibility for certifying competence in some requirements to be met for electrical authorisation. RailCorp Learning & Development Division of the Human Resources Group also has responsibility for authorising Accredited Electrical Permit Holders.

Access to and operation of electrical equipment comprising RailCorp’s distribution system is restricted by the use of a range of RailCorp standard locks as described in document SMS-06-EN-0555 Locking Systems for Electrical Equipment. Upon Authorisation to perform work on RailCorp distribution system, persons so authorised are issued with keys appropriate to the duties covered by such authorisation.

With

draw

n - f

or re

fere

nce

only

Page 21: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 19 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

Appendix A RailCorp Electrical Publications EP 00 00 00 01 TI RailCorp Electrical System General Description

EP 00 00 00 02 SP Electrical Technical Maintenance Coding System

EP 00 00 00 07 SP Requirements for Handling and Disposal of Material containing PCB

EP 00 00 00 12 SP Electrical Power Equipment - Integrated Support Requirements

EP 00 00 00 13 SP Electrical Power Equipment - Design Ranges of Ambient Conditions

EP 00 00 00 15 SP Common Requirements for Electrical Power Equipment

EP 00 00 00 16 SP Electrical Power System Signage

EP 00 00 00 17 SP Electrical Waiver Management

EP 01 00 00 01 SP 33kV AC Indoor Switchgear- Non-Withdrawable

EP 01 00 00 02 SP 11kV AC Indoor Switchgear SP

EP 01 00 00 03 SP 11kV AC Switchgear RMU Suitable For Indoor and Kiosk Installation

EP 01 00 00 04 SP 33kV Outdoor Live Tank Circuit Breaker and Post Type CTs

EP 01 00 00 05 SP 33kV Outdoor Dead Tank Circuit Breaker Assembly

EP 01 00 00 06 SP Replacement of 11kV Circuit Breaker (D4XD) Trucks in South Wales Switchgear

EP 02 00 00 01 SP Transformer Loss Evaluation

EP 02 10 00 01 SP Power Transformer - 33-11kV

EP 02 44 00 01 SP 11kV Voltage Regulator

EP 05 00 00 01 SP Substation Auxiliary Transformer from Rectifier Transformer Secondary

EP 06 01 00 01 SP System Substation Battery

EP 10 00 00 04 SP Transmission Line Easement Conditions

EP 10 00 00 05 SP Aerial Line Current Ratings and Standard Conductors

EP 10 01 00 01 SP Wood Pole Serviceability Policy

EP 10 01 00 02 SP Aerial Line Maintenance Standards

EP 10 01 00 03 SP Aerial Line Base Safety and Operating Standards

EP 10 01 00 05 SP Requirements for Electric Aerials Crossing RailCorp Infrastructure

EP 10 01 00 06 SP Aerial Line Standard for Design and Construction

EP 10 01 00 07 SP Timber Poles

EP 11 03 00 02 SP Electrical SCADA System Remote Terminal Unit Specification

EP 11 00 00 07 SP Design Technical Reviews for Electrical SCADA Equipment

EP 12 00 00 01 SP High Voltage and 1500V System Earthing References and Definitions

EP 12 00 00 02 SP Low Voltage Distribution and Installations Earthing References and Definitions

EP 12 10 00 10 SP System Substation Earthing

EP 12 10 00 11 SP Distribution Substation Earthing

EP 12 10 00 12 SP Transmission Line and Cable Earthing

EP 12 10 00 20 SP Low Voltage Distribution Earthing

EP 12 10 00 21 SP Low Voltage Installations EarthingWith

draw

n - f

or re

fere

nce

only

Page 22: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 20 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

EP 12 10 00 22 SP Buildings and Structures Under Overhead Lines

EP 12 30 00 01 SP Electrolysis From Stray DC Current

EP 15 00 00 01 SP HV AC Voltage Detector (nominal Voltage of 11kV – 66kV)

EP 15 00 00 04 SP Pole Top Rescue kits

EP 15 00 00 05 SP Substation Electrically Safe Work Area Demarcation Taping Equipment

EP 16 00 00 01 SP Pole Mounted Distribution Transformer

EP 16 00 00 02 SP Outdoor Ground Type Distribution Transformer

EP 17 00 00 06 SP Installation Inspections

EP 17 00 00 11 SP Low Voltage Isolating Transformers

EP 17 00 00 12 SP Demarcation of RailCorp Low Voltage Distribution System

EP 19 00 00 02 SP Protection System Requirements for High Voltage Network

EP 19 00 00 03 SP Commissioning of Translay Pilot Wire Protection Scheme

EP 20 00 00 03 SP Above Ground Cable Installation Systems - Selection Guide

EP 20 00 00 20 SP Testing of High Voltage Cables

EP 20 00 03 01 SP Requirements for Cable Polymeric Terminations and Joints

EP 20 00 04 01 SP Cable Route Selection Guide

EP 20 00 04 02 SP Underground Installation Configurations for High Voltage and 1500 Vdc Cables

EP 20 00 04 04 SP Ground Entry Arrangements

EP 20 00 04 05 SP Cable Pits

EP 20 00 04 06 SP Underground Cable - Location Recording

EP 20 10 00 02 SP High Voltage Cable Selection Guide

EP 21 00 00 01 SP Insulation Co-ordination and Surge Arrester Selection

EP 23 10 00 01 SP LV Tunnel Services Board

EP 23 10 30 01 SP Tunnel Emergency Light Fittings

EP 90 10 00 01 SP Electrical Phase Relationships

EP 90 10 00 02 SP Standard Voltage Tolerances

EP 90 30 00 01 SI Polarity of AC Signalling Supplies

EP 95 00 00 12 SI Advertising of New Work

EP 95 00 30 03 SP Customer Installation Safety

EP 95 00 30 04 SP Public Electrical Safety Awareness

EP 95 00 30 05 SP Bush Fire Risk Management

EP 95 00 30 06 SP Network Safety and Reliability (this document)

EP 95 10 00 06 SP Requirements for Portable Earthing Equipment for the High Voltage System

EP 99 00 00 01 SP Substations Minimum Construction Standards

EP 99 00 00 02 SP System Substation Commissioning Tests

EP 99 00 00 04 SP Substations - Base Safety and Operating Standards

EP 99 00 00 07 SP Substation FencingWith

draw

n - f

or re

fere

nce

only

Page 23: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 21 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

EP 99 00 00 08 SP Substations Fire Protection and Detection Standard

Technical Maintenance Plan

EP 00 0 00 00 MP Electrical Technical Maintenance Plan

EP01 HV AC SWITCHGEAR

EP02 POWER TRANSFORMERS & REGULATORS

EP05 AC AUXILIARY POWER SUPPLIES

EP06 AUXILIARY SERVICES

EP10 HIGH VOLTAGE AERIAL LINES

EP11 SCADA

EP12 PROTECTIVE EARTHING, BONDING AND ELECTROLYSIS MITIGATION

EP16 DISTRIBUTION TRANSFORMERS

EP17 LOW VOLTAGE DISTRIBUTION

EP19 FAULT PROTECTION

EP20 HIGH VOLTAGE AC AND TRACTION CABLES

EP22 VOLTAGE TRANSFORMERS AND CURRENT TRANSFORMERS

EP23 LOW VOLTAGE INSTALLATIONS

EP97 DISTRIBUTION SUBSTATIONS

EP99 SYSTEM SUBSTATIONS

With

draw

n - f

or re

fere

nce

only

Page 24: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 22 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

Appendix B Other RailCorp Publications Electrical Network Safety Rules (ENSR) Manual

INTRODUCTION

SMS-06-EN-0550 Electrical Network Safety Rules

Part A General

SMS-06-EN-0551 Definitions Conventions for Electrical Safety

SMS-06-EN-0552 General Requirements for Electrical Work

SMS-06-EN-0553 Electrical Hazards Warnings

SMS-06-EN-0554 Pre-work Hazard Assessment for Work on Poles with Live Exp Equip

SMS-06-EN-0555 Locking Systems for Electrical Equipment

Insulated Sticks, Tools and Equipment for Electrical Work - Inspection, SMS-06-EN-0556 Testing, Care and Maintenance.

SMS-06-EN-0557 Inspection and Testing of Fixed Electrical Equipment

SMS-06-EN-0558 Pole Top Rescue Kits

SMS-06-EN-0599 DANGER Tags for Electrical Equipment

SMS-06-EN-0668 Electrical Operational Communication and Records

Part B High Voltage

SMS-06-EN-0559 Description and Labelling of the HV Distribution System

SMS-06-EN-0560 Removal and Restoration of High Voltage Supply

SMS-06-EN-0561 Working High Voltage Instruction

SMS-06-EN-0562 High Voltage Operating Procedures

SMS-06-EN-0563 Earthing High Voltage Equipment Using Portable Earthing Equipment

Inspection and Care of Portable Earthing Equipment for the High Voltage SMS-06-EN-0564 System

Part D Low Voltage

SMS-06-EN-0573 Description and Labelling of the LV Distribution System

SMS-06-EN-0574 Isolation and Energisation of Low Voltage Equipment

SMS-06-EN-0575 Work on the Low Voltage Distribution System

Part E Permits

SMS-06-EN-0577 Electrical Permits

SMS-06-EN-0598 Electrical Permit to Work

SMS-06-EN-0583 Substation Access Permits

SMS-06-EN-0584 Low Voltage Access Permits With

draw

n - f

or re

fere

nce

only

Page 25: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 23 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

SMS-06-EN-0585 Operating Agreements

Part F Live Work

SMS-06-EN-0590 Work on Live Low Voltage Equipment

ENSR Comment Form

SMS-06-FM-0712 ENSR Comment Form

With

draw

n - f

or re

fere

nce

only

Page 26: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 24 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

Appendix C Training Matrix FUNCTIONS / ACTIVITIES COMPETENCIES

App

ly re

susc

itatio

n te

chni

ques

Rel

ease

a P

erso

n fro

m L

ive

Ele

ctric

al A

ppar

atus

Res

cue

a pe

rson

from

a p

ole,

stru

ctur

e or

EW

P

Wor

k al

oft

Cer

tifie

d as

hav

ing

pass

ed a

n ap

prov

ed tr

aini

ng c

ours

e fo

r spe

cifie

d fu

nctio

n/ac

tivity

Aut

horis

ed b

y th

e S

yste

m C

ontro

l Eng

inee

r

Aut

horis

ed b

y th

e C

hief

Eng

inee

r, E

lect

rical

Sys

tem

s

Hol

ds a

spe

cifie

d ce

rtific

ate

III q

ualif

icat

ion

Hol

ds a

qua

lifie

d S

uper

viso

r Cer

tific

ate

(Ele

ctric

ian)

or

Con

tract

or L

icen

ce (E

lect

rical

- Q

)

Hol

ds P

ole

Exa

min

ers

Cer

tific

ate

App

ropr

iate

kno

wle

dge

of R

ailC

orp'

s E

lect

rical

Saf

ety

Man

ual

HIGH VOLTAGE OVERHEAD LINES

Work under supervision on high voltage overhead lines √ √ √ √ √

Work without supervision on high voltage overhead lines √ √ √ √ √ √ √ √ Operate high voltage field switches, √ √ √ √ √ √ √ √ Isolate, Test Dead and Earth Transmission Lines √ √ √ √ √ √ √ √

Issue and retrieve Permits and Operating Agreements for work on high voltage overhead lines and associated cables outside substations, √ √ √ Manage WHVI √ √ √ Approve a "WHVI". √ √ √ Pole inspection √ √ √

With

draw

n - f

or re

fere

nce

only

Page 27: Technical Note - TN 052: 2016 - Transport for NSW · EP 95 00 30 06 SP . RailCorp Network Management Plan Chapter 1 Network Safety ... are referred in other ASA standards and any

RailCorp Engineering Standard — Electrical Railcorp Network Management Plan Chapter 1 - Network Safety and Reliability EP 95 00 30 06 SP

© RailCorp Page 25 of 25 Issued May 2013 UNCONTROLLED WHEN PRINTED Version 3.4

FUNCTIONS / ACTIVITIES COMPETENCIES

App

ly re

susc

itatio

n te

chni

ques

Rel

ease

a P

erso

n fro

m L

ive

Ele

ctric

al A

ppar

atus

Res

cue

a pe

rson

from

a p

ole,

stru

ctur

e or

EW

P

Wor

k al

oft

Cer

tifie

d as

hav

ing

pass

ed a

n ap

prov

ed tr

aini

ng c

ours

e fo

r sp

ecifi

ed fu

nctio

n/ac

tivity

Aut

horis

ed b

y th

e S

yste

m C

ontro

l Eng

inee

r

Aut

horis

ed b

y th

e C

hief

Eng

inee

r, E

lect

rical

Sys

tem

s

Hol

ds a

spe

cifie

d ce

rtific

ate

III q

ualif

icat

ion

Hol

ds a

qua

lifie

d S

uper

viso

r Cer

tific

ate

(Ele

ctric

ian)

or

Con

tract

or L

icen

ce (E

lect

rical

- Q

)

Hol

ds P

ole

Exa

min

ers

Cer

tific

ate

App

ropr

iate

kno

wle

dge

of R

ailC

orp'

s E

lect

rical

Saf

ety

Man

ual

LOW VOLTAGE EQUIPMENT

Work under supervision on low voltage overhead lines √ √ √ √ √

Work without supervision on low voltage overhead lines √ √ √ √ √ √ √ Work under supervision on low voltage equipment √ √ √ √ √ Work without supervision on low voltage equipment √ √ √ √ √ √ √ √ √

Issue and retrieve Permits for work on low voltage overhead lines and associated cables outside substations √ √ √ SUBSTATIONS Work under supervision on Substation equipment √ √ √ √ √ Work without supervision on Substation equipment √ √ √ √ √ √ √ √ Operating work inside a substation √ √ √ √ √ √ √ √ √

Issue and retrieve Permits for work on substation equipment √ √ √ Entry into a Substation √ √ √ CABLES Undertake specific cable jointing work √ √ √ √ √ √ √ GENERAL Work aloft in the vicinity of electrical apparatus √ √ √ √ √ Holding a permit √ √ √ Receiving Operating Agreement √ √ √

With

draw

n - f

or re

fere

nce

only