64
1 TECOBLOCK® as an alternative building solution? Chapter 1: Introduction 1.1) Background TECOBLOCK® is a blocking concept designed in Australia, which entails a revolutionary way of building with blocks. The system is being introduced into South Africa and TECOBLOCK® Africa (Pty)Ltd has been founded to run the project here. The blocking system consists of hollow blocks (400X250X100mm), each containing four vertical core holes. The system is either dry stacked or glued together with a bonding compound. Plastic locators are used to align the blocks in a line as they have being stacked. After every fourth course of blocks, the plumbness of the blocks is re- aligned through an insertion of a steel strap. These straps lie horizontally between courses and are secured by means of nails. This is done with the use of a nail gun. A special cement based render is used to put the final finish on to the wall. This also adds additional water proofing properties to the system as it is made up of special hydrophobic chemicals. Every fourth vertical core, unless otherwise stated by the engineer, is filled with concrete slurry, which may or may not have reinforcement bars in it, depending on the load the wall experiences. These specified cores are anchored down by

TECOBLOCK® as an alternative building solution?

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

1

TECOBLOCK® as an alternative

building solution?

Chapter 1:

Introduction

1.1) Background

TECOBLOCK® is a blocking concept designed in Australia, which

entails a revolutionary way of building with blocks. The system is

being introduced into South Africa and TECOBLOCK® Africa

(Pty)Ltd has been founded to run the project here.

The blocking system consists of hollow blocks (400X250X100mm),

each containing four vertical core holes. The system is either dry

stacked or glued together with a bonding compound. Plastic locators

are used to align the blocks in a line as they have being stacked.

After every fourth course of blocks, the plumbness of the blocks is re-

aligned through an insertion of a steel strap. These straps lie

horizontally between courses and are secured by means of nails.

This is done with the use of a nail gun. A special cement based

render is used to put the final finish on to the wall. This also adds

additional water proofing properties to the system as it is made up of

special hydrophobic chemicals. Every fourth vertical core, unless

otherwise stated by the engineer, is filled with concrete slurry, which

may or may not have reinforcement bars in it, depending on the load

the wall experiences. These specified cores are anchored down by

2

Y10 rebar, which are drilled into the raft foundation below. This

provides for a stable, strong and reinforced wall that can withstand

both vertical and horizontal forces (as depicted in Figure 1 below).

Figure 1 – 3D computer imagery of a TECOBLOCK® wall

Source: TECOBLOCK® Australia (Pty)Ltd

The concept provides for a fast, accurate and complete building

system that provides numerous benefits such as easier cutting and

laying of the blocks and the placement of services down the unused

voids. The system also facilitates carrying the blocks due to its

dimensions and light weight.

In July of 2008 I suggested the building of a real BNG house (figure

2-4) (previously known as RDP). The company in Australia accepted

the proposal and invited the author of this dissertation to Melbourne,

in order to construct a house of such a nature. This was a test to see

if the concept could prove itself for the South African market in terms

of:

• Speed of building in comparison to conventional methods

• Structural integrity

• Ease of construction/erecting of block work

3

• Vertical plumbness and Horizontal leveling of the blockwork

These aspects will be discussed in detail in Chapter 2 together with

the success/failure of each point.

The blocks are stacked at ¼ intervals over the next block. This allows

the overlapping interval on corners to work out, without having to cut

the blocks. (This can be seen in Figures 2-4)

Figure 2 – Constructing a wall with TECOBLOCK® blocks

Source: Own

Figure3 – TECOBLOCK® wall

Source: Own

Figure 4 - TECOBLOCK® BNG House

4

Source: Own

1.2) Statement of main problem:

Will the TECOBLOCK® concept/system be feasible and viable in

South Africa?

1.3) Statement of sub problems:

1) Is TECOBLOCK® cost competitive in the local market?

2) Will TECOBLOCK® be accepted in the market by

architects, contractors, engineers, the government and the

end-users?

3) Can all technical issues be addressed to make

TECOBLOCK® work in South Africa?

4) What are the logistical problems regarding the

manufacturing of TECOBLOCK® in South Africa?

1.4) Hypothesis of main problem:

The TECOBLOCK® concept is likely to work in South Africa due to

its exceptionally practical design and the various benefits it has to

offer (including the possibility of involving township residents in the

construction of their own houses).

5

1.5) Hypothesis of sub problems:

1) The cost competitive aspect of the system is holding the

concept back from flourishing in the market. There is high

confidence level though, that with further research into the

compositional make-up the block, the system will succeed

in the market.

2) The deviation from the conventional method is not that

much; therefore an educated guess would be that the

system will be accepted in the market place.

3) Through a thorough business plan and other professional

means of analysing the system, there is a good assurance

that all technical issues can be sorted out.

4) By taking the manufacturing of the blocks close to the

production of the raw materials, all logistical problems can

be sorted out.

1.6) Delimitations

The limitation of this analysis will only extend up to the actual viability

and feasibility of the concept and will not include company aspects

such as BBBEE (Broad Based Black Economic Empowerment) and

its effects on the success of the product in South Africa.

This viability analysis/feasibility study will include the characteristic of

cost acceptability in the market place compared to conventional

building methods, and pure analysing of the system is actually going

to work and be accepted in South Africa.

6

1.7) Definitions of Terms

• Viability analysis and feasibility study will be used

interchangeable

• TECOBLOCK®: Is the concept/system as explained in

1.1

1.8) Assumptions

It will be assumed that a reasonable cost can be reached in using a

variety of different materials and technologies in producing a cost

effective mix for the block. If this cannot be reached then the concept

will fail.

1.9) Importance of the study

The importance of this study is to show both the practical reader and

the academic audience a top of the range new technology which has

been devised together with the affectivity thereof. The reader will

acquire insight into the blocking and brick industry together with

relevant flaws attached to the sector.

1.10) Research Method:

1) Conduct interviews with key interested and affected

parties:

• Architects

• Engineers

• Contractors

7

• End-users

• Government

2) Conduct laboratory experiments to determine the most

cost-effective mix

3) Look at case studies on similar concepts/systems and

what the outcomes of those were.

8

Chapter 2:

Is TECOBLOCK® cost competitive in the local

market?

2.1) Concise Overview:

For the purpose of testing the relevant hypothesis pertaining to this

study a bench mark needs to be set. This benchmark is based on

studying and comparing conventional building blocks (in this case

MAXI Blocks) with the TECOBLOCK® system.

Theoretical Cost comparisons will be done between the

TECOBLOCK® walling system and a conventional MAXI Block

system. They will take into account the measurement of all direct and

indirect costs pertaining to the construction of a house.

A questionnaire is also used to ascertain what built environment

professionals i.e. architects, engineers, contractors and developers

think of the system in terms of time, cost and quality of the product.

2.2) Comparison, variables and fixed variables:

Cost comparisons will be done on a basis of a theoretical 200 unit

low cost housing development. All factors will be taken into account

including direct and indirect cost pertaining to the project. The area

for the project is set within the parameters of Gauteng, where,

according to the Department of Housing, the government subsidies

are R47000 for the super structure of a BNG (Breaking New Ground)

house.

9

The fixed variables will be the usage of a raft foundation and a single

layer block wall.

2.3) Investigation of conventional walling systems

versus existing alternative building methods and

relating them to TECOBLOCK®.

When considering the viability of alternative building methods one

has to keep in mind that a performance approach is the relevant

driver in innovative building solutions (Becker 2001) and this finding

can be linked to the cost, time and quality of a product.

However, although conventional building methods such as the MAXI

Block building system are relatively slow and labour intensive,they

have stood the test of time.

No other Agrément accredited alternative building solution has really

boomed in South Africa. This needs to be taken into consideration

when looking at the viability of TECOBLOCK® in South Africa on a

large scale.

2.4) The direct cost of the traditional MAXI Block Walling system

The direct costing of a wall consists of two elements, namely raw

material and labour to build the wall structure. In costing a specific

walling system, it is always easier to take all elements into

consideration and to then divide the total by the area of walling that

needs to be completed. This will equal a rate per metre squared,

which can then be used in comparing different systems.

10

2.4.1) Raw Material Prices and Quantities

All prices are excluding VAT and excluding delivery and are set for

May 2009. Prices were obtained from various building product

supplier companies in and around Pretoria. The bill of materials is for

the walling of a BNG house and prices are as follows:

Type of Material Price

MAXI Bricks (220x115x90) per 1000 bricks R1270

Cement 32.5N per bag R59.89

Building Sand per m³ R155.00

Plaster Sand per m³ R173.00

Brick Force per roll R35.80

Precast Concrete Lintol (100x1200mm) R25.95

DPC (Damp Proof Course) 225mm x 30m R66.25

Table 1 – MAXI brick wall components

Source: Own

A typical BNG house has a walling area of 92m². This is according to

a typical building plan for a 50m² BNG house, which was obtained

from the Ekhuruleni municipality.

For a walling area of 92m² the following quantities were obtained:

MAXI Bricks:

MAXI Brick (290x140x90mm) Quantity for

92m²

34 bricks per m² x 92 3128

Plus 10% waste factor 3441

Table 2 – MAXI brick quantity per m²

Source: Own

11

Mortar:

Table 3 – Mortar quantities

Source: www.afrisam.co.za/bricklayingguide

Cement Quantities:

Table 4 – Cement Quantities Source: www.afrisam.co.za/bricklayingguide

12

Mortar mix 1:5 cement:sand Quantity per m² of walling

Mortar: 1.87m³ / 100 x 34 0.64 m³ Cement: 3.6 bags / 1000 x 34 0.1224 bags Building Sand: 0.7m³ / 1000 x 34 0.0238 m³ Table 5 – Quantity of materials needed per m² of walling Source: Own Other Materials: Description: Quantity per

m² of walling Plaster Mortar 1 x 1 x 0.025 x 1.15 x 2 (15% waste factor and both sides)

0.0575 m³

Cement (plaster) 1:5 ratio 0.165 bags Plaster Sand 1:5 ratio 0.0575 / 6 x 5 0.04791 m³ Brick Force 2.5m Lintol 8 / 92m² 0.0869 Damp Proof Course 33m/ 92m² 0.3586m Table 6 - Quantity of other materials needed per m² of walling Source: Own Pricing of materials to build a plastered wall: Description: Price per m²

of walling MAXI Bricks: R1270 / 1000 x 34 R43.18 Cement: R59.89 x (0.1224bags + 0.165bags) R 17.21 Building Sand: R155.00 x 0.0238 R 3.69 Plaster Sand: R 173.00 x 0.04791 R 8.29 Brick Force: R 35.80 / 20 x 2.5 R 4.48 Lintols: R25.95 / 1.2 x 0.0869 R 1.88 DPC: R66. 25 / 30 x 0.3586 R 0,79 TOTAL MATERIAL COST R 79.52 /m² Table 7 – Material pricing per m² Source: Own

13

2.4.2) Labour and transport Items:

This total material cost depicts the cost of the materials for the

construction of a BNG house. Other elements such as transport for

materials and goods and labour for brickwork, plastering and chasing

of walls need to be added to come to a total direct construction cost.

The chasing work needs to be done for the installation of electrical

plug points and light switches. In this case five plug points and five

light switches would be needed. Light switches are set 1200mm and

plug points are set at 400mm above the finished floor level. This

would add up to some 16 metres of chasing work set at a ceiling

level of 2400mm.

According to Krucon Homes (Pty) Ltd (2009) such chasing and

patchwork is a tedious process and involves cutting the slots with an

angle grinder, placing and fixing the conduits and patching the

chased slots with a mesh reinforced plaster. The mesh is placed over

the chased slot and nailed into the wall. A plaster mix is then used to

fill the slot and is finished off like the rest of the surrounding wall. This

process is priced at an additional amount of R55.00/ metre.

2.4.3) Total direct building cost for a conventional wall:

Description: Price per m² of walling

Labour for brickwork R71.50 Labour for plastering (both sides) R46.00 Chasing work R55.00/m x 16m / 92m² R9.57 Transportation of goods to site 15% of material cost R11.93

14

Total Material cost R79.52 TOTAL WALLING COST (excluding Preliminaries & General)

R218.52/m²

Table 8 – Total direct MAXI brick walling cost per m² Source: Own 2.5) TECOBLOCK® wall costing 2.5.1) Raw Material Cost and Quantities Raw material price: Type of Material Price

TECOBLOCK (400 x 250 x 100mm) per 1000

blocks R8050.00

Block adhesive (20kg) R24.99

Metal strip (80 x 0.5 x 2400mm) R11.85

Render (20kg) R24.99

TECOBLOCK locators (1000) R200.00

Nails (1kg) R35.80

Precast Concrete Lintol (100x1200mm) R25.95

Table 9 – TECOBLOCK® material pricing Source: Own Quantities per m²

Description: Quantity per m² of walling

TECOBLOCK 10/m² 10 blocks TECOBOND adhesive 11.5m²/bag 0.087 bags TECOBLOCK locators 40 locators

15

Metal Strip 1.415m Render (both sides) 0.45 bags Lintol 8 / 92m² 0.0869 Table 10 – TECOBLOCK® quantities per m² Source: Own Material cost per m²: Description: Price per m²

of walling TECOBLOCK 10/m² R80.50 TECOBOND adhesive 11.5m²/bag R2.17 TECOBLOCK locators R8.00 Metal Strip R4.83/m R6.83 Render (+10% waste factor) R12.34 Lintol 8 / 92m² R1.88 TOTAL MATERIAL COST R111.72 Table 11 – TECOBLOCK® Material pricing per m² Source: Own

2.5.2) Total direct building cost for a TECOBLOCK®

wall:

Total brick work labour cost is a mere 40% compared to that of a

conventional MAXI brick building system, according to a case study

conducted in Melbourne, Australia. The amount of time it takes to

construct a 50m² BNG house was also tested during this case study,

as depicted below.

16

Figure 5 – BNG house built in Australia

Source: Own

The structure of this BNG house was constructed in one day.

Conventional MAXI brick systems would take in the region of about

2.5 to 3 days of construction to get to the same level, according to

the project manager at Group Five Construction.

The labour cost on rendering the walls decreases by 40% compared

to conventional plastering. This is due to the render only being

applied 3mm think compared to an average of 25mm on a normal

plastered wall. Furthermore, the application is mixed and sprayed on

by a mortar machine and not applied by hand compared to

conventional methods.

17

Total Cost for building the wall:

Description: Price per m² of walling

Labour for “block work” R71.50 x 40% R28.60 Labour for plastering (both sides) R46.00 x 60% R27.60 Transportation of goods to site 10% of material cost R11.17 Total Material cost R111.72 TOTAL WALLING COST (excluding Preliminaries & General)

R179.09/m²

Table 12 – Total direct cost for a TECOBLOCK® wall per m² Source: Own 2.6) Indirect Construction Costs:

2.6.1) Preliminaries and General

Preliminaries is found in the first section of the Bill of Quantities or

the specification in which management requirements for the contract

are set out (Finsen 1999: 46).

These items are based are on indirect construction costs for items or

services that are needed for the execution of the works. These are

referred to in Section A of the Master Bill of Quantities and include:

• Objective and Preparation – Documents, contractors site

representative, compliance with laws and regulations,

indemnities, insurances, securities etc.

• Execution: Site access, preparation for execution of works,

Contracts instructions, Setting out of the works

• Temporary Plant and Equipment: Concrete mixer, TLB,

pick-up, scaffolding, wheel burrows, shovels/spades, mortar

machine etc

18

• Completion: Practical completion, works completion, final

completion etc.

According to the ASAQS Model Bills of Quantities, the preliminary

sections of items are either fixed, variable or time related costs. In

order to compare a conventional brick system with a TECOBLOCK®

system, only the time related items are taken into account. All other

items that fall under variable and fixed groupings, are not applicable,

as they are set for the execution of the work and are usually coupled

to the value of the work, such as insurance or other basic items such

as setting out of work.

These time related items of the preliminaries are of substantial

importance as they can have a serious impact on the final

construction value of a project, depending on the duration of the

execution of the work.

2.6.2) Escalation on materials

Every longer building contract is subject to escalation from an initial

contract sum to a final contract value over the duration of the

contract. This is known as CPAP – Contractors Price Adjustment

Provision, whereby prices are escalated on a monthly basis

according to the Haylett price indices table set forward by Statistics

South Africa. According to these industry indices, escalated amounts

are calculated and the contractor has the right to claim them in every

interim payment.

This makes time of the essence in every building contract for the

client, as the longer the project takes the more the contract value will

19

increase.

2.6.3) Finance Costs

Compounded interest on money loaned from financial institutions is

also a time related cost. Employers, developers or owners bear the

burden of paying this interest on a monthly basis. Most buildings are

built for either selling them again for a profit, renting the property out

to tenants or running a business entity within the building. Overall,

most buildings are built for the purpose of regaining some kind of

return in order to pay back the money to the bank that was borrowed

initially for the financing of the construction of such a building. In

essence this leads to the incentive to finish the project in the shortest

period possible. This needs to be done in order to gain income from

the project as soon as possible and to start paying back the money

borrowed with the income of the project. Although this is not a factor

in the theoretical case study put forward in this paper, it will definitely

have an impact on developers and owner-builders that borrow money

from financial institutions for the execution of their construction

project endeavour.

2.7) Total cost comparison

In order to shed some light on this comparison between the

TECOBLOCK® system and the MAXI Block system, a theoretical

indirect cost comparison scenario needs to be created. In this

20

scenario a 300 unit BNG housing development is chosen with the

following fixed variables attached to the project:

• The project is based in the Tshwane metropolitan area

• The duration of the contract is estimated at 18 months, using

conventional MAXI bricks

• All foundations are raft foundations and are cast by ready mix

companies

• The company is of a medium size and the labour size is kept

constant

For the purpose of this comparison between conventional MAXI brick

construction and the TECOBLOCK® system certain assumption

need to be made based on the case study that was conducted in

Melbourne, Australia.

These would be:

• The duration of building the structure of a BNG house using

the TECOBLOCK® system is reduced to 30% in comparison

to building with conventional MAXI Bricks.

• Plastering time is reduced to 60% compared to conventional

plastering methods.

• All castings of concrete for raft foundations, construction of

roofs and finishing of houses stay constant as it will take the

same amount of time to complete in both instances.

To determine the project duration using the TECOBLOCK® system,

a project program has to be drawn up. This program is a simplified

version of a real project program, using the main summarised items

to establish the project duration of a conventional MAXIbrick system

compared to the TECOBLOCK® system and taking all above

21

mentioned variables into account. This project program was done in

consultation with HC Projects (Pty) Ltd.

Figure 6 – Building Program Source: Own in consultation with HC Projects (Pty) Ltd

The original project duration, which was planned for the 300 unit

BNG Construction Project, using conventional methods of brick-work

and plastering, was 18 months.

The aforementioned facts of the case study done in Melbourne,

Australia, were used. These were:

• TECOBLOCK® block work took 30% of the time compared to

that of conventional MAXI Brick work

• Plastering using the TECOBLOCK® walling system equalled

60% of the time compared to the conventional method of

plastering.

22

The fixed variables that were taken into account, namely

excavations, casting of raft foundations, erecting and assembly of

roofs and finishing, where those which would remain unchanged

throughout the duration of execution of the work.

In taking all these factors and proven assumptions into consideration,

the TECOBLOCK® system would theoretically reduce the project

duration from 18 months using the conventional MAXI brick system

to 10 months.

In turn it would save the employer some 8 months of relevant time

related preliminaries from the contractor, building related escalations

and finance cost (which would not be applicable in this case as

discussed above). This would also increase the contractors turn-

around time, giving him more projects in a shorter period of time and

in turn increase his annual profit with exactly the same work force.

In order to find out how much would be saved, a relevant

preliminaries document would need to be drawn up with only items

included in it that are time related and specific to the circumstances

they address. This would be the most accurate way of determining

those savings. This would however not quite work as standard

amounts are put forward by the government on projects like these.

Below is an overview of the allocated amounts per BNG house

issued by the Department of Housing for the 2009 financial year.

23

Table 13 – BNG subsidy breakdown Source: Government Department of Housing allocated subsidy for 2009 financial year.

Although the subsidy is only for a 40m² house, the overheads and

P&G’s amounts can be assumed to stay the same. Of course not all

P&G expenses are time bound as was mentioned before. According

to Pienaar (2009), a quantity surveyor and consultant for the

government on housing, it is safe to say that 40% of those costs can

be taken as time related. The rest would either be fixed or variable.

The same can be assumed for the overhead expenses. If the

theoretical building programme is taken into consideration it cuts the

construction time from 18 to 10 months this is an overall saving of

45%. So to be on the safe side it would be good to take a time saving

factor of 40% into consideration. Should this be the case the

following would occur:

24

Description Current allocation

Time related amounts @ 40%

Time savings factor @ (1-40%)

Total saving on Preliminaries

P&G’s R4 968,14 R1987.26 R1192.35 R794.91

Overheads R2095.32 R838.13 R502.88 R335.26

Table 14 – Indirect cost Source: Own

According to the calculations above, the government could be saving

a total of R1130.17 on the preliminaries per house because the work

would be getting done faster. This would decrease the P&G amount

to R4173.22 and the Overhead amount to R1760.06. This of course

is a very theoretical approach and would have to be tested in practice

to see if it could really work.

According to the plans of a 50m² house it has 88m² of walling. The

final building cost of a conventional MAXI Block system compared to

that of a TECOBLOCK® system including the preliminaries would be

as follows:

Description per m² MAXI Block system TECOBLOCK® system

Total building cost excluding preliminaries

R218.52 R179.09

P&G’s R56.46 R47.43

Overheads R23.81 R20.00

Total R298.79/m² R246.52/m²

Table 15 – Total cost comparison per m² Source: Own

25

2.8) Summary:

This theoretical exercise has given great insight into the costing of

both the MAXI Block system as well as the TECOBLOCK® System.

All aspects were taken into account during the costing including

material, labour and preliminaries and general. The time factor was

extensively researched and applied by taking into consideration a

case study that was conducted in Melbourne, Australia. The result of

the time saving aspects show significant impact on the total of the

building cost and especially favours the TECOBLOCK® system.

2.9) Conclusion:

In conclusion looking at the overall cost involved in building a wall the

TECOBLOCK® system is cheaper at R246.52/m² compared to that

of the MAXI Block system, which is R298.79/m². This is a saving of

17.5% and it proves that even though the TECOBLOCK® system’s

raw material price is 28.8% more expensive than the MAXI Block

system, taking the time factor into account and labour hours

reduction makes the TECOBLOCK® system more viable to use.

2.10) Testing of the Hypothesis

Looking at the above conclusion sets the hypothesis as true and it

proves that the TECOBLOCK® system as being cost competitive in

the country compared to that of conventional systems.

26

Chapter 3:

Will TECOBLOCK® be accepted in the market

by Architects, Contractors, Developers,

Engineers, the Government and the end-user?

3.1) Concise Overview:

To be able to come to a conclusion on the acceptability of the

TECOBLOCK(R) system in the market a questionnaire was drawn

up. This questionnaire was split into three sections:

• Section A: For engineers, architects, developers and

contractors

• Section B: For general home owners

• Section C: For state authorities

The questionnaire was divided into the three sections in order to

target different users of the product, from the professional who will

work with the product to the end user who will live in the home that

was built with the system.

In this chapter, each of the questions is discussed and a conclusion

is drawn from them thereafter.

3.2) Body of the chapter:

As mentioned above Section A was presented only to Built

Environment professionals. A mixed number of professionals were

asked ranging from architects, engineers, contractors and

27

developers. The Built Environment professionals were evenly spread

out for the questionnaire. The questionnaire provided a question

pertaining to either the cost effectiveness or acceptability in the

market place of the product. The questions were set up in such a

way that only Yes or No could be answered.

3.3) Questionnaire – Section A

Section A contained a response from Architects, Engineers,

developers and Contractors. The questions that were put forward to

the respondents were structured in such a way as to concentrate on

the design, cost and ease of use of the product. 12 professionals

were asked to fill out the questionnaire.

• Have you ever heard of the alternative building system

TECOBLOCK®?

All respondents answered No to this question. This clearly

shows that the product is not well known in the South

African Built Environment market and that its advertising

has not reached South African shores.

• After viewing the brochure do you understand the

TECOBLOCK® concept?

All respondents answered Yes. This shows that the

brochure had sufficient information on it to make it the

concept understandable to the average Built Environment

professional.

• Would you design/build with an alternative building solution

if it where Agrément certified?

28

Ten respondents answered Yes and two answered No.

Out of these answers a conclusion can be drawn that the

Agrément certification has a relatively high standing within

the Built Environment. One of the respondents that

answered No was an architect and the other a developer.

• If the alternative building solution were faster than

conventional methods would you build/design with the

system?

Eleven of the respondents answered Yes and one

answered No. These answers show that the majority of the

respondents would encourage a system to be used on the

basis of it being faster than a conventional method.

• If the cost of the system was the same or slightly higher,

but faster and more accurate than conventional systems,

would you consider building/designing with it?

Eight of the respondents answered Yes and four answered

No. These answers show that some of the respondents are

concerned about the price of the system. This was

specifically the case for the contractors and the

developers.

• If the required labour force would decrease when building

a TECOBLOCK® house compared to building a

conventional house, would you design/build with it?

Nine of the respondents answered Yes and three

answered No. These answers indicate that the majority of

the professionals would be in favour of a system that would

decrease the labour force for the same amount of work.

29

• If the blocks could be manufactured on site, would this be

an incentive to build the house with such a system i.e.

TECOBLOCK®?

Ten of the respondents answered Yes and two answered

No. This indicates that Built Environment professionals

would see the possibility of producing blocks on site as an

incentive to build with the product.

3.4) Questionnaire – Section B

Section B contained a response from the potential end user. The

questions that were put forward to the respondents were structured

in such a way as to concentrate on the aesthetic appeal and

practicality of the product. 20 end users were asked to fill out the

questionnaire.

• If the wall was built with an alternative building system

such as the TECOBLOCK ® system and the finish of the

wall looked exactly like a conventional plastered wall

would you live in it?

Out of the 20 respondents all answered Yes. This is an

overwhelming indication that anything that looks exactly

like a conventional plastered wall would be acceptable.

• If the acoustics inside the house were the same using the

TECOBLOCK® system as in a conventional house would

you consider building your house with it?

All of the 20 respondents answered Yes. This indicates a

high level of acceptability for the TECOBLOCK® system.

30

• If the walls were 100mm thick using the TECOBLOCK®

system compared to the 220mm width as per

conventional brick work, but with the same insulation

properties would you consider living in the house?

Nineteen out of the 20 respondents said Yes and only

one answered No. This shows a high level of acceptance

for the insulation aspect of the system.

• If the house had the same or better structural properties

using the TECOBLOCK® system compared to that of

conventional masonry walling would you consider living in

the house?

All 20 respondents answered Yes. This shows people

would accept the system if it were the same or stronger

than a conventional method.

3.5) Questionnaire – Section C

Section C contains a response from a Government representative.

The questions were posed in such a way as to determine if the

TECOBLOCK® system could be potentially used for government

projects.

• Is the Government interested in making use of alternative

building systems for building BNG housing?

The answer here was Yes. The representative’s answer

was straight to the point, “We have an enormous housing

backlog at the moment and if one could find a way of

overcoming this problem, by building high quality houses

31

in the most efficient way possible, then the government

would surely look at it.”

• After viewing the explanatory section above do you

understand the concept at hand?

The representative answered Yes and added that she

thought it was a very clever and innovative way of

building.

• Would a faster turn-around time – compared to

conventional methods – for completion of houses be an

incentive to use the TECOBLOCK® concept?

The representative answered Yes and added that “as

mentioned before if it supports the rolling out of more

houses than presently, then that would be a great

incentive to use the product”.

• If the system offered a rational design by an engineer or

were accredited by Agrément South Africa would the

Government consider accepting this alternative building

solution?

The representative answered Yes and motivated that

using the system would be a prerequisite for any of the

projects put forward by the Government.

• If the systems were the same price or slightly more

expensive compared to conventional methods, but

offered savings in time, would the Government still accept

this alternative building solution?

The representative answered No and emphasised the

fact that there is a fixed price per unit for a Government

32

subsidised BNG project. She stated that there is a set

budget put forward per project and that no project is

allowed to go over that budget.

• If the system was the same price or slightly more

expensive compared to a conventional method but

offered better built quality, would the Government still

accept the alternative building solution?

The representative emphasised that if the product was of

a higher quality compared to conventional systems then

that would be good, but as was mentioned before there

would be no chance for the product to work if it would go

over the allocated budget.

3.6) Summary

In summary the Built Environment professionals in Section A were all

in all impressed with the system although the developers and

contractors were very concerned about any increase in price from

what they are used to. After further interviews with some contractors

and developers one came to the conclusion that they are very raw

price driven and if the raw price of one product versus another is

lower, then the latter would be chosen even if it could be proven that

the overall price of the former would be lower in the long run.

Architects in general were not too concerned about price but were

more aesthetics and product driven. They showed an interest in the

product and said that they would be willing to design with it, if it would

pass all accreditation processes or if a rational design was made by

an engineer.

33

Engineers locked closely at the integrity of the concept and there

general view was that the concept could work up to a specific height

only and beyond that as an infill wall.

In section B the potential users gave an overwhelming sign of

acceptance. As the end-user anything that resembles the current

method of living is accepted and small deviations from the norm

could be tolerated.

Section C saw input from the Government side. In overall terms it

was accepted especially if the product would be faster than the

conventional methods, as an emphasis was put forward to meet the

backlog of houses and to fast track the housing output.

The only main concern was the budgetary amount put forward as a

subsidy by the government per house. This amount cannot be

exceeded as this would go against government policies, which would

not be allowed.

3.7) Conclusion

In conclusion, the product could be generally accepted by the Built

Environment professionals, general end-user and the Government.

The only problem that the TECOBLOCK® system faces is the cost

aspect. It was proven in Chapter 2 that the TECOBLOCK system is

more cost effective than a conventional method. This proves to

developers, contractors and Government that the system would meet

their requirements in terms of cost and would therefore be

acceptable to them for their purposes.

34

3.8) Testing of the Hypothesis

The completed questionnaire shows that the majority of the

respondents would accept the system, which therefore proves the

hypothesis that the system could be accepted in the market place in

South Africa.

35

Chapter 4:

Can all technical issues be addressed to make

TECOBLOCK® work in South Africa?

4.1) Concise Overview

In this chapter the technical difficulties that face the TECOBLOCK®

system will be discussed. The technical aspects include:

• Production processes

• Mix ratios and

• Material make-up of the block

According to McCaffer (2006:33), an economy comprises of many

companies and organisations all continually striving to stay profitable

or viable. Consequently, the construction sector also must improve

relative productivity of resources in order to maintain final prices

attractive to potential customers, otherwise demand for its products

either stagnate or fall.

From this it is derived that all business that want to exist need to be

profitable. How is this achieved? According to McCaffer (2006:34) a

productivity factor is needed, which is:

Total factor of productivity = Output / Input = Commodities /

(Natural Resources + Labour + Capital Goods + Entrepreneurship

This monitors and evaluates the basic productivity of a company

using the ratio of outputs over inputs.

36

This productivity ratio factor will be duly noted and be further

discussed in the body of the chapter under production processes.

Material usages and ratio mixes can be seen as the most important

natural resource input. It furthermore is the main contributor of the

final cost of the product.

4.2) Body of the chapter

4.3) Current production process

The production process is one of the most important aspects during

manufacturing of the block. This needs to be a process that is

streamlined, efficient, effective and that can handle large volumes of

producing the blocks. The existing process used in Australia were

polystyrene moulds that were sprayed with releasing oil and the

block once cured, was pushed out by pneumatic arms. The photos

below show the mould and extraction machine.

37

Figure 7 – Block moulding process

Source: Own

Figure 8 – Extracting process of the TECOBLOCK®

Source: Own

The problem that was noticed with this process, according to building

and process expert Sutherland (2009), is that it takes too long for a

block to be manufactured. The process and time related aspects

were as follows:

• Spraying releasing agent into mould – 7 seconds

• Pouring of slurry mix into mould - 20 seconds

38

• Curing and drying of block – 1 day (depending on the amount

of accelerator added to the mix)

• Extracting of block out of the mould – 30 seconds

The problem with this process is that the block is made of a slurry

mix. This mix then needs an accelerator in order for curing time to be

decreased so that the block can be extruded as soon as possible.

This adds unnecessary additional raw material costs to the block.

The turn-around time of the mould is the most important. According

to the breakdown of the production process above, this means that a

mould will have to stand approximately one and a half days from start

to end of the process.

If a mould extracting machine can extract around 2 blocks per minute

then one machine could extract around 120 blocks per hour, which in

turn would work out to 960 per day, if the machine works

continuously for 8 hours. This equates to 96 m² of walling, which is

just slightly more than what is used in one BNG house.

If the building program is taken into consideration from chapter 2 on

a 300 BNG unit development as follows:

Figure 9 – Building Program Source: Own in consultation with HC Projects (Pty) Ltd

39

This clearly shows that a number of these machines would be

needed to be able to supply a development of such a nature.

According to the program the building process for the 300 units

would take around 5 months. This would equate to some 3 houses

per day, meaning that at least 3 machines would be needed to

complete only this development.

The next problem that is faced is the amount of moulds needed to

supply the number of blocks required for the development. If three

BNG houses are built per day then around 270 blocks are needed

per day. In order to have a continuous production process and taking

the 1.5 days lag time into consideration in which the blocks lie in the

mould, this would equate to the following number of moulds:

This would mean that at least one and a half time the amount of

moulds would be needed compared to blocks being produced per

day. This would entail that some 270 blocks would start being

extracted in the morning during the process and whilst this was

occurring the extra 135 “buffer” moulds would be initiated with the

filling process. As the filling process carries on, the remaining 135

moulds needed for the daily quota would be taken from the extracted

batch. This would allow maximum time for the 24 hour curing process

together with having a 135 mould buffer.

From this it is clear that this process is not practical for mass

production, as a large number of moulds would be needed to supply

the daily quota.

Suggested answer:

According to process expert Sutherland (2009), the best would be to

use an extrusion or mass mould process to make the blocks. For the

40

extrusion process a machine would need to run on a type of rail

system on the floor and extrude the block on the floor, which would

then be cut one they are dry. The mass mould system would

constitute of a very large mould, which would have numerous blocks

within the one mould. This mould would then work on the exact same

principle as the single mould system above. The only thing that

would be easier, would be that the blocks could be extracted on a

larger scale and could be more mechanised, which would save

significant time in the production process.

4.4) Raw Materials

The biggest aspect of being profitable is to keep the raw material

prices as low as possible. A large number of experiments have been

done by Pharaoh Cement (Pty Ltd) and WACKER Australia using a

combination of financial analysis and trial mixes to see which

material would work out the cheapest for the block while still

providing the required strength.

Each type of mix is different for every country, depending on the

availability of the raw materials and the cost thereof. In Australia the

mix constitutes a mix of cement, sand, accelerator, recycled fibre

filler, volumetric filler and a special polymeric additive called

Vinnapas, which is produced by the chemicals company WACKER,

and which gives the block flexibility and water impermeable

characteristics.

The recycled fibre filler allows the block to be cut with a normal hand

saw and prevents the block from becoming brittle. This filler, being

the most cost effective of all the raw material, is then also used in the

largest quantity in the block.

41

The Australian government is very supportive of recycling materials.

It makes these materials readily available and very cheap or even

free. The recycled fibres are obtained from a number of sources, one

being old carpets that are chopped up into 1-1.5mm fibre strands or

polyester fibres that are obtained from chopping up the plastic coke

bottles.

All these aspects could also be explored in South Africa but would

take a large amount of time and community involvement to obtain

these bottles at a price that makes economic sense to both the

manufacturer of the block and the community at large to make it

worth the effort.

In South Africa a study was conducted by Pharaoh Cement (Pty) Ltd

and the author of this dissertation, on materials that could be used in

the make-up of the blocks. The make-up of the different materials

that were:

• Readily available

• Cost effective

• Contribute as a component to strength, volumetric aspects,

flexibility or water impermeability.

Certain materials were identified that make up the main components

of the block.

The first of course is Portland cement. This provides the main

strength of the block, which occurs during a hydration process. The

strength is determined by the water: cement ratio of the mix (Addis,

2004:66) and for this application ranges between 4 and 9 MPa for

this specific application.

42

The second raw material used in the mix is Fly Ash. In South Africa

fly ash is a major filler used in the “all purpose cement” blend and

originates from the burning process in the coal power stations and is

sold off relatively cheaply to the cement industry. According to Addis

(2004:67) it:

• Workability is improved

• Durability is enhanced

• Strength development is slightly lower

This gives beneficial aspects to the block, if it is used in the mix,

especially considering the low cost of the product. The only negative

element here is the lowering of the strength development. This

difficulty can be overcome by adding more Portland Cement.

The third material identified is well graded sand or crusher dust,

which is a suitable and cost effective bulk filler material. This,

according to the lab tests done at Pharaoh Cement (Pty) Ltd,

enhances density, durability and contributes as an aggregate binder

to the cement, which in turn increases the strength of the mix. The

problem with this bulk filler is that it starts adding too much weight to

the block. The TECOBLOCK® concept is all about having a simple

light weight block to build walls with. This poses restrictions on how

much sand can be added to the mix without compromising too much

on strength and weight of the block.

4.4.1) Accelerators

The accelerator plays a large part in the quick curing process. This is

necessary to get the blocks out of the moulds as soon as possible in

order to decrease the turn-around time of the of the moulds.

43

According to TECOBLOCK founder Toni Mucci, the problems that

are faced with accelerators are:

• Strength: Decreases strength of a given mix in comparison to

the same mix that does not have an accelerator in it

• Price: Increases cost of the block and adds no real value to

the actual block other than decreasing the setting time of it to

get it out of the mould faster.

• Amount added: Needs special attention when it is added to

the mix so that the exact quantity ratio is added. Too much

could have a detrimental effect on the strength and hydration

reaction of the mix, resulting in an immediate setting of the mix

which will lead to cracking of the block. Too little will not

contribute to the increased setting time but will still decrease

the strength of the block.

• Adding time: Some accelerators are very sensitive to how

much they are allowed to be mixed into the mix, such as

Aluminium Sulphate which is only allowed to be mixed into the

mix for a very short period of time before it then needs to be

cast into the moulds. The reason for this is the more the mix is

mixed whilst the accelerator is in the mix the more the

accelerator is broken down and therefore it becomes less

effective. This means that an accelerator generally must be

added when the mix is complete and just before it would be

cast into the mould, whereby it is mixed just enough to allow

for an even consistency throughout the mix.

44

4.4.2) Fillers/Fibres

Fillers and fibres are an essential part in the block mix. During the lab

tests that were conducted it became clear that the fillers and fibres

influenced the block mix in terms of:

• Bulking: This means that fewer other materials are needed to

fill the mould amount of the block. Although it decreases the

block strength dramatically, it decreases the weight of the

block dramatically, which is a general benefit in terms of

handling the block during the building process and using the

block in high rise buildings as infill walling. This brings down

the cost of the actual concrete structure. Therefore it was

found that a maximum of around � of the block could be a

filler. If this figure is exceeded then the block just becomes too

weak. A volumetric filler such as pearl lite means that a

considerable amount of shrinking will during the curing

process, which could distort the block.

Figure 10 – Different grades of perlite

Source: www.inspect-ny.com

• Flexibility: Usage of fibre fillers contributes enormously to

flexibility i.e. tensile test. During lab testing it was found that a

block, which had no fibres versus a block with fibres was four

times more tensile. This is a huge benefit, as should there be

45

any movement in the wall, it will be more resistant to cracking.

Other benefits that were found, is the fact that the block could

be cut with a normal hand saw in the most precise manner.

The fact that fibres are present makes the block less brittle

than blocks with no fibres in them, which allows for the block

to be cut perfectly with a hand or band saw.

Fibres that can be used are natural fibres such as wood or

plant fibres, or artificial fibres, for example polyester fibres.

Figure 11 – Cutting block with a handsaw

Source: Own

46

Figure 12 – Cutting of TECOBLOCK® with a band saw

Source: Own

4.5) Summary:

In this chapter the most significant technical issue were discussed.

The production process seems able to work effectively on small-

scale aspects, with certain challenges being faced for larger scale

applications.

The material constituents of the block mix pose a challenging aspect

to the whole blocking system. This is linked to challenges in terms of

geographically bound areas, availability and cost of the product.

47

4.6) Conclusion:

The present production process works well, but is limited to relatively

small-scale operations. This is therefore not viable for numerous

large-scale developments that would be built at the same time. A

more streamlined and large-scale production line would have to be

devised, which would be largely mechanised. An industrial or

mechanical engineer would have to be employed to devise such a

process, as the present one could never meet the demands of a

large-scale operation.

The raw materials in the block are one of the main contributors to the

cost of the block. Therefore this will make or break the financial

viability of the system. A certain raw material matrix would need to be

devised to come up with the most optimal mix, which would satisfy:

• Minimum compressive strength requirements

• Lowest possible cost

• Fastest possible curing time

• Optimal flexible strength

• Weight requirements (as light as possible)

Intense further lab testing would need to be conducted to develop

such a mix.

48

4.7) Testing of the Hypothesis

Based on the conclusion, an array of industrial engineering

processes would need to be devised. This could be done and

therefore the hypothesis could be proven to be true and valid.

49

Chapter 5:

What are the logistical problems regarding the

manufacturing of TECOBLOCK® in South

Africa?

5.1) Concise Overview:

In this chapter the logistical aspects of the production process are

explored. These aspects pertain to geographical challenges within

South Africa and how, what and where to optimally set up production

plants.

The following variables are taken into consideration in order to see

what area will be most suited for the establishment of manufacturing

plants.

• Distance of manufacturing plant from raw materials or end

user

• Population density of South Africa

• Potential growth areas for the future

• Coal fired power stations – fly ash production

• Cement manufacturing plants – OPC production

5.2 Body of chapter – plant location

It is always debateable where the optimal area in South Africa would

be for a manufacturing plant of this nature. The options are to either

have it close to the source of the raw material or close to the end

user.

50

According to production plant expert Sutherland (2009), it is always

better to have the production plant closer to the origin of the raw

material source than to the end user, with certain restrictions

governed by maximum distances. However, if a combination of both

can be achieved then an optimal compromise is reached. The reason

for this is, according to Brian Sutherland, that should there be any

occurrence of wastage during the manufacturing process, this

wastage will have travelled the minimum distance from the raw

material point of origin to the manufacturing plant and not the full

distance to the closest end user. This in turn saves money on

haulage and therefore it is more effective to have a manufacturing

plant closer to the origin point of the raw material source than to the

end user point.

The next problem occurs when a number of raw materials are placed

into a product and all raw materials come from different areas. This

makes the location of the manufacturing plant more complicated.

According to Sutherland (2009), the following variables need to be

taken into consideration:

• Percentage amount of raw material that forms part of the end

product and what its weight and bulking contribution are in the

end product.

• Distance matrix between all sources of raw materials

• Individual raw material price i.e. value of the raw material

within the end product

51

5.2.1) Population Density:

The above mentioned variables are only some of the considerations

that need to be taken into account. Population density is a major

driving force that determines where to have a manufacturing plant.

According to Pienaar (2009), a low cost housing expert, once a

potential population growth area has been identified, then the closest

raw material deposits for the end product must be sourced in the

surrounding area.

The population density map below shows people/km² for every

municipal region throughout South Africa.

Figure 13 – Population densities in South Africa

Source: Department of Environmental Affairs (14th August 2009)

52

The map depicts medium to high population density in the

• Greater Gauteng area

• Parts of the Northwest Province

• Parts of Mpumalanga and Limpopo Province

• Central Freestate Province

• Central Eastern part of Kwazulu-Natal

• South western area of the Western Cape Province

• And parts of the Eastern Cape

These high density areas would also be potential growth areas,

because people would stay in an area where there is work. This

means that any of the above mentioned areas would entail a demand

for housing.

5.2.2) Sources of raw materials

Following on from this assessment, the next step would be to assess

a strategic placement of the production plant by having a look at

availability of the main raw material sources in the block, namely

Portland cement and fly ash together with a crusher stone.

This is depicted in the maps given below. Crushed stone is not taken

into consideration, as this is assumed to be readily available

throughout South Africa. Figure 14 and 15 show both raw lime

deposits and PPC’s production plants within South Africa. For the

purpose of this assessment, only PPC’s production plants will be

taken into consideration. Figure 16 and 17 show Eskom’s power

plants in and around Mpumalanga and Limpopo Province, which

produce fly ash as a bi-product from the coal that is burnt.

53

A clear matrix can now be derived for the location of the initial

production plants of the blocking system. According to Pienaar

(2009), it is best to first target the economic hub of South Africa, the

greater Gauteng area. He also says that other potential growth areas

are the Rustenburg area, were mining giants such as Anglo Platinum

are expanding their mining areas, and also towards the Limpopo

Province where the new Medupi coal fired power station is being

built. Further growth areas are within Mpumalanga and Witbank,

where coal mining is also expanding.

Figure 14 – Limestone deposits in South Africa

Source: Department of Minerals and Energy ( www.dme.gov.za/pdfs/minerals )

The initial areas chosen for the plants are:

• Gauteng – Johannesburg

• Rustenburg

54

• Ellisras

• Witbank

According to the maps below:

The Gauteng area manufacturing plant could get its raw material

from the following places:

• Portland cement – Jupiter PPC

• Fly ash – Kendal, Lethabo or Grootvlei power stations

Proposed Rustenburg manufacturing plant:

• Portland cement – Slurry PPC

• Fly ash – Lethabo or Kendal

Proposed Ellisras manufacturing plant:

• Portland cement – Dwaalboom PPC

• Fly Ash – Medupi

Proposed Witbank manufacturing plant:

• Portland cement – Hercules PPC

• Fly ash - Duvha

55

Figure 15 – PPC’s Kiln plants in South Africa Source: Pretoria Portland Cement (www.ppc.co.za )

Figure 16 – Power station plants located in Gauteng and Mpumalanga area Source: Airshed Planning Professionals

56

Figure 17 – Power station plants located in the Limpopo Province Source: Airshed Planning Professionals

5.2.3) Transportation:

According to Sutherland (2009), transport either makes or breaks a business. The four proposed manufacturing plants cover a wide range of areas. Sutherland says that a maximum of a distance of up to 100km to the end user is possible

The map below depicts a +/- 100km radius from each proposed manufacturing plant.

57

Figure 18 – Road map of South Africa with potential demand areas Source: www.sa-venues.com

This would cover an area: A= � x r² x 4 , which would equal 125 663

km². As can be seen from the map above, these areas overlap

slightly. Therefore an assumption of around 100 000 km² can be

made together with a population density taken from figure 13 at an

average of +/- 600 people / km². This would equate to a potential

market of around 6 million people of which approximately 20% need

low cost housing, and would entail a potential market of around 1.2

million houses for the proposed area.

58

5.3) Summary:

From a logistical point of view the greater Gauteng area was chosen

due to its high population density and the fact that it is the economic

hub of South Africa. A pre-potential market of around 1.2 million

houses was calculated on the basis of taking an average population

density and assuming 20% of that figure to be the potential market.

All raw materials are within acceptable distances of the proposed

manufacturing plants and it would therefore be viable have them

there.

5.4) Conclusion

In conclusion all aspects and variables need to be taken into account

when deciding on where to have a manufacturing plant. A basic

design matrix was set up taking into account all applicable variables

and therefore four sites were chosen within the greater Gauteng and

surrounding areas.

5.5) Testing of Hypothesis:

Taking into consideration all above mentioned applicable variables,

the hypothesis is true, but with certain restrictions to certain areas.

59

Chapter 6:

Summary

6.1) Background:

The analysis of the TECOBLOCK® building system focused on

whether this advanced building system could work in South Africa.

This system is promising in that it has numerous advantages over

existing methods such as shorter construction time, ease of use

during construction and relatively light weight blocks.

The main question that needs to be asked however is if

TECOBLOCK® could be successful in the South African market in

terms of:

• Cost effectiveness

• Visual acceptability

• Technical challenges and

• Logistical challenges

6.2) Summary

The summary entails discussing all of the above mentioned sub-

problems and the manner in which they were resolved.

60

The cost effectiveness of the system in the market place was tested

against a Maxi Block system, which is typically used in low cost

housing applications. A theoretical 300 unit low cost housing

development was used as an example to test the hypothesis. Even

though the initial raw block cost was calculated to be approximately

28.8% more expensive, it still works out to be 17.5% cheaper on a

total project basis due to the fact that a considerable amount of time

is saved.

The acceptability of the TECOBLOCK® system in the market was

analysed in Chapter three on the basis of questionnaires that were

completed by selected sets of respondents.

• Section A: For engineers, architects, developers and

contractors

• Section B: For general home owners

• Section C: For state authorities

The participants generally answered favourably and seem to find the

proposed TECOBLOCK System promising. This level of acceptance

proves the hypothesis true that the TECOBLOCK® System could be

accepted and could work in the South African context.

The two main technical issues that the TECOBLOCK® System would

face in South Africa were discussed in Chapter Four. These were:

• The production process and

• The material constituents of the block

It was proven that both the production process and the material

constituents were not at their optimal level yet and that further

development in this field is necessary to find the best fit for the

production processes and material constituents.

61

The logistics problem was discussed in Chapter Five. This focused

on the geographical location of where best to construct a production

plant in South Africa. The following aspects were taken into

consideration:

• Distance of manufacturing plant from raw materials or end

user

• Population density of South Africa

• Potential growth areas for the future

• Coal fired power stations – fly ash production

• Cement manufacturing plants – OPC production

After taking all above mentioned aspects into consideration the area

found to be worth exploring was the greater Gauteng area including

surrounding areas, as discussed in the chapter.

6.3) Conclusion:

Taking into consideration all of the above-mentioned sub–problems it

is clear that the TECOBLOCK® System could theoretically be

applied in the South African context. It fulfils all viability and feasibility

aspects and therefore the pre-feasibility analysis of the

TECOBLOCK® System yields satisfactory results. Whether this

could work in practice is another study and would be subject to pure

business building strategies and enough capital input.

All findings seem plausible and realistic, with certain problems still

faced in the production line process and material constituents of the

block.

62

6.4) Further recommendations:

It is recommended that this issue should be researched in more

depth. In terms of the practical implementation of the TECOBLOCK®

System in South Africa, it will need a far more in-depth feasibility

study.

Other recommendations would be to analyse and come up with a

more streamlined production process, which will result in the

production of the blocks on a large scale and with an optimal material

constituent in the block.

63

Bibliography:

Addis, B 2004. Fundamentals of Concrete. Midrand: Cement and

Concrete Institute

ASAQS Bill of Quantities – Preliminaries –Master 2007

Becker, R. 2001. Implementation of the performance approach in the

investigstion of innovative building systems. Pergamon, 24 August

2001, p. 1.

Finsen, E. 1999. The Building Contract. Cape Town: Juta

McCaffer,R. 2006. Modern Construction Management. Singapore:

Blackwell publishing

Personal Interviews:

Pienaar, J.S. 2009. Personal Communication. 15 April, 20 June, 26

July

Sutherland, B. 2009. Personal Communications. 26 March, 17 April,

29 July

Internet:

www.afrisam.co.za Access: 24 April

www.inspect-ny.com Access: 3 August

www.dea.gov.za Access: 20 August

64

www.dme.gov.za Access: 20 August

www.ppc.co.za Access: 20 August

www.sa-venues.com Access: 21 August