Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
J. D. Woodard Executive Vice President
Southern Nuclear Operating Company. Inc. 40 Inverness Center Parkway Post Office Box 1295 Birmingham, Alabama 35201
Tel 205.992.5086
SOUTHERN k
COMPANY Energy to Serve Your World'
July 23, 2001
LCV- 1545
Docket No.: 50-425
U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555
Ladies and Gentlemen:
VOGTLE ELECTRIC GENERATING PLANT INSERVICE INSPECTION SUMMARY REPORT
Southern Nuclear Operating Company (SNC) submits herein the "Owner's Report for Inservice Inspections (Form NIS-1)" for inservice inspection activities conducted at
Vogtle Electric Generating Plant, Unit 2 (VEGP-2) during its Spring 2001 maintenance/refueling outage. Paragraph IWA-6230 of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Section XI, 1989 Edition, requires submittal of the enclosed report. The supporting documentation, e.g., examination records, equipment and material certifications, etc., from which the enclosed "Owner's Report for Inservice Inspections (Form NIS-1)" was compiled is
available for review upon request at the plant site.
In addition, "Owner's Reports for Repair and Replacements (Form NIS-2)" are included in the enclosed report for repairs and/or replacements of piping and components that were documented and completed at VEGP-2 from the end of the previous maintenance/refueling outage (Fall 1999) through the Spring 2001
maintenance/refueling outage. Any attachments, e.g., code data reports, etc., that are referenced in the completed NIS-2 forms will be made available for review upon request at the plant site.
A discussion on the examination of steam generator tubes performed during the Spring 2001 maintenance/refueling outage is included in the enclosed VEGP-2 "Owner's Report for Inservice Inspections (Form NIS-1)." That discussion constitutes the report required by VEGP Technical Specification 5.6.10.b to be submitted to the NRC within 12 months following completion of the steam generator
U. S. Nuclear Regulatory Commission LCV- 1545 Page Two
tube examinations. As a result, a separate submittal will not be made to the NRC on steam generator tubes examined during the subject outage.
None of the steam generator tubes required plugging as a result of the examinations performed during the Spring 2001 maintenance/refueling outage at VEGP-2. Pursuant to the requirements of VEGP Technical Specification 5.6.10.a, a report was submitted to the NRC within 15 days of the completion of the steam generator tubing examinations and indicated that none of the steam generator tubes required plugging during the subject outage. SNC letter LCV-1536 dated May 2, 2001, transmitted the VEGP Technical Specification-required 15-day report to the NRC.
In addition to components already identified in current requests for relief, seven (7) Class 1 and 2 piping and equipment welds had limited volumetric examination coverage. The affected welds included the following:
Class 1 Equipment - Reactor Coolant System 21201-V6-002-W17 - Pressurizer (PZR) Safety Nozzle-to-Safe End, 21201-V6-002-W18 - PZR Safety Nozzle-to-Safe End, 21201-V6-002-W19 - PZR Safety Nozzle-to-Safe End, and 21201-V6-002-W20 - PZR Relief Nozzle-to-Safe End.
Class 1 Piping - Reactor Coolant System 21201-058-7 - 6" Elbow-to-Flange.
Class 2 Piping - Containment Spray System 21206-005-1 - 8" Flange-to-Pipe, and 21206-006-1 - 8" Flange-to-Pipe.
Physical limitations due to the geometric configuration of the welded area prevented full ultrasonic examination coverage for each of the affected welds. As a result of the physical limitations, the examination coverage was limited to less than ninety percent (<90%). ASME Section XI Code Case N-460, as approved by the NRC in NRC Regulatory Guide 1.147, allows Code acceptance when the reduction in examination coverage is less than ten percent (<10%). Each of the welds identified above was examined using surface means, e.g., liquid penetrant, and the Code-required surface examination coverage was achieved. Because it is impractical to achieve the Coderequired volumetric examination coverage for the affected welds due to the geometric configuration of the welded areas, request(s) for relief from the ASME Section XI Code requirements will be submitted to the NRC, as allowed by 10 CFR 50.55a, for review and approval.
U. S. Nuclear Regulatory Commission LCV-1545 Page Three
In addition to the inservice inspection of Class 1, 2, and 3 components and supports
during the VEGP-2 Spring 2001 maintenance/refueling outage, Class MC (IWE) and
CC (IWL) containment examinations and tests were performed prior to and/or during
the subject outage in response to the September 9, 1996, NRC rulemaking to 10 CFR
50.55a. That rulemaking invoked the requirements of Subsections IWE and IWL to
the 1992 Edition of ASME Section XI with 1992 Addenda (as amended by the NRC).
The containment examinations and tests performed during the VEGP-2 Spring 2001
maintenance/refueling outage were performed in accordance with the requirements of
the 1992 Edition of ASME Section XI with 1992 Addenda (as amended by the NRC)
except where relief has been granted by the NRC. They were performed by either
SNC or vendor personnel and included, but were not limited to, the containment liner
plate general visual examination, tendon tests, containment concrete examinations,
and examinations of bolting, seals, and gaskets of disassembled components. Details
on the examinations and tests performed, conditions observed, and their resolution are
provided in the enclosed "Owner's Report for Inservice Inspections." The Class MC
and CC containment examinations and tests required by the rulemaking to 10 CFR
50.55a to be completed by September 9, 2001, were completed during the VEGP-2 Spring 2001 maintenance/refueling outage.
The signed original and four copies of the "Owner's Report for Inservice Inspections
(Form NIS-1)" for ISI activities conducted during the Spring 2001
maintenance/refueling outage at VEGP-2 are provided for your review. Two copies
of the subject report are being provided to the Regional Administrator for NRC Region II.
Should there be any questions in this regard, please contact this office.
Sincerely,
J. D. Woodard
JDW/JAE/
Enclosure: "Owner's Report for Inservice Inspections (Form NIS-1)" for VEGP-2 Eighth Maintenance/Refueling Outage (2R8), Spring 2001
U. S. Nuclear Regulatory Commission LCV-1545 Page Four
xc: Southern Nuclear Operating Company Mr. J. B. Beasley, Jr. (w/o enclosure) Mr. J. T. Gasser (w/o enclosure) Mr. M. Sheibani (w/enclosure) SNC Document Management (w/enclosure)
U. S. Nuclear Regulatory Commission Mr. R. R. Assa, Project Manager, NRR (w/o enclosure) Mr. L. A. Reyes, Regional Administrator (w/ 2 enclosures) Mr. J. Zeiler, Senior Resident Inspector (w/enclosure)
Vogtle Electric Generating Plant Unit 2
Eighth Maintenance/Refueling Outage (2R8) Owner's Report for Inservice Inspection
Southern Nuclear Operating Company the southern electric system
OWNER'S REPORT FOR INSERVICE INSPECTIONS
for the
EIGHTH MAINTENANCE/REFUELING OUTAGE
of
VOGTLE ELECTRIC GENERATING PLANT, UNIT 2 (7821 River Road, P. 0. Box 1600, Waynesboro, Georgia 30830)
COMMERCIAL OPERATION DATE: May 20, 1989
DOCUMENT COMPLETION DATE: June 2001
Prepared by
SOUTHERN NUCLEAR OPERATING COMPANY (40 Inverness Center Parkway, P. O. Box 1295, Birmingham, Alabama 35201)
as LICENSEE AND OPERATING AGENT
for
GEORGIA POWER COMPANY (241 Ralph McGill Boulevard, N.E., P. O. Box 4545, Atlanta, Georgia 30308-3374)
as OWNER
TABLE OF CONTENTS Page
Introduction 1-1
ASME Form NIS-1 with Abstract - ASME Class 1 and 2 2-1
ASME Class 3, MC, and CC Examinations and Tests 3-1
Augmented Inspections 4-1
Examination Summary Listings
Introduction to Summary Listings 5-1
ASME Class 1
Equipment Examinations 6-1 Piping Examinations 7-1
ASME Class 2
Equipment Examinations 8-1 Piping Examinations 9-1
Supports
Introduction and Equipment Support Examinations 10-1 Introduction and Piping Support Examinations 11-1
Snubber Functional Examinations
Introduction to Snubber Functional Testing and Results 12-1
Pressure Tests 13-1
Indication Notification Forms 14-1
NIS-2 Forms 15-1
i
LIST OF ABBREVIATIONS
ACC Acceptable AD Anchor/Darling AFW Auxiliary Feedwater System Al GPC Action Item (followed by unique no. denoting Action Item number) ANII Authorized Nuclear Inservice Inspector ASME American Society of Mechanical Engineers ASNT American Society for Nondestructive Testing ASTM American Society for Testing and Materials BC Branch Connection CCSS Centrifugally Cast Stainless Steel CCW Component Cooling Water CE Combustion Engineering CH Closure Head CR Condition Report CS Containment Spray CVCS Chemical and Volume Control System DS Downstream ET Eddy Current Examination EVAL Evaluation FAC Flow-Accelerated Corrosion (may also be referred to as "erosion/corrosion") FB Flange Bolting FNR FAC Notification Report FW Feedwater System FSAR VEGP Final Safety Analysis Report (includes updates thereto) GEO Geometric Indications GPC Georgia Power Company HHSI High Head Safety Injection HL Hanger Lug HX Heat Exchanger HYD Hydraulic Snubber IEN NRC Information Notice (may also be shown as "IN" followed by unique no. denoting notice
number) ILRT Integrated Leakage Rate Test IND Indication INF Indication Notification Form ISI Inservice Inspection IST Inservice Testing ID Inside Diameter IR Inside Radius LB Large Bore LD Longitudinal Seam Weld Extending Downstream LD-I Longitudinal Seam Weld Downstream Inside of Elbow LLRT Local Leakage Rate Test LMT Lambert, MacGill and Thomas LU Longitudinal Seam Weld Extending Upstream LU-O Longitudinal Seam Weld Upstream on Outside of Elbow MECH Mechanical Snubber MS Main Steam System MT Magnetic Particle Examination NCI Nonconformance Item NDE Nondestructive Examination
ii
LIST OF ABBREVIATIONS - (continued)
NI NRC NRC-B NRI NSCW OR PL PM PR PROF PS PSA PSI PT RCS RCP RHR RI RLW RL RPV RR RWST SAT "SB SCS SI SSI SNC SUP T&C TDAFW TS UNSAT US UT VEGP
VT W
iii
No Indication United States Nuclear Regulatory Commission NRC Bulletin (followed by unique no. denoting Bulletin number) No Recordable Indication Nuclear Service Cooling Water System Outside Radius Pipe Lug Paul-Munroe ENERTECH Pipe Restraint Profile Pipe Support Pacific Scientific Preservice Inspection Liquid Penetrant Examination Reactor Coolant System Reactor Coolant Pump Residual Heat Removal System Recordable Indication Refracted Longitudinal Wave Restraint Lug Reactor Pressure Vessel Relief Request (followed by unique no. denoting relief request number) Refueling Water Storage Tank Satisfactory Examination Results Small Bore Southern Company Services Safety Injection System Sonics Systems International Southern Nuclear Operating Company Supplemental Data Thickness and Contour Turbine Driven Auxiliary Feedwater (Pump) VEGP Technical Specification Unsatisfactory Examination Results Upstream Ultrasonic Examination Vogtle Electric Generating Plant (common unless followed by "-1" or "-2" to designate a specific plant unit) Visual Examination Westinghouse
INTRODUCTION
This report documents the examinations and tests performed at Vogtle Electric Generating Plant, Unit 2 (VEGP-2) between November 3, 1999 (date of last examination performed during the seventh maintenance/refueling outage, 2R7) and May 1, 2001 (date of last examination performed during the eighth maintenance/refueling outage, 2R8) to meet the requirements of Article IWA-6000 of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Section XI, 1989 Edition (Code). In addition, a sunmmary of the following augmented examinations are included in this report:
"* VEGP Technical Specification 5.5.9 - Steam Generator Tube Inspections,
"* VEGP Technical Requirement 13.7.2 - Snubber Visual Inspections and Functional Tests,
"* United States Nuclear Regulatory Commission (NRC) Bulletin 88-09 - Thimble Tube Thinning in Westinghouse Reactors,
"* Westinghouse Technical Bulletin NSD-TD-90-02 - BMI Conduit Guide Tube Leaks,
"* GPC Action Item 87-0131 - Cracking in Stagnant Borated Water Piping Welds, and
"* Balance of Plant Examinations for Flow-Accelerated Corrosion.
This report also addresses Code-applicable repairs and/or replacements, which were documented since the last maintenance/refueling outage at VEGP-2 through the completion of the eight maintenance/refueling outage in May 2001. The Owner's Reports for Repairs and Replacements (Forn NIS-2) are included herein.
In addition to the examination of Class 1, 2, and 3 piping and components and other components, e.g., flux thimble tubes, as an "augmented" scope, Class MC and CC components associated with containment were also examined. These examinations were performed in accordance with the requirements of the 1992 Edition of ASME Section XI with 1992 Addenda (as amended by 10 CFR 50.55a) except where relief has been granted by the NRC. These examinations were performed in response to the rulemaking to 10 CFR 50.55a that became effective September 9, 1996 (Ref. Federal Register Notice 61 FR 41303).
1-1
FORM NIS-1 OWNER'S REPORT FOR INSERVICE INSPECTIONS As required by the Provisions of the ASME Code Rules
1. Owner: Georgia Power Company, 241 Ralph McGill Blvd., N. E. P. 0. Box 4545, Atlanta, Georgia 30308-3374
2. Plant: Vogtle Electric Generating Plant, 7821 River Road P. 0. Box 1600, Waynesboro, Georgia 30830
3. Plant Unit: Two
4. Owner Certification of Authorization: N/A
5. Commercial Service Date: May 20, 1989
6. National Board Number for Unit: N/A
7. Components Inspected:
Component or Manufacturer or Manufacturer or Installer State or Province National Board Appurtenance Installer and Address Serial Number Number Number Reactor Combustion Eng. 7372 N/A 22004 Pressure Vessel Inc.,
Chattanooga, TN
Steam Westinghouse Elec., GBGT 1984 (S/N 77743), N/A 36, Generators 1, 2 Tampa, FL GBGT 1983 (S/N 77745), 35, and 3, GBGT 1982 (S/N 77742) 34 respectively
Pressurizer Westinghouse Elec., 77749 N/A 24 Pensacola, FL
Selected Piping, Pullman Power 1201, 1204 & 1206 N/A N/A Components, Products, and Supports Williamsport, PA
2-1
FORM NIS-I (Back)
8. Examination Dates: November 3, 1999 to May 1, 2001
9. Inspection Period Identification: First Period of Second Inspection Interval
10. Inspection Interval Identification: Second Inspection Interval
11. Applicable Edition of Section XI 1989 Addenda None
12. Date/Revision of Inspection Plan: February 28, 2001 / Revision 4
13. Abstract of Examinations and Tests. Include a list of examinations and tests and a statement concerning status of work required for the Inspection Plan. (See Abstract and Examination Summary Listings)
14. Abstract of Results of Examinations and Tests. (See Abstract)
15. Abstract of Corrective Measures. (See Abstract)
We certify that a) the statements made in this report are correct, b) the examinations and tests meet the Inspection Plan as required by the ASME Code, Section XI, and c) corrective measures taken conform to the rules of the ASME Code, Section XI.
Certificate of Authorization No. (if applicable) N/A Expiration Date N/A
Date: gL _ 20.04 Signed: Southern Nuclear Operating By: Company, Inc. for
Georgia Power Company Owner
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State of Georgia and employed by The Hartford Steam Boiler Inspection and Insurance Company of One State Street, Hartford, CT 06102 have inspected the components described in this Owner's Report during the period November 3, 1999, to May 1, 2001, and state that to the best of my knowledge and belief, the Owner has performed examinations and tests and taken corrective measures described in this Owner's Report in accordance with the Inspection Plan and as required of the ASME Code, Section XI.
By signing this certificate neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations, tests, and corrective measures described in this Owner's Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this inspection.
/•_7 Commission: 6A 203 "InspecrsSnature National Board, State, Province, and Endorsements
Date: e. - -7 9 200/
2-2
ABSTRACT - ASME CLASS 1 AND 2
Introduction/Status
The ASME Boiler and Pressure Vessel Code, Section XI, 1989 Edition (Code), is the applicable code for conducting inservice inspection activities during the second ten-year inspection interval at VEGP-2. Examinations and tests required by the Code are scheduled in accordance with "Inspection Program B" as defined in Code paragraphs IWB2412 and IWC-2412. This "Owner's Report for Inservice Inspection" is for those first inspection period examinations and tests which were performed between November 3, 1999 (date of last examination performed during the seventh maintenance/refueling outage, 2R7) and May 1, 2001 (date of last examination performed during the eighth maintenance/refueling outage, 2R8). The Code required percentage of examinations and tests scheduled for the first inspection period were completed during 2R8.
By Federal Register Notice 64 FR 51370 dated September 22, 1999, 1OCFR50.55a(g)(6)(ii)(C), Implementation of Appendix VIII to ASME Section XI, was incorporated into the rule to expedite implementation of Appendix VIII. The Supplements of Appendix VIII of Section XI, ASME Boiler and Pressure Vessel Code, 1995 Edition with the 1996 Addenda, have been implemented in accordance with the applicable schedule.
In addition to the summary of inservice inspection activities, this report addresses Code-applicable repairs and replacements documented at VEGP-2 since 2R7 through the end of 2R8. The Owner's Reports for Repairs or Replacements (Form NIS-2) are provided herein.
It should be noted that Authorized Nuclear Inservice Inspector (ANII) inspection services were provided for those examinations and tests required by the Code. ASME Section XI examinations and tests are itemized in the applicable sections by reference to Examination Category. Examinations that do not meet the Code-required coverage either reference request(s) for relief or indicate that additional relief is required.
Class I Examinations
Selected Class 1 components were examined by Southern Nuclear Operating Company (SNC) personnel utilizing ultrasonic testing (UT), dye penetrant testing (PT), magnetic particle testing (MT), and visual testing (VT) methods, as applicable. Specific components and examination areas are itemized in the applicable portions of this document. A summary of those components examined are listed below:
"* Steam Generator Inner Radii, "* RPV Closure Head, "* RPV Closure Head Studs, Nuts and Washers, "* Pressurizer Shell, Nozzle and Safe-End Welds, "* Piping Welds, and "* Valve and Piping Flange Bolting.
During the scope of VEGP-2 examinations conducted, no Class 1 components were observed to have either reportable ultrasonic, liquid penetrant, magnetic particle or visual indications.
In addition to components already identified in current requests for relief, one piping weld and four equipment welds had limited volumetric coverage during ultrasonic examinations because of physical limitations due to the geometric configuration of the welded areas. In order for adequate ASME Section XI Code-required examination coverage to be attained, more than ninety percent (90%) of the required volume must be examined as addressed in ASIMIE Code Case N-460. The subject code case has been approved for use in NRC Regulatory Guide 1.147. It is impractical to achieve the ASME Section XI Code-required volumetric examination coverage due to the geometric configuration of the welded area. Relief from the ASME Section XI Code requirements will be requested from the NRC for the affected welds through the relief request process as allowed by 10 CFR 50.55a. The applicable welds are indicated
2-3
by "Relief Request Required" in the Class 1 weld tables. Each of the affected welds was examined using surface means, e.g., liquid penetrant, and the Code-required surface examination coverage was achieved.
The Eddy Current (ET) examinations of steam generator tubing, as required by VEGP Technical Specification 5.5.9, were performed by Westinghouse and are discussed in the "Augmented Examinations" portion of this document.
Class I Pressure Test
Table IWB-2500-1, Examination Category B-P, of ASME Section XI requires the performance of-a system leakage
test (IWB-5221) each maintenance/refueling outage. This system leakage test (LT-1) was performed prior to plant
startup following the maintenance/refueling outage. These visual examinations revealed minor leakage and boron
residue at mechanical connections and one through-wall pressure boundary leak. These leakage conditions were corrected.
The one through-wall pressure boundary leak was located on the leak-off line (3/8 inch diameter) of valve 2HV8701B. Design Change Package (DCP) 00-V2N0017 was implemented during the 2R8 maintenance/refueling
outage. This DCP utilized the existing leak-off connection near the bonnet connection of valve 2HV8701B and routed it to the existing thermal bypass line (3/4 inch diameter). The purpose of the design change was to route the
leak-off line to the existing bypass line in such a manner that this flowpath could be used to preclude the potential
for pressure-locking of double disk gate valve 2HV8701B. In order to correct this leakage condition, valve 2HV8701B was repacked with packing below the leak-off line and the piping installed by the DCP was removed.
Subparagraph IWA-5242(a) of ASME Section XI requires removal of insulation from pressure-retaining bolted
connections for VT-2 examination during system pressure testing for systems borated for the purposes of controlling
reactivity. Relief was requested (Ref.: Request for Relief RR-26) from this Code requirement and subsequently approved as documented by NRC letters dated October 24, 1997, for Class 1 components and December 31, 1998, for Class 2 and 3 components. The approved alternative allows insulation to be removed and connections to be
examined while they are at atmospheric or static pressures. With the insulation removed a direct visual examination is performed to detect previously occurring leakage through the presence of boric acid crystals.
The test boundary of the system leakage test includes both Class I and Class 2 components. The Class 2 components
comprise part of the reactor coolant pressure boundary but are not required to be classified as Class 1 per
1OCFR50.55a(c)(2). The frequency for removal of insulation and direct visual examination for Class 1 pressureretaining bolted connections is once each refueling outage (refer to Table IWB-2500-1, Exanmination Category B-P)
and, as such, those activities occurred during the 2R8 maintenance/refueling outage.
The frequency for removal of insulation and direct visual examination for Class 2 pressure-retaining bolted
connections is once each inspection period (refer to Table IWC-2500-1, Examination Category C-H). For the first inspection period those activities were scheduled and performed either before or during the seventh maintenance/refueling outage (2R7).
Class 2 Examinations
Selected Class 2 components were examined utilizing MT, PT, and UT, as applicable. Specific components and
examination areas are itemized in the applicable portions of this report document. A summary of those components
examined are listed below:
"• Steam Generator Nozzle Welds, and "• Piping Welds.
During the scope of VEGP-2 manual examinations conducted, no Class 2 components were observed to have either "reportable ultrasonic, liquid penetrant, or magnetic particle indications.
2-4
In addition to components already identified in current requests for relief, two piping welds had limited volumetric coverage during ultrasonic examinations because of physical limitations due to the geometric configuration of the welded areas. In order for adequate ASME Section XI Code-required examination coverage to be attained, more than ninety percent (90%) of the required volume must be examined as addressed in ASMIE Code Case N-460. The subject code case has been approved for use in NRC Regulatory Guide 1.147. It is impractical to achieve the ASME Section XI Code-required volumetric examination coverage due to the geometric configuration of the welded area. Relief from the ASME Section XI Code requirements will be requested from the NRC for the affected welds through the relief request process as allowed by 10 CFR 50.55a. The applicable welds are indicated by "Relief Request Required" in the Class 2 weld tables. Each of the affected welds was examined using surface means, e.g., liquid penetrant, and the Code-required surface examination coverage was achieved.
Class 2 Pressure Tests
Table IWC-2500-1, Examination Category C-H, of ASME Section XI requires system pressure testing each inspection period. The specific system pressure tests performed are itemized in the "Pressure Tests" portion of this report document. The visual examinations performed during these system pressure tests found only minor leakage at mechanical joints such as valve stem packing and at flanged connections. These leaks were either corrected or evaluated and determined acceptable for continued system operation.
Subparagraph IWA-5242(a) of ASME Section XI requires removal of insulation from pressure-retaining bolted connections for VT-2 examination during system pressure testing for systems borated for the purposes of controlling reactivity. Relief was requested from this Code requirement and subsequently approved as documented by NRC letters dated October 24, 1997, for Class 1 components and December 31, 1998, for Class 2 and 3 components. The approved alternative allows insulation to be removed and connections to be examined while they are at atmospheric or static pressures. With the insulation removed a direct visual examination is performed to detect previously occurring leakage through the presence of boric acid crystals. This approved alternative was implemented on applicable pressure-retaining bolted connections.
Class 1 and 2 Component Supports
No examinations were scheduled nor performed during the 2R8 maintenance/refueling outage.
2-5
ASME CLASS 3. MC. AND CC EXAMINATIONS AND TESTS
"Class 3 Supports and Integral Attachments
No examinations were scheduled nor performed during the 2R8 maintenance/refueling outage.
Class 3 Pressure Tests
No Class 3 Pressure Tests were scheduled nor performed during the 2R8 maintenance/refueling outage.
Class MC Containment Examinations and Tests (IWE)
Category E-A, Containment Surfaces
During the VEGP-2 Spring 2001 maintenance/refueling outage, containment examinations were performed in response to the NRC rulemaking to 10 CFR 50.55a in which the requirements of Subsections IWE and IWL to the
1992 Edition of ASME Section XI with 1992 Addenda were invoked. A general visual examination of the VEGP-2
containment liner, a Class MC component as defined in Subsection IWE to the Code, was performed by SNC
personnel during the outage. The examination was performed using VEGP procedure 84303-C, Revision 0, "Containment Liner General Visual Examination". Personnel performing the general visual examination of the
containment liner plate were qualified in accordance with VEGP procedure 85001-C, Revision 10, "Qualification of
Inspection, Examination, and Testing Personnel". The examination was performed under the guidance of a
Registered Professional Engineer. Optical aids such as flashlights and binoculars were used when performing the general visual examination that included both direct and indirect, i.e., remote, visual examination methods.
One hundred thirty-five anomalies were identified during 2R8 and were recorded on an Anomaly Data Sheet as
"required by procedure 84303-C. That procedure defines an anomaly as a deviation or departure from the normal or
common order, form, or rule with evidence of degradation that may affect either the containment structural integrity
or leak tightness. The VEGP-2 containment liner was examined for evidence of flaking, blistering, peeling, discoloration, cracking, wear, pitting, excessive corrosion, arc strikes, gouges, surface discontinuities, dents, and
other signs of surface irregularities and distress. Of these anomalies, there were twenty-six indications of rust, forty
eight indications of bare metal, twelve indications of depressions, and forty-nine indications of arc strikes were observed. All anomalies were evaluated as cosmetic in nature only and not affecting the structural integrity of the containment liner plate. SCS letter SG-18218 dated February 28, 2001, provided an "Engineering Evaluation" as allowed by the ASME Section XI Code. That letter, which is available at the plant site for review upon request, provides the justification for evaluation of arc strike areas that meet specific thickness criteria from the inspection and repair requirements referenced in section 1.9.94 of the updated VEGP FSAR.
Category E-B, Pressure-Retaining Welds
The rulemaking contains a modification that makes examinations of Subsection IWE, Category E-B optional. SNC has chosen to not examine category E-B welds at VEGP.
Category E-C, Containment Surfaces Requiring Augmented Examination
Any surface areas likely to experience accelerated degradation and aging, should such areas exist, need to be
identified. Such areas (if identified) require the performance of augmented examinations as defined in Examination
Category E-C. There are no existing areas in VEGP-2 requiring Category E-C examination.
Category E-D, Seals, Gaskets, and Moisture Barriers
The rulemaking contains a modification that makes examinations of Subsection IWE, Category E-D optional. SNC
has chosen to implement Request for Relief (RR)-E-1 to allow leak tightness to be verified by 10 CFR 50, Appendix
3-1
J Type B testing (LLRT). The NRC approved SNC's use of RR-E-1 in its June 16, 2000, letter to SNC. The Type B test results, along with the Type C test results, will be reported to the NRC in the Integrated Leakage Rate Test (Type A test) report as required by 10 CFR 50 Appendix J.
Category E-F, Pressure-Retaining Dissimilar Metal Welds
The rulemaking contains a modification that makes examinations of Subsection IWE, Category E-F optional. SNC has chosen to not examine category E-F welds at VEGP.
Category E-G, Pressure-Retaining Bolting
One hundred percent (100%) of the accessible containment boundary and pressure-retaining bolting (bolts and studs) are to be examined during the interval using a VT-1 examination method. All of the visible surfaces are required to be examined when the bolting is not disassembled. Approximately 34% of the penetration bolting listed in Table 2.2 of the VEGP Containment Inservice Inspection Program Plan was examined during the outage (2R8). These examinations were accomplished using Surveillance 84303-201 and Inspection Report (IR) #24483. The penetrations examined using this IR included the following:
2-1818-H3-P16 2-1818-H3-P10 2-1818-H3-P32 2-1818-H3-P53 2-1818-H3-P15 2-1818-H3-P09 2-1818-H3-P30 2-1818-H3-P49 2-1818-H3-P14 2-1818-H3-P58 2-1818-H3-P56 2-1818-H3-P48 2-1818-H3-P12 2-1818-H3-P57 2-1818-H3-P54 2-1818-H3-P47 2-1818-H3-P46 2-1818-H3-P45 2-1818-H3-P33 2-1818-H3-P31 2-1818-H3-P29
All examinations of the bolting for these twenty-one penetrations were completed with satisfactory results.
All IWE examinations have been completed for VEGP-2 that are required by the rulemaking to 1OCFR50.55a to be completed by September 9, 2001.
Class CC Containment Examinations and Tests (IWL)
During the VEGP-1 and 2 Spring 2000 In-Service Tendon Inspection, containment examinations were performed in response to the NRC rulemaking to 1OCFR 50.55a in which the requirements of Subsections IWE and IWL to the 1992 Edition of ASME Section XI with 1992 Addenda were invoked. The general visual examination of the reinforced concrete and the post-tensioning systems of Class CC components, was performed during the tendon surveillance by a vendor qualified under criteria specified by the 1992 Edition and 1992 Addenda of ASME Section XI. The baseline inspection was conducted per IWL to allow on-going monitoring of the containment condition. The IWL general visual inspection was performed under the guidance of a Registered Professional Engineer. Light meters, flashlights, feeler gauges, and an optical comparator were used when performing the general visual examination that included both direct and indirect visual examination methods. The subject examination was repeated during VEGP-2 Outage 2R8 because the visual examination of the concrete containment was not performed "during a refueling outage" as required by NRC Regulatory Guide 1.163.
During the visual examination, two conditions were noted that required an engineering evaluation from SCS. It was necessary for SCS to determine if the conditions would require a detailed inspection. The first condition was an indication of metal exposure, which was later determined to be rebar-chairs, a support used to hold rebar in place while the concrete is being poured. The second concern was the areas of spalling on the edge of the containment buttresses. SCS letter SG-16802 dated March 5, 1999, provided an Engineering Evaluation Report as described in
IWL-3300 for two concrete spalls and also included the initial concrete repair procedure for these two areas. Spall is
defined as a fragment, usually in the shape of a flake, detached from a larger mass by a blow, by the action of
weather, pressure or expansion within the large mass. SCS' response was documented in their letter SG-17640 dated
May 25, 2000, to SNC. It was noted that both indications were non-structural in nature and had no considerable effect on the structural integrity of containment.
3-2
During the containment concrete examinations, inclusive of tendon testing, and in response to lOCFR50.55a(b)(2)(ix), the following information is provided by SNC:
No adverse conditions were identified during the examination and test of the containment concrete, including tendons, which involve the additional requirements of 1OCFR50.55a(b)(2)(ix), Paragraphs A, B, C, and E. With regard to lOCFR50.55a(b)(2)(ix), Paragraph D, there were areas identified where grease leakage was observed on the containment concrete surfaces. A detailed examination was performed by the test vendor and is included in its final report submitted to SNC. That report is available for review upon request at the VEGP plant site. The amount of grease leakage observed was less than the excessive grease leakage reporting threshold value of seven (7) gallons as specified in Enclosure 2 to SNC letter LCV-1307 dated April 5, 1999, that was submitted to the NRC for review and approval. The subject document requested relief from the regulatory requirements of 10CFR50.55a(b)(2)(ix), Paragraphs A and D, relative to the reporting of grease leakage to the NRC in the "ISI Summary Report", otherwise referred to as the "Owner's Report for Inservice Inspection (Form NIS-1)". Excessive grease leakage, i.e., grease leakage in excess of 7 gallons, as it pertains to VEGP is reported to the NRC pursuant to the requirements of VEGP Technical Specification 5.6.9. The NRC reviewed and approved the SNC request for relief pertaining to the reporting of grease leakage and was documented in its June 16, 2000, letter to SNC. Based on the foregoing information, reporting of excessive grease leakage is not required to be addressed in this report due to the NRC approval of the SNC request for relief. No report was filed in response to VEGP Technical Specification 5.6.9 since the observed grease leakage was less than 7 gallons. The actual leakage observed during the VEGP-2 containment concrete examination was 89 ounces (0.70 gallons).
All IWL examinations have been completed for VEGP-2 that are required by the rulemaking to 10CFR50.55a to be completed by September 9, 2001.
3-3
AUGMENTED INSPECTIONS
VEGP Technical Requirements Manual - TR 13.7.2 Snubbers
Visual Inspections
VEGP Technical Requirements Manual (TRM) Technical Requirement (TR) 13.7.2, Technical Requirement Surveillance (TRS) 13.7.2.1 requires each snubber to be visually examined. During the VEGP-2 seventh maintenance/refueling outage, (2R7), one of the snubbers that comprise the total snubber population was found to have unsatisfactory visual examination results. Based upon Table 13.7.2-2, Note 3 in the VEGP TRM, the next visual examination interval remains 36 months, which coincides with the performance of the visual examinations being required during the VEGP-2 ninth maintenance/refueling outage (2R9). Therefore, visual examination of snubbers was not required during the eighth VEGP-2 maintenance/refueling outage (2R8).
Functional Testing
VEGP TR 13.7.2, TRS 13.7.2.3 also requires functional testing of snubbers. The snubbers were categorized into six types as follows:
Type I Pacific-Scientific mechanical snubbers (Models PSA-1/4 and PSA- 1/2) Type II Pacific-Scientific mechanical snubbers (Models PSA-1, PSA-3, and PSA-10) Type III Pacific-Scientific mechanical snubbers (Model PSA-35 and PSA-100) Type IV Anchor/Darling mechanical snubbers (Model series AD-40 through AD-500) Type V Anchor/Darling mechanical snubbers (Model series AD-1600 through AD-12500) Type VI Paul-Munroe ENERTECH 1000 kip steam generator hydraulic snubbers.
Each snubber type was functionally tested utilizing a test plan (as detailed in VEGP TRM 13.7.2.3 in accordance with Table 13.7.2-4) which requires that an initial representative random sample of ten percent (10%) of the population to be functionally tested. The result of the functional testing of the snubber types is as follows:
Snubber Type I II HI IV V VI Total Total Population 21 59 26 236 111 8 461 10% Initial Representative Sample 3 6 3 24 12 1 49 Quantity Failed in Previous Outage 4 0 0 1 1 * 0 6 Total Original Outage Test Scope 7 6 3 25 13 1 55 Total Tested Which Passed Acceptance Criteria 8 6 3 26 35 1 79 Total Tested Which Failed Acceptance Criteria 0 1 0 0 2 0 3 Expanded or Additional Snubbers Tested during Outage 1 1 0 1 24 0 27 (Details Provided Below) Total Tested 8 7 3 26 37 1 82
Expanded or Additional Snubbers Tested during Outage
Type I Scope increased by one due to visually observed condition at 2-1201-239-HOOI. Type II Scope increased by one due to location adjacent to Type V failed snubber
2-1301-015-H004. Type III There were no scope additions for this type snubber. Type IV Scope increased by one due to visually observed condition at 2-1301-168-H012. Type V *Scope increased by one due to Condition Report (CR) #1999001715 identified during 2R7. Scope
increased by twelve due to failure of Type V snubber 2-1301-015-H004 and one additional Type II due to location adjacent to failed snubber. Scope increased by twelve due to failure of 2-1301-106H005.
Type VI There were no scope additions for this type snubber.
4-1
Functional Test Failure Analysis
In accordance with VEGP TR 13.7.2, Table 13.7.2-4, paragraph 4, engineering evaluations were performed by Southern Company Services (SCS) for the one (1) Type II snubber and the two (2) Type V snubbers that failed functional testing. The engineering evaluations were performed in order to determine the cause(s) of the failures and to determine if the piping systems to which the failed snubbers were attached were adversely affected. The affected piping systems to which the failed snubbers were attached were returned to their approved design configuration by replacing the failed snubbers with known operable snubbers. The following is a listing of snubbers and the correspondence associated with the engineering evaluations that are available at the plant site for review upon request.
Type Affected Snubber(s) Applicable SCS Evaluation Letter/Date Condition Report Number V 2-1301-015-H004 SG-18366, 04/10/2001 2001000714 II 2-1301-094-H002 SG-18410, 04/26/2001 2001000979 V 2-1301-106-H005 SG-18414, 04/26/2001 2001000986
The specific Types I through VI snubbers that were functionally tested in response to VEGP TR 13.7.2 are itemized in the Snubber Functional Testing Listings of this report document.
GPC Action Item No. 87-0131 - Stagnant Borated Water Systems Cracking
As a result of generic concerns of pipe cracking in stagnant borated water systems in pressurized water reactors, several welds in Class 2 piping systems were examined in response to GPC Action Item No. 87-0131. Nondestructive examination methods utilized included ultrasonic and/or liquid penetrant examination techniques. "Welds were examined in the Safety Injection and Containment Spray systems. No reportable indications were observed.
The examinations are itemized in the Class 2 Piping section of this report.
Balance of Plant Examinations For Flow-Accelerated Corrosion
Ultrasonic thickness examinations were performed on selected components (fittings, piping, and equipment) in the Condensate, Heater Drain, Heater Vent, Main Feedwater, Turbine Drain, Main Steam, Steam Generator Blowdown, Extraction Steam, and Turbine Drive Steam systems. In all, seventy-one (71) large-bore components were ultrasonically examined during the 2R8 maintenance/refueling outage. Of the seventy-one large-bore components ultrasonically examined, twenty-six (26) were due to the re-examination of previously examined components and forty-five (45) were examined for the first time. In addition, twenty-one (21) small-bore (<2" NPS) ultrasonic examinations were performed on selected portions of small-bore pipe lines and visual examinations were performed on the inside surface of two (2) drain tanks. The ultrasonic examination of large and small-bore components was performed using SNC procedure UT-V-466, Rev. 6, "Ultrasonic Flow-Accelerated Corrosion Examination Procedure". The visual examination of the two drain tanks was performed using SNC procedure VT-V-715, Rev. 2, "Visual Examination (VT-1)".
Eighteen (18) large-bore components were identified to have wall thickness measurements that indicated possible wear due to flow-accelerated corrosion (FAC). The affected components had wall thickness readings that were at or below the "Action Level" wall thickness value assigned to each of the components. The "Action Level" value is defined as the wall thickness which is fifty percent (50%) of the difference between the nominal wall and Code minimum wall. The examination results for sixteen of these large-bore components were reported by SNC Inspection and Testing Services (ITS) to VEGP Engineering Support by means of FAC Notification Reports (FNRs) which are available at the plant site for review. One FNR was subsequently determined to not be required due to the
4-2
component not actually being below its "Action Level" value. The examination results of the other two below "Action Level" components were reviewed by the site FAC Engineer and it was determined that no FNR was required due to the wall thinning not being significant. SCS engineering personnel were requested by the site FAC Engineer to perform an expedited evaluation to determine the continued acceptability of each below "Action Level" component for which an FNR had been initiated. The continued acceptability of small-bore components was determined by the site FAC Engineer. The following is a listing of correspondence associated with the engineering evaluations that are available at the plant site for review upon request:
Affected Component FNR Number/Date SCS Eval. Letter No./Date Type and System 21304031-14-P014 F01V2001, SG-18362, 14" Pipe Section, 04/10/01 04/11/01 Heater Drain System 21304004-12-R032HD28 F01V2002, SG-18373, 6"xl2" Expander, 04/10/01 04/13/01 Heater Drain System 21304123-12-R034 F01V2003, SG-18373, 6"xl 2" Expander, 04/10/01 04/13/01 Heater Drain System 21305-E4-021 F01V2004, SG-18380, 6A FW Heater Shell Wall 04/11/01 04/14/01 Main Feedwater System 21305-E4-022 F01V2005, SG-18380, 6B FW Heater Shell Wall 04/11/01 04/14/01 Main Feedwater System 21305055-16-POll F01V2006, SG-18381, 16" Pipe Section, 04/12/01 04/20/01 Main Feedwater System 21304031-14-POlO F01V2007, SG-18386, 14" Pipe Section, 04/13/01 04/19/01 Heater Drain System 21304031-14-P006 F01V2008, SG-18386, 14" Pipe Section, 04/13/01 04/19/01 Heater Drain System 21305547-34-P017 F01V2009, SG-18391, 34" Pipe Section, 04/17/01 04/20/01 Main Feedwater System 21305055-24-PO07MFW15 FO1V2010, SG-18398, 24" Pipe Section, 04/17/01 04/23/01 Main Feedwater System 21305055-16-EO12MFW17 FO1V2011, SG-18381, 16" Elbow, 04/16/01 04/20/01 Main Feedwater System Downstream Ext. of F01V2012, SG-18391, 21305547-34-E018 04/17/01 04/20/01 34" Elbow, Main Feedwater System Upstream Ext. of F01V2013, SG-18413, 21305055-24-E004 04/20/01 04/26/01 24" Elbow, Main Feedwater System
4-3
Affected Component FNR Number/Date SCS Eval. Letter No./Date Type and System Downstream Ext. of F01V2014, N/A - Determined Not 21304021-30-E029 04/23/01 Below "Action Level" 30" Elbow, Heater Drain System 21305061-16-P018 F01V2015, SG-18412, 16" Pipe Section, 04/23/01 04/24/01 Main Feedwater System Upstream Ext. of F01V2016, SG-18422, 21305547-34-EO20CND18 04/24/01 04/26/01 34" Elbow, Main Feedwater System Downstream Ext. of N/A - FNR Determined Not N/A 21305029-24-R013, Required 30"x24" Reducer, Condensate System 21305157-6-P004, N/A - FNR Determined Not N/A 6" Pipe Section, Required Main Feedwater System
Examination results concerning each of the affected components were evaluated by SCS and it was determined that immediate corrective action was appropriate for two components. Portions of components 21305-E4-021 and 21305-E4-022 (i.e., FW Heaters 6A and 6B Shell Walls) were determined to be below acceptable wall thickness and were subsequently replaced. An additional four of the above components were determined to have significant wear and are being scheduled for replacement during the next maintenance/refueling outage, i.e., 2R9. This includes components 21304004-12-R032HD28, 21304123-12-R034, 21305055-16-POl1, and 21305055-16-EO12MFW17. All other large-bore components were determined to be acceptable for continued service for at least two more fuel cycles and no other corrective action was deemed necessary. In regards to small-bore examination results, five small-bore lines showed signs of wear significant enough to require immediate action during the maintenance/refueling outage. This included portions of four steam drain lines and a feedwater heater vent line. This small-bore piping was subsequently replaced. No other corrective actions were required or taken in regards to Flow-Accelerated Corrosion examinations during the 2R8 outage.
NRC Bulletin 88-09 - Thimble Tube Thinning in Westinghouse Reactors
In response to NRC concerns of thinning in Bottom-Mounted Instrumentation (BMI) flux thimbles in Westinghouse reactors, eddy current examination of the fifty-eight (58) flux thimbles was performed during the eighth maintenance/refueling outage at VEGP-2. The purpose of the examinations was to detect and size indications of possible wear on the outer diameter of the flux thimbles. The examination of the flux thimbles was performed by Westinghouse in accordance with their procedure MP 2.3.1 GAE/GBE-2, "Thimble Tube Eddy Current Inspection at Vogtle Units 1 and 2".
An evaluation was performed by Westinghouse using WCAP-12866, "Bottom Mounted Instrumentation Flux Thimble Wear", on BMI flux thimbles which were found to have indications of wear after the eighth fuel cycle. The evaluation indicates that that the 2R8 data and the projected wear on all thimbles for 2R9 and 2R1 0 is within the allowable limit of 80% specified in WCAP-12866. There was no need for repositioning the flux thimbles or capping at the seal table location.
4-4
In determining the projected wear data for 2R9 and 2R10, the 2R8 values were adjusted up based on the previous data from 2R6 and 2R7. Normally the maximum value of the last 3 cycles is used for this projection, however there were several tubes where the 2R8 data did not correlate with the previous outages. In these instances the larger value from the last two outages that was closest to the 2R8 data was used. This adjustment was performed based on a Westinghouse engineering judgement call.
The evaluation was transmitted to the plant site in Westinghouse letter GP-17252 dated April 25, 2001, for Flux Thimble Eddy Current Data Evaluation and is available at the plant site for review upon request.
Westinghouse Technical Bulletin NSD-TD-90-02 - BMI Conduit Guide Tube Leaks
In accordance with the recommendations in Westinghouse Technical Bulletin NSD-TD-90-02, the BMI conduit (flux thimbles) guide tubes were visually examined for any signs of leakage. The examination was performed by SNC personnel. There were no signs of cracks, pitting, or other signs of degradation to the BMI conduit guide tubes. The inspection was performed under MWO 20002019.
4-5
Technical Specification 5.5.9 - Steam Generator Tube Inspections
NOTE
The following discussion on the steam generator tubing inspections, in addition to fulfilling the reporting requirements of ASME Section XI for Inservice Inspection activities, constitutes the report required by VEGP Technical Specification 5.6.10.b to be submitted to the NRC within twelve (12) months following completion of the steam generator tube inspections. Accordingly, a separate submittal is not being made to the NRC on the inspection of the steam generator tubes performed during the eighth maintenance/refueling outage (2R8) at VEGP-2.
Introduction
During 2R8, the Steam Generator Maintenance Services Group of the Westinghouse Nuclear Services Division performed eddy current testing of two Westinghouse Model F steam generators in parallel from April 18, 2001, through April 24, 2001. One hundred percent (100%) of the active tubes from two steam generators, i.e., Steam Generators 2 and 3, were inspected rather than only one steam generator as required by VEGP Technical Specification Table 5.5.9. The extent of the examinations and their results are summarized in Table I (refer to pages 4-15 to 4-18) including the location and the accumulative number of previously plugged steam generator tubes. Although Steam Generators 1 and 4 were not examined during 2R8, Table I provides information for those steam generators as well.
Tables II & III (refer to pages 4-19 and 4-20) identify the steam generator tubes with indications by location and percent of wall thickness penetration for Steam Generators 2 and 3, respectively. Information is provided only for the steam generators examined during 2R8.
Applicable procedures, personnel qualifications, material and equipment certifications, sign-off sheets, and supporting data, etc., can be found in Westinghouse Electric Company Nuclear Service Division Steam Generator Maintenance Services Field Service Report, MRS-FSR-1091-GBE, "Steam Generator Eddy Current Inspection ", which is available at the plant site for review upon request.
Tube Inspection Plan
Bobbin Inspection Plan
Steam generator tube inspections conducted during 2R8 met or exceeded the recommendations made in the EPRI PWR Steam Generator Examination Guidelines, EPRI TR-107569-V1R5, which were adopted by SNC for steam generator tube inspections. The VEGP inspection plan requires that 100% of the tube population be inspected from two steam generators each outage rather than twenty percent (20%) of the tube population from four steam generators each cycle or forty percent (40%) of the tube population from two steam generators each cycle. This plan offers the advantage of a shorter inspection interval in order to achieve complete steam generator tube inspection and offers an improved sensitivity to degradation mechanisms that might be initiating within a particular steam generator. Each of the tubes examined was tested full length.
Motorized Rotating Pancake Coil (MRPC) Inspection Plan
The inspection program outlined in the VEGP response to NRC Generic Letter 95-03, "Circumferential Cracking of Steam Generator Tubes", was met or exceeded during 2R8. During 2R8, the MRPC inspection plan for Steam Generators 2 and 3 for top-of-tubesheet circumferential cracking exceeded the minimum requirements specified in Revision 5 of the EPRI guidelines on steam generator tubing inspection. Approximately 64% of the tube population in each of the two steam generators were inspected. The MRPC inspections typically were conducted at the top of the tubesheet in a region approximately three inches above to three inches below the top of the tubesheet. The PlusPoint probe was used to conduct the inspections. Special-interest MRPC inspections were performed at hot leg and
4-6
cold leg distorted bobbin (possible flaw) indications using the 0.560 inch diameter Plus-Point probe. The VEGP plans include inspecting twenty percent (20%) of the hot leg freespan straight length and U-bend dings> 5 volts identified by the bobbin probe utilizing the Plus-Point probe.
In response to the lessons learned from the tube rupture event at Indian Point 2, VEGP utilized a dual frequency (high/mid frequency) probe to ensure the data quality for the detection of Primary Water Stress Corrosion Cracking (PWSCC) in the low row U-bends was adequate. Presently, there are no published industry criteria for data quality and signal-to-noise (S/N) ratio. An evaluation of the S/N ratio was performed by Westinghouse on the low row U-bends and the S/N ratio was found to be acceptable for steam generators 2 and 3. A similar study, with acceptable results, was performed on SGs 2 and 3 on VEGP-1 during 1R9. The VEGP-2 review is documented in Westinghouse letter SGO-01-35 dated May 15, 2001.
Inspection Plan Implementation
To summarize the bobbin inspection plan, active tubes, row 3 and higher, were inspected with a Westinghouse 0.560-inch diameter probe throughout their entire length. The rows 1 and 2 straight lengths were tested using a 0.560-inch diameter probe.
The top of tubesheet and special interest examinations were performed with .560/115 +Point Probes at 900 rotations per minute (rpm). Approximately 60% of the rows 1 and 2 U-bend area RPC examinations were performed with High Frequency/Mid Range +Point RPC Probes. After the completion of the bobbin inspection program, special interest MRPC inspections were performed to better characterize indications in the steam generators. Disposition of tubes for which special interest MRPC was performed confnrmed that these indications did not represent serviceinduced degradation.
The Eddy Current inspection program was conducted in accordance with Westinghouse Field Procedure MRS 2.4.2 GPC-3 Rev. 8, Eddy Current Inspection of Preservice and Inservice Heat Exchanger Tubing. Inspection probes used were in accordance with Probe Authorization Rev. 1 and test configurations and acquisition rates were in accordance with the Eddy Current ACTS Sheets GBE-01-101 (Bobbin), GBE-02-101 (TSH and Special Interest RPC), GBE-03101 (Low Row Bobbin), GBE-04-101 (2 Coil U-bend RPC), GBE-05-101 (permeability), and GBE-06-101 (permeability, special interest and restrictions).
Per ACTS GBE-01-101, the bobbin inspection plan withdrawal rate was 40 inches per second and the test frequencies were 630 kilohertz (kHz), 320 kHz, 160 kHz, and 10 kHz. Per ACTS GBE-03-101, the bobbin withdrawal rate was 24 inches per second for low-row bobbin tube inspections. Per ACTS GBE-02-101, the withdrawal rate for the TSH and Special Interest Plus-Point RPC inspection plan was 0.4 inch per second and the test frequencies were 600 kHz, 300 kHz, 200 kHz, 100 kHz, and 20 kHz. Per ACTS GBE-04-101, the specifications for the low row U-bends 2 coil +Point Exam, the inspections are specified. ACTS GBE-05-101 and ACTS GBE-06-101 were written to facilitate the inspection of locations masked by permeability. Each probe, along with its inspection plan, corresponding ACTS number, and the EPRI Guidelines, Appendix H qualifications, is listed on the Probe Authorization dated March 27, 2001.
All tubes on the inspection plan were tested to their required extent. Special interest examinations (191 total) were required in all channelheads. Bobbin examinations were performed with Replaceable Probe Heads (RPH) mounted on WA-RLLC probe conduit. Row 1 and 2 U-bend RPC examinations were examined with a special order two coil high frequency / mid-range (HF/MR) probe. Four U-bends that would not pass the two coil probe head were tested with a standard one coil probe head.
4-7
Inspection Summary Table
The above extents met or exceeded the inspection plan. In some cases, either the required minimum extent was exceeded or additional tubes were tested.
Data Evaluation
Data collection was performed by Westinghouse using the ROSA and TC6700 tester. Data was sent from the site via a data transmission line (T-1) in the ANSER format to the Westinghouse Waltz Mill, Pennsylvania facility. Westinghouse and its subcontractors performed the primary analysis of the eddy current data using Automated Data Screening (ADS) and ST2000 software for Data Management. Framatome performed the secondary analysis of the eddy current data. Resolutions were performed jointly by Westinghouse and Framatome at the Waltz Mill facility. All analysis was performed using ANSER Software. SNC site-specific Data Analysis Guidelines and procedure MRS 2.4.2 GPC-37, Revision 6, "Steam Generator Eddy Current Data Analysis Techniques for Vogtle Units 1 and 2", were used to perform the analysis.
Analysts were required to complete a training session and then were tested on their performance. The analyst training meets the requirements of the EPRI PWR Steam Generator Examination Guidelines, EPRI TR-107569VIR5, which included training tapes, test tapes, and a training manual for SNC. Analysts are required to pass an exam prior to analyzing any new data. One Westinghouse analyst did not pass the required exam and was rejected. Prior to the start of data acquisition a complete history review was performed of all baseline data for VEGP-2 to minimize the impact history lookups would have on the analysis schedule.
The primary analysis was performed off-site by Westinghouse at their Waltz Mill Facility. Secondary analysis was also performed off-site by Framatome at their Lynchburg and Benicia facilities. Remote analysis was accomplished using T-1 lines to communicate between the plant site and the remote locations. Data management was performed off-site with reports being generated on-site via the T- 1 lines. A SNC Level III was located at the Waltz Mill site to facilitate the resolution of eddy current data and performed the duties of the independent qualified data analyst (QDA). In addition, SNC QDA performed random samples of test data to ensure the EPRI requirements were being followed. In addition, all comparison reports between the primary and secondary analysis were verified by the SNC QDA.
The bobbiniMRPC inspections conducted during 2R8 identified no pluggable indications in Steam Generator 2 or 3. The following table summarizes the indications found by stating the number of tubes in which each type of indication was found.
4-8
Type and Extent of Inspection SG 2 SG 3 Bobbin Full Length TEH through TEC 5132 5137 Bobbin 7H through TEC 1 3 Bobbin 7C through TEC 486 485 Bobbin 7C through TEH 244 245 Bobbin 7H through TEH 243 243 +PointTM RPC TSH +/- 3" 3598 3613 +PointTM RPC U-bend, Row 1 -(HF/MR) 73 71 +PointTM RPC U-bend, Row 1 0 2 +PointTM RPC U-bend, Row 2 (HF/MR) 71 72 +PointTM RPC U-bend, Row 2 1 1 +PointTM RPC U-bend, Row 3 (HF/MR) 0 1 +PointTM RPC Special Interest, HL 35* 107* +PointTM RPC Special Interest, CL 7 28* +PointTM RPC Special Interest, U-bend 8 6 * -- Reflects tubes with multiple Special Interest Inspections.
Indication Summary Table
Number of Tubes per Indication Size Steam Generator (S/G)
S/G 2 S/G 3 40% and greater wall 0 0 thickness penetration 30-39% wall thickness 3 0 penetration 20-29% wall thickness 8 3 penetration Less than 20% wall 39 26 thickness penetration Possible Loose Part Wear 0 4 Manufacturing Buff Marks (total tubes) 1139 948 Dent or Ding (total tubes) 200 277
It should be noted that the above table is based on the largest indication per tube. Tubes with multiple indications had only the largest indication counted.
More details regarding indication distributions can be found in the maps, which follow the steam generator tubing inspection discussion.
Degradation Assessment
Prior to maintenance/refueling outage 2R8, VEGP performed a degradation assessment as required by the provisions of Nuclear Energy Institute (NEI) guideline NEI 97-06 and Revision 5 of the EPRI guidelines for steam generator tube inspection. The purpose of the degradation assessment was to ensure that the appropriate nondestructive examination (NDE) techniques and personnel would be used during eddy current testing at VEGP. The degradation assessment provides assurances that the NDE techniques used are appropriate for detection and measurement performance to support growth rates, repair criteria, and structural limits for the degradation mechanisms.
Degradation mechanisms were grouped into categories according to their likelihood of occurrence. The categories include: active mechanisms for degradation previously found in the VEGP steam generators, relevant mechanisms for degradation found in similar plants with the same tubing material and similar design features, and potential mechanisms for degradation not found in similar plants but not judged to have a meaningful potential to occur based on historical or laboratory data. Other degradation mechanisms judged to be non-relevant for Westinghouse Model F steam generators were addressed in the assessment A subgroup included in the assessment identified the process applied to resolve potential indication signals in order to classify the signals for disposition relative to leaving the tube inservice or repairing the indications.
The only observed degradation mechanism at VEGP is anti-vibration bar (AVB) wear. As defined by the EPRI guidelines, the AVB wear observed at VEGP is not considered an active damage mechanism. The VEGP inspection plan requires the use of the bobbin probe to test all tubes in contact with the AVBs for the SGs tested that outage. The VEGP inspection plan is more conservative than the EPRI guidelines. Potential degradation mechanisms included in the assessment are Outside Diameter Stress Corrosion Cracking (ODSCC) and PWSCC which have been detected in thermally treated tubing in European plants. The VEGP inspection plan includes MRPC inspections at the top of tubesheet expansion region and at the small radius U-bends for detection of stress corrosion cracking (SCC). The assessment also concluded that the likelihood of initiation of both ODSCC and PWSCC at either the top of tubesheet expansion region and the small radius U-bends is considered low for VEGP.
Non-relevant degradation mechanisms include those degradation mechanisms observed in other steam generators with differing materials of construction and manufacturing practices. In general, these mechanisms are associated
4-9
with drilled-hole carbon steel tube support plates (TSP). The VEGP TSPs are broached, quatrefoil tube holes with stainless steel TSPs. The likelihood of initiation of these degradation mechanisms at VEGP is considered remote.
In response to the lessons learned from the tube rupture event at Indian Point 2, VEGP utilized a dual frequency (high/mid frequency) probe to ensure the data quality for the detection of PWSCC in the low row U-bends was adequate. Based upon our acceptable S/N measurements and the difficulty encountered while trying to push the double headed high/mid frequency probe through the row 1 tubes, it was determined that enough data was collected with the high/mid frequency probes to accept the single headed (mid-frequency) probe data. Approximately 60% of the total row 1 and 2 U-bends were examined with the high/mid frequency probe.
For each degradation mechanism identified, the assessment specified the probe(s) to be used during inspection, the detection qualification including techniques sheet and estimated probability of detection (POD) information, the inspection sample plan, and the basis for expanding the inspection, if required. The degradation assessment also included information supporting the sizing qualification (when sizing is applied) including technique sheet and uncertainty data.
Condition Monitoring
There were no steam generator tubes identified during 2R8 that challenged the structural integrity recommendations of NRC Regulatory Guide 1.121. Furthermore, there were no tubes that required in-situ leakage testing or pressure testing. The only tube degradation mechanism observed at VEGP-2 during 2R8 was tube mechanical wear at AVB and Baffle Plate intersections. The AVB wear observed during 2R8 was consistent with the historical performance and structural expectations as projected in the degradation assessment report. No tubes were found to have experienced excessive AVB wear. Based upon the results of the Wear Projection Technology, tube stabilization will not be required in either generator until after the end of plant life (38 years allowing for 20 year life extension). The VEGP-2 pre-outage degradation assessment identified a structural limit of approximately twenty-four percent (24%) (remaining wall thickness) for AVB wear which satisfies the requirements of NRC Regulatory Guide 1.121. The following table lists indications seen after final disposition during the inspection. Only AVE percent wear indications are representative of a tube degradation in the VEGP steam generators.
2R8 Indications/Signals Condition S/G 2 S/G 3 AVB AVB % Wear Indications 95 43 BLG Oversize Tube Diameter 11 33 DFI Freespan indication (+Pt confirmed) 0 0 DFS Benign Freespan Signal 134 145 DNG Freespan Ding 132 187 DNI Distorted Ding/Dent Indication 0 0 DNS DNI cleared by +Pt (+Pt confirmed) 1 0 DNT Dents (TSP, Baffle, TS) 129 218 DSI TSP Indication (+Pt confirmed) 0 0 DSS DSI History Cleared 37 28
MBM Manufacturing Buff Marks 1788 1588 MMB Multiple MBMs 10 0 PCT Bobbin Sizing 95 43 PLP Possible Loose Part 0 4 PVN Permeability Variation 8 1
4-10
VOGTLE 2R8 AVB WEAR INDICATION SUMMARY
S/G # IND # Ž 40% Max. % Depth 2 cycle 95% A 2 95 0 37 3.46 3 43 0 27 2.11
Degradation Mechanisms
As defined in the degradation assessment, indications were categorized as observed, relevant, and non-relevant based upon their likelihood of occurrence. The AVB indications observed during 2R8 were consistent with expectations. For the ninety-five (95) indications reported in Steam Generator 2 and forty-three (43) indications reported in Steam Generator 3, none exhibit per cycle growth rates in excess of the 95% cumulative distribution allowance (11.7%) on the basis of prior cycle and documented in the Degradation Assessment Report. Forty-four (44) "new" indications, none > 16% in depth of penetration, were reported: this number was adjusted downward to 5 after lookups from the 2R6 data for new indications. None of the AVB wear indications were found to challenge tube integrity requirements and condition monitoring requirements are satisfied for these indications.
Foreign objects have been reported at VEGP-2 in prior inspections. Five PLP indications have been reported in SG 3 for 2R8. Those in the neighborhood of Row (R) 41 and Column (C) 25 are believed to be associated with a strap identified by visual examination in 2R7; loose parts evaluation indicated that no excessive wear was anticipated. A PLP signal was reported at SG 3 R21/C58-TSH+0.15"; no indication of wear is associated with this location. A visual inspection of this area did not indicate the presence of a PLP due to no definition of shape. The area identified appeared to be a scale bridge. If there is a PLP at this location, it is covered with scale that will prevent any relative motion or drag force.
There were no indications of outside diameter (OD) pitting or transition zone stress corrosion cracking detected. These degradation modes have not been observed in US Model F SGs with thermally treated tubes.
U-bend PWSCC, ODSCC related to the presence of freespan dings or support plate level dents, and sludge pile ODSCC are degradation mechanisms that have not been observed in similar SGs but are considered on a contingency basis should such indications be detected. There were no indications attributable to any of these mechanisms at VEGP-2 during 2R8. The likelihood of occurrence of these indications have the lowest probability of occurrence in the Westinghouse Model F design steam generators.
Indications reported in the VEGP-2 steam generators include manufacturing burnish marks and benign indications. The signals associated with these categories do not represent in-service degradation. The locations of these signals were carefully monitored for change from baseline or initial condition. In addition, approximately 191 other locations were re-examined with the Plus-Point probe because of questions concerning the nature of their bobbin signal. All these locations were confirmed to exhibit characteristics that were not indicative of tube degradation.
All straight tube section dents (Ž_5 volts) in both SG 2 and 3 were examined with Plus-Point probes. Also, twenty percent of the U-bend dents Ž_ 5 volts were examined with a Plus-Point probe. All of the locations tested in both S/Gs were reported as No Detectable Degradation (NDD). The dings and dents in Model F SGs do not result from TSP corrosion, because the 405 stainless steel plate quatrefoil tube hole design is unlikely to support in-service denting. There were no indications for the dents and dings other than the change in geometry and no degradation was detected.
AVB Wear Projection Technology-based Assessment
The Wear Projection Technology's Outage-Follow Mode application supporting the VEGP-2 2R8 Outage provided daily, and cumulative, confirmation that there was no wear site data obtained during the outage which indicated a need for tube stabilization (or tube plugging during this outage). Further, a near-worst-case interpretation of the largest (worst case) tube / AVB wear site increment (of 16% between 2R6 and 2R8) was evaluated. This evaluation
4-11
indicated that, for this near-limit-case scenario, the margin relative to requiring stabilization at expected end-ofoperation (with a 20 year Plant-Life-including life extension) is more than 38 years. Westinghouse concluded that the tube U-bend wear degradation mode is presently not strongly progressing in VEGP-2 Steam Generators 2 and 3.
Operational Assessment
NEI 97-06 requires that a "Forward Looking" operational assessment be performed. This assessment must establish if observed degradations mechanisms will continue to meet tube structural and leakage integrity requirements at the end of the upcoming cycle. This is calculated by adding growth rates and NDE uncertainty to the largest flaw left in service (the maximum indication that can be left in service is 39%). Performing this calculation using a 95% Confidence Limit (CL) the projected AVB wear at 2R9, when SG 1 and 4 are next inspected is 39% + 14.8% + 4.3%, or 58.1% Through-Wall (TW). For 2R10, the calculation for SG 2 and 3 is 39% + 14.5% + 4.3%, or 57.8% TW. This is below the structural limit of 75.75% TW identified in the Degradation Assessment, therefore tube integrity is demonstrated and operational assessment requirements are met for two-cycle inspection intervals.
The above evaluation is conservative based on the following:
1) The growth rate for the inspection period ending at 2R6 was used. The 2R6 data was used as a conservative measure since the observed growth rates were negative for end of 2R8.
2) Generally, the largest growth rates do not occur at the largest indications left in service. 3) Largest wear assumed to be left in service was 39%.
The 2R8 growth rates for the AVB indications were, on the average, slightly negative. SG 3 had a more negative average change that did SG 2. The general implication of this is that there is little or no growth to the AVE indications as a population. As addressed in the Condition Monitoring Operational Assessment (CMOA), this negative growth rate can be attributed to slight differences (still acceptable tolerances) between the standards used in the inspections. In summary, based on the CMOA evaluation, the negative average growth rates observed for AVB indications during 2R8 imply little or no average growth in the population charted.
The projected wear using the observed data for 2R8 would be significantly less. The end of cycle (EOC) wear for 2R10 in SG 2 is 43.2% TW. The EOC wear for 2R10 in SG 3 is 32.2% TW. The EOC wear for 2R9 in SG 1 is 42.2% TW and EOC for 2R9 in SG 4 is 5 1.0% TW. These values using the observed 2R8 data are significantly less than the conservative calculations above using 2R6 growth rates and maximum allowable wear for return to service.
The projection used at 2R7 for SGs 1 and 4 employed a 15.1% growth allowance. Therefore the 2R7 projection for 2R9 remains the most conservative for these SGs. These projections predict maximum wear depths well below the structural limit of 75.75% TW identified in the Degradation Assessment; thus, tube integrity is demonstrated and the operational assessment requirements are met for two cycle inspection intervals.
AVB wear is the only systematic degradation mechanism that has been observed at VEGP-2. Based on application of conservative prior AVE wear growth rates, the condition of the VEGP-2 SG tubes has been analyzed with respect to continued operability of the SGs until the end of Cycle 10, without exceeding the structural integrity recommendations of draft Reg. Guide 1.121. Conservative projection of the AVE wear in SGs 2 and 3 to EOC1O indicates that all structural criteria will continue to be satisfied until the next planned inspection for each SG. Similarly, based on the current data from 2R8, projections for SGs 1 and 4 to EOC9 indicate that all structural criteria will continue to be satisfied for these SGs as well until their next inspection at 2R9. The conclusion for SGs 1 and 4 will be re-evaluated based on the data from 2R9.
4-12
Visual Inspection
A visual inspection of the tubesheet was performed of plugged tube ends to identify signs of leakage. There were no signs of visible leakage from plugged tubes. Westinghouse procedure MRS-SSP-1 102-GAE/GBE, "Visual Inspection of Mechanical Plugs for Vogtle Site", was used to inspect the tube plugs.
Mechanical Plugging
As noted above, there were no tubes required to be plugged in steam generators 2 or 3.
By letter LCV-1536, dated May 2, 2001, SNC notified the NRC pursuant to VEGP Technical Specification 5.6.10.a and reported that no tubes were plugged in SG 2 or 3 during 2R8.
VEGP-2 Outage 2R8 Plugging Summary
SG2 SG3 Tubes plugged this outage 0 0 Tubes previously plugged 7 1 Total plugged tubes 7 1
4-13
Maps
1. Steam Generator 2 - Bobbin Inspection Plan - Cold Leg (page 4-21)
2. Steam Generator 2 - Bobbin Inspection Plan - Hot Leg (page 4-22)
3. Steam Generator 2 - Tubesheet +PT Inspection Plan- Hot Leg (page 4-23)
4. Steam Generator 2 - UB +PT Inspection Plan (page 4-24)
5. Steam Generator 2 - Bobbin Test Extents (Actual) (pages 4-25 and 4-26)
6. Steam Generator 2 - +PT Tests Extents (Actual) (pages 4-27 and 4-28)
7. Steam Generator 3 - Bobbin Test Program - Cold Leg (page 4-29)
8. Steam Generator 3 - Bobbin Test Program - Hot Leg (page 4-30)
9. Steam Generator 3 - Tubesheet +PT Inspection Plan- Hot Leg (page 4-3 1)
10. Steam Generator 3 - UB +PT Inspection Plan (page 4-32)
11. Steam Generator 3 - Bobbin Test Extents (Actual) (pages 4-33 and 4-34)
12. Steam Generator 3 - +PT Test Extents (Actual) (pages 4-35 and 4-36)
4-14
TABLE I
Steam Generator 1
Total No. of Tubes:
No. of Tubes Inspected:
No. of Tubes Degraded:
No. of Tubes Defective:
No. of Tubes Plugged Prior to Outage 2R8:
No. of Tubes Plugged during Outage 2R8:
Total No. of Tubes Plugged:
Overall Percentage of Tubes Plugged:
5,626
5,622
N/A
N/A
4
N/A
4 (plugs located at Row 1, Colunm 1; Row 27, Column 42; Row 54, Column 35; and Row 48, Column 26)
0.07%
4-15
TABLE I (continued)
Steam Generator 2
Total No. of Tubes:
No. of Tubes Inspected:
No. of Tubes Degraded:
No. of Tubes Defective:
No. of Tubes Plugged Prior to Outage 2R8:
No. of Tubes Plugged during Outage 2R8:
Total No. of Tubes Plugged:
Overall Percentage of Tubes Plugged:
5,626
5,619
11
0
7
0
7 (plugs located at Row 2, Column 48; Row 5, Column 48; Row 16, Column 103; Row 48, Column 98; Row 53, Column 86; Row 50, Column 67; and Row 51, Column 32)
0.12%
4-16
TABLE I (continued)
Steam Generator 3
Total No. of Tubes:
No. of Tubes Inspected:
No. of Tubes Degraded:
No. of Tubes Defective:
No. of Tubes Plugged Prior to Outage 2R8:
No. of Tubes Plugged during Outage 2R8:
Total No. of Tubes Plugged:
Overall Percentage of Tubes Plugged:
5,626
5,625
3
0
1
0
1 (plug located at Row 25, Column 102)
0.02%
4-17
TABLE I (continued)
Steam Generator 4
Total No. of Tubes:
No. of Tubes Inspected:
No. of Tubes Degraded:
No. of Tubes Defective:
No. of Tubes Plugged Prior to Outage 2R8:
No. of Tubes Plugged during Outage 2R8:
Total No. of Tubes Plugged:
Overall Percentage of Tubes Plugged:
5,626
5,609
N/A
N/A
17
N/A
17 (plugs located at Row 48, Column 25; Row 3, Column 35; Row 12, Column 36; Row 57, Column 46; Row 8, Column 56; Row 52, Column 56; Row 16, Column 57; Row 51, Column 59; Row 48, Column 64; Row 23, Column 67; Row 51, Column 73; Row 22, Column 90; Row 24, Column 93; Row 57, Column 45; Row 50, Column 67; Row 57, Column 44; and Row 44, Column 21).
0.30%
4-18
TABLE H
Steam Generator 2
Row Column Reference Point Distance from Wall Thickness Plugged (Note 1) Ref. (in.) Penetration (%) (Y/N)
(Note 2)
42 19 AV3 -.03 11 N 43 20 AV2 -.26 13 N 54 38 AV4 .00 15 N 38 39 AV5 -. 17 22 N 39 43 AV3 .00 19 N 39 44 AV5 .00 13 N 40 48 AV4 .00 22 N 59 56 AV4 .26 12 N 40 58 AV5 .00 33 N 43 64 AVI .00 17 N 52 71 AV4 .00 37 N 44 72 AV5 .00 12 N 51 72 AV3 .00 11 N 40 73 AV5 .00 17 N 43 73 AV4 .00 21 N 52 73 AV4 .00 36 N 38 74 AV2 .00 15 N 42 74 AV2 .00 28 N 49 74 AV3 .20 20 N 51 74 AV3 .11 16 N 57 79 AV3 .00 9 N 38 81 AV6 .00 12 N 51 87 AV5 .00 29 N 39 88 AV4 .00 18 N 42 88 AV2 .00 12 N 53 88 AV5 .06 18 N 50 89 AV5 -. 11 13 N 51 89 AV5 .06 29 N 53 90 AV6 .00 9 N 49 91 AV2 .00 22 N 28 115 AV6 .00 19 N
The above information is based on the largest indication observed for the respective tube during the eighth maintenance/refueling outage at VEGP-2.
Note 1: Reference Point Location Description
Note 2:
TSH, TSC - Top of Tubesheet Hot and Cold BPH, BPC - Baffle Plate Hot and Cold #H, #C - (# = Number) of Support Plate Hot and Cold, e.g., 2H, 2C AVI, AV2, AV3, AV4, AV5, AV6 - Anti-vibration Bars
Unless indicated otherwise, distance is above Reference Point. A negative number, e.g., -2.00, indicates that the distance is below the Reference Point.
4-19
TABLE HI
Steam Generator 3
Row Column Reference Point Distance from Wall Thickness Plugged (Note 1) Ref. (in.) Penetration (%) (Y/N)
(Note 2)
32 12 AV5 .00 19 N
34 13 AV5 .14 20 N
38 15 AVI .00 14 N
32 16 AV2 .00 14 N
41 19 AV4 .00 12 N
42 19 AV5 -.49 11 N
42 20 AV4 .00 13 N
43 21 AV2 .06 11 N
44 21 AV2 .00 15 N 45 22 AV3 .12 15 N 44 23 AV3 .19 11 N
45 23 AV3 .19 15 N
47 24 AV4 .00 18 N
47 25 AV2 .00 14 N
48 25 AV6 -.03 9 N
50 29 AV4 .00 11 N
51 31 AV6 .00 11 N
48 37 AV3 .14 13 N
54 38 AV5 .00 13 N
57 48 AV6 .03 13 N
57 49 AV4 -.08 10 N
58 49 AV6 -.08 16 N
42 53 AV4 -.27 9 N 39 72 AV3 .25 16 N
41 77 AV4 .36 22 N
57 78 AV2 .00 10 N 56 82 AV3 .00 27 N
42 104 AV6 -.05 10 N
40 106 AVI .52 10 N
The above information is based on the largest indication observed for the respective tube during the eighth maintenance/refueling outage at VEGP-2.
(1) See Note 1, page 4-19.
(2) See Note 2, page 4-19.
4-20
0
LLJ ui
0
LL z
m
LU 0 m
C\j
LO
X
c
Lu LU co C/)
< = m FCO cn
is U) rn w Ln
N co
Ln Ln .9 Ln CD U) Ln n v cv LO
x x
x x x xLn
ts
Uj m
Ln
LLI cm cm M
N
x x x x. .1 x xx .1 1. x
, * , x x x x . z x x x . x xx
x x x x x x x x x x x x x x x x x
I x . . x x x x x x x . 1. 1. x x x x I X x x x x x x x ;X x
x x x x . x . . . .
x x x
N x x x x x x x
. .I x *x x x .1 .1 t x x . x x x x
- -- .
x x x x x x x x x x x .1 Ix x, xx xx xx xx x, Ix xx x, ij
I x x
x .1 xx x x x x
xx x x x x x x x x x x
X X x x xx x. 1. .1 Ix xx xx .1 1. xx Ix xx xx .1 xx xx x Ix 1. xx x . . . . x x . x x x xx x, ýx ýx x x x, .1 1 Ix x xx .1 . xx xx x
, x x
x
-x -x x
x x x x x x x
x x
xx I
x x x I x , x x x x
x x x I
x x x . x x x
x x x x x x x x
x
x x I I x . . x x x x
x x x x
. . . .
x x x x -x xx xx x x x x x x x x x . x x
x x
x x x x x x x . . . .
x x x x x x x x x x . x -x x
x x : x x x x
x x x x x x x , x . x .
xx x x,
x ý x x :
x x . x x . .x x x x x x x x x x
xx x
-x x x x x x x x x x x x
x, x ". x x
x x x . . .
x x x x x x
x x x
x x x x x
x x x 1 x x x x
x
x x x x x x x x x x x x x x x
x x, xx ýx x- x x, ýx ý, x, x, x x x. x x x x x x x x x x x x
- , x I I
13
in
x
tri x. v
x x x x
CS, x
x x x x
Lf) x Ln x x
x x x x 4D xx xm xm xx x . W, x x
w
x I I ,
x x
x
x x x to x x r, x
x x
x In
x x x
x x x x x x x x
x
x xx .1 x. . x x
x x
x x x x x x
x x x x
x x x I x . . . x x x x x x x
x x 'x
xx wx x x x x x x x x x x x
x- - x, "x i x x , x
x . x x x . x
x . . . x x m x x x x x x x x x x, x" "x x I I x x . x x x i
x "x x "x x x x
x . x . x x x x
x x x x
lxx
x x x
x. x x x x . . . x x x . x x x
x x . x x - x . x x x x x x x .1 ol C', " w x x x x x x x x x x x to co C4 co x x (a *2 co C., in M
x x x I I x --- " 0 x x x x . x x x x x x x x x x x x x x x x x
Cl) 0 67 03
x x x x x x x x x x x x x x x . x x x x x w x x I fA f, fo W .1 1 1 x * rd) 0 co co
x x19z x x x x
x x x x . x x x x x x
x -x . x x x x
x
- - - " x x x x
x
i x x x x x xx ýx "x x x x 1 x x x x x X K X
x . . .
x x x x 2 x x
x x x
x x x x
x x x x x x x x . x
x x x x x x x x x x
c x x x x
: x x x x : x x . .
x x x x
x x x x x
x xx x xx x x x x x X
1
xx x x I x x x x
x x x x x x
x . x x
x x x x I
x x x x
xx .1 xx xx
x x x x
x x x x
x x
- . . x
x, xx x x x x x x
x x x
x x x
x x xx x
x xx
ýx x
xx .
xx x x
xx -x-x x-x- -x-x
t x x x
x xx
x x
x xx , xx
x x x-xx x x x x .
t x x x x
co 0)"0,ca
to ca co co to
C13 02 co co '9,00, CO co ca CO co co
000 co 'A rA a Ln,
x x x x x x x x x x x x . x . x x I
x x x x x x x x x x x x x x x x x x xx xý x
. x x x xx x xx x x x x x x x x xx x x x X K X X X X X . X x x x x . x x x . x . x
x 1
w &co 03 co co
WCoca 0 i
CO co
U)x . x x x . Z x x x x x x
x x x x x x x x x x x x x
x . x x x x x x x x x . x x
x x x
x x x x
: x . xx
-x 1. .1 x x x
I x I x x x x
x x z
ý--x ýxx--x- -xxx x x x 2
I I I x . I
x x x xx *.
x x . x i "x
x x x x :
I I x I I x x
x x x x x .1 x x- x "x x x x x
x
" I
x x
CO to C4 to co co 0 w (a w 0 co W (n co Go to 0) co rA co 0000 11
61 S. 6,
W
z
0
w
a_ U) z Z
Co 0 9 uj LL UJ
C)
LO
m IX
0) N
icpo oý . .; x x x . x x x x , x x x x x K x x - x. x x I x x x
x x x x x x x x x x x
xx 'x xx xx .1 x x x x x x x x x x : x x x
I
x x x x x x x x
x x x x x x x x x x x x x x x x I x x x x x . x x x x x x ý x 7 .7T6 x x x x .... I x x x W 0 to xx x x x x x x x x x x x x C4 to co x x x x x x x xx : x- x
'
x 0 Co co cc.1 x x x x
.xxx x x x x
x x x x x x x x x x x x x x x x I
x - x x x x x - x x x xx x,
x x x x
x x x x x x x x 1 X x x x
xx xx -x
x x x x x x x
xx x x x i
x x x x x x x x x
x x x x x x x
x x x x
x . . . x x x
x x x x x x , ,
x x x x x x x x x x x x x
x x x x x x x x x x x x x x x x x x, x xx x x: x x x x x x x x xx xx X :
x x x x x x x x x x x xx x x
co W w Cl) co co co co
x x X x x x x x x xx xx x x x xx xx xx 'm xw x x, xx xx x x x x
x x x . x x x x x x x xx x x Ix x x x x
x . x x x x x x x xx x x x x
, , x xx x x x ococow CO (a 00
xx x
: x, x xx X, x : x x -x x x x x
x x x x
x x xx x x x x
XX K X- XX
,
x x x x
x x x x
x, x x x x x x x x x
x x
xx , x x x x i
x x xx x . x . x x x x
xx x x. x-
x x 1 x . ý .... : x x x x : x x x x
xx x xx x x
,
x
x I x x x x x x x x x x 1 x
x x ý x x x x x X
x x xx x . x x x x x x
x x x x x x x x I x x x I
x x I x x x x, x x x x x x I
x x x x 1 x x x x x x x x
co co " C. go co C* co ca 0 (1) rA W) 6p (7,
ca I*
60 GO CO 0 0Go co
IS -4
Lo
CD
x . I - I -x _ X
- w ' ' ' X X x x x x x x x x x x x x x xx x x x x x x x . x x 'x x x xx , x x x x x x x x x x x x x x x x xx x x x x x x x x X x x x x x x x x x x x x x x x x x x x x x x x ...x x I I x x x x xx x x xx
x x ... x x x x x x . x x x .1 x, -xx xx x xcocowco cocow 0101 C., Co 67
6,
x x- x x . x x xx x x i x x x x x x x x I x x x x x x x x x x x x x x x
x x x x x - x . x x x x x . x x x x x x I . , . . - "
V) 07 co C') co co
co a *I C., (a co
A12
to U7 W) ýl 11 m All Lei ep Le) cm N
4-21
: co 03 co co m cli 03 (a co co W 40 (a Go co co w (0) FA 09 Go , , w co co U) co co co ....
co rA co CD
03 co to 03 C9 0 0
0.11.0 0.1 co cli (a co co CO (4 "
1496,44" CIS
c) c) co C', Q3 0 co (1)
ý 0 0) 67
fA co 0 co CD m
i 02 V) Go w (4cowco 02 (a ca co
: ca CO V) co 0N
x x x x x x x x x x x x x x x x x x x . x x x x x I
x x x x x
x x x , cn 0 CO cc
X x , x ca 0 co cc x x 0 C7 co
x x xx x IN,
x x40....
U,
x x
1
Ix
C0 14 10 1,
T
SG - 2 .560 BOBBIN INSPECTION PROGRAM Hot Leg - ACTS: GBE-03-101 RO Vogtle U2R8 GBE F S 243 TEST STRAIGHT SECTION WITH
.566 BOBBIN
0 244 TEST FROM 7C THROtUGH TEH WITH
.560 BOBBIN PROBE
o 7 PLUGGED TUBE
120 116 110 105 100 95 90 85 8 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5
0004 0000 )00001
00 00...... ......... 0000 000 ,,0ooo 0000 .... ......... .. ..... .......... .... 0 0... .
4) .o :::o 0o0,,, ..o *•
04)o •. ..? ; t ' : ' ~ k tT T ] ; :. . .... .... •:,:o. s00 0 .... 1 .. .... .. ..... ..t 00 0(1 ... . .... . . . . . . . . . . ... . -00.. .. . . . .. . .o
o 00.0............................................ • ...................... t.... t... .... t.. . 45 45
03 0 ?o o .. . . . . . . . . . . . . . . ., . . . . . .. ... ...._ . • .. ?O~ .0 0
3 . . . . . . . . . . . . o ................. 00.... •.... 1.... •.... ........... •............... • • •......... }.... }.... •.... i..........2
00 .... .. .. .. .. 0. : : : : :: : ; ,::: : : :.•" " "o S:: , : : : : : : ::: : : : :.: . ... . . .. ......
25 35
0 0 .. . . . . . . . . . . . . . ... ..: : : : : : : : : : : :1 . : . . . .. . . . . . . . . . . . . . . .. . . . . .. . . o(
0 20
20--
15
10
5
O0 .0
o. .. .. .. .... . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . ............... .................. ...... 00... ............. ...
006
00. .... . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . ....................... .......... ... 0
o .000 ... .. . .0
0 A Ainrrnf In A AAAA flnfl AAAA In lfl IA Ann A AnnA AAA AAnfi nnnn AfiflAn~ An A flAAA AAAAn Ann nnA nfln AAAAA lA lA An"A
nnr nnnnnnn
A
f) rnnn~rn~ AAA~~AlA AAA , fiiiiffff llllffA A.A An Af AAA 22iA An~ AA AAA
3 SSS S SS SS S S I SS SS S 8 SS S SS: S , S8 S B S S S S 1 1 S I S S S 1S S 9 5 9S 8 5 8S 7S 7 6 58 3 5 S S 4 4 S S S 3 S S S S S 5 SS S S S S
120 115 110 105 100 95 90 85 80 75 70 65 60 55 s0 45 40 35 30 25 20 15 10 5
15
W4 04 M0 0D 40 04 m4 0 0 40 40 V4 44 m4 m4 N N - 4
II 4. 4 .44x.44.44.44444.
L0
LU
LO) en IC
LW
(D 0 0ý
z 0
CL CU) z
LUI
LL 0
CLN
LO 66 a) 0 0.
40 44
04 40
x I -e-I-I-I-*----I-I-I+- + - - I-I - - - -x I I444.4. x . .4*. x x.4 >. x. . .4 44.444444444I 444x*I 44 I . .44.4. . ..4.4.44.4.44.44.4.44.4.44.44.4 .44.4.4.4.4.4.4*4. 4.4
40 x_ .. .. x x i 4X X44444 X . .X .4X .44 4. 44.). .4x.4)4)
__ _ ~ o 21.-....1...... .. ... .0.. .. .. .w t. x .4 . x.I.I. I X .1 .1 1 1 .1X x I 1 .1 1 1i X. X X x I X I I I4 x.4 X .4 I4 4 I4I.4 . I
___ 1 x 4 . .. .44 44424. .4....444...44 .4.4444.44I 1 .4444.. 44I I
o.......' xWx x X 0.
G0 00
0 ~ . .oo . . ... IIii0 a) kx xxx 4.4.4..4. 4 .4............ .4..44444.4.444.4.444 x.4.4444.44I 4444. 4
e ~ ~ ~ x x x x x I I4 I I :144.I4.4 i I I I4 x X I I 4
x.4.x4 x 4).44 x 4 .44x4 44. .4 4.4.. 4444 .. .4... .4444 . .4.4.4.442.x4 xx xI
I41.0 0. . . . . . ..44 4 .44 4. 44.4. . . . . . . .4. 4 4 4 4 .4..444.44..444.44 4 )I44 4 24 4. 4 . 4)... .4
x x x 044444. ~0. :wwu.4..4.4.4 r 4 . . ... 0
.4. 44444 444.4 .44444.. .444 1 .4444.4 .1 . .1 X, .444.4. .4444444 4 44.444.. . 4.44.4.
k4 xxxIxo 444444~~~~~~~~~ 4444424444 I444 I4444..4. 44444 44)444444 4.4)
04~ ~ x4444444444.......... x x x x x I xx I ; x x x xK x x x x x .44444.4 .4. . :4.44
0 . 00.4.0
400 .~ .4 .0...
x .4> x x 4 4.44 . . .4xI
44 4 4 4 4 4 I 4 4 4 4 4 4 4 4 4 4 4 4 4 I4 4 4 4 4 44X4 4 4 4 4 4 4 4 4 4 4 4I4 4 4 4 4 4 4 4 4 4 4 4 4 44xI W x X x x x x : x .4.444444.44.444.4 4.44I 4 44444 .444 . 4.4.4.4. 44.4.4.4. .44.4..4
x x 4444 444.4.444
I44
x4
X.44
x'x .444444444444444 44444 444.. 4.0
04Ln _ _ _*
00 0 0.0 x4 x44. 4444 4444 4444 4444444..44.. 444 .. 4.4..
" I44 . .I 4 4 4 4 4 . 4 4 I4 .x4x4 4 x x4x4 4 4 4 2 4 . 4 4 4x 4 4 4 4 4 4 4 4 4 4 4 . 4 . 4 4 .I.x . 4 4x . 4 . 4 . 4 . 0 .
oo..l .... o.... .4.4.4, *4444:44:.4 .4444 .4444...44.4..4....... 444.4 44.444
LO4 4 4 4. . . 4 4 44 4 4 4 4 4 4 4 4 4 4 4 4 . .4 4 4 . 4 . 4 4 4 4 4 4 4 4
9D .4447.4.4 .4.. 'x 4444..44 744444444 L444. 4x44444.4X x xxx l
40~~~~~~~~~~~~~~ i4.4~4444.4..444.44)444..0 ... 4 4444 4.)4
0 0I .44....... 4 .44442>..4 .44.4 .4.444 44444 1.44 1
4.0.44;4: .444.4.4444244. 444.) .4444 I44.. 4444x.4.x4 xx xK
n0.. . 4.44. 4 . 4444...44 ....
04x .4 00 N~~, x x x4' x4444....
-~~~~~~ ______ ______ !- -666-- -
04
4', '0
I__ I__ I -- 60 I---- I- + I~~~. .4444 444 4. 4. 44 . 4.4.).).4.4.4. .
I I44 I.144.. 5.4 x444..4x.4.4.4 x* x )4)4I
1~x 4. 4. .4 .4.44x .4.4.4444&44444.444
4.4.4
x .4 ..4 x x x .4 x 4.4
In0
40 a V) 1 in cp tn 04 In 0 40 W4 44 *t ) m4 N N -I -
4-23
x x I x
x x
SG - 2 .520 UB +PT INSPECTION PROGRAM ACTS: GBE-04-101 RO Vogtle U2R8 GBE F
N 145 TEST U-BEND
"1 7 PLUGGED TUBE
105 100 95 90 85 80
00
0
0000 0 ...
75
,OOOO0
70 65 60 55 000 T0 0 0 0
0 00
?•00 :: ,,,,0,:O1???OO
50 45 40 35 30 25 20 is le
000
.... 0000
0001i .. .. . . . . . . . . . . . 0000
00" . 0 ... .. . . .00.
0 .0
0o ? . . . . .. . .. 00 c .. . ..000.. . . . . . . .. . . . . . .. . . . . . . .00 1
100.
- --,-- -- - -- - - -- - - ------- ---- -- ----
00 .. .00. .
0 .00
10..0:0 00
00.0
00.0
0 ....... .. . . . . . . . . . . . . . . . . . . . .
0? ..... . . . . . . . 00 ..... 0 00... . .. . .. .
( 00.. ....... .. . . . . . . . . . . . . . . . . . ... ..00 0
00 . .. . .. . . .. . .. . .. . . .... ... .. .. .. .0 00 .... ...... ...... ....... .... .... .... .... ... ... ...
0 00. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
- -.... .. i....... .... .... .... ......... .... .... .... .... .... .... .... .... .... ...................................
0 .................. .... ........ .... . ...... .... .. .... .... .... .. . .. . 0
a.......................................................................................0
/
120 115 1e
55
45
40
35
25
20
15
5e
5
o inon , n n o nAnon o %n An > noN no 4 ,no n n An, An, on n onoA g non- ,o no no1 , g An n n, Anfon non on n no4,Anon, o i An on
120 115 116 105 10. 95 90 86 80 75 70 66 60 55 50 45 40 35 30 25 20 15 10
".0
'nono5
<
S @1 ST Oz Sz ac SE oi' l V as ss9 09 s9 aL si 0M sa 06 s6 oat SOeT oil sTi anI
LLLL LLL, ZLiiLiLt. 4LZLLLLLLL, LLL, 444LLL
9333- -3-3-3-33333 3333
333 3333 333 3333 333 3333
3333333 3333 333 3333
33 3333 33 3333
LLLL LLLt LLLL LLiL
13333 !3333 13333
13333 13333 '3333 13333 13333 13333
:iiLiW ZLLLL,
ýLLLLi
L4LL•,
Liii. iLL 1,
LLLL,
iLLi LLLL
LtLL SLLLiLiLL4 LZiii
uLLZI LiLi,
ZLLL,
LLLL, .4LLL,
.LLLL
.LLLL
it ii 'L4LLL
'LLLL
'LLi LLiLt
:iiiLL 4LLL ýLZLL •LL LL
Liii, LILLL•
:LLLL, .Liii'
4L4, •LLLL,
LL4L,
Liii, •LLLL,
.LLLL,
Liii LiLiL Z11.4 LLLL
Liii 4 LiLii
Li 4i .Liii iLLi L4 LiULLLL
cLLLL
.LLL L
ýLLZLL
Liii Liii 4LIi Liii
tLLZZ LL4LL
LLLLi
4z Li
IL
333313333'33 - ZZ 3 3 3 3 A 3 1 qq- 3 il 3 ' 3 3 3 9-3-33333i 3333 33333 333333-3-33333 3333. 3333 3333
3333 3333 3333 3333
[3333 [3333 [3333 13333
' 333 '933 333
1333 F3-3! 1333 1333 133
]1333
33 31 3
331
31 33
131 3•:
.3 3 33331 33331 A333ý1
3933: 3333: 3333: 3333:
33333333 9333 33333
3333 3333 3333 3333
3333 3333 3333 3333
3333 3333 3333 3333
33331 3333~ 33331
33337
3333: 3333: 3333: 3333:
3333 33333333 3333
3333 3333 '3333 3333
13333 3333
13333 '3333
-3333 13333 '3333 13333
333333331
3333• 3 33 3:
33333333 33333333
'3333 '3333 [3333 '3333
33333333ý 33333333
3333 3333 3333
3333' 3333: 3333: 3333'
33
3 3 3
- l .34 - t -- ---ý3-3nI9-433319 - 3 9 3ý3-~h~~3~443-3 43-3-43 t3 1--- -a33:
3333: 3333: 3333:
3333: 3 3331 33333333
3333 '3333 13333 13333
3333 3333 3333 3333
3333 3333 3333 3333
3333 3333 3333 3333
333333333333 3333-
33333333: 3333 3333-
3333 '3333 13333 13333
13333 13333 13333 13333
'3333 '3333 '3333 13333
3333 3333 3333 3333
333333ý 3333 33333
3333 3333 3333
-3333
13333 '3333 '3333 13333
33333333 3333 3333
3333 3333 3333 3333
-3-3333 3333 3333
3 [3
S
SI
OT ST Oz S OE
3133333333 3 13333 13333 S 333 3333
at, st CS
13333 333313333 ;3333 ;3333 3333 ;3333 ;3333 3333 33 3 3 3333-333
09 99 OL
3333 3333 333333333 333313
133
SL 08 51 06 96 COT SCT OTT 5I 0?!
9
St
Oz
OE
33 3333 3 3 3 33 3333 333333333333333333333 33333 33 333 3333 333 3333 333 33 3333 33333 333 33303 3333 3333 i333 3 3333 33333 3333 3333 3333 3333ý 3333:3333 3333 3333 3333 33333 3333 3333 3333 3333 3333: 3333 3333 3333 3333 3333ý 3333 3 3333 33333 3333 3333 3333 3333 3333ý3333 3333 3333 3333 3333 3333 3333 3333ý 3333 3333 3333 3333 3333 3333 3333 3333
3333 3333 3333 3333 3333 3333 3333 3333ý 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 ý333 39 -3-3-3 3-3-3- 33333-9-33-3: -33-3-3- 3 33-33 3-- 3ý- 3-3-3 -3333 -3-3-9-F 3i 3 -"-3-+3-33-3 3-333-33-33-3 3-3-33 33-3-33-3-33 3-33-3 33-33 3-3-3-9 33-
313333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 2333 3333 9333 3333 3333 3333 3333 3333 3333 333 13333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 333 3333 3333 3333 3333 3333 3333 3313 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 9333 3333 3333 3333 33 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333:3333 3333 3333 3333 3333 3333 3333 3333 33333333 33333333 33 -33-3 3333333-3-3-3 33-3 3-33 139333 3-3--3-3-3-3-3- 333-3-3 -3-3-333-33 333-3- -3-3 -3333- 3339-33 33333-3- -3-3 -3-a3-3-3 3333-3- 3
333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3 33 3333 3333]33333 333 3333 3333 3333 33333 333333333333333333333333333 3333 3333 3333 3333 3333 3333 33 3333 3333 3333 3333 3333 333 3 3333 333 3333 3333 3333 3333 33 3333 3333 3333 3333 3333 3333 3333 3333
3333 3333 3333 3333 3333 3333 3333 333 3333 3333 33333 3333 3 33 333333 3333 3333 33 13 3 33 3 3 313 3 ] ] ]3 3 3 3 3 33 33 313 3 33 3 33 3 3333. 3333! 333 3 333:3 33 3ý 333 3 3333 13 33 1 31 - 3 3-3 3-3 3-3-3-3 3-ý13-- 3-3333- -3-3-3 3-93 3-a-]3-3 33 3 -3_3-93-3-33 33 3- 33'33- 3-3-3 3-3 3-33, -3-3-3 33-9-3-3 ---3 3-3-3 3-33-3 3-3-33 3333.
3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 333 3333 3333 33333 3333 3333 333•3 3333 3333 3333 3333 13333 3333 3333 3333 33333 3333 3333 3333 3333 3333 33
333 3333 3333 3333 3333 3333ý3333 3333 333313333 3333 3333ý3333 3333 3333 3333 3333 3333 333333333 333 1333 3333ý3333 3333ý3333 3333 3333 33333333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3
33-3 933 3-i 3-3 3 -3-3333-9-3-3 3--+33 3-3-3 3 33-3-3-3 - 9 33 3 -13333-333 3 333- 3-3-333 333-3-9333-3 3333-33 3333 333 3333 3333 33 3333 3333 3333 3333ý3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333
3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333,3333 3333 3333 3333 3333 333
3333 3333 3333 3333 3333 3333 3 3 3 3 3 3 3 3 3
3333 3333 3333 3333 3333 3333 3333 3333 3333 333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 33 - - -3-33 333- 333-3333 333 -3-3' 33 9-3-3-9 - 13-3"3 3333 3-3-3-33-333 3333 3-3:3- 333 -333 -3-33-3-33333- 3333 33 3 -3333
3313333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 333313333 3333333333 3333 3333 3333r3333 3333 3333333 3333 3333 3333 3333 333313333 3333,3333
33333 3333 3333 3333 3333 3333 3333 3333 3333 3333 33333333 3333 3333r 3333 3333 333 3333 3333. 3333 3333 3333 3333 3333 3333 3333 3333 3333: 3333 3333 3333 3333 3333 33
-3-3333 3 33333 3-3-333 333 33333 3333 -333-3333 3333 333-3-3-3-3-3-3-3-3 9333-333-3-33 3-3-3 33-3 3 3333 3333 3333 3333 3333 3333 3333 9333 3333 3333 3333 3333 3333r 3333 3333 3 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3333
3333 3333 3333 3333 3333 3333 3333 3333 3333 3333:3333 3333 3333 3333 330
3 3333 3333 3333 3333 3333 ý3 333 3333 3333 3333133 3
-33-333 33-3? 33-33 3-3333333333 3 553-3-3 3--- 3-- 3-3333 3-333 33-333-33 3033 3333 33 -33 3 33 3 3333:3333 3333 3333 3333 3333 3333 3333 33
333 3333 33L33 3333 3333 3333 3333 3333 3333 3333 3333 u3333 333333 3333 3 3 33 3333 3333 3333 3333 3333 3333 3333 0333
33333 333333 3333 -3-3-3-3- 3333 3333 -33-33 33333399
381 039flld L 10
031 HgAOUHI OL 031S31 98V Z
031 H900UH1 Ht 031S31 T U
(331-H3I) HO9N3i 11n3 031S31 ZfTS 3
/
- 380 su•m 160A
SIN3_LX3 0313ldVOO N18809 0931 000
)
Z -OS
)
Sty
09
0t,
sty
59
9
K
SG -2 HOT LEG BOBBIN COMPLETED EXTENTS
Vogtle U2R8 GBE F7 244 TESTED 7C THROUGH TEH
7 243 TESTED 7H THROUGH TEH
m 7 PLUGGED TUBE
10 105 100 95 90 85 Be 75
00 .1 .~.00.
______ I 1- 1-4- i-4--1---1-
0 00
000(
00?.,
70 65 50 55 00? 10?400I00
?0? .... ... .. . .
50 45
000
0000
-� 4 I 4-� �O0.
000
0 ...
35 30
I I
o00
*00 .o0
?00 -004
25
00 0
00. . . . . . . . . . . . . . . . . . . . . .,,,.. ., ,...= o o ., . , ,o
_ _"I I __ .. ._, .. ................... i.... i.... I....
00? 00,. 0..
20 15 10
00
.00 .,000 .. 0
-0 ? ~O 0
0. .000.
0.. 0''
00..
55
45
40
35
30
25
20
15
1e
0
00 ,0 -00
-e-.. 00
,,,0
. . . .. . .. . . . ... . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . .
7777 7777 7777 7777'7777 7777 '7777177:
777717777~~~77 7777777771 1 f 7777 T77777 7777 7777 7777 77: 77 7777 7777 7777 7777 7777 7777 7777 7777 7777 7 7'7777 7777 777
120 115 11e 105 10e 95 90 85 80 75 70 65 60 ss 50 45 40 35 30 25 20 15 10
.7
77 77 77
120 1155
1- 1. .
0... .... ... .... ... . ....... ... .. . .
---.. - ----.- - -..-. --1
.~ . .. .... .... ... ... .. . . . 00 00:00.. . . . . . . . . . ..... . ......... . . .0
o ................. ..................... *
oc 0. 00
55
50
0..*.
)0...*
0 0.?
00? 0..
35
0 0 0
O00 5 0-.
77 77 77 77
-- 25
20
:o o0 o0
00 . 0 (
.0
.00
- - 15
* .00 .Q 5
7777 7777 7777 7777 5
. . . . . . .
1
.... ... ... .45
: : 0. 0 ... ?, ....
..T.-Tiii::o, o.0o(
:: ....
. . . . .
. . . .
S 10 5 10 -� -4
U)
-o
a) L0
Cd,
HD
0)
L--
10 00
010 . . P . ," ,o •I- I-HF-- - I- ,
•,I i-l- I- HI-F--- I
00 00... 10 -I-I- HF-I -I
0 I
0. .... ....
I-I- -II -- I
S I--I--I- I-I-I"-I--I'-I"'"i-HI
O . •, . . . . . .
, I -l--I-- I-I-I--I-- I-H'"I'- I--"
•>o o -- G', _,
F-I-I- I I-I-I- I-I-HI-
0+. •r... .. r
10 -HI I-I-I F-F-HI
N .',," _"."."
w0
FI-
wU 0)
Hj
S 10 -4 10 S 10 -4 10 5 U) N N N N .1 -4
4-27
O0,
F-I
F-HI-,
-F-HI
-HI-I
tiit -HI-H
-I.II-I
-I-I-I- F
-I-,-I
-HlI-HF
-I.)'I-I'.I
l-H w H LX W
0 LU H r7
LU W
-a
_J
O_
0 0
M-
H
aCo 8
UJ m oD
LL 0 a.w
! aID
I
0
t7-I--t-I-E E
. . . . . . - 0
•" . .. .. .. . . . . .. . . . .. .
. . . . . . . . .. o . . . . . . 0 o (o *• - ,•- .
H•. - I-I-HI. I-HI •-I- I-I-HkkI-" HI-I-I- HI- -I--I-- - - I-I-HY -•-I - HI-- I-H -
:. . . o'+. . . . . . . . . . . . . .. . . . . • ' . . .
..... .................... .....
-I- II_-I,_i .. ; _- -I- ;-I-ft i-HI- HI. -I,--I- H- -. I-HH- ,-• ~ HI-H HHH HHHI- ••
i ,-H I,- I,- I, , , , _) ., ,. .- i-i ,-i-i,- HI-I-I•HI-HH HI-I- -HH I,-,- .- H I,-H. •I - HH -I I-I-HI- S
S........ ........... -r r rr!rr
-t--I-HHI---I-HI--I--' I-I- H - I- I- HI--I--I ..I--FI-H I-- I--I-H-I-- HI--I I- I
-I- I-I I-- HI-- HII--I... .... .... I---H , I-HI-H I-I-HI- I-HI-H
'01
*0 0
.0
:'" I......!{!{[{+........-.0o<
., . .. .. . .. . .o.
. ... 000 o............ " ""O° 1
"I-I-I-H F I-I: H I I-I-I-I- F-I-HF- I -I-HI I -I-I- F - HI- :
- F- F - I-I-F-I- F-I-I-I I-I-I- I-HI-I
I-H-I- I-IHI I-I-F I--IF- HI-I-I H-F- I-IH- FIII
*~ HIIFF----IIII ---- IIH-IIH- I-I--IH--S
- --- -III -- III IIF- I---- IIIH IIH- HIF-H
.. ............ • . o. ........ 0o1
.~0
-l I-.I-.I--I-- F-H-I.-H- HI-I-I--I--I .- I-F. .- I-I-I-I- Il-H-Il- I- HF-t--I.- F- HHH-b•
- I-I-F-.I-.. I -tl• . .I-I-I I-,,I,.-I-F- I~l-I-HI-] HI,-I=-H Iii-HI'-I-l' H ,I,,-F i-H I i .-HI-I
- I-I-I-H HI-I-H, i i,.i,. <,., I-H-I- I-I I-I- F-HFi.,.t-H ,.i i-Fi-HI.-.-- , I-HFi -- I-- F-HI- H
I IIn
SG - 2 U-BEND +PT COMPLETED EXTENTS From Base Scope Vogtle U2R8 GBE F
A 71 TESTED 7H THROUGH 7C WITH a 7 PLUGGED TUBE .520-HF UB +PT PROBE
N 73 TESTED 7C THROUGH 7H WITH .5204IF UB +PT PROBE
U I TESTED 7H THROUGH 7C WITH .500 NON-HF UB +PT PROBE
126 115 110 105 100 95 90 85 80 75 70 65 60 55 50 45 40 I 000 00000,000
0 000 00 . . .. .01
00 0 .. . .. . .. . .. .. . .. 0 0
35 30 25 20 15 10 5
000Z- 0.. .. ... .. ... .. 00
00o.... ... ...... ....... . ... o 00
0... .... ...... .... .... .. 0 000..0... ........ ....... ....
000: ... .. .. . . . . . . . ........ 0...0
00. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .0 ? 0........... ............ . . .. . . 0 1
00........... .. ... .. . . . .... .... ....... .0. 0 .... ......... .... .... ....... ..... . ..... .... 00
_ _ ----- -- ---- -- - - - - - - - - ~ - - 0 00. .. . . . .. . . . .. . . . .. . . . . 0001
0 0. . . . . . . . . . .. ....... . . . . . . . . . 0 . . . . . . . . . . . . . ...... ... . . . . . . . . .
0 00 .. .. .. . . .... .... . . . . . . . . . . .0 - ------ --- --- - - - - - - - - - - - - - - - - -
0 ...... . . . . . . . . . . . . . . . . . . . . . 0
'. " : : : : :: : : : : : : :: : : : : : : :: : : : : : :::: :::: :::: :::: :::: ::: ::1 ?
0. . . . . . . . . . . . . . . . . :: :. ... . ... ... .. .0 . 0 .... ........... .. ......... .... .. .... . .... 0
00.................... ..... . ............ .....
?. . ............... ...... .. ................. .O0
0........................0..... .... .... .. 00...
. . ..:. . . . . . . .. .. .... ... . .000.. ..... .00 ... . . . . . . . . . . . . . .0::: ::: : :: :: :
0 ... ... .... . . . ..... .. .... ......... ... .... .... . ....... .... .... .... .... .... 0 0 00. . . . . 0.0. . . . . . . . . . . . . . . . . . . . . . . . . . 0
,0 0:. .... ... :......................................_o
O, 00
A \o�( \0\0\ \O\ \0k0 '-~o 0 Xo0 \\0k \ok o X. 4.0\. 0 01 0fI.;10//01'Uo/;4,"0/;0 10;; //0/ /~ IIo
120 115 110 105 16l 95 90 85 86 75 70 65 60 55 56 45 40 35 38
1. .; .: /0/0j
25101; 01;.00,
20 1510
55
35
55
50
45
40
35
30
25
20
".0 Io0
500
C (
25
20
15
16
5
16
5
0.
0. 0\
%0\025
6Z-t' 0c
a; a;a; a a;to a G )
W> C D A )
oc)aw U X>>> a,44
CD4> >
o 0 W>»» 44)) XWW x
o- w A~l0 >4>>> t4>.>>.>.>>.>4.>.>4.>4.4.»»0
a O W 4 4» >4 4> 4 .4» ) .44> > . 4 >4 > .> >) . .X. . .
w 11)>>> X4)0 »>>>.>>t444>>> . .XX . 4>..>>»4 >4>4>4
0>>)) >444> 44>>» 444444444 >>,):>>>> 4») >>>
wX>>) >44>4 x44>4 »>>4»4>44444 4>>».>>44 >
0 W)> W .))> .)») . X>)' >X X .4» x .4» . 4 > . . . . . ,X.
W W 0)) » > 4 > x . . .XX
.. > ) 4 4 > 4.4 4l
w> W% 15.)> 4440>)) x4»>
4>») 1.> ) >. -a
w >E) wC) 0 w V)
It.
a; (44.(4>) 444>>4 >»)>> >)))» .4>44> 4>4>'» 4»» >44)44>4>>)».r)»>4 >4))>>.03
CA4>> CO» W4)>I4444>x>>4(n>4
w .oo>> »»)O > 0.4)4 x t>> » > »>4>>)> >>>4>44» 444>4 44>> >X
44>44)0>444~~~~~~~~~~ ~
444>> X>> 444»
x4>)'44 c> Y.>>X X )» 44» 4>)4>44»)
1. o a~~~~~~~~~~~~
x0»>) »>>x 44)>>.44»» > » 4 »x»> 4444444' >>»> >444>> CD co-z CD )>)> CO 4>> 4>)'> >4.X4.4)'0»X> »)44>>»)>»4> 44444>4> 44442
a; o It000
>4444444>4)»4444>>> »>>4.>>» »>44>X 4»)) >>»a
(n0(4)) to 444>X>> w444>4 W»>> >4>>44'4>LnX44.44>)
4»» 4>4>.444
S .O oo»>) owl 4)4 4>4>>>44>4 X.>) »)44)44»4 4>>4»44»» »)»4)X
o 4>»)>»> 044"4444 4" 44444> 44)) >4>) 4>>> »>44 >44»3
a;' 0>>>>4>>4 1>4 >444444 >44» XX> X 4 >44» X ) >>'4 -X'-.>>»
V, to (1)
0owo>C4.»~X.)) 4>XZK X>X.X ».4444 X)> 4444 X> XX4
w;444>l0.X>4 4)» X4X4>X >44» X )» X»> X X )X> 44> 44> 0
0OjOX»4>>X> MX)> to»4XX 4 XX4»»44>».XX4»»X
X
a; 0>W~C .4 .'» » > .X > .X >4X XX4 >4> It4>» .>4. .X.4'It>4It
4X4It4 .
wA0wo4. XX»> »)>4 XX I XX»».
.>))) .444>>44)» X>X.444.4 .
o>>>>>444 w44» Cc))44.XX XX»)' .4>)) X . .44.>.X..»»
ul X>)4X> wwooX.X4X 'tXX XX' X)»4
.X4 X.44X >X4
En It It It
CD It>00 >44 4> > »» 'X 4> ) *4 4> 4.4X 4 4 4 ' 4 It>4X4>4,'It
woa It 0
_0~~~C : I3 t
w OC) cl x tW . . I
a; w4>>~ W 4>4) Co>>4>
t4444444> ») 4
4) > » It~-u >3xT.I
wwwo t X Xx N.m U.
It444>4>>4).4»4) 4»>4X4> >>4>
It X ItT Itat
VC0CX0w )>.> It)
' x4>> c
a. a; a a; a a;a S
OW.O4> t4I
N> It-:I XI
W4 04 04 01 -0 04 04 44 U) w4 -q Z4 m4 4 N N.
I ~~ 1000040 0004,. .' ? c C o C)
cC
Il
r-.
CO4
0 0?? C00404 4 00' ? 0... .. I c,
000 .00..0 ... c*OW
00 140 00 0 0 ' 0 04
000 40
N _ _ _ . 0. . .. . .. . 1,00 U) 0 1, .. . CC C 000404
0~~~~ C ..... Co000 00 c .. 4... . o 00).
062. cc cc Co 00
0 00
0'.'.' 0. 11111171! V IIILU
000444) C000404 00044 0 -0-8-4464) e e0000 '00040 000cow
'000 0o C -84C-44 O
-CC4Co C0COCO C 000404
'000 04o -8-8-(a644l) 000404 * 000C04
04
0
N
0
w0
14
04 0 0
04 0 0
0 0. 04
00 c :00040
0 C 04 Co)
.no 0000404 0v 000404m
. .* .00..0.cccc4t
04 00 oo 0004
:0... 04 8-0-..0 . . .CCm
000-
'...C0004
00~~ .0 0. o 0000 0 .. 0.. . 0.'. C 000
U)~~0 0.. .00..04.04co
00
O)0C c .0 .04,
0' 0040
0000 .0..00..404)
0 00cc,, 000 .. 0 .. .. c... .. 0 ,)0
0 .. . 0 0o 0000
0 000 co4(
0040 0On~
S0 0 4 .44 m' A4 N N -
4-30
.00Co0w
Cmz <0 QI
U) c GO
C/) Cz
LI -0
N
LU 0D CD
CL
0
(9 0
z 0
w
z z
OLUC
m .
00~OuT :0000,
0
A
00m
0 0 00
in B 9 CD InCR 'CX CC CCI N cmI
(It
0) 4
V U) LU 4
S
(C
'IC
x XXI
XX XX 14 X'CX'C 14 X X'CX
w 0
I
0 w (0 (0 -I
0�
C-C
.X.X.I.X.X.. . .
I4 X_ _ I_
_ I_
_ I_ _ -I I I I X CI Cx X
x_ _ _ _ -II1- 11 X X X X X X X X IXCC xIIC' X
V4 __ _ _ _ e e -~ --- t-- -'C------ - -1~I I I I 'CCCXX
- + IC-IC--.'C-X-4
XIIXII.+IX XXI&XX'X *'CX. XXXI+XX.X .XX
XX. ..§. . xI x xx ... . x . X. x x . . ... . x x x x X X I I
. . . . . . . . . . .
I I X1x x
rx x -x
0
x. .C.x-AC 'x XI'CX, x X 4
x4 x 44 I.. .[a xx x 01 X 4 4 41 x4 NCC X'IXIX X IXCC XXX 1, CC
.* IC I I *1 * ,t 1 4 4.1 ...1.... 4 4 .. 4-II
:1 XX XCX '4 XX 4 XX 4 X X .zX'CCC X . .X.X
x x wx NX xx III X X I X ICXX I IIIIIIII E X XXX CI I
0 1Ix1.X, 1.X.1.X
IC X4C.X. 4I. CX X4'X CC x'Cx
ICICCCx X X X X XXI XXX4C X
CCXXX4XXXXx >00
I xX i X
I P us:IC X If x x x x
Cx xx x
ICCII C XXX 'X XX I4 'C X 'C X 'C X CCX 'X X * . .X
xC C~ x x x.1
- .. x x-x .1 x1 4
x x xx
... I CXIX IX XX xI * '' X IC X If I' . IX I ,X
. :4 : I I I
F ' X X. 'I
XICX X X' I CX ICX IXC IC ''C X XX I.X .4 .X . X.C.C.X
XXI 'CX CIX xCX 'X x 'XX 'x XI x x x xxI*x X X ,XXI 'C X X X C X XCXCC '
I 1 1.XXX XIX'C 'XX ICCXC ICCII 'CCX 'CX
IX X X IX IX I~ X IX'X * .X . .
X .4I)O O I .. ; ___ ____
CXXX X I:XIX 4'C XfXX I
:.X I tIX IX XIICIC1CCI XCCX I XCC . I
1XXX'C1 1 X X.XXC 'XCI. .X 'CCX 'CX . XX X X'C. X 4.1 .1 XX'C' Ix C. X 4. 1 . ' .. XXX 4~~~~~~ ..44___ ---. ~__
(D 0
U) z
w CI)
w
+C,) C)Mw
U-) 0 a
0a ao
--Xx-xx .... x x x
X X X X x x x
00 . X . .C XX . .. ..
II-~~ ~~ IC XX 4CX C
X0 x4;
F-I 4
x4 . 4
'X.X IX I XXX
XX'CXI4XX'CX I
'C x .CCXXX CXX 4. X , X' XI
I ICX IC I I . . .- . x.4
xX If 'X X.X If ' X 4C X X X XIICI CX XX CX X X
ICCXXXC
1011
-. ______ . L---------4 4 - I.
Ba La B
ICIICI * xx CX X *XXX 4
CxX x 4 x XCCX X 4 CXX X
4
XXXXIf'CXXIC If CCXXX 14 CCXXXI
XCIC C XX *'C X4C'XI
XX x 0 x 4 XX 7 CC X j xx XX. IC
XX¶ ICC X
CO LD B S n a t IX CT C N "
.II' B0
X X .C .C1
x - p
B XC
In
'IC'IC
.. ICX CO
.x - I
IC IICX n
x x
x
xIC..0f 4C DCC
... ox N
.I.O
Bxx .. C. 0
IC--o ...0 u
ICIC.QX
IC XOXCC I.
x
in U)
x0 .4. .X.T.X .X.X. . C. .
4 1 4 1
WB In
co
In
4 4-00'
____ .1��
x x I
In
B 'CC
B CC
14O
In fr-
s..
10*
0.
I X. X N
xC~ 4 , 1 X .4 'C4 Xx CX X, 'xX x x x '' X x~ ' x xXC CCX I X XX x1 .C X . XX .XX IIXC I IC X I IXC I IX .C X : 'Ci xX
()0 j .CICXCCCC . C*C~C .- IC. .C~ICC*I.-CC .~ .I~C' .XICXC'LO co
tn
I00
Bn
a
k-F
B
B
4-31
X x . . . . . . . . . . . .x
x
'x
x x
x x x x X I I I x x
I I x . . .
I X I I
x x x
.... Xxxxx ...
x x xx x X
x x x . . x x
1 1 Ix XX 11
x x x x
.1 X XX X x
X. x x x
4n
00
I x
K
SG - 3 .520 +PT U-BEND INSPECTION PROGRAM ACTS: GBE-04-101 RO Vogtle U2R8 GBE F
(
n 145 TEST UB
X I TEST U8 - ADDED 4-20-01
13 1 PLUGGED TUBE
120 115 110 105 10 95 90 85 8s 75 79 65 60 55 5s 45 40 35 30 25 29 15 1 5
000 fl0000 0000M 0 000O-0 0 0 0000 000
0000 .00 0...... . .. o 00 O. ... . . .. . . . . .. .0? 00000
000) .. 0000..
^^ o . .. : : - :t:: :::: ,::: .: ... ..... .. .. .. .. ...... 00 o
0 ... .... .... .. . .. 00 0 0 0
.. . .0 0
0=. . .... .... .... ;.... .... i.... .... i.... . ; • . . . . . .,. . . . .,. . .. o
00. .. ........ .. .. . . . >0o.. . .. . .. . ... .. ... ... I ... :: : : :: : :: ::: :: : :... ... ... ...... . ....? "
oo ?.. . . . . . . . . . . . . . .. . . . . . . . . . . .. . . . . .... ..... .... .. .i .
0. .. ..... .. .. .... .. 00. 0
0~00
o .. . . . . . . . . . ...01 • . . . . . . .... .... . .. ::: . . :: ': ": : .. . . . . . . .. . . .. . o .. .. .. .. ... . . . . . . . . . . . . . . . . . . . ;; ; ; ; ; ; ; : ; .... .... .... .... ... o o 0 .... .... ..... .. .. .. .. .. ..... 00
o ....... ~~~~~~~~~~~~ ~~~~~.... .... .... .......... . . . . .: : : : : : : : . . . . . . . . . . . . . . . . . . . .
00*
0 .... :00.
0 ... . . . 00
00. . . . ... 0 0
•:: .. ....:-• ... . .. .. . . .... ...... .. ..~/I ~ l 0l l l l 0..i~ i 1 i i i l I i
O0 . . . . . .. .. .. . . . . . . . . . . . .. . . . . . . . . ................ ...
0:: .... ... . ...
Oo0
o,.
000..........
on
00 :5-57 5 0 0 3 0 -5 .. .... 0 000 n n . . . .
non0 n 0n Ann,7-l 1- nonoo A00n0 oono oonooono 00no oonn
0...........................................................................................................................
- 45
- 35
39
25
55
5s
45
49
35
30
25
20
5
S2
0 0 000 ---- 15
:0 -0
?00
,&0 .. 00
.0.0 0.000
5
5
-- 55
so 5
i 01 S T 0 Sz E SE O£ sip S. es 95 09 59 1 St 5 58 g 06 96: OOt 90T OTT SIT OZT
51z t, L , LL L LL 4 ZLL 4LL tL 4 L 4ZZ LL-L 3L- 3LLL
LL LL 44. "ZL Z ZL Z i St
LLLZLL L, L LZLL Z L4 LZLt.ZLZ44Z LL4Z t•L LL Z 4LL •LL44 tLitLLL ZLL L4LL 'LtLL, LZLL ZZLL 44ZL 4LLLL UZ.LZ 4Z
-3-- 3-3- 33 3-3-3 3 3 -3-3-3-3- -3-3-3-3- 3 -3-3 + -l 33-"-++ --3 -- 333-3- S-3L
LL 3 . 4
333•33331333313 3333 33313 333•3333•33333 333•33333 339 3333 3333 3333 39333 333 3333 33 33 3333 r333 3333 3333 3333" )33 333 3333 13333! 3333 •3333 3333 3333 3333 )3333 33 33 3333 333 3 3333 3333 ]3333 333 3333 333 "-13333 3333 '33 -33 13333 33 33 333 .3 3 333 333313333i 3333 3333 3333 3333 3333 3333 33333333 •3333 3333 3333 333 | 33 333 3333 3333• 3333• 3333 3333 33333333 3333 3
O --333- 3-33--33-3-3 33- -3-333 a333 3 33 3333 333+ 3333s3333 33 3333 3 O 3333333 3333i 3333 f3333 1333 •333333 33313333•33333• 3333 3333 3333 1333 3333 3333 3333• 333• 3333 333 3333 3333 3333 3 3•333333 3333! 3333 )3333 i3333 ;3333 3333 33333 333 333 • 3333 3333 3333 ]3333 333 3333 3333 F3333 3333 3333 3333 3333 3333ý
•33 331333333 3333 3333 3333 33333333 3333 333333 3 33 3 333333 93333 333 3333 3333 3333 3333 333313333 3333 3333
9 33333333 3333 3333 3333 3333:3333 3333 3333 33 3333 3333 3333 3333333 3333 33333331 3333 3333 3333 3333 3333
ST 3-3 33 3333 333333 33 3 a333a- 33331 -33 -3-333 3 3 3 3-3-13- • 3333 33a + 1 -a433 ; 3 ] 33 3 3 3333 3333 3333• 3333 3333 13-3 3 13333 333 S 33 3333 33 3333 3333333 3333 ,3333 3333 3333333 3333,3333 3333 3333 3333 3333 3333 3333 3333 3333 3333 3 33133333 3333 3333 3933 33333 3333 •3333 333 13313 •3333 3333 1339 13333 333 3333 3J33 9333- 3333 3333 3333 333k333 3333 3333 3333 3333 3333 3333• 3333 •3333 3333 3333 •3333 3333 3333 333 13333 333 3333 3333 3333- 3333 3333 3333 3333 33 133 333133333 3333 3333 3333i 3 33 3 ý3333 333 3333 •3333 3333 1333 3 1 33 3 333 3333 3333 3333 •3333 3333 3333 3333 3
UZ ~ ~ 3 -33-J- 3--3 33- 3 -3-3-3-a- -3-333 -a3-3-3- 3 -3333 33313- -3a93-3 3 3 13- -3 - 3 1 -ý-a3-3 - 3333 33 3333• ]33 3 3333 33333e 3333 3333 •3333 9 3 3333 3333 3 3 33 3333: 333 1333P3 3333 3333 3333, 3:333 333 33333333 3333• 3333 3333 3333 3333 3 33 3 333 133331 333 3 3333 3333 33 33 33331 3 a3 3 3313 3333 3333 33331 i3333 333 3 3 3 3 3333 3333 ]33 333333 3333 333 3 3333 3333 33331 333 3 3333! 33331 3 3 3 .3333 33 33333• 33 1 33 33 3333 3333 333 3 1 33 33333 3333 3333 3333 ] 33 333333 33331 3 3 33 33 333 3 3333 i 3333 3333 3 333 3 333. 3 1 333 1333:3 3333 31333 3333 3333 333 33 H333 333 3 3333 3333 3333 3333 3 3 Sz -~~3-3-3-333 1 3 -3-331 a333 3 -3-1a3 3 _3_3_a. -3-13-3 3 -3-3-3 a3 3 3 -3 33 3 -3-3-3-3- 3 3 j 3- 3 333-3-2 3- 33-4 33 j1 3 3 433 a33 -3-3333 3 3 333 3 33 33 333 3 13333 13 333 •3333 H i 333 3333 3333 3333 333" 33" 33• 33 3 333 3333! 3333 3333 1 33331333 333333 333 3 3333 3333 ;3333 3333 333 3 3 3 33 3333 333 3333• 3333 3333 3333 13331 3 3 3 3' 3333 3333 1 33331333 3333 333 33331 '3 3 3 3 ,3 33 3 3 ,3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 33 3 333 33333 3 333 33 ) 3333 3333 333331 33 333 33 33.'- 3 ) 333• 333 3 33 333 33 33333 3333333 3333 3333• 3 3333 3 3 3 3 33 3 t3333 3333 333 3 •3333 3333 333 3333 13333 •3333 3333- 33 3 3 33331 33 333333 3333 3333 3333313333 -- - -3--3-33 3- 3 3-3-3 3 3 3 -3-33-3 -3333 3 333. -3 13 3 3 13-33-3- -3-333- -3a33 - 3-3-3-3- -3-3-3-3-3 - -3-3-23-33 3 -3a 3333 333333333 3333 333r3 3333 333 333'3 1333fI13 33•33 3333 "§3 33333333 3 333 33 3 333 1ý3333 3333• 3333113333 333 33-33 33 333 3333 33 33 33• 33 3 3333 3333 33331 333 3 3 333 33 3 33 3 33 33 3 333 3333 3333313333 3333 3333 3333 3333 3333 333333333• 3333 3333 33331 33 3 3
333 333 3333 3333L 3333 3333 3333 333 33 33 3333333 3
3- 3 -3 33 3 -3- " -3--3"-3 3 3-3 3-'--3-3-3"- -3+-3"-3- 3-3+ -3333. ------ 333.....ý 33 ----- 3 " -- 93 9 -- S
331 333 3: 3333 33H3 L 3 a 3
3333 3 33 3 33 33 3 3 3 3 3333 3333 33 3 3 33333333 3 333 ý 333 3333 3333 3333333• 333• 3333 31333 33 333 33 3 3 33 33,33333 3333 3333 3333 3333 3333 333 33333•3333 •3333 3333 3 3 3 33 3 3 3 3333 3333.33 3333 3333 3333 3333 3333 3333ý333 3333 3333 3333 ]3333 ,3333 3 3 3 3 3 3 3 ... ... 3-3--- -333 a3-3--3- T -33 3 :3 3 - 3 31- 33 33 333 333 333 3333333 3333 33 3313333 " 3333 3333V33 33333333 33 33 3 33 33 33 33 33 333 33331 3333 3333 3333 33 33 333 3 3 3 3 3 3 3 3 3 333 33 33 33 33 33 333333333 3333fil331 3333 3333• 333 3333 33
33133333333 333H 3333 33
£
J3BB112U3flfeld o
SiN3iX3 09191~dvlO9 NiBBOS 0£ -
)) /
0000
D DJ4 .. . . ...
-. 40 . . . ......
C .0000
.0 0.
.0 0*
n D
D Z)
D 44::
(n 4::
.- 4 D D
D 0
Nl w w4 4, 01 ep G1 M 01 01 C 0
00* -00~
_________ 4 4 4 C
)0 0 .000
I_______ 1 4
0.0 .000
0E)
000
*00
000 S?00(
1 4 ± C0
.4 00 I
* 0 0 1
'0
.00 00
'0 '00
.0
0.0
.. . . . ... .4.o00
... .... .... .... ...
.... .... .000
*000
;000 .
(3UIlN N w4 w~ (a'01
W GI (7 C l' 0 Li'
(D cz
00 (A
010 Io F1
0'
0~
0
.00
.0
00 'an 0 0
0
n �
-� -4 r- m C 0) � -I d� rn m
�-1 -I C)
� -4 m
0 0
: 09I j - i 1 - I I
I
_r -~
0
H
00 co z 0 0
R-i
m X m z
M n
en
+
r•
02 in
U,-,
L.
C
H i.-
LI-.
(0 LU
(D to
co-
G In S; 04 -
c,'
I-
V)
Cn Co
SC H,,
C, -,
In
I- * I-I-I-II-I- I-I-h-h- If- HI-HI4HI-I-h- I-HI-I- If- I-I-HII-I-I- I-I-I-h- I-I-HI- I]- I-HI-H ,n
I-I-I- I. HI-.I-I- If- I-I-.-I.- . I.-I-I- I.- I-HI-I- 4 I-I-I-I-
1 -• ~ I-II-I- I-HII-I- HI.• -•l• -- - h-- h-- - HI- H I. I..I- -I -Ill-I10 _ _ _ _ 1 1 I-I-h-I- HI- I-H 4h-h- HI- I- HI..-.• - H I-I- -I- H I-I-I-I-- • - I--I.-I. - I- .-.- I- I - HI.- . i .•I-HI-I-h- HI- H I- HI- HI•-- h- HI-I- I•- HI•- I --- I-h-HI- HI -- I-I-HI-
O0_. .1. . . . . .......H-- -- I4--H. . . .. . . . .. .. . .. . .. .. ..
oI "F--I- -• -I- -I- I-I I- -• -I I I- I I I--•• F--I-l--I-
in
0 4... ... .. . . . .
HI- HIII I-II N-H-- ---- IIhh Ihh- IIhI --- IIH- IIII
I.-HI-H-- f- ,I-hi-l-I-H It--H I-HI-- --1--HI-I-H- I-I-I--I-- HI-h-t-I-- Ir I--I---I-- H-I.-I-I-- h-HI-HI--0HI-I,-h- o--II HI-I- HI-HI It o h-H-h oh--hh-1 -H-I I-Ih-h I-H-h
y~o.... .,....3 .. .".t.'.>."t ?. . . . . .t. .- I I t-I--------~I IH-h-II- I- I-I--I-* II-h-- 4I-H-H I-I-H HI-hI- f- -h--h- h-hh-h-4 hHI- 4 -h--I
I-fIII--I-HIII f h--- If-I--- I-IH*h--- IH-- 1
H---fhIIhI I- If- h--- h--I I----.IIh I--I .fhIII H. IH4 H .f I---
0.4o'r '.
I-I hH--
S.... ... .. . .. .4 . . . .. .
! . . .• . . . .i . . . ... 4• .... • .. * .4 .. . . . I- HI- Ij-l- I-hl-I- I-4 I-H- I--l- 4- I---I--... H HI. -. -4-.l- I--I'-h•I- I-N-HI-H-If- I-H-I'-I--I
*0 'lo
I- I-HI-H, If - I- I-I-I- i
I--I-I-HI- H -I- I-I,-
, .-- , .,.-.- .. -,.-.. I
0., • . .• . 4f f .. j. 1 0.
S.... ... . . .oo. .. 0... .. ..
F- I • F- F- P.- ', 0 '-I- ..-H--. --IH.--IH HIHI.I--- I-I-HI-.I-I-I-H.HI-h-I- I I-IH H-- --
0 1 1000. . . . . ........ ... . . . .0'
0 . . . . . ... ... ..
) f" i " .. .F .. .. .° I III ~ ~ ~ ~ ~ ~ ~ ~ ~ .0- T- It If----H--II - --- IIII - II
.... . . . . . .
. 4 . HI I- Hh I- I-HI-H
I-I-HI-. I--- :I::.iII I I-I- HI-I-h-. . . . .0
I-~~~~~~~~~~~~~~~~~ h-I- I--I HIII .-I- .--I I-I- HII- I-II . ---- IIII --H 0 I--II I--hh I--II I--- N- I--Ih I-II I-II I-II I-Ih I--II HI-HI-o..
I-HI-H HI-II- HI-HH4 II-I-H LI H -I-I - IH ---- ~--- IIH IhIh1
H- I a. I b l In .---- .+..I . ..-..
I-h-I-I- I-HI-- I-h-h-H I-I--H h-h-I-h- 4 F-H-- hI I-4 IHI H--- H-I- -IIH 00 0o 4
L)
w w U
C•
LL w 0H
LU
F
a
LU
C.0
IL
LU D
U) L
DD
LL 0
0
LU
-Jr
oo,
In
.. . . . . . . . . .- . . . . . .•.. . 'I.--I-I-I-•[ * I-I-I.-I.- *I-I-HI--If- I--I-H--I-*'I -I-I'- If- HI--IIl-] If--I--I--I--I
I'-HI-I-*. -I---l- I--I--I-I- -IhIh- If- I-Il-I--I-I- I-H-I-f-I"-I',-I--I i-If- I-I-I--I
HI-.HH....-I-H ... 1--...-II-...............4I-hI-H I--I--I- H --- I-- If--I--I-I- F- F-I-I-- I -I-I- * -HI-i-- N- I-I-I-I-I
1 1 hh- -I- Nl-HI-h--.- I--I-I- N- hHII- h,-HI-I--I,-N-HI---If--HI--H-I
F- F- F-- F -I'""--I--( DO-- h -I-HI-i HI-HI
I--I-'I-I I--I-H -I-I .-I.- I-I-
I w rI mS N
in - -G- L -
4-35
IW
In)
4 -.
CD In 1 7i N
inJ
I
Ini
C..,
It.
In
ull
)o...
In S
S
]
!! ! . . . . . . . I] I
,, . . . . . I 1 1 1a{t
I
A
s ST Oz s9 or Se v S i as . 99 09 99 UL SL 08 So 06 96 O T SOT OTT Sl T SI T 0/0/ 0.I 0/joon to// 0/0/ /0/i 0Y0/4,/0/ 0//1/ //// O0 loZ\U.0Of 0T0o 0~0o~// IY1110
S.. .. .... .... .... ... .... .... ... °t 0 ... = .... .. .. .. .... o.... .... .... .... 0oe t- _. . . - r : l r : • : r :. . . . . . 0-
0 00 . +. + , * .... ....
-e"0 + e . ++ = l . + . 0 ..................................... o ..............
... .... .............. . . . ..... ... ...... .... ....... ... .. ............................... 0 9 + . . .. .._.. . . . 0 I I I I ' I I I 1 e l e l l p " l
0 . .... ................. ...... ................. o "..-..:: :: .... .I. .... ... 1 )1 0................................. .............. ......... .... .................. .... ..... ..... .... ..... .... ..00.....................
)+ .... .... .... ... . . .. . ..... .... ...... ...... ... .... .. Co °) ... .. I... .. ...... . .. ... .... .... .... .... .... ..... .... ... .~ ... .... ..... .... --...- ... .. .. 00 .. ........ .... .... .... .... .... .. .OO. .... .... ..... .... . .. .... .... .. . . ... . . . . . 0 S... . .... . ...... . . ..... + ... :;Ios
oo ... t .. . . . : ... : + .... ..... .... •..o o... 0 ... ..... . ... . . ... .:: [ : t.. .. . . . . . . .f. . . . ooi : :.. . . ! : _: : . . . . t . . . . . . . . .. . .. .. .t .^ 0 0 .. ' " .. . . . . . . . . . .o . . . . t . . . . t . . . . . . . .. . . . . . . . .. . . . . ..o O Ef 0+ + + .... .. .. + + ....0 o• : :: :: • . . . .. .... .... .... .... .. . • ..... : : : : :.... . .... .... ....... 00 ... .... .. ......... .. I: ::.... .. .... . .......... .... ... I ..... ..... .. .... .... ... ... .. ..... .. .. SE
S 0 0 . . . . . . ." . . . . . . . . . . . . . ; ' ; , ; ; ; . . . . .. -.
001 ii i I0 I i i i i ~ i i I I ~ I I I I I ~ l
ooo. .. . . ... . . . I: ... SSE
005
00
S.. .. .. ...l l . .... .. ... .......... . .... ... . l ..o "0 ., , ::,.~ e :: + ::+ ::: :: : '::: : .:: -:: -: + -: :::: ::== :::: :::•:,::L0 0
,oo. .. .. .... .... .... .... .... .... ...:i ... . ... .... .... .:: * ... * * . . .. o 00
. - : : ... .
..l i i i ii 0 0
00 .. .. . .. . . . . I - [ : = : : : = = . = = + .... •: =.. ...
.. .... ::o: .... ...+ • . 110 0
ss ooo i .... . ... .... .... ... .... .... .... ... 0 000 SS 9
5 l 01 51 O~S E se o r 1 05 95 09 99 OL 9L 081 98 06 96 001 961 OTT SIT OZI
3801 0399111d T 1
380d id+ 8A AH-NON 009' HIIM HL HI9O1f H1 3L 031S3i E 11 38041d Id& 8G ,H ZS"
HIIM O3 HDAObHi HL 031S31 IS X
3808d Id+ u0 JH O9 H1I/1 Hl HqnOUH1 380d d- 8fl A.H @Z9'
' 031S3i - 38n1 03nA03HOSNn I I HIM HN H~nOMN 31 031S31 Z /
d 3i9 c -fl esA SIN3IX3 Q0L17dVLJ0o id+ QN•8-fl • - OS
) )
( ( (
Augmented ASME Sect. XI Examination Component or Weld No.] Calibration Exam
Item No./Cat. Requirement Description Exam Procedure Block(s) Sheet No(s). Results Remarks
See Note A See Note B See Note C See Note D See Note E See Note F See Note G See Note H
NOTES:
A. The ASME Section XI Item No. and Category of the examination area are listed in this colunmn.
B. The implementing document e.g., VEGP Technical Specifications, NRC Bulletin, etc., requiring performance of augmented examinations is referenced here.
C. Each examination area is listed in this column. The component or weld number typically is similar to the drawing number, e.g., weld number 21201-005-8 is found on drawing number ISI-21201-005.
D. This column lists the applicable NDE procedures used for the examination.
E. This column lists the calibration block(s) that was/were used.
F. This column references the examination data sheet(s) which records exam data, examiners, and any pertinent remarks.
G. The results of the examinations are indicated in this column. The absence of indications is indicated in the column as "NI" or "SAT". The presence of nonrelevant indications or indications which are less than the recording level is indicated in the column as "NRI". The presence of indications deemed recordable (per NDE procedure) are indicated in the column as "RI" or "UNSAT" and are explained in the remarks column of the summary table.
H. The remarks column is used to describe any pertinent features of the examination such as limitations, INFs, etc. Refer to INF section in this report for their disposition.
FIGURE 1. EXPLANATION OF SUMMARY TABLE FORMAT
5-1
(
VEGP-2 EIGHTH MAINTENANCE / REFUELING OUTAGE CLASS I EQUIPMENT EXAMINATIONS
AS ME SECTION XI ITEM NO./CAT.
AUGMENTED EXAMINATION REQUIREMENT(S)
COMPONENT OR WELD NO. / DESCRIPTION
EXAMINATION PROCEDURE(S)
CALIBRATION BLOCK(S)
EXAM SHEET NO(S). RESULTS REMARKS
VT-1 PER RR-6
VT-1 PER RR-6
TS 5.5.9
TS 5.5.9
21201 -B6-002-IR-01
INLET NOZZLE INNER RADIUS
21201 -B6-002-1 R-02 OUTLET NOZZLE INNER RADIUS
21201 -86-002-T01
TUBING - ENTIRE LENGTH OF SELECTED TUBES
21201 -B6-003-T01
TUBING - ENTIRE LENGTH OF SELECTED TUBES
B3.140
B-D
B3.140
B-D
B 16.20
B-Q
B16.20
B-Q
B6.30 B-G-1
B6.30
B-G-1
B6.30
B-G-1
B6.30
B-G-1
B6.30
B-G-1
B6.30
B-G-1
VT-V-715
VT-V-715
MT-V-505
UT-V-482
MT-V-505
UT-V-482
MT-V-505
UT-V-482
MT-V-505
UT-V-482
MT-V-505
UT-V-482
MT-V-505
UT-V-482
S01V2V045 SAT
S01V2V046 SAT
419A
419A
419A
419A
419A
419A
S0lV2M001 NRI
S01V2U326 NRI
S01 V2M002 NRI
S01V2U327 NRI
S01 V2M003 NRI
SOIV2U328 NRI
S01 V2M004 NRI
S01V2U329 NRI
S01 V2M009 NRI
S01V2U330 NRI
S01 V2M010 RI
SOlV2U331 NRI
N/A
N/A
SEE AUGMENTED SUMMARY SECTION FOR DETAILS AND RESULTS.
SEE AUGMENTED SUMMARY SECTION FOR DETAILS AND RESULTS.
N/A
N/A
N/A
N/A
N/A
MT RI / CODE ACCEPTABLE.
6-1
(
21201 -V6-001 -801
CLOSURE HEAD STUDS
21201 -V6-001 -802
CLOSURE HEAD STUDS
21201-V6-001--B03
CLOSURE HEAD STUDS
21201 -V6-001 -804
CLOSURE HEAD STUDS
21201-V6-001 -B05
CLOSURE HEAD STUDS
21201-V6-001-B06
CLOSURE HEAD STUDS
(
VEGP-2 EIGHTH MAINTENANCE / REFUELING OUTAGE
CLASS 1 EQUIPMENT EXAMINATIONS
ASME SECTION XI ITEM NO./CAT.
AUGMENTED EXAMINATION REQUIREMENT(S)
B6.30
B-G-1
B6.30 B-G-1
B6.30 B-G-1
B6.30
B-G-1
B6.30
B-G-1
B6.30
B-G-1
B6.30
B-G-1
B6.30
B-G-1
B6.30
B-G-1
B6.30 B-G-1
COMPONENT OR WELD NO. / DESCRIPTION
21201-V6-001-B07
CLOSURE HEAD STUDS
21201-V6-001-B08
CLOSURE HEAD STUDS
21201-V6-001-B09
CLOSURE HEAD STUDS
21201-V6-001-B10
CLOSURE HEAD STUDS
21201-V6-001-B11
CLOSURE HEAD STUDS
21201-V6-001-B12
CLOSURE HEAD STUDS
21201-V6-001-B13
CLOSURE HEAD STUDS
21201-V6-001-B14
CLOSURE HEAD STUDS
21201-V6-001-B15
CLOSURE HEAD STUDS
21201-V6-001-B16
CLOSURE HEAD STUDS
EXAMINATION PROCEDURE(S)
MT-V-505
UT-V-482
MT-V-505
UT-V-482
MT-V-505
UT-V-482
MT-V-505
UT-V-482
MT-V-505
UT-V-482
MT-V-505
UT-V-482
MT-V-505
UT-V-482
MT-V-505
UT-V-482
MT-V-505
UT-V-482
MT-V-505
UT-V-482
CALIBRATION BLOCK(S)
419A
419A
419A
419A
419A
419A
419A
419A
419A
419A
EXAM SHEET NO(S).
S01 V2M01 1
S01V2U332
RESULTS
NRI
NRI
S01 V2M005 NRI
S01V2U333 NRI
S01V2M006 NRI
SOIV2U334 NRI
S01V2M007 NRI
S01V2U335 NRI
S01V2M008 NRI
S01V2U336 NRI
S01 V2M012 NRI
S01V2U350 NRI
S01V2M013 NRI
S01V2U351 NRI
S01 V2M014 NRI
S01V2U352 NRI
S01 V2M015 NRI
S01V2U353 NRI
S01 V2M016 NRI
S01V2U354 NRI
6-2
(
REMARKS
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
(
VEGP-2 EIGHTH MAINTENANCE / REFUELING OUTAGE
CLASS 1 EQUIPMENT EXAMINATIONS
ASME SECTION XI ITEM NO./CAT.
B6.30 B-G-1
AUGMENTED EXAMINATION REQUIREMENT(S)
COMPONENT OR WELD NO. / DESCRIPTION
212014-6-001 -B317 CLOSURE HEAD STUDS
EXAMINATION PROCEDURE(S)
MT-V-505
UT-V-482
CALIBRATION BLOCK(S)
419A
EXAM SHEET NO(S).
S01 V2M01 7
S01 V2U355
FSAR 5.3.3.7
B6.30
B-G-1
B 13.10
B-N-I
B6.10
B-G-1
B6.10
B-G-1
B6.10 B-G-1
B6.10 B-G-1
B6.10
B-G-1
B6.10
B-G-1
B6.10 B-G-1
B6.10
B-G-1
21201 -V6-001 -118
CLOSURE HEAD STUDS
21201-V6-001-102
VESSEL CLOSURE HEAD INTERIOR
21201-V6-001-NO1
CLOSURE HEAD NUTS
21201 -V6-001 -N02
CLOSURE HEAD NUTS
21201 -V6-001 -N03
CLOSURE HEAD NUTS
21201-V6-001-N04
CLOSURE HEAD NUTS
21201 -V6-001 -N05
CLOSURE HEAD NUTS
21201 -V6-001 -N06
CLOSURE HEAD NUTS
21201 -V6-001 -N07
CLOSURE HEAD NUTS
21201 -V6-001 -N08
CLOSURE HEAD NUTS
MT-V-505
UT-V-482
VT-V-735
419A
VT-V-715
VT-V-715
VT-V-715
VT-V-715
VT-V-715
VT-V-715
VT-V-715
VT-V-715
S01 V2M018 NRI
S01V2U356 NRI
S01V2V006 SAT
S01V2V009 SAT
S01V2V010 SAT
S01V2V011 SAT
S01V2V012 SAT
S01V2V013 SAT
S01V2V014 SAT
S01V2V015 SAT
S01V2V023 SAT
6-3
(
RESULTS
NRI
NRI
REMARKS
N/A
VT-1 PER RR-5
VT-1 PER RR-5
VT-1 PER RR-5
VT-1 PER RR-5
VT-1 PER RR-5
VT-1 PER RR-5
VT-1 PER RR-5
VT-1 PER RR-5
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
il
( (
VEGP-2 EIGHTH MAINTENANCE/ REFUELING OUTAGE
CLASS 1 EQUIPMENT EXAMINATIONS
ASME AUGMENTEDSECTION XI EXAMINATION ITEM NO./CAT. REQUIREMENT(S)
COMPONENT OR WELD NO. / DESCRIPTION
EXAMINATION CALIBRATION PROCEDURE(S) BLOCK(S)
EXAM SHEET NO(S). RESULTS
B6.10
B-G-1
B6.10
B-G-1
B6.10
B-G-1
86.10 B-G-1
B6.10 B-G-1
B6.10
B-G-1
B6.10
B-G-1
B6.10 B-G-1
B6.10
B-G-1
B6.10
B-G-1
B6.50
B-G-1
B6.50
B-G-1
VT-i PER RR-5
VT-1 PER RR-5
VT-I PER RR-5
VT-i PER RR-5
VT-i PER RR-5
VT-I PER RR-5
VT-I PER RR-5
VT-I PER RR-5
VT-I PER RR-5
VT-i PER RR-5
REMARKS
21201 -V6-001 -N09
CLOSURE HEAD NUTS
21201 -46-001 -N 10
CLOSURE HEAD NUTS
21201 -46-001 -N 1I
CLOSURE HEAD NUTS
21201 -V6-001 -N12
CLOSURE HEAD NUTS
21201 -V6-001 -N13
CLOSURE HEAD NUTS
21201-V6-001 -N 14
CLOSURE HEAD NUTS
21201 -46-001 -N 15
CLOSURE HEAD NUTS
21201 -46-001 -N16
CLOSURE HEAD NUTS
21201-V6-001-N17
CLOSURE HEAD NUTS
21201 -V6-001-N18
CLOSURE HEAD NUTS
21201 -V6-001 -S01
CLOSURE WASHERS
21201 -V6-001-S02
CLOSURE WASHERS
VT-V-71 5
VT-V-715
VT-V-715
VT-V-715
VT-V-715
VT-V-715
VT-V-715
VT-V-715
VT-V-715
VT-V-715
VT-V-71 5
VT-V-715
S0l1V2V024
S0l1V2V025
S01'V2V026
S01 V2V031
S01'V2V032
S01 V2V033
S01'V2V034
S01 V2V035
S01 V2V036
S01 V2V037
S01V2V016
S01V2V017
SAT
SAT
SAT
SAT
SAT
SAT
SAT
SAT
SAT
SAT
SAT
SAT
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
6-4
ASME AUGMENTED SECTION XI EXAMINATION ITEM NO./CAT. REQUIREMENT(S)
B6.50
B-G-1
B6.50
B-G-1
B6.50
B-G-1
B6.50
B-G-1
B6.50
B-G-1
B6.50
B-G-1
B6.50 B-G-1
B6.50
B-G-1
B6.50
B-G-1
B6.50
B-G-1
B6.50
B-G-1
B6.50 B-G-1
COMPONENT OR WELD NO. / DESCRIPTION
21201-V6-001 -S03
CLOSURE WASHERS
21201 -V6-001 -S04
CLOSURE WASHERS
21201 -V6-001 -S05
CLOSURE WASHERS
21201-V6-001-S06
CLOSURE WASHERS
21201 -V6-001 -S07
CLOSURE WASHERS
21201-V6-001-S08
CLOSURE WASHERS
21201-V6-001-S09
CLOSURE WASHERS
21201-V6-001-S10
CLOSURE WASHERS
21201 -V6-001 -Sl$
CLOSURE WASHERS
21201-V6-001-S12
CLOSURE WASHERS
21201-V6-001 -S 13
CLOSURE WASHERS
21201 -V6-001-S14
CLOSURE WASHERS
VEGP-2 EIGHTH MAINTENANCE / REFUELING OUTAGE
CLASS 1 EQUIPMENT EXAMINATIONS
EXAMINATION CALIBRATION EXAM S PROCEDURE(S) BLOCK(S) NO(S).
VT-V-715 S01 V2VC
VT-V-715 S01 V2V(
VT-V-715 S01 V2VC
VT-V-715 S01V2V(
VT-V-715 S01 V2V(
VT-V-715 S01 V2V(
VT-V-715 S01 V2V(
VT-V-715 S01 V2V(
VT-V-715 S01 V2V(
VT-V-715 S01 V2V(
VT-V-715 S01 V2V(
VT-V-715 S01 V2V(
HEET
318
319
320
321
)22
027
028
029
030
038
339
040
6-5
(
RESULTS
SAT
SAT
SAT
SAT
SAT
SAT
SAT
SAT
SAT
SAT
SAT
SAT
REMARKS
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
i.
(
VEGP-2 EIGHTH MAINTENANCE / REFUELING OUTAGE CLASS I EQUIPMENT EXAMINATIONS
ASME SECTION XI ITEM NO./CAT.
AUGMENTED EXAMINATION REQUIREMENT(S)
COMPONENT OR WELD NO. / DESCRIPTION
EXAMINATION PROCEDURE(S)
CALIBRATION BLOCK(S)
EXAM SHEET NO(S). RESULTS REMARKS
B6.50 B-G-1
B6.50 B-G-1
B6.50
B-G-1
B6.50
B-G-1
NRC BULL. 88-09
WTECH BULL NS
B3.120
B-D
B3.120
B-D
B2.11
B-B
21201-V6-001-SI5
CLOSURE WASHERS
21201-V6-001-S16
CLOSURE WASHERS
21201-V6-001-S17
CLOSURE WASHERS
21201-V6-001 -S18
CLOSURE WASHERS
21201-V6-001-TO1 - T58
INCORE FLUX THIMBLE TUBES
21201-V6-001-T01-OD - T58-OD
THIMBLE TUBE GUIDE TUBES
21201 -V6-002-IR-01
6" SAFETY NOZZLE INNER RADIUS
21201 -V6-002-IR-04
6" RELIEF NOZZLE INNER RADIUS
21201 -V6-002-WO1
UPPER HEAD TO UPPER SHELL WELD
VT-V-715
VT-V-715
VT-V-715
VT-V-715
VENDOR
VENDOR
UT-V-416
UT-V-416
UT-V-411
S01V2V041 SAT
S01V2V042 SAT
51 V2V043 SAT
S01V2V044 SAT
N/A
N/A
N/A
N/A
SEE AUGMENTED SUMMARY SECTION FOR DETAILS AND RESULTS.
SEE AUGMENTED SUMMARY SECTION FOR DETAILS AND RESULTS.
411A
411A
403A, 411A
S01V2U423 NRI
SO1V2U424 NRI
S01V2U435 SOlV2U437
SOIV2U438
S01V2U439
S01V2U440
S01V2U441
S01V2U442
S01V2U443
N/A
N/A
NRI NRI
NRI NRI
NRI
NRI
NRI
NRI
UT SCANS LIMITED / RR-7.
6-6
(
C (
VEGP-2 EIGHTH MAINTENANCE / REFUELING OUTAGE CLASS 1 EQUIPMENT EXAMINATIONS
ASME SECTION XI ITEM NO.ICAT.
AUGMENTED EXAMINATION REQUIREMENT(S)
B2.12
B-B
MT PER RR-7B3.110
B-D
MT PER RR-7B3.110 B-D
MT PER RR-7B3.1 10 B-D
B5.40
B-F
COMPONENT OR WELD NO. I DESCRIPTION
21201 -V6-002-W06
UPPER SHELL LONGITUDINAL WELD
21201 -V6-002-W1 0
UPPER HEAD TO 6" SAFETY NOZZLE WELD
21201 -V6-002-W1 I
UPPER HEAD TO 6" SAFETY NOZZLE WELD
21201 -V6-002-W1 6
14" SURGE NOZZLE WELD TO LOWER HEAD
21201 -V6-002-W1 7
6" SAFETY NOZZLE TO SAFE END WELD
EXAMINATION PROCEDURE(S)
UT-V-411
MT-V-505 UT-V-411
MT-V-505
UT-V-411
MT-V-505
UT-V-411
PT-V-605
UT-V-404
CALIBRATION BLOCK(S)
403A
411A
411A
411A
324A, 355A
RESULTS
NRI
NRI
NRI
NRI
EXAM SHEET NO(S).
S01V2U431
S01V2U432
SOlV2U433
S01V2U434
S01 V2M019
S01V2U367
S01V2U368
S01V2U369
S01 V2U370
S01V2M020
S01 V2U363
S01 V2U364
S01V2U365
SO1V2U366
S01 V2M021
S01V2U372
S01V2U373
SO1V2U374
S01V2U375
S01V2P025
S01V2U390
S01V2U391
S01 V2U392
SO1V2U393
S01V2U394
S01V2U395
S01V2U396
S01V2U397
REMARKS
UT SCANS LIMITED / CODE CASE N-460 (>90%).
UT SCANS LIMITED / RR-7.
UT SCANS LIMITED / RR-7.
UT SCANS LIMITED / RR-7.
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
6-7
UT SCANS LIMITED / RELIEF REQUEST REQUIRED.
(
VEGP-2 EIGHTH MAINTENANCE / REFUELING OUTAGE
CLASS 1 EQUIPMENT EXAMINATIONS
ASME SECTION XI ITEM NO./CAT.
AUGMENTED EXAMINATION REQUIREMENT(S)
COMPONENT OR WELD NO. / DESCRIPTION
EXAMINATION PROCEDURE(S)
CALIBRATION BLOCK(S)
EXAM SHEET NO(S). RESULTS REMARKS
21201 -V6-002-W1 8
6" SAFETY NOZZLE TO SAFE END WELD
21201 -V6-002-W1 9
6" SAFETY NOZZLE TO SAFE END
21201 -V6-002-W20
6" RELIEF NOZZLE TO SAFE END WELD
PT-V-605
UT-V-404
PT-V-605
UT-V-404
PT-V-605
UT-V-404
324A, 355A
324A, 355A
324A, 355A
B5.40
B-F
S01V2P026
S01V2U398
S01V2U401
S01V2U404
S01V2U407
S01V2U410
S01V2U413
S01V2U416
S01V2U419
S01V2P027
S01V2U399
S01V2U402
S01V2U405
S01 V2U408
S01V2U411
S01V2U414
S01V2U417
S01V2U420
S01V2P028
S01V2U400
S01V2U403
SO1V2U406
S01V2U409
S01V2U412
S01V2U415
S01V2U418
S01V2U421
UT SCANS LIMITED / RELIEF REQUEST REQUIRED.
PT RI / CODE ACCEPTABLE. UT SCANS LIMITED / RELIEF REQUEST REQUIRED.
UT SCANS LIMITED / RELIEF REQUEST REQUIRED.
6-8
(
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
RI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
B5.40
B-F
B5.40
B-F
(
VEGP-2 EIGHTH MAINTENANCE/ REFUELING OUTAGE
CLASS I EQUIPMENT EXAMINATIONS
ASME SECTION XI ITEM NO./CAT.
AUGMENTED EXAMINATION REQUIREMENT(S)
COMPONENT OR WELD NO. / DESCRIPTION
EXAMINATION PROCEDURE(S)
CALIBRATION BLOCK(S)
EXAM SHEET NO(S). RESULTS REMARKS
21201 -V6-002-W22
14" SAFE END WELD TO SURGE NOZZLE
B5.40 B-F
PT-V-605
UT-V-404315A, 357A N/AS01V2P020
S01V2U357
S01V2U358
S01V2U359
S01V2U360
S01V2U361
S01V2U362
NRI NRI
NRI
NRI
NRI
NRI
NRI
6-9
(
VEGP- 2 EIGHTH MAINTENANCE / REFUELING OUTAGE
CLASS 1 PIPING EXAMINATIONS
ASME SECTION XI ITEM NO./CAT.
B9.11 B-J
AUGMENTED EXAMINATION REQUIREMENT(S)
COMPONENT OR WELD NO. I DESCRIPTION
21201-053-6
14" PIPE TO SAFE END
21201-056-1
6" SAFE END TO ELBOW
21201-057-1
6" SAFE END TO ELBOW
21201-058-1
6" SAFE END TO ELBOW
21201-058-7
6" ELBOW TO FLANGE
B9.11
B-J
B9.11 B-J
B9.11
B-J
B9.11
B-J
B7.50
B-G-2
B7.70
B-G-2
B9.11
B-J
B9.11
B-J
21201-058-7 FB
6" FLANGE BOLT ASSEMBLY FOR
21201 -PSV-801 OA
21201 PSV801 OA
VALVE BOLTING (ISI-21201-058)
21201-059-1
6" SAFE END TO ELBOW
21201-059-11
6" PIPE TO TEE
EXAMINATION PROCEDURE(S)
PT-V-605 UT-V-481
PT-V-605
UT-V-481
PT-V-605
UT-V-481
PT-V-605
UT-V-481
PT-V-605
UT-V-481
VT-V-715
VT-V-715
PT-V-605 UT-V-481
PT-V-605 UT-V-481
CALIBRATION BLOCK(S)
315A
304A, 324A
304A, 324A
304A, 324A
304A
EXAM SHEET NO(S).
S01V2P021 NRI S01V2U376 NRI
S01V2P018 S01V2U380
S01V2U381
S01V2P019
S01V2U386 S01V2U387
S01V2P016 S01V2U384
S0lV2U385
S01V2PO17
S01V2U388
S01V2U389
S01V2V004 SAT
S01V2V003 SAT
304A, 324A
304A, 348A
S01V2P012 S01V2U382 S01V2U383
S01V2P022
S01V2U427
S01V2U428
NRI NRI
RI
NRI
NRI
NRI
NRI NRI
RI
NRI
NRI
NRI
RESULTS REMARKS
N/A
UT RI / GEOMETRY.
N/A
UT RI / GEOMETRY.
UT SCANS LIMITED / RELIEF REQUEST REQUIRED.
EXAMINED IN PLACE UNDER TENSION.
EXAMINED IN PLACE UNDER TENSION.
UT RI / GEOMETRY.
N/A
NRI NRI RI
NRI
NRI
NRI
7-1
( (
C
ASME AUGMENTED SECTION XI EXAMINATION ITEM NO./CAT. REQUIREMENT(S)
B9.21
B-J
B9.21
B-J
B9.21
B-J
B9.21
B-J
B9.21
B-J
B9.11
B-J
B9.11
B-J
B9.21
B-J
B9.21
B-J
B9.21
B-J
B9.21
B-J
C (
COMPONENT OR WELD NO. / DESCRIPTION
21201-059-14
3" REDUCER TO ELBOW
21201-059-15
3" ELBOW TO ELBOW
21201-059-17
3" PIPE TO VALVE
21201-059-18
3" VALVE TO PIPE
21201-059-21
3" PIPE TO VALVE
21201-060-1
6" TEE TO PIPE
21201-060-2
6" PIPE TO REDUCER
21201-060-3
3" REDUCER TO ELBOW
21201-060-4
3" ELBOW TO ELBOW
21201-060-5
3" ELBOW TO PIPE
21201-060-6
3" PIPE TO VALVE
VEGP- 2 EIGHTH MAINTENANCE / REFUELING OUTAGE
CLASS 1 PIPING EXAMINATIONS
EXAMINATION CALIBRATION EXAM SHEET PROCEDURE(S) BLOCK(S) NO(S).
PT-V-605 S01V2P029
PT-V-605 S01V2P030
PT-V-605 S01V2P013
PT-V-605 S01V2P014
PT-V-605 S01V2P015
PT-V-605 304A S01V2P023
UT-V-481 S01V2U425
PT-V-605 304A S01V2P024
UT-V-481 S01V2U426
PT-V-605 S01V2P031
PT-V-605 S01V2P032
PT-V-605 S01V2P033
PT-V-605 S01V2P034
RESULTS
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
NRI
7-2
REMARKS
N/A
N/A
N/A
N/A
N/A
UT SCANS LIMITED I CODE CASE N-460 (>90%).
N/A
N/A
N/A
N/A
N/A
C
VEGP- 2 EIGHTH MAINTENANCE / REFUELING OUTAGE CLASS I PIPING EXAMINATIONS
ASME SECTION XI ITEM NO./CAT.
AUGMENTED EXAMINATION REQUIREMENT(S)
COMPONENT OR WELD NO. / DESCRIPTION
EXAMINATION PROCEDURE(S)
CALIBRATION BLOCK(S)
EXAM SHEET NO(S). RESULTS REMARKS
21201-060-7
3" VALVE TO PIPE
21201-060-10
3" PIPE TO VALVE
21204U6079
VALVE BOLTING (ISI-21204-124)
PT-V-605
PT-V-605
VT-V-715
S01V2P035 NRI
S01V2P036 NRI
S01V2V005 SAT
N/A
N/A
EXAMINED IN PLACE UNDER TENSION.
7-3
(
B9.21 B-J
B9.21 B-J
B7.70 B-G-2
VEGP- 2 EIGHTH MAINTENANCE / REFUELING OUTAGE CLASS 2 EQUIPMENT EXAMINATIONS
ASME SECTION XI ITEM NO.ICAT.
C2.21
C-B
AUGMENTED EXAMINATION REQUIREMENT(S)
COMPONENT OR WELD NO. I DESCRIPTION
212011-B6-001-W18
32" STEAM OUTLET NOZZLE TO UPPER HEAD WELD
EXAMINATION CALIBRATION PROCEDURE(S) BLOCK(S)
MT-V-505 409A
UT-V-411
EXAM SHEET NO(S).
S01V2M023
RESULTS
NRI
REMARKS
SURFACE ONLY. VOLUMETRIC PERFORMED 2R7.
8-1
VEGP- 2 EIGHTH MAINTENANCE / REFUELING OUTAGE
CLASS 2 PIPING EXAMINATIONS
ASME SECTION XI ITEM NO.ICAT.
C5.11
C-F-1
AUGMENTED EXAMINATION REQUIREMENT(S)
A[ 87-0131
Al 87-0131C5.11
C-F-1
C5.11
C-F-1
C5.11
C-F-1
C5.11
C-F-1
Al 87-0131
A[ 87-0131
A[ 87-0131
Al 87-0131C5.11 C-F-1
C5.11 C-F-1
Al 87-0131
COMPONENT OR WELD NO. / DESCRIPTION
21204-008-3
8" PIPE TO ELBOW
21204-008-4
8" ELBOW TO PIPE
21204-011-6
6" PIPE TO TEE
21204-012-10
8" ELBOW TO PIPE
21206-005-1
8" FLANGE TO PIPE
21206-005-2
8" PIPE TO ELBOW
21206-006-1
8" FLANGE TO PIPE
EXAMINATION CALIBRATION PROCEDURE(S) BLOCK(S)
PT-V-605 UT-V-481
PT-V-605
UT-V-481
PT-V-605
UT-V-481
PT-V-605
UT-V-481
PT-V-605
UT-V-481
PT-V-605
UT-V-481
PT-V-605
UT-V-481
414A
414A
337A
414A
414A
414A
414A
EXAM SHEET NO(S).
S01V2P001
S01V2U 302
S01V2U303
S01V2P002
S01V2U304
S01V2U305
S01V2P008
S01V2U307
S01V2U308
S0lV2P011
S01V2U306
S0lV2U322
S01V2P007
S01V2U314
S01V2U319
S01V2U320
S01V2U321
S01V2P006
S01V2U317
S01V2U318
S01V2P003
S01V2U315
S0lV2U316
S01V2U323
RESULTS REMARKS
NRI
NRI
T&C
NRI
NRI
T&C
NRI
NRI
T&C
NRI
NRI
T&C
NRI
NRI
NRI
NRI
T&C
NRI
NRI
T&C
NRI
NRI
T&C
NRI
N/A
N/A
N/A
N/A
UT SCANS LIMITED / RELIEF REQUEST REQUIRED.
N/A
UT SCANS LIMITED / RELIEF REQUEST REQUIRED.
9-1
VEGP- 2 EIGHTH MAINTENANCE / REFUELING OUTAGE
CLASS 2 PIPING EXAMINATIONS
ASME SECTION XI ITEM NO./CAT.
C5.11
C-F-1
C5.11
C-F-1
C3.20 C-C
C3.20 C-C
AUGMENTED EXAMINATION REQUIREMENT(S)
Al 87-0131
Al 87-0131
COMPONENT OR WELD NO. I DESCRIPTION
21206-006-2
8" PIPE TO ELBOW
21206-006-3
8" ELBOW TO PIPE
21206-006-18
SUPPORT H008
21206-006-41
SUPPORT H015
EXAMINATION CALIBRATION PROCEDURE(S) BLOCK(S)
PT-V-605
UT-V-481
PT-V-605
UT-V-481
PT-V-605
PT-V-605
414A
414A
EXAM SHEET NO(S).
S01V2P004
S01V2U312
S01V2U313
S01V2P005
S01V2U309
S01V2U310
RESULTS REMARKS
NRI
NRI
T&C
NRI
NRI
T&C
S01V2P010 NI
S01V2P009 NRI
N/A
N/A
N/A
N/A
9-2
C ( I,
ASME Sect. Support No. & Examination Exam XI Cat. ISI Class Description. Procedures Sheet No. Results Remarks
See Note A See Note B See Note C See Note D See Note E See Note F See Note G
NOTES:
A. The ASME Section XI category designation for the equipment support is listed in this column.
B. The ASME Section XI class no., e.g., 1, 2, or 3, for the system on which the equipment support being examined is listed in this column.
C. The equipment support number and support description are listed in this column.
D. This column lists the applicable NDE procedure(s) used during the examination. When a class 3 support lists VT-V-715 (VT-1) in addition to VT-V-735 (VT-3), the class 3 support also received a VT-1 on the integral attachment per IWD-2500-1 and Code Case N-509 (RR-20).
E. This column references the examination data sheet(s) which serve to document the examination and lists the examiner, any pertinent remarks, etc.
F. The results of the examinations are indicated in this column.
G. The remarks column is used to describe any pertinent features of the examination such as limitations, reportable results, INFs, etc. Refer to INF section in this report for their disposition.
FIGURE 2. EXPLANATION OF EQUIPMENT SUPPORT SUMMARY TABLE FORMAT
10-1
EQUIPMENT SUPPORT EXAMINATIONS
No equipment support examinations were performed during the 2R8 maintenance/refueling outage.
10-2
( ( I
ASME Sect. Support No. & Examination Exam
XI Cat. ISI Class NPS (In.) Description Procedure(s) Sheet No. Results Remarks
See Note A See Note B See Note C See Note D See Note E See Note F See Note G See Note H
NOTES:
A. The ASME Section XI category designation for the piping support is listed in this column.
B. The ASME Section XI class no., e.g., 1, 2, 3, for the system on which the piping support being examined is listed in this column.
C. This column indicates the nominal pipe size in inches for the piping on which the piping support is being examined.
D. The piping support number and support description are listed in this column.
E. This column lists the applicable NDE procedure(s) used during the examination. When a class 3 support lists VT-V-715 (VT-1) in addition to
VT-V-735 (VT-3), the class 3 support also received a VT-1 on the integral attachment per IWD-2500-1 and Code Case N-509 (RR-20).
F. This column references the data sheet(s) which serve to document the examination and list the examiner, any pertinent remarks, etc.
G. The results of the examinations are indicated in this column.
H. The remarks column is used to describe any pertinent features of the examination such as limitations, reportable results, INFs, etc. Refer to INF section in this
report for their disposition.
FIGURE 3. EXPLANATION OF PIPING SUPPORT SUMMARY TABLE FORMAT
11-1
PIPING SUPPORT EXAMINATIONS
No piping support examinations were performed during the 2R8 maintenance/refueling outage.
11-2
Snubber Mfgr/Size
See Note C
Scope Examined
See Note D
A. The unique tag number for the snubber being examined is listed in this column.
B. The ASME Section XI class no., e.g., 1, 2, 3, for the system on which the snubberbeing examined is listed in this column.
C. This column lists the name of the manufacturer of any snubbers functionally tested and the size of the snubber, e.g., PSA-1/4. Manufacturer designations are abbreviated and can be found in the List of Abbreviations.
D. This column lists the scope of examination in which the snubber is functionally tested, i.e., original scope or expanded scope. Snubbers included in the expanded scope of examination are generally as a result of other snubber functional test failures.
E. The results of the functional test of the snubber tested is listed in this column.
FIGURE 4. EXPLANATION OF SNUBBER FUNCTIONAL TEST RESULTS SUMMARY TABLE FORMAT
12-1
Tag Number
See Note A
ISI Class
See Note B
NOTES:
Results
See Note E
TAG NUMBER 21201-239-H001
21204-057-H019
21208-047-H604
21217-073-H623
21305-063-H1004
21305-063-H004E
22402-022-11004
22402-023-H003
VEGP-2 EIGHTH MAINTENANCE/REFUELING OUTAGE SNUBBER FUNCTIONAL TESTS
TYPE I SNUBBERS
SNUBBER SCOPE ISI CLASS MFGR/SIZE EXAMINED RE 2 PSA-1/2 EXPANDED PA,
2 PSA-1/2 PREV FAILURE PA
1 PSA-1/2 PREV FAILURE PA
3 PSA-1/4 ORIGINAL PA
- PSA-1/2 PREV FAILURE PA
- PSA-1/2 PREV FAILURE PA
PSA-1/4 ORIGINAL PA
PSA-1/4 ORIGINAL PA
SULTS SS
SS
SS
SS
SS
SS
SS
SS
TYPE II SNUBBERS
TAG NUMBER 21201-030-H608
21201-030-H611
21206-005-11008
21208-001-H026
21301-015-H007
21301-094-H002
21305-155-H003
ISI CLASS 1
1
2
1
2
SNUBBER MFGR/SIZE PSA-3
PSA-3
PSA-3
PSA-3
PSA-3
PSA-10
PSA-3
SCOPE EXAMINED ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
EXPANDED
ORIGINAL
TYPE Ill SNUBBERS
TAG NUMBER 21201-053-11005
21204-126-H020
21305-056-H022B
ISI CLASS 1
SNUBBER MFGR/SIZE PSA-35
PSA-35
PSA-35
SCOPE EXAMINED ORIGINAL
ORIGINAL
ORIGINAL
12-2
RESULTS PASS
PASS
PASS
PASS
PASS
FAILED
PASS
RESULTS PASS
PASS
PASS
VEGP-2 EIGHTH MAINTENANCE/REFUELING OUTAGE SNUBBER FUNCTIONAL TESTS
(continued)
TYPE IV SNUBBERS
TAG NUMBER 21201-014-H641
21201-051-H006
21201-106-HOOI
21202-231-H030
21204-192-HOOI
21208-007-H002
21208-008-H025
21208-011-H045
21208-055-H046
21208-225-H004
21217-071-H628A
21301-118-H011
21301-121-H004
21301-127-H024
21301-128-H006
21301-129-HO16
21301-136-H003
21301-137-H004
21301-139-H003
21301-168-HOOI
21301-168-HO12
21301-213-H003
21302-108-H005
21302-109-HO13
21302-109-HO15
21302-110-H019
ISI CLASS 2
1
2
2
1
2
2
2
2
3
2
2
2
2
2
2
2
2
2
2
2
2
2
SNUBBER MFGR/SIZE AD-41
AD-41
AD-71
AD-153
AD-503
AD-501
AD-73
AD-41
AD-153
AD-41
AD-41
AD-151
AD-43
AD-503
AD-501
AD-151
AD-71
AD-151L
AD-71
AD-41
AD-73
AD-73
AD-503
AD-503
AD-501
AD-501
SCOPE EXAMINED ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
PREV. FAILURE
ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
EXPANDED
ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
ORIGINAL
12-3
RESULTS PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
VEGP-2 EIGHTH MAINTENANCE/REFUELING OUTAGE SNUBBER FUNCTIONAL TESTS
(continued)
TYPE V SNUBBERS
12-4
TAG N UMBER 21201-064-11614A
21201-064-H614B
21201-064-11625
21202-004-H073
21204-023-HOOI
21204-023-11005
21204-023-H009
21204-024-H038
21204-025-H006
21204-043-H013
21204-125-H007
21205-007-H019
21208-008-H018
21301-014-H005
21301-015-H004
21301-104-H004
21301-104-11005
21301-104-11006
21301-105-11002
21301-105-1-1003
21301-105-11006
21301-106-11002
21301-106-11005
21301-106-11006
21301-107-11004
21301-107-11005
ISI CLASS
3
1
1
1
1
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
SNUBBER MFGR/SIZE AD-1603
AD-1603
AD-1601
AD-1601
AD-5501
AD-1603
AD-1601
AD-1601
AD-1601
AD-1601
AD-5501
AD-1603
AD-1603
AD-1603
AD-1603
AD-5501
AD-5501
AD-5501
AD-5503
AD-12501
AD-5501
AD-5503
AD-5501
AD-5501
AD-5501
AD-5501
SCOPE EXAMINED ORIGINAL
EXPANDED
EXPANDED
ORIGINAL
ORIGINAL
EXPANDED
ORIGINAL
EXPANDED
EXPANDED
EXPANDED
EXPANDED
ORIGINAL
EXPANDED
EXPANDED
ORIGINAL
EXPANDED
EXPANDED
EXPANDED
ORIGINAL
CR#199901715
EXPANDED
EXPANDED
EXPANDED
EXPANDED
ORIGINAL
EXPANDED
RESULTS PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
FAILED
PASS
PASS
PASS
PASS
PASS
PASS
PASS
FAILED
PASS
PASS
PASS
VEGP-2 EIGHTH MAINTENANCE/REFUELING OUTAGE SNUBBER FUNCTIONAL TESTS
(continued)
TYPE V SNUBBERS (continued)
TAG NUMBER 21301-107-H006
21302-109-H018
21302-109-H024
21302-110-HO13
21305-058-H003
21305-058-HOO5
21305-060-1-1003
21305-060-HG005
21305-062-H006
21305-064-H006
22403-036-H601
ISI CLASS 2
2
2
2
2
2
2
2
2
2
SNUBBER MFGR/SIZE AD-5501
AD-1603
AD-1603
AD-1601
AD-12501
AD-12501
AD-12501
AD-12501
AD-12501
AD-12501
AD-1601
SCOPE EXAMINED EXPANDED
ORIGINAL
EXPANDED
ORIGINAL
EXPANDED
ORIGINAL
EXPANDED
EXPANDED
ORIGINAL
EXPANDED
EXPANDED
TYPE VI SNUBBERS
SNUBBER MFGR/SIZE
SCOPE EXAMINED
212011-B6-002-S08 2
RESULTS PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
PASS
TAG NTTMRE•R TSI CTA~Sq
PM-25701
RESULTS
ORIGINAL PASS
12-5
NUMBER ISI CLASS
SYSTEM PRESSURE TESTS
The following pressure tests were included in the scope of the eighth maintenance/refueling outage (2R8) at VEGP-2. These pressure tests included system inservice tests and system leakage tests. No functional tests or hydrostatic tests were performed during 2R8. Boundaries for the pressure tests that were performed during 2R8 are described in the VEGP-2 Inservice Inspection Plan - Second 10-Year Interval document. Examination results are discussed in the applicable sections of this report document. The examination data for these pressure tests is available at the plant site for review upon request.
System Inservice Test Schedule (ITs)
System Leakage Test Schedule (LT)
LT Exam. Test Description
B-PI Class 1 System Leakage Test
NOTE 1: Most portions of this pressure test boundary were examined prior to the end of the seventh maintenance/refueling outage. The remaining portions were examined after the end of the seventh maintenance/refueling outage after the incorporation of a design change (DCP-V2NO056) which replaced the positive displacement charging pump with a centrifugal-type normal charging pump.
13-1
INDICATION NOTIFICATION FORMS
No Indication Notification Forms were required during the 2R8 maintenance/refueling outage.
14-1
OWNER'S REPORTS FOR REPAIRS OR REPLACEMENTS (FORM NIS-2)
The following Owner's Reports for Repairs or Replacements (Form NIS-2) are provided for work activities documented at VEGP-2 since the last maintenance/refueling outage (2R7) through the completion of the eighth maintenance/refueling outage (2R8) in May 2001. Reports are identified by their respective traveler number which is denoted on each of the NIS-2 reports. The originals of the NIS-2 reports are filed with their respective traveler packages at the plant site. Only those NIS-2 reports applicable to VEGP-2 are included in this report document. Any attachments, e.g., code data reports, etc., referenced in the NIS-2 reports will be made available for review upon request at the plant site.
The NIS-2 reports for the following travelers are included herein:
96236 99138 99181 99224 99264 99282 96348 99139 99189** 99226 99265 99283 99050 99140 99190** 99227 99266 99285 99051 99141 99191 99228 99267 00015 99052 99142 99202 99229 99271 00087 99115 99143 99204 99232 99272 00090
99124 99144 99209 99233 99273 00139 99125 99145 99210 99257 99274 00141
99127 99146 99211 99258 99275 00157
99128 99148 99218 99259 99276 00193 99129 99149 99219 99260 99277 01003
99130** 99150** 99221 99261 99278 01011 99131 99170 99222** 99262 99279 99133 99179** 99223 99263 99280
"**These travelers are certified on the same NIS-2 report:
99130 is certified with 99222, 99150 is certified with 99179, and 99189 is certified with 99190.
15-1
ORIGINAL FORM NIS-2 OW 4ER'S REPORT FOR REPAIRS OR REPLACEMENTS
As F ,quired By The Provisions Of The ASME Code Section Xl
Traveler # 96-236
1. Owner Georgia Power CompFny Name
333 Piedmont Avenue, Atlanta GA.
2. Plant Voqtle Electric Generatina Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Namr-e
4. Identification Of System
Date
Sheet
Unit
MWO #
9/12/96
I of
2
29601768 Repair Organization P.O. No., Job No., etc.
Plant Voutle Address
1208 / Chemical and Volume Control Sv sten5. (a) Applicable Construction Code ASME SEC II1 1977 Edition, Winter 1977 Addenda, N-249-1 Code Case
(b)Applicable Edition of section XI Utilities For Repairs Or Replacements 1983
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTUR NATIONAL " REPAIRED, ASME CODE OF OF E', BOARD OTHER YEAR REPLACED OR STAMPED COMPONENT MANUFACTURER SERP L NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO)
PULLMAN NI.A N/A V2-1208-066-HO19 19d8o REPLACEMENT YES PIPE POWER •14 e/'1 SUPPORT PR UCT,-,q
7. Description Of Work Snubber Ar-43. S&W 402 was replaced with AD-43, SIN 258 to support surveillance testing.
8. Test Conducted: NIA
Hydrostatic ] Pneumatic[] Nominal Operating Pressure[] Other [] Pressure N/A PSI Test Temp. NiA OF
We certify that the statements made in th. report are correct and this rules of the ASME Code, Section XI.
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commtss-ion issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia arid employed by Hartford Steam boiler Insnection and Insurance Co of a C. nneticu have inspected the components described in this Owner's Report during the period • , , to -, - o , and state that to ýhe best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
s�-1
By signing this certificate, neither !he Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any nner for any personal injury or property damage or a loss of any kind arising from or connected with this ýi Commissions 9A0o3
"Ineor's Signature National Board, State, Provi:.:- and Endorsements
Date /_ 200
FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS As Required By The Provisions Of The ASME Code Section XI
Traveler
I Owner
2 Plant
flsrn/. Din.,.. fla.,.a....
Name 333 Piedmont Avenue. Atlanta GA
Voati. Electtlc Generatino Piau,
Wa*nasbr-O. CA 102l8aAddress
3 Work Performed ByL % Maintenance
Date I1, -A % sheet____________
unit_
Repair Organization P.O. No., Job No., etc.
P/anf VefiftName Address
4 identification Of Systm \ \ ~ d\~ ~~'~ ~ ImA kAC-'ý 5 ali Applicable Construction Code.ASME SEC i•1 .EEdition, Witeor 1•t Addenda, N-249-. Code Case
fb) Applicable Edition Of Section XI Utilities For Repairs Or Replacernents 19.U
I idenlafication Of Components Repairs Or Replaced And Replacement Components
%&ME NAME MANUFACTURER NATIONAL REPAIRED, ASME COOE or OF SERIAL eo7o OmE YEAR R0AEt.•.D OR STAMPED _.______ENT MANUFACTURER NO. NO. IDENTIFICATION GMT RAYCS OR NO
Puolman Po,•,t WA -\ Xl\ 9 j Pope Support Products NWA W/A \rc -, ýA6 _- "f,•Q 98 Repnl_€emen.t
7. Description Of Work Snubbi
8. Tests Conducted: WNAIW
.Serlal#
Hydrostatic:: Pneumatic: Nominal Operating Pressure0 OtherZ Pressum PSI Test Temp. _ F
CERTIFICATE OF COMPLANCE - V, " We certify that the statements made in the report are correct and this e-.o\ r. :- conforms to the rules of the ASME Code, Section XL
repair or replacement
Type Code Symbol Stamp.
Certificate of Atlthýation No.
AI'IQIUVW OT • u~r,,NMsNlAN1A Date
O....... r. ....... -'"; mI'+ " '
WA
WI' xpiraton UDat
Date . . nao -
was re laced wth AD - 1 Serial 0 Lt 1 -1
WA72/]+
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid conmission issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Gworala and employed by Harfford Steam Boiler Inspecctlon and Insurance Co. of Hartford, Connectlicut have inspected the components described in this Owner's Report during the period I&-7-1-. to. JL-Wo60 -, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owner's Report in accordance with the requirements of the ASME Code, Section XL
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manner for any personal Injury or property damage or a loss of any kind arising from or connected with this inspection. ,
Comriss.ons GA 701
Nauonal Board, State, Province and EndorsementsDate
Voatle Ef tife Commune PLa,.#
. - . ....... •rlT1
i
,ý, 4- - -,a -ý. ctc",-,rea
I r ¸
Owner or Owner's Desi - -a ,
,99(-Zol----- "• Ybl
AD- I
v_
'ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern NuclearOperating Company Name
40 Invemess Center Parkway, Birmingham, AL
2. Plant Vogte Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99050
09/15/99
Of
2
29900308 Repair Organization P.O. No., Job No., etc.
Plant VoctleAddress
4. Identification Of System 1208 / Chemical and Volume Control
5. (a) Applicable Construction Code ASME SEC III 1974 Edition, Summer 1975 (b)Applicable Edition of section Xi Utilities For Repairs Or Replacements 19M
6. Identification Of Components Repairs Or Replacement Components
system
Addenda, NIA
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) VALVE ROCKWELL BX844 N/A 2-1208-U4-483 1985 REPLACEMENT YES
INTERNATIONAL
7. Description Of Work Performed locking tack weld on valve caD to body connection per WPCS 990050.
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating Pressure[E] NIA Other E Pressure N/A PSi Test Temp. N/A 9F
CERTIFICATE OF COMPLIANCE
We certify that the statements made In the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed Owne or Ownr ' TDate IT 19 Owner or Owner's Designee,Tti
Date //-/9 19 010
4l
Code Case
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticut have inspected the components described In this Owner's Report during the period 01/21/99 to //- Jq-L t , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section Xi.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this
Ins ACti " •A-2L/aý- L Commissions__ ____
Inspector's Signature / National Board, State, Province and Endorsements
ORIGINAL. FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xi
Traveler # 99051
1. Owner Southem Nuclear Operating CompanyName
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogte Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations MaintenanceName
Date
Sheet
Unit
03/23/00
1 Of 3
2
MWO # WO# 29900499, PO# 7038022 and PO# 7038895 Repair Organization P.O. No., Job No., etc.
Plant Vogtle Address
4. Identification Of System 1201 / Reactor Coolant System
5. (a) Applicable Construction Code ASME SEC IIl 1971 Edition, Winter 1972 (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
Addenda, N/A
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) SAFETY CROSBY VALVE N60446-02- N/A 2PSV-8OOB 1978 REPLACEMENT YES
VALVE & GAGE CO. 0028
7. Description Of Work Valve was re=laced. The reolacement valve was purchased under PO 7038022 from Union Electric's, Plant Callowav as S/N N60446-00-0028. The setooint pressure for this valve was changed by Crosby Valve & Gaoe Company under PO 7038895 in accordance with DCP 97-V2N0009. CrosbV Valve & Gaae Company assigned SIN N60446-02-0028 to this valve uoon completion of the setnoint chance. A copy of Form NV- i for the original serial numbered replacement valve is attached.
8. Test Conducted: WA-
Hydrostatic [] Pneumatic[l Nominal Operating Pressure[x' Other [] Pressure NIA PSI Test Temp. N/A
Date 7- 120
I
Code Case
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. Repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No. a A
Owner or Owner's Desinee, Title 7
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Geoomia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticui have Inspected the components described In this Owner's Report during the periodQIl . to owAriJA.a, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any man for any personal injury or property damage or a loss of any kind arising from or connected with this inspepton. /J/
_______________ __.____- ___ Commissions (•4ppJ' "Inspec)6r's Signature National Board, State, Province and Endorsements
2000•
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
1. Owner Southern Nuclear Operating CompanyName
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations MaintenanceName
4. Identification Of System
Date
Sheet
Unit
Traveler # 99052
03/30/00
Of 3
2
MWO # WO# 29900499, PO# 7038220 and PO# 7038895 Repair Organization P.O. No., Job No., etc.
Plant Vogtle Address
1201 / Reactor Coolant System
5. (a) Applicable Construction Code ASME SEC III 1971 Edition, Winter 1972 (b)Applicable Edition of Section Xi Utilized For Repairs Or Replacements 19L9
Addenda, N/A Code Case
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) SAFETY CROSBY VALVE N60446-02- N/A 2PSV-801IA 1978 REPLACEMENT YES VALVE & GAGE CO. 0006
7. Description Of Work Valve was replaced. The replacement valve was purchased under PO 7038220 from Union Electric's, Plant Callowav as S/N N60446-00-0006. The setooint pressure for this valve was changed by Crosby Valve & Gace Company under PO 7038895 in accordance with DCP 97-V2NO009. Crosby Valve & Gage Company assgqned S/N N60446-02-0006 to this valve upon completion of the setpoint chance. The valve nozzle, disc insert and spindle assembly were also replaced durino this modification. A cony of Form NV-1 for the oriomnin~ _.rrinl
8. Test Conducted: MAD
61II1I�
Hydrostatic [ PneumaticE Nominal Operating Pressure'X Other ] Pressure N/A PSI Test Temp. N/A 2F
I
CERTIFICATE OF COMPLIANCE
We certify that the statements made In the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. Repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No. _ror__,__seeTtl_
Signed ~ )l~J-~, ae' 1 20 &o~ Ow-ner -or `Owner's Designlee, Ttie -
CERTIFICATE OF INSERVICE INSPECTION
1, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticut have inspected the components described In this Owner's Report during the period 01/25/99 to 7-/L-x -, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore,. neither the Inspector nor his employer shall be liable In any mann for any personal Injury or property damage or a loss of any kind arising from or connected with this
VY//,&' s_.x. ,_... Commissions _ A__ 3__ "lnspectssig;nature National Board, State, Province and Endorsements
Date 7-...(" 20 oOe•
soindle assembly were also replaced dunna this modification A cony of Forin NV-1 for the nrini, / sF,_Z" 2EWkWa-U.
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogde Elecfrc Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99115
08112J99
! of 3
2
29901418 Repair Organization P.O. No., Job No., etc.
Plant VogUeAddress
4. Identification Of System 1202/NuclearService Cooling Water
6. (a) Applicable Construction Code ASME SEC III 1974 Edition, Winter 1975 (b)Applicable Edition of section Xl Utilities For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
System
Addenda, N/A Code Case
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) VALVE CROSBY VALVE N67951-00-0011 N/A 2PSV-11744 1999 REPLACEMENT YES
& GAGE CO.
7. Description Of Work Safety relief valveS/N N67951-00-0003 was replaced with S/N N67951-00-001 1. A copy of Form NV-I for the replacement valve is attached,
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating Pressurerx NWA [] Other Fl Pressure NIA PSI Test Temp. N/A OF
CERTIFICATE OF COMPUANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. NIA Expiration Date N/A
Signed " 64 ,. ,•") J- Date }iu 19 q9 Owner or Owner's Designee, TitleL/
4 i'CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Geormia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticut have inspected the components described in this Owner's Report during the period 04/21/99 to 9.j-0-7-9 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in an manner for any perxe al injury or property damage or a loss of any kind arising from or connected with this ins ion. Commissions . g4S,7
Inspectors Signature 7 Nationdl Board, State, Province and Endorsements
Date Z' •7 19
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
1. Owner Southern Nuclear Operating CompanyName
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99124
02/25/00
Of 5
2
29901684Repair Organization P.O. No., Job No., etc.
Plant VogtleAddress
4. Identification Of System 12081 Chemical and Volume Control System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Addenda, N/A Code Case (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989 Code Case N-416-1
6. Identification Of Components Repairs Or Replacement Components
I I. I ______________ I
7. Description Of Work Installed piping modifications per DCP 97-V2NO056. The modification included installation of orifice 2FO-10133 and a olobe valve (2-1208-U4-150). Copies of Form N-2 for the flow orifice (SIN 98P-91447) and Form NPV-1 for the olobe valve (SIN B3995) are attached,
8. Test Conducted: N/Al
Hydrostatic[] PneumaticE Nominal Operating Pressureg]Code Case N-416-1 Other R Pressure N/A PSI Test Temp. N/A 2F
Date ____-__ Zg_
'I
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO)
1208 PIPING SOUTHERN N/A N/A 2J3-1208-501-01 1999 REPLACEMENT NO SYSTEM NUCLEAR
IOPERA TING QQ-
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date F. :;2 W,4 N/A
Signed aYý _ Date atsO Owner or Owner's Designee, Tl1t%
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Ggooi.a and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have inspected the components described in this Owner's Report during the period 06/14/99 to j09- C)- ) - , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any onal Injury or property damage or a loss of any kind arising from or connected with this Ins~ton. _ _ _ _ _ __ _
I ionspeco 's " Commissions C alBog S Inpco' intrrNatinlBo ard, State, Province and Endorsements
-ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
Traveler # 99125
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Wavnesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO#
02t28/00
_ _ _ _ _ Of _
2
29901681 and 29901683 Repair Organization P.O. No., Job No., etc.
Plant VogSte Address
4. Identification Of System 1208 / Chemical and Volume Control System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Addenda, N/A Code Case
(b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989 Code Case N-416-1
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1208 PIPING SOUTHERN N/A N/A 2K3-1208-003-01 1999 REPLACEMENT NO
SYSTEM NUCLEAR
7. Description Of Work Installed Diping modifications eer DCP 97-V2NO056. This modification includes the installation of a flow orifice 2F0-10 124. fabricated under Section XI Traveler# 99132 and WO# 29901681.
8. Test Conducted: WAD
C
Hydrostatic [ Other E
Pneumatic[] Nominal Operating Pressure[K]Code Case N-416-1 Pressure WA PSI Test Temp. N/A OF
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date• l-N/A
Signed "N, Date ____,__ _
Owner or Owner's Designfee, TItI'-
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have Inspected the components described In this Owner's Report during the period 06114199 to 3.-ZZ- op O, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal Injury or property damage or a loss of any kind arising from or connected with this Insection. 9 " d.7 ln ,cf_!•j / , Commissions _ _ _ _ _ _ _ _
Inspector's Signature/ Nationial Board, State, Province and Endorsements
Date OkZZ-00
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xi
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830Address
Traveler # 99127
03/07/00Date
Sheet I Of 3
Unit
MWO#
3. Work Performed by Nuclear Operations Maintenance Name
2
29901682 Repair Organization P.O. No., Job No., etc.
Plant VogqteAddress
4. Identification Of System 1208 / Chemical and Volume Control System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Addenda, N/A (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989 Code Case N-416-1
6. Identification Of Components Repairs Or Replacement Components
Code Case
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1208 PIPING SOUTHERN N/A N/A 2K3-1208-123-01 1999 REPLACEMENT NO
SYSTEM NUCLEAR OPERATING QQ
7. Description Of Work Installed piping modifications per DCP 97-V2NO056. This modification included the installation of various pipe fittinos tccommainstallation of the new charoino pumo as well as 2" drain valve (2-1208-X4- 6071A conyof Form NPV-1 for this valve S/N C2499 is attached.
8. Test Conducted: NIAE
cAý
Hydrostatic [] Pneumatic[] Nominal Operating Pressure[X]Code Case N-4116-1 Other F1 Pressure NIA PSI Test Temp. NIA 'F
CERTIFICATE OF COMPLIANCE
We certify that the statements made In the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization.No. N/A Expiration Date N/A
Signed " ,1' J'i1kha-# Y n I Date 7 ) • 200, Owner or Owner's Designee, Title
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Insoection and Insurance Co. of Hartford. Connecticut have Inspected the components described In this Owner's Report during the period 0_114/99 to e,4-0-5-00_, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be lipble in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this In n Commissions 1A 4197
Inspector's Signaturoe National Board, State, Province and Endorsements
Date s 0-!5 20 40
!
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
1. Owner Southern Nuclear Operating Company Name
40 Invemess Center Parkway, Birmingham, AL
2. Plant Vogte Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance
Date
Sheet
Unit
MWO #
Name
Traveler # 99128
03/03/00
Of
2
29901732 Repair Organization P.O. No., Job No., etc.
Plant Voctle
Address
4. Identification Of System 1208 / Chemical and Volume Control System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Addenda, N/A Code Case (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989 Code Case N-416-1
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1208 PIPING SOUTHERN N/A N/A 2K3-1208-003-01 1999 REPLACEMENT NO
SYSTEM NUCLEAR 2K3-1208-003-03 OPERATING Q, 2K3-120R-09q-O1
7. Description Of Work Installed pininG modifications oer DCP 97-V2NO056. This modification included the installation of varinus nin,fittinas to accommodate installation of the new charaina Dump.
8. Test Conducted: WAJ
Hydrostatic r- Pneumatic[] Nominal Operating Pressure[Z]Code Case N-416-1 Other El Pressure N/A PSI Test Temp. N/A QF
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georaia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Harford. Connecticyu have inspected the components described in this Owner's Report during the period 06/14/99 to p5-ol/.. 600, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manner for any p~r~onal injury or property damage or a loss of any kind arising from or connected with this Insl:to - Co sn -- "=44tg- • • •••-- Commissions 1,4- 4"'97
National Board, State, Province and Endorsements
2o
-EInspector's Signature e'
Date /3_ - t•/
v
Sw • r
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
Traveler # 99129
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Voptle Electric Generating Plant
Waynesboro, GA 30830Address
Date
Sheet
Unit
MWO #
3. Work Performed by Nuclear Operations Maintenance Name
02122/00
I Of
2
29901624 and 29902725 Repair Organization P.O. No., Job No., etc.
Plant VogUeAddress
4. Identification Of System 1208 / Chemicai and Volume Control System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Addenda, N/A (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 19" Code Case N-416-1
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1208 PIPING SOUTHERN N/A N/A 2K3-1208-144-01 1999 REPLACEMENT NO
SYSTEM NUCLEAR OPERA TING QO
7. Description Of Work Installed eiia modifications per DCP 97-V2N056. The modification included installation of orifice plate 2F010123 which was fabricated under Traveler# 99221: the addition of a pressure indicator 2PI-8474: and the shortenino of the oump discharae spool.
8. Test Conducted: WAfl
Hydrostatic ] Pneumatic[] Nominal Operating Pressure[' Code Case N-416-1 Other 1] Pressure N/A PSI Test Temp. N/A 2F
Code Case
CERTIFICATE OF COMPLIANCE
We certify that the statements made In the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section Xi. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorlzatign No. N/A Expiration Date N/A
Signed Ti• Date "--'- D Owner or Owner's Designee, Title V
CERTIFICATE OF INSERVICE INSPECTION
1, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Insoection and Insurance Co. of Hartford, Connecticui have Inspected the components described in this Owner's Report during the period ,0621/)99 to _"- 9 -O , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section Xi.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for anyrprsonai injury or property damage or a loss of any kind arising from or connected with this "Ins"pinq Commissions ,A V9 7
Inspector's Signetu National Board, State, Province and Endorsements DateA
ORIGINAL' FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
Traveler # 99222 and 99130
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Voctle Electric Generatinq Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
4. Identification Of System
Date
Sheet
Unit
MWO #
11/30/99
1 Of I
2
29901625 and 29902725 Repair Organization P.O. No., Job No., etc.
Plant Vogtle Address
1208 / Chemical and Volume Control System
5. (a) Applicable Construction Code ASMESECIII 1977 Edition, Winter1977 Addenda, N/A Code Case (b)Appllcable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1208 PULLMAN N/A N/A 2K3-1208-146-01 1988 REPLACEMENT YES PIPING POWER
I YTnM PRODUCTS T
7. Description Of Work Fabricated and installed orfice plate 2F010122 with new boltino materials. Also, installed a sockolet on line 1208-154-4" per DCP 97-V2NO049.
8. Test Conducted: WAD
c
��.1
Hydrostatic [] Pneumatic[] Nominal Operating PressureFrI Other [] Pressure N/A PSI Test Temp. WA
.3
CERTIFICATE OF COMPUANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed / Oneo Owe' DesineeDate 1 /l 19 Owne orOnrsDsineil
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georqia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticu• have inspected the components described in this Owner's Report during the period 021/9 to 0a2 L - , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any peirsonal injury or property damage or a loss of any kind arising from or connected with this
djcX, - Commissions • I--7 Inspector's Signature V " National 3oard, State, Province and Endorsements
Date _02 - &d_ _JwA
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
Traveler # 99131
1. Owner Southern Nuclear Operating Company Name
40 Invemess Center Parkway, Birmingham, AL
2. Plant Vogtie Electric Generating Plant
Waynesboro, GA 30830Address
Date
Sheet
Unit
MWO #
3. Work Performed by Nuclear Operations Maintenance Name
02/22100
I Of 3
2
29901685 Repair Organization P.O. No., Job No., etc.
Plant VoqtleAddress
4. Identification Of System 1217 / Auxiliary Component Cooling Water System
5. (a) Applicable Construction Code ASME SEC IIl 1977 Edition, Winter 1977 Addenda, N/A (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 19§1 Code Case N-416-1
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1217 PIPING SOUTHERN N/A N/A 2K3-1217-182-02 1999 REPLACEMENT NO
SYSTEM NUCLEAR 2K3-1217-183-03 OPERA TING CO. 2K3-1217-184-01
2K3-1217-186-01
7. Description Of Work Installed DIino modifications oer DCP 97-V2NO056. Modifications include the installation of a 1-1/2" olobe valve. A copy of Form NPV-1 for this valve &W HO50ABJ is attached.
8. Test Conducted: WAE-
Hydrostatic R Pneumatic[] Nominal Operating PressurefZCode Case N-416-1 Other F1 Pressure NIA PSI Test Temp. NIA 2F
'3
Code Case
CERTIFICATE OF COMPLIANCE
We certify that the statements made In the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorizaton No. N/A Expiration Date NIA Signed IAa QDate "___..______
Owner or Owner's Designee, Titlf 90
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georqia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticut have Inspected the components described in this Owner's Report during the period 06/14/99 to 4- /-4-o , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report In accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in anyannr for any/,"rsonal Injury or property damage or a loss of any kind arising from or connected with this
ins I Commissionsc4tio 7 Inspector's Signaturi National Board, State, Province and Endorsements
Date_ _ _ _ _ _
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
Traveler # 991331. Owner Southern Nuclear Operating Company
Name 40 Inverness Center Parkway, Birmingharn, AL
2. Plant Vo10e Electic Generating Plant
Waynesboro, GA 30830 Address
Dats
Sheet
Unit
MWO #
03/03100
I Of
2
29901732 Repair Organization P.O. No., Joi No., eatc.
3. Work Performed by Nuclear Operations Maintenance Plant Vogfie
Name Address 4. Identification Of System 1204 / Safety Injection System 5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Addenda, N/A Code Case (b)Appllcable Edition of Section X1 Utilized For Repairs Or Replacements 198I" Code Case N-416-1
6. Identification Of Components Repairs Or Replacement Components
7. Description Of Work Installed oionOa modifications Per DCp 97-V2NO056. This mldifiction included the installation of a tee in line 1204-057-3' to loin line 1208-003-3'.
8. Test Conducted: N/A
Hydrostatic [3 PneumaticE] Nominal Operating Preseureg]Code Case N-416-1 Other [] Pressure N/A PSI Test Temp. N/A OF
CERTIFICATE OF INSERVICE INSPECTION 1, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georo2L and employed by Hartford Steam Boiler Inspection and Insurance Co. of H have Inspected the components described In this Owner's Report during the period__ Q1AW . to - o_-Z.C_, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report In accordance with the requirements of the ASME Code, Section XI. 0.. •-- -- .
sign.ng mis certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the Iminatlons and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall liable in any manner for any perso7 Injury or property damage or a loss of any kind arising from or connected with this ~cIon. Ar-A' Commissions 6;4.19/- 7
National Board, State, Province and EndorsementsAv �j
uste 20 bol
ORIGINALFORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Voglie Electic Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99138
02/16/00
I Of
2
29901687 Repair Organization P.O. No., Job No., etc.
Plant VogUeAddress
4. Identification Of System 1208 / Chemical and Volume Control
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
System
Addenda, N/A
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1208 PIPE SOUTHERN N/A N/A V2-1208-0O3-H606 1999 REPLACEMENT NO SUPPORT NUCLEAR
OPRTING CO.I
7. Description Of Work Installed Pice support per DCP 97-V2NO056.
8. Test Conducted: Hydrostatic [] PneumatlcEJ- Nominal Operating PressureE[ WA [] Other [ Pressure N/A PSI Test Temp. WA QF
CERTIFICATE OF COMPLIANCE
We certify that the statements made In the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authori1tio No. N/A Expiration Date N/A
Signed 1 2 I Date _____"_,,_c.___
Owner or Owner's Designee, Tooe 20 $t) O3-1"-CO
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georcia and employed by Hartford Steam Boiler Insoection and Insurance Co. of Hartford nnecti have Inspected the components described in this Owner's Report during the period__.Q9 A ___ to " , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report In accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal Injury or property damage or a loss of any kind arising from or connected with this
ZA.~ ý ý& Commissions G4 4/97 Inspector's Signaturdr National Board, State, Province and Endorsements
Date 0 - 4•-
I
Code Case
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xi
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99139
03/03/00
Of
2
29901732Repair Organization P.O. No., Job No., etc.
Plant VogdeAddress
4. Identification Of System 12081 Chemical and Volume Control System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Addenda, N/A Code Case (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1208 PIPE SOUTHERN N/A N/A V2-1208-OO3-H605 1999 REPLACEMENT NO SUPPORT NUCLEAR
OPERA TING CO.
7. Description Of Work Installed pipe support per DCP 97-V2N056,
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating Pressure[] WA [j Other E Pressure WA PSI Test Temp. N/A 2F
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section Xi. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorizatin N7. N/A Expiration Date N/A
Signed or tle Date Owner or Owner's Designee, Title
Date os5- 6/ 20ob
7
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State oi Province of Georoia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have inspected the components described in this Owner's Report during the period 06/14/99 to t6"-/-oa , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be II ble in any manner for any persoll: injury or property damage or a loss of any kind arising from or connected with this in • .• Ž •-4L. •-• •-Commissions S_ __ _ _
Inspector's Signature National Board, State, Province and Endorsements
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
Traveler # 99140
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Blrminqham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
4. Identification Of System
Date
Sheet
Unit
MWO #
03/03100
I Of
2
29901732 Repair Organization P.O. No., Job No., etc.
Plant VodlleAddress
1208 / Chemical and Volume Control System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Addenda, N/A (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
Code Case
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1208 PIPE SOUTHERN N/A N/A V2-1208-003-H607 1999 REPLACEMENT NO SUPPORT NUCLEAR
OPERATING C.
7. Description Of Work Installed pide suoport oar DCP 97-V2NO056,
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating Pressure[] N/A E] Other [] Pressure N/A PSI Test Temp. N/A 9F
CERTIFICATE OF COMPUANCE We certify that the statements made In the report are correct and this REPLACEMENT Conforms to the
rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
# Certificate of Authorization No. N/A Expiration Date N/A
A) Y '0w Signed or kwn r Date 11n 20 Owner or Owner's Designee,V1
Date _____________
I
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of bolier and Pressure vessel Inspectors and the State oi Province of Georqia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have Inspected the components described in this Owner's Report during the period 06/14/99 to Lb5"o/-20t0.3 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section Xi,
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any persnal injury or property damage or a loss of any kind arising from or connected with this _ _ _ _ _ _ Commissions n __/,9_7_
Inspector's Signature National Board, State, Province and Endorsements
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
Traveler # 99141
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham. AL
2. Plant Voptle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
03/03/00
I Of 1
2
29901732 Repair Organization P.O. No., Job No., etc.
Plant VootleAddress
4. Identification Of System 1208 / Chemical and Volume Control System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Addenda, N/A (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 19§.
6. Identification Of Components Repairs Or Replacement Components
Code Case
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1208 PIPE SOUTHERN N/A N/A V2-1208-003-H029 1999 REPLACEMENT NO SUPPORT NUCLEAR SOPERATING QO
7. Description Of Work Installed Dioe supoort oer DCP 97-V2NO056,
8. Test Conducted: Hydrostatic [] Pneumatlc-- Nominal Operating Pressure[] N/A FXJ Other rE Pressure N/A PSI Test Temp. N/A F
CERTIFICATE OF COMPMANCE
We certify that the statements made In the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date N/A
Signed " . Qý 4 Date 20_ Mner or Owner's Designee, TItle L1
5�O
C-
CERTIFICATE OF INSERVICE INSPECTION
1, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georoia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticut have Inspected the components described in this Owner's Report during the period 06/14/-to 1)5- 61.260c and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manner for any personal injury or property damage or a loss of any kind arising from or connected with this
__ Commissions c;, Isti~on., (I,•/7 "
Inspector's Signature National Board, State, Province and Endorsements
Date 2000- )/
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
4.
5.
6.
Date
Sheet
Unit
MWO #
Traveler # 99142
02/16/00
1 Of 1
2
29901687 Repair Organization P.O. No., Job No., etc.
Plant VogtieAddress
Identification Of System 1208 / Chemical and Volume Control System
(a) Applicable Construction Code ASME SEC Ill 1977 Edition, Winter 1977 Addenda, N/A Code Case (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1208 PIPE SOUTHERN N/A N/A V2-1208-123-H604 1999 REPLACEMENT NO SUPPORT NUCLEAR
OPERA TING C(Q.
7. Description Of Work Installed Pipe support per DCP 97-V2NO056.
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating Pressure[] NIA Other ] Pressure WA PSI Test Temp. WA 2F
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date N/A
SOgnedrnejor ne' Dn I T ke Date _ /,___-__
Owner or (Uner's Designee, T1#e) '4000 1~
I
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georqia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticul have Inspected the components described In this Owner's Report during the period 06/14/99 to -O.-:6..,, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manger for any pars al injury or property damage or a loss of any kind arising from or connected with this Insp:in - , f/1,("
!t- LJ . _ Commissions GX LZ97 Inspector's Signature 9V National Board, State, Province and Endorsements
Date 2ýO -. 260_0
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xi
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations MaintenanceName
Date
Sheet
Unit
MWO #
Traveler # 99143
02/16/00
I Of 1
2
29901687 Repair Organization P.O. No., Job No., etc.
Plant VoatleAddress
4. Identification Of System 1217 / Auxiliary Component Cooling Wat
5. (a) Applicable Construction Code ASME SEC I/1 1977 Edition, Winter 1977 (b)Applicable Edition of Section Xi Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
er System
Addenda, N/A Code Case
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1217 PIPE SOUTHERN N/A N/A V2-1217-182-H601 1999 REPLACEMENT NO SUPPORT NUCLEAR
OPERA TING CO.
7. Description Of Work Installed iDe suDOort per DCP 97-V2NO056,.
8. Test Conducted: Hydrostatic F1 PneumaticE] Nominal Operating Pressure[] N/A [ Other ] Pressure N/A PSI Test Temp. N/A 2F
CERTIFICATE OF COMPUANCE
We certify that the statements made In the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date N/A
Signed ,2 1k / . Date "..//•.' -R) Owner or Owner's Designee, Titlo'J
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Insoection and Insurance Co. of Hartford. Connecticut have Inspected the components described In this Owner's Report during the period 06/A1_4/99 to 613- Z4- 00 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any per Il Injury or property damage or a loss of any kind arising from or connected with this
42~~J AýLOýC; Commissions A~4 0 -7Inspectors Signature f /
Date - 20 -ft. ZQ.O
National Board, State, Province and Endorsements
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
1. Owner Southern Nuclear Operating CompanyName
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Wainesboro, GA 30830Address
3. Work Performed by Nuclear Operations MaintenanceName
Date
Sheet
Unit
MWO #
Traveler # 99144
02/16/00
I Of 1
2
29901687 Repair Organization P.O. No., Job No., etc.
Plant VootleAddress
4. Identification Of System 1217 / Auxiliary Component Cooling Wa
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 (b)Applicable Edition of Section Xi Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
.ter System
Addenda, N/A
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1217 PIPE SOUTHERN N/A N/A V2-1217-183-H621 1999 REPLACEMENT NO SUPPORT NUCLEAR
OPERATING CO.
7. Description Of Work Installed pipe suoport per DCP 97-V2N0056.
8. Test Conducted: Hydrostatic [ Pneumatic[] Nominal Operating Pressure[_ NWA RX Other R Pressure N/A PSI Test Temp. WA 2F
CERT1FICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date N/A
Signed a 1A4 Date 4& //rp -1 e:a
Owner or Own'er's Designee, Title -a -t 00,.
Code Case
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticul have Inspected the components described in this Owner's Report during the period 06/14/99 to a3-,O-0 -, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any man or for any perspnoI Injury or property damage or a loss of any kind arising from or connected with this a,. 7 commissions -04V?7
Inspector's Signature National Board, State, Province and Endorsements
Date ___________
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtie Electric Generating Plant
Date 0
Sheet 1
Unit
raveler # 99145
2/16/00
Of I
2
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
MWO # 29901687Repair Organization P.O. No., Job No., etc.
Plant Vogtle Address
4. Identification Of System 1208 / Chemical and Volume Control System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Addenda, N/A Code Case (b)Appilcable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO)
1208 PIPE SOUTHERN N/A N/A V2-1208-501-H602 1999 REPLACEMENT NO SUPPORT NUCLEAR
OPERA TING C.
7. Description Of Work Installed pipe suPcort per DCP 97-V2NO056.
8. Test Conducted: Hydrostatic [] PneumaticE] Nominal Operating PressureL] N/A[K Other [ Pressure N/A PSI Test Temp. N/A 2F
CERTIFICATE OF COMPMANCE
We certify that the statements made In the report are correct and this REPLACEMENT Conforms to the
rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date N/A
Signed a,., 2f o-4, De ) ))R Owner or Owner's Designee, Title 47 ;Vo-i,.Oj
c111Dk
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georqia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticu have inspected the components described In this Owner's Report during the period 061L4L92 to 10-00 -, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any pe on Injury or property damage or a loss of any kind arising from or connected with this inspe ion.I
_____ _____ mmissions 64i 497nd? inspector' Sinature National Board, State, Province and Endorsements
Date 03-20 -'r2-6
K.-
'1 4
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830Address
Date
Sheet
Unit
MWO #
02/16/00
I Of 1
2
29901687 Repair Organization P.O. No., Job No., etc.
3. Work Performed by Nuclear Operations Maintenance Name
4. Identification Of System
Plant Vogte Address
1208 / Chemical and Volume Control Svstem
5. (a) Applicable Construction Code ASME SEC li 1977 Edition, Winter 1977 Addenda, N/A (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
Code Case
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1208 PIPE SOUTHERN N/A AVA V2-1208-501-H603 1999 REPLACEMENT NO SUPPORT NUCLEAR
OPERA TING CO.
7. Description Of Work Installed ipe suoo oer DCP 97-V2NO056.
8. Test Conducted: Hydrostatic E] Pneumaticj] Nominal Operating PressureaZ N/A F] Other [] Pressure N/A PSi Test Temp. NIA 9=
CERTIFICATE OF COMPUANCE
We certify that the statements made In the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section Xi. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date N/A
Signed Owner oO r C.Dl4 M44i -Date -4;Owner or Owner's Designee, TItl~'6' .
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xi
Traveler # 99146
CERTIFICATE OF INSERVICE INSPECTION
1, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have Inspected the components described In this Owner's Report during the periodgfid.12-_ to 1-2, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section Xi.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personpl-.injury or property damage or a loss of any kind arising from or connected with this
_,.d••i-. i . ,- Commissions 4 V9 Inspector's Signature 0 National Board, State, Province and Endorsements
Date 03 - 4 2
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xi
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant VogUe Electdc Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99148
02/16/00
I Of 1
2
29901687 Repair Organization P.O. No., Job No., etc.
Plant VootleAddress
4. Identification Of System 1208 / Chemical and Volume Control
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1919
6. Identification Of Components Repairs Or Replacement Components
Systemn
Addenda, N/A
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1208 PIPE SOUTHERN N/A N/A V2-1208-123-H603 1999 REPLACEMENT NO SUPPORT NUCLEAR
OPERATIING CQ
7. Description Of Work Installed pipe supoort per DCP 97-V2N0056.
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating Pressure[] N/A [] Other El Pressure N/A PSI Test Temp. N/A OF
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorlzgtiol No. N/A Expiration Date N/A
Signed )•1ýý) Date _ _ _ 5-3 Owner or Owner's Designee, Title 0 ,4Ou -)7-eO
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georcia and employed by Hartford Steam Boiler Insoection and Insurance Co. of Hartford. Connecticul have Inspected the components described In this Owner's Report during the period_06/14/99 to o-Zo- -, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report Furthermore, neither the Inspector nor his employer shall be liable in any manner for any persiqal Injury or property damage or a loss of any kind arising from or connected with this
~cZZ sy4__ý e Commissions (,# 497
Inspector's Signature •/
Date '. -00 4. _
National Board, State, Province and Endorsements
I
Code Case
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xi
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
Traveler# 99149
Date 02/16/00
Sheet Of
Unit 2
MWO # 29901687 Repair Organization P.O. No., Job No., etc.
Plant VogteAddress
4. Identification Of System 1208 / Chemical and Volume Control System
5. (a) Applicable Construction Code ASME SEC II 1977 Edition, Winter 1977 Addenda, N/A Code Case (b)Applicable Edition of Section Xi Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1208 PIPE SOUTHERN N/A N/A V2-1208-501-H601 1999 REPLACEMENT NO SUPPORT NUCLEAR
7. Description Of Work Installed ioe suoort er DCP 97-V2NO056.
8. Test Conducted: Hydrostatic [1 Pneumatic[] Nominal Operating Pressurea] NWA nX Other n] Pressure NIA PSI Test Temp. NIA 2F
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section Xi. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date N/A
Signed Ye) e-h & k Date - / ) 46-e- 62.' Owner or Owner's Designee, Titi6' "3 0 - (7-00
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georqia and employed by Hartford Steam Boiler Insoection and Insurance Co. of Hartford. Connecticut have Inspected the components described in this Owner's Report during the period 06/14/99 to p3 -20- on , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report In accordance with the requirements of the ASME Code, Section Xi.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measur"_ .described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any person• lIinjury or property damage or a loss of any kind arising from or connected with this Ins oction. I~i
__ _____ __ _ __ __ommissions e (/97 Inspector's Signature National Board, State, Province and Endorsements
Date Q)A- ,20r
R I
k
#
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
Traveler # 99150199179
1. Owner Southern Nuclear Operating Company Date 1219/99
Name 40 Inverness Center Parkway, Birmingham, Sheet I Of 2
Ala.
2. Plant Vogtle Electric Generating Plant Unit 2
Waynesboro, GA 30830 MWO # 29901719
Address Repair Organization P.O. No., Job No., etc.
3. Work Performed by Nuclear Operations Maintenance Plant Vogtlie
Name Address
4. Identification Of System 12021 NUCLEAR SERVICE COOLING WATER SYSTEM
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 77 Addenda, N/A Code Case
(b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE
OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO)
PIPING PULLMAN N/A N/A 2K3-1202-187-01 1988 REPLACEMENT YES
SYSTEM POWER - PRODUCTS
PIPING PULLMAN N/A N/A 2K3-1202-222-01 1988 REPLACEMENT YES
SYSTEM POWER PRODUICTS
PIPING PULLMAN N/A N/A 2K3-1202-187-02 1988 REPLACEMENT YES
SYSTEM POWER _pRCIOLUCTS
PIPING PULLMAN N/A N/A 2K3-1202-002-01 1988 REPLACEMENT YES
SYSTEM POWER PROBUCjrTS
PIPING PULLMAN N/A N/A 2K(3-1202-226-01 1988 REPLACEMENT YES
SYSTEM POWER PRODUCTS
PIPING PULLMAN N/A N/A 2K3-1202-187-03 1988 REPLACEMENT YES
SYSTEM POWER I pRODUtCTS
PIPING PULLMAN N/A N/A 2K3-1202-002-02 1988 REPLACEMENT YES
SYSTEM POWER _ Q pRoQIDUTS _
PIPING PULLMAN N/A N/A 2K3-1202-194-01 1988 REPLACEMENT YES
SYSTEM POWER
7. Description Of Replaced exlsting studs and nuts with corrosion resistant material per REA 97-VAA678 at the bolted
Work connections In the following Iocations:.2FE1818A.2HV1806 2FE1818B.2HV1822.2HV2143.2FE2132A.2HV" 1808.2FE-1820A.2HV-1830.2FE-1820B, 2H-12138. 2FE2132B, 2-1202U4-197,2HV-1 1687,21202U4-199. 2HV
11688: blind flanqes near 2FE-1820A,2FE1820B.2HV11687, and flanaed soacer near2-1204-P6-003.
8. Test Conducted: Hydrostatic [] PneumaticZ] Nominal Operating Pressure[
N/A E] Other [] Pressure N/A PSI Test Temp. N/A 2F
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
Section XI Travelers 99150/ 99179 Page 2 of 2
repair or replacement
CERTIFICATE OF COMPUANCE
Conforms to theREPLACEMENTWe certify that the statements made in the report are correct and this rules of the ASME Code, Section Xl.
WAType Code Symbol Stamp
WAExpiration DateCertificate of Authorization No. N/A
Signed 4)a) 4 • 1e )-- . Date Owner or Owner's Designee, Atle
19 !4
."- :J.��'
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgla and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticut have Inspected the components described In this Owner's Report during the period /, - I- 9! to 12-14-w •9?, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be lieale in any manner for any pers o4al injury or property damage or a loss of any kind arising from or connected with this °'Inspeglon"
ns t :;e' J •• Commissions t?-4' 7
Inspector's Signature i National Board, State, Province and Endorsements
Date 1900
'ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southem NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99170
11/17/99
I Of
2
29901380 Repair Organization P.O. No., Job No., etc.
Plant VootleAddress
4. Identification Of System 1301 / Main Steam System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
Addenda, N-249-1 Code Case
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
PIPE PULLMAN N/A N/A V2-1301-105-HO03 1988 REPLACEMENT YES SUPPORT POWER
PRODUCTS
7. Description Of Work Snubber AD- 12501. serial # 53 was replaced with AD-12501. serial # 23 to supoort surveillance testing.
8. Test Conducted: Hydrostatic f] Pneumatic[ Nominal Operating Pressure[-' N/A [] Other rI Pressure N/A PSI Test Temp. N/A F
CERTIFICATE OF COMPLIANCE
We certify that the statements made In the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A !No. .
Signed•l )( Th -//_f Date I 19 / i_ 9 Owner or Owner's Designee, Tie
Iv c�3�
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by H-arford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticut have inspected the components described In this Owner's Report during the period 06/02/99 to - - and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any persl I Injury or property damage or a loss of any kind arising from or connected with this
SCommissions 4A (197
Inspector's Signature ' National Board, State, Province and Endorsements
Date 19
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
Traveler # 99181
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830Address
Date 11/23/99
Sheet I Of 2
Unit
MWO #
3. Work Performed by Nuclear Operations Maintenance Name
2
29901721 Repair Organization P.O. No., Job No., etc.
Plant VogtleAddress
4. Identification Of System 1202 /Nuclear Service Cooling Water System
5. (a) Applicable Construction Code ASME SEC //I 1977 Edition, Winter 1977 Addenda, N/A (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
Code Case
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1202 PULLMAN N/A N/A 2K4-1202-188-03 1988 REPLACEMENT YES PIPING POWER 2K4-1202-192-04
SYSTEM PRODUCTS
1202 PULLMAN N/A N/A 2K4-1202-196-05 1988 REPLACEMENT YES PIPING POWER 2K4-1202-138-02
SYSTEM PRODUCTS
1202 PULLMAN N/A N/A 2K4-1202-139-02 1988 REPLACEMENT YES PIPING POWER 2K4-1202-225-03
SYSTEM PRODUCTS
1202 PULLMAN N/A N/A 2K4-1202-223-03 1988 REPLACEMENT YES PIPING POWER 2K4-1202-001-05
SYSTEM PRODUCTS I 1 1
7. Description Of Work Installed reolacement studs and nuts in accordance with REA 97-VAA678 on piing flanges located at the inlet and outlet of Containment Cooling Units 2-1501-A7-001-000: 2-1501-A7-002-000: 2-1501-A7-005-000: 2-1501-A7-
uuuuf••-J'l 'L/UU•'UU, J = r- ¶UL-UUIJII/ Pli~tU If Id(•UUUJ LIJ~lf( III i•d8fCJS IUCd1eU a~[ Zt-dd7: •PI--2224- 2F0 -2222 2F0-2225; 2FE-2227: 2FE-2230- 2F0-2184: 2FE-2186, 2F0-2188- 2FE-2190- 2F0-2228 and2F0-2231 (reference Section XI Traveler numbers 99181 throuah 99188).
8. Test Conducted: NIA
Hydrostatic [] Pneumatic[] Nominal Operating Pressure[] Other F- Pressure NWA PSI Test Temp. N/A
.
ORIGINAL Traveler # 99181
Sheet 2 of 2
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A N o . b a
D t Signed -Date __ __ __ _i 9 Owner or Owner's Designee, Title
Date /_ _ __9 19
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticu; have inspected the components described in this Owner's Report during the period 015/9_ to / 4.-'- ?9 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this
a-., •- ",ZeL ( , Commissions .4 e19 7
Inspector's Signature' National Board, State, Province and Endorsements
1. Owner S
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
Traveler # 99189; 99190
outhern Nuclear Operating Company Date 11/24/99Name
40 Inverness Center Parkway, Birmingham, Ala.
2. Plant Vogtle Electric Generatinl Plant
Waynesboro, GA 30830
Sheet
Unit
MWO #
1Ot 2
2
29901723Address Repair Organizatl
3. Work Performed by Nuclear Operations Maintenance Plant Vo! Name Addre
4. Identification Of System 1202 1 NUCLEAR SERVICE COOLING WATER
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 77 Addenda, (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components:
on P.O. No., Job No., etc.
gtless
SYSTEM
N/A Code Case
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO)
PIPING PULLMAN N/A N/A 2K7-1202-215-01 1988 REPLACEMENT YES SYSTEM POWER
PRODUCTS PIPING PULLMAN N/A N/A 2K7-1202-099-01 1988 REPLACEMENT YES
SYSTEM POWER PROOU•rT.1 PIPING PULLMAN N/A N/A 2K7-1202-098-01 1988 REPLACEMENT YES SYSTEM POWER
PRODUCTS PIPING PULLMAN N/A N/A 2K7-1202-213-01 1988 REPLACEMENT YES
SYSTEM POWER PRODUCTS
PIPING PULLMAN N/A N/A 2K7-1202-228-01 1988 REPLACEMENT YES SYSTEM POWER
PRODUCTS£ PIPING PULLMAN N/A N/A 2K7-1202-232-01 1988 REPLACEMENT YES
SYSTEM POWER PRODUCTS
PIPING PULLMAN N/A N/A 2K7-1202-098-02 1988 REPLACEMENT YES SYSTEM POWER
_RODUCT_ PIPING PULLMAN N/A N/A 2K7-1202-099-02 1988 REPLACEMENT YES
SYSTEM POWER RODUC•TS
7. Description Of Replaced existing studs and nuts with corrosion resistant material per REA 97-VAA678 at the followin~f Work locations:2HV-8109.2FE-1821A.2HV.1831.2FE-1821B, 2HV1807. 2FE-1819A, 2HV-1823. 2FE=1819B. 2HV-2135.
8. Test Conducted: NIAE
ciMei nv-i moe. 01nv-i io-u. ann4 cl-naas near 0-97of-~J.185: 2-1202-X4-O70:2-1202-U4-184;2.1202-X4.53.
Hydrostatic [] Pneumatic[:] Nominal Operating PressureE] Other [] Pressure N/A PSI Test Temp. NIA
r,
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
Traveler Number - 99189; 99190 Page 2 of 2
CERTIFICATE OF COMPLIANCE
we certify that the statements made in the report are correct and this REPLACEMENT Conforms to the
rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp NIA
Certificate of Authorization No. N/A Expiration Date WA
Signed - '7 n• p- te I 19 :<• Owner or Owhner's Designee, Title
CERTIFICATE OF INSERVICE INSPECTION
1, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticut have inspected the components described in this Owner's Report during the period (,- /-9 I to /,?- 0 g-q -, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this Insectlon'/. 1 -, 4_, ",, Commissions a4 '/97
Inspector's Signature V National Board, State, Province and Endorsements
Date , 19 _
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
Traveler # 99191
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electrc Generating Plant
Waynesboro, GA 30830
Date 11/23/99
Sheet I Of 2
Unit
MWO #Address
3. Work Performed by Nuclear Operations Maintenance Name
2
29901722Repair Organization P.O. No., Job No., etc.
Plant VogteAddress
4. Identification Of System 1202 /Nuclear Service Cooling Water System
5. (a) Applicable Construction Code ASMESEC#III 1977 Edition, Winter1977 Addenda, (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1202 PULLMAN N/A N/A 2K4-1202-21 1-01 1988 REPLACEMENT YES PIPING POWER 2K4-1202-205-01 SYSTEM PRODUCTS
1202 PULLMAN N/A N/A 2K4-1202-209-02 1988 REPLACEMENT YES PIPING POWER 2K4-1202-212-02
SYSTEM PRODUCTS
1202 PULLMAN N/A N/A 2K4-1202-216-04 1988 REPLACEMENT YES PIPING POWER 2K4-1202-220-04
SYSTEM PRODUCTS
1202 PULLMAN N/A N/A 2K4-1202-229-05 1988 REPLACEMENT YES PIPING POWER 2K4-1202-140-01
SYSTEM PRODUCTS
1202 PULLMAN N/A N/A 2K4-1202-141-01 1988 REPLACEMENT YES PIPING POWER 2K4-1202-231-05
SYSTEM PRODUCTS I I 1 1
7. Description Of Work Installed replacement studs and nuts in accordance with REA 97-VAA678 on piping flanges located at the inlet and outlet of Containment Coolinq Units 2-1501-A7-002-000: 2-1501-A7-003-000: 2-1501-A7-004-000: 2-1501-A7007-01: 2-1501-A7-008-01: 2-151 I-E7-001-000: and 2-1515-A7-002-000. Also replaced bolting in flanges located at 2F0-2210: 2FE-2209: 2FE-2212: 2F0-2214: 2FE-2215 2FE-2218: 2F0-2216:2F0-2219: 2F0-2 185: 2FE-2191
8. Test Conducted: NIAE
and 2F0-2189 (reference Section XI Traveler numbers 99191 through 99200).
2F
N/A Code Case
Hydrostatic [] Pneumatic[] Nominal Operating PressureEl Other [ Pressure NIA PSI Test Temp. N/A
1202 / Nuclear Service
Cooling Water
System
ORIGINAL Traveler # 99191
Sheet 2 of 2
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed ne Ow Date ________ 19T Owner or Owner's Designee, Tidb
Date /42 -0 9
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticui have Inspected the components described In this Owner's Report during the period 6/1 5/99_ to j.-d9o99 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this
i,:24 Commissions 4A ("/7
Inspector's SNational Board, State, Province and Endorsements
-ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtile Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler #
I Of 2
2
29901858
99202
Repair urganization P.O. No., Job No., etc.
Plant Voatle
PAddroates4. Identification Of System 1302 / Auxiliary Feedwater System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Adc (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1912
6. Identification Of Components Repairs Or Replacement Components
denda, NIA
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED COMPONENT MANUFACTURER I NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) VALVE ANCHOR! E-9001-26-15 N/A 2-1302-U4-043 1980 REPAIR! YES DARLING VALVE REPLACEMENT
7. Description Of Work Valve bonnet was replaced under Traveler# 99202. A copy of Form N-1 for the replacement bonnet is attached Thevle ysaloweld repaired in th nr.r• 1 nrnn ,n-' ao,,',Aseal
8. Test Conducted: NIA[
Hydrostatic 11 Pneumatic[] Nominal Operating Pressureo] Other [I Pressure NIA PSI Test Temp. WA
i
Code Case
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPAIR/REPLACEMENT conforms to the rules of the ASME Code, Section Xl. repair or replacement Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed Owner COn 'sDesneeTi 20 tl Owner orOne'esignee, Title U1
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Geomiap and employed by Hartford Steam Boiler Insoection and Insurance Co. of Hartord. Cnn have Inspected the components described in this Owner's Report during the period 1/15/99 to 0 44 6_(e_, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report In accordance with the requirements of the ASME Code, Section XI. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manner for any sonal Injury or property damage or a loss of any kind arising from or connected with this
I-• Commissions 64 e197 Inspector's Signature National Board, State, Province and Endorsements
ORIGINALFORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Voptle Electric Generating Plant
Waynesboro, GA 30830
Date
Sheet
Unit
MWO #Address
3. Work Performed by Nuclear Operations Maintenance Name
Traveler # 99204
12/05/00
1 Of 7
-+- 2. ~L Qý0
29901677 and 29902366 Repair Organization P.O. No., Job No., etc.
Plant Vogtle Address
4. Identification Of System 1208 / Chemical and Volume Control System
5. (a) Applicable Construction Code ASME SEC III 1974 Edition, Summer 1975 Addenda, N/A Code Case
(b)Applicable Edition of section Xl Utilities For Repairs Or Replacements 1989 Code Case N-416-1
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO)
PUMP INGERSOLL- 0398019 N/A ,+-'1208-P4-001 1999 REPLACEMENT YES DRESSER PUMP Z
____C____ co ________lz-oý- 00________
PUMP PENN IRON 129132-1A 1 & 76 & e-1208-P4-001 1998 REPLACEMENT YES PEDESTALS WORKS, INC. 129132-IB2 79 -Z
7. Description Of Work The positive displacement pump was replaced by a centrifuaal normal charging pump per DCP 97- V2NO056. This replacement also includes welding of the suction and discharge nozzle flanges and their bolting to the Dump. Copies of Form NPV-1 for the replacement Pump and NF-1 for the replacement pump pedestals are attached.
8. Test Conducted: Hydrostatic [] PneumaticE] Nominal Operating Pressure [ Code Case N-416-1 N/A j] Other [] Pressure N/A PSI Test Temp. N/A 2F
CERTIFICATE OF COMPLIANCE
We certify that the statements made In the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed- 'L_4-k 1A--- ,2i a ,.i-t.Date /. /• 20 00 Owner or Owner's Designee, Title (-
/
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georaia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connectic have Inspected the components described In this Owner's Report during the period 06/23/99 to , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report In accordance With the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any ma er for any personal injury or property damage or a loss of any kind arising from or connected with this InspeI.. -'1/J
______ _,.,______ __ _ Commissions GAo3 Inspedtor-'s-Signature National Board, State, Province and Endorsements
Date /2. // 20 4o
-ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99209
12102/99
Of
2
29901923 Repair Organization P.O. No., Job No., etc.
Plant VootleAddress
Identification Of System 2101 / Containment Building System5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977
(b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
Addenda, N/A
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
EQUIPMENT CHICAGO N/A N/A 2-2101-R2-016 1988 REPAIR NO HATCH BRIDGE AND
IRON
7. Description Of Work Welded load in ramp to equipment hatch barret per DCP 99-V2NO037.
8. Test Conducted: Hydrostatic [] PneumaticE] Nominal Operating PressureR N/A 2] Other ] Pressure N/A PSI Test Temp. N/A F
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPAIR conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No. V1_ _ _ _ _ _ _ _ _ __Date
Signed -' po • - Date _I_ Z___ __ 19 q. Owner or Owner's Designee, TItlb
4.
Code Case
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticui have inspected the components described In this Owner's Report during the period 07/21/99 to ,-04 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any pe/sQnal Injury or property damage or a loss of any kind arising from or connected with this _________. /Commissions t;, 4 97
Inspector's Signature 6 National Board, State, Province and Endorsements
Date 42-A3 19
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xi
1. Owner Southern NuclearODeratina ComnanvName
40 Inverness Center Parkwav. Birminaham. AL
2. Plant Vogtle Electric Generatinq Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler #
03/13/00
99210
1Of 3
2
29900185Repair Organization P.O. No., Job No., etc.
Plant Vogte Address
4. Identification Of System 1301 / Main Steam System
5. (a) Applicable Construction Code ASMESEC III 1977 Edition, Winter 1977 (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
Addenda, N/A
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) VALVE CONTROL 23469-1-3 N/A 2PV3020 1982 REPAIR / YES
COMPONENTS, REPLACEMENT INC.
7. Description Of Work Valve pluo was replaced, Pressure seal area of valve body was waildad and rmachined to r~ctore nfitntm-Ugl
surface. A copy of Form N-2 for the replacement plug is attached.
8. Test Conducted: NA1
0\
Hydrostatic [] Pneumatic[] Nominal Operating Pressure[] Other [] Pressure WA PSI Test Temp. N/A
Code Case
CERT1FICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPAIR/REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Coda Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed" x <6 4 L ý t1 ,; t"-'u Date A_/__ _2_ 20 Oe-,
Owner or Owner's Designee•it le-
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georqia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have inspected the components described In this Owner's Report during the perlod__Q.•WQ4 to .•ý.3- 0 ) , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report In accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manner for any rmsonal Injury or property damage or a loss of any kind arising from or connected with this - cZ1 Commissions el,+ 4/-17
Inspector's Signature National Board, State, Province and Endorsements
Date , 15 - O- 20__
F
.......
•'
.....
r---"
-.
,r wv_ U
ORIGINAL' FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham. Ala.
2. Plant Vogtie Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
4. Identification Of System
Date
Sheet
Unit
MWO #
Traveler # 99211
5/24/2000
1 Of
2
29900967 Repair Organization P.O. No., Job No., etc.
Plant Vogtle Address
1202 1 NUCLEAR SERVICE COOLING WATER
5. (a) Applicable Construction Code ASME SEC III 1974 Edition, Winter '75 Addenda, N/A Code Case (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) VALVE Crosby Valve & Gage N67951-00-0003 N/A 2PSV1 1752 1984 REPLACEMENT YES
Co.
N/A N/A N/A Nl/A N/A N/A N/A N/A
7. Description Of Work: Relief valve S/N N67951-00.O008 was replaced with spare relief valve S/N N67951-00-0003 to facilitate valve testing. The replacement valve was oreviouslY installed as 2PSV-11744.
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating Pressurerx N/A E Other jJ Pressure WNA PSI Test Temp. N/A 2F
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date NIA SignedJ/ -V aWA Date 6_
Owner or Owner's Designee, TttL%
I
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State ol Province of Georgla and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticut have inspected the components described in this Owner's Report during the period__ -___- 9!?__ _ to & -Z3- 00 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any per al injury or property damage or a loss of any kind arising from or connected with this inspe'tion I Commissions
Inspector's Signature National Board, State, Province and Endorsements
Date _________
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern Nuclear Operatinq ComoanvName
40 Inverness Center Parkway, Birmingham, Ala.
Vogtle Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance
Name
Date
Sheet
Unit
MWO #
N
Plant Vogtie Address
4. Identification Of System 1202 / NUCLEAR SERVICE COOLING WATER SYSTEM
5. (a) Applicable Construction Code ASME SEC III 1974 Edition, Winter '75 Addenda, N/A Code Case ~ (b)Applicable Edition of Section Xi Utilized For Repairs Or Replacements 1989
$ C6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) VALVE Crosby Valve & Gage N67936-00-0002 N/A 2PSVI 1759 1984 REPLACEMENT YES
Co.
N/A N/A N/A N/A A N/A N/A N/A
7. Description Of Work: Relief valve S/N N67936-00-0003 was replaced with spare relief valve S/N N67936-00-0002 to facilitate valvetesting. The replacement valve was previously installed as 1PSV-11766.
8. Test Conducted: . A =-'- Hydrostatic L] Pneumatic-] Nominal Operating Pressurer9 Other [] Pressure WA PSI Test Temp. N/A
Date
Traveler # 99218
5/24/2000
1 Of
2
29901912 Repair Organization P.O. No., Job No., etc.
2. Plant
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp WA
Certificate of Auth rizaton No. N{A Expiration Date NA
Signed or_ O e i ellnee__ _, Date Tltl__-_-_ Owner or Owner's Designee, Titlif - S 6/ Z
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have inspected the components described in this Owner's Report during the period !7-/1 -99 to & -2,3 -6 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section Xi.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any mnner fon e injury or property damage or a loss of any kind arising from or connected with this
ap tion.Commissions ,4 -/9 7
Inspector's Signature National Board, State, Province and Endorsements
|
1it
|
•
--17.
QF
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xi
1. Owner Southern Nuclear Operating Company
2. Plant
Name 40 Inverness Center Parkway, Birmingham, Ala.
Voatle Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance
Name
4. Identification Of System
Date
Sheet
Unit
MWO #
Traveler # 99219
5/23/2000
Of
2
29901913 Repair Organization P.O. No., Job No., etc.
Plant VoatleAddress
12081 CHEMICAL VOLUME CONTROL SYSTEM
5. (a) Applicable Construction Code ASME SEC ill 1971 Edition, Winter '72 Addenda, N/A
(b)Applicable Edition of Section Xi Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
Code Case
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO VALVE Crosby Valve & Gage N569000-00- N/A 2PSV8121 1977 REPLACEMENT YES
Co. 0049
N/A N/A N/A N/A NIA N/A N/A N/A
7. Description Of Work: Relief valve SiV N56900-00-0025 was reolaced with spare relief valve SIN N56900-00-0049 to facilitate valve testing. The replacement valve was previously Installed as 1PSV-8121.
8. Test Conducted: N/AmF-
Hydrostatic [] Pneumatic[] Nominal Operating Pressure[-] Other n Pressure N/A PSI Test Temp. N/A
CERTIFICATE OF COMPUANCE
We certify that the statements made In the report are correct and this rules of the ASME Code, Section Xl.
REPLACEMENTrepair or replacement
Conforms to the
Type Code Symbol Stamp
Certificate of Authorizaiony. N/A
Signed-• , r - Date Owner or Owner's Designee, Title J,
Expiration Date
• .so_-, O
I
NIA
N/A
CERTIFICATE OF INSERVICE INSPECTION
1, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgla and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticut have inspected the components described in this Owner's Report during the period t? -m/: -" to ol-,Z- oV , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section Xi.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any peeeq al injury or property damage or a loss of any kind arising from or connected with this
S .A/•t•Aoc c Commissions aA 7
inspeicor's Signature i/ National Board, State, Province and Endorsements
Date 6 -Z-3 ."760tl
FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS As Required By The Provisions Of The ASME Code Section Xi
1. Owner Southern Nuclear Operating CompanyName
40 Invemess Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generatino Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99221
05/03/00
I Of 1
2
29900570 Repair Organization P.O. No., Job No., etc.
Plant VootlePlant VootleAddress
4. Identification Of System 1205 / Residual Heat Removal Sy
5. (a) Applicable Construction Code ASMESEC III 1971 Edition, Summer 1972 (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
stem
Addenda, N/A Code Case
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) HEAT SENTRY 796018 1307 2-1205-P6-002- 1979 REPLACEMENT YES
EXCHANGER EQUIPMENT M01 CORP,
7. Description Of Work Motor heat exchanger end covers and channels were replaced"
8. Test Conducted: Hydrostatic ] Pneumatic[] Nominal Operating PressurefZJ NIA E Other [] Pressure N/A PSI Test Temp. NIA 2F
I
4(1
Erf lhIr.RI E I- CUMPLIANCE We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. Repair or replacement
Type Code Symbol Stamp NIA
Certificate of Authorization N/A Expiration Date N/A No.
Signed R r 20 De e Owner or Owner's Designee, Title RV
CERTIFICATE OF INSERVICE INSPECTION
1, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inswection and Insurance Co. of Hanford. Connecticu have inspected , the components described in this Owner's Report during the period 01/25/99 to -6-.-. -CO, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be lla le in any manner for any persooI Injury or property damage or a loss of any kind arising from or connected with this
Commissions • a9 n/Ba Inspector's Signat National Board, State, Province and Endorsements Date / 200
I
1. 1. .. .,
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Voatle Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99223
11/17/99
Of
2
29901501 Repair Organization P.O. No., Job No., etc.
Plant VootleAddress
4. Identification Of System 1501 / Containment Cooling System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Add (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 198f.
6. Identification Of Components Repairs Or Replacement Components
enda, N/A
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1501 PULLMAN N/A AL/A 2V4-1501-034-01 1988 REPLACEMENT YES PIPING POWER 2V4-1501-035-01
SYSTEM PRODUCTS
7. Description Of Work Installed replacement studs and nuts on opoino fiances located on Containment Cooler unit 2-1501-A7-006.
8. Test Conducted: Hydrostatic [] Pneumaticl] Nominal Operating PressureN/A [X1 Other El Pressure N/A PSI Test Temp. N/A F
CERTIFICATE OF COMPUANCE
We certify that the statements made In the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed -lk )Y, .) -•,- ý -L7 19ata 71/ ig1 Owner or Owner's Designee, Title U
Code Case
COVI
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georoia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticui have inspected the components described in this Owner's Report during the period 09/28/99 to /2- of- 9! , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this in • J • - 4 Commissions SA Z/?
Inspector's Signature National Board, State, Province and Endorsements
Date /.2- 01/ 19
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
/1. Owner S
ORIGi vi FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
Traveler # 99224
'nthern Nuclear Oneratinay Comnanv Date 12/9/99Name
40 Inverness Center Parkway, Birmingham, Ala.
Vog•te Electric Generating Plant
Waynesboro, GA 30830
Sheet
Unit
MWO #
Of 2
2
29801500Address Repair Organization P.O. No., Job No., etc.
3. Work Performed by Nuclear Operations Maintenance Plant Vogtle Name Address
4. Identification Of System 1501 I Containment Air Cooling System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 77 Addenda, N/A Code Case (b)Applicable Edition of section XI Utilities For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (ES OR NO) HEAT CVI INC. 02A338 1229 2-1501A7-003 1982 REPLACEMENT YES EXCHANGER HEADER
HEAT CVI INC. 024347 1230 2-1501A7-003 1982 REPLACEMENT YES EXCHANGER HEADER
HEAT CVI INC. 02A356 1231 2-1501A7-003 1982 REPLACEMENT YES EXCHANGER HEADER
HEAT CVI INC. 02A364 1232 2-1501A7-003 1982 REPLACEMENT YES EXCHANGER
HEAT CVI INC. 02A365 2-1501A7-003 1982 REPLACEMENT YES EXCHANGER 1233 HEADER
HEAT CVI INC. 02A376 2-1501A7-003 1982 REPLACEMENT YES EXCHANGER 1234 HEADER
7. Description Of Replaced existing studs and nuts with corrosion resistant material per Specification AX4AJ16-123 on Inlet Work outlet manifolds as shown on isometric drawings 2V4-1501-028-01.& 2V4-1501-029-01.
8. Test Conducted: Hydrostatic [] PneumaticE] Nominal Operating Pressure -] NIA nX Other n Pressure NIA PSI Test Temp. N/A QF
2. Plant
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
Traveler Number - 99224 Page 2 of 2
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the
rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. WA Expiration Date WA
Signed1A? 1i" ý- , Date ____c-_ 19 g Owner or Owner's Designee, T"le
Date______ 19
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgla and employed by Hartford Steam boiler Inspection and Insurance Co. of Hartfo Connecticut have Inspected the components described in this Owner's Report during the period 9-a9. 9 to /./- 9 ? , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance With the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manner for any personal Injury or property damage or a loss of any kind arising from or connected with this
Iion . 'A = (I Commissions 6 -4AV19 7
Inspector's Signature National Board, State, Province and Endorsements
ORIGINAL FORM NIS-2 OWNER'S.REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern NuclearOperating Company Name
40 Invemess Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Wavnesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99226
11/17/99
I Of 1
2
29900559 Repair Organization P.O. No., Job No., etc.
Plant VoatleAddress
4. Identification Of System 1202 / Nuclear Service Cooling Water
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
System
Addenda, N/A
7. Description Of Work Installed replacement studs and nuts on piping blind flan•es located on lines 1202-530-8" and 1202-531-8"
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating Pressure[] NIA E] Other E Pressure WA PSI Test Temp. NIA 2F
CERTIFICATE OF COMPUANCE
We certify that the statements made In the report are correct and this REPLACEMENT conforms to the
rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed 17&'/J•- -k , ,- . Date Ii/1 19 9 Owner or Owner's Designee, TItle U
Code Case
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1202 PULLMAN N/A N/A 2K7-1202-228-01 1988 REPLACEMENT YES PIPING POWER 2K7-1202-3281
SYSTEM -PRODUCTS - --- i
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticui have Inspected the components described in this Owner's Report during the period 10/04/99 to L2• , , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any p onal injury or property damage or a loss of any kind arising from or connected with this InslectlonV 1 _ in-`La4%ý ,5. 7LJ Commissions CV, LA 7
Inspector's Signature f National Board, State, Province and Endorsements
Date /0?- 0 6 - 9 17 1990
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern NuclearOperating CompanyName
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electrc Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99227
12108/99
Of
2
29902563 Repair Organization P.O. No., Job No., etc.
Plant VogtleAddress
4. Identification Of System 1205 / Residual Heat Removal System
5. (a) Applicable Construction Code ASMESECIII 1977 Edition, Winter1977 Addenda, N/A Code Case (b)Applicable Edition of Section Xi Utilized For Repairs Or Replacements 19!2
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1205 PIPING PULLMAN N/A N/A 2K3-1205-008-01 1988 REPLACEMENT YES SYSTEM POWER
_______ PRODUC(TS ____ ___ _____ ____ _____
7. Description Of Work Installed reolacement studs and nuts in the piving flanoes located at 2F0-10443.
8. Test Conducted: Hydrostatic ] PneumaticE] Nominal Operating Pressure[] WA [] Other 51 Pressure N/A PSI Test Temp. N/A RF
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed !j/ • V nL Date J ZII57-" 19 9'• Owner or Owner's Designee, TWt -
Date /,,g -Y1 19
I
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of bolier and Pressure vessel Inspectors and the State or Province of Georqia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have Inspected the components described In this Owner's Report during the period 10/03/99 to - q , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this in I ti ,4- Com m issions 49 l 9 -7
Inspector's Signature 1" , National Board, State, Province and Endorsements
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
Traveler # 99228
1. Owner Southern Nuclear Operating Company
2. Plant
Name 40 Inverness Center Parkway, Birmingham,
Ala.
Vogtle Electric Generating Plant
Waynesboro, GA 30830
Date
Sheet
Unit
MWO #
Address
3. Work Performed by Nuclear Operations MaintenanceName
12f10/99
Of
2
29902566 Repair Organization P.O. No., Job No., etc.
Plant Voatle
Address
4. Identification Of System 12051/ RESIDUAL HEAT REMOVAL SYSTEM
5. (a) Applicable Construction Code ASME SEC Ill 1977 Edition, Winter '77 Addenda, N/A
(b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
Code Case
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED. ASME CODE
OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO)
PIPING Pullman Power NIA N/A 2K3-1208-008-01 1988 REPLACEMENT YES
SYSTEM Company Inc.
NIA N/A N/A N/A N/A NI/A N/A N/A
7. Description Of Replacement of studs and nuts In PpDing flanqes for 2FV-0619. Work
8. Test Conducted: Hydrostatic [] Pneumatic- Nominal Operating Pressure[]
NIA 7X Other 7 Pressure WA PSI Test Temp. NIA
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the
rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp NIA
Certificate of Authorization No. NIA Expiration Date NIA
Signed Y) i Yý., Date -LJ0o 19 q Owner or Owner's Designee, TIt1#
Date /Aý - /3 19 _.
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State
or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticut have
inspected the components described in this Owner's Report during the period /0- 03-99 to / 2-144 9 9 -, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken
corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section Xi.
By signing this certificate, neither the inspector nor his employer makes any warranty, expressed or Implied, concerning the
examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall
be liable in any manner for any personal Injury or property damage or a loss of any kind arising from or connected with this
Ins n ý Q Commissions &4 42-"7
Inspector's Signature i , National Board, State, Province and Endorsements
ORIGINALFORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
1. Owner Southern NuclearOperating CompanvName
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations MaintenanceName
Date
Sheet
Unit
MWO #
/
Address
4. Identification Of System 1205 / Residual Heat Removal Sy
5. (a) Applicable Construction Code ASME SEC I/_ 1977 Edition, Winter 1977 (b)Applicable Edition of Section Xi Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
stem
Addenda, l/A Code Case
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1205 PIPING PULLMAN N/A AVA 2K3-1205-007-02 1988 REPLACEMENT YES SYSTEM POWER
PRODOICTS
7. Description Of Work Installed replacement studs and nuts in the piping flanoes located at 2FV-0618.
8. Test Conducted: Hydrostatic E] PneumaticE] Nominal Operating Pressure' N/A [ Other [ Pressure N/A PSI Test Temp. N/A F
CERI1FICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed YV• , Date I /'•/i7 19 Owner or Owner's Designee, Title U
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georcia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Ha Cdnnecti ul have Inspected the components described In this Owner's Report during the period 10//9 to eL3 -OZ.-00 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manner for an personal Injury or property damage or a loss of any kind arising from or connected with this • Commissions 7 "£/9
Inspector's SignatuF6 National Board, State, Province and Endorsements
Date 0,802-
Traveler # 99229
12/15/99
Of
2
29902620 Repair Organization P.O. No., Job No., etc.
Plant Voatle
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
1. Owner Southern NuclearOperating CompanyName
40 Inverness Center Parkway, Birminrham. AL
2. Plant Vogtle Electfic Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations MaintenanceName
Traveler # 99232
Date 04/03/00
Sheet Of 3
Unit 2
MWO # 29801685 Repair Organization P.O. No., Job No., etc.
Plant Vogtie Address
4. Identification Of System 1201 / Reactor Coolant System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Summer 1979 Addenda, N/A Code Case (b)Applicable Edition of Section Xi Utilized For Repairs Or Replacements 1982
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
VALVE GARRETT P-144 N/A 2PV0455A 1984 REPLACEMENT YES
7. Description Of Work Installed replacement valve Duo. A copy of Form N-2 for the reolacement Dlua S/N N96012-38-0027 is attached.
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating Pressure[X' N/A Other [ Pressure N/A PSI Test Temp. N/A 2F
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No. Signed Date _..__ _ -7 20 00
Owner or (Owner's Designee, Titlet
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georoia and employed by Hartford Steam Boiler Inspection and Insurance Go. of Hartford. Connecticul have inspected the components described In this Owner's Report during the period 10/07/99 to 4.5-01- Z , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report In accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manner for any p" nal injury or property damage or a loss of any kind arising from or connected with this
cj= J)it- ,• Commissions /i4A 41!9 7Inspector's Signature I
Date &. -0/"2
National Board, State, Province and Endorsements
'S'1
fe 0Vi
0o. __
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern NuclearOperatinq CompanyName
40 Inverness Center Parkway, Birmingham. AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99233
12107/99
Of 2
2
29900514 Repair Organization P.O. No., Job No., etc.
Plant VoqtleAddress
4. Identification Of System 1302 / Auxiliary Feedwater System
5. (a) Applicable Construction Code ASME SEC III 1974 Edition, Summer 1975 Addenda, N/A Code Case (b)Applicable Edition of Section Xi Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
VALVE ANCHOR E9001-110-6 N/A 2-1302-U4-120 1983 REPLACEMENT YES DARLING VALVE
rn
7. Description Of Work Installed reolacement valve bonnet. A copy of Form N-2 for the renlacement bonnet is attached.
8. Test Conducted: Hydrostatic [] Pneumaticl] Nominal Operating PressureJ] N/A E Other [ Pressure N/A PSI Test Temp. WA 2F
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed ,• c !J•A . Date L -- / 1 19 7 Owner or Owner's Designee, TItIJ
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance CO. of Hartford. Connecticut have inspected the components described in this Owner's Report during the period 10/10/9 to 12- D9-,?? , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any persIa injury or property damage or a loss of any kind arising from or connected with this I=n 5& Commissions e4 4,17
I.npuCuLr s oSgnature ,
1"2 09 inDate
National Board, State, Province and Endorsements
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
Traveler # 99257
1. Owner Southern Nuclear Operating ComDanvName
40 Inverness Center Parkway, Birmingham. AL
2. Plant Vo0t0e Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance
Name
4. Identification Of System
Date
Sheet
Unit
MWO #
11/29/99
I Of
2
29900436 Repair Organization P.O. No., Job No., etc.
Plant Voctle
Address
12011/ Reac~tor Coola~nt S tern 5. (a) Applicable Construction Code ASME SEC III 1971 Edition, Summer 1972 Addenda, 1484-2 Code Case
(b)Applicable Edition of Section Xi Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1201 WESTINGHOUSE 1983 35 2-1201-B6-002 1982 REPLACEMENT YES
7. Description Of Work Installed reolacement bolt and a helical threaded insert on nozte side handhole at the supportolate.
8. Test Conducted: Hydrostatic 0 Pneumatic[] Nominal Operating Pressurez] NIA [ Other ] Pressure N/A PSI Test Temp. NIA QF
CERTIFICATE OF COMPUANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed 2Ow0er or Owner_0 Owner or Owner's Designee, Titleý
I
.. n ir"FI ICA UI" IOINEHVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have inspected the components described in this Owner's Report during the period 10/13/99 to 6/0-O , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this Inspetr. S r Commissions CA -,97 inspicto~r's Signature N~lA U, A , re vuuuUI .iusee
Datet9 Province naEndorsements Date !C. -I10 201)
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
1. Owner Southern NuclearOperating CompanyName
40 Inverness Center Parkway, Birmingham. AL
2. Plant Vobtle Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99258
11/29/99
1 Of
2
29900440 Repair Organization P.O. No., Job No., etc.
Plant VootleAddress
4. Identification Of System 1201 / Reactor Coolant System
5. (a) Applicable Construction Code ASME SEC III 1971 Edition, Summer 1972 A (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
ddenda, 1484-2 Code Case
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1201 WESTINGHOUSE 1982 34 2-1201-B6-003 1982 REPLACEMENT YES
7. Description Of Work Installed replacement bolt on hot lea side secondarm inspection handhole.
8. Test Conducted: Hydrostatic [] PneumaticE] Nominal Operating PressureN/A D Other f] Pressure N/A PSI Test Temp. N/A RF
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed D•k 2, Kh -p-.4 -"/i& Date . )• 19' Owner or Owner's Designee, Title U
Date A2 - 07 19
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticuy have inspected the components described in this Owner's Report during the period 10/99 to 1-2-,79 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal Injury or property damage or a loss of any kind arising from or connected with this insA-n 7/ •2 § Commissions (14 9-19 7
Inspector's SignatureV National Board, State, Province and Endorsements
ORIGINAL
FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern NuclearOperating CompanyName
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance
Date
Sheet
Unit
MWO #
Name
4. Identification Of System 1208 / Chemical and Volume Control
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
Traveler # 99259
11/22/99
1 Of
2
29902743 Repair Organization P.O. No., Job No., etc.
Plant Vootle
Address
System
Addenda, N/A Code Case
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1208 PULLMAN N/A N/A 2K4-1208-020-02 1988 REPLACEMENT YES PIPING POWER
SYSTn PRODUCTS I _ _
7. Description Of Work Installed replacement studs and nuts on aioing flanges located at 2FE0157.
8. Test Conducted: Hydrostatic E] PneumaticE] Nominal Operating Pressure[] N/A [g] Other ] Pressure N/A PSI Test Temp. N/A RF
CERTIFICATE OF COMPLIANCE
We certify that the statements made In the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signeder or O e DesigDateee, Tile 199 Owner or Owner's Designee, Tntle C
I
II�
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartord Connecticut have inspected the components described in this Owner's Report during the period 10/15/99 to 1,2-f(,- , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal Injury or property damage or a loss of any kind arising from or connected with this ins ction., __________________,,__._Commissions - 47
Inspector's Signaturet National Board, State, Province and Endorsements
Date /,Ra-I 19 Q
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtie Electric Generatinq Plant
Waynesboro, GA 30830
Traveler # 99260
01/06/00Date
Sheet I Of I
Unit
MWO #Address
3. Work Performed by Nuclear Operations Maintenance Name
2
29902400 Repair Organization P.O. No., Job No., etc.
Plant VogqteAddress
4. Identification Of System 1202 /Nuclear Service Cooling Water System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Addenda, (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 19D9
6. Identification Of Components Repairs Or Replacement Components
N/A Code Case
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT ES OR NO) 1202 PIPING PULLMAN N/A N/A 2K5-1202-031- 1988 REPLACEMENT YES
SYSTEM POWER 01 PRODUCTS
7. Description Of Work Installed replacement studs and nuts in viinn flanoes located at valves 2HV-11605 and 2-1202-U4-031.
8. Test Conducted: Hydrostatic [] PneumaticE] Nominal Operating PressureE[ N/A [] Other [ Pressure N/A PSI Test Temp. N/A RF
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed orDate O ss et Owner or Owner's Designee, Title(I e9-
Date 0-4 - b 2- id 2dfoo
'4
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georaia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticul have Inspected the components described in this Owner's Report during the period 10a/1/_9 to 03-oz-oc- -, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report In accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any persopaI injury or property damage or a loss of any kind arising from or connected with this Ins ction, Commissions GA 4Q7
l Date •)•, -
• Z.
1• 2•O•J%I
National Board, State, Province and EndorsementsInspector's Signature V
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Binningham, AL
2. Plant VogUe Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Traveler # 99261
11/17/99IDntn
Sheet I Of _
Unit 2
MWO # 29902934 Repair Organization P.O. No., Job No., etc.
Plant Vogtle Address
4. Identification Of System 1302 / Auxiliary Feedwater System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Addenda, N/A Code Case (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1302 PULLMAN N/A N/A 2K2-1302-002-01 1988 REPLACEMENT YES PIPING POWER
SySTE PRODUCTS
7. Description Of Work Installed replacement studs and nuts on bining flangoes located at 2FE5267.
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating PressureD N/A[] Other F Pressure NIA PSI Test Temp. NIA QF
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed • ),4 6U-Date _ _ __ _ _ 19 Owner or Owner's Designee, Title
I
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georoia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticua have inspected the components described In this Owner's Report during the period 10/18/99 to /,I-lo -- -, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any pemronal injury or property damage or a loss of any kind arising from or connected with this insl ction. I !/// .",,
:n j 4-:KNA Commissions__ __ __ __ __ __
Inspector's Signature V National Board, State, Province and Endorsements
Date 19
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xi
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birminaham. AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance
Date
Sheet
Unit
MWO #
Name
Traveler # 99262
11/22/99
Of
2
29902933 Repair Organization P.O. No., Job No., etc.
Plant Vont/eAddress
4. Identification Of System 1302 / Auxiliary Feedwater System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Addenda, N/A Code Case (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 130Z NO. f PULLMAN N/A N/A 2K3-1302-030-01 1988 REPLACEMENT YES
PIPING POWER SYSTEM POUCT_
7. Description Of Work Installed replacement studs and nuts on biDing flanges located at 2FE5286.
8. Test Conducted: Hydrostatic [] PneumatlcE] Nominal Operating PressureE] NIA[] Other [ Pressure NIA PSI Test Temp. NIA 2F
CERTIFICATE OF COMPLIANCE
We certify that the statements made In the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xi. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed J'Ji • Date W Q44 19 Owner or Owner's Designee, Title
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticu have inspected the components described In this Owner's Report during the period 10/18. to 0 -O(o--t , and state that to the best of my knowledge and belief, the Owner has performed examinations and takenr corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section Xl. By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this -- Ins In Isptr I gn Commissions t4 4(q 7
Inspector's Signature INational Board, State, Province and Endorsements
Date 19
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Voqtle Electric Generatina Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99263
11/17/99
Of
2
29902935 Repair Organization P.O. No., Job No., etc.
Plant VoatleAddress
4. Identification Of System 1302 / Auxiliary Feedwater System
5. (a) Applicable Construction Code ASME SEC I// 1977 Edition, Winter 1977 Adc (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
lenda, N/A
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1302 PULLMAN N/A N/A 2K2-1302-003-01 1988 REPLACEMENT YES PIPING POWER
RYTF PRODUICTS _______________________
7. Description Of Work Installed replacement studs and nuts on piping flanges located at 2F05284.
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating PressureE[ N/A j] Other [ Pressure N/A PSI Test Temp. N/A 5F
CERTIFICATE OF COMPUANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed PA ,t D)ate 19 Owner or Owner's Designee, Titlea
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georcia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have inspected the components described in this Owner's Report during the period 10/18/99 to _/_2. -02- 1?1 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report In accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any person1.al injury or property damage or a loss of any kind arising from or connected with this • •a - &LG0o Commissions (A C/•9 _
National Board, State, Province and Endorsements
I
Code Case
Inspector's Signature /
Date 1Z -02- 19
J
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99264
11/22/99
Of
2
29902932 Repair Organization P.O. No., Job No., etc.
Plant VogteAddress
4. Identification Of System 1302 / Auxiliary Feedwater System
5. (a) Applicable Construction Code ASME SEC I!1 1977 Edition, Winter 1977 Addenda, N/A Code Case (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) i302- NO.
PULLMAN N/A N/A 2K3-1302-030-01 1988 REPLACEMENT YES PIPING POWER
RYXTEL PRODUCTQS
7. Description Of Work Installed replacement studs and nuts on piping flances located at 2F05282.
8. Test Conducted: Hydrostatic F] Pneumatic[] Nominal Operating PressureN/A [ Other E] Pressure N/A PSI Test Temp. WA QF
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed klavý!L @ Date /24 19 Owner or Owner's Designee, Title J
CERTIFICATE OF INSERVICE INSPECTION
1, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georoia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticui have inspected the components described in this Owner's Report during the period 1018/ to /,Z- 02 - and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report In accordance with the requirements of the ASME Code, Section Xi.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal Injury or property damage or a loss of any kind arising from or connected with this
= npao' In Inatu4-:0 Y Commissions 6A• 49 7 " Inspector'sCommissions National Board, State, Province and Endorsements
19Date /;- - 0.;--
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
1. Owner Southern Nuclear Operating CompanyName
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99265
02/15/00
I Of 1
2
29802330 Repair Organization P.O. No., Job No., etc.
Plant VoatleAddress
4. Identification Of System 1302 / Auxiliary Feedwater System
5. (a) Applicable Construction Code ASME SEC I/I 1974 Edition, Summer 1975 (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 198
Addenda, N/A
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) VALVE ANCHOR! E-9001-25-1 NIA 3-1302-U4-116 1980 REPLACEMENT YES
DARLING VALVE Co.
7. Description Of Work Installed reDlacement valve disc. A copy of Form N-2 for the reolacement disc is attached.
8. Test Conducted: Hydrostatic E] PneumaticE] Nominal Operating Pressure E] N/A Z Other L Pressure N/A PSI Test Temp. N/A ?F
CERTIFICATE OF COMPUANCE
We certify that the statements made In the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed L) A • L. - Date a/____ __
Owner or Owner's Designee, TRtlW
Date ________
J
Code Case
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of GeoroLa and employed by Hartford Steam Boiler Insoection and Insurance Co. of Hartford. Connecticut have , ingpected the components described in this Owner's Report during the period 10/18/99 to !Y - d .o 0 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manner for any-lr onal Injury or property damage or a loss of any kind arising from or connected with this iCommissions A,44 4197
Inspector's Signature, National Board, State, Province and Endorsements
:ýi1 k APP
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
Traveler # 99266
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electfic Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
4. Identification Of System
Date
Sheet
Unit
MWO #
03/07/00
1 Of 3
2
29902485 Repair Organization P.O. No., Job No., etc.
Plant Vog•te Address
1203 / Component Coolina Water Svstem
5. (a) Applicable Construction Code ASME SEC III 1974 Edition, Winter 1975 Addenda, N/A Code Case (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) VALVE FISHER 7785019 6382 2HV-11817 1981 REPLACEMENT YES
CONTROLS CO.
7. Description Of Work Installed replacement retaining dina (S/N 2) in valve. A copy of Form N-2 for the replacement retaining rino is attached. The material channe nf th4 rnnlpI-rnThnt rntnininn rinn7 k. •nnrnvp•rl fnr '•hnrf tnrrn incftllhthn
aooroved by CR# 2000000008,
8. Test Conducted: NIA
Hydrostatic [] PneumaticE] Nominal Operating Pressure[] Other F1 Pressure N/A PSI Test Temp. N/A 2F
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed D'ce4/,,.a ". Dt __-._Date_ __ /_ 20 I Ov~ner or Owner's Designee, Title [. I
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georqia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticu have inspected the components described in this Owner's Report during the period 1___ to 04-jP4-0OO , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report In accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manner for any personal Injury or property damage or a loss of any kind arising from or connected with this Insp Ion _ _ _ _ _ ... . Commissions _ _ _ _ _ _ _ _
Inspector's Signature National Board, State, Province and Endorsements
Date 'A0 (, - 2040
attached. The material rhantia rd tha ranhqn-ament n4faininn rinn, iq qnnrnved for short f- inatAllatinn
ORIGINAL
FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern Nuclear Operating Company
2. Plant
Name 40 Inverness Center Parkway, Birmingham,
Ala.
Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
4. Identification Of System
Date
Sheet
Unit
MWO #
Traveler # 99267
11t23/99
Of
2
29903046 Repair Organization P.O. No., Job No., etc.
Plant Vogtie
Code Case
Address
12041 SAFETY INJECTION
5. (a) Applicable Construction Code ASME SEC III 1974 Edition, Summer '75 Addenda, N/A (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) VALVE Rockwell BR140 N/A 2-1204-U4-143 1983 REPAIRED YES
International
N/A N/A N/A N/A N/A N/A N/A N/A
7. Description Of Performed locking tackweld on valve after maintenance. Work
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating Pressure[ NIA E Other n Pressure WA PSI Test Temp. N/A F
CERTIFICATE OF COMPLIANCE
We certify that the statements made In the report are correct and this REPAIR Conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. NIA Expiration Date N/A
Signed oýr Owners Date De 2knee 19Te Owner or Owner's Designee, TIt~e,#
/
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have inspected the components described in this Owner's Report during the period /0-0/. -q to Z?-0"7- 9- , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manner for any personal injury or property damage or a loss of any kind arising from or connected with this 1• 1' jý,- Commissions 4;A 4-/9 7
Inspector's Signature National Board, State, Province and Endorsements
Date_________q_91
1204 / SAFETY INJECTION
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xi
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtie Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99271
01/03/00
I Of 3
2
29903124 Repair Organization P.O. No., Job No., etc.
Plant Vootle
Address4. Identification Of System 1202 / Nuclear Service Cooling Wate
5. (a) Applicable Construction Code ASME SEC II! 1974 Edition, Winter 1975 (b)Applicable Edition of Section Xi Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
r System
Addenda, N/A Code Case
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) VALVE CROSBY VALVE N67936-00- N/A 2PSV-11766 1997 REPLACEMENT YES
& GAGE CO. 0005
7. Description Of Work Installed replacement valve. A copy of Form NV- 1 for the reolacement valve is attached.
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating PressureXN/A [] Other[] Pressure N/A PSI Test Temp. N/A OF
CERTIFICATE OF COMPLIANCE
We certify that the statements made In the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed 'JŽ,j4 k C - Date q' -tJ- Z- e' Owner or Owner's Designee, TItl i - ÷
S~AP I I-Ah UP ........... I..S...T.ONCERTIF;ICIIATE• OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co, of Hartford. Connecticut have Jnspected the components described in this Owner's Report during the period 10/20/99 to 0#1o3,_ -, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section Xi.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any per nal injury or property damage or a loss of any kind arising from or connected with this ins ction. Commissions A4• JQ,7
-National 1oard, State, Province and Endorsements
ce\oO
Inspector's Signature ,/
Date 04 1 -43 -. Ai
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Voftie Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #Repair Organization P.O. No., Job No., etc.
Plant VogtleAddress
4. Identification Of System 1205 / Residual Heat Removal System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Addenda, N/A Code Case
(b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1205 PULLMAN N/A N/A 2K3-1205-006-01 1988 REPLACEMENT YES PIPING POWER
SYSTEM PRODUCTS __
7. Description Of Work Installed replacement studs and nuts on piping flances located 2FE061 1.
8. Test Conducted: Hydrostatic ] Pneumatic[] Nominal Operating Pressure[] NIA[•] Other F] Pressure NIA PSI Test Temp. N/A F
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed "•a- fiV 4,4_. Date Ii " 19 '71 Owner or Owner's Designee, Tltlq(
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have Inspected the components described In this Owner's Report during the period 10/21/29 to Z, -9, , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal Injury or property damage or a loss of any kind arising from or connected with this
_ _ _ _ Commissions aA V/97
Inspector's SIgnatur&1' National Board, State, Province and Endorsements
Date 19
Traveler # 99272
11/17/99
Of 1
2
29902568
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkwav. Birminaham. AL
2. Plant Vogtle Electdc Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99273
12/16/99
I Of 1
2
29902622 Repair Organization P.O. No., Job No., etc.
Plant VootleAddress
4. Identification Of System 1205 / Residual Heat Removal Sy,
5. (a) Applicable Construction Code ASME SEC I _I 1977 Edition, Winter 1977 (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
stem
Addenda, N/A Code Case
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1205 PIPING PULLMAN N/A N/A 2K3-1205-009-01 1988 REPLACEMENT YES SYSTEM POWER
PRODUCTS
7. Description Of Work Installed reolacement studs and nuts in the oinina flanaes located at 2FE-0618.
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating Pressure[] N/A n] Other n] Pressure NIA PSI Test Temp. NIA OF
CERTIFICATE OF COMPUANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No. _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _ _
Signed Date i/s)
Owner or Owner's Designee, Title F /-)0<
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Insoection and Insurance Co. of Hartford. Connecticui have Inspected the components described in this Owner's Report during the period 10/21/99 to 0.3-,• 2-00 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any perst=nl Injury or property damage or a loss of any kind arising from or connected with this !Insaction./s
J , • ---•, c a4.• = \ 4 . Commissions (:4 09 7
Inspector's Signature a National Board, State, Province and Endorsements
Date 0.3- o 2- - " X zo
SORIGINAL
FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS As Required By The Provisions of The ASME Code Section Xi
Traveler # 99274
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830Address
Date
Sheet
Unit
MWO #
3. Work Performed by Nuclear Operations Maintenance Name
08/15/00
! Of 3
2
29901788 Repair Organization P.O. No., Job No., etc.
Plant Vootle
Address
4. Identification Of System 1208 / Chemical arnd Volume Control System
5. (a) Applicable Construction Code ASME SEC Ill 1974 Edition, N/A (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
Addenda, N/A
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE
OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED COMPONENT MANUFACTURER NO. NO. IDENT1FICATION BUILT REPLACEMENT (YES OR NO)
VALVE FISHER 9318722 2628 2FV-0121 1985 REPLACEMENT YES CONTROLS CO.
7. Description Of Work Valve vlua was reolaced. A covy of Form N-2 for the reolacement valve p"uo is attached.
8. Test Conducted: Hydrostatic E] Pneumatic[] Nominal Operating Pressure[] NIA [] Other fl Pressure NIA PSI Test Temp. N/A 9F
CERTIFICATE OF COMPUANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the
rules of the ASME Code, Section Xl. Repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed " V/'1 oi• - Date 20 Owner or Owner's Designee, Title/
Code Case
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticu have Inspected the components described In this Owner's Report during the period__Q10Q20l9 to R. od , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manner for any personal Injury or property damage or a lose of any kInd arising from or connected with this
___________••___•_____•_•ommissions -. -4. .-23 Inspecjlr's Signature National Board, State, Province and Endorsements
Date •-.Tp 20400
ORIGINAL
FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS As Required By The Provisions Of The ASME Code Section Xl
Traveler # 99275
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vootle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet I
Unit
MWO #
11/17/99
Of 3
2
29802005 Repair Organization P.O. No., Job No., etc.
Plant VogSte Address
4. Identification Of System 1208 / Chemnlcal and Volume Control System
5. (a) Applicable Construction Code ASME SEC I11 1977 Edition, Winter 1977 Addenda, N/A
(b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
VALVE FISHER 5945210 2938 2HV-8149A 1978 REPLACEMENT YES CONTROLS CO.
7. Description Of Work Installed replacement plug assenmbly in valve. This replacement activity was not reviewed by the ANIII or Quality Control prior to implementaton as documented by condition report number4099e5S9. A copy of Form N-2 for therevid•LeInaF LJIU I,• •IIantIg. p w a-__ ____,
8. Test Conducted: NtAn
Hydrostatic [] Pneumatic[] Nominal Operating PressureL] Other F1 Pressure N/A PSI Test Temp. N/A 2F
Date "5-WS
Code Case
CERTIFICATE OF COMPLIANCE
We certify that the statements made In the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Owner or Owner's Designee, Title
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georola and employed by Hartford Steam Boiler Insoection and Insurance Co. of Hartford. Connecticu have inspected the components described In this Owner's Report during the period to - 1,5 _- W , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective medsures described In this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any perp al Injury or property damage or a loss of any kind arising from or connected with this ins lction.I ins~c . I -J " I 1A-• \ ý Commissions !ýa 4L97
Inspector's Signature V National Board, State, Province and Endorsements
IQe•I/Yl I•'•:1 <"
'ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern Nuclear~perating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtie Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99276
11/16/99
I Of /
2
29902034 Repair Organization P.O. No., Job No., etc.
Plant VoqtleAddress
4. Identification Of System 1208 / Chemical and Volume Control
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 (b)Appllcable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
I System
Addenda, N/A
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1208 PULLMAN NIA N/A 2K3-1208-116-01 1988 REPLACEMENT YES PIPING POWER
RYTE PROPUCTS ________ _____
7. Description Of Work Installed replacement studs and nuts on piping flanges located at 2FE01 11.
8. Test Conducted: Hydrostatic [] Pneumaticr' Nominal Operating Pressurel] N/A nX Other Rl Pressure N/A PSI Test Temp. N/A 1F
CERTIFICATE OF COMPLIANCE
We certify that the statements made In the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
____, _tle A._Da
Signed Owner or Owner's Designee, Title -1
Date 1; - 4 7, 19
Code Case
CERTIFICATE OF INSERVICE INSPECTION
1, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have inspected the components described In this Owner's Report during the period 10/21/99 to /0 - ?- , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manner for any personal injury or property damage or a loss of any kind arising from or connected with this
IscosSn at N naorSPCommissions 64 4197 Inspector's Slgnaturif National Board, State, Province and Endorsements
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southem NuclearOperating CompanyName
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogt/e Electric Generating Plant
Wavnesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99277
11/22/99
Of
2
29902742 Repair Organization P.O. No., Job No., etc.
Plant VoatleAddress
4. Identification Of System 1208 / Chemical and Volume Control
5. (a) Applicable Construction Code ASME SEC/III 1977 Edition, Winter 1977 (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
System
Addenda, N/A
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1208 PULLMAN N/A N/A 2J4-1208-037-01 1988 REPLACEMENT YES PIPING POWER
SYSTE PRODUCTS
7. Description Of Work Installed repLacement studs and nuts on piping flanges located at 2FE0156.
8. Test Conducted: Hydrostatic ] Pneumatic[] Nominal Operating PressureN/A [] Other R Pressure N/A PSI Test Temp. N/A 2F
CERTIFICATE OF COMPUANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed -AZ;a A 4 M Date iJ/ Q9. 19 i' Owner or Owner's Designee, TltleG
Code Case
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georqia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticui have Inspected the components described In this Owner's Report during the period_ 1024/9 to 1.2-0 2 -9 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corfective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any 7ersonal injury or property damage or a loss of any kind arising from or connected with this in ectn Commissions t '
Inspector's Signature National Board, State, Province and Endorsements
Date /2-02- 19
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
Traveler # 99278
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
01/23/01
] Of 1
2
29902632 Repair Organization P.O. No., Job No., etc.
Plant VogtleAddress
4. Identification Of System 1208 / Chemical and Volume Control System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
Addenda, N/A
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) 1208 PIPING PULLMAN N/A N/A 2K3-1208-055-01 1989 REPLACEMENT YES
SYSTEM POWER PRODUCTS
7. Description Of Work Installed replacement studs and nuts on opiing flanges at inlet to letdown reheat exchanger 2-1208-E6-007.
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating PressureE] N/A []j Other l Pressure N/A PSI Test Temp. N/A F
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorizati ntN. N/A Expiration Date N/A
Signed oY)r Owners Date Title0 Owner or Owner's Designee, Thite
Date I - ,s,2-
Code Case
961CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have Inspected the components described in this Owner's Report during the period 10/26/00 to /-A.r-a/ , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner r any personal Injury or property damage or a loss of any kind arising from or connected with this
__nsp _on. ____--,-, _____Commissions GA 20
"Inspector'SSignature National Board, State, Province and Endorsements
2001
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern Nuclear Operatng CompanyName
40 Invemess Center Parkway, Birmingham, AL
2. Plant Vogde Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler #
04/06/01
99279
Of
2
29902633
Repair Organization P.O. No., Job No., etc.
Plant Vogtie Address
S.... .. . . . . . A _._ , st_-4. Identification Of System 1208U/ Chlemical and Volume Control
5. (a) Applicable Construction Code ASME SEC III 1974 Edition, Winter 1975
(b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
Addenda, N/A
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO)
HEAT JOSEPH OAT 2322-4B 1055 2-1208-E6-003 1978 REPLACEMENT YES
EXCHANGER CORPORATION
7. Description Of Work Installed replacement studs and nuts on letdown heat exchanger head in accordance with MDC# 99-V2M062.
8. Test Conducted: Hydrostatic ] PneumaticE[] Nominal Operating Pressure[] N/A [] Other F] Pressure N/A PSI Test Temp. N/A OF
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the
rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date N/A
Signed Nk• or -.- e r.. Date 12 20 r-> o r or Owner's Designee, Ttle
20 0/
I
Code Case
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or
Province of Georaia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Harfforci Connectcut have
inspected the components described in this Owner's Report during the period 10/27/00
to /4-e" -01 -, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the
examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall
be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this insqction. , - ,
22M Commiissions 4'4L7National Board, :Sate, Province and EndorsementsInspector's Signature
Date
Z I
Systemn
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xi
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations MaintenanceName
Date
Sheet
Unit
MWO #
Traveler # 99280
12/08/99
1 Of 1
2
29902741 Repair Organization P.O. No., Job No., etc.
Plant VogqteAddress
4. Identification Of System 1208 / Chemical and Volume Control
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
I System
Addenda, N/A Code Case
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1208 PULLMAN N/A N/A 2K4-1208-041-01 1988 REPLACEMENT YES PIPING POWER
SYSTEM I PROU_ _
7. Description Of Work Installed replacement studs and nuts on gibina flanaes at 2FE-0154.
8. Test Conducted: Hydrostatic [] Pneumatlc[E Nominal Operating PressureEr NA fX] Other E Pressure N/A PSI Test Temp. N/A 9F
CERTIFICATE OF COMPLIANCE
We certify that the statements made In the report are correct and this REPLACEMENT conforms to the
rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed k"/JL 1 Y}t % Date 19 q
Owner or Owner's Designee, Title [/ --
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut
have inspected the components described in this Owner's Report during the period 2 to 9 and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XL.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any gersonal Injury or property damage or a loss of any kind arising from or connected with this "ýd Ipts lg r Commissions 5*c10
Inspector's Signatur.J Natiofiai Board, State, Province and Endorsements
Date 12- 1-3 19 4-9
I
•System
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern NuclearOperating CompanyName
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 99282
11/08/99
Of
2
29903364 Repair Organization P.O. No., Job No., etc.
Plant VotileAddress
4. Identification Of System 1501 / Containment Cooling System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Add (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
ends, N/A
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1501 PULLMAN N/A N/A 2V4-1501-038-01 1988 REPLACEMENT YES PIPING POWER
SyTM PRODUCTS ________ _____
7. Description Of Work Installed replacement nut on cooler2-1501-A7-008-000 outlet header fRance saddle support.
8. Test Conducted: Hydrostatic E] Pneumatic[] Nominal Operating PressureE] N/A [] Other [] Pressure N/A PSi Test Temp. WA QF
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.n n n1
Signed kI r ý1~~ ~kDate II 0 19 ct
Date _ _/- I/ __ _ 19 99
V
Code Case
V
CERTIFICATE OF INSERVICE INSPECTION
1, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have inspected the components described In this Owner's Report during the period 11/08/99 to 11-19'-492 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described In this Owners Report Furthermore, neither the Inspector nor his employer shall be liable In any manner for any personal Injury or property damage or a loss of any kind arising from or connected with this Ins n. 1 <. ,n A I Commissions 8,4 0 -97
Inspector's Signatur4V National Board, State, Province and Endorsements
ORIGINAL. FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant VogUe Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations MaintenanceName
Date
Sheet
Unit
MWO #
Traveler # 99283
11/08/99
1 Of _
2
29903363 Repair Organization P.O. No., Job No., etc.
Plant Vopt/eAddress
4. Identification Of System 1501 / Containment Cooling System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Add (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
enda, N/A
NAME NAME MANUFACTUR NATIONAL REPAIRED, ASME CODE OF OF ER BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER SERIAL NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) NO.
1501 PULLMAN N/A NIA 2V4-1501-033-01 1988 REPLACEMENT YES PIPING POWER
SYSTEM PRODUCTS
7. Description Of Work Installed replacement nut on cooler2-1501-A 7-005-000 outIet header flange saddlQe sunDOrt.
8. Test Conducted: Hydrostatic Fl Pneumatlc[] Nominal Operating Pressure[] NIA [J Other [] Pressure NIA PSI Test Temp. NIA 2F
CERTIFICATE OF COMPUANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xi. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A N.o Signed -wPner or OnesDieeTt, Date it 19q
O;wn;1er or` Owner's Designee, Tltlh[j
Code Case
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georola and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. ConnecticuA have Inspected the components described In this Owner's Report during the period 11/08/99 to I - 9 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report In accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manner for any p"M Injury or property damage or a loss of any kind arising from or connected with this
pAV _ Commissions 3A V9 7 Inspector's Signature National Board, State, Province and Endorsements
Date 19 .9..
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
1. Owner Southern NuclearOperating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Traveler # 99285
03/09/00Date
Sheet I Of
Unit
MWO #
I
2
29903481 Repair Organization P.O. No., Job No., etc.
Plant VogSte Address
4. Identification Of System 1217/1 Auxiliary Component Cooling Water System
5. (a) Applicable Construction Code ASME SEC Ill 1977 Edition, Winter 1977 Addenda, N/A (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989 Code Case N-416-1
6. Identification Of Components Repairs Or Replacement Components
Code Case
- & L
7. Description Of Work A weld on line 2-1217-183-1.12 had to be to be cut out and rewelded to facilitate piping instlation under DCP97-V2NO056. Pressure test performed in coniunction with Section XI Traveler# 99131 under WO# 29901685.
8. Test Conducted: WADl
Hydrostatic ] Pneumatic[] Nominal Operating Pressure[X] Code Case N-416-1 Other E1 Pressure NIA PSI Test Temp. NIA 9F
Date o Vo-6 o20_
]
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODEOF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO)
1217PIPING PULLMAN N/A N/A 2K3-1217-183-03 1987 REPAIR YES SYSTEM POWER
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPAIR conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No. _ _ _ _ _ _ _ _
Signed ek2)A,4•',\- 1 Date 3/ I • 20
Owner or Owner's Deslgnee,nItle/"
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticui have Inspected the components described in this Owner's Report during the period 11/16/99 to 0 -,jo 0 , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described In this Owners Report in accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal Injury or property damage or a loss of any kind arising from or connected with this
4?Ln jdiLS( Commissions de •4°• 7
Inspector's Signature L/ National Board, State, Province and Endorsements
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xi
.1
1. Owner Southern Nuclear Operating CompanyName
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler # 00015
05/17/00
I Of 3
2
20000132 Repair Organization P.O. No., Job No., etc.
Plant VogUeAddress
4. Identification Of System 1301 / Main Steam System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
Addenda, N/A
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) VALVE CONTROL 23469-1-4 N/A 2PV-3030 1982 REPLACEMENT YES
COMPONENTS INC_
7. Description Of Work Valve pluo was replaced. A copV of Form N-2 for the replacement valve Dlu is attached.
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating PressureDNWAE] Other E] Pressure WA PSI Test Temp. NIA 2F
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xl. Repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No.
Signed %k- 2 ,.. ) 7 P) , Date -/ Vj 2000 Owner or Owner's Designee,'Title d
Code Case
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georoia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have inspected the components described In this Owner's Report during the period 02/29/00 to _, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this
.151=4 Commissions 5,4 ý;47 Inspector's Signature National Board, State, Province and Endorsements
Date 0
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
Traveler # 00087
1. Owner Southern Nuclear Operating CompanyName
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations MaintenanceName
Date
Sheet
Unit
MWO #
09/05/00
Of
2
20001127Repair Organization P.O. No., Job No., etc.
Plant Vogtie Address
4. Identification Of System 2101 / Containment Building System
5. (a) Applicable Construction Code ASME SEC III 1975 Edition, Winter 1975 Addenda, N/A (b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 192_
Code Case
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO)
CONTAIN- WALSH N/A N/A 2-2101- 1988 REPLACEMENT NO MENT CONSTRUCTION CNMTBLDG
BUILDING CO.
7. Description Of Work Concrete was replaced around the grease vents.
8. Test Conducted: Hydrostatic ] Pneumatic'] Nominal Operating PressureDl N/A [] Other E Pressure N/A PSI Test Temp. N/A 2F
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the
rules of the ASME Code, Section XI. Repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A No._..... ._ _
Signed , 2ol Owner or Owners Designee, Title IJ
Date 9-/A-- 20 00
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Insoection and Insurance Co. of Hartford. Connecticut have inspected the components described in this Owner's Report during the period 06/21/00 to 9 - Ar"-o. , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any maq er for any personal injury or property damage or a loss of any kind arising from or connected with this Ins_ ection._&4__ _ _ _ Commissions 6A 7 0 3
Inspedtor's Signature National Board, State, Province and Endorsements
Date q -/A--, 20 0 0
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required ByThe Provisions Of The ASME Code Section Xl
Traveler # 00090
1. Owner Southern Nuclear Operating CompanyName
40 Inverness Center Parkway. Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
02/08/01
_ _ _ Of 1
2
20001032 Repair Organization P.O. No., Job No., etc.
Plant VogtleAddress
4. Identification Of System 1902 ( Waste Processing System - Gas
5. (a) Applicable Construction Code ASME SEC III 1974 Edition, Summer 1976 Addenda, N/A
(b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
Code Case
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) HEAT AMETEK 78H-104 255 2-1902-C6-002 1978 REPLACEMENT YES
EXCHANGER SCHUTTE &
7. Description Of Work Installed replacement studs and nuts on heat exchanger head.
8. Test Conducted: Hydrostatic ] PneumaticE] Nominal Operating Pressure[] N/A [] Other [] Pressure N/A PSI Test Temp. N/A QF
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date N/A
Signed /_ Oe r " _ ow nr s Date DQin T 20 nl Owner or Owner's Designee, TIN
Date -- 1- 20ý
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have inspected the components described In this Owner's Report during the period 07/18/00 to 1-2i-/ •l , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any man er for any personal injury or property damage or a loss of any kind arising from or connected with this
Commissions CA 2 63'
Insp9-tor's Signature National Board, State, Province and Endorsements
20 0 /
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
Traveler # 00139
1. Owner Southern Nuclear Operating CompanyName
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtfe Electfic Generating Plant
Waynesboro, GA 30830Address
Date
Sheet
Unit
MWO #
3. Work Performed by Nuclear Operations Maintenance Name
04/03/01
_ _ _ _ Of
2
20001879 Repair Organization P.O. No., Job No., etc.
Plant Vo0tie
Address
4. Identification Of System 1202 / Nuclear Service Cooling Water System
6. (a) Applicable Construction Code ASME SEC III 1974 Edition, Winter 1975 Addenda, N/A
(b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
Code Case
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) RELIEF CROSBY N67951-00-0001 N/A 2PSV-11746 1984 REPLACEMENT YES VALVE
7. Description Of Work Relief valve SAV N67951-00-0007 was removed for inservce testinf and was replaced by relief valve S/V N6795100-0001. Relief valve S1N 67951-00-0001 was originally instalied as 1PSV-11744. removed under MWO# 10001472 and returned to warehouse stock as a spare.
8. Test Conducted: Hydrostatic ] Pneumatic[] Nominal Operating Pressure[•] N/AD Other [] Pressure N/A PSI Test Temp. N/A OF
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the rules of the ASME Code, Section Xl. Repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date N/A
Signed .On orOwnersesinere Date ,Titloe 20 0
I owner or Owner's Designee, Title ~' I
Date 20 - -0
I
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticut have inspected the components described in this Owner's Report during the period 11/02/00 to 4 - 6 ( _, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this inspeion• insp,9•/,on - ,•"• 'OI 4 Commissions ($ "
Inspector's Signature National Board, State, Prbvince and Endorsements
E¸
!
20 cl
/
1. Owner Southern Nuclear Operating Company Name
40 Invemess Center Parkway, Birmingham, AL
2. Plant Vogtile Electric Generating Plant
Wavnesboro, GA 30830
Date
Sheet
Unit
MWO #Address
3. Work Performed by Nuclear Operations Maintenance Name
Traveler # 00141
02/21/01
Of
2
20001880 Repair Organization P.O. No., Job No., etc.
Plant Vogtie
Address
4. Identification Of System 1202 / Nuclear Service Cooling Water System
5. (a) Applicable Construction Code ASME SEC III 1974 Edition, Winter 1975 Addenda, N/A
(b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO)
RELIEF CROSBY N67951-00- N/A 2PSV-11752 1984 REPLACEMENT YES
VALVE 0006
7. Description Of Work Relief valve S/N N67936-00-0003 was removed for inservice testing and was replaced by relief valve S'N N67936-00-0006. Relief valve SIN 67936-00-0006 was orfinally installed as 1PSV- 11752, removed under MWO# 10000136, and returned to warehouse stock as a spare.
8. Test Conducted: NIA-
A'
Hydrostatic [] Pneumatic[] Nominal Operating Pressure[l Other [] Pressure N/A PSI Test Temp. N/A
Date 20 �li
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
Code Case
gF
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT conforms to the
rules of the ASME Code, Section XI. Repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization N/A Expiration Date N/A
No.
Signed . J ') . .-- A,'n• , Date -/z-/ 20 O0 _)Owner or Owner's Designee, Title IJ
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut
have Inspected the components described in this Owner's Report during the period 11/16/00
to ,1--- ) / , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken
corrective measures described In this Owners Report In accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the
examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable In any manner for any personal Injury or property damage or a loss of any kind arising from or connected with this
_n_______ _________ Commissions e$4,;e . Inspectorfs Signature National Board, State, Province and Endorsements
r-'. ,•"
Date 20 .0/_
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
Traveler # 00157
1. Owner Souther Nuclear Operating CompanyName
40 Inverness Center Parkway, Birmingham, AL
2. Plant Voglie Eectric Generating Plant
Waynesbom, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO#
04/06/01
1 Of 1
2
29902633 Repair Organization P.O. No., Job No., etc.
Plant Vodtle
Address
4. Identification Of System 1208 / Chemical and Volume Control System
5. (a) Applicable Construction Code ASME SEC III 1977 Edition, Winter 1977 Addenda, N/A
(b)Applicable Edition of Section Xl Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
Code Case
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE
OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO)
1208 PIPING PULLMAN N/A N/A 2K3-1208-055-01 1989 REPLACEMENT YES
SYSTEM POWER 2K3-1208-066-01 PRODUCTS
7. Description Of Work Installed replacement studs and nuts on piping flanges at the tube side inlet and outlet to letdown exchanoer 2-1208E6-003.
8. Test Conducted: Hydrostatic [] Pneumatic[] Nominal Operating Pressure[:]
N/A f] Other [] Pressure N/A PSI Test Temp. N/A OF
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the
rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date N/A S . I . .Mc•n• , rae ____________
Signed -V\..----Mr Date q .,_ 20
7 Owner or Owner's Designee, Title
Date 72 - / -&/
t
CERTIFICATE OF INSERVILIP•ON mNmu iur
1, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or
Province of Georqia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticut have
inspected the components described in this Owner's Report during the period 12/06/00
to '0"4-1-61J , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken
corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the
examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall
be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this
inspe on. /J6'v2~.-w-,t_. //'•lJ/,j'a'rJ• L, Commissions 6' /6.!
National Board, State, Province and EndorsementsInsdctor's Signature
20
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xl
Traveler # 00193
1. Owner Southern Nuclear Operating Company Name
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
Date
Sheet
Unit
MWO #
3. Work Performed by Nuclear Operations Maintenance Name
02/09/01
1 Of 3
+" Z c/ao'
20000453 Repair Organization P.O. No., Job No., etc.
Plant Voatle
Address
4. Identification Of System 1204 / Safety Injection System
5. (a) Applicable Construction Code ASME SEC III 1974 Edition, Summer 1974
(b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
Addenda, N/A
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE
OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO)
HEAT SENTRY 786103 1279 Ae1204-P6-003- 1978 REPLACEMENT YES
EXCHANGER EQUIPMENT "- M01
HEAT SENTRY 786104 1280 Jf1204-P6-003- 1978 REPLACEMENT YES
EXCHANGER EQUIPMENT A- M01
7. Description Of Work Installed replacement water boxes (plenums) on motor heat exchanaers per REA 98-VAA600. Copy of Form N-2
for the replacement water boxes is attached S/N 1279-1. 1279-2. 1280-1 and 1280-2. The bolts on these heat
exchanoers were also replaced.
8. Test Conducted: NIAL
Hydrostatic [:] Pneumatic[-] Nominal operating Pressure[9] Other [] Pressure N/A PSI Test Temp. N/A
Date � /9 20 � I
I
Code Case
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the
rules of the ASME Code, Section XI. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorizatlo5g No. N/A Expiration Date N/A
Signed Owe r Oi Date ,20 L)
Owner or Owner's Designee, TIO
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or
Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford, Connecticbi have
inspected the components described In this Owner's Report during the period 12/15/00
to V- I/r - , and state that to the best of my knowledge and belief, the Owner has performed examinations and taken
corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or Implied, concerning the
examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall
be liable in any mar er for any personal Injury or property damage or a loss of any kind arising from or connected with this
_________________,,_r_-.- Commissions GA ,63 "Insoeepor's Signature National Board, State, Province and Endorsements
20. 0/Date -23- 19)
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section XI
Traveler# 01003
1. Owner Southern Nuclear Operating Company DateName
40 Inverness Center Parkway, Birmingham, AL Sheet
2. Plant Vogtle Electric Generating Plant
Waynesboro, GA 30830 Address
3. Work Performed by Nuclear Operations Maintenance Name
Unit
MWO #
03/01/01
1 Of 3
2
20000451 Repair Organization P.O. No., Job No., etc.
Plant Vogtle Address
4. Identification Of System 1208 / Chemical and Volume Control System
5. (a) Applicable Construction Code ASME SEC III 1971 Edition, Summer 1972 Addenda, N/A
(b)Applicable Edition of Section Xi Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO)
HEAT SENTRY 78100 1276 2-1208-P6-002- 1978 REPLACEMENT YES
EXCHANGER EQUIPMENT M01 CORP.
HEAT SENTRY 78101 1277 2-1208-P6-002- 1978 REPLACEMENT YES
EXCHANGER EQUIPMENT M01 I - I CORP
7. Description Of Work Installed replacement water boxes (plenums) on motor heat exchanoers Per REA 98-VAA600. Copy of Form N-2 for the replacement water boxes is attached SIN 1276-1. 1276-2. 1277-1 and 1277-2.
8. Test Conducted: NIAf-
Hydrostatic [] Pneumatlc[] Nominal Operating Pressure[Z] Other [] Pressure N/A PSI Test Temp. N/A
Date ,-?-A-,
Code Case
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the
rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date N/A
Signed 7 O D Aeign . 5 cod I Date I a 2o ( Owner or Owiner's De~ignee, Title 1,51) 114,/& 4, 1V (dC/(c,p
CERTIFICATE OF INSERVICE INSPECTION
1, the undersigned, holding a valid commission Issued by the national Board of boiler and Pressure vessel Inspectors and the State or
Province of Georgia and employed by Hartford Steam Boiler Inspection and Insurance Co. of Hartford. Connecticut have
Inspected the components described In this Owner's Report during the period 01/09/01
to - f, and state that to the best of my knowledge and belief, the Owner has performed examinations and taken
corrective measures described in this Owners Report In accordance with the requirements of the ASME Code, Section Xl.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the
examinations and corrective measures described In this Owners Report. Furthermore, neither the Inspector nor his employer shall
be liable in any mann for any personal Injury or property damage or a loss of any kind arising from or connected with this
SCommissions . A os "Inspec6r's Signature National Board, State, Province and Endorsements
2041
ORIGINAL FORM NIS-2 OWNER'S REPORT FOR REPAIRS OR REPLACEMENTS
As Required By The Provisions Of The ASME Code Section Xi
1. Owner Southern Nuclear Operating CompanyName
40 Inverness Center Parkway, Birmingham, AL
2. Plant Vogtde Electric Generating Plant
Waynesboro, GA 30830Address
3. Work Performed by Nuclear Operations Maintenance Name
Date
Sheet
Unit
MWO #
Traveler #
04/03/01
01011
I Of 3
20000454Repair Organization P.O. No., Job No., etc.
Plant Vogtfe Address
4. Identification Of System 1204 / Safety Injection System
5. (a) Applicable Construction Code ASME SEC III 1974 Edition, Summer 1974 (b)Applicable Edition of Section XI Utilized For Repairs Or Replacements 1989
6. Identification Of Components Repairs Or Replacement Components
Addenda, N/A
NAME NAME MANUFACTURER NATIONAL REPAIRED, ASME CODE OF OF SERIAL BOARD OTHER YEAR REPLACED OR STAMPED
COMPONENT MANUFACTURER NO. NO. IDENTIFICATION BUILT REPLACEMENT (YES OR NO) HEAT SENTRY 786102 1278 1204-P6-04-MOl 1978 REPLACEMENT YES
EXCHANGER EQUIPMENT ?CORP. _ _ _ _ ___ _
HEAT SENTRY 786105 1281 X1204-P6-004-M01 1978 REPLACEMENT YES EXCHANGER EQUIPMENT I - CORP. _ _ _,1_ _
7. Description Of Work Installed replacement water boxes (plenums) on motor heat exchangers Mer REA 98-VAA600. Copy of Form N-2 for the replacement water boxes is attached S/IN 1278-1. 1278-2. 1281-1 and 1281-2.
8. Test Conducted: N/A
Hydrostatic [] Pneumatic[-] Nominal Operating Pressure[Z Other [] Pressure N/A PSI Test Temp. N/A
Code Case
OF
CERTIFICATE OF COMPLIANCE
We certify that the statements made in the report are correct and this REPLACEMENT Conforms to the rules of the ASME Code, Section Xl. repair or replacement
Type Code Symbol Stamp N/A
Certificate of Authorization No. N/A Expiration Date N/A
Signed Ow owDate ner's 20 D T Q? Ownier or Owner's Designee, Title J
CERTIFICATE OF INSERVICE INSPECTION
I, the undersigned, holding a valid commission issued by the national Board of boiler and Pressure vessel inspectors and the State or Province of Geomia and employed by Hartford Steam Botler Inspection and Insurance Co. of Hartford Connecticut have insperted the components described in this Owner's Report during the period 01/29/01 to -7- 1 ) ,. and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners Report in accordance with the requirements of the ASME Code, Section XI.
By signing this certificate, neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this insp-'tion. /
42'JA',, ,ý Commissions A/•7 Inspector's Signature National Board, State, Province and Endorsements
Date I*- 7'-, / 20